TEMPO Overview
Third Science Team
Meeting
Wendy Pennington,
Project Manager
May 26, 2015
Project TeamSmithsonian Astrophysical Observatory- Principal Investigator, Science Team, Science Data Processing, Instrument Ops Center
Principal Investigator: Dr. Kelly Chance, Deputy PI: Dr. Xiong Liu
NASA Langley -Project Management, Systems Engineering, Safety/Mission Assurance
Project Manager: Wendy Pennington
Instrument Provider: Ball Aerospace Technologies Corporation
Science Team and International Science Advisory NCAR, Harvard, St. Louis U., UC Berkley, U Alabama, GSFC, NOAA, EPA, Carr Astro, Dalhousie U.; GEO Instruments GEMS, Sentinel-4 & PHEMOS
Science Objectives:
Project Overview:
Selected Earth Venture Instrument-1 Nov/2012
• NASA Cost Capped & Schedule constrained to Sept. 2017 delivery
• Targeted for hosting on GEO satellite nadir deck mounted for viewing Greater North America (GNA) (Tar-sands, Canada-Yucatan P. Mexico)
• Responds to the NRC Decadal Study element of GEO-CAPE
• Spectroscopic measurements in the UV/Vis wavelengths provide a measurement suite of key elements of tropospheric air pollution chemistry.
• Measurements built on 5 heritage spectrometers flown in LEO, and SAO operational algorithms
TEMPOTropospheric Emissions: Monitoring of Pollution
• Serve as the North American geostationary component of an international constellation for air quality monitoring
• Collect simultaneous high temporal and spatial resolution measurements of pollutants over GNA
• Measure the major components, directly or by proxy, of the diurnal tropospheric O3 chemistry cycle and the cloud fields needed for data processing.
• TEMPO spectroscopic measurements will provide the measurement suite of Ozone (O3), Nitrogen dioxide (NO2),
• Formaldehyde (H2CO)• Determine the diurnal instantaneous radiative forcings
associated with pollutants and other climate agents on the continental scale.
5/26/2015 Document Title 3
TEMPO Milestones Status
Milestone Date Comments
KDP-B April 4, 2014 2 actions-closed
PDR July 28-31, 2014 12 RFA-closed
KDP-C walk through November 13, 2014 PI decision to investigate conversion of instrument contract from CPFF/IF to FFP
Post PDR decision meetingto SMD
December 17, 2014 Concurrence of strategy to convert the Ball contract from CPFF/IF to FFP.Approval to authorize Ball work to proceed, moving into Phase C activities
FFP Instrument contract award
March 10, 2015 Completed
Key Decision Point -C April 10, 2015 Confirmed
Where’s the PI?
Celebrating Phase C confirmation!
• A change, to TEMPO’s contract structure to a Firm Fixed Price Contract, was accomplished to increase the confidence in a successful instrument development under the cost cap from CPFF.
• Instrument development risks were assumed by the Prime Instrument Contractor (Ball).
• Performance Specifications:– The instrument design and interface specifications are mature
– PI/PS evaluated all science requirements to assure minimal risk
– Discipline and processes are in place that provide effective communication and review of contract deliverable products in a timely manner by the government SMEs.
• Programmatic insight and a continued collaborative environment– Continue to receive critical path report and narrative variance reports,
technical parameter metrics, technical risks and open discussions.
Firm Fixed Price Conversion Summary
TEMPO IP Organization
16 March 2015
TEMPO Hardware Progress
Dalsa CCD wafers
CCDs and Sensor Support Fixtures (SSF)
Focal Plane
Electronics
EDU
Early start on key TEMPO subsystem HW reduces development risk
Single Board
Computer EDU
in test
TEMPO KDP-CApril 10, 2015 7
The spectrometer diffraction grating delivered and Ball verifying performance
What were once challenges are nowHistory
Challenging Science requirements and decisions made by the PI Post SRR to Phase B
Reallocate subsystem portions of MTF requirement
SNR relaxation by reduction of operational products
S/N performance for remaining products accepted after analysis
Wavelength stability
Polarization sensitivity
Field of regard (instrument plus mission jitter budget) resolved by changing acceptable range
Stray light performance accepted after analysis
What were once challenges are nowHistory
Phase C Critical Milestones
Milestone Date Critical technical tasks
Critical Design Review(CDR)
06/25/2015STOP Model 2.0
Manufacturers ReadinessReview (MRR)
06/2/2016Scan Mechanism/MirrorAssembly
Test Readiness Review (TRR)
9/15/2016Telescope Assembly,Flight Instrument Control Electronics Box Assembly
System Integration (SAR)/Pre-Ship Review
(PSR)05/30/2017
TVAC and EMI/EMC test, Performance and Calibration testing, Command Telemetry Handbook to SAO
TEMPOInstrument/Instrument Simulator/Instrument
Support Items
05/30/2017
10
TEMPO Instrument Project IMS
11
The TEMPO TEAM from Proposal to Implementation!
Proposal team March 2012
Mission/Instrument Projects Organization F2F- March 2013
Ground Ops TIMFebruary 2015
Science Team Meeting-May 2014
PDR July 2014
What’s Next?
• Image Performance Peer Review May 12, 2015
• TEMPO Science Team Meeting May 27-28, 2015
• CDR Readiness Reviews June 4, 5, 10 2015
• Instrument CDR June 24-25, 2015
• IOC Health & Safety Dataflow Peer Review July 2015
• IOC Science Data Flow Peer Review August 2015
• SDPC/IOC Ground Systems CDR March 2016
THE END