A & D High Tech Case

TEAM 3

PROJECT COMPLETION TIMELINE

Page 2: Team 3 Presentation on a&D Tech Case

A & D High Tech Project Plan• Project Go-Live Date• 11/15/2002 [Assuming Project start date

of 06/03/2002]• Project Completion Date• 11/29/2002

• Total Cost• Labor Cost = $834,030.00• Capital Cost = $98,500.00• Total Cost = $932,530.00

Page 3: Team 3 Presentation on a&D Tech Case

A & D High Tech Project Plan• Critical Path

Page 4: Team 3 Presentation on a&D Tech Case

A & D High Tech Case Plan• Potential of the project to be

completed on time - Feasible– The online store project is feasible and could go live

before the holiday season– Extensive testing phase should highlight potential

problems– Strong Project Management & history of timely delivery

project– Simple and clearly defined project scope– Detailed Project Plan– Strong Support from Upper Management

Page 5: Team 3 Presentation on a&D Tech Case

A & D High Tech Case Plan• Risks & Mitigations

– Scope Creep - Incorporate Checkpoints & Milestone, Functionality Vs Aesthetics, No changes after Functional Requirements

– Human Resources - Hire only experienced resources with both prior Domain and Technical experience

– Resource Back Up - Take services of another Consulting Firm

– Mythical Man Month - Resource Leveling and Loading• Room for Accommodating Scope

Changes– Minor alterations to existing requirements are feasible

but no big changes can be accommodated e.g. adding/changing few fields vs adding a new page.

Page 6: Team 3 Presentation on a&D Tech Case

QUESTIONS??????