Attachment B - County IT Progress Forward Report - 20181009 - ver001 Page 1
Team Lead Item # Description Projected
Completion
Date
Update as of October 5, 2018
3-PMO Craig 1-Project-B TechShare.LEA
Portal
2018-10 The issues blocking testing and deployment of the Q2 2018 build have been resolved and testing is
underway. Anticipated to be completed by Wednesday, 10/10/18.
Efforts continue to have Tyler, Inc. configure their pre-production environments to mirror production
environments so that E-Filing testing and certification processes can be completed.
EDR Gateway – Testing of the EDR gateway is currently blocked by an issue which is preventing the ER3 files
from being generated. CUC is researching the issue and is planning to meet with Dallas implementation
resources on Friday 10/5/18 to work though and resolve this issue. Testing will commence once this issue is
resolved.
Progress towards acclimation and training of IT Support Staff resources who will take over support of
Prosecutor has been delayed due to other pressing project priorities. The IT Justice Systems Architect will
schedule a meeting with the IT Applications Leadership during week of 10/15/18 to finalize the support
transition plan.
3-PMO Peju 1-Project-C TechShare.Courts TBD A development release was delivered on 9/27/18 (Release 2.0.4427.1). The release is now deployed in the
Dallas County Test environment. The release included one (1) bug fix for Dallas County related to OCA.
The Dallas County SMEs and the FPM Team held a two-day working session to review open JIRA items for the
TSC project. The output from the working session is scheduled for a review session with the CUC on
Wednesday 10/3/18.
A separate working session will be scheduled with the CUC to review JIRA items related to the Judicial Portal.
Waiting on CUC to schedule this working session.
A data conversion technical review is underway and the tentative date for the validation work session with the
business unit is now scheduled for Wednesday, 10/17/18 due to the review working sessions scheduled for the
Punch List. The initial review by the Project Data Team identified the following issues:
o Duplicate SID number for the same defendant. The Project Team is working with the DCSO and the IT
Mainframe Team to address the duplicate SID issue.
o Cases with “No Filed Date” and duplicate “Filed Date”. We are working with WhiteBox to address this
issue.
The Dallas County Project Team is also working to address the issues with ORI numbers as it relates to the
Court wheel within the Courts application.
3-PMO Mark
Kenneth
1-Project-D TechShare.Jail TBD Governance Planning
Attachment A has been re-presented and is now under County review with an anticipated signature date in
October 2018.
Development use of the tracking tools and methodology still not fully redefined by TechShare –a more agile
approach is now being implemented and starting to be effective.
“Earn versus burn” reporting not available – awaiting finalization of total project sizing from TechShare. At this
stage, we have no “earn” data recorded from accepted software.
Attachment B - County IT Progress Forward Report - 20181009 - ver001 Page 2
The Finance Committee has not received up to date financials through the current process facilitated by Tarrant
County. The financial picture to date is not representative although it shows “under budget”, there has been no
forecast of items delivered versus expected as discussed in “earn versus burn” above.
The DCSO Jail Chief has authorized the process of starting investigating devices for such items as Officer
rounds management and inmate location tracking. This will require a RFI / RFP process – we have requested
clarity on the required next steps from the Dallas IT Leadership.
Project Execution
Re-engagement with TechShare with story grooming, prioritization and elaboration now taking place and
appears effective.
The Product Owners now starting to be able to influence development prioritization, stories and sequencing.
Updated software was moved into a County test environment and tests performed – Currently cataloging the
status and testing results of that build.
Cross-functional process mapping work is currently underway with Release and Disposition.
Concerns
Development has restarted –the lessons learned about lack of communication are starting to improve, but have
not yet been fully resolved within TechShare Team.
Unclear model to execute the project within the proposed timelines without changes in the staffing model or
approach.
Timelines need to be appropriately assessed given the reset to ensure that development meets requirements and
that the scope is not reduced just to meet the remaining hours.
Sequence of development items and the process of moving items into development that have been appropriately
reviewed is not yet well controlled.
Without the ability to measure the “earn versus burn”, the projection of project status and timelines can not yet
be accurately made.
Issues with the CUC QA process and quality are under discussion with the Counties.
Offshore development issues are evident based on items released into the test environment that are not up to
standard.
3-PMO Todd 1-Project-E TechShare.JP
TBD The DC IT Application Support Team is working towards a solution for reporting OCA Collection Improvement
Program statistics. Next steps are to support the scoping effort with clarification of any requirements with
Subject Matter Expert input. The goal is to provide a solution with the current system in place today due to
delayed delivery of the new JP software. Deadline for this effort is October 31, 2018.
At this point, currently awaiting the CUC to “restart” the development effort, per the item connected to the
TechShare.Courts development.
3-PMO Craig 1-Project-E1 TechShare.Indigent
Defense
2019-04
(for the ID
portion)
Completed Pre-Kick Off meeting with Judicial Committee on Indigent Defense. Approval to proceed has
been secured from this group.
Attachment B - County IT Progress Forward Report - 20181009 - ver001 Page 3
Met with Pre-Trial Working Group to further understand and refine the business processes which will be
implemented in response to the injunction around bail reform.
Note the County Judge has submitted the formal request to the Texas Indigent Defense Commission to
extend the expiration date for the TechShare.Indigent Defense grant funding to 3/31/19.
Planning a site visit at Tarrant County to observe Indigent Defense and Magistration procedures and how they
map to the use of the software system.
Planning formal kick-off meeting with all affected business units to occur during week of 10/12/18.
Planning project is currently targeted for completion by 11/16/18.
3-PMO Tamica 1-Project-F HHS EHR Interface
with the PHHS
EHRs
2018-10 The Interface was scheduled to go live in September 2018, however, Greenway and PHHS are still working
through validating the test version of the interface against the production version in order to find a resolution for
the error message being received. All the pieces of the interface work except for the “inbound query” piece from
PHHS to Greenway. Greenway has a team that is still troubleshooting this issue. The County Project Team is
getting status updates at least twice a week and continue to monitor the efforts to bring this to fruition.
3-PMO Nathan 1-Project-G DCIM Direction TBD
The DCSO has placed the integrated and web-based rollouts on hold for now while the CJIS compliance
remediation work is underway. (Pending)
2-Apps Richard 1-Project-K LIMS
repair/replacement
2019- Catapult, the vendor who was developing the LIMS replacement application, has submitted their final invoice
for consideration for payment after the early termination of the development activity. This reported activity is
being internally reviewed for close-out. (Pending)
The IT Applications Team is making plans with Microsoft to make modifications to the existing LIMS
applications in order to extend the useful life of the platform until a suitable replacement is identified for it.
Expect to brief the assessment engagement with Microsoft in November 2018 so that they can start their
assessment work in December 2018.
4-
Security
Nathan 1-Project-L IT Security audit
remediation
2018-10 Provided a detailed update to the ITEGC Chair Commissioner Dr. Daniel and County Administrator Mr.
Martin on 10/5/18 on the CJIS compliance preparations.
Please see the attached CJIS Compliance Checklist update from 10/6/18.
The State DPS CJIS Auditor Mr. Petty will be on site on 10/10/18 to conduct the formal CJIS compliance audit.
3-PMO Shirley 1-Project-
N2
Jail Camera
Expansion Project
TBD Awaiting the switch equipment delivery date and task dates from the camera and cabling vendors for the schedule.
2-Apps Kim I. 1-Project-P Oracle 12c
Modernization
2018-08 The Hyperion application was scheduled to be migrated to the Oracle ExaData infrastructure. Step one was to
perform migration in the Test/Dev environment. The migration to the Test/Dev environment was “functionally”
successful, but unexpected performance issues were encountered with processing the data. The IT Migration
Team worked on the issue and engaged Oracle services to resolve it. Also, approaching a few data processing
timelines from the County Audit’s Office’s CAFR project which will need the Test/Dev environment running as
efficiently as possible.
Attachment B - County IT Progress Forward Report - 20181009 - ver001 Page 4
With Oracle services help, we were finally able to get resolution to the issue. It is a 2-phased approach.
1. Phase 1 - Rollback Test/Dev to its original configuration to facilitate the County Auditor’s Office’s data
processing timelines for the CAFR processing.
2. Phase 2 - The previous approach was a hybrid one, with application servers in the Cloud with the database
on the on-site ExaData platform. Plan to move both the application Servers and the database to on-site
Exadata platform, which is expected to resolve the performance issue encountered.
10/04/2018 High Level Overall Status
Status
Delayed
On-Schedule
Ahead of schedule
Hyperion Application Migration
Task Task Details Task Owner Due Date % Complete
1. Phase (1) Rollback Test/Dev to its original configuration
Rollback Test/Dev to its original configuration to facilitate auditors data processing timelines
for CAFR processing.
Oracle Team
11/2/2018 20%
2. Phase (2) Migrate Test/Dev to On-Prem.
Move both application Servers and database on-Prem (Exadata)
Oracle Team N/A 0%
3. Phase (2) Migrate Test/Dev to On-Prem.
Complete testing of Test/Dev environment for functionality & performance
Oracle Team Auditors Users
N/A 0%
4. Phase (2) Migrate Production to On-Prem with same configuration as Test/Dev
Move both application Servers and database on-Prem (Exadata)
Oracle Team Auditors Users
N/A 0%
5. Project Close Out Review surrounding lessons learned including documentation as needed.
Kim Ingram
N/A 0%
3-PMO Sabrina 1-Project-Q HEAT System
Rollout
2019-01 Civil DA provided redline SOW for professional services for the Change Management Module
implementation. Provided updated SOW to vendor on 9/25/18.
Reviewing configurations for Service Request and Service Catalog.
Attachment B - County IT Progress Forward Report - 20181009 - ver001 Page 5
The iHEAT Application Administration and Configuration training for the IT Applications Team’s M&O
support is planned for the week of 10/29/18. The transition of the production support to the IT Applications
Team is tentatively scheduled for November 2018 after the training has been completed.
2-Apps Gary 1-Project-T Web Content
Management
System (CMS)
TBD Item %
Completed
Note
Web Design – County
Clerk 99% Waiting on department signoff
Web Design – District
Clerk 99% Waiting on department signoff
Web Design – HHS 92%
Web Design – District
Attorney 35%
Web Design – District 4 85%
Web Design – District 1 0%
Web Design – District 2 0% Web Design – Tax 0% Web Design – Sheriffs
Print Shop 0%
Web Design – Sheriff 1%
Web Design – IT
Intranet 0%
Web Design – RWPC 0%
2-Apps Janice 1-Project-U Mainframe
Application Offload
TBD 10/01/2018 High Level Overall Status
Status
Delayed
On-Schedule
Ahead of schedule
Mainframe Offload
Component Status % Complete
1. Guide Book Complete 100%
2. Supply Inventory Active 85%
3. Forensics Active 87%
4. Voter Registration Pending
5. Rapsheet Complete 100%
6. Civil Papers Pending
7. WRWI Pending
Attachment B - County IT Progress Forward Report - 20181009 - ver001 Page 6
8. Historical Active 49%
Also, note that the changes for the OCA Collections Report for the JP Courts are currently being tested. Per the
meeting the JP Clerks on Thursday, 10/4/18, the plan is to have the changes moved into production on Friday,
10/12/18.
1-Ops Paulette 1-Project-X Cisco Phone System
upgrades
2018-10 Task Name Start Finish % Complete
ELECTION & JURY
SERVICES IVR Mon 8/13/18 Thu 10/4/18/18 83%
DNS? Need third party
input meeting Mon 9/24/18 Thu 9/27/18 100%
Schedule/Communicat
ed with IVR Engineers Mon 9/24/18 Thu 9/27/18 100%
Reconfigure IVR if
necessary resources
needed on cut night
CM731201810432
(Pending)
Thu 10/4/18 Thu 10/4/18 50%
2-Apps Richard 1-Project-Y 911 CAD (et. al)
Systems upgrades
TBD The briefing scheduled for 9/4/18 was pulled based on an inquiry from the County Judge, noting that he would like
to have the MOU with the City of Dallas presented as part of the briefing. Will address this with the City of Dallas
and place this back on the Court Agenda accordingly. (Pending)
2-Apps Richard 1-Project-Z1 Commissioners
Court Agenda
Management
System Transition
2018-10 Per recent discussions with County Clerk Mr. Warren, understand the new application is expected to be deployed
for production use in November 2018 (In progress).
Attachment B - County IT Progress Forward Report - 20181009 - ver001 Page 7
3-PMO Stephani
e
1-Project-Z3 CSS Application
implementation for
CSCD
TBD Pre-Trial Services received the latest draft requirements documentation on 9/21/18 for review.
Pre-Trial is continuing to review the requirements documentation and will provide an update to changes or
corrections by CoB on 10/5/18.
3-Apps Richard 1-Project-Z4 AP Automation
Project
TBD In light of related work being done as part of the TechShare.Indigent Defense Project, the CIO will schedule a
follow-up meeting with County Auditor Mr. Thomas and the IT Leadership during the week of 10/15/18 after the
State CJIS compliance audit scheduled for the week of 10/8/18.
3-PMO Sabrina 1-Project-Z6 Queuing System
rollout
TBD The County Tax Office would like to continue monitoring Queuing system implementation at their Garland Office
through the upcoming Tax Season through the end of January 2019. Once the initial rollout is stable, Mr. Ames,
the County Tax Assessor, intends to roll out the system to the other Tax Offices around the County. The District
and County Clerks have noted their interest in possibly deploying the system once it is fully implemented in the
County Tax Office. (Pending)
3-PMO Sabrina 1-Project-Z7 Voting System RFP
and ePoll Book RFP
rollouts
2019-03 The ePoll Book RFP solicitation closed on 9/24/18. The Evaluation Committee is currently reviewing the
vendor’s RFP responses.
The Voting System RFP Pre-Bid Conference was held on 09/19/18. The RFP will be advertised until
10/11/18. (In progress)
3-PMO Shirley 1-Project-Z8 Juvenile
Assessment Project
TBD The Civil DA’s Office completed their review of and revision to the Noble contract on 9/27/2018. Review by
the Juvenile Legal Advisor were completed on 9/28/2018. The contract was subsequently returned by Noble
with the additional documents and items for discussion. A meeting between the County Juvenile Department
stakeholders and the vendor, Noble, is being scheduled for discussion of the open items. In light of these
additional discussions, project that the item will be briefed to the Commissioners Court on 11/6/18 pending the
open items being addressed.
1-Ops Paulette 2-Platform-
F
ASE-OnDemand
Rollout
2018-10 A follow-up meeting is pending with AT&T Legal and the Civil DA’s on the remaining issues:
1. Indemnification: Suggested language from AT&T has been added and is pending approval by County IT.
2. Equipment Lien: Under review by Dallas County IT.
3. Warranties/Pricing: Have added language to clarify & address any potential conflicts between the Master Agreement and the service publications. See Sections 4.1. and 6.4.
4. Insurance – County HR
1-Ops Paulette 2-Platform-
H
eFax Rollout 2018-11 CIO is currently reviewing the updated end-user’s guide for eFax for approval so that this one can be closed out.
(Pending)
1-Ops Sean 2-Platform-I IT Infrastructure
Modernization
Initiative, combined
with Platform-G1 &
Platform-G2
2018-10 Desktop Support The September 2018 patch releases have been assessed and are scheduled to begin being pushed out on
10/9/18.
The new PC group policy for implementing Windows Firewall began deploying on 10/3/18 for all laptops and
tablets to meet CJIS requirements.
Infrastructure Modernization Desktop Refresh Phase III -
Attachment B - County IT Progress Forward Report - 20181009 - ver001 Page 8
Replacements for the County Public Defender’s Office in FCCB have been completed, ones for the DA’s Office
are underway and the ones for the DCSO are scheduled to begin the week of 10/8/18.
Thirty-five (35) computers were installed for the DA’s Office during the week of 10/1/18.
Sixteen (16) computers installed for County Facilities thus far with four (4) pending installation.
Desktop Refresh Phase IV (Elections Poll Books) - All systems have been delivered to County Elections. We
are now looking at how to push the September updates to the laptops systems that were imaged over the past two
weeks in order to have them ready before the general election.
Desktop Refresh Phase V (DSCO MDC replacement) – The Commissioners Court has approved the
replacement of the Panasonic PCs. The IT Operations Team is networking with the IT Applications Team to
confirm the schedule for the deployment of the replacement assets in order to “retire” the in-service platforms.
Desktop Refresh Phase VI - Discussions continue with Dell and GTS to develop a lease program for the
County. At this time, we're reviewing both a 3- and 4-year lease models using a fair market value buyout at the
end of the lease to minimize costs. Assuming we receive approval to move forward, we are looking for a Q1
2019 kickoff. (Pending)
Bomgar - Configurations are complete and documentation released to the CIO for review. Awaiting IT
Management review and notification to staff of process changes for how vendors will access County assets
going forward.
Nutanix – System configuration complete and handed over to DBA team to begin the Civil database
migrations. Brief submitted to IT Management for review for Phase II to setup the remaining Civil virtual
machines, Criminal Cluster and Disaster Recovery systems.
TechShare Isilon - Production system configuration and deployments are complete and space concerns are
mitigated as of this report. Shelves were added to DR system this week and we're scheduling an OS upgrade to
complete the configuration.
Office 365 – Migration SOW is still under review.
Windows 2016 Upgrade - Continue to work with Applications to migrate systems to Windows Server OS
v2016. As the Nutanix environment comes on-line, the migrations will accelerate.
Network – All switches with the exception of the core switch at HHS/Elections have been replaced. The EOL
module on that system has been removed to meet CJIS compliance and we are awaiting the completion of the
General Election in November 2018 before scheduling the replacement as part of the Phase II CJIS compliance
effort.
2-Apps Tamica 2-Platform-J KRONOS upgrade TBD We have sent over the marked up Statement of Work from the Civil DA to Kronos. We received their edited
version back 10/2/18. They accepted several of the changes, but rejected the additional language recommended by
Dallas County as this order is under the IMMIX GSA contract. We have requested that the Civil DA’s Office
review the updated document and determine if we can accept the revised Statement of Work.
Attachment B - County IT Progress Forward Report - 20181009 - ver001 Page 9
1-Ops Sean 2-Platform-
L
Platform
Stabilization
2018-09 Have started working on building patches for the Windows v10 OS and Windows v7 32-bit OS PCs and
anticipate re-starting desktop patch deployments after additional testing. (In progress with the next push
scheduled in October 2018.)
The Commissioners Court approved on 10/2/18 the engagement of an network consultant to assist with the
optimization assessment of the County Data Network as the County examines its options for fully
implementing network segmentation.
2-Apps Richard 2-Platform-
M
Microsoft
Enterprise Mobility
Suite Deployment
TBD In light of the 2-Factor Authentication needed for the CJIS compliance effort, intend to move forward with the
implementation of the InTune module of the EMS as soon as possible. Briefing for engaging Integration Partners
to assist with the deployment was approved by the Commissioners Court on 9/18/18 (In progress).
1-Ops Paulette 2-Platform-
N
Mass Notification 2018-11 Next steps are:
o County to create two dial-casts (dial to page) - 10/5/18
o Collaboration Group - configure (1) virtual workspace for a designated group of users, conference calling or
Webex Teams
Training (6 seats – HSEM & Juvenile = Senders & Service Desk , IT = senders & Administrators)
2-Apps Richard 3-Plans-B Enterprise GIS
setup
2018-09 Anticipate a to the Commissioners Court on 11/6/18, pending the interim meeting with County Public Works in
order to provide County PW with a more detailed overview as to the anticipated GIS services.
5-Admin Vic 3-Plans-C MTF budget audit
and structuring
2019-01 Per follow-up discussions with the County Purchasing Office on the development of a contract Staffing RFP for
our future Staff augmentation needs, expect County Purchasing to submit the proposed RFP to the Court for
approval to release for bid in October 2018. (Pending)
4-
Security
Michael
A.
3-Plans-D Cybersecurity
Training &
Awareness
2019-03 The Commissioners Court approved the acquisition of a web-based LMS which the County IT Security Team
intends to leverage for conducting enterprise-wide cybersecurity awareness training. This platform will be used
for other enterprise learning needs as well. (The new CISO, Mr. Michael Anderson, is onboard as of 9/28/18
and this is one of his 6-month goals to have completed.)
Still plan to meet with Chief Bass of OHSEM to plan the next EM table-top exercise for the County Staff with a
cybersecurity emphasis. (The new CISO, Mr. Michael Anderson, is onboard as of 9/28/18 and this is one of
his 6-month goals to have completed.)
5-Admin Vic 3-Plans-E Data Driven Justice
Initiative
TBD County IT is currently in testing with LoopBack with the data the County has provided to them (In progress).
5-Admin Vic 4-People-A Vacancies 2018-12 Michael Anderson, the new CISO, started work at Dallas County on 9/28/18.
Welcomed Jamil Nikkon as a new IT Senior SQL DBA, filling the vacancy created by the promotion of
Kim Ingram to an IT Applications Support and Development Manager.
Note the retirement of Tim Murray, IT Senior Network Engineer on the IT Security Team, effective
9/30/18.
As of 10/1/18, moving forward with the applicable HR actions to fill the remaining four IT vacancies (i.e.,
Senior Project Manager, Senior Business Analyst, Senior Voice Engineer [approved by the Court on 10/2/18]
Attachment B - County IT Progress Forward Report - 20181009 - ver001 Page 10
and IT Senior Network Engineer [which will need to be reclassified possibly as an IT Senior Security
Engineer]).
5-Admin Vic 4-People-B Certifications-
Stipends Review
TBD Per a follow-up discussion with Mr. Graham of County HR on 9/6/18, we note that County HR still has this item
under review in terms of confirming what components will be included in the policy proposed to the
Commissioners Court for consideration. (Pending)
5-Admin Vic 4-People-C Staff Recognition
and Development
NA The CIO plans to network with the County HR Office and the Civil DA’s Office the week of 10/15/18 to
schedule the IT Management Team for a series of HRM courses for FY2018-19.
The County IT Team recognized the following IT Team members celebrating their County Service
Anniversaries during the month of October 2018:
Caryn Warren, IT Senior Oracle DBA (6th) – 12 years (!!!!)
Andrea Andrews, IT Technical Support Analyst (23rd) – 12 years (!!!!)
Kimberly Thomas, IT Senior Systems Analyst (30th) – 12 years (!!!!)
Derek Yang, IT Senior Developer (29th) – 11 years (!!!)
Carlos Blanco, IT Senior Oracle DBA (10th) – 7 years
Ashley Arnold, IT Continuous Improvement Agent (22nd) – 7 years
Prasad Ravuri, IT Senior SQL DBA (27th) – 4 years
Varma Mudunuru, IT Technical Support Analyst (19th) – 3 years
Lisa Green, IT Senior Business Analyst (24th) – 2 years 5-Admin Vic 4-People-D IT Organizational
Review
2018-12 The CIO plans to begin discussions on and planning for an IT organizational review during the week of
10/22/18. (Still planned for the noted week.)
The IT Staff Survey is being distributed to the IT Team to complete by 10/12/18. (In progress)