Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
TasWater
Blackmans Bay STP
DPEMP
August 2016
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | i
Executive Summary
The proposed Project is an upgrade of the existing Blackmans Bay Sewage Treatment Plant
(STP), located on the western shore of the lower Derwent Estuary off Tinderbox Road, at the
end of Treatment Plant Road (south of the main suburban area of Blackmans Bay).
The upgrade will involve both an increase in capacity of the plant as well as improved overall
effluent treatment to improve the quality of water discharged to the Derwent Estuary and meet
EPA compliance requirements. It will also improve odour and noise for local residents.
The upgrade will benefit the Kingborough area, both now and for future generations, by allowing
TasWater to improve performance and capacity of the Blackmans Bay STP and facilitate the
consolidation of the Kingborough sewerage system to accommodate growth in the area and
centralise waste from local catchments. This will allow TasWater to close underperforming STPs
at Electrona, Margate and Howden in the future. A key driving factor for the amalgamation of
STPs at Electrona, Margate and Howden is the long term benefits to North West Bay by
removing wastewater discharges from these STPs.
Project Overview
At its core the upgrade will address deficiencies with the current STP to meet emission limits
and manage odour impacts to the surrounding environment as well as catering for projected
increases in sewage flow to the to the Blackmans Bay STP from the immediate catchment. The
Blackmans Bay STP is part of Tasmania’s wastewater infrastructure and maintaining its ability
to cater for current and projected loads without prejudicing emission limits or public amenity is a
core requirement for ongoing public infrastructure in the region. In addition to immediate
catchment pressures; the upgrade has been planned in the context of a strategic rationalisation
of STPs in the broader area and will be designed to cater for current and projected future loads
from the ageing Margate, Electrona and Howden STPs, which are planned to be
decommissioned. The decommissioning of these plants and the subsequent new influent
pipework transferring the loads from these catchments to the Project are excluded from this
application.
The Project aims to significantly improve plant performance to the Tasmanian EPA’s Accepted
Modern Technology (AMT) performance criteria (with some alteration to phosphorus and
nitrogen treatment criteria) and to meet the capacity requirements of projected sewage volumes
based on a 2040 population growth horizon for the aforementioned catchments.
The upgrade includes the conversion of the existing Blackmans Bay activated sludge system
STP with a current design capacity of 4.125 ML/day to an Intermittently Decanted Extended
Aeration - Sequential Batch Reactor (IDEA-SBR) system with an Average Dry Weather Flow
(ADWF) design capacity of 8.53 ML/day.
The Project Proponent is Taswater, the State’s water authority.
Approvals Process
Schedule 2 of the Environmental Management and Pollution Control Act 1994 (EMPCA), states
that Level 2 approval is required for wastewater treatment and disposal of more than 100 kL/day
(average dry weather flow) of effluent. As the Project aims to treat a maximum ADWF of 8.53
ML/day, it is above the Scheduled Level 2 limit and therefore the Project needs to obtain
approval to operate under the Land Use Planning and Approvals Act 1993 and EMPCA as a
Level 2 activity.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | ii
A Notice of Intent (NOI) was submitted to the Tasmanian EPA in 2014, seeking confirmation of
the level of approval and seeking Project Specific Guidelines. The EPA determined the project
to be a Level 2B assessment and Project Specific Guidelines were issued.
The resulting approval pathway for the Project is the submission of a Development Proposal
and Environmental Management Plan (DPEMP – this document) and associated development
application (DA) to Kingborough Council, which is subsequently referred to the EPA Board for
joint assessment and approval.
The DA and associated DPEMP are then advertised for public comment and representation.
Any comments received are taken into consideration during the Council and EPA assessment
process. Once a determination has been made by the EPA Board and the Council a permit may
be issued (if approved) with conditions (if required) and an appeals period applies before the
approval comes into effect.
In the approvals process this DPEMP forms the key document by which agencies and the public
can obtain an understanding of the Project and its potential impacts, benefits and commitments
to management actions.
Community consultation prior to submission of the DPEMP to Kingborough Council will also
provide the public with an understanding of the Project’s impacts and benefits, along with
TasWater’s commitment to manage both construction and operation.
No significant impacts are expected to occur to Matters of National Environmental Significance
as a result of the Project, as has been determined through relevant studies. Therefore, the
project has not been referred to the Commonwealth under the Environment Protection
Biodiversity Conservation Act 1999 (EPBC Act).
Project Site
The Site is within a relatively large parcel of land (surrounding the existing STP site) which is
currently owed by Kingborough Council and used as a buffer for the existing STP and for
recreational walking by the local community. TasWater has entered into an agreement with
Kingborough Council to purchase that parcel of land which will continue to be used for its
current purpose and to accommodate the expansion of the Project. The combined parcels of
land (existing STP site and surrounding Council owned parcel to be acquired by TasWater) form
the combined ‘Project Site’ for this application (i.e. ‘The Land’).
The Project Site is bounded to the north by medium density residential development, to the west
by low density residential development, to the south by a Council owned land parcel
(predominantly bushland used for walking and dog exercise) and to the east by the Derwent
Estuary. The Project Site slopes from west to east, towards the estuary, and contains two small
drainage lines immediately to the north and south of the existing STP.
The development footprint (Project Footprint) is within and adjacent to the existing STP and
therefore contains partially disturbed land, as well as undisturbed land. The Project Footprint
contains a small number of mature eucalypt trees and other small native species but is
otherwise dominated by exotic grasses and already disturbed areas.
Key Impacts and Mitigation
The proposed Project involves upgrades and expansion to an existing site (for the majority of
the Project Footprint), therefore many of the impacts normally associated with a new STP are
lessened in this case as the site is already utilised for that purpose. The expansion does,
however, pose a number of key changes to onsite and offsite impacts, summarised as follows
(details provided in the body of this DPEMP):
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | iii
The Project design will result in significant improvements to treated effluent quality across
almost all parameters. Nitrogen and ammonia in particular will be treated to a much lower
level under the new arrangements than is achieved by the existing STP. The Project design
will also provide greater reliability of treatment and capacity to cater for upset and storm
conditions, providing a significant treatment improvement over the current plant. The
proposal does however also involve a gradual increase in discharge flows as a result of
growth in the area as well as catering for existing Margate, Electrona and Howden sewage
flows in the event these plants are decommissioned and redirected to Blackmans Bay.
An assessment has been made of the increased effluent flows from the Project into the
Derwent Estuary. This assessment found that the existing mixing zone (for the current
plant) is sufficient for complete mixing of toxicants to ambient concentrations at the Project
design capacity, therefore no expansion of the existing STP effluent mixing zone is needed.
The assessment also found residual risks of eutrophication, algal blooms and impacts to
human health and marine ecosystems are limited as a result of the relatively high treated
effluent quality, the nature of the outfall site (no threatened species) and the exposed
nature of the discharge environment (i.e. large estuary mouth, rather than a confined river
or bay). The Project does have potential to impact on a local giant kelp forest by reducing
current effluent nutrient loads. This is considered further in the body of the DPEMP.
An associated benefit of the upgraded plant to the marine environment is the potential
facilitation of the removal of treated effluent from the constrained environment of North
West Bay through the provision of sufficient treatment capacity to cater for future loads from
Margate, Electrona and Howden plants (currently discharging into North West Bay) which
can be decommissioned.
The proposal involves some clearance of mature eucalypt species and a very small area of
a threatened vegetation community but is predominantly focused on already disturbed land.
TasWater has commitment to a landscaping program replacing all mature eucalypts
removed with new trees at a ratio of 3 to 1. Residual impacts to native flora and fauna are
considered low.
An assessment of odour impact from the new plant illustrated compliance with the relevant
legislation and shows the 2 odour unit contained within the Project Site on al l occasions bar
a simulated “worst-case scenario”. Odour impacts from the Project are expected to be
greatly reduced in comparison to the current plant.
An assessment of noise impacts from the Project showed compliance with the adopted
criteria under all normal operating conditions. Noise during emergency power generation
scenarios and the construction period were assessed against different criteria (due to the
short-term nature of these impacts and the lack of night time work in the case of
construction) and found to be compliant.
The Project will involve some additional visual intrusion for nearby residents, but is cut into
the existing bank considerably, will be painted to blend into the existing environment, is
similar in nature to the existing STP and will be screened by proposed landscaping from
most angles. With these measures in place overall visual intrusion is expected to be limited.
Conclusion
Overall the Project offers a significant improvement in wastewater treatment capacity, quality
and reliability and poses a relatively small number of environmental and social impacts .
Treatment plant upgrades and expansions are an essential part of maintaining the State’s
wastewater assets for current and projected population growth and the Blackmans Bay sit e has
been carefully selected and designed to minimise impacts as far as practical whilst allowing the
provision of long term wastewater treatment in the Kingborough Local Government Area.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | iv
Acronyms
AADT Annual average daily traffic Kl Kilolitre
ABS Australian Bureau of Statistics kWh Kilowatt hour
ADCP Acoustic doppler current profiler LAeq Equivalent sound level (weighted)
ADWF Average dry weather flow LAmax Maximum sound level (weighted)
ADWG Australian Drinking Water Guidelines
LGA Local government area
AER Annual Environmental Report LUPAA Land Use Planning and Approvals Act 1993
AHD Australian Height Datum L/S Litres per second
AHT Aboriginal Heritage Tasmania M Million
AMT Accepted modern technology MBR Membrane bioreactor
ANZECC Australian and New Zealand Environment Conservation Council
MCC Motor Control Cabinet
AS Australian Standard ML Megalitre
AS/NZS Australian New Zealand Standard ML/d Megalitre per day
BOD Biological oxygen demand MNES Matters of National Environmental Significance
BTF Bio-trickling filter NEPM National Environmental Protection Measures
C Celsius NGERS National Greenhouse
and Energy Reporting Scheme
CEMP Construction Environmental Management Plan
NMPM Noise Measurement Procedures Manual
CFEV Conservation of Freshwater Ecosystem Values
NO. Number
CFU Colony forming unit NOI Notice of Intent
CMM Contingency Management Manual NTU Nephelometric turbidity unit
COD Chemical oxygen demand NHMRC National Health and
Medical Research Council
DA Development Application NRMMC National Resource
Management Ministerial Council
DB Decibel NWP National Waste Policy 2009
DBA Decibel (weighted) OEMP Operational Environmental Management Plan
DBH Diameter at breast height O&M Operation and maintenance
DEP Derwent Estuary Program OMP Operational Management Plan
DFCS Design for Construction Safety OU Odour unit
DOTF Department of Treasury and Finance
PEV Protected Environmental Value
DPEMP Development Proposal and Environmental Management Plan
PLC Programmable logic controller
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | v
DPIPWE Department of Primary Industries, Parks, Water and the Environment
PSU Practical salinity unit
DTA Direct toxicity assessment RAS Return activated sludge
ELG Emission Limit Guidelines for Sewage Treatment Plants that Discharge Pollutants in Fresh and Marine Waters 2001
SBR Sequential batch reactor
EMP Environmental Management Plan SOER Specific Odour Emission Rates
EMPCA Environmental Management and Pollution Control Act 1994
SPS Sewage pump station
EMPCR Environmental Management and Pollution Control Regulations 2014
SSMP Sewage Sludge Management Plan
EMZ Environmental Management Zone STP Sewage treatment plant
EPA Environment Protection Authority SWL Sound power level
EPBC Act Environment Protection and Biodiversity Conservation Act 1999
SWMP Soil and Water Management Plan
EPN Environmental Protection Notice RMPS Resource Management and Planning System
EPP Environmental Protection Policy 2004
t Tonnes
GFA Gross floor area tCO2-e/annum
Tonnes of equivalent CO2 per annum
ha Hectare TDS Total dissolved solids
hr Hour THC Tasmanian Heritage Council
HSMP Health and Safety Management Plan
TJ/annum Terajoules per annum
H2S Hydrogen sulphide TSPA Tasmanian Threatened Species Protection Act 1995
Hz Hertz TSS Total suspended solids
IBC Intermediate bulk container TW TasWater
IDEA-SBR Intermittently decanted extended aeration – sequential batch reactor
µg Microgram
ITP Inspection and test plans UV Ultraviolet
Kg Kilogram VOCs Volatile organic compounds
KHz Kilohertz WAS Waste activated sludge
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | vi
Table of contents
1. Introduction..................................................................................................................................... 1
1.1 Title of Proposal ................................................................................................................... 1
1.2 Proponent ............................................................................................................................ 1
1.3 Proposal Background........................................................................................................... 1
1.4 Legislative Framework ......................................................................................................... 2
2. Proposal Description ...................................................................................................................... 3
2.1 Project Overview .................................................................................................................. 3
2.2 Location and Site Context .................................................................................................... 4
2.3 Project Rationale and Context ............................................................................................. 8
2.4 Project Design Parameters ................................................................................................ 13
2.5 Sewage Treatment Plant Design ....................................................................................... 18
2.6 Operational Parameters ..................................................................................................... 25
2.7 Pre-Construction and Construction .................................................................................... 28
2.8 Commissioning .................................................................................................................. 32
2.9 Off-Site Infrastructure......................................................................................................... 34
2.10 Land Tenure and Public Site Access ................................................................................. 35
3. Project Alternatives ...................................................................................................................... 37
3.1 Project Rationale ................................................................................................................ 37
3.2 Alternative STP Sites ......................................................................................................... 37
3.3 Reuse Investigations.......................................................................................................... 38
3.4 Layout at the Blackmans Bay STP Site ............................................................................. 40
3.5 Alternative Treatment Plant Technology............................................................................ 41
4. Public Consultation ...................................................................................................................... 43
4.1 Stakeholder and Community Engagement Plan ................................................................ 43
4.2 Key Stakeholders Engaged ............................................................................................... 43
4.3 Key Engagement Tools...................................................................................................... 44
4.4 Summary of Feedback Received ....................................................................................... 44
4.5 Future Consultation ............................................................................................................ 44
5. Existing Environment ................................................................................................................... 45
5.1 Planning Aspects and Land Tenure ................................................................................... 45
5.2 Environmental Aspects ...................................................................................................... 51
5.3 Socio-economic Aspects ................................................................................................... 54
6. Existing Conditions, Potential Effects and Management ............................................................. 56
6.1 Air Quality .......................................................................................................................... 56
6.2 Surface Water Quality ........................................................................................................ 67
6.3 Groundwater ...................................................................................................................... 70
6.4 Noise Emissions ................................................................................................................ 73
6.5 Waste Management ........................................................................................................... 82
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | vii
6.6 Dangerous Goods and Environmentally Hazardous Materials .......................................... 85
6.7 Biodiversity and Natural Values ......................................................................................... 90
6.8 Marine and Coastal ............................................................................................................ 99
6.9 Greenhouse Gases and Ozone Depleting Substances ................................................... 118
6.10 Heritage ........................................................................................................................... 120
6.11 Land Use and Development ............................................................................................ 122
6.12 Visual Impacts .................................................................................................................. 143
6.13 Socio-economic Issues .................................................................................................... 145
6.14 Health and Safety Issues ................................................................................................. 147
6.15 Hazard Analysis and Risk Assessment ........................................................................... 149
6.16 Fire Risk ........................................................................................................................... 155
6.17 Infrastructure and off-site Ancillary Facilities ................................................................... 157
6.18 Environmental Management Systems ............................................................................. 158
6.19 Cumulative and Interactive Impacts ................................................................................. 160
6.20 Traffic Impacts ................................................................................................................. 161
7. EPBC Act Assessment ............................................................................................................... 163
7.1 Background ...................................................................................................................... 163
7.2 Matters of National Environmental Significance .............................................................. 163
7.3 Listed Ecological Communities ........................................................................................ 163
7.4 Listed Threatened Species and Migratory Species ......................................................... 164
8. Monitoring and Review ............................................................................................................... 165
9. Decommissioning and Rehabilitation ......................................................................................... 170
10. Commitments ............................................................................................................................. 171
11. Conclusion.................................................................................................................................. 175
12. Limitations .................................................................................................................................. 176
13. References ................................................................................................................................. 177
Table index
Table 2-1 Flow Characteristics at Existing STPs for 1 July 2014 – 30 June 2015 .............................. 9
Table 2-2 Effluent Quality Data for the 1 July 2014 – 30 June 2015 Reporting Period (from
Submitted 2014-15 AERs) ................................................................................................. 11
Table 2-3 Existing Mass Loads .......................................................................................................... 12
Table 2-4 Trade Waste Volumes accepted from 1 July - 30 June 2015 at Blackmans Bay,
Margate and Electrona STPs ............................................................................................. 13
Table 2-5 Required Treatment Capacities ......................................................................................... 14
Table 2-6 Design Effluent Performance of Upgraded STP ................................................................ 16
Table 3-1 STP Process Selection Criteria ......................................................................................... 41
Table 5-1 Land Title Details - Development Site ............................................................................... 46
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | viii
Table 5-2 Land Use Zoning – Location & Description ....................................................................... 49
Table 6-1 Odour Modelling Scenarios ............................................................................................... 60
Table 6-2 Relevant Groundwater PEVs and Water Quality Indicators .............................................. 70
Table 6-3 Noise Criteria for Sensitive Receptors During Operations ................................................ 74
Table 6-4 Noise Criteria for Construction and Emergency Diesel Generation .................................. 75
Table 6-5 Modelled Sound Pressure Levels during Operation .......................................................... 77
Table 6-6 Modelled Sound Pressure Levels during Construction ...................................................... 78
Table 6-7 Vegetation Communities Impacted by the Development................................................... 94
Table 6-8 Upgraded Blackmans Bay Treatment Plant Mass Loads into Derwent Estuary
(median effluent quality)................................................................................................... 107
Table 6-9 Approximate Mass Load Contributions to the Derwent Estuary (median effluent
quality) ............................................................................................................................. 109
Table 6-10 Nitrogenous Compounds Concentration Comparison between Ambient Lower
Derwent Estuary and Outfall Monitoring Sites ................................................................. 112
Table 6-11 Water Quality Monitoring Sites, Parameter Groups and Monitoring Frequency ............. 114
Table 6-12 Water Monitoring Parameters .......................................................................................... 114
Table 6-13 Benthic Infauna Site and Frequency ................................................................................ 115
Table 6-14 Giant Kelp Forest Monitoring Sites .................................................................................. 115
Table 6-15 NGERS Calculations for the Project ................................................................................ 119
Table 6-16 Regulation 11 of the Water and Sewerage (General) Industry Regulations 2009 .......... 123
Table 6-17 Likelihood Ranking with Design Control .......................................................................... 149
Table 6-18 Environmental Consequence Ranking ............................................................................ 150
Table 6-19 Risk Matrix ....................................................................................................................... 150
Table 6-20 Risk Rating Key for Proponent Action and Ultimate Acceptability ................................... 150
Table 6-21 Environmental Hazard Identification and Risk Assessment Outcomes ........................... 151
Table 8-1 Treated Effluent Sampling ............................................................................................... 165
Table 8-2 Receiving Environment Monitoring .................................................................................. 167
Table 10-1 Commitments ................................................................................................................... 171
Figure index
Figure 2-1 Location Map ....................................................................................................................... 5
Figure 2-2 Site Plan ............................................................................................................................... 6
Figure 2-3 Land Tenure and Surrounding Land Use ............................................................................ 7
Figure 2-4 Projected Medium & High Population Growth for Kingborough LGA ................................ 15
Figure 2-5 Process Flow Diagram ....................................................................................................... 19
Figure 2-6 Public Access ..................................................................................................................... 36
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | ix
Figure 5-1 Title Plans .......................................................................................................................... 47
Figure 5-2 Land Use Zoning - Development Site & Surrounds ........................................................... 50
Figure 5-3 Reserves and Geomorphological Features ....................................................................... 53
Figure 5-4 Age and Sex Pyramid for Kingborough (ABS Census, 2006) ........................................... 55
Figure 6-1 Sensitive Receptors considered in Odour Assessment (Source: MWH 2016).................. 58
Figure 6-2 Major odour emission sources modelled (Source: MWH 2016) ........................................ 59
Figure 6-3 Odour Modelling Scenario 1: Normal Operating Conditions (Source: MWH
2016) .................................................................................................................................. 61
Figure 6-4 Odour Modelling Scenario 2: Inlet Works Maintenance (Source: MWH 2016) ................. 62
Figure 6-5 Odour Modelling Scenario 3: Upset in Treatment Process (Source: MWH 2016) ............ 63
Figure 6-6 Odour Modelling Scenario 4: Upset in Sludge Process (Source: MWH 2016).................. 64
Figure 6-7 Noise Sources from Upgraded STP (Source, Vipac 2016) ............................................... 76
Figure 6-8 Residential Locations used for Baseline Noise Assessment (Source, Vipac
2016) .................................................................................................................................. 76
Figure 6-9 Predicted Noise Emission Contours for Normal Operations in Neutral Weather
(Source: Vipac, 2016) ........................................................................................................ 80
Figure 6-10 Predicted Noise Emission Contours for Normal Operations with Temporary
Power Generation in Neutral Weather (Source: Vipac, 2016) ........................................... 81
Figure 6-11 Flora and Ecological Values within STP Footprint ............................................................. 98
Figure 6-12 Modelled 50th and 95th percentile (left and right respectively) tracer
concentrations from the pre-extension Blackmans Bay STP marine outfall over
a 3-month period from December 2003 - March 2004 (from Herzfeld et al, 2005) ......... 110
Figure 6-13 Marine Monitoring Sites ................................................................................................... 117
Figure 6-14 Landslide Hazard Area Overlay & Development Site (Low Landslide Hazard
Area on the Left and Medium Hazard Landslide Area on the Right) ............................... 137
Figure 6-15 Coastal Erosion Hazard Overlay & Development Site .................................................... 141
Appendices
Appendix A - Design Drawings
Appendix B - Ecological Appendices
Appendix C - Sewage Treatment Plant Contingency Management Manual
Appendix D - Near-field Modelling of Effluent
Appendix E - Odour Modelling Report
Appendix F - Noise Modelling Report
Appendix G - Marine Monitoring Reports
Appendix H – EPA Project Specific Guidelines
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 1
1. Introduction
1.1 Title of Proposal
The proposal is referred to as “Blackmans Bay Sewage Treatment Plant Upgrade”.
1.2 Proponent
The proposal proponent is Tasmanian Water and Sewerage Corporation Pty Ltd (TasWater):
TasWater
ACN: 133 654 976
ABN: 47 162 220 653
Australian Private Company
169 Main Road, Moonah, TAS 7009
The contact person for the proponent is:
Lance Stapleton, Department Manager Product Quality
Phone: 0408 175 522 and Email: [email protected]
TasWater is a State Agency responsible for the provision of water, wastewater and recycled
water services throughout Tasmania. TasWater was formed in 2013 from the previous regional
water authorities (Southern Water, Cradle Mountain Water and Ben Lomond Water) and has
over 700 staff. The annual revenue for TasWater is approximately $246 million and annual
capital expenditure of approximately $105 million. Drawing on the combined experience of the
previous water authorities, TasWater owns and operates 113 sewage treatment plants (STPs)
and has the necessary experience in the design and operation of STPs to deliver this Project.
1.3 Proposal Background
1.3.1 Background and Rationale
The existing Blackmans Bay STP has been operating for approximately 30 years, treating
wastewater from the Kingston, Huntingfield, Blackmans Bay and southern Bonnet Hill areas.
Accepted wastewater sources comprise residential, commercial, and to a lesser degree,
industrial.
The current STP operates under the following licence arrangements:
Licence to Operate Scheduled Premises No. 3326 (18/11/1987)
Permit Conditions – Environmental No. 7551 (10/12/2008)
The existing STP treats an average flow of ~4 ML/day, which is approaching the currently
licenced limit (and design capacity) of 4.125 ML/day for average dry weather flow (ADWF).
Effluent quality results in recent years have shown plant performance to be sub-optimal and
odour has been an ongoing issue; this, together with the growing sewage treatment demands
from the current catchment, has highlighted the necessity to upgrade the plant at some point in
the near future.
With the Blackmans Bay STP requiring an upgrade in the near future and TasWater’s parallel
plans to close several underperforming STPs in the Kingborough local government area (LGA),
it was proposed that the sewage catchments from three existing STPs, namely the Margate,
Electrona, and Howden plants could potentially be redirected and amalgamated with the current
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 2
Blackman Bay catchment and directed into the larger upgraded Blackmans Bay STP. A key
driving factor for the amalgamation of STPs at Electrona, Margate and Howden is the long term
benefits to North West Bay by removing wastewater discharges from these underperforming
STPs. The Blackmans Bay STP upgrade has been sized to facilitate this eventuality but is not
contingent upon it and the amalgamation is excluded from this application.
1.3.2 Overview
The proposal is an upgrade of the existing Blackmans Bay Sewage Treatment Plant (the
Project), located on the western shore of the lower Derwent Estuary off Tinderbox Road, at the
end of Treatment Plant Road (south of the main suburban area of Blackmans Bay). The
upgrade will involve both an increase in capacity of the plant as well as improved overall effluent
treatment.
The proposed Project will be designed to cater for current and projected future flows (up to a
~2040 design horizon) for the current Blackmans Bay STP catchment as well as potentially the
wastewater catchments currently serviced by the Electrona, Margate and Howden STPs (which
will eventually be decommissioned under a separate approval process). The transfer of
wastewater from the other three STPs to the Project is outside of the scope of this application.
The Project is anticipated to cost in the vicinity of $30-40 million, with a 24-month construction
period followed by a six-month commissioning period. The project is currently in the design
phase, with construction work aimed to commence as soon as all necessary approvals have
been sought and obtained.
1.4 Legislative Framework
Schedule 2 of the Environmental Management and Pollution Control Act 1994 (EMPCA), states
that Level 2 approval is required for wastewater treatment and disposal of more than 100 kL/day
(ADWF) of effluent. As the Project aims to treat a maximum ADWF of 8.53 ML/day, it is above
the Scheduled Level 2 limit and therefore the Project needs to obtain approval to operate under
the Land Use Planning and Approvals Act 1993 (LUPAA) and EMPCA as a Level 2 activity.
To this effect a Notice of Intent (NOI) was submitted to the Tasmanian EPA in 2014, seeking
confirmation of the level of approval and seeking Project Specific Guidelines. The EPA
determined the project to be a Level 2B assessment and Project Specific Guidelines were
issued in mid-2014. In March 2015 a revised NOI was submitted to the EPA to address some
changes to the proposal and in the same month a response was provided by the EPA
confirming there would be no change to the level of assessment or the Guidelines as a result of
the updated NOI; the Project Specific Guidelines are provided in Appendix H.
The project has not been referred to the Commonwealth under the Environment Protection
Biodiversity Conservation Act 1999 (EPBC Act) as it has been determined by the proponent that
the Project will not significantly impact on any Matters of National Environmental Significance
(MNES) and as such does not trigger the criteria for referral under the EPBC Act. As such there
will be no commonwealth involvement in the planning and environmental approvals for the
Project.
The resulting approval pathway for the Project is the submission of a Development Proposal
and Environmental Management Plan (DPEMP) and associated development application (DA)
to Kingborough Council, which is subsequently referred to the EPA Board for joint assessment
and approval.
In addition to the standard approval process the proposed Project will also have to comply with
a broad range of environmental and planning legislation, guidelines, standards and policies as
described in the relevant sections of this DPEMP.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 3
2. Proposal Description
2.1 Project Overview
The proposed Project is an upgrade of the existing Blackmans Bay STP, located on the western
shore of the lower Derwent Estuary off Tinderbox Road, at the end of Treatment Plant Road
(south of the main suburban area of Blackmans Bay).
The upgrade will involve both an increase in capacity of the plant as well as improved overall
effluent treatment. This will improve odour and noise for residents, as well as improving the
quality of water discharged to the Derwent Estuary and meet EPA compliance requirements.
The Project will be located at the brownfield Blackmans Bay STP site and will consist of both
repurposed existing infrastructure and new infrastructure.
An overview of the Project location is shown in Figure 2-1.
The upgrade includes the conversion of the existing activated sludge system STP with a current
capacity of 4.125 ML/day to an Intermittently Decanted Extended Aeration (IDEA) -sequential
batch reactor (SBR) system with an ADWF capacity of 8.53 ML/day and the ability to treat up to
4 x ADWF for contingency. The upgraded plant will result in a significant improvement in treated
effluent quality, and provide mitigation for odour and noise.
At its core the upgrade will address deficiencies with the current plant to meet emission limits
and manage odour impacts as well as catering for projected increase in sewage flow from the
immediate catchment. In addition, the upgrade has been planned as part of a strategic
rationalisation of STPs in the broader area and will be designed to cater for current and
projected future loads from the ageing Margate, Electrona and Howden STPs, which are
planned for decommissioning (the decommissioning of these plants and influent pipework
transferring these loads to the Blackmans Bay STP is excluded from this application). The
amalgamation of STPs at Electrona, Margate and Howden will provide long term benefits to
North West Bay by removing wastewater discharges from these underperforming STPs.
The Project aims to significantly improve plant performance to the Tasmanian EPA’s Accepted
Modern Technology (AMT) performance criteria (with some seasonal alteration to nitrogen and
phosphorus treatment criteria, explained further below) and to meet the capacity requirements
of projected sewage volumes based on an estimated 2040 population growth horizon for the
aforementioned catchments.
The upgraded plant will contain the following key components:
Inlet works including screens, a vortex grit chamber, grit classifier and collection bins;
Two IDEA-SBR tanks for nutrient removal;
Gravity thickener for waste activated sludge (utilising existing primary sedimentation tank);
Four cell aerobic digester with dewatering centrifuge (utilising existing aeration tank);
Balance tank (utilising existing secondary clarifier infrastructure);
Ultraviolet disinfection system;
New odour control facility including odour treatment via a bio-trickling filter and activated
carbon system, with an associated 12 m emission stack;
Use of the existing 600 m effluent discharge pipeline with 80 m diffuser at the Blackmans
Bay STP (no change to the outfall pipe or diffuser); and
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 4
Landscaping consisting of native grasses, shrubs and trees to reinstate the site values post
construction.
The Project is designed to produce effluent to the water quality limits outlined in Section 2.4.3.
The connection of the additional sewage from the decommissioned plants to the Project is
planned to occur via an overland rising main several kilometres in length, with a final pipeline
route yet to be selected. It is important to note that the construction of the rising main pipeline
for the planned amalgamation scheme and the decommissioning of the Margate, Electrona and
Howden STPs do not form part of the proposal; nor is this proposal contingent upon the
amalgamation proceeding.
The upgrade of the STP is anticipated to cost in the vicinity of $30-40 million, with a 24-month
construction period followed by a six-month commissioning period.
A detailed site plan is presented in Figure 2-2. The existing house shown on the western
boundary of the site is to be used as a site office during the construction phase and demolished
at the completion of construction and native vegetation reinstated in its place.
2.2 Location and Site Context
The proposed Project is located in southern Tasmania on the margins of the township of
Blackmans Bay (refer Figure 2-1).
The Project site itself includes two land titles, one currently owned by TasWater and containing
the existing Blackmans Bay STP, and another currently owned by Kingborough Council which
contains the former caretaker’s cottage (which is currently vacant) and areas for public walking
and recreation. TasWater have entered into discussions with Kingborough Council to purchase
the parcel of land (as marked on Figure 2-3) to facilitate construction of the Project. There is no
requirement for subdivision of this land as TasWater proposes to acquire the entire parcel from
Kingborough Council. TasWater will maintain public access and walking tracks on the land
surrounding the Project as outlined in Section 2.10.
The combined area of both land titles is referred to in this DPEMP as the Project Site (i.e. ‘the
Land’) (refer Figure 2-3).
The Project Site contains the existing Blackmans Bay STP, two waterways/drainage lines, an
existing (vacant) house owned by Council, the Suncoast Headlands Track, an access road
(Treatment Plant Road) and incoming wastewater pipelines, water pipelines and electricity.
The Project Site is a mosaic of exotic grassland and native vegetation including a number of
juvenile and mature eucalypts. The land slopes generally from the west to the east and includes
a geoconservation site along the eastern coastal boundary.
The Project Site is bounded by residential properties to the north and west, by adjoining council
land (used for recreation) to the south and the Derwent Estuary to the east.
The Project Site is accessed via Tinderbox Road and then Treatment Plant Road to the west.
Maps of the Project Site and surrounds are provided in Figure 2-1 to Figure 2-3.
Const
ruction
Acces
s Roa
d
Treatment Plant Road
CURRENT SITE BOUNDARY
40 m
50 m
60 m
70 m
30 m
20 m
10 m
80 m
90 m
100 m
Suncoast Drive
Tinderbox Road
Liberty Court
Wells Parade
Tahun
e Cres
cent
Ephesus Place
Jodie Court
Syracuse Place
Tahune Crescent
526,400
526,400
526,600
526,600
526,800
526,800
5,237,
200
5,237,
200
5,237,
400
5,237,
400
5,237,
600
5,237,
600
G:\32\18107\GIS\Maps\MXD\3218107_001_Figure2-1_Location_RevC.mxd
0 50 10025
MetresMap Projection: Transverse Mercator
Horizontal Datum: GDA 1994Grid: GDA 1994 MGA Zone 55
© 2016. Whilst every care has been taken to prepare this map, GHD (and DATA CUSTODIAN) make no representations or warranties about its accuracy, reliability, completeness or suitability for any particular purpose and cannot accept liability and responsibility of any kind (whether in contract, tort or otherwise) for any expenses, losses, damages and/or costs (including indirect or consequential damage) which are or may be incurred by any party as a result of the map being inaccurate, incomplete or unsuitable in any way and for any reason.
Tasmanian Water CorporationBlackmans Bay STP DPEMP
Figure 2-1
Job NumberRevision C
32-18107
05 Aug 2016
Location MapDate
Data source: DPIPWE (cadastre, imagery, land tenure, land zoning, waterways, contours), TasWater (proposed infrastructure). Created by: jtoregan
2 Salamanca Square Hobart TAS 7000 Australia T 61 3 6210 0600 F 61 3 6210 0601 E [email protected] W www.ghd.com.au
Paper Size A3
LEGENDContours (10 m)WaterwayElectrical to site (OH)Cadastral ParcelDog excersise area
ProposedThe project siteConstruction compound *Existing fenceNew fenceSTP infrastructure
CutFillProposed screening vegetation
* site office, parking, machinery, laydown, stockpiles and bunded fuel and chemical storage.
LOADING / UNLOADINGAREA
CHEMICALSTORAGE
NEW
ACCE
SS R
OAD
TO EXISTINGOUTFALLIDEA-SBR 4-CELL
AEROBICDIGESTER
EFFLUENTATTENUATION
TANK
GRAVITYTHICKENER
AMENI
TIES B
UILDIN
GINLET WORKS
ODOURCONTROL
PLANT
DE-WATERING BUILDING(CENTRIFUGE / WORKSHOP / STORAGE)
IDEA-SBRBLOWERS
UV DISINFECTIONFACILITY
MOTOR CONTROLCENTER
PUMPSTATION
SUBSTATIONSTANDBY GENERATOR
FUTURECLOTHMEDIA
FILTRATION
WATER PUMPSTATION
THICKENED SLUDGEPUMP STATION
40 m
30 m
20 m
50 m
10 m
526,650
526,650
526,700
526,700
526,750
526,750
526,800
526,800
5,237,
300
5,237,
300
5,237,
350
5,237,
350
5,237,
400
5,237,
400
5,237,
450
5,237,
450
5,237,
500
5,237,
500
G:\32\18107\GIS\Maps\MXD\3218107_002_Figure2-2_SitePlan_RevB.mxd
0 10 205
MetresMap Projection: Transverse Mercator
Horizontal Datum: GDA 1994Grid: GDA 1994 MGA Zone 55
© 2016. Whilst every care has been taken to prepare this map, GHD (and DATA CUSTODIAN) make no representations or warranties about its accuracy, reliability, completeness or suitability for any particular purpose and cannot accept liability and responsibility of any kind (whether in contract, tort or otherwise) for any expenses, losses, damages and/or costs (including indirect or consequential damage) which are or may be incurred by any party as a result of the map being inaccurate, incomplete or unsuitable in any way and for any reason.
Tasmanian Water CorporationBlackmans Bay STP DPEMP
Figure 2-2
Job NumberRevision B
32-18107
05 Aug 2016
Site PlanDate
Data source: DPIPWE (cadastre, imagery, land tenure, land zoning, waterways, contours), TasWater (proposed infrastructure). Created by: jtoregan
2 Salamanca Square Hobart TAS 7000 Australia T 61 3 6210 0600 F 61 3 6210 0601 E [email protected] W www.ghd.com.au
Paper Size A3
LEGENDContours (10 m)WaterwayElectrical to site (OH)Cadastral parcel
ProposedThe project siteConstruction compound
Existing fenceNew fenceSecurity gateMajor process pipeSTP infrastructure
CutFill
(site office, parking, machinery, laydown, stockpilesand bunded fuel and chemical storage)
Const
ruction
Acces
s Roa
dTreatment Plant Road
The project area is delineated as 'The Site'and TasWater have entered into an agreementwith Kingborough Council to purchase the land
title within 'The Site'.
172 m
170 m
167 m
170 mSuncoast Headlands Track
Suncoast Headlands Track
Suncoast Headlands Track
Suncoast Drive
Tinderbox Road
Liberty Court
Wells Parade
Tahun
e Cres
cent
Ephesus Place
Jodie Court
Syracuse Place
Suncoast Drive
Tinde
rbox R
oad
Liberty Court
Tahune Crescent
Wells Parade
Tahun
e Cres
cent
Tahune Crescent
Ephesus Place
Jodie Court
Syracuse Place
526,400
526,400
526,600
526,600
526,800
526,800
5,237,
200
5,237,
200
5,237,
400
5,237,
400
5,237,
600
5,237,
600
G:\32\18107\GIS\Maps\MXD\3218107_003_Figure2-3_LandTenure_RevB.mxd
0 50 10025
MetresMap Projection: Transverse Mercator
Horizontal Datum: GDA 1994Grid: GDA 1994 MGA Zone 55
© 2016. Whilst every care has been taken to prepare this map, GHD (and DATA CUSTODIAN) make no representations or warranties about its accuracy, reliability, completeness or suitability for any particular purpose and cannot accept liability and responsibility of any kind (whether in contract, tort or otherwise) for any expenses, losses, damages and/or costs (including indirect or consequential damage) which are or may be incurred by any party as a result of the map being inaccurate, incomplete or unsuitable in any way and for any reason.
Tasmanian Water CorporationBlackmans Bay STP DPEMP
Figure 2-3
Job NumberRevision A
32-18107
21 Jul 2016
Land Tenure and UsesDate
Data source: Data Custodian, Data Set Name/Title, Version/Date. Created by:jtoregan
2 Salamanca Square Hobart TAS 7000 Australia T 61 3 6210 0600 F 61 3 6210 0601 E [email protected] W www.ghd.com.au
Paper Size A3
LEGENDWaterwayElectrical (OH)Cadastral ParcelDog excersize area
Land Tenure (LISTmap, 2016)Private FreeholdPublic ReserveCrown LandLocal GovernmentCasementLocal Government Act ReserveTas Water
ProposedThe Project SiteFenced Area (STP Operational Boundary)Construction Compound(site office, parking, machinery, laydown,stockpiles and bunded fuel and chemicalstorage)
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 8
2.3 Project Rationale and Context
The proposed Project is multifaceted and at its core is driven by a need to improve performance
of the current plant and cater for current and projected increases in flow from the area currently
serviced by the Blackmans Bay STP (Kingston, Huntingfield, Blackmans Bay and southern
Bonnet Hill) heading into the next 20-30 years. The current Blackmans Bay STP is limited in
size and treatment capacity and upgrades are necessary to facilitate ongoing provision of
wastewater treatment to the area services by the existing STP.
With a large number of aging treatment plants across the state, updating of facilities has
become a primary focus for TasWater in the near future. Amalgamation of smaller outdated
STPs into larger centralised schemes is one option that TasWater considers when reviewing its
current wastewater treatment infrastructure across the state; this is often a cost effective and
efficient solution. With this in mind, through the planning of the Blackmans Bay STP upgrade,
consideration was also given to the broader sewage treatment network in the Kingborough
Local Government Area (LGA) and the need to address deficiencies in other smaller local
plants, namely Electrona, Margate and Howden STPs. This has led to the TasWater decision to
decommission Margate, Electrona and Howden STPs and redirect all sewage to the upgraded
Blackmans Bay STP (decommissioning of the other plants and infrastructure to transfer
resulting effluent to Blackmans Bay is outside of the scope of this application).
The proposed Project is not dependant on the decommissioning of the abovementioned STPs,
as the Blackmans Bay STP requires the upgrade regardless.
2.3.1 Amalgamation of Treatment Plants
TasWater has identified the need to improve wastewater treatment in the Kingborough LGA
heading into the next 25-30 years. Issues identified within the current STPs within the LGA
treatment scheme include the following:
The Blackmans Bay STP, which currently services all the urban areas within greater
Kingston, is close to its current treatment capacity and is an aging plant which
underperforms under higher load conditions in the areas of biochemical oxygen demand
(BOD) generation, suspended solids removal and disinfection. There is also a history of
odour complaints associated with the existing plant.
The Margate STP continues to consistently underperform in effluent treatment and requires
upgrading in the near future from a lagoon system and cannot accept any additional
sewage until upgrades are performed.
The lagoon system at Electrona STP underperforms in effluent treatment and, like the
Margate STP, cannot accept any additional sewage until significant upgrades are
undertaken. The current lagoon is overloaded and minimal nutrient removal is achieved.
The Howden STP, although generally functioning satisfactorily, is a small package plant
that would be more cost effective to close and merge the catchment into a larger scheme.
With all major treatment plants mentioned either nearing capacity and/or underperforming,
an increase in both treatment capacity and effectiveness in the immediate future is
required. Amalgamation of the abovementioned STPs into one large STP rather than
separately upgrading each individual plant was in this case seen as the most effective
solution.
Within the Kingborough LGA area, the Blackmans Bay STP was assessed as the most suitable
plant to upgrade in a centralised scheme owing to the following:
It is the largest existing STP and therefore the most cost effective to upgrade;
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 9
It has suitable surrounding land for expansion; and
The STP has a superior existing open ocean effluent discharge pipeline (upgraded in
2010), when compared to the remaining plants, which discharge into the lower energy
North West Bay area.
North West Bay is not considered an optimum receiving environment due to several factors. The
shallow waters and sheltered nature of the bay creates a lower energy environment not
conducive to the most effective mixing when compared with an open ocean outfall. Longer
retention times in the bay of discharged effluent may also result in nutrient build-ups. This can
lead to problem algal growth in the shallower areas and is more likely to impact on the
environment, especially the intertidal habitat at the northern end of the bay.
The long term benefits to North West Bay by removing wastewater discharges from these
underperforming STPs is a key driving factor in the amalgamation of these plants into the
Blackmans Bay STP site.
2.3.2 Existing STPs – Treatment Quantity and Quality
To provide background context to the rationale for the need to improve sewage treatment
quality and capacity, the following sections outline flows, quality and trade waste characteristics
of the existing STPs for the licence reporting period of 1 July 2014 to 30 June 2015.
Treatment Volumes
Flow results for the four STPs for the 2014-2015 reporting period are presented in Table 2-1. It
should be noted that licences for these plants are not in the form of modern contemporary
licences and are outdated to a degree.
The results identify the Blackmans Bay STP is at capacity and therefore requires upgrade and
also highlights that the Electrona STP is also approaching capacity.
The Margate STP flows do not suggest a need to immediately upgrade for physical flow
capacity, however the issue with this plant is more related to effluent treatment effectiveness, as
highlighted in the following section.
Table 2-1 Flow Characteristics at Existing STPs for 1 July 2014 – 30 June
2015
STP 2014-2015
Average Daily
Flow (kL/day)
Licence Limit –
Average Dry Weather
Flow (kL/day)
Month with highest
average daily flow
(kL/day Average)
2014-2015
Highest Peaking
Flow (kL)
Blackmans
Bay
3985 4125 4800 (Aug) 15,260
Margate 362 681 474 (Jul) -
Electrona 310 450 492 (Aug) 1,857
Howden 42 100 56 (Jun)
Total 4699 - - -
Table Note – The Blackmans Bay STP also has a licence limit of 15,000 maximum wastewater
throughput (kL/day).
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 10
Effluent Quality
Effluent qualities at the four STPs are shown in Table 2-2 for the 2014-15 reporting period. The
table shows the compliance percentage with the STP licenced discharge limits; as can be seen,
non-compliances occur at all STPs for several parameters.
When results are compared to the proposed treatment that will be achieved by the Project in
Section 2.4.3, it can be seen that a large improvement in effluent quality will be achieved when
compared to the current standard.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 11
Table 2-2 Effluent Quality Data for the 1 July 2014 – 30 June 2015 Reporting Period (from Submitted 2014-15 AERs)
Parameter
(mg/L unless
otherwise
stated)
Blackmans Bay STP Margate STP Electrona STP Howden STP M
ed
ian
90
th
Ma
x
EP
N
Lim
it
EP
N
Co
mp
lia
nce
Me
dia
n
90
th
Ma
x
EP
N
Lim
it
EP
N
Co
mp
lia
nce
Me
dia
n
90
th
Ma
x
EP
N
Lim
it
EP
N
Co
mp
lia
nce
Me
dia
n
90
th
Ma
x
EP
N
Lim
it
EP
N
Co
mp
lia
nce
BOD5 22 51 68 40 83% 36.5 72.8 76 66 75% 156 237 280 206 83% 8 24.8 27 15 67%
Suspended
Solids
15.5 24.2 28 60 100% 24.2 50.8 57 66 100% 98 198 418 186 83% 7 22 44 20 83%
Thermotolerant
Coliforms
(cfu/100ml)
155 694 5600 1000 92% 50 154 770 750 92% 255 105400 120000 1000 67% 235 771 970 1000 100%
Oil & Grease 1.4 2.2 2.3 10 100% 2.25 3.47 3.5 10 100% 20.4 58.9 63.4 46 83% 1 1 1 10 100%
Total Nitrogen 42.6 55.0 57.5 - - 55.3 62.73 63.0 44 17% 51.7 57.9 65.0 65 100% 11.9 21.9 22.1 15 58%
Ammonia
Nitrogen
29.8 41.9 43.6 - - 40.2 45.5 47.7 37 33% 32.1 36.4 43.5 45 100% 4.2 17.6 18.5 10 67%
Total
Phosphorus
8.6 9.47 11.8 - - 9.35 9.99 11.7 10 92% 8.15 11.1 11.4 12 100% 1 2.41 3.8 10 100%
Cl 0.76 1.26 2.93 1 75% 1.13 3.0 5.19 1 75% 0.71 6 6 1 73% - - - - -
Min
50
th
Ma
x
EP
N L
imit
EP
N
Co
mp
lia
nce
Min
50
th
Ma
x
EP
N L
imit
EP
N
Co
mp
lia
nce
Min
50
th
Ma
x
EP
N L
imit
EP
N
Co
mp
lia
nce
Min
50
th
Ma
x
EP
N L
imit
EP
N
Co
mp
lia
nce
pH 5.8 7.2 7.5 6.5-
8.5
96% 6.19 7.68 7.86 6.5-
8.5
96% 6.32 7.19 7.43 6.5-
8.5
95% 5.9 7.81 8.55 6.5 -
8.5
92%
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 12
Mass Loads
Existing mass loads for the upgraded treatment plant were calculated using the median effluent
quality for each of the contributing treatment plants and flows presented in Table 2-1 and Table
2-2 (July 2014 to June 2015). The parameters selected were based on those for which there is
an existing license condition. The result are provided in Table 2-3.
Table 2-3 Existing Mass Loads
Parameter Blackmans
Bay STP
(kg/day)
Margate
STP
(kg/day)
Electrona
STP
(kg/day)
Howden
STP
(kg/day)
Total kg/day
Combined
Plants
Total
BOD5 87.7 13.2 48.4 0.034 149.3 54.5
TSS 61.8 8.8 30.4 0.029 100.9 36.8
Oil &
Grease 5.6 0.8 6.3 0.004 12.7 4.6
Total
Nitrogen 169.8 20.0 16.0 0.050 205.9 75.1
Ammonia
Nitrogen 118.8 14.5 9.9 0.018 143.2 52.3
Total
Phosphorus 34.3 3.4 2.5 0.004 40.2 14.7
Trade Waste
The existing Blackmans Bay STP accepts sewage from a variety of residential, commercial, and
to a lesser degree, industrial premises, with no trade waste over Category 2C. The key
parameters of concern in the industrial waste stream include: ammonia, nitrogen, biochemical
oxygen demand (BOD), total suspended solids (TSS), total dissolved solids (TDS), sodium and
oil & grease.
Margate and Electrona accept mainly residential and commercial sewage, with the Margate
STP accepting Category 2A and 2B trade waste, and Electrona STP accepting Category 2A
only. No key industrial contaminants of concern were identified from these waste streams.
The Howden STP does not accept any trade waste.
Trade waste customer numbers and accepted volumes for 1 July 2014 – 30 June 2015 at the
three STPs are detailed in Table 2-4. Note that no Category 3 or Category 4 waste is accepted
at any of the STPs.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 13
Table 2-4 Trade Waste Volumes accepted from 1 July - 30 June 2015 at
Blackmans Bay, Margate and Electrona STPs
Trade
Waste
Category
Blackmans Bay STP Margate STP Electrona STP
Number of
Customers
Estimated
Volume
(ML/year)
Number of
Customers
Estimated
Volume
(ML/year)
Number of
Customers
Estimated
Volume
(ML/year)
Cat 1 26 3.0 5 0.6 1 0.1
Cat 2A 47 8.7 10 1.9 4 0.7
Cat 2B 7 2.1 2 0.6 - -
Cat 2C 5 2.5 - - - -
Tankered 1.8 - - - -
Total 85 18.1 17 3.1 5 0.8
2.3.3 Improved Treatment Technology
As can be seen from Section 2.3.2, the existing STPs have several issues with treatment quality
and capacity, with exceedances of some parameters occurring on a regular basis. There is also
the issue of odour complaints at the Blackmans Bay STP; complaints were received several
times over the 2014-2015 reporting period.
The design of the Project will utilise significantly more modern treatment equipment than is
currently employed, including mitigation for problematic issues that have been occurring at the
existing STPs. This includes:
An odour control facility integrated into the primary treatment system to remove and treat
foul air;
Large improvement in nitrogenous compound removal through the use of modern IDEA-
SBRs; and
Upgraded disinfection through the use of an ultraviolet treatment system.
2.4 Project Design Parameters
2.4.1 Proposed Treatment Capacity
The Project is designed to cater for 8.53 ML/day ADWF.
The rationale of the new plant includes having sufficient capacity to treat wastewater received
from the four STP catchments to at least a ~2040 horizon.
A similar methodology to the one outlined below was originally used to calculate the standing
8.53 ML/day treatment design capacity, which has been used extensively in the design process
to date. As this number was calculated a number of years ago, it was seen as prudent to
reassess capacity requirements using more up to date catchment data to ensure the design
capacity was still appropriate.
The following methodology was utilised to determine the required capacity of the new plant and
whether the existing design capacity of 8.53 ML/day was still suitable.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 14
Influent flow data was analysed for the four STPs from the 2014-15 reporting period (and
available TasWater data for the Level 1 Howden STP) to calculate a combined total estimated
ADWF as of June 2015. This was calculated to be approximately 4,400 ML/day ADWF and
presents a starting point for the currently required ADWF treatment capacity of all the STPs.
In order to estimate future flows and hence the new STP size requirement, the percentage
change in population from 2012 – 2040 was calculated and the percentage difference used to
estimate future ADWF requirements.
Projected population growth data for the Kingborough LGA generated by the Department of
Treasury and Finance (DOTF) was utilised to estimate the 2040 population increase.
The data available was for low, medium and high growth rates from 2012 – 2037. Therefore, in
order to estimate further towards 2040, the data was analysed to develop a formula to extend
the projection towards 2040 and beyond. The growth formulas used by the DOTF were found to
be linear and were applied to medium and high growth population estimates to provide a 2040
estimate.
Figure 2-4 provides the projected medium and high population growth for the Kingborough LGA
in a medium growth environment, which equated to a 2040 population projection of 50,089, a
change of approximately 42.7 % from 2012. The projected population increase for a high growth
environment was 58,520, a change of approximately 66.8 % from 2012.
Using the percentage population changes as an estimation figure for future treatment volume
requirements gives the estimates presented in Table 2-5. These projected treatment capacities
are compared to the ‘current’ 4,400 ML/day ADWF from the combined Blackmans Bay,
Electrona, Margate and Howden STPs, using 2014/15 data.
Table 2-5 Required Treatment Capacities
Year Predicted ADWF from Medium
Growth Rates (kL/day)
Predicted ADWF from High
Growth Rates (kL/day)
2040 6,336 7,404
Using the high growth data for conservatism, the projected ADWF treatment capacity required
for the new plant in 2040 is estimated at 7.4 ML/day.
Limitations with the calculation methodology that must be taken into account include that the
numbers used are projections only and that they are for the entire Kingborough LGA, with
potentially more or less growth in the focussed catchment areas of Margate, Electrona, Howden
and Blackmans Bay.
The calculations reaffirm that the original design capacity of 8.53 ML/day ADWF at a 2040
design horizon is more than adequate to treat the projected flow requirements, therefore no
alterations to design capacity were necessary. The 8.53 ML capacity in the design will provide
additional operating headroom in the years leading up to the design horizon, providing a high
degree of redundancy in treatment capacity.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 15
Figure 2-4 Projected Medium & High Population Growth for Kingborough LGA
2.4.2 Proposed Treatment Process - SBR
Two sewage treatment processes were considered for the upgrade of the Blackmans Bay STP
A Membrane Bioreactor (MBR) and a Sequenced Batch Reactor (SBR). The primary difference
between these processes is that the SBR achieves solids removal by sedimentation (wi thin the
bioreactor) while the MBR achieves solids removal through membrane filtration. An SBR has
been selected as the preferred technology as outlined in Section 3.5 - Alternative Treatment
Plant Technology.
Further detail on the specifics of the adopted treatment process are provided in Section 2.5.
2.4.3 Proposed Treated Effluent Quality
The proposed upgrades to the Blackmans Bay STP have been designed to achieve a high level
of effluent quality. Accepted Modern Technology (AMT) limits outlined in the Emission Limit
Guidelines for Sewage Treatment Plants that Discharge Pollutants in Fresh and Marine Waters
(ELG) (June 2001) were used as a basis for effluent quality design and modified to suit site
specific receiving environment conditions. The final design effluent treatment targets for the
upgraded Blackmans Bay STP are displayed in Table 2-6.
By comparing the proposed emission limits below to current plant performance (refer Table 2-2)
it can be seen that a considerable improvement in treated effluent quality is proposed
particularly with respect to nitrogen and ammonia removal.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 16
Table 2-6 Design Effluent Performance of Upgraded STP
Parameter Unit
Median 90th Percentile Max
Normal Winter Normal Winter Normal Winter
Ammonia (as N) mg/L 1 3 2 5 5 10
Total Nitrogen (as N) mg/L 7 15 10 25 15 35
Total Phosphorus mg/L 10 12 15
BOD5 mg/L 10 15 20
TSS mg/L 10 20 30
Oil & Grease mg/L 2 5 10
Thermotolerant
Coliforms
CFU/100ml 200 500 750
pH - 6.5 to 8.5
Table Notes:
*Normal is defined as all months other than winter (i.e. Sept to May inclusive).
**Winter is defined as the months June, July and August inclusive.
Nutrient Removal
The exception to the AMT limits are the concentration limits proposed for total nitrogen,
ammonia, and total phosphorus. For these parameters, adjusted effluent quality targets were
developed by TasWater based on the characteristics of the receiving environment (Derwent
Estuary), as outlined below.
The Derwent Estuary has historically shown significant fluctuations in nutrient concentrations
with seasonal changes (DEP, 2015). Oxides of nitrogen and ammonia/ammonium (the
bioavailable components of total nitrogen) and dissolved reactive phosphate (the bioavailable
form of total phosphorus) historically tend to increase significantly in concentration during winter
months in the lower estuary (DEP, 2015). This is thought to be a combination of both changes in
upstream inputs of nutrients from anthropogenic sources and through natural seasonal oceanic
input variation throughout the year.
Relaxed effluent quality targets (limits) for nutrients are being proposed by TasWater for the
Project, resulting in increases to AMT limits. Specific rationales for each proposed nutrient limit
are provided below.
Total Nitrogen/Ammonia
One of the most significant tasks of the STP is the removal of nitrogenous compounds through
biological nutrient removal processes. These processes are influenced by sewage temperature,
with rates of conversion slowing significantly as influent temperatures drop, resulting in the
requirement to treat the sewage longer in the bioreactor or heating the reaction during winter
months to maintain the same efficiencies as warmer months.
By reducing the degree of treatment required for nitrogenous compounds, significant efficiencies
in power consumption and the STP footprint itself can be made (i.e. smaller bioreactor); forming
the rationale behind the proposed relaxed limits.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 17
With the higher ambient concentrations of nitrogenous compounds in the receiving environment
during winter mentioned previously, the release of effluent with slightly higher concentrations
than AMT during this period is not seen as a significant risk to the receiving environment. This is
covered in detail in Section 6.8 where risks to the marine environment are discussed.
With this in mind, the most cost effective and efficient solution for the Blackmans Bay STP was
to design the plant with seasonal nitrogenous compound removal targets. During winter months
(June, July, August) when influent temperatures are lowest and nitrogen levels highest in the
receiving environment, nitrogen (and ammonia) removal will be relaxed. During the remainder of
the year when influent temperatures are higher and nitrogen levels are lower in the receiving
environment, AMT limits will be adhered to.
Phosphorus
The design of the STP is not specifically aimed at the removal of phosphorus, however some
removal is achieved in the biological processes, through the uptake of phosphorous in activated
sludge biomass, and removal of suspended solids. Removal of additional phosphorus is
possible (if required) but would require the addition of chemicals such as aluminium sulphate or
ferrous chloride into the treatment process. This would result in approximately 15-20% greater
sludge production due to the chemical precipitation required to achieve the required
phosphorous removal.
Algal blooms are considered one of the major potential impacts of eutrophication of a waterway.
As the limiting nutrient in algal growth in the lower portions of the Derwent Estuary is considered
to be nitrogen, relaxation of the effluent concentration limits of phosphorus in comparison to
AMT limits (four-fold increase for 90th percentile effluent) are not seen as a significant risk to the
marine environment. This is considered in more detail in Section 6.8 also.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 18
2.5 Sewage Treatment Plant Design
Following the design capacity rationale outlined in Section 2.4.1, the Project has been designed
to treat an ADWF of 8.53 ML/day, with an estimated 2040 design horizon. The plant has been
designed to provide full treatment at flows up to 34 ML/day (4 x ADWF at the design horizon).
The plant will be capable of hydraulically passing 700 L/s (60.5 ML/day). Management of wet
weather flows is discussed in Section 2.5.9.
The following sections describe the proposed treatment process in sequential order. The
schematic in Figure 2-5 outlines the treatment process in more detail.
2.5.1 Primary Treatment
Inlet Works Structure
The inlet works is an above ground concrete structure which receives the raw sewage, removes
certain contaminants, including screenings and grit. All concrete channels are covered and the
foul air extracted and treated in an odour control unit. The inlet works structure is designed to
hydraulically pass all flows to the plant.
Inlet Screens
Sewage will initially be accepted in a receival chamber where it will be passed through three 3
mm spiral screw screens operating in parallel. A standby unit is provided for redundancy. The
spiral screw screens will capture and remove larger waste contaminants within the influent,
which will be conveyed, washed and dewatered by dewatering screws to an odour-controlled
screening bin for collection. Each screw screen will have a capacity of 304 L/s.
A bypass channel with a manually raked coarse bar screen is provided as a backup to the
primary screens in the event of blockages.
Vortex Grit Chamber and Classifier
Screened sewage is passed into a single vortex grit chamber to remove grit from the screened
sewage. The grit chamber underflow is periodically pumped to the grit classifier where organics
are removed and the grit is conveyed and dewatered to an odour-controlled grit bin for
collection. The vortex grit chamber has a nominal capacity of 880 L/s, suffic ient to process all
screened sewage flows.
A grit chamber bypass is provided for maintenance purposes.
The screened and degritted sewage then passes to the IDEA-SBR for secondary treatment.
RECEIVALCHAMBER
RAWSEWAGESCREENS
CELL #1 CELL #2 CELL #3 CELL #4
EXIST GRAVITY THICKENER
EXISTING AERATION BLOWERS
CENTRIFUGE
BALANCE TANK
GRIT BIN SITE ODOUR CONTROL
UV DISINFECTION
AEROBIC DIGESTER
CENTRATE PUMPS
ACTIVATED CARBON
AERATIONBLOWERS
BIO-TRICKLING FILTER
RAKED SCREEN
STACK
GRITVORTEX
CHAMBER
GRITCLASSIFIER
FLOWSPLITTER
EFFLUENTDISCHARGE
SERVICEWATER
DEWATERED SOLIDS BINS
IDEA-SBR #2
IDEA-SBR #1SEWAGE
AEROBIC DIGESTER
This Drawing must not beused for Construction unlesssigned as Approved
Date
CheckDrafting
Plot Date: Cad File No:
DateDrawnRevisionNo A3Original Size
Title
Project
Client
Check
DesignerDrawn
Scale
DesignConditions of Use.This document may only be used byGHD's client (and any other person whoGHD has agreed can use this document)for the purpose for which it was preparedand must not be used by any otherperson or for any other purpose.
DO NOT SCALE
Note: * indicates signatures on original issue of drawing or last revision of drawing
2 Salamanca Square Hobart TAS 7000 AustraliaGPO Box 667 Hobart TAS 7001T 61 3 6210 0600 F 61 3 6210 0601E [email protected] W www.ghd.com
28 July 2016 - 3:53 PM G:\32\18107\CADD\Drawings\32-18107-B001.dwgPlotted By: Robin Lawson
(Project Director)Approved
JobManager
ProjectDirector
PRELIMINARY
32-18107-B001 A
RSL
AS SHOWN
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 20
2.5.2 Secondary Treatment
Intermittently Decanted Extended Aeration – Sequential Batch Reactors (IDEA-SBR)
Secondary treatment of the screened and degritted sewage will be provided by two
Intermittently Decanted Extended Aeration – Sequential Batch Reactors (IDEA-SBRs). The
purpose of the secondary treatment is to oxidise organic material, oxidise ammonia and organic
nitrogen to nitrates (“nitrification”), and subsequently convert nitrates to nitrogen gas
(“denitrification”), hence reducing the total nitrogen of the sewage. Suspended solids are also
retained in the IDEA-SBRs.
The terms IDEA and SBR refer to two possible process operating modes. IDEA mode involves
continuous inflow to both bioreactors, whereas SBR mode involves inflow only during the
aerate/react phase.
Under both the SBR and IDEA modes, conditions in each bioreactor are passed through a
series of timed phases to achieve biological processing of the pollutant load (“aeration” phase),
settling of the biomass to leave a clear supernatant layer at the bioreactor surface (“settling”
phase), and removal of the clear supernatant layer as effluent (“decant” phase). On completion
of these three distinct phases, the cycle is repeated.
The sewage feed to each IDEA-SBR tank passes first to a small anoxic selector tank where it is
mixed with return activated sludge (RAS) pumped from the downstream end of the tank. The
selector is configured to provide a high ratio of substrate (“food”) to biomass (“microbes”) to
protect against the proliferation of certain types of filamentous organisms, and promote the
formation of a plant biomass with favourable settleability. The selector is fitted with mechanical
mixers to maintain the biomass in suspension throughout the operational cycle.
The flow from the anoxic selectors will pass to a “swing zone” operated under aerobic or anoxic
conditions as required. Under normal loading conditions, the swing zone will typically be
operated under anoxic conditions with aeration limited to periodic pulsing for mixing purposes.
In this mode, the swing zone shall promote effective denitrification throughout the operational
cycle. During periods of higher than normal loading, or low temperatures, the zone may be
operated aerobically to enhance nitrification.
From the swing zone, the flow will pass to the main zone of the IDEA-SBR tank. During the
“aeration” phase, oxygen is supplied to the main zone of the IDEA -SBR tanks by the Aeration
Blowers via the Fine Pore Membrane Diffusers. The aeration phase will also include periods of
low or no dissolved oxygen during the aeration phase to increase the extent of denitrification .
At the end of the “aeration phase” aeration is stopped to allow the biomass to settle. On
completion of the “settling” phase, the decant mechanism at the downstream end of the tank will
gradually lower to withdraw the clear supernatant, which will flow to the Balance Tank to
moderate the flow prior to disinfection. At the conclusion of the “decant” phase, the IDEA -SBR
tank will have returned to the initial bottom operating water level, the decant mechanisms will be
raised to the park position above the water surface, and the IDEA-SBR tank will return to the
“aeration” phase.
During each operating cycle, a portion of the biomass will be withdrawn from each IDEA-SBR
and transferred to a Gravity Thickener, in order to maintain the desired solids retention time
(sludge age) in the reactor.
The IDEA-SBRs provide full treatment at flows up to 34 ML/day (4 x ADWF at the design
horizon), through operating in a “storm mode” which involves shortening the durations of the
aeration, settling and decant phases. At flows greater than 34 ML/day, the operation of the
system will switch to “continuous decant” mode.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 21
During operation in continuous decant mode, flow is evenly split between both IDEA-SBR tanks
and the aeration system in the main zone of the IDEA-SBR tanks is shutoff, such that they act
as a clarifier.
Management of wet weather flows is discussed in more detail in Section 2.5.9.
2.5.3 Sludge Treatment
Gravity Thickener
The waste biomass or Waste Activated Sludge (WAS) is transferred from the IDEA-SBRs to a
gravity thickener to increase the WAS concentration as required by the Aerobic Digester
downstream. The thickened WAS is pumped from the underflow of the gravity thickener to the
Aerobic Digester, while the resultant supernatant will be transferred to the Balance Tank.
A standby thickened WAS pump is provided for redundancy, and the gravity thickener
supernatant can alternatively be reprocessed through the IDEA-SBR tanks if it is of a poor
quality.
Aerobic Digester
The WAS will be stabilised through aerobic digestion in a four-cell Aerobic Digester. The aerobic
digester cells will be intermittently aerated using Aeration Blowers via Fine Pore Membrane
Diffusers. This aeration pattern will cycle each cell between aerobic conditions (to nitrify the
ammonia released through digestion to nitrate) and anoxic conditions (to denitrify the nitrate
formed) in order to maintain a neutral pH in the digester.
The digester is configured such that one cell can be removed from service without disrupting
digestion in the remaining cells. A standby aeration blower is also provided for redundancy
purposes.
Stabilised sludge will be pumped directly from the final Aerobic Digester cell to the Dewatering
Centrifuges.
Dewatering Centrifuge
The Dewatering Centrifuge is the final step in the sludge treatment process and will dewater the
sludge (biosolids), with the dewatered cake transferred to covered, odour-controlled self-loading
bins for collection and removal offsite. The liquid (centrate) from the separation process will then
be transferred back to the inlet works for treatment.
The sludge transfer pumps, transfer pipeline, centrifuges, sludge transfer conveyors, self-
loading bins, and centrate pipeline will be fully enclosed and continuously ventilated to the
odour control system to prevent odour emissions.
2.5.4 Tertiary Treatment / Disinfection
Balance Tank
The supernatant from the SBRs will be transferred into a Balance Tank, which will be operating
on different timing cycles under ADWF conditions.
The existing secondary clarifier onsite will be reconfigured as the Balance Tank. The outflow
from the Balance Tank will be controlled by an actuated valve during dry weather conditions to
smooth the intermittent decant flows from the IDEA-SBR tanks to the UV disinfection system.
Under the high flows associated with wet weather events, the actuated valve will be closed and
the Balance Tank will operate as a clarifier to capture additional solids from the effluent stream.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 22
Ultraviolet Disinfection
Disinfection of the secondary effluent will be achieved by UV disinfection in three reactors
configured as Duty/Duty/Assist. The plant shall also include provision for the addition of cloth
media filters in the future.
The UV dose applied to the secondary effluent will be adjusted through manipulation of the
power applied to the UV lamps, and during wet weather events, the number of UV reactors in
service. It is anticipated that only one UV unit will be required under the design 2040 ADWF of
8.53 ML/day, with the second and third units used during peak and wet weather events.
The existing chlorine disinfection system will no longer be used.
2.5.5 Effluent Discharge
Following disinfection, the resultant treated effluent will be discharged through the existing 600
m long open ocean outfall to the east of the plant, in approximately 13 m of water. The outfall
includes an 80 m long diffuser at the terminus of the pipeline, the diffuser has 21 individual 80
mm ports spaced at 4 m intervals. The effluent discharge pipeline and diffuser are already in
place and no changes to the outfall or diffuser are proposed as part of this application.
2.5.6 Odour Control
The Odour Control System will continuously extract foul air from the gravity section of the
incoming sewage main, the Primary Treatment Area, Flow Splitter, Biosolids Dewatering
System, Dewatered Cake Self Loading Bins, and General Purpose Pump Station. The forced air
extraction will maintain each of these enclosed process units at a negative pressure to prevent
fugitive odour emissions. Where necessary, the air inlets to these process units will be fitted
with weighted air inlet dampers which will close to limit fugitive emissions on a loss of sealing
(e.g. on opening of an inspection hatch).
The foul air extracted from the process will be treated using a Two Stage Bio-trickling Filter
(BTF) followed by an Activated Carbon Filter, then discharged to the atmosphere via a 12 m
stack.
The BTF removes both volatile organic compounds (VOCs) and hydrogen sulphide, while the
Activated Carbon Filter provides a polishing function.
An odour impact assessment is provided in Section 6.1.
2.5.7 Noise Control
Noise at the Project site will be emitted from several sources, including the inlet works
mechanical equipment, the Motor Control Centre (MCC), generators, extraction fans, IDEA-SBR
and aerobic digester blowers, and air compressors associated with the centrifuge system. The
design limit for noise exposure onsite is set at 70 dBA at 1 m from the envelope of the noise
source, this is in accordance with AS1217.1.
The main mitigation for noise emissions at the plant is through the enclosure of noise emitting
processes and machinery. The following is included in the plant design to mitigate noise
emission from the abovementioned sources:
Blowers are to be installed in acoustic enclosures and under cover;
Acoustic insulation in the MCC room;
The centrifuge system including air compressors will be located inside the biosolids
management building
Odour fans and ducting will meet the design specification of <75 dB; and
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 23
Generators to be installed inside acoustic enclosures.
A noise assessment is provided in Section 6.4. The degree of noise mitigation on key
infrastructure will be consistent with the model assumptions in the Noise Assessment (refer
Section 6.4).
2.5.8 Ancillary Components
Motor Control Centre (MCC)
This building will be used to control power to the various motorised items of equipment around
the plant. A new substation will be located adjacent to the MCC.
Amenities Building
The existing control building onsite will be refurbished into an amenities building for staff.
Work Shop
A workshop and storage area will be integrated into the dewatering building.
Fencing
Existing fencing will be extended to encompass the whole of the upgraded facility.
Roads and Turning Areas
A new section of access road is included in the proposed design, which will run between the
SBR and inlet works area around the east of the plant and link with the existing access road as
shown in Figure 2 2.
A new hardstand turning circle area is also included to the east of the dewatering building to
allow trucks to collect biosolid waste from the centrifuge area.
Stormwater Management
Stormwater from the majority of the existing site is captured by drains and stormwater pipes and
transferred to the nearby creeks and over the cliff to the marine environment.
The proposed upgrade will involve small additional roof areas, access roads and hardstand,
resulting in a relatively small increase in stormwater.
The intention of the new design is to minimise collection and concentration of stormwater and
allow natural flows to occur wherever possible. Diversion drains will be installed around the
upslope edge of new hardstand areas to direct clean stormwater away from the site. Any new
roofed structures will be sloped to direct rainwater onto adjacent hardstand areas. New
hardstand areas will be sloped to direct stormwater away from the site and into constructed
grass swales before diffuse discharge into the surrounding environment. Some of the new site
stormwater will be captured by the existing stormwater collection system through natural s urface
drainage (e.g. from parts of the new access road).
The Kingborough Interim Planning Scheme 2015 includes a requirement for sites with new
impervious areas greater than 600 m2 (applicable to this Project) to have a stormwater system
for the new development sufficient to achieve the targets set out in the State Stormwater
Strategy 2010 (unless it is not feasible to do so). In response to this requirement, during the
detailed design phase of the project a detailed stormwater design will be prepared (including
review of the existing stormwater capture) to achieve the stormwater management targets for
new developments as set out in the State Stormwater Strategy 2010 (unless it is not feasible to
do so). Any installed features (such as vegetated swales) will be planned to avoid any impacts
to existing native vegetation.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 24
Contained and potentially contaminated areas of stormwater will be collected via new pipework
and directed to the inlet works of the new plant for treatment. This includes the sludge bund
loading area, the inlet works, screenings and grit collection bin area and the diffuser wash-down
area near the IDEA/SBR tanks.
Landscaping
At the completion of the construction phase all temporary facilities (e.g. construction compounds
etc) will be reinstated and revegetated using native species. In addition to reinstatement of
temporarily disturbed areas (to be done immediately following construction); new landscaped
areas will be created around the new STP to provide visual screening. Landscaping of the site
will involve planting of native tree, shrub and grass species. An indication of the area to be
landscaped is shown on Figure 2-2 with more detailed information provided in the design
drawings in Appendix A. Note that where landscaping is proposed in areas of existing
vegetation, this will be to supplement the existing native vegetation on site and existing native
trees within the landscaping zones will be retained.
2.5.9 Capacity for Upset Conditions
Upset conditions and contingency includes planning for storm and extreme weather events as
well as consideration for power and equipment failure.
The STP will have a number of different operating modes in order to cater for increased inflows
during wet weather – a shortened “storm” cycle and “continuous decant” mode. These are
described below.
The intention of the system design is that pump stations in the Blackmans Bay catchment will be
operated in a way that only triggers the STP to move into “continuous decant” mode when
deemed absolutely necessary. This decision will consider the available wet weather/emergency
storage at the pump stations and the maximum instantaneous pumping rates.
Based on recent experience at the existing Blackmans Bay STP1, it is expected that the
upgraded STP will received flows of greater than 34 ML/d (which would move the STP from
“storm” mode into “continuous decant” mode) on a very infrequent basis. For comparison
purposes, the maximum daily flow received at the Blackmans Bay STP in the three-year period
Jan 2013 – Jan 2016 was 15.9 ML/d.
“Storm” Events (Storm Cycle)
During storm flow events, when influent flows exceed nominally 25-30 ML/d (>3-3.5 x ADWF at
the design horizon), the system will adopt a shorter “storm” cycle, with a reduced aeration phase
(nominally 1 hour rather than the 2 hours under normal dry weather operation). This allows
higher wet weather flows to be treated and achieves compliance with the proposed 90th
percentile emission limits during such storm events.
It should also be noted that it may be possible to operate in “storm” cycle at even higher flows
than stated, depending on the STP’s operating parameters at the time (specifically the settling
capacity of the biomass).
“Extreme” Weather Events (Continuous Decant Mode)
During extreme events where influent flows exceed a flow of greater than 34 ML/d, (>4xADWF
at the design horizon), the system will automatically switch from the “storm” cycle to a
“continuous decant” mode. In this mode of operation flow enters both IDEA-SBR tanks, the
1 The upgrade has been sized to cater for Margate, Electrona and How den flows and peaks are also experienced in their catchments, how ever as Blackmans Bay f low s make up 85% of total f low s and there is considerable redundancy in the design
sizing, additional consideration of peak f low s in these catchments other has not been discussed herein.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 25
aeration system in the main zone is shut-off and the decanters rise to their top level, and the
tanks essentially act as clarifiers.
Extreme weather events are infrequent and typically short in duration, and therefore the plant
will not remain in “continuous decant” mode for extended periods. The plant influent is also
significantly diluted during these extreme wet weather events.
Solids contact stabilisation is achieved by maintaining operation of Return Activated Sludge
(RAS) pumps, and the “first flush” of incoming sewage is diluted in the IDEA-SBR tanks. The
effluent will then pass through the balance tank, where it will operate as a clarifier to capture
additional solids from the effluent stream during wet weather.
All wet weather flows will then pass through the UV disinfection unit for treatment, where all
three UV units will be operative to achieve greater disinfection. Operation in “continuous decant”
mode provides a superior level of treatment to the alternative of bypassing screened and
degritted sewage during extreme events of greater than 34 ML/d, (> 4 x ADWF at the design
horizon).
Power Failure and Equipment Failure
The site and all infrastructure will be subject to a routine maintenance program to limit potential
for equipment failure. In the event of equipment failure there is redundancy built into the design
to provide for back up processing (e.g. multiple process units in most cases) until any issues
can be repaired.
As the Blackmans Bay STP is not a gravity fed plant (i.e. sewage is pumped to the site) any
local power failure may also affect incoming flows to the plant and will be managed at the pump
stations rather than the plant itself. Localised power failure at the site only (i.e. not affecting
pump stations) will be managed in the short term through operation of an emergency generator
(refer Figure 2 1) to maintain critical STP operations.
During operation with the emergency generator, raw sewage will be screened, degritted and
pass through the SBR-IDEA tanks, which will operate in continuous decant mode. In continuous
decant mode, solids contact stabilisation will be achieved by operation of Return Activated
Sludge (RAS) pump. The SBR-IDEA tanks will act as a clarifier, and clear water will pass
through to the effluent balance tank (existing secondary clarifier). The effluent balance tank will
also operate as a clarifier, allowing additional settlement of solids. Effluent will then pass
through the UV disinfection system. The odour control system will continue to operate. SBR-
IDEA aeration, aerobic digestion, and dewatering processes will be suspended during these
power outage events.
Some deviation of effluent quality may be experienced during such a power outage; however,
the frequency and duration of power outages that would require emergency power generation is
limited2 and the residual risk to the environment and sensitive receptors is low (particularly as
the UV disinfection and odour control units will remain operational through emergency generator
use). In addition, the capacity to cater for upset conditions is improved as a result of the plant
upgrade, in comparison to existing conditions.
2.6 Operational Parameters
2.6.1 Staffing Arrangements
The plant will have a rotating roster with three plant operators working ons ite during normal day-
time operating hours (0700 to 1700). Out of hours, a staff member will be on standby duty to
2 TasWater have obtained a Site Specific Reliability Analysis from TasNetworks to understand the power outage risk for the site and have taken that information into account in planning emergency power generation.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 26
attend the plant in the event of unforeseen circumstances, which will be communicated via SMS
from the STP computer controlled system.
Additional staff and contractors will be onsite during maintenance events scheduled throughout
the year, with variable numbers dependant on the event, but not expected to be greater than 25
at any one time.
2.6.2 Operating Hours
The plant process will be automated and operate on a continuous basis throughout the year,
24-hours a day. The site will be manned during operating hours five to six days a week, where
biosolids/screenings collection, system optimisation, maintenance and monitoring will be
undertaken. Outside of daily operating hours (0700 to 1700), the plant will run autonomously
unmanned, with an operator on standby who will be notified by the plant system if any
malfunctions occur.
2.6.3 Traffic and Transportation
The Project will require three full-time staff during operation, resulting in three cars moving to
and from the site each day. Cars and trucks (as needed) will access the site via Treatment Plant
Road, which services the site from Tinderbox Road.
Biosolid waste will be collected on a daily basis by truck, with a maximum of one removal event
expected to be required per day at full operating volume of 8.53 ML/day ADWF (expected to be
reached at the 2040 design horizon) and less in the intervening period. Collection of screening
and grit bins will occur less frequency, with at least one collection event per week expected.
During maintenance periods, a maximum of 25 vehicles are expected at any one time, resulting
in 50 movements in a day, potentially for up to a week, depending on the size of the
maintenance task.
Chemical delivery will occur on an as need basis, expected to be the vicinity of a maximum of
three trucks to and from the site per week.
The proposed traffic volumes during operation are not significantly different from current vehicle
movements for the existing plant.
2.6.4 Energy Use
The Project is estimated to have an energy consumption of 6500 kWh/day at the full operating
volume of 8.53 ML/day ADWF. This capacity can be met by existing infrastructure and power
supply.
2.6.5 Waste Streams
The main waste streams from the plant will be the collected screenings and grit from the primary
treatment area and the dewatered biosolids cake produced by the sludge treatment area. Other
waste streams will include general waste and minor chemical disposal as required.
Screenings and Grit Waste Stream
Front loading skip bins with a nominal 1.5 m3 capacity will be used to store screenings and grit
prior to removal from site. These bins are covered. Screening and grit collection rates vary from
catchment to catchment, and are also dependent on the type of screening and grit removal
installed. Collection rates are also greater during wet weather events.
Estimated collection rates are summarised as follows:
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 27
Screenings collected during primary processing will average 0.23 m3/day (0.9 m3/day @ 4 x
ADWF) in the first year of operation, with an average storage capacity of 6.6 days;
Screenings collected to a 2040 design flow will average 0.37 m3/day (1.47 m3/day @ 4 x
ADWF) with an average storage capacity of 4.1 days;
Grit collected during primary processing will average 0.05 m3/day (1.1 m3/day @ 6 x
ADWF) in the first year of operation, with an average storage capacity of 29 days; and
Grit collected to a 2040 design flow will average 0.12 m3/day (2.7 m3/day @ 6 x ADWF) in
the first year of operation, with an average storage capacity of 12 days.
Biosolids Cake Waste Stream
Biosolids cake will be stored in three odour-controlled self-loading bins (10m3), which will be
transferrable onto collection trucks. The bins have been sized appropriately in the design to hold
maximum loads at the 2040 design horizon.
Dewatered biosolids cake production is estimated to an average 5.1 t/day (6.3 t/day max) in the
first year the plant is running and grow incrementally to a 2040 peak of an average of 9.2 t/day
(11.5 t/day max), based on a biosolids cake solids concentration of 16%.
2.6.6 Chemical and Dangerous Goods Storage
Current Chemical Storage
The current STP sites houses a number of chemicals and fuels including:
Gaseous chlorine
Lubricating oils
Diesel for mower
Polyelectrolyte
These goods are stored in accordance with statutory regulations.
Proposed Chemical Storage
As part of the proposed STP upgrade the existing gaseous chlorine system will be
decommissioned and minor changes will be made to existing chemical storage on site, with the
following materials to be stored.
Small quantities of lubricating oils for various mechanical components.
Small quantities of diesel (max 250L) associated with the emergency for generators. Diesel
is classified as a Class 3 Dangerous Good under the Australian Dangerous Goods Code.
Small quantities of cleaning chemicals and descalents.
Polyelectrolyte (flocculent) – to be used in the biosolids dewatering process. The specific
type of polyelectrolyte (either liquid or powder form) will be selected during design and
commissioning. Liquid polyelectrolyte will be delivered in intermediate bulk containers
(IBCs) and powered form polyelectrolyte will be delivered in pallets of 20 kg bags.
Carbon substrate (liquid sugar solution) - Depending on the actual influent characteristics of
the sewage, and the operational performance of the IDEA-SBR process, it may be
necessary to store and dose a carbon substrate, such as liquid sugar solution. The storage
tank would be in the order of 5,000 L.
Nutrients for the Bio-trickling Filter - The nutrient requirements of the bio-trickling filter will
be dependent on the type of proprietary system, however it is likely that small amounts of a
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 28
specific nutrient solution will be required to be stored on site and dosed to the bio-trickling
filter module.
The liquid sugar solution will be stored within the bulk chemicals store marked on Figure 2-2,
immediately south of the inlet works. This chemical store will be secured, signed, roofed and
bunded in accordance with statutory requirements.
The other chemicals and fuels will be stored in very small volumes within a designed bunded
storage area in the Dewatering Building (Figure 2-2) including restricted access and appropriate
signage.
Possible Future Chemical Storage
The proposed plant design does not include targeted phosphorus removal and a commitment
has been made to ongoing ambient phosphorus monitoring and retrofit of phosphorus removal if
required in the future. In the event phosphorus removal is required additional chemicals will be
needed on site.
Magnesium hydroxide liquid (up to 30,000L tank) and Aluminium sulphate (up to 30,000L tank)
could be stored on site in the future if phosphorus removal was required. These chemicals are
both defined as Hazardous Substances under the Safe Work Australia classification but are not
considered Dangerous Goods under the Australian Dangerous Goods Code.
If required these chemicals would be stored in the roofed and bunded bulk chemical storage
facility south of the inlet works.
2.7 Pre-Construction and Construction
2.7.1 Construction Overview and Timing
At a high level the construction process involves site establishment, bulk earthworks,
construction of structures, installation of equipment, piping etc and commissioning of the new
STP elements. As the Blackmans Bay STP is an operating site (which will continue to operate
throughout the construction activities to facilitate ongoing wastewater treatment until the new
plant is fully functional) construction sequencing is planned accordingly and dovetails with the
commissioning process.
A number of existing assets will be retrofitted as part of the plant upgrade. This necessitates a
staged and linked approached to construction and commissioning. An important aspect to the
staging is that the construction and process commissioning of the new major structures (such as
the new IDEA-SBR tanks, inlet works and related ancillary items) will occur prior to the retrofit of
existing equipment. This results in a parallel schedule for many of the construction and
commissioning activities. Refer also to Section 2.8 which summarises how the process
commissioning will be undertaken to compliment the staged construct ion approach.
Overall the construction phase is expected to take approximately two years, followed by a
period of approximately six months commissioning (noting that some early commissioning
activities will be conducted during the two year construction period). The proposed two year
construction period does not involve constant ‘building works’ (e.g. earth works and building
construction) but rather reflects a staged approach to gradually bringing each piece of
equipment online in a staged manner aligned with the gradual decommissioning and retrofit of
existing assets. During the two year period there will be short periods of active construction (e.g.
bulk earth works, construction of roadways, erection of new buildings) interspersed with quieter
periods of equipment installation and commissioning.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 29
2.7.2 Construction Process and Staging
The stages described below are indicative and based on preliminary design work completed to
date. Specific details and sequencing may be modified through detailed design and
development of pre-construction and construction planning.
Stage 1 - Procurement
Following completion of the detailed engineering design, major equipment will be procured. This
includes mechanical equipment (e.g. screens, grit removal, aeration blowers, pumps, mixers,
dewatering centrifuge, etc), electrical equipment (e.g. switchgear, PLCs, instrumentation, etc),
building construction materials and other necessary items. The delivery times of these items will
constrain when mechanical installation of these components can commence.
Materials will be delivered to site and stored within the Construction Compound (refer Figure
2-1).
Stage 2 - Site Preparation
Once all necessary approvals are in place mobilisation, site establishment and construction
works will commence as follows:
Mobilisation and Site Establishment - Once the Construction Management Plan has
been approved, equipment will be brought to site and the site office and contact point will
be established (refer Figure 2-1).
Initial Site Works - Temporary boundary fencing and associated signage will be erected
and access points and sign-in procedures enacted. Vegetation clearance will be
undertaken (as delineated in Section 6.7). Sediment controls and water management
procedures for the construction phase will be installed.
Stage 3 - Major Construction and Initial Process Commissioning
This stage involves the construction of the major structures associated with the upgrade works ,
in particular the Primary and Secondary Treatment Areas. These areas involve the majority of
the bulk earthworks, which will be undertaken during this stage. Refer to the cut and fill areas
identified in Figure 2-2 for details.
The construction and initial commissioning of the following areas will occur concurrently and is
expected to take approximately 12 months.
Construction of the Primary Treatment Area - Activities include construction and
installation of inlet works and flow splitter, including drum screens, vortex grit chamber, and
associated valves, pipework, and electrical components. The odour treatment system will
also be installed at this time.
Secondary Treatment Area - Installation of IDEA-SBR tanks, as well as complete
electrical, mechanical and instrumentation and control equipment. This will include pumps,
aeration system, mixers, decant systems, WAS control valves.
Odour Control System - The existing odour control will be temporarily relocated in order to
allow for construction of the new odour control system, blowers and MCC building.
Blowers and MCC Building - Blowers to be installed and MCC building to be constructed,
including new transformer, switchboards, drives, junction boxes, control panels,
communication panels. The standby generator will also be installed in this area.
Pre-commissioning of New Liquid Stream - This involves commissioning of the new
installed assets and processes to ensure everything functions as intended, prior to
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 30
shutdown of existing processes to allow for additional minor construction work relating to
the retrofit of existing equipment. Refer to Section 2.8 or commissioning details.
Initial Process Commissioning of New Liquid Stream - This stage is the initial phase of
process commissioning where sludge from the bioreactor at the existing STP setup will be
transferred to IDEA-SBR tank 1 to act as a “seed” sludge. Operation of the new liquid
stream (inlet works and IDEA-SBR tanks) will enable a phased commissioning to
commence which enables certain existing equipment to be taken offline. Refer to Section
2.8 for details on the phased commissioning approach proposed.
Stage 4 - Additional Minor Construction, Retrofit and Integrated Commissioning
This stage involves additional minor construction work, largely associated with the Biosolids
Treatment Area, as well as existing equipment that requires works retrofit and repurpose of
existing assets. This stage involves staged commissioning, as described in Section 2.8.
The construction and commissioning of the following areas is expected to take approximately 12
months.
Retrofit existing secondary clarifier to an effluent balance tank - The necessary
modifications to convert the existing secondary clarifier to an effluent balance tank will be
made. Treated effluent will bypass the balance tank during this time. UV disinfection will
commence at this stage. Refer to Section 2.8 for related commissioning details.
Retrofit primary sedimentation tank to a gravity thickener, and existing bioreactor to
aerobic digester - The necessary modifications to convert the existing primary
sedimentation tank to a gravity thickener will be made. Refer to Section 2.8 for related
commissioning details, and how equipment is proposed to transition during this stage.
Biosolids dewatering - The new dewatering centrifuge and associated solids handling
infrastructure will be installed.
Administration Building - Installation of the permanent Control Room with the new PLC,
SCADA terminals. A shutdown is required to merge the temporary control system, with the
permanent control system located within the Administration Building.
Stage 5 - Site Reinstatement and Landscaping
At the completion of this stage the Construction Compound and associated fencing will be
removed, the Construction Compound area reinstated to its original conditions and the
Suncoast Headlands Track re-established in its final position.
Landscaping will be undertaken in accordance with the landscape plan in Appendix A and the
site will move from construction to commissioning phase.
2.7.3 Construction Compound
As illustrated on Figure 2-1 a Construction Compound will be established on western side of the
site. The Compound will be accessed via the existing gravel road (may require maintenance but
not proposed for widening) and will be the location for all materials storage, parking, site office,
stockpiling, waste storage etc. The Construction Compound will be fenced and signed as a
restricted access zone.
The existing Suncoast Headlands Track will be re-routed along the western side of the
Construction Compound during the construction period and subsequently reinstated to a new
alignment through the middle of the site post construction. The remainder of the site (outside the
fenced STP site and Construction Compound) will remain available for public access and
walking for the duration of the Project.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 31
2.7.4 Construction Traffic
During construction local traffic is expected to increase and will be composed of staff vehicles,
trucks, utes and vans delivering electrical and plumbing equipment. During peak periods in the
construction phase there will be approximately 6-12 trucks visiting the site each day and 20
trade vehicles and 20 cars or other vehicles.
Construction access to the site will be via Treatment Plant Road, Tinderbox Road and then via
either Algona Road or Rolsyn Avenue before hitting the major Highways (Southern Outlet,
Channel Highway, Huon Highway) depending on the direction of travel.
Bulk construction materials including concrete and gravel will be sourced locally, likely travelling
to site from Hobart and the Huon respectively.
Traffic management during construction is addressed in Section 6.20.
2.7.5 Construction Hours
Working hours for construction involving heavy machinery will be restricted to 7am to 6pm
Monday to Saturday. Minor electrical or activities which do not generate noise or dust may occur
outside of these times (but within the hours of 6am to 9pm Monday to Saturday).
2.7.6 Construction Machinery and Equipment
Machinery and equipment used during construction is likely to include:
Mobile cranes (20 T through to 100 T possibly)
Concrete pump
20 T dump truck
30 T excavators
15 T Roller
4.2m Blade Grader
All equipment will be stored (when not in use) either within the STP footprint or within the
Construction Compound. There will be no stockpiling, machinery storage or other activities
outside of the identified STP fenced area and Construction Compound.
There will not be any concrete batching plant or rock crusher on the site.
With respect to bulk materials the construction work will require deliveries of gravel and
concrete, which are to be sourced from local providers. Concrete is expected to be sourced
from suppliers in Hobart and gravel from local quarries within the Kingborough and Huon Valley
municipalities. The project design relies predominately on cut rather than fill so there are no bulk
supplies of fill material required. The fill resulting from the cut on site will be removed to a
suitably licenced facility (by a licenced transporter) with any topsoil retained on site and
stockpiled within the Construction Compound or fenced STP site for subsequent rehabilitation.
Minor quantities of fuels and chemicals may be stored on site during construction including:
Fuels, oils and lubricants
Paints and solvents (several hundred litres)
Cement and bitumen materials; and
Small quantities of disinfectants and cleaning chemicals.
These materials will be housed in a roofed and bunded facility within the construction compound
(refer Section 6.6 for management of hazardous substances).
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 32
2.8 Commissioning
2.8.1 Commissioning Planning
Commissioning activities will be carefully planned to ensure a smooth and effective transition
from operation of the current STP to the upgraded STP. A step-by-step approach of the
commissioning activities is provided below, describing a phased approach to minimise
disruption to current operations and to improve quality of treated effluent during commissioning
compared with current operations. The phases described below are indicative and based on
preliminary design work completed to date. Specific details and sequencing may be modified
through detailed design and development of specific commissioning plans and procedures.
The commissioning process outlined below is expected to take approximately 6 months after the
completion of the construction period; noting however that some early commissioning activities
will be undertaken concurrently with the final phases of construction. The result is a 2.5-year
program, with approximately 2 years for construction (includes early phase commissioning)
followed by 6 months of active commissioning.
2.8.2 Commissioning Phases
Phase 1 - Pre-commissioning
This phase will include area-specific handover from the construction to the commissioning
teams. This includes initial checks on completeness of equipment installation and testing
required prior to commissioning. Following this, pre-commissioning tests will be undertaken on
all equipment associated with each functional area of the plant through comprehensive
inspection and test plans (ITPs).
Phase 2 - Wet commissioning
Following pre-commissioning sign-off, wet commissioning shall commence. This stage involves
the testing of all equipment using potable/recycled “clean” water. Typically, the following tasks
will be undertaken:
Pump system capacity testing;
Equipment noise emission testing;
Leak and level testing of diffusers, aeration capacity testing;
Odour control testing, including capture rate, duct air flow balancing and fan capacity
testing;
Testing of hydraulics and control valves throughout system;
Tuning of control loops throughout the STP; and
Simulation of full operational conditions.
Following wet commissioning of an item, it will be left in operation with recirculating temporary
clean water until it can be connected to the new system. This allows the equipment to be tested
for an extended period of time.
During both Phases 1 and 2, the sewage will be treated by the existing STP as per current
operation.
Phase 3a - Process Commission (Liquid Stream with IDEA-SBR 1)
During this initial phase of process commissioning, sludge from the bioreactor at the existing
STP setup will be transferred to IDEA-SBR tank 1 to act as a ‘seed’ sludge.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 33
Once the desired solids concentration in the IDEA-SBR tank is reached, influent from the
existing STP, will be diverted through the new inlet works into IDEA-SBR tank 1, slowly draining
the old bioreactor until empty. The decant from the IDEA-SBR tanks will be diverted directly to
the new UV disinfection system, bypassing the secondary clarifier at this point (still in
construction at this stage). Chlorination at the plant will now be suspended.
Once the mixed liquor concentration in IDEA-SBR tank 1 reaches design levels after
approximately 3-5 weeks, waste sludge will be transferred to IDEA-SBR tank 2 to temporarily
aerobically digest the waste activated sludge (WAS) stream. Dewatering can occur via the new
centrifuge if required.
This process will continue for a further 5-6 weeks without WAS discharge as SBR tank 2
reaches the design level.
The new odour control system will be switched on at this stage.
It is during this time that modifications can be made to existing infrastructure that will be utilised
as part of the upgraded STP. This includes conversion of the primary sedimentation tank to the
WAS gravity thickener, modification of the existing bioreactor to an aerobic digester, and
modification of the existing secondary clarifier to the new balance tank.
Phase 3b - Process Commission Balance Tank
Following modification of the existing secondary clarifier to the new balance tank, flows will be
diverted to the balance tank to attenuate the flow to the UV disinfection units.
Phase 3c - Process Commission Solids Stream
Following completion of the conversion of the existing primary sedimentation tank to the new
gravity thicker and the conversion of the existing bioreactor to the new aerobic digester, the new
units will be process commissioned by receival of the WAS; simultaneously, IDEA-SBR tank 2
will be converted from the primary aerobic digester to its design function as a secondary
treatment process tank.
Following transition into the new sludge treatment system, normal sewage flow will be
transferred to IDEA-SBR tank 2 and plant operation will now be in its fully upgraded form.
The whole process of Phase 3 will take in the vicinity of 3 months to complete.
Phase 4 - Redundant Equipment Decommissioning
The anaerobic digester will be decommissioned during the process commissioning phase with
careful removal of the existing sludge in the four tanks. Several safety procedures will be
carefully followed in the decommissioning phase of the digester as gases pose a safety risk until
all existing sludge is removed. Once the sludge is removed, it will be carted to an appropriate
disposal facility.
Decommissioning of the existing MCC facilities will also be undertaken, as the new controls are
installed.
Phase 5 - Performance Testing
Phase 5 includes the testing of the newly upgraded plant for performance with respect to the
design intent. There will be five groups of performance tests undertaken in order to evaluate the
performance of the new STP against the Project’s requirements.
1. Initial 30 Day system integrity testing
2. Summer period performance tests
3. Winter period performance tests
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 34
4. Peak wet weather flow tests
5. Power and consumables test
The initial 30-day system integrity testing will occur at the completion of the commissioning
phase, once the quality of treated effluent and operation of the plant equipment is acceptable.
The results of this performance test will largely confirm whether commissioning has been
successfully completed.
Various aspects of the plant will be monitored to ensure compliance with acceptance testing
criteria. These will include items such as:
Treated effluent quality (e.g. TSS, COD, BOD, TP, TN, Ammonia, pH, alkalinity,
Thermotolerant Coliforms)
Thickened biosolids concentration
Stabilisation of dewatered biosolids
H2S removal in odour control unit
During this time the overall functionality of the integrated STP control system will also be t ested,
including the automatic start sequence of the emergency power generator, and the emergency
shutdown and restart functionality of the STP controls.
2.8.3 Treated Effluent Management During Commissioning
During the commissioning phase outflowing effluent will be tested regularly and continuous
online measurements will be used as appropriate (refer proof of performance testing in the
previous Section).
Treated effluent quality will be maintained as per the current STP emission limits during the six
month commissioning phase. If emission limits (based on the current plant limits) are not being
met corrective action will be undertaken within the plant (including operational changes,
temporary storage or retreatment).
At the end of the 6-month commissioning period treated effluent will meet the newly proposed
emission limits as documented in Section 2.4.3.
2.8.4 Complaints During Commissioning
An online complaints register will be available at all times during commissioning (and
construction) and will be checked daily, with complaints dealt with as soon as possible.
2.9 Off-Site Infrastructure
The site is already serviced by road access (via Treatment Plant Road), power (overhead lines
from the west of the site to the centre of the existing STP), telecommunications and water
supply (enters via the south west of the site to the existing STP).
Minor onsite upgrades to some of these features will be required, including minor maintenance
(no widening) to Treatment Plant Road and the access track to the existing house on site as
well as a new substation within the STP site itself.
The Blackmans Bay STP is being sized for the future design horizon for both the local
catchment as well as the existing Margate, Electrona and Howden STP catchments to allow for
future decommissioning of those other plants. The pipelines required to transport effluent from
those other STPs to the upgraded Blackmans Bay STP do not form part of this application
however; nor is this application contingent on their construction. As such those pipelines are not
considered as part of this application.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 35
There are no other proposed changes to any off site infrastructure required to facilitate the
development.
2.10 Land Tenure and Public Site Access
The existing Blackmans Bay STP is situated on land owned by TasWater and not currently
accessible to the public. The existing site however is surrounded on all sides by land owned by
Kingborough Council and currently available for public recreational use, predominately for
walking and dog exercise.
This proposal will involve the purchase of the land title surrounding the existing STP site from
Kingborough Council to allow for expansion of the STP footprint (the combination of the existing
STP site and the surrounding Council land parcel will form The Site/The Land). Figure 2-3
shows the current land tenure and the proposed parcel to be purchased (the Project Site)
TasWater recognises the current public usage of that parcel of land and will ensure ongoing
public access to the broader site for walking and other recreational activities. In particular, the
Suncoast Headlands Track traverses the site from north to south and this track will be realigned
and retained as part of the works. Access to the track will be maintained during both
construction and operational phases.
During the construction phase temporary fencing will be erected around the construction site
and a new section of the Suncoast Headlands Track established along the western edge of the
property boundary to allow continued access across the site from north/south. Once the
construction phase is completed the temporary fencing will be removed and only the main STP
site itself will be permanently fenced, allowing ongoing recreational access to the remainder of
the site as currently occurs. The Suncoast Headlands Track will be reinstated with only a minor
deviation of its current route.
The construction compound itself will be fully rehabilitated post construction to reinstate the
existing natural and ecological values of the site. A new vegetation screen will be planted along
the western boundary of the new STP to provide screening for nearby residents and users of
the recreational space and Suncoast Headlands Track.
Figure 2-6 illustrates the Suncoast Headlands Track and the construction phase and final
fencing proposal.
Const
ruction
Acces
s Roa
dTreatment Plant Road
Temp
orary
SCH T
rack (
durin
g con
struc
tion)
Realig
ned S
CH Tr
ack (
post
cons
tructio
n)
Suncoast Headland Track
Suncoast Drive
Suncoast Headland Track
Suncoast Drive
Tinderbox Road
Liberty Court
Wells Parade
Tahun
e Cres
cent
Ephesus Place
Jodie Court
Syracuse Place
Suncoast Drive
Tinde
rbox R
oad
Liberty Court
Tahune Crescent
Wells Parade
Tahun
e Cres
cent
Tahune Crescent
Ephesus Place
Jodie Court
Syracuse Place
526,400
526,400
526,600
526,600
526,800
526,800
5,237,
200
5,237,
200
5,237,
400
5,237,
400
5,237,
600
5,237,
600
G:\32\18107\GIS\Maps\MXD\3218107_004_Figure2-7_PublicAccess_RevB.mxd
0 50 10025
MetresMap Projection: Transverse Mercator
Horizontal Datum: GDA 1994Grid: GDA 1994 MGA Zone 55
© 2016. Whilst every care has been taken to prepare this map, GHD (and DATA CUSTODIAN) make no representations or warranties about its accuracy, reliability, completeness or suitability for any particular purpose and cannot accept liability and responsibility of any kind (whether in contract, tort or otherwise) for any expenses, losses, damages and/or costs (including indirect or consequential damage) which are or may be incurred by any party as a result of the map being inaccurate, incomplete or unsuitable in any way and for any reason.
Tasmanian Water CorporationBlackmans Bay STP DPEMP
Job NumberRevision B
32-18107
01 Aug 2016
Public AccessDate
Data source: DPIPWE (cadastre, imagery, land tenure, land zoning, waterways, contours), TasWater (proposed infrastructure). Created by: jtoregan
2 Salamanca Square Hobart TAS 7000 Australia T 61 3 6210 0600 F 61 3 6210 0601 E [email protected] W www.ghd.com.au
Paper Size A3
LEGENDWaterwayCadastral ParcelDog excersize area
ProposedThe project siteFenced area (STP operational boundary)Construction Compound(site office, parking, machinery, laydown,stockpiles and bunded fuel and chemicalstorage)
Figure 2-6
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 37
3. Project Alternatives
3.1 Project Rationale
The rationale behind the Project is outlined in Section 2.3 and at its core is driven by a need to
improve performance of the current STP and cater for projected increases in flow from the area
currently serviced (Kingston, Huntingfield, Blackmans Bay and southern Bonnet Hill) heading
into the next 20-30 years. A very closely linked objective of the Project is to provide the potential
to rationalise the broader STP network of aging infrastructure by providing sufficient capacity in
the upgraded Blackmans Bay STP to cater for projected future flows from the Margate,
Electrona and Howden STPs in order to allow them to be decommissioned in the future.
Details are provided in Section 2.3 of the capacity and deficiencies of these STPs and the
rational for the potential amalgamation.
As noted previously this DPEMP relates only to the Blackmans Bay STP Upgrade and does not
include the decommissioning of the other plants mentioned for potential amalgamation or the
infrastructure required to transfer the sewage catchments from these areas to the Project
Footprint. The Project is not dependent on the amalgamation going ahead, but the plant has
been designed to cater for that eventuality as part of TasWater’s forward planning process.
3.2 Alternative STP Sites
In investigating the amalgamation of STPs in the Kingborough Local Government Area (LGA),
consideration was given to upgrades at any of the existing STP sites as well as the possibility of
a new STP site to which all local effluent could be directed.
The key document investigating these options is the Kingborough Wastewater Management
Strategy, Long Term Strategy (CEE, 2007). This document considers limitations of the existing
STPs (particularly aging infrastructure, STPs at or reaching capacity and existing issues wit h
treatment compliance), the regional context of the existing STPs, the opportunities for reuse
(outlined in Section 3.3), and a risk assessment and investigation of a preferred site for upgrade
and amalgamation. This study considered the regional STPs more broadly (including Taroona
and Woodbridge) but provided focused analysis specifically of the STPs currently proposed for
amalgamation (namely Blackmans Bay, Electrona, Margate and Howden).
The amalgamation of some or all of Blackmans Bay, Margate, Electrona and Howden STPs was
considered in detail by the report; including identification of alternative treatment sites and a
triple bottom line assessment. Alternative sites for amalgamation that were considered included
Margate, Electrona, Howden Road, Barretta Landfill, Brookfield Estate, Electrona Industrial
Zone and Conningham. These options were reviewed and subsequently shortlisted to the four
most suitable sites - Blackmans Bay, Brookfield, Baretta and Conningham. The two existing
sites, Margate and Electrona were discounted due to size limitations and proximity to existing
sensitive uses (e.g. Dru Point Recreation Area) making them unsuitable for expansion to treat
an amalgamated network.
Details of the reuse assessment for these amalgamated flows is available in CEE 2007. The
conclusion of these 2007 investigations was that the most suitable option for combined flows
(Blackmans Bay, Margate and Electrona) when considering economic, environmental and social
factors was a new STP and reuse opportunity at the Brookfield site, followed closely by the
option of upgrading the existing Blackmans Bay STP to take combined flows from the other
existing plants in North West Bay.
The Kingborough Council made a considerable effort to acquire the Brookfield site following the
investigations but was not successful, thereby ruling out this option. Thus the decision was
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 38
made to transfer wastes from Margate, Electrona and Howden to the Blackmans Bay plant.
Without the Brookfield site, there is no practical alternative to the continued operation of the
Blackmans Bay STP, as confirmed in a re-assessment of options by Southern Water in 2010.
In summary the culmination of the 2007 study, Kingborough Council’s unsuccessful efforts to
secure the Brookfield property and subsequent assessments undertaken by TasWater
(Southern Water) was that the preferred option would be as proposed – to decommission the
Margate, Electrona and Howden STPs and divert combined flows to an upgraded Blackmans
Bay STP3. The key factors influencing the outcome were:
The existing STPs are at or nearing capacity, as well as experiencing issues with treated
effluent compliance which results in the need to upgrade and expand existing treatment
capacity in the area;
North West Bay is a small and sensitive water body in comparison to the Derwent Estuary
and there is a clearly defined long term objective to remove STP discharges into North
West Bay and redirect those discharges to the Derwent Estuary;
Of the alternative sites assessed (including both existing STPs and greenfield sites) the two
most suitable options were identified to be Brookfield Estate and Blackmans Bay STP;
The new Brookfield Estate STP and associated reuse opportunity was assessed as
requiring more capital investment than Blackmans Bay, but resulted in better social and
environmental outcomes. However, despite considerable effort, the property was not able
to be obtained and therefore the option ruled out; and
The Blackmans Bay site provides suitable size and capacity for upgrade and has an
existing long outfall into the comparatively high energy Derwent Estuary (as compared to
North West Bay) and was therefore assessed overall as being the most suitable option.
3.3 Reuse Investigations
3.3.1 Detailed Reuse Analysis - 2007
As part of the Kingborough Wastewater Management Strategy, Long Term Strategy (CEE,
2007), consideration was also given to reuse opportunities for treated effluent across the
Kingborough municipality for predicted wastewater flows in the years 2015 and 2030.
The 2007 investigation considered reuse flows from all STPs in the Kingborough municipality,
which includes Taroona (now decommissioned) and Woodbridge which are currently not
included in the proposed amalgamation to Blackmans Bay. However, the 2007 study is still
considered a valid information source for the current proposal as (at that time) Blackmans Bay,
Electrona, Margate and Howden STPs made up 90% of flows, with the other plants (Taroona
and Woodbridge) contributing only 10% to the total.
The specific effluent reuse options considered in the development of the sewerage strategy
were:
North Bruny Island, including the Murrayville pastoral reserve located on the east coast
near Barnes Bay, of which about 600 ha is considered suitable for irrigation.
Brookfield (Margate), about 140 ha suitable for irrigation.
3 The decommissioning of Margate, Electrona and Howden and subsequent amalgamation and transfer of their flows to the upgraded Blackmans Bay STP does NOT form part of this application, nor is this application dependant on them. The key reason for inclusion of the broader amalgamation strategy in this DPEMP is to provide context of the chosen sizing and design of the Blackmans Bay STP in order to allow for the potential amalgamation.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 39
Golf Courses and Parks, including:
– North West Bay Golf Course~ 25 ha;
– Kingston Beach golf course
– Parks and ovals in Kingston, Blackmans Bay and Taroona; and
– Dru Point recreation reserve.
The reuse investigation in 2007 (CEE, 2007) involved a water balance for a range of future flow
scenarios and climatic conditions (including the 1 in 10 wet year). The data was used to
consider a number of reuse scenarios, namely:
Full reuse (1 in 10 wet year case) involving large storage of effluent over winter due to
limited capacity for winter irrigation;
Reuse in years of low and average rainfall with a small discharge of effluent in wet years to
avoid carry-over of effluent from one year to the next; and
Partial reuse, consisting of reuse in summer months only with excess effluent to be
discharged via outfall.
This assessment concluded that full effluent reuse is not considered feasible as there is not
sufficient land area available in the region. Similar results were found for the option of full reuse
in dry years and discharge of treated effluent to the environment in wet years; namely
insufficient land availability.
Partial reuse was then investigated further for Bruny Island, Brookfield Estate and other local
opportunities around Margate. A triple bottom line assessment was undertaken for the identified
options.
Reuse of effluent in the summer months on Bruny Island could take approximately 52 % of the
total effluent, but has a very high total capital cost4 of $64 M (for a partial reuse scheme on
Bruny Island) and is not considered viable without external funding. This option also has
substantial social and environmental risks and resulted in a negative overall outcome on the
triple bottom line assessment.
The next largest reuse opportunity identified was Brookfield Estate. This option was further
investigated and found to be able to accommodate only a small proportion (8%) of the total
projected treated effluent volume at a 2030 horizon.
Irrigation on smaller ovals and golf course was found to accommodate only 4% of projected
(2030) treated effluent volumes; resulting in an expensive option for a very small proportion of
effluent.
The resulting outcome of the partial reuse investigations was that the combined issues of land
availability (as noted previously Kingborough Council were unsuccessful in attempts to acquire
Brookfield Estate), social, environmental factors and high capital costs deemed partial reuse
unfeasible.
Other options including industrial reuse, groundwater recharge, river replenishment and direct
provision of treated effluent to households were considered by the 2007 report and discounted
as unfeasible for the Kingborough LGA.
4 Total Capital Costs includes capitalised annual costs at 7%. Numbers are taken from the 2007 reuse investigations (CEE) and therefore are somewhat outdated.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 40
3.3.2 Consideration of New Reuse Opportunities
TasWater has recently (2016) undertaken an internal review of reuse opportunities identified in
the intervening years between the 2007 study and this application. The only new reuse
opportunity identified by TasWater during the period since 2007 is the Arm End Golf Course.
TasWater were approach by the developers of the Arm End Golf Course (across the Derwent
from Blackmans Bay on the tip of the South Arm) to explore opportunities for irrigation water
supply to their development. Initially, consideration was given to provision of treated effluent
from the Rokeby STP; however, this water is fully allocated to current customers in the Coal
River Valley and a supply line would have had to cross the ecologically significant Ralphs Bay.
Subsequently investigations were made into provision of treated effluent from Blackmans Bay
via an undersea pipeline across the Derwent River. The total volume of effluent that the golf
course would require is estimated at 1 ML/day during the summer period and less at other times
of the year. There are minimal additional opportunities for reuse identified at South Arm that
would make it viable for TasWater to fund this reuse project. Given the small proportion of
treated effluent required by the development, the high capital and environmental costs of a
pipeline across the Derwent and the lack of other significant reuse opportunities at South Arm it
is not considered to be economically viable for TasWater to fund a reuse pipeline to the Arm
End Golf Course at this time.
If the golf course development were to proceed and the developer were to fund the reuse
pipeline across the Derwent, there remains opportunity in the future to install the necessary
infrastructure at Blackmans Bay STP to facilitate offtake of treated effluent for reuse.
TasWater will continue discussions with the developer for the Arm End Golf Course and
facilitate future offtake of treated effluent if required as a separate project to the current Project.
3.3.3 Summary
From the 2007 investigation and subsequent considerations, TasWater has determined that full
or partial reuse of treated effluent is not a viable and feasible option for the Project at this time
and therefore will not be committing to a reuse scheme.
However, the proposed Project does not preclude future reuse opportunities and the
improvements in treated effluent discharge quality significantly increases the opportunity for
future reuse in the region. TasWater will continue to investigate opportunities for reuse in the
future.
3.4 Layout at the Blackmans Bay STP Site
Within the Project Site itself the upgraded STP is inherently linked to the existing STP by its
design and therefore must be constructed within and adjacent to the existing plant. This limits
the opportunities for alternative site consideration within the identified Project Site.
The proposed layout (Project Footprint) involves locating the main IDEA-SBRs in an area of
considerable ‘cut’ and as far as possible down the hill towards the existing plant. This serves to
limit visual intrusion and keep the Project as far as practical from the existing residential
properties. The proposed Project Footprint also aims to minimise impacts to native vegetation
and mature eucalypts by siting as much as possible on already cleared land.
The construction compound has been sighted to minimise impacts to native vegetation, utilise
existing infrastructure (access track and house for a site office) and respond to limitations of
terrain. Similarly, site fencing has been modified in response to ecological investigations and
current usage of the existing walking track on site to minimise impacts where possible. The
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 41
proposed vegetation screening has been designed to provide a visual buffer to existing
residents as well as recreational users of the broader site.
3.5 Alternative Treatment Plant Technology
Two sewage treatment processes were considered for the upgrade of the Blackmans Bay STP
A Membrane Bioreactor (MBR) and a Sequenced Batch Reactor (SBR). The primary difference
between these processes is that the SBR achieves solids removal by sedimentation (within a
bioreactor) while the MBR achieves solids removal through membrane filtration. It should be
noted that numerous bioreactor configurations can be applied to an MBR, and this selection
depends on the specific design requirements and the treatment objectives.
Through the preliminary design phase, further analysis was undertaken to determine the
appropriate treatment process for the upgrade.
Both MBR and SBR processes were deemed to be capable of achieving the proposed effluent
quality requirements outlined in Section 2.4.3. Both processes were also deemed to produce
comparable odour emissions and allow for appropriate odour management options. Ultimately,
an SBR process was selected based on cost, operability, process robustness and management
of wet weather flows. An analysis of the positive and negative factors for each process type is
summarised in Table 3-1.
Table 3-1 STP Process Selection Criteria
Criteria Membrane Bioreactor (MBR) Sequenced Batch Reactor
(SBR)
Operability × Large number of control loops,
pumps and actuated valves.
× Substantial chemical
use/handling for membrane
cleaning (e.g. citric acid, sodium
hypochlorite)
Additional disinfection only
required for bypass flows
(disinfection provided by
membranes)
Fewer mechanical items,
fewer control loops and
operationally simple
Minimal chemical
requirements
Maintainability × Extensive additional mechanical
equipment (i.e. permeate pumps,
air scour blowers, chemical
cleaning systems). Membrane
renewal and aeration diffusers
required every 7-10 years.
Few mechanical items
(i.e. RAS pumps, mixers,
decanters). Renewal of
aeration diffusers only.
Other additional
equipment
requirements
× Additional finer screening (1-
2mm) required to protect
membranes
× Additional disinfection
required
Effluent quality MBR provides superior effluent
quality in terms of suspended solids
and thermotolerant coliforms
×Class A+ reuse quality water not
utilised by local reuse opportunities
SBR technology can meet
the proposed effluent quality
requirements
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 42
Criteria Membrane Bioreactor (MBR) Sequenced Batch Reactor
(SBR)
Footprint Compact bioreactor footprint × Larger bioreactor footprint
Treatment of wet
weather flows
× Need for either large-offline
storage or high membrane
throughput (4xADWF) to treat wet
weather flows
× Odour management
risks/requirements introduced when
storing sewage during wet weather
Cost effective treatment
of wet weather flows by
adopting shortened treatment
cycles
Potential for
malfunctions and
breakdowns
× Potential for membrane fouling
and flux issues
(Significant flux rate reductions
could lead to bypasses during dry
weather. The mitigation against this
would be continual monitoring of
membrane flux, and implementation
of required chemical recovery
cleaning)
× decanter malfunctions can
lead to suspended solids
carryover to downstream
balance tank
(A decanter malfunction
could lead to solids carryover
during dry weather.
Mitigation measures against
this is to provide two
decanters per tank, and also
capture carried over solids in
the downstream balance tank
(the existing secondary
clarifier)
Energy consumption
(OPEX)
× Higher, due to membrane air
scour requirements
Ability to optimise
treatment cycles in dry
weather
Chemical consumption
(OPEX)
× On-going cleaning chemical costs
(e.g. Citric Acid, Sodium
Hypochlorite)
Fewer chemical
requirements
Membrane
replacement (OPEX)
× Membrane renewal required
every 7-10 years.
No renewals on solids
separation equipment
Capital cost × MBR typically ~10-20% more
expensive than an SBR
Less expensive than
MBR
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 43
4. Public Consultation
This section provides an overview of TasWater’s commitment to stakeholder and community
engagement implemented to date for the Kingborough Sewage Upgrade Project of which the
upgrade to the Blackmans Bay STP is a component.
Consultation on the Blackmans Bay STP began over a decade ago by the then asset owner,
Kingborough Council, in 2006. This consultation related to the proposed outfall extension but
also considered future expansions of the site. In the intervening years Kingborough Council,
Southern Water and now TasWater has undertaken range of stakeholder and community
engagement activities on various aspects of the overall Kingborough Sewage Upgrade Project.
4.1 Stakeholder and Community Engagement Plan
At commencement of the Project, a Stakeholder and Community Engagement Plan (the Plan)
was developed to guide consultation activities for the Project. The Plan was developed in line
with TasWater’s commitment to early and thorough consultation with the community to establish
a relationship and create awareness of, and involvement in, the project during the decision
making process. It’s important to note that the Plan and included activities are for both the STP
and the associated infrastructure (pipeline route, potential STPs and subsequent
decommissioning of STPs) which do not form part of this application.
The Plan directed activities such as:
Developing key Project messages and Q&As
Drafting and distributing Project newsletters to the community and stakeholders
Establishing and maintaining a Project webpage, including feedback channels such as a
contact person, contact email address, phone number and postal address
Establishing and managing a database of project stakeholders
Drafting and distributing letters to the community and stakeholders
Conducting one-to-one and small group meetings with landowners, stakeholders and
interested members of the community
Conducting community information sessions to provide Project information
Issues regarding the STP upgrade were raised and discussed with stakeholders during the
preliminary design stage so that the community could provide feedback on the proposal and
raise concerns over potential issues during construction.
4.2 Key Stakeholders Engaged
The key parties actively engaged through the consultation process to date include:
Kingborough community
Blackmans Bay residents
Property owners and adjacent neighbours to STP
Kingborough Council – in particular General Manager, Mayor and Councillors
Tasmanian EPA
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 44
4.3 Key Engagement Tools
During the course of the Project’s development a number of community engagement tools have
been employed including:
Community information sessions (a total of four have been held during 2015 and 2016,
each spanning three to four days at local community venues);
Stakeholder meetings (with community groups, local residents, individuals and agencies);
Community survey (undertaken in 2013);
Website and online feedback form;
Emails to subscribed community members (approx. 200);
Newsletters and letters to local residents;
Feedback forms;
Phone calls from the community; and
Stakeholder Workshop – in 2016 TasWater engaged Solutions2 to assist with developing
and implementing a workshop for those in the community with a close interest in the
pipeline routes from Margate, Electrona and Howden STPs to the Blackmans Bay STP as
part of the proposed amalgamation.
4.4 Summary of Feedback Received
Much of the consultation to date has been about the overall Kingborough Sewage Upgrade
Project and therefore relates to a range of issues outside of the boundaries of this application.
Of particular relevance to the Blackmans Bay STP site the following themes have been
identified:
General support for improvements in treatment technology resulting in improved discharge;
Odour, and to a lesser extent noise, are local issues of concern to residents within close
proximity to the plant;
Local residents have expressed concerns over visual intrusion of the plant;
Ecological impacts of the discharge have also been raised but to a lesser degree than other
issues; and
Some participants raised questions on STPs system redundancy and planning for future
sewage loads.
These issues have been considered as part of the design process with efforts made to minimise
visual intrusion (plant placement and extent of proposed ‘cut’), reduce odour and noise effects,
minimise ecological impacts on land and at the outfall and ensure the plant is designed to cater
for future flows and to sustain upset conditions.
These matters are discussed in more detail throughout this DPEMP.
4.5 Future Consultation
TasWater is committed to ongoing stakeholder and community engagement . This includes
consultation prior to the DPEMP submission, through the DPEMP advertisement period and
beyond. TasWater will continue to implement the Stakeholder and Community Engagement
Plan and employ the well-established tools (newsletters, letters, meetings, information sessions
and website) through the project planning, construction and commissioning stages.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 45
5. Existing Environment
The Blackmans Bay upgraded STP is located at the site of the existing STP on the margins of
the Blackmans Bay township in southern Tasmania.
The following sections provide an overview of the planning, environmental and social-economic
conditions of the site and immediate surrounds. An assessment of the potential impact of the
Project on these value is provided under the relevant subheadings in Section 6.
5.1 Planning Aspects and Land Tenure
5.1.1 Development Site
The development site encompasses the existing Blackmans Bay STP and an expansion area
immediately to the west (between the existing plant and original caretaker’s cottage). A map of
the development site and the proposed development and associated infrastructure is identified
in Figure 2-1 and Figure 2-2.
5.1.2 Site History
The existing sewage treatment site was developed by Council in the 1980s. A description of the
existing infrastructure on site is detailed in Section 2 of this DPEMP.
The adjoining Council land, to be acquired for the proposed upgrade works, essentially
comprising a buffer around the existing plant to the adjoining residential areas. It is used for
recreational purposes including walk ing tracks and includes the former treatment plant’s
caretaker’s cottage.
The caretaker’s cottage ceased use in 1988, when the plant supervisor vacated the premises.
Council then sought to occupy the property with a Council employee for security purposes. It is
understood that Council has also rented the property privately (it is assumed after Council
ceased responsibility for the STP). The cottage is currently vacant.
As a sewage treatment plant the site is identified as a potentially contaminated site. See
assessment against the Kingborough Planning Scheme 2015 (in Section 6.11) Potentially
Contaminated Code below and Section 6.5.
5.1.3 Proximity to Sensitive Uses
The site is located within 500 metres of the Blackmans Bay urban and fringe urban areas (see
Figure 5-2).
The former caretaker’s cottage is located 90 m from the boundary of the existing plant. This will
be used as the site office during construction, and will not be used for residential use post
construction. The next nearest residences on Suncoast Drive are located approximately 170m
from the boundary with the existing treatment plant. There are also three properties located on
Tinderbox Road, which are located approximately 200-250m from the existing treatment plant
boundary fence.
There is an existing walking track (Suncoast Headlands Track) to the northwest of the existing
sewage treatment plant; this is part of a network of trails along the foreshore and to the
adjoining dog exercise area to the south.
The existing STP is subject to a 300m attenuation area under the Interim Scheme, the objective
of which is to protect the site from encroachment from sensitive use (refer Section 6.11). There
are already existing residences within the attenuation area to the north and the west.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 46
5.1.4 Land Titles
The land tenure and title details affected by the proposed works are summarised in Table 5-1
and the current property boundaries in Figure 5-1.
The boundaries relative to the proposed works are illustrated in Figure 2-1.
A copy of these two titles is provided as an attachment.
Table 5-1 Land Title Details - Development Site
Address Title Reference
(Folio/Reference) Area Owner Extent of Works
116 Tinderbox
Road,
Blackmans Bay
157728/1 1.59ha Tasmanian
Water and
Sewerage
Corporation Pty
Ltd
Upgrade works
114 Tinderbox
Road,
Blackmans Bay
157728/2 9.704ha Kingborough
Council
Expansion of
existing plant
onto part of site
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 47
Figure 5-1 Title Plans
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 48
5.1.5 Easements
The development site is affected by the following rights of way and service and drainage
easements which are shown on the title plan and Figure 5-1.
The existing treatment plant (known as lot 1) is together with a:
– Right of Carriage Way and Service Right over the Right of Way (Private) and Service
Easement 12m over the adjoining Council land (known as Lot 2).
– Right of Drainage over the Drainage Easement 12m wide over Lot 2
– Right of Carriageway and Service Right (appurtenant to Lot 1) over the Right of Way
“A” (Private) and Service Easement 6m
– Right of Carriageway and Service Right over the Right of Way “B” (Private) and
Service Easement 6m wide over Lot 3
The adjoining Council land (known as Lot 2) is together with:
– Right of Carriageway and Service Right over the Right of Way “A” (Private) and
Service Easement 6m wide over Lot 3;
– Right of Carriageway and Service Right over the Right of Way “B” (Private) and
Service Easement 6m wide over Lot 3
The adjoining Council land (known as Lot 2) is subject to:
– Right of Carriageway and Service Right (appurtenant to Lot 1) over the Right of Way
(Private) and Service Easement 12m;
– Right of Drainage (appurtenant to Lot 1) over the Drainage Easement 12m
A copy of the relevant schedule of easements is attached.
5.1.6 Land Use Zoning
The existing sewage treatment plant is zoned Utilities. The adjoining Council land to be
acquired for the upgrade works is zoned Environmental Living.
The surrounding area is zoned Residential, Environmental Living, Environmental Management,
and Recreation, which reflects the existing uses of residential, recreational (dog park and trails)
and environmental (foreshore areas, geoheritage features, and trails) that surround the site.
The land zoning of the site and surrounding area is illustrated in Figure 5-2 and summarised in
Table 5-2.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 49
Table 5-2 Land Use Zoning – Location & Description
Location Zoning Description
Development Site
Existing Treatment Plant Utilities TasWater
Adjoining Council Land Environmental Living Council
Surrounding Area
Blackmans Bay urban area General Residential Zone boundary is 150m
North of the existing
Treatment Plant on
Suncoast Drive and
extends North
Blackmans Bay residential
areas to lower density where
existing natural and
landscape values are to be
retained
Environmental Living Zone boundary is 130m
West of the existing
Treatment Plant on
Tinderbox Road and
extends West and South
Derwent River, and adjoining
foreshore and walking tracks
located on DPIPW and
Council land
Environmental Management Closest zone boundary is
30m east of the existing
Treatment Plant and
extends south along the
foreshore. There is
additional EMZ land to the
north.
Blackmans Bay Scout Hall
and designated dog walking
area
Open Space Zone boundary is 77m
south of the existing
treatment plant
Const
ruction
Acces
s Roa
dTreatment Plant Road
Suncoast Drive
Tinderbox Road
Liberty Court
Wells Parade
Tahun
e Cres
cent
Ephesus Place
Jodie Court
Syracuse Place
Suncoast Drive
Tinde
rbox R
oad
Liberty Court
Tahune Crescent
Wells Parade
Tahun
e Cres
cent
Tahune Crescent
Ephesus Place
Jodie Court
Syracuse Place
526,400
526,400
526,600
526,600
526,800
526,800
5,237,
200
5,237,
200
5,237,
400
5,237,
400
5,237,
600
5,237,
600
G:\32\18107\GIS\Maps\MXD\3218107_005_Figure5-1_LandZoning_RevC.mxd
0 50 10025
MetresMap Projection: Transverse Mercator
Horizontal Datum: GDA 1994Grid: GDA 1994 MGA Zone 55
© 2016. Whilst every care has been taken to prepare this map, GHD (and DATA CUSTODIAN) make no representations or warranties about its accuracy, reliability, completeness or suitability for any particular purpose and cannot accept liability and responsibility of any kind (whether in contract, tort or otherwise) for any expenses, losses, damages and/or costs (including indirect or consequential damage) which are or may be incurred by any party as a result of the map being inaccurate, incomplete or unsuitable in any way and for any reason.
Tasmanian Water CorporationBlackmans Bay STP DPEMP
Job NumberRevision C
32-18107
27 Jul 2016
Land ZoningDate
Data source: Data Custodian, Data Set Name/Title, Version/Date. Created by:jtoregan
2 Salamanca Square Hobart TAS 7000 Australia T 61 3 6210 0600 F 61 3 6210 0601 E [email protected] W www.ghd.com.au
Paper Size A3
LEGENDWaterwayCadastral parcelDog excersize area
Tasmanian Planning Zones (LISTmap, 2016)10.0 General Residential14.0 Environmental Living19.0 Open Space28.0 Utilities29.0 Environmental Mangement
ProposedThe project siteFenced area (STP operational boundary)Construction compound(site office, parking, machinery, laydown,stockpiles and bunded fuel and chemicalstorage)
Figure 5-2
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 51
5.2 Environmental Aspects
The following subheadings summarise the environmental context of the site, however full details
for all salient topics are found under the relevant subheadings in Section 6.
5.2.1 Physical Characteristics of the Site
The Project Site is located immediately adjacent to the coast, along the lower Derwent Estuary.
Elevation levels range from sea level to approximately 60 m AHD. The Project area slopes from
hills to the west down to the estuary to the east, the site is bordered by a mosaic of regenerating
cleared land, urban open space and remnant native vegetation. The land surrounding the
current Blackmans Bay STP site is currently owned by Kingborough Council.
In general, the site is partially vegetated with areas of developed space and regenerating
cleared land.
5.2.2 Weather and Climate
The Blackmans Bay region has a cool temperate climate. It is maritime-influenced and
experiences generally cool summers and mild winters. Climatic data from the Hobart weather
station (094029) (BOM 2016) shows:
Temperature ranges from a mean minimum of 4.6 C in July and mean maximum of 21.7 C
in January and February.
Rainfall in the Hobart and Blackmans Bay region is distributed relatively evenly over the
year. The Project Site receives an average annual rainfall of approximately 614 mm. Lower
average rainfall of 39.7 mm occurs in February and the maximum average rainfall of 61.3
mm in October.
The most common winds at Blackmans Bay come from the south-east and the west. There
are fewer winds from the north and south, possibly due to the sheltering effects of the hills
and trees to the north and south of the Project Site. Winds from the south-east occur for
approximately 15% of the time. Further information on wind patterns is provided in Section
6.1.
5.2.3 Geology and Geomorphology
Broadly, the geology of the area around the Project Site consists of hard rock; predominately
Jurassic dolerite. The dolerite intrusion extends about 1 km north and 1 km south of the site,
ending just prior to Tinderbox Road to the west. Further inland, the rock is mainly Triassic quartz
sandstone.
The topsoil at the Project Site is shallow (<100 mm) and is mostly podzolic. There are no known
areas of potential acid sulphate soil near the Project Site.
The geomorphology of the region around the Project Site is characterised by the coastline
directly east of the site (dominated by a steep hard rocky cliff) and a narrow pebble/cobble
beach, with rock shelves extending offshore.
A geoconservation site is mapped on TheLIST database along the coastline within the
boundaries of the Project Site but outside of the proposed Project Footprint.
5.2.4 Natural Hazards
The Site is mapped as low coastal erosion hazard band on TheLIST database, indicating some
risk of coastal regression by 2100. According to TheLIST database the Project Site is not within
a Proclaimed Landslip Zone and is categorised as Low to Medium Landslide Hazard Band. The
Low Hazard Band relates to sites with 11 to 20 degrees’ slope and no known landslide features,
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 52
but a susceptibility. The Medium Hazard Band relates to site with a >20 degree slope and with
known landside features or within a landslide susceptible area. The proposed Project features
are predominately concentrated on the parts of the Project Site within the Low Landslide Hazard
Band.
The site is not subject to flooding due to its natural slope towards the Derwent Estuary. The site
is not known to be particularly susceptible to fire.
5.2.5 Surface and Groundwater
Surface drainage flows down gullies to the top of the cliff. Drainage at the existing STP site is
controlled and discharged through existing stormwater pipes.
There are two water bodies within the Project Site, an ephemeral drainage line to the north of
the current STP and a natural waterway to the south. Both waterways are outside of the
proposed Project Footprint.
The surface water bodies drain into the adjacent Derwent Estuary which bounds the site to the
east. Considerable monitoring data is available for the Derwent Estuary, which is characterised
in Section 6.8.
Depth to groundwater at the site is not known and there are no nearby extraction bores.
5.2.6 Reserves and Wilderness Areas
There are Informal Reserves adjacent to The Project Site at both the northern and southern
ends, but no reserves within the site itself. Approximately 0.5 km south of the Project Site is the
Fossil Cove Conservation Area, which will not be impacted by the Project.
There are no wilderness areas in the vicinity of the Project Site.
5.2.7 Existing STP Licence Arrangements
The existing plant is operated by TasWater under the following licence arrangements:
Licence to Operate Scheduled Premises No. 3326 (18/11/1987); and
Permit Conditions - Environmental No. 7551 (10/12/2008).
5.2.8 Ecological Context
Ecological surveys of the Project Site were undertaken in 2014 and again in 2016. These
surveys found the site to contain a mosaic of developed areas, open exotic grassland and
native vegetation communities.
Native vegetation communities found on site in 2016 include Eucalyptus globulus dry forest and
woodland (listed community under the Nature Conservation Act 2002), Eucalyptus amygdalina
forest and woodland on dolerite and Allocasuarina verticillata forest. Small areas of these
communities will be impacted by the Project Footprint, which is predominantly constrained to
already cleared land.
There were no threatened flora species found on site during either of the ecological surveys.
The surveys found relatively limited habitat values for threatened fauna species within the
Project Site, with the exception of the swift parrot which could nest and feed within the eucalypt
species found on site. Some eucalypts will be impacted by the Project; the potential impact of
this is assessed in Section 6.7.
A small number of environmental weeds were identified on the Project Site and their
management forms part of proposed management and mitigation measures in Section 6.7.
Black
mans
BayD
olerite
Conta
ct
526,400
526,400
526,600
526,600
526,800
526,800
527,000
527,000
5,237,
200
5,237,
200
5,237,
400
5,237,
400
5,237,
600
5,237,
600
5,237,
800
5,237,
800
G:\32\18107\GIS\Maps\MXD\3218107_006_Figure5-3_ResrvGeo_RevB.mxd
0 50 10025
MetresMap Projection: Transverse Mercator
Horizontal Datum: GDA 1994Grid: GDA 1994 MGA Zone 55
© 2016. Whilst every care has been taken to prepare this map, GHD (and DATA CUSTODIAN) make no representations or warranties about its accuracy, reliability, completeness or suitability for any particular purpose and cannot accept liability and responsibility of any kind (whether in contract, tort or otherwise) for any expenses, losses, damages and/or costs (including indirect or consequential damage) which are or may be incurred by any party as a result of the map being inaccurate, incomplete or unsuitable in any way and for any reason.
Tasmanian Water CorporationBlackmans Bay STP DPEMP
Figure 5-3
Job NumberRevision B
32-18107
27 Jul 2016
Reserves and Geomorphology FeaturesDate
Data source: DPIPWE (cadastre, imagery, land tenure, land zoning, waterways, contours), TasWater (proposed infrastructure). Created by: jtoregan
2 Salamanca Square Hobart TAS 7000 Australia T 61 3 6210 0600 F 61 3 6210 0601 E [email protected] W www.ghd.com.au
Paper Size A3
LEGENDContours (10 m)WaterwayElectrical to site (OH)Cadastral ParcelDog excersise areaGeoconservation site (listed)Informal Reserve on other public land
ProposedThe project siteConstruction compound *Existing fenceNew fenceSTP infrastructure
* site office, parking, machinery, laydown, stockpiles and bunded fuel and chemical storage.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 54
5.3 Socio-economic Aspects
This section describes the existing social and economic environment that may be affected by
the Project.
The existing Blackmans Bay STP currently treats wastewater from residences and commercial
areas in Kingston, Huntingfield, Blackmans Bay and southern Bonnet Hill. Following completion
of the Project, wastewater will also potentially be received from Margate, Snug and Electrona as
part of the aforementioned amalgamation scheme. All of these suburbs are part of the
Kingborough LGA.
The Kingborough LGA is essentially residential in character and, according to the ABS 2011
census, has the highest population growth rate in Tasmania (approximately 9% between 2006
and 2011). It is located 12 to 35 km south of Hobart and has a long stretch of coastline (330
km).
The business district is in Kingston, which is the major commercial, retail and administrative
centre in the region. The total population of Kingborough is approximately 34,000 persons (ABS
2011) including 10,000 persons in Kingston (which are generally a younger population) and
over 1,200 persons on Bruny Island.
The median age over the whole of Kingborough is 40 years (36 years in Kingston) and the
population is comprised of 52 % females and 48 % males. The age distribution is illustrated in
Figure 5-4. This figure highlights the gap in 20-30 year ages, while there is a high proportion of
older persons, particularly in the 55 to 65 age groups. Kingborough, and Tasmania in general,
has an aging population both numerically (absolute number of people aged over 65 years) and
structurally (proportion of people aged over 65 years).
Other demographic features of Kingborough are:
There is a higher average income than elsewhere in Tasmania;
Kingborough is above the national average in terms of socio-economic advantage;
Kingborough has lower unemployment than elsewhere in Tasmania;
There is higher educational achievement than in many regions in Tasmania (other than
Battery Point and Sandy Bay); and
Kingborough has a higher proportion of people working in the professions, management or
senior administration positions than other regions of Tasmania.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 55
Figure 5-4 Age and Sex Pyramid for Kingborough (ABS Census, 2006)
According to the 2011 census, employment patterns in Kingborough are: 30 % of residents are
employed in government - professional or administration; 20 % in construction; 15 % in retail; 12
% in health or community service; and 10 % in education. Manufacturing and primary industry
are small sectors of employment in the Kingborough LGA.
The Project offers major advantages to the residents (present and future) of Kingborough,
including:
Allowing for continued development in existing catchments of Kingston, Blackmans Bay
and Huntingfield;
Potentially allowing for continued development in Margate, Snug and Electrona;
Improving odour conditions for residents living near the existing Blackmans Bay STP with
improved odour control;
Reducing nitrogen inputs to the Derwent Estuary with potential for improved water quality
and lower risk of algal blooms; and
Allowing TasWater to consolidate and enhance the overall Kingborough sewerage system
so underperforming STPs at Electrona, Margate and Howden can be closed, providing long
term benefits to North West Bay.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 56
6. Existing Conditions, Potential Effects
and Management
6.1 Air Quality
6.1.1 Existing Conditions
Ambient air quality within the vicinity of the Project is generally considered to be of a good
quality with the exception of fugitive odour events that occur from time to time from the existing
STP.
Between April 2010 and June 2016 TasWater received 38 complaints from the public in relation
to fugitive odour from the existing STP, with 28 of these events occurring between 2013 and
2014. The majority of complaints have been received from properties to the north of the site
including those on Suncoast Drive, Liberty Crescent and Tahune Crescent.
Other than odour from the existing STP, no other air quality issues have been identified in the
area.
6.1.2 Performance Requirements
The Tasmanian Environmental Protection Policy (Air Quality) 2004 (EPP) provides a framework
for the management and regulation of both point and diffuse sources of emissions to air, and for
pollutants with the potential to cause environmental harm. This EPP is made pursuant to the
provisions of section 96A-96O of EMPCA.
The Air Quality EPP goes on further to state a 2 odour unit (OU) 99.5th percentile, 1-hr average
design criteria for new projects. This design criterion is normally applied at the property
boundary (i.e. ‘The Land’).
The key performance requirements relate to maintenance of air quality during the construction
and operational phases of projects to minimise potential impacts to site workers, local residents
and the environment.
6.1.3 Potential Effects, Management and Mitigation
Dust
Dust may be generated throughout the construction phase of the Project through various
pathways, including the excavation of materials for construction, demolition, loading and
unloading of building materials, road construction and vehicular movements throughout the
Project area on unpaved roads. Once operational there is no change to potential dust
generation from this site (compared to the existing STP) and dust management is not
considered to be an issue for the operational phase.
Potential impacts from dust generation during construction include respiratory impacts to
workers, residents, flora and fauna (coating of flora can restrict respiratory processes) and
impacts to visual amenity through dust plumes.
The following management and mitigation measured will be employed during the construction
phase of the Project to minimise dust impacts:
Sealed roads will be used to access the site where available;
All incoming trucks will have their loads covered;
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 57
Spraying of stockpiles and roads if dust generation becomes problematic, with the potential
use of dust suppressants if water spraying is not sufficient;
Daily visual monitoring by site staff;
Maintenance of an online complaints register to monitor any dust complaints;
Retaining existing vegetation where possible;
Staging works to minimise areas of disturbance at any one time before working on other
areas;
Using jute mesh where applicable following works;
Redirecting all recreational users of the site to the west of the Construction Compound
during the construction phase (refer Figure 2-6) to limit direct dust exposure; and
Ceasing work in dry and extremely windy conditions.
With these measures in place the residual risks from dust generation are low. The nearest
residence to the site is approximately 170m from the STP fence boundary and offsite dust
impacts at this distance are not expected, with the management measures in place.
With the low potential for impacts for dust, together with the proposed management and
mitigation, residual impacts as a result of the Project are considered likely to be negligible.
Engine Exhaust
Vehicle emissions in the Project area will temporarily increase as a result of the machinery and
vehicles required during construction activities only. The additional volumes of engine exhaust
emissions compared to those emitted under ambient conditions for the area are considered
negligible.
Potential for impacts are limited to recreational users of the adjacent park areas if exposed for
long periods of time, which is considered an unlikely scenario.
Management and mitigation for the Project will include the following aspects:
Emission levels to be taken into account during selection of machinery;
Scheduled maintenance of all vehicles, earth moving equipment and other combustion
engines to maximise emission quality; and
Construction area to be fenced to prevent exhaust exposure to recreational users.
With these management and mitigation measures in place, residual impacts to the environment
from engine exhaust emissions are considered to be negligible.
Odour
Fugitive odorous emissions may be released from the Project from several sources, including
the inlet works, IDEA-SBRs and aerobic digesters. Potential for impacts may also increase as a
result of malfunctioning equipment during STP operation or during upset flow conditions. This
has the potential to impact on the amenity of the local area, including nearby residential
dwellings, with impacts dependant on wind strength, direction, and volume of odorous
emissions.
To assess odour emissions from the upgraded STP MWH was commissioned to prepare a 3D
odour model of the site and proposed development. The full report is provided in Appendix E
with the salient information summarised below.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 58
The odour modelling report considered a total of seven sensitive receptors around the STP site
as illustrated in Figure 6-1. The polygons on the figure represent the current STP boundary
(blue line) and proposed site boundary (the Boundaries of the Land – red line).
The following sensitive receptors were included in the model:
SR1: Rural property to be purchased by TasWater. Note, this property is part of the land to
be acquired by TasWater from Council. The house will be used as a site office during
construction and demolished at the end of the construction period.
SR2: Rural property
SR3: Rural property
SR4: Residential property along Suncoast Drive
SR5: Residential property along Suncoast Drive
SR6: Residential property along Suncoast Drive
SR7: Rural property
Figure 6-1 Sensitive Receptors considered in Odour Assessment (Source:
MWH 2016)
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 59
To assess the likely impacts of the Project on the surrounding environment, 3D odour modelling
was undertaken for a variety of scenarios (Appendix E). The defined criteria for the odour
modelling was to achieve no nuisance odours at nearby residences together with meeting the
odour criteria under EPA Tasmania’s Environment Protection Policy (Air Quality) 2004 which
requires an odour limit of 2 odour units based on a 1-hour averaging periods and 99.5%
compliance measured at or beyond the facility boundary.
The modelling was undertaken using the modelling program CALPUFF, which was setup and
performed in accordance with the Tasmanian EPAs current draft of Tasmanian Atmospheric
Dispersion Modelling Guidelines V 0.93e. The full modelling methodology, including
meteorological sources, dispersion options, terrain elevation and odour emission data and
assumptions are available in the full modelling report in Appendix E. An aerial image showing
the main emission source locations is provided below. The following key sources of odour (and
corresponding process units) were considered in the assessment (full details refer Appendix E
and map showing key infrastructure refer Figure 2-2):
Inlet works (INWRKS);
Flow distribution channel (FLWDST);
Inlet works return pump station (IWPUMP);
General purpose pump station(GPPUMP);
IDEA-SBR tanks (numerous emissions based on time-based treatment phases);
Gravity thickener (GRAVTH);
Aerobic digester (DIGAER, DIGANO);
Dewatered cake self-loading bins (SPIROT); and
Odour Control Facility Stack (within the Odour Control Plant) (BTFOCF).
Figure 6-2 Major odour emission sources modelled (Source: MWH 2016)
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 60
Five scenarios were considered for modelling for the Project, as listed in Table 6-1. The five
scenarios covered a range of potential events, including inlet works maintenance, sludge
processing upsets, and a simulated worst-case upset in treatment process.
The variance between the scenarios was the Specific Odour Emission Rates (SOERs) used for
each potential odour emitting source within the Project. The SOER was altered for each piece of
equipment or area of the Project, according to each scenario.
The worst-case upset scenario (Scenario 3) simulates a major failure in all process areas. This
is considered an unrealistic event, but was included to demonstrate a simulated worst case.
This scenario should not be considered as a high flow event, or the event of a malfunction in a
single area (both more creditable scenarios) which would result in much lower odour emissions.
A commissioning scenario was also investigated, but as SOERs for the scenario were lower
than the normal operating scenario, modelling was not deemed necessary (i.e. odour profile
during commissioning is likely to be similar or less than under normal “full” operations).
The modelled results are shown in the output diagrams in Figure 6-3 to Figure 6-6. On each of
these images the dashed red line represents the existing STP boundary, the blue dashed line
represents the proposed STP boundary (The Land) to be acquired from Kingborough Council.
The solid coloured lines represent the 2 odour unit contour, based on each modelled scenario.
Table 6-1 Odour Modelling Scenarios
Scenario Description Specific Odour Emission Rates (SOER)
Scenario 1 Normal STP
Operation
Normal Operating SOER as per Appendix E
Scenario 2 Inlet Works
Maintenance
Period
Normal Operating SOER with:
100% increase in SOER for inlet works
Scenario 3 Upset in
Treatment
Process
Normal Operating SOER with:
100% increase in SOER for inlet works, flow distribution
channel, inlet works return pump station, general
purpose pump station, IDEA-SBR tanks, gravity
thickener, and aerobic digester.
Scenario 4 Upset in Sludge
Process
Normal Operating SOER with:
100% increase in SOER for areas surrounding the
centrifuge building
Scenario 5 Commissioning
Activities
Commissioning SOER as per Appendix E
(Model not run as SOERs were less than Normal
Operating SOERs)
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 61
Figure 6-3 Odour Modelling Scenario 1: Normal Operating Conditions (Source:
MWH 2016)
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 62
Figure 6-4 Odour Modelling Scenario 2: Inlet Works Maintenance (Source:
MWH 2016)
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 63
Figure 6-5 Odour Modelling Scenario 3: Upset in Treatment Process (Source:
MWH 2016)
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 64
Figure 6-6 Odour Modelling Scenario 4: Upset in Sludge Process (Source:
MWH 2016)
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 65
The results show that under normal operating conditions (Scenario 1), the EPA odour criteria
(2 ou) is met well within the Project Site (The Land). Scenario 2 (Inlet Works Maintenance
Period), showed very similar results to normal operating conditions, as was the case in Scenario
4 also (Upset in Sludge Process).
The worst-case Scenario 3 results show that the EPA criteria (2 ou) are not met at the southern
Project Site boundary (The Land), with the 2 OU contour extending ~50 m past the boundary.
As discussed, this scenario is highly improbable, but shows the worst possible case that could
occur as a result of the Project. In their report MWH conclude that this scenario (3) is not
considered to be a realistic scenario and all realistic scenarios resulting in increases in liquid
stream emissions are unlikely to exceed the 2 OU limit at the boundaries of the land.
Regardless of the unlikeliness of this “scenario 3”, consideration is given to how far the
predicted 2 odour unit contour extends beyond the boundary. In this scenario, the 2 odour unit
extends only 50m beyond the boundaries of the land and into a Council owned parcel of land
zoned as “open space”. Given the ownership and zoning (residential development is prohibited
in the open space zone) the potential impacts on this small area of land are minimal even in the
unlikely event of “scenario 3”.
The modelled scenarios focus on impacts outside of the boundaries of the land; however, it is
noted that ongoing recreational use within that boundary will be accommodated by the Project.
The area surrounding the existing STP is already used for walking and other recreation and is
already subject to odour impacts from the existing STP. Under the upgraded STP odour impacts
on this land will be improved (due to improved odour treatment). Of particular note, all scenarios
aside from the unrealistic “scenario 3” result in the 2 odour unit contour being contained almost
entirely within the proposed fenced area of the new STP. The areas of the site likely to be used
for public recreation (western portion) are outside of the modelled are of impact. Given the
current odour conditions of the site, the predicted 2 odour unit contours and the proposed
fenced STP extent, the impact to recreational users of the site from odour is considered to be
negligible.
MWH also investigated management of odour during adverse weather conditions, different
times of day, during biosolids export and during construction with the following findings:
Time of day – as modelling did not show any off site impact for any of the scenarios likely to
eventuate, time of day impacts were not considered further.
Adverse weather conditions - during storm flows the retention time within the sewer
decreases and wastewater tends to become more dilute, reducing odour potential.
However, first flush of stormwater can deposit silted sludge into the inlet works leading to
short periods of increased odour form the inlet works. For a plant the site of Blackmans
Bay, this rarely affects plant downstream of the inlet works and was not considered further.
Odour during biosolids export – This risk will be managed through the design of self-loading
enclosed spirotainer type bins which are filled on demand via enclosed conveyors. The
spirotainers and conveyors are ventilated at a high rate to contain odour and the sludge is
not exposed to atmosphere during its removal. Odour produced from the dewatered
biosolids will be contained at all times. As such odour nuisance caused by out -loading
events is not envisaged with the proposed design.
Construction – A detailed odour mitigation plan will be prepared for the construction phase
of the project and include:
– Network dosing to reduce site gas levels and potential for odour nuisance;
– Maintaining the existing odour treatment as long as possible, until upgraded odour
treatment is operational;
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 66
– Regular rebalancing and surveillance of odour control systems during construction to
ensure satisfactory operation;
– Prompt removal of sewage products and cleaning of decommissioned vessels;
– The use of atomization sprays (if required) during the de-gritting and removal of
products from the digester;
– No storage of odorous products on site; and
– Phased start-up of plant to enable new odour control facilities to acclimatise and use
downstream carbon during this period to prevent odorous gas discharge.
The potential for power failure at the site has been addressed under Section 2.5.9 and involves
the supply of emergency power generation in the event of power outage. The odour control
system will continue to operate (through emergency power generation) during power outages
and no significant changes to odour impacts are anticipated. The modelled scenarios include
consideration of upset/malfunction in the treatment process and the potential for changed odour
conditions as a result.
With the odour control measures in place the residual odour impact during both construction
and operation of the upgraded STP is limited and an improvement in relation to current site
conditions.
6.1.4 Monitoring, Review, and Adaptive Management
Along with proactive community consultation leading up to, and during, construction, the
TasWater online complaints register will be the main vehicle for the monitoring of problematic air
emissions. If complaints regarding air quality, including odour are received, the source of the
issue will be isolated and assessed for further management and mitigation.
Visual identification of dust plumes will trigger management and mitigation actions, including
identifying the source of emissions and mitigating accordingly using the options outlined in the
relevant sections above.
Review of air emission management and any incidents that occur throughout each
environmental reporting period will be addressed in annual environmental reports to the EPA.
Commitment 1 Trucks with potentially windblown materials will be
covered.
Commitment 2 Daily visual monitoring of the site for dust will be
undertaken during construction and water sprays applied to roads
and stockpiles if needed.
Commitment 3 A complaints register will be established for both the
construction and operational phases. All complaints will be logged,
actioned and all outcomes documented.
Commitment 4 TasWater will undertake community and stakeholder
engagement leading up to and during construction.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 67
6.2 Surface Water Quality
This section concentrates on potential impacts to freshwater surface waterbodies around the
Project. Potential impacts to the marine environment from effluent discharge from the STP, is
covered in Section 6.8 - Marine and Coastal.
6.2.1 Existing Conditions
The Project Site is set on easterly sloping land, with the Project Site boundary meeting the sea
cliffs to the east. There are two existing ephemeral waterways within the Project Site:
A modified drainage line to the north-east of the Project Footprint which is not registered on
the Conservation of Freshwater Ecosystem Values (CFEV) database; and
A slightly larger ephemeral creek to the south of the Project Footprint, listed on the CFEV
as a ‘Conservation Value C’ waterway with a naturalness value of ~0.9, meaning the creek
is in close to natural condition and has the lowest rated conservation value.
There is a network of drainage systems on the existing site and the majority of stormwater is
collected and discharged via stormwater drains to the nearby creeks and over the cliffs to the
marine environment.
Existing water quality within the waterways is unknown, with no requirement under the existing
operating licence to monitor the sites.
6.2.2 Performance Requirements
The key legislation, policy and guidelines of relevance to surface water management in
Tasmania are the:
Water Management Act 1999;
State Policy on Water Quality Management 1997 (Water Policy);
Inland Fisheries Act 1995;
Environment Protection & Biodiversity Conservation Act 1999 (EPBC Act) - noting the
project is a Controlled Action (refer Section 8); and
Tasmanian Threatened Species Protection Act 1995 (TSPA).
No PEVs have been set for either of the waterways on the Project Site and due to their
ephemeral nature are unlikely to support any significant species or communities. However, the
waterways drain to the marine environment, with the PEVs for this environment described in
Section 6.8, and have been adopted for this section.
6.2.3 Potential Effects, Management and Mitigation
Potential sources of discharge to local surface waters from the Project include contaminated
stormwater run-off, major leaks from treatment infrastructure, and large scale spills of chemicals
or fuels.
Discharge of contaminated fluids to the waterways surrounding the Project Footprint have the
potential to have acute/chronic toxic effects on flora and fauna in the immediate environment, as
well as the flora and fauna and recreational users in the eventual downstream marine and
coastal environment, including potential for immunological risks to recreational users from
discharge of untreated sewage.
Management of Dangerous Goods and Environmentally Hazardous Materials has been
discussed in detail in Section 6.6, including the management and mitigation for treatment
infrastructure leaks.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 68
The Project Specific Guidelines required confirmation of any vegetation clearance within 10 m of
a waterway or within the coastal area. It is confirmed that there will be no vegetation clearance
within 10 m of any watercourses and there are no works planned for the coastal area east of the
existing STP site.
Construction Phase Management
A Soil and Water Management Plan (SWMP) will be developed for the construction phase and
incorporated into the site Construction Environmental Management Plan (CEMP). The principles
of Soil and Water Management as set out on the EPA website will be followed (and further
detailed in that plan) including:
Minimising areas of soil disturbance, staging the soil disturbance work and retaining
vegetation where possible;
Establishing a stabilised site access and wheel wash point within the Construction
Compound, with resulting drainage to the sediment control features;
Installing diversion drains around the up slope of the construction footprint and any material
stockpiles;
Covering material stockpiles or installing sediment fences down gradient as required; and
Installing and maintaining collection drains and small retention basins to capture site
stormwater during construction.
With the proposed management and mitigation of wastewater and stormwater, the residual risk
of contaminants reaching the identified waterways are considered low, with potential impacts
likely to be negligible.
Operational Management
The proposed upgrade results in a small increase in roofed areas, access roads and hardstand
areas. All new roofed areas will be sloped and drain to adjacent hard stand. New hardstands
will be sloped to direct stormwater away from the site and into constructed grass swales before
diffuse discharge into the surrounding environment. Diversion drains will be installed around the
upslope edge of new hardstand areas to direct clean stormwater away from the site. Some of
the newly generated stormwater will be captured by the existing stormwater drains through
natural surface flows (e.g. from parts of the new access road). These existing drains report to
the nearby creek and over the cliffs to the marine environment.
In accordance with the requirements of the Kingborough Interim Planning Scheme 2015, during
the detailed design phase of the project a detailed stormwater design will be prepared (including
review of the existing stormwater capture) to achieve the stormwater management targets for
new developments as set out in the State Stormwater Strategy 2010 (unless it is not feasible to
do so). Any installed features (such as vegetated swales) will be planned to avoid any impacts
to existing native vegetation.
Potentially contaminated areas of stormwater will be collected via new pipework and directed to
the inlet works of the new plant for treatment. This includes the sludge bund loading area, the
inlet works, screenings and grit collection bin area and the diffuser wash-down area near the
IDEA/SBR tanks.
6.2.4 Monitoring, Review, and Adaptive Management
Weekly monitoring of water and sediment control measures will be undertaken during the
construction phase, with additional monitoring within 24 hrs of any storm event.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 69
Commitment 5 A Construction and Environmental Management Plan
(CEMP) will be developed prior to commencement of construction.
Commitment 6 A Soil and Water Management Plan (SWMP) will be
incorporated into the Site Construction and Environmental
Management Plan (CEMP).
Commitment 7 Weekly monitoring of water and sediment control
measures will be undertaken during the construction period, with
additional monitoring within 24 hrs of a storm event.
Commitment 8 Prior to construction a detailed stormwater design will
be prepared (including review of the existing stormwater capture)
to achieve the stormwater management targets for new
developments as set out in the State Stormwater Strategy 2010
(unless it is not feasible to do so).
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 70
6.3 Groundwater
6.3.1 Existing Conditions
There are no known groundwater investigations from the Project site or direct surrounds. The
closest bore to the Site is up gradient, 850 m to the south west.
Groundwater flow is inferred to drain across the site from west to east following the natural
contour and culminating at the coast line.
There is no known productive aquifer at the Project site, which sits at the bottom of a sloping
catchment. The Project sits on Jurassic dolerite, with an unknown depth to groundwater layers.
From the topography of the site it can be assumed that any groundwater will report to the cliff
faces and drainage lines surrounding the site.
There is potential that the existing STP on the Project site may have leaked over the years into
the groundwater system, however no impacts on the shoreline or drainage lines have been
investigated.
In summary, any groundwater present is not used for consumption and is does not appear to be
supportive of any ecosystems.
6.3.2 Performance Requirements
The proposal should be consistent with the objectives and requirements of relevant water
management policies and legislation, including the Water Management Act 1999 and State
Policy on Water Quality Management 1997 (Water Quality Policy). In particular, it must be
demonstrated that the proposal will not prejudice the achievement of any water quality
objectives set for water bodies under the State Policy on Water Quality Management, which
defines water quality objectives as the most stringent set of water quality guidelines which
should be met to achieve all of the PEVs nominated for that body of water.
The relevant PEVs for groundwater are based on the Total Dissolved Solids (TDS) of the water.
With results of <1000 mg/L expected in the area (i.e. fresh water), the relevant PEVs are listed
in Table 6-2.
Table 6-2 Relevant Groundwater PEVs and Water Quality Indicators
PEV Existing Use Water Quality Indicators
Maintenance of
Ecosystems
Unknown The water quality objectives to protect environmental
values shall be the criteria specified in the ANZECC
2000 guidelines for the chosen level of ecosystem
protection. In this case the 95% level of protection
(moderately disturbed ecosystems) is appropriate for
toxicants.
Potable None Those criteria specified in the NHMRC & NRMMC
(2011) Australian Drinking Water Guidelines (ADWG)
Potable Mineral
Water
None
Agriculture, Parks
and Gardens
None Those criteria specified in the ANZECC 2000
irrigation guidelines
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 71
PEV Existing Use Water Quality Indicators
Stock Watering None Those criteria specified in the ANZECC 2000
livestock drinking water guidelines
Industrial Water
Use
None Those criteria specified in the ANZECC (1992)
guidelines for industrial use. These guidelines have
been rescinded due to the specific nature of water
quality requirements for various industries.
Primary Contact
Recreation
None Those criteria specified in the ANZECC 2000
guidelines which defer to the WHO Guidelines for
safe recreational water environments (current version
2003) which in turn defers to a default value of 10
times the drinking water guideline, in this case
ADWG (NHMRC & NRMMC 2011).
Buildings and
Structures
None The groundwater shall not be corrosive to structures
or building materials (pH, sulfate, redox potential).
6.3.3 Potential Effects, Management and Mitigation
Construction
Construction of the project has the potential to impact groundwater through spills of liquids,
including hydrocarbons, permeating into the groundwater.
During construction, to mitigate against impacts of fuels and chemical spills, all potentially
hazardous substances will be stored within the Construction Compound in locked and bunded
storage areas. All refuelling of construction machinery will be undertaken in bunded laydown
areas, as detailed in Section 6.6. An emergency spill management protocol will be established
and documented in the Site Construction Environmental Management Plan (CEMP).
The residual risk to groundwater is considered to be low.
Operation
During operation there is the potential for several sources of liquids to enter the groundwater
system. This may include stormwater run-off, hydrocarbon or chemical spills or leaking of
wastewater from treatment facility components (e.g. inlet works or IDEA-SBRs). The potential
impacts would be dependent on the volumes released and the receptors present at the exit
point of the water into the greater environment. Long term leakage of untreated sewage to the
coastline through the groundwater vectors mentioned may result in deleterious impacts to the
marine and coastal environment, including impacts to recreational users of the area.
The majority of the wastewater treatment at the Project will occur in closed vessels and
pipelines, which will be designed with corrosion resistant materials to minimise the chance of
leakages occurring. Computer systems and sensors integrated into the treatment system will be
capable of detecting irregular flows or operational behaviour of equipment, providing feedback
to plant operators to enact on, as reported in Section 6.6.
Regular inspections of areas susceptible to leakages, including pipelines, flanges, water holding
tanks and reactors will be undertaken as part of routine maintenance of the Project.
All hazardous substances and dangerous goods will be stored in roofed and bunded facilities.
Refuelling of machinery such as generators will be a rare occurrence during operation and will
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 72
not involve large volumes of fuel. A spills contingency plan will be incorporated into the Site
Operational Management Plan (OMP).
With the outlined control measures in place the risk to groundwater from site operation is
consider to be low and, most importantly, improved from current conditions due to significant
upgrade and improvement to infrastructure on site.
6.3.4 Monitoring, Review, and Adaptive Management
Inspection of the Project components for leaks or risk of leaks will be undertaken on a regular
basis, with each aspect of the treatment process inspected as required by specification of the
manufacturer. Plant operations will be monitored both manually and remotely on a daily basis.
These processes will allow for early detection of any potential leakage risk during operation.
Any spills of potentially environmentally harmful liquids greater than 100 L during construction or
operation will be reported to the EPA and groundwater monitoring will be undertaken if
warranted (as determined by the EPA), with monitoring requirements to be determined in
consultation with the EPA.
No direct groundwater monitoring is proposed at the current time due to the low likelihood of
significant impacts to the groundwater system or the receiving environment.
Commitment 9 Any spills of environmentally harmful liquids greater
than 100 L will be reported to the EPA, with commitment to
undertake a groundwater monitoring event if deemed necessary by
the EPA.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 73
6.4 Noise Emissions
Specialist consultants VIPAC Engineers and Scientists (Vipac) were engaged to undertake
noise assessments for the Project. In 2014 Vipac prepared a preliminary report for the site
which characterised the existing noise environment and established noise criteria for the
upgraded plant to meet. In 2016 Vipac prepared a follow up report which assessed the likely
noise impacts from the proposed STP against the pre-established criteria. The results of those
two assessments is summarised below with the full reports available in Appendix F.
6.4.1 Existing Conditions
The existing acoustic environment of the residential areas surrounding the Project includes light
traffic noise from the local roads (Tinderbox Road and Suncoast Drive), faint noise from the
existing Blackmans Bay STP, general ‘bush’ related noises, wave action from the estuary and
typical suburban noises; overall the area is classed as acoustically ‘quiet’’ (Vipac, 2016).
As part of the 2014 investigation Vipac measured community noise levels (background noise) at
three residential locations considered typical of houses surrounding the STP. These residential
properties correspond with houses 1, 3 and 5 in the images below. The analysis found relatively
low levels of noise at each of these locations. At house 1 (the existing house within the Site and
proposed for demolition post construction) the dominant noise was waves from the foreshore
with the existing STP also audible from this property. At house 5 (to the west of the STP) the
existing STP was found to be inaudible and bush noises were the main noises registered. At
house 3 (to the north of the STP on Suncoast Drive) wave noise and intermittent traffic noise
from Suncoast Drive were clear with a ‘tone’ also audible from the existing STP (presumed to be
associated with the existing fan).
In general, this represents a fairly quiet ambient noise environment with waves, bush sounds
and traffic noise most common and the existing STP audible from some locations.
As part of the first assessment Vipac also characterised noise sources from the existing STP.
Noise from the existing STP was taken into account when measuring background “community”
noise, which was subsequently used to inform the site specific criteria.
Further details on the existing noise conditions and existing STP are available in the full report
(Appendix F).
6.4.2 Performance Requirements
The key legislation, policy and guidelines of relevance to noise management in Tasmania are
the:
ANZECC Technical basis for guidelines to minimise annoyance due to blasting
overpressure and ground vibration 1990 (ANZEC 1990);
Environmental Management and Pollution Control Act 1994;
Environmental Management and Pollution Control (Miscellaneous Noise) Regulations 2014
(EMPCR);
Environment Protection Policy (Noise) 2009;
Tasmanian EPA Noise Measurement Procedures Manual (NMPM), dated July 2008; and
Kingborough Council Draft Interim Planning Scheme 2014
The Environment Protection Policy (Noise) 2009 sets out a strategic framework for noise
management in Tasmania focusing on protection of human health, both within the community
and for individual’s health and wellbeing. In addition to protecting community and individuals
(including site workers) from noise impacts, the project also aims to minimise noise impacts to
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 74
wildlife. The policy provides guideline levels that, if met, would be expected to protect the
majority of the population.
The Kingborough Council Draft Interim Planning Scheme 2014 also includes acceptable noise
criteria in its Use Standards, which have been included in the establishment of noise criteria.
6.4.3 Potential Effects, Management and Mitigation
The project has the potential to impact local residents through the generation of noise during
both the construction and operational phases. The potential for impacts to wildlife from noise are
very limited as no blasting is proposed, construction work will be restricted to daylight hours and
the existing STP already operates 24 hrs a day, therefore local animals are already accustomed
to this noise. As such impacts to fauna have not been considered further.
Noise Criteria
As noted above, in order to assess the potential noise impacts as a result of the Project
TasWater commissioned Vipac to undertake an acoustic assessment of the area in two parts
during 2014 and then 2016. As outlined in Section 6.4.1 the existing noise environment was first
established, with site based measurements at three local properties. These background
measurements were used to determine site specific noise criteria against which the modelled
impacts were assessed. The sites assessed for background noise in 2014 were originally
labelled A, B and C but correspond to locations 5, 1 and 3 respectively in the final modelling
effort (refer figures below). It is noted that house 1 (B in original assessment) is within the Site
and has since been determined by TasWater to be part of the overall land acquisition from
Council and is to be demolished post construction. It is still useful in understanding background
conditions, but is not relevant in assessment of future impacts.
During the operational phase noise criteria were set with reference to the Kingborough Interim
Planning Scheme 2015 and the Victoria Regional Noise lowest base level. The Tasmanian EPP
and NSW Industrial Noise Policy were also considered (refer Appendix F) but were in excess of
the adopted guidelines and therefore the more conservative limit was applied. The Kingborough
Interim Planning Scheme 2015 makes reference to adopting the L90 measured background
level plus 5 dBA (or 40 dBA whichever is lower). This was initially applied to all measured
background sites but those with results lower than the Victoria Lowest Base Level (namely
house 5) were revised to adopt the Victorian Lowest Base level as industry recognised
standard. The resulting noise criteria are illustrated in Table 6-3.
Table 6-3 Noise Criteria for Sensitive Receptors During Operations
House Number Sound Pressure Level, dBA
L90 Night Time
(Monitored) L90 + 5
Minimum Criteria
(Victoria) Project Criteria
5 (low density
housing west of the
Site)
23 28 32 32
1 (within the Site) 30 35 32 35
3 (medium density
housing north of the
Site)
32 37 32 37
Source: Vipac 2016
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 75
Once the appropriate criteria to be met was established at the measured receptors, it was
applied to the remaining sensitive receptors in Figure 6-8 using the density of housing as a
guide (i.e. all low density housing to the west and south adopted the same criteria as house 5
and all medium density housing to the north adopted the same criteria as house 3). These
criteria were adopted for normal operations only. Different criteria were adopted for the
construction phase and occasional emergency generator use.
For the construction period and periods of emergency power generation (diesel generator),
noise criteria from the Tasmanian Environmental Protection Policy (Noise) 2009 were applied
(see Table 6-4). These more relaxed criteria were used for construction as construction noise
will be intermittent, only during the day, and only for short periods of time (although the overall
construction period is 2 years, only short periods of noise generating activity will occur within
this period). These more relaxed criteria are adopted for emergency diesel generation given the
infrequent and short duration of such activities and that emergency power generation does not
represent any deviation from current site operations.
Table 6-4 Noise Criteria for Construction and Emergency Diesel Generation
Specific
Environment
Critical Health Effects LAeq
dBA
Time base
(hours)
LAmax fast (dB)
Outdoor living
area
Serious annoyance, daytime
and evening 55 16 -
Moderate annoyance,
daytime and evening 50 16 -
Outside
bedrooms
Sleep disturbance, winder
open (outdoor values) 45 8 60
Source: Tasmanian Environmental Protection Policy (Noise) 2009. Only outdoor criteria adopted.
Noise Modelling Methodology
SoundPLAN software was used for carrying out detailed noise emission spectra and contour
modelling. SoundPLAN via the CONCAWE prediction algorithm models atmospheric attenuation
using Pasquill stability indices in combination with vector wind speed and direction to determine
appropriate frequency dependent attenuation/amplification. Neutral wind weather conditions
were modelled. Other weather conditions were not considered due to the proximity of closest
sensitive receptor locations negating any significant influence from atmospheric conditions.
Sound power levels and sound power level spectra were established using the proposed design
as inputs. The main noise sources included in the model are shown in Figure 6-7. Assumptions
were made in relation to noise control measures on the proposed infrastructure (refer below)
and these form commitments in the detailed design phase in order to achieve the level noise
outputs as modelled.
Two model scenarios were considered, namely normal operations and operations with
emergency power generation. The second run was done to simulate the operation of generator
as well as the STP in power outage scenario
A total of eight houses (sensitive receptors) were included in the model as outlined in the figure
below. As noted previously house number 1 is now to be acquired by TasWater, used as a site
office during construction then demolished so is not considered further in this DPEMP (but is
included in the attached noise reports).
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 76
Figure 6-7 Noise Sources from Upgraded STP (Source, Vipac 2016)
Figure 6-8 Residential Locations used for Baseline Noise Assessment
(Source, Vipac 2016)
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 77
Noise Modelling Results
Following development of all applicable criteria, the noise modelling was then undertaken using
software and data sources outlined in Appendix F.
The resulting modelled noise contours are presented in Figure 6-9 for normal operations and
Figure 6-10 for normal operations with a generator.
The results from the figures for each of the sensitive receptors are summarised in Table 6-5. As
the plant will operate 24 hours a day modelled south pressure levels are provided for all periods
and not delineated into day and night time.
Table 6-5 Modelled Sound Pressure Levels during Operation
Sensitive
Receptor ID5
Low Level Noise
Emission Criteria (dBA)
Source - Kingborough
Scheme and Victoria
Lowest Base Level
Tasmanian EPP
noise criteria for
outdoor areas and
outside bedrooms
(LAeq dBA)
Model Scenario Results (predicted
sound pressure levels in dBA)
Operations Operations
with generator
Site 2 37 45 to 55 30 43
Site 3 37 45 to 55 33 38
Site 4 32 45 to 55 24 44
Site 5 32 45 to 55 21 35
Site 6 32 45 to 55 16 33
Site 7 32 45 to 55 23 27
Site 8 32 45 to 55 30 34
The results from Table 6-5 show that during normal operations, the relevant noise criteria were
not exceeded at any of the sensitive receptors, with the highest noise levels apparent at Site 3.
Under normal operations the Low Level Noise Criteria apply and are not exceeded at any site
during normal operations.
Under emergency power generation the Tasmanian EPP criteria apply and are not exceeded at
any site during normal operations. Note that although higher criteria have been adopted for
periods of emergency power generation, these are highly infrequent events of short duration
and do not represent any deviation from current operations (which already use emergency
generation in power outages).
It is noted that sound pressure levels at receivers 7 and 8 have the potential to be 1 to 2 dBA
higher under worst case weather conditions. Even with this deviation, they remain within the
adopted criteria.
The stages of construction with highest potential for noise generation were assessed by Vipac,
namely excavation, trenching, concrete works, compaction and tank cleaning. Sound power
data were assessed for each of these stages predicted sound pressure levels generated. For
the construction period, the predicted sounds pressure levels from the three main stages of
construction are presented in Table 6-6. As can be seen in the table, the highest sound
pressure levels are modelled to occur during the major trenching and concrete works.
5 Note that although site 1 has been removed from this s ummary, it is included in the original report and also complies with the adopted criteria.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 78
Predicted levels show that there will be some degree of disturbance, but this will be intermittent
and depend on the stage of construction. The modelled construction phase sound pressure
levels are within the adopted criteria (Tasmanian EPP).
The main mitigating factors for construction noise will be limiting operations of construction
equipment to normal daytime hours, so as to not impact on night time periods. Working hours
for construction involving heavy machinery (as modelled) will be restricted to 7 am to 6 pm
Monday to Saturday.
Table 6-6 Modelled Sound Pressure Levels during Construction
Sensitive
Receptor ID
Tasmanian EPP
noise criteria for
outdoor areas
and outside
bedrooms
(LAeq dBA)
Model Scenario Results (predicted sound pressure levels in dBA)
-30t excavator
and trucks for
earthworks for
IDEA-SBRs
-20t Excavator for trenching
-Concrete trucks and
concrete vibrators
-Compaction equipment and
grade for backfill and road
construction
-Cleaning tanks and
modifications to
existing infrastructure
-20t excavator for
trenching pipelines
Small concrete works
Site 2 45 to 55 37 43 39
Site 3 45 to 55 38 45 41
Site 4 45 to 55 38 42 28
Site 5 45 to 55 27 38 27
Site 6 45 to 55 20 31 22
Site 7 45 to 55 20 34 31
Site 8 45 to 55 33 38 36
Design Commitments
As noted above, the noise modelling work made assumptions about a number of noise
generating elements in order to develop the predictions provided. During the detailed design
phase these assumptions will be reviewed with respect to design elements in order to achieve
the level of sound reduction built into the model. In particular:
The SWL (sound power level) for the inlet works will be 85 or less. A reduction of 3 to 6
dBA may be required on the inlet works to achieve this. If needed this will be achieved by
enclosing the works on the north and east sides with a material with an appropriate sound
transmission loss and lining the internal sides with adsorption.
An enclosure of the odour control fan will be applied that will provide performance of 80
dBA sound pressure level at 1 m or less.
The new odour control fan inlet duct is likely to require a silencer providing 10 dBA insertion
loss with performance across the frequency range 250 Hz to 4 kHz 1/1 octave bands to
achieve a sound power level of 89 or less.
The exhaust of the odour control fan will have a discharge silencer fitted with an insertion
loss performance as stipulated in Table 9 of Vipac 2016 to achieve a sound power level of
84 dBA or less.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 79
Care will be taken in the development and selection of enclosures for the IDEA blowers
such that tonal noise emission breakout does not generate potentially intrusive noise
emissions.
6.4.4 Monitoring, Review, and Adaptive Management
Along with proactive community consultation leading up to, and during, construction, t he
TasWater online complaints register will be the main vehicle for the monitoring of problematic
noise emissions. If complaints regarding noise are received, the source of the issue will be
isolated and assessed for further management and mitigation.
Commitment 10 Noise complaints will be tracked using the online
complaints register. All complaints will be logged, actioned and all
outcomes documented.
Commitment 11 Detailed design will address the required noise limits on
equipment and acoustic enclosures as stipulated in this DPEMP
and the Vipac Noise Report (2016) namely 85 dBA or less for the
inlet works, 80 dBA (at 1 m) or less for the odour control fan,
89 dBA or less for the odour control fan inlet duct and 84 dBA or
less for the exhaust from the odour control fan.
Commitment 12 Care will be taken in the development and selection of
enclosures for the IDEA blowers such that tonal noise emission
breakout doesn’t generate potentially intrusive noise emissions.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 80
Figure 6-9 Predicted Noise Emission Contours for Normal Operations in Neutral Weather (Source: Vipac, 2016)
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 81
Figure 6-10 Predicted Noise Emission Contours for Normal Operations with Temporary Power Generation in Neutral Weather
(Source: Vipac, 2016)
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 82
6.5 Waste Management
This section outlines the solid waste streams from the upgraded STP during construction and
operation.
The primary liquid waste stream from the site is the treated effluent itself which is discharged via
the existing outfall to the marine environment. As this outfall impacts the marine environment it
is addressed under Marine and Coastal in Section 6.8.
6.5.1 Performance Requirements
The key legislation, policy and guidelines of relevance to the management of solid and
controlled wastes in Tasmania are:
Environmental Management and Pollution Control Act 1994
Environmental Management and Pollution Control (Waste Management) Regulations 2010
Environmental Management and Pollution Control (Controlled Waste Track ing) Regulations
2010.
National Waste Policy 2009 (NWP)
Used Packaging Materials NEPM
The objectives of the Resource Management and Planning System as set out in Schedule
1 of the Land Use Planning and Approvals Act 1993 (LUPAA)
Specifically, for Biosolid management:
Biosolids Reuse Guidelines August 1999
Approved Management Method for Biosolids Reuse - June 2006
Sewage Sludge Management Plan Guidelines, September 2014
The key performance requirements, as related to the legislation outlined above are:
Approval must be sought prior to controlled wastes being transported from the site;
Controlled wastes must be removed from the site by an approved controlled waste
transporter; and
Controlled wastes must be disposed of at an approved disposal facility.
6.5.2 Project Sources
Construction
During construction, excess fill material will be generated from the cut and fill process to install
the new treatment infrastructure. The vast majority of earthworks for the development is on land
outside of the existing STP site and up gradient from it. There is however a small area of cut on
the western boundary of the existing STP site and other construction works (including new
unloading/loading facility) within the existing STP site. As STPs are potentially contaminating
activities consideration needs to be given for any excavated material from the site to be
contaminated. Management of this risk is outlined below.
Other solid waste streams will include excess construction materials and general waste
generated by the contractors.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 83
Operational
The solid and controlled wastes which will be generated during operation include:
Miscellaneous general waste;
Solids from inlet screening and grit removal; and
Sludge from the treatment process in the form of compressed sludge cake (biosolids cake).
Sludge is classified as a controlled waste in accordance with the Environmental
Management and Pollution Control (Waste Management) Regulations 2010 (Regulation 5);
The estimated quantities of solid wastes generated during operation of the Project are identified
in Section 2.6.5 - Waste Streams. The type of solid waste remains the same for the existing
and upgraded STP, but quantities are increased in line with increases in future flows through
the plant.
6.5.3 Potential Effects, Management and Mitigation
Excavated Materials
As stated above the vast majority of all excavated material is from areas outside of and up
gradient from the existing STP site. However, a small area along the western side of the existing
STP boundary (up gradient of the existing plant) will be excavated and some ground
disturbance will occur at the new loading/unloading facility. As the existing STP is a “potentially
contaminating activity” risk of contaminated soil being encountered needs to be considered. To
manage this risk a targeted inspection of areas proposed for subsurface excavations will be
undertaken by a Certified Practitioner (Site Contamination Practitioners Australia) prior to
construction. This inspection will review available history for the site and delineate which areas
proposed for excavation would be considered lower risk and therefore not require classification
and which areas are higher risk and therefore need soil testing and classification (for reuse or
disposal). In accordance with this assessment, areas of higher contamination risk (within the
excavation footprint) will be subject to soil testing and classification. Any resulting material from
these areas will be handled, transported and disposed on in accordance with relevant
guidelines and utilising licenced practitioners.
General Waste
During construction a waste collection area will be established within the Construction
Compound. This area will allow for separation of reusable, recyclable and other waste streams.
All potentially wind-blown wastes will be covered. All wastes will be collected and transported
offsite on a regular basis by licensed contractors to licenced facilities.
During operation small quantities of “general waste” generated will be collected in covered skip
bins (separate for general waste and recyclables) around the Project Site and collected on a
fortnightly basis by a licenced waste removal contractor.
Inlet Screenings
Inlet screenings have the potential to create an odour nuisance if left uncollected, and impact on
the general hygiene of the Project Site.
Inlet screenings will be dewatered, compressed in a screw press and disposed of to a covered
hopper bin that will be removed weekly from site by a licenced waste contractor.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 84
Grit Removal
There are no significant potential effects from collected grit to the environment. Dewatered grit
will be disposed of to a covered hopper bin that will be removed weekly from site by a licenced
waste contractor.
Sludge/Biosolids
During operation, the Project will continuously be generating biosolid waste as a by -product of
the treatment process. The biosolids from the treatment process will be discharged to self-
loading bins via fully enclosed conveyors. Biosolids will be treated to a Class 2 Biosolids
Classification as defined in the Tasmanian Biosolids Reuse Guidelines, 1999, suitable for reuse
in agriculture, forestry or land rehabilitation (as per current arrangements). Subject to testing
(refer below) this waste will be collected on a daily basis (by a licenced operator) and
transported offsite to existing agricultural reuse sites.
Detailed information about biosolids monitoring, handling and management will be incorporated
into a Sewage Sludge Management Plan (SSMP) for the Project, based on the requirements of
the Tasmanian EPA’s Sewage Sludge Management Plan Guidelines, September 2014.
The SSMP for the Project will include, but not be limited to, the following details:
An overview of sludge treatment and handling at the STP, including transportation details.
Setting of satisfactory controls to ensure sludge contaminant quality will be consistently
maintained;
Identify arrangements and alternative pathways for any sludge that does not meet the
criteria for reuse (including transport to a licenced landfill facility if required) and
Define a sludge monitoring program that fully complies with the requirements of the
Biosolids Reuse Guidelines August 1999.
6.5.4 Monitoring, Review, and Adaptive Management
Management of the solid waste streams generated by the Project will be monitored on a
continual basis during operation. Regular internal audits of the waste management system will
also be undertaken by TasWater to identify any efficiencies that may be gained by alt erations to
solids waste producing processes.
The SSMP developed for the Project will be reviewed regularly throughout the commissioning
phase of the Project.
Commitment 13 A targeted inspection of areas proposed for subsurface
excavations will be undertaken by a Certified Practitioner (Site
Contamination Practitioners Australia) prior to construction to
identify any areas of high risk for land contamination for
subsequent soil testing, classification and management.
Commitment 14 A Sewage Sludge Management Plan (SSMP) will be
developed for the Project.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 85
6.6 Dangerous Goods and Environmentally Hazardous Materials
6.6.1 Performance Requirements
The project must fulfil the requirements of the following legislat ion and policy in relation to
dangerous goods and environmentally hazardous materials:
Australian Code for the Transport of Dangerous Goods by Road and Rail;
Dangerous Substances (Safe Handling) Act 2005 and associated regulations;
Australian Dangerous Goods Code (7th edition); and
Relevant Australian Standards (e.g. AS 1940 and AS 3780).
6.6.2 Project Sources
Construction
Environmentally hazardous materials used during the Project’s construction will include varying
quantities of:
Fuels, oils and lubricants
Paints and solvents (several hundred litres)
Cement and bitumen materials; and
Small quantities of disinfectants and cleaning chemicals.
These materials will be housed in a roofed and bunded facility within the construction compound
(refer Figure 2-1).
Operation
The operational side of the Project will involve the use or production of a number of hazardous
materials.
As outlined in Section 2.6.6 the existing gaseous chlorine system will be decommissioned and
the following chemicals and hazardous substances will be stored in site during operation. Note
that many of these substances are already held on site as part of the existing STP.
Small quantities of lubricating oils for various mechanical components.
Small quantities of diesel (max 250L) associated with the emergency generator. Diesel is
classified as a Class 3 Dangerous Good under the Australian Dangerous Goods Code.
Small quantities of cleaning chemicals and descalents.
Polyelectrolyte (flocculent) in either liquid or powder form. Liquid polyelectrolyte will be
delivered in intermediate bulk containers (IBCs) and powered form polyelectrolyte will be
delivered in pallets of 20 kg bags.
Carbon substrate (liquid sugar solution) stored in a tank approximately 5,000L in size.
Nutrients for the Bio-trickling Filter – The specific nutrient solution is yet to be identified but
small quantities will need to be stored on site.
The liquid sugar solution will be stored within the bulk chemicals store marked on Figure 2-2,
immediately south of the inlet works. This chemical store will be secured, signed, roofed and
bunded in accordance with statutory requirements.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 86
The other chemicals and fuels will be stored in very small volumes within a designed bunded
storage area in the Dewatering Building (Figure 2-2) including restricted access and appropriate
signage.
In addition to the substances outlined above two additional chemicals may need to be stored on
site in the future if phosphorus removal is required as a retrofitted element to the STP. In that
event Magnesium hydroxide liquid (up to 30,000L tank) and Aluminium sulphate (up to 30,000L
tank) could be stored on site in the future. These chemicals are both defined as Hazardous
Substances under the Safe Work Australia classification but are not considered Dangerous
Goods under the Australian Dangerous Goods Code. If required these chemicals would be
stored in the roofed and bunded bulk chemical storage facility south of the inlet works.
The Project will also produce environmentally hazardous waste streams including:
Waste sludge from the digestion process;
Inlet screenings; and
Influent could also be considered an environmentally hazardous waste stream in the event
it was to leak/spill at some stage during the treatment process.
6.6.3 Potential Effects, Management and Mitigation
Ineffective management, including storage, transport, handling and use of dangerous goods
and environmentally hazardous material could lead to significant impacts to environmental
receptors within both the terrestrial and aquatic environments.
General dangerous goods and environmentally hazardous materials
Spills of chemicals and fuels have the potential to occur during construction, which may lead to
environmental impacts to both terrestrial and aquatic environments and may lead to personnel
safety issues on site. The same risks and potential impacts as the construction phase for spills
of chemicals or fuels also apply during operation.
Risks from production of waste sludge and inlet screenings are considered low, as these will be
produced in a controlled environment and removed offsite, as explained in Section 6.5.
General dangerous goods and environmentally hazardous material management and mitigation
for the Project will include the following:
Employees and contractor inductions will include information on dangerous goods and
environmentally hazardous materials, their handling, management and any mitigation
measures that may be applicable in the event of a spill incident, in accordance with the
Australian Standards;
Dangerous goods and environmentally hazardous materials storage, handling and clean up
procedures will be incorporated into the site CEMP for the construction phase and the
Operational EMP (OEMP) during the operational phase.
Fuels, oils, and cleaning chemicals will be stored in dedicated bunded areas with suitable
ventilation, roofs, restricted access and signage.
During the construction phase, storage of dangerous goods will either occur at a designed
location within the Construction Compound or within the existing storage locations at the
current STP site.
During operation, these materials will be stored in permanent onsite storage areas; small
quantities will be in the De-Watering Building and any large quantities (sugar solution) will
be in the designated bulk chemical storage shed near the inlet works (Figure 2 2).
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 87
Fuel for construction machinery and vehicles will be delivered to fully bunded temporary
fuel storage tanks, with refuelling of machinery occurring within the same bunded area.
Larger volumes of cement and bitumen for road works during construction will be delivered
in suitable trucks as required and will not be stored onsite.
Chemical/fuel clean-up kits will be maintained onsite at several locations during
construction and operation.
If ground spills of dangerous goods/environmentally hazardous materials occur, clean-up
will include collection of all material and affected soil in suitable containers (e.g. skip bins,
44 gallon containers, depending on volumes). Contained soils will then be disposed of at
suitable landfill sites by licenced contractors.
All spills will be reported to the site manager immediately and clean up procedures
commenced. Once cleaned, all spills will be recorded along with information on any follow
up actions or procedure modifications to avoid subsequent spills.
All significant spills of dangerous goods/environmentally hazardous materials (including
those to waterways and/or involving >100 litres) will be reported to the EPA within 24 hours.
Handling of chemicals and their subsequent storage to be kept away from drainage lines.
With these mitigation measures in place the residual risks from the presence of general
dangerous goods and environmentally hazardous materials onsite is considered to be low.
Uncontrolled Wastewater Releases
Release of untreated wastewater onsite from leaks/spills presents potential impacts to human
health, air quality (odour), and environmental receptors in the direct area. This includes
receptors exposed in drainage lines/waterways, as covered in Section 6.2 (Surface Water) and
Section 6.8 (Marine and Coastal).
The largest risk to the environment from environmentally hazardous material discharge from the
Project is considered to be the uncontrolled release of poorly treated effluent to the marine
environment through the effluent discharge pipeline. The likelihood of this occurring is
considered highest during extreme storm events where the system cannot sufficiently handle
the high influent loads received (i.e. >7x ADWF) or as a result of malfunctioning components of
the treatment system (particularly the disinfection system). This could also occur as a result of
power or equipment failure.
Impacts of the release of poorly treated effluent to the aquatic environment has the potential to
impact flora and fauna through direct acute/chronic toxicity (e.g. through nitrogenous
compounds) and through secondary impacts resulting from high loads of suspended particulate
matter and localised reduction in dissolved oxygen. There are also the impacts to recreational
users of the marine area from potential algal blooms (resulting from eutrophication of the marine
environment) and harmful pathogens.
As well as releases to the marine environment there is also the risk of leaks from treatment
infrastructure to the terrestrial environment and subsequently to adjacent drainage lines and
recreational areas.
To manage and mitigate the types of potential scenarios mentioned above, TasWater have
developed a Sewage Treatment Plant Contingency Management Manual (CMM) for existing
sites which references Site Response Procedures for various emergency scenarios. The CMM
and associated procedures will also be applicable to the Project.
The CMM and applicable Site Response Procedures are presented in Appendix C and include
the following:
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 88
Excessive Wet Weather
Flood
Spill to Water
Spill to Land
Power Failure
Loss of Disinfection
Fire
Odour
In addition to the CMM, there will be additional Project design features to prevent or minimise
the release of environmentally hazardous wastewater, including:
As outlined in Section 2.5.9 the Blackmans Bay STP is not gravity fed so any power failure
in the area will be managed at pump stations rather than the STP. Localised power failure
at the site only (i.e. not affecting pump stations) will be managed in the short term through
residual storage within the plant itself while a generator is sourced to maintain essential
operations. At this stage it has not been confirmed whether a permanent generator will be
installed on site or a mobile generator kept on standby.
The site and all infrastructure will be subject to a routine maintenance program and in built
to limit potential for equipment failure. In the event of equipment failure there is redundancy
built into the design to provide for back up processing (e.g. multiple process units in most
cases) until any issues can be repaired.
Malfunction sensors have been included in the Project design to detect malfunctioning
treatment infrastructure.
Isolation valves and bypasses have been incorporated in the Project design to allow leaking
infrastructure to be isolated.
With the inbuilt design features, the overall nature of the selected plant and the contingency
measures outlined in the TasWater CMM the residual risk of unplanned discharge of untreated
(or insufficiently treated) effluent is low.
In addition, the risk of such failure is considerably less under the proposed STP upgrade than
the existing plant which is ageing and reaching capacity.
6.6.4 Monitoring, Review, and Adaptive Management
Storage and use of dangerous goods or environmentally hazardous materials, presence of spill
kits and employee awareness will be audited on a monthly basis by operational staff to assess
the suitability of management and mitigation measures in use. Audit and inspection outcomes
that require actioning will be provided to site management for further investigation.
Improvements to storage or use of these materials will be noted in annual environmental reports
to the EPA.
Dangerous goods spills >100 L will be recorded and reported to the EPA, with improvement to
mitigate further spills included in correspondence.
In the case of a large marine discharge event of poorly treated effluent, the following will be
undertaken by TasWater:
Relevant Site Response Procedure to be invoked.
The EPA will be notified.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 89
The cause of the uncontrolled or under-treated discharge will be investigated and
thoroughly reviewed by TasWater to determine whether the incident was avoidable or a
rare circumstantial event (e.g. an unusually large storm).
The results of the investigation will be used to determine if additional mitigation or
management could be incorporated into the Project to either avoid the event reoccurring or
reducing the potential for impact.
Water quality monitoring will be undertaken at incremental distances from the outfall, wi th
sites, number of samples, and monitoring period to be determined based on consultation
with the EPA. The commencement of monitoring will occur as soon as practicable with
regards to mobilisation availability of marine subcontractors and weather conditions.
Commitment 15 All hazardous materials will be stored in suitably
bunded areas in accordance with the relevant guidelines.
Commitment 16 Any spilt waste will be immediately reported to the site
manager and clean-up will occur.
Commitment 17 Inspections and audits of environmentally hazardous
material use and storage will be undertaken monthly.
Commitment 18 Dangerous goods and environmentally hazardous
materials storage, handling and clean up procedures will be
incorporated into the site CEMP for the construction phase and the
Operations and Maintenance Manual during the operational phase.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 90
6.7 Biodiversity and Natural Values
This section considers terrestrial ecological values. Marine values are outlined and assessed
separately in Section 6.8. Surface water impacts are described separately under Section 6.2.
6.7.1 Existing Conditions
The existing STP site and surrounding land were surveyed for ecological values in
October/November 2014 by TasFlora and again in July 2016 by GHD. TasFlora undertook a
vegetation survey and fauna habitat assessment of three discrete areas of potential disturbance
on 14 October 2014 and 6 November 2014. Subsequent to this, the proposed design and
boundaries of disturbance were altered, and an additional ecological survey was undertaken by
GHD on 7 July 2016 to encompass the expanded Project area.
The entire area detailed in Figure 6-11 as the Project Site was surveyed on foot by a GHD
senior ecologist on 7 July 2016. The total area surveyed was approximately 10.2 hectares. The
results of the TasFlora ecological investigation (2014) are provided in full in Appendix B. The
results of the GHD survey are reported below.
The following summarises the salient information from the detailed ecological studies and
addresses all disturbance areas of the Project Footprint.
Vegetation Communities
The study site is comprised of cleared urban areas and agricultural land, with remnant patches
of native vegetation, and planted eucalypts. Three native vegetation communities (one listed as
threatened) and two agricultural, urban or exotic communities were identified and mapped within
the study area by GHD.
Eucalyptus globulus dry forest and woodland (DGL) - Threatened (2.45 ha)
Eucalyptus amygdalina forest and woodland on dolerite (DAD) (0.72 ha)
Allocasuarina verticillata forest (NAV) (0.52 ha)
Agricultural land (FAG) (4.8 ha)
Urban areas (FUR) (1.71 ha)
Eucalyptus globulus dry forest and woodland (DGL) is listed as threatened under the
Nature Conservation Act 2002. It is also listed as a high priority native vegetation
community under the Kingborough Interim Planning Scheme 2015. This community occurs
around the perimeter of the study area and covers approximately 2.45 hectares. Some
areas of this community, in particular along the southern Project Site boundary, are in
reasonable condition, however, the majority of the community is in poor condition with
several declared weed species such as Rubus fruticosus agg. (blackberry) and
Chrysanthemoides monilifera ssp. monilifera (boneseed), along with many introduced grass
species present. A significant number of the E. globulus trees along the western boundary
of the Project Site appear to have been planted rather than naturally seeded.
Eucalyptus amygdalina forest and woodland on dolerite (DAD) occurs near the
western boundary of the study area and is a transitional community into the area mapped
as Agricultural Land (FAG). The DAD is a highly modified version of what would be
considered a typical example. There were occasional E. amygdalina trees with E. ovata
occurring in the less well drained areas. The understorey is very sparse with a ground layer
of introduced grass species that appear to be regularly mown.
Allocasuarina verticillata forest (NAV) - This community occurs near the coastal fringe of
the study area and occupies approximately 0.52 hectares. It is a typical example of the
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 91
community type with Allocasuarina verticillata as the dominant canopy species with the
occasional emergent Eucalyptus globulus tree with a sparse understory of native grasses.
The remainder of the Project Site is a mosaic of agricultural and developed land.
Figure 6-11 shows the location of vegetation communities within the Project Site. On this figure
the mapped trees are those of Eucalyptus globulus and Eucalyptus ovata but the figure does
not show point locations for all trees and shrubs occurring on site. E.globulus and E.ovata were
specifically targeted for individual mapping due to their habitat value for the listed swift parrot
(refer below).
Threatened Flora
According to the Natural Values Atlas (DPIPWE 2016) one threatened flora species has
previously been recorded within 500 m of the study area, Austrostipa bigeniculata
(doublejointed speargrass), which is listed as rare under the TSPA. An additional 19 species
have previously been recorded within 5 km of the site.
No threatened flora species were observed during either of the field survey events (TasFlora
2014, GHD 2016).
The GHD survey was conducted in winter which is considered a sub-optimal time of the year for
survey of flowering plants, in particular it is not a suitable time to survey annual grasses.
However, when considering the condition of the potential habitat available, it is considered
unlikely that threatened species have been over looked. In addition, the TasFlora survey was
conducted in October and November which is a suitable time of year for many seasonal
flowering species and did not find any threatened species either.
Threatened Fauna
No threatened fauna listed under the TSPA or EPBC Act were recorded on site during either the
2014 (TasFlora) or 2016 (GHD) site surveys. No targeted fauna surveys have been undertaken
at the site.
A small number of threatened fauna identified by desktop review (refer to the Natural Values
Atlas report in Appendix B) may occur on site. The key species identified during desktop
research as ‘possibly’ occurring but not detected on site, are summarised as follows (a full list of
species potentially occurring on site and an assessment of likelihood is provided in Appendix B
(TasFlora 2014):
Swift Parrot (Lathamus discolor)
The general area has a high number of Eucalyptus globulus trees along with scattered
individuals of E. ovata which may provide foraging and possibly nesting options for the swift
parrot (Lathamus discolor). Four eucalypts (three E. globulus and one E. ovata) had
observed hollows which may provide nesting habitat for the species. The locations of these
are detailed in Figure 6-11. There are known nesting and foraging locations within 5 km of
the study site, however, there are no recorded observations of the species within the study
area. A number of E. globulus trees had a DBH of greater than 70 cm which in the future
are likely to provide more hollows that may be utilised for nesting.
Eastern Barred Bandicoot (Perameles gunnii)
The Project Site includes potential foraging habitat for this species, occurring amongst the
eucalypt and agricultural areas mapped. Diggings were observed during the field
assessment that are likely to have been made by a bandicoot species however it is quite
possible that at least some if not all of these bandicoot signs were made by the non-
threatened southern brown bandicoot (Isoodon obesulus).
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 92
Although the potential for this species remains, there was no confirmed evidence observed
and the Project Site contains limited and lower quality habitat than that available in the
vegetated areas directly adjacent to the site.
Eastern Quoll (Dasyurus viverrinus) - TSPA not listed, EPBC Endangered
The Eastern quoll is now listed as endangered on the EPBC Act but is not listed on the
TSPA.
No Eastern quolls were detected during the site assessments; however, the Project Site
does provide some potential foraging habitat. The Site is unlikely to provide key
denning/nesting habitat, and the potential habitat available is considered low quality in
comparison to the habitat available in the directly adjacent land to the south of the Project
Site.
General Fauna Habitat Values
The study area provides some habitat for fauna species such as birds, bandicoots, wallabies,
and possibly fauna utilising burrows/dens. However, due to the highly modified nature of the site
and its proximity to densely populated residential areas it is not considered prime habitat. In
addition, there are large areas of alternative habitat adjacent to the study area that are of much
higher quality.
An animal burrow was recorded close to the creek near the southern boundary (refer Figure
6-11). Without undertaking a targeted survey (such as a camera survey) it cannot be confirmed
if the burrow is in use or the species that may be utilising the burrow. There were no scats or fur
evident that may provide more conclusive confirmation. Given the proximity of the burrow to
residential development and the existing STP, and a lack of suitable surrounding foraging and
sheltering habitat, it is considered unlikely it would be utilised by threatened species such as the
Tasmanian devil (Sarcophilus harrisii). The burrow is outside of the Project Footprint.
The Project Site contains limited freshwater habitat, although a drainage line is present in the
north-eastern region of the study area, and a minor creek is located at the southern boundary of
the site. These water courses are discussed in further detail in Section 6.2, Surface Water
Quality. These features are unlikely to provide habitat for threatened freshwater fauna species
due to their limited size and ephemeral nature.
Weeds and Pathogens
Six of the plant species recorded within the study area are listed as declared weeds under the
Tasmanian Weed Management Act 1999. These species are:
Ulex europaeus (gorse)
Rubus fruticosus aggregate (blackberry)
Genista monspessulana (montpellier broom)
Chrysanthemoides monilifera subsp. monilifera (boneseed)
Erica lusitanica (spanish heath)
Foeniculum vulgare (fennel)
The above species were recorded as scattered individuals or small patches, generally
distributed in the vicinity of already disturbed areas, associated with the existing STP site.
No evidence of the pathogen Phytophthora cinnamomi was observed within the Project Site
area nor is the site particularly susceptible.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 93
Geoconservation Sites
There is one geoconservation site mapped along the eastern boundary of the Site (Figure 5-3).
This site is the Blackmans Bay Dolerite Contact and is related to coastal exposure of dolerite
along the foreshore. The geoconservation site lies outside of the proposed Project Footprint and
is not expected to be impacted by the Project.
The Kingborough Planning Scheme also mentions two geoheritage features (refer Section
6.10), namely the Blackmans Bay Geoheritage Site and Blackmans Bay Geological Monument.
The address given for these features is Fossil Drive and they are presumed to be part of the
Fossil Cove Conservation Area, approximately 500 m south of the Project Site. No impacts will
occur to these features.
Reserves
There are no reserves within the Project Site.
There are two informal reserves immediately adjacent to (but outside of) the Site on the coast,
one to the north and another to the south (Figure 5-3). There is also a formal reserve, the Fossil
Bay Conservation Area, approximately 500 m south of the Project Site.
6.7.2 Performance Requirements
The key legislation relevant to protecting flora and ecological communities of relevance to this
project are:
Environment Protection & Biodiversity Conservation Act 1999 (EPBC Act)
Tasmanian Threatened Species Protection Act 1995 (TSPA);
Forest Practices Act 1985 and associated regulations;
Weed Management Act 1999; and
Nature Conservation Act 2002.
In addition to the above legislation assessment of the project also considers the National
Strategy for the Conservation of Australia’s Biological Diversity, the draft Tasmania’s Nature
Conservation Strategy and the Threatened Species Strategy for Tasmania.
Key performance requirements include:
Avoid and/or mitigate against potential impacts to native flora and ecological communities,
particularly species and communities listed under above legislation;
Where possible avoid impacts to significant and listed native fauna and their habitats;
Where avoidance is not possible, establish mitigation measures to ameliorate impacts and
obtain necessary approvals for impacts to protected species; and
Minimise, control and eradicate any declared weed incursions arising from the Project.
6.7.3 Potential Effects
Vegetation Communities
The main impacts on flora and vegetation communities are through vegetation clearing
associated with construction of the new infrastructure.
The anticipated direct impact to vegetation communities is documented in Table 6-7, which
shows the approximate area of impact for each of the vegetation communities found on site.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 94
Table 6-7 Vegetation Communities Impacted by the Development
Vegetation Community Total Present within
Study Area (ha)
Total Impacted by
Proposed Works (ha)
DGL 2.45 0.03
DAD 0.72 0.00
NAV 0.52 0.00
FAG 4.8 1.45
FUR 1.71 1.46
Total all Communities Impacted 2.94 ha
Of the total areas impacted, the majority will be agricultural land (1.45 ha) and urban areas (1.46
ha) rather than native vegetation.
A very small proportion of the threatened native vegetation community Eucalyptus globulus dry
forest and woodland (DGL) present on site will be impacted by the proposed works
(approximately 1.2%), with the majority protected through careful siting of infrastructure and
laydown areas.
The other native vegetation communities on site (DAD and NAV) will not be impacted by the
proposed works.
The overall impact on vegetation communities is not expected to affect the viability of these
communities in the region.
There is no proposal to clear vegetation within 10m of any waterways or along the coastal area
east of the existing STP.
Threatened Flora
No threatened flora was detected during the site surveys (which were generally conducted at
suitable times of year) and therefore there are no impacts to threatened flora anticipated.
Weeds and Pathogens
The proposal has the potential to spread existing weeds within or outside of the site as well as
introducing new weeds or pathogens as a result of construction or operational vehicular and
materials movement. These risks are to be managed in accordance with the Weed and Hygiene
Management Plan as outlined below.
Threatened Fauna
As identified in Section 6.7.1, the site provides possible habitat for a small number of fauna
species listed under the EPBC Act and TSPA as well as providing potential habitat for a range
of non-listed native fauna.
Vegetation clearance, in particular individual E.globulus trees, has been identified as the
primary potential impact to threatened fauna. The swift parrot (Lathamus discolour), Eastern
barred bandicoot (Perameles gunnii) and Eastern quoll (Dasyurus viverrinus) may all utilise the
site, most likely for foraging. With the exception of a small area of DGL to be removed, the quoll
and bandicoot will not be impacted by a loss of reasonable quality foraging habitat. Impacts to
these species are expected to be negligible.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 95
A total of 252 E. globulus trees were recorded within the study area. Up to 31 of these may be
impacted, of which approximately 21 are juveniles. No hollow bearing trees will be impacted by
the works. A replanting proposal (at a ratio of 3:1) is discussed below in 6.7.4 to mitigate this
impact. With replacement planting in place and the mitigation below implemented, any residual
impact on the swift parrot is not expected to be significant.
There will be a small increase in vehicle activity to the site during the construction period,
however the overall traffic volumes are relatively low and will be during daylight hours therefore
increased risk of fauna roadkill is considered to be limited.
There are no works proposed within 10 m of any waterways.
Geoconservation Sites
There are no impacts anticipated to the identified geoconservation sites as they all fall outside of
the development footprint.
Reserves
There are no impacts anticipated to the Reserves identified north and south of the site as no
development will occur near these reserves and all drainage from the Project Site is directly into
the Derwent Estuary not the reserves to the north and south.
6.7.4 Management and Mitigation
The most significant mitigation for impacts to threatened vegetation communities and native
fauna is restricting the clearance of native vegetation wherever possible. This has already been
applied as part of the design process (aiming to site infrastructure on cleared areas where
practical) and the refinement of ancillary features such as the Construction Compound and site
fencing which have been modified to limit ecological impacts.
The mitigation measures outlined below will contribute to protecting both vegetation and native
fauna, and include keeping impacts to already disturbed land where possible, avoiding ancillary
activities in native vegetation and applying weed controls.
Proposed mitigation measures include:
At the commencement of construction, the Construction Compound and the Project Site
will be fenced as illustrated on Figure 2-1. This will protect against fauna inadvertently
falling into open trenches or accessing hazardous area. It also delineates the area of
impact for the Project, which will be restricted to the construction and operational fenced
areas (with additional exclusion zones applied within this area as per the following point).
The fence line will be microsited to avoid individual eucalyptus trees.
Eucalyptus trees to be impacted (removed) by the works will be clearly marked on site and
all other eucalypt trees will be retained.
Temporary high-visibility fencing will be erected around the DGL forest to be retained, to
avoid impacts to the community.
Temporary high visibility fencing will also be erected around the eucalypt trees to be
retained within the STP fence line (refer Figure 6-11) to protect these from accidental
clearance.
All machinery, equipment and personnel will be kept outside of the fenced area protecting
the DGL community and other eucalypts during construction.
In recognition that a number of eucalypt trees will be removed as part of the works, a
landscaping plan has been developed, which includes replacement planting of E. globulus
and/or E. ovata trees elsewhere on the property (refer Landscaping Plan in Appendix A).
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 96
For every mature E. globulus/E.ovata tree removed, 3 new E. globulus/E. ovata seedlings
will be planted.
Maintenance (e.g. water, replacement planting) of all E. globulus and/or E. ovata trees
planted will be undertaken for a minimum of five years.
All ancillary activities during construction (e.g. materials stockpiling, site administration,
parking areas) will be within already disturbed land either within the delineated Construction
Compound or within already cleared areas within the proposed fenced STP site.
Areas that are disturbed temporarily (e.g., for access during construction) will be
rehabilitated (back to their original condition) as soon as practicable.
In the unlikely event that threatened flora species are detected up to or during the time of
construction, all practical efforts will be made to avoid such species and if avoidance is not
possible then a permit to take under the TSPA will be sought prior to any impact.
A weed hygiene plan will be developed (to be incorporated into CEMP) and adhered to
during the construction process to prevent the spread of declared weed seed to other sites,
and to prevent the introduction of new declared weeds and soil based pathogens to the
site. The following broad management principles and hygiene protocols will be included:
– Undertake pre-construction weed control with the aim of eradicating the identified weed
locations within the main STP works area to minimise potential for spread during
works.
– Ongoing weed control during construction (6 monthly inspections and control).
– Prior to and after working on site, all machinery will be cleaned following the general
washdown procedure and machinery checklists detailed in the Tasmanian washdown
guidelines for weed disease and control (Rudman et al 2004) to ensure it is free from
weed seeds or soil bearing pathogens. These checklists include the removal of soil,
mud etc. and the blowing out of any dry plant material. A wheel wash will be provided
at the Construction Compound.
– Bare areas of soil remaining after excavation and topsoil stockpiles will be regularly
monitored for new weed germinants and, when required, control measures adopted in
a timely fashion.
6.7.5 Monitoring, Review, and Adaptive Management
The following vegetation, weed and pathogen monitoring is proposed:
An initial pre construction weed treatment will be undertaken, followed by 6 monthly weed
surveys during construction, and additional weed control applied as required.
A post construction weed, pathogen and revegetation success survey will be undertaken at
the completion of construction, with follow up surveys completed annually thereafter for a
period of 5 years.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 97
Commitment 19 All areas of DGL community outside of the immediate
development footprint will be flagged with temporary high visibility
fencing and protected during construction works.
Commitment 20 All eucalypts outside of the immediate development
footprint will be flagged with temporary high visibility fencing and
protected during construction works.
Commitment 21 Replacement planting will be undertaken for all mature
Eucalypt trees removed at a ratio of 3:1 as part of the Landscaping
Plan
Commitment 22 Weed and hygiene management will be incorporated
into the site CEMP following the principles outlined in this DPEMP.
Commitment 23 Annual monitoring for the first five years of the
landscaped area to assess success of tree growth, weed invasion
and replacement plantings.
Commitment 24 An initial pre construction weed treatment will be
undertaken, followed by 6 monthly weed surveys during
construction, and additional weed control applied as required.
Commitment 25 A post construction weed, pathogen and revegetation
success survey will be undertaken at the completion of
construction, with follow up surveys completed annually thereafter
for a period of five years.
FAG
DGL
FUR
NAV
DAD
DAD
FUR
DGL
FAG
526,600
526,600
526,800
526,800
5,237,
200
5,237,
200
5,237,
400
5,237,
400
5,237,
600
5,237,
600
G:\32\18107\GIS\Maps\MXD\3218107_007_Figure6-1_Ecology_RevC.mxd
0 40 8020
MetresMap Projection: Transverse Mercator
Horizontal Datum: GDA 1994Grid: GDA 1994 MGA Zone 55
© 2016. Whilst every care has been taken to prepare this map, GHD (and DATA CUSTODIAN) make no representations or warranties about its accuracy, reliability, completeness or suitability for any particular purpose and cannot accept liability and responsibility of any kind (whether in contract, tort or otherwise) for any expenses, losses, damages and/or costs (including indirect or consequential damage) which are or may be incurred by any party as a result of the map being inaccurate, incomplete or unsuitable in any way and for any reason.
TasWaterBlackmans Bay STP DPEMP
Vegetation & Ecological Values
Job NumberRevision B
32-18107
28 Jul 2016Date
Data source: DPIPWE (imagery, cadastre), TasWater (infrastructure design), GHD (vegetation communities, points). Created by: jtoregan
2 Salamanca Square Hobart TAS 7000 Australia T 61 3 6210 0600 F 61 3 6210 0601 E [email protected] W www.ghd.com.au
Paper Size A3
LEGENDFauna Habitat Values
Bandicoot diggingsBurrow
WeedsBlackberryBoneseedSweet BriarSpanish Heath
Eucalypt SpeciesE. globulus (impacted)E. globulus (retained)E. globulus (retained - hollow habitat)E.ovata (retained)E.ovata (retained - hollow habitat)Ecology study boundary
Proposed DevelopmentNew fenceExisting fenceThe project siteConstruction CompoundInfrastructure footprintCut / fill footprint
Vegetation Communities (GHD Survey, June 2016)Dry eucalypt forest and woodland
Eucalyptus amygdalina forest and woodland on dolerite (DAD)Eucalyptus globulus dry forest & woodland (DGL)
Non-eucalypt forest and woodlandAllocasuarina verticillata forest (NAV)
Agricultural, urban and exotic vegetationAgricultural land (FAG)Urban Areas (FUR)
Drainage lineWaterwayCadastre
Figure 6-11
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 99
6.8 Marine and Coastal
This Section outlines the potential effects of the Project on the marine environment, namely
release of treated effluent via the existing outfall.
As the Project does not involve any physical works on the existing outfall or any part of the site
on the coastal (eastern) side of the existing boundary fence, there are no other coastal impacts
anticipated.
6.8.1 Existing Conditions
Broader Derwent Estuary Environment
The Derwent Estuary in south-eastern Tasmania stretches from the upper head waters at New
Norfolk some 52 km to the mouth of the estuary at the Iron Pot Light (DEP, 2015). The Project is
located on the western shore towards the mouth of the estuary.
The estuary undergoes considerable physical change from the narrow headwaters at New
Norfolk to the estuary mouth, with the widest point at the mouth extending for approximately 5-6
km. Depths range from 3-6 m in the upper reaches of the estuary, to depths from 10-30 m in the
mid to lower regions; a maximum depth of 44 m is located around the Tasman Bridge, the
location of the Lake Illawarra shipwreck.
The upper to mid reaches of the estuary are generally stratified to some degree with a tidal salt
wedge present with the freshwater inputs from the catchment; this is more pronounced in the
very upper reaches. The lower reach around the mouth of the estuary is well mixed and can
generally be considered a marine environment in the areas concerned with the Project; however
partial seasonal stratification does still occur to some degree.
Water temperatures in the Derwent Estuary generally ranges from 12-22 °C and prevailing
winds are from the south-west / north-west depending on time of day.
Tidal currents are generally low in the estuary, with a typically diurnal tidal cycle with a tidal
range of 0.3 to 1.6 m; tidal currents are generally in the 0.1 - 0.2 m/sec range. Flushing periods
for the estuary average approximately 12 days (DEP, 2015).
During summer months, the marine waters entering the estuary are dominated by flows of
nutrient poor sub-tropical waters from the east coast of Tasmania. During the winter months,
marine flows are dominated by nutrient dense sub-Antarctic waters, significantly altering the
water quality dynamics of the estuary during these periods.
Water quality in the estuary obviously varies by location, but is considered relatively good
overall considering the anthropogenic discharges into the estuary. There are 11 STP outfalls
that discharged approximately 42 ML/day into the estuary during 2013-14 (DEP, 2015), of which
Blackmans Bay contributed around 4 ML/day.
Along with treated effluent there are also considerable waste contributions to the system from
the two major industrial complexes along the river, namely the Nyrstar Zinc smelter to the north
of Tasman Bridge and the Norske Skog pulp mill near New Norfolk. Inputs from the smelter
include heavy metals, particulates, sulphur oxides and to a lesser degree nutrients. Inputs from
the pulp mill include organic matter, particulate matter, hydrocarbons and wood resins (DEP,
2015). Additional pollutants also enter the Derwent system through stormwater run-off and
groundwater pathways. The key pollutants of concern for the estuary are nutrients and heavy
metals.
Overall, the Derwent Estuary is not a particularly diverse ecosystem, with dominantly soft
sediment habitat throughout the estuary, with silty mud in the upper to mid reaches, becoming
sandier in the higher energy areas around the mouth of the estuary. There are also areas of
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 100
rocky outcrops towards the mid to lower reaches of the estuary where ecological diversity
increases. Several introduced species dominate the estuary, including the Northern pacific
seastar (Asterias amurensis), New Zealand screwshell and the Pacific Oyster. The Spotted
Handfish is one particularly sensitive endemic species that inhabits the estuary around the mid
to lower reaches, listed as Critically Endangered under the EPBC Act.
Estuary Mouth and Outfall Area
As the major potential impact of the Project to the Marine and Coastal environment is concerned
with the STP effluent discharge, the existing conditions of this section are focused on the
environment at the estuary mouth and surrounding the outfall.
As described previously, the effluent outfall pipeline stretches approximately 600 m offshore in
an easterly direction from the Project site. The 80 m diffuser at the terminus of the pipeline sits
in 13-14 m of water. The diffuser includes 21 ports (alternating to the north and south) with an
80 mm nozzle diameter, spaced at 4 m intervals; the terminal port is directed to the east.
As part of the monitoring program for the effluent pipeline, which was extended in 2010 (see
DPEMP from CEE, 2009a), annual water quality and benthic infauna monitoring has occurred. A
baseline ecological assessment was also undertaken prior to the construction of the pipeline in
late 2009 (CEE, 2009b).
The dominant habitat in the area towards the mouth of the estuary and the Project area is sandy
sediment. Along the shoreline on the western side of the estuary, the substrate changes to a
rocky reef / boulder dominant habitat, an extension of the rocky shoreline. There are also
subtidal patches of isolated reef throughout the mouth of the estuary.
Specifically, around the outfall pipeline area, a subtidal boulder reef extends some 200 m
towards the middle of the estuary from the shoreline, before transitioning to a sand dominant
habitat with patchy areas of boulder reef (CEE, 2009b), and finally to a sandy expanse.
The sandy habitats in the estuary mouth area are not especially biodiverse areas, with the
dominant flora and fauna including a range of sparsely distributed algae (generally turfing or
drift algae) and epifauna, including native and introduced seastars and ascidians. The sandy
habitat along the eastern shore, and to a lesser degree on the western shore of the mouth of
the estuary provides important habitat for the EPBC listed Spotted Handfish (Critically
Endangered), with populations residing in lower energy sandy bays around the lower estuary
(including around Bellerive Bluff, Droughty Point and Halfmoon Bay on the eastern shore and
Nutgrove Beach on the western shore). Flathead, flounder and various skates are common
demersal fish in the sandy habitat areas, with common pelagic species including Australian
Salmon, silver trevally and jack mackerel (DEP, 2015).
The rocky shorelines of the lower Derwent Estuary, including the Project area, support a more
diverse range of flora and fauna, typical of the temperate rocky reef habitat around Tasmania.
This includes a variety of species of algae, including introduced and native species. Brown and
green algae generally dominate the rocky substrata around the outfall pipeline (e.g. Ecklonia
radiata, Lessonia corrugate, Caulerpa sp.) (CEE, 2009b, DEP, 2015), along with foliose red
algae (Plocamium species dominate near the outfall) and encrusting coralline algae
(predominantly Feldmania). Of specific importance to the Project is the presence of giant kelp
(Macrocystis pyrifera) in the vicinity of the outfall (discussed further in more detail below). This
species can grow up to 30 m in height from the substrate as it reaches for the surface and forms
forested canopies. Giant kelp forests were once common throughout the lower reaches of the
estuary, but have become less so, most likely due to climatic and anthropogenic induced
changes in the environment.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 101
A variety of sessile and motile invertebrates inhabit the rocky coastline and subtidal reefs
around the outfall, including various species of encrusting and solitary ascidians and sponges,
anemones, zoanthids, seastars, crabs and molluscs (including the commercially important
blacklip abalone). The area also supports communities of the southern rock lobster,
recreationally fished in the area.
A number of fish species also inhabit the rocky reef areas around the outfall, consistent with
similar habitat throughout southern Tasmania. Common fish species include the Banded
Morwong, Bastard Trumpeter and various species of wrasse.
Potential Sensitive Receptors
There are several Federally or State listed marine species or communities that have the
potential to inhabit, or are known to inhabit the area that may be affected by the effluent outfall.
Spotted Handfish (Brachionichthys hirsutus)
When undertaking projects in the Derwent, the potential presence of the Spotted Handfish
(Brachionichthys hirsutus), listed as endangered under the TSPA and Critically Endangered
under the EPBC Act, must be considered. Spotted handfish populations are found in sheltered
bays around the Derwent Estuary and can occur in a depth range from 2 - 30 m, on
unconsolidated substrate (ranging from shell grit to finer sands), but are more common in the
estuary in shallower water from 5 - 10 m (DEP, 2015). The area that may be affected by the
Project (i.e. from the effluent plume), although containing soft sediments in some areas, is not a
known location for Spotted handfish; with only seven known population areas around the
Derwent Estuary (five on the eastern shore and two on the western shore). The site of the
outfall is likely to be too high in energy for the species, as it is subject to open ocean swells. No
Spotted handfish were found on any of the baseline ecological transects surveyed in 2009 as
part of the pipeline extension DPEMP (CEE, 2009b). The closest population to the Project is
likely to be the Halfmoon Bay population on the opposite shoreline to the Project. Therefore, this
species is not considered to be present within the influence of the Project area.
Gunn’s Screw Shell (Gazameda gunnii)
Surveys for the native Gunn’s Screw Shell (Gazameda gunnii), listed as vulnerable under the
TSPA, were undertaken as part of the baseline survey for the effluent pipeline extension (CEE,
2009b). This species has become rare in shallower Tasmanian waters, where it has been
severely outcompeted by the introduced New Zealand screw shell (Maoricolpus roseus). Grab
samples of sediment where taken by CEE (CEE, 2009) around the outfall location, with no
native screw shells identified from the samples. It is considered unlikely that Gazameda gunnii
are present in the area that may be affected by the Project.
Giant Kelp Forests (Macrocystis pyrifera)
As mentioned above, there is a giant kelp forest (Macrocystis pyrifera) present around the
outfall location. When certain criteria are met, forests of Macrocystis are considered under the
EPBC Act as the threatened ecological community titled ‘Giant Kelp Marine Forests of South
East Australia’, listed as ‘Endangered’ under the Act.
The forest was surveyed as part of the baseline study for the outfall extension in 2009 (CEE,
2009). The kelp forest extends several hundred metres in either direction along the shoreline
from centreline of the effluent pipeline. In the 2009 baseline survey of the area, Macrocystis first
appeared around 90 m from the shoreline and extended out to 200 m into deeper waters of 7-
8 m. The forest spread laterally along the coast several hundred metres in 3-8 m of water depth.
The densest area of the kelp forest was found to occur in the 3-6 m depth range (CEE, 2009).
In 2015 CEE undertook an ecological risk assessment to determine whether this kelp forest met
the EPBC Act listing criteria and therefore should be considered part of the Giant Kelp Marine
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 102
Forests of South-East Australia (an EPBC Act Listed Threatened Ecological Community). CEE
(2015)6 found that the Giant Kelp forest at Blackmans Bay fulfils most of the criteria to be
considered part of the threatened ecological community, however it does not occur in water
more than 8 m deep (one of the defining characteristics). They therefore concluded the
Blackmans Bay Giant Kelp Forest was not part of the EPBC Act listed Giant Kelp Marine
Forests of South-East Australia. Although the kelp forests have been assessed by CEE as not
meeting the EPBC Act listing criteria, they remain an important ecological feature and have
been considered in the impact and mitigation sections in this DPEMP.
As noted previously the Blackmans Bay STP outfall was extended in 2010 to improve dilution of
the effluent. As part of the approval process for the extension of the original outfall, it was
recognized that nutrients from the then existing Blackmans Bay outfall discharge was likely to
be supplementing the high nutrient requirements of the macrocystis forest to a large degree. In
light of this, three diffuser ports were included in the nearshore section of the outfall extension to
enable the continued ‘fertilisation’ of the forest.
The results of the referral assessment are discussed in detail in Section 7- EPBC Act
Assessment.
Human Receptors
The shoreline immediately surrounding the existing outfall is not commonly used for shore
based fishing or swimming due to its isolation and difficult access, however recreational diving
or fishing from boat is undertaken along the shoreline.
There are no aquaculture leases within the estuary, with the nearest leases being those to the
south within North West Bay and along Bruny Island.
The Tinderbox Marine Reserve extends west from Tinderbox Bay around Passage Point to
approximately 1.5 km south of the existing outfall, and 300 m offshore. This reserve is used
regularly for recreational diving.
Water Quality
Water quality in the area surrounding the effluent outfall has been assessed on an annual basis
by TasWater following the extension of the outfall in 2010. Complimenting this is the extensive
water quality monitoring program undertaken as part of the Derwent Estuary Program, with four
monitoring sites in the vicinity of the Project.
Ambient water quality is summarised in the following sections and is interpreted from the closest
DEP monitoring site to the Project area (site B1 from DEP, 2015, which lies a little under 1km
south of the Project area) from the DEP monthly monitoring results from the State of the
Derwent 2015 report (covering January 2009 - December 2013) and from more recent data
collected from the DEP for the period July 2013 - July 2015, which was made available to
TasWater for the Project. Results are compared to the ANZECC (2000) Physical and Chemical
Stressor Default Trigger Values, which are to be interpreted with caution owing to the absence
of Tasmanian marine and estuarine water quality data in the dataset used in the development of
the trigger values, as stated in the Guidelines (ANZECC, 2000).
Physicochemical Parameters
Salinity in the area of the Project is for the most part unstratified, with concentrations
throughout the water column at a median value of 33.63 PSU (2013-2015 data). However,
stratification does occur sporadically throughout the year following large freshwater inputs
6 CEE 2015, Internal memo - Blackmans Bay STP Upgrade – Assessment of effects on Giant Kelp and North West Bay ecosystem, January 2015
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 103
from the catchment after large rain events, dropping salinity in the top layers of water to as
low as ~26 PSU (2013-2015 data).
Dissolved oxygen is generally high in the area around the Project, with a median
concentration > 97% saturation (2013-2015 data). Oxygen concentrations are generally
slightly higher at the top of the water column.
The median pH for the 2013-2015 period ranged from 7.85 - 8.24; with a median result of
8.05, typical of marine waters. There are no significant pH fluctuations with depth of water
column.
Water temperatures range from approximately 10°C in winter months to 18°C in summer
months (2013-2015 data).
Turbidity was generally very low in the area around the Project site, with samples rarely
exceeding 5 NTU, with a median value generally <1 NTU around lower estuary sites (DEP,
2015).
Site specific monitoring around the outfall location commissioned by TasWater (CEE,
2015a) correlates well with the abovementioned physiochemical attributes, as can be
expected given the proximity to the DEP monitoring site.
Nutrients and Algae
Total nitrogen is at times elevated in the Derwent Estuary when compared to the ANZECC
(2000) Physical and Chemical Stressor default trigger value (300 µg/L). This is the case for
most of the middle to lower estuary. Median values have historically been below the trigger
values though. As the estuary system is seasonally dynamic with respect to nutrient inputs,
large variations occur throughout the year. Higher nitrogen loading in the estuary system is
known to occur during winter months as a result of inputs of nutrient rich waters from the
Southern Ocean. TasWater monitoring undertaken found total nitrogen concentrations
around the outfall site ranged from 7 µg/L in November 2013 to 590 µg/L during the
baseline survey in September 2009.
Median levels of oxides of nitrogen (nitrite/nitrate) are below ANZECC (2000) default
stressor trigger values at the nearest DEP monitoring site to the Project, as outlined in
State of the Derwent Estuary 2015 (DEP, 2015); however, concentrations do exceed the
trigger value at times, generally during winter months, owing to the natural flux of nutrients
in the system, as mentioned above. Concentrations were found to be generally lower in
surface waters than bottom waters.
NHx (ammonia and ammonium) concentrations at the DEP monitoring site B1 did not
exceed stressor trigger values from 2009 - 20013 (DEP, 2015), with a median
concentration from 2013-2015 DEP data of 5 µg/L.
From the available data, organic nitrogen compounds appear to be the dominant proportion
of the total nitrogen in the estuary (e.g. particulate organic matter including phytoplankton
and suspended solids).
Total phosphorus concentrations are above ANZECC Guideline (2000) stressor trigger
values from the mid estuary to the well flushed lower parts also, suggesting that the
ANZECC stressor triggers are not appropriate for the estuary for total phosphorus (DEP,
2015).
Reactive phosphorus concentrations, as for total phosphorus, have elevated median values
above the ANZECC Guideline (2000) stressor value from the mid to lower estuary. This
may be a result of naturally higher concentrations throughout the estuary, however
concentrations appear to decline towards the mouth of the estuary according to the DEP
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 104
data, suggesting anthropogenic sources in the middle estuary may be contributing to the
concentrations observed.
Chlorophyll-α concentration is used as a proxy indicator of the concentration of
phytoplankton in an aquatic environment. At the DEP monitoring site closest to the outfall,
values have not exceeded ANZECC Guideline (2000) trigger values over the 2009-2013
period (DEP, 2015), suggesting phytoplankton blooms are not a significant issue towards
the mouth of the Derwent Estuary. Nitrogen is believed to be the likely limiting nutrient in
the growth of phytoplankton in the lower portions of the estuary (DEP, 2015), given the
ratios of nitrogen to phosphorus compounds relative to the Redfield ratio.
Metals
There have historically been large inputs of heavy metals into the Derwent Estuary as a result of
industrial water discharges, most significantly from the zinc smelter in the middle section of the
estuary (Lutana) and the paper mill at Boyer.
The most significant heavy metal still affecting water quality in the estuary is zinc; which
continues to be monitored regularly by the DEP. Concentrations around the Project area are
generally below the ANZECC (2000) 99% species protection toxicity threshold triggers;
concentrations exceeding ANZECC (2000) trigger values are most prominent in the middle
estuary area, most likely as a result of legacy groundwater intrusion from the zinc smelter site
into the waterway.
6.8.2 Performance Requirements
The key legislation, policy and guidelines of relevance to marine and estuarine management in
Tasmania are the:
Water Management Act 1999
State Policy on Water Quality Management 1997 (Water Policy)
Environment Protection & Biodiversity Conservation Act 1999 (EPBC Act)
Tasmanian Threatened Species Protection Act 1995 (TSPA)
Under the Water Policy, the EPA sets a range of environmental values of an aquatic area to be
protected, referred to as Protected Environmental Values (PEVs). For the receiving environment
of the effluent discharge pipeline at Blackmans Bay, the following PEVs were identified (from
EPA, 2003):
Derwent Estuary Area 2 - Lower Derwent Estuary (Tasman Bridge to Tinderbox/South Arm)
A. Protection of Aquatic Ecosystems
i. Protection of modified (not pristine) ecosystems from which edible fish, crustaceans
and abalone, but not other shellfish harvested
B. Recreational Water Quality and Aesthetics
i. Primary contact water quality
ii. Secondary contact water quality
iii. Aesthetic water quality
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 105
6.8.3 Potential Effects, Management and Mitigation
There is no proposal to change the existing outfall in any way; its existing orientation and
configuration will remain unchanged as a result of the Project. The following assessment relates
to the impact of the proposed change in effluent quality and quantity to be discharged from that
outfall, with no physical changes to the outfall proposed at all.
The proposal does however involve an overall increase in treated effluent to be discharged from
the STP, as well as changes (predominantly improvements) to the treated effluent quality from
the upgraded STP. Details of the proposed quality and quantity from the upgraded STP is
provided in Section 2.4.
Toxicity to Marine Species
Discharge of toxicants to the aquatic environment at concentrations above recommended limits
defined in the literature (e.g. ANZECC (2000) Guidelines) have the potential to induce acute or
chronic effects on both flora and fauna species.
Known toxicants within the Project effluent stream include ammonia and nitrate only.
Investigations on industrial waste streams currently accepted within the existing catchments to
be associated with the Project have not identified any metals or other contaminants of concern
(Section 2.3.2).
Ammonia is generally considered more toxic than nitrate in the marine environment, with no
specific guidelines for nitrate in marine or estuarine waters set in the ANZECC (2000)
Guidelines (default trigger values for freshwater ecosystems are used as a proxy). In order to
define the trigger value for ammonia in the mixing zone study, 80th percentile background data
from the Derwent Estuary Program was assessed from four nearby sites, along with the
ANZECC Guideline limits. The ANZECC (2000) Guideline default trigger value for 95% species
protection (adjusted for pH) was adopted (0.75 mg/L), as the calculated background
concentration was well below this value.
To determine the potential impacts from the effluent discharge and to define a mixing zone for
the project in line with the principles defined in Section 20.3 of the State Policy on Water Quality
Management 1997, near field mixing zone modelling was undertaken. The mixing zone
modelling report is included in Appendix D.
Several modelling runs were performed, with varying effluent flow scenarios (design capacity
ADWF and 4 x ADWF), and receiving environment characteristics, including salinity
stratification, currents and future potential climate change scenarios. Ammonia toxicity trigger
values from the ANZECC (2000) Guidelines (adjusted for ambient pH) were used to define the
mixing zone extents.
The various modelling scenarios (Scenarios 1-8 in Appendix D) all resulted in ammonia being
diluted below toxic concentrations within 5 m of each of the diffuser nozzles. Therefore, no toxic
impacts are predicted by the modelling outside of 5 m to the north and south of the diffuser, and
also 5 m to the east, as the terminal diffuser nozzle is directed perpendicular to the shoreline.
The mixing zone for the existing Blackmans Bay STP effluent discharge is set as 15 m to the
north and 15 m to the south of the diffuser. No ammonia concentrations above tox icant trigger
values have been detected at the edge of this mixing zone during the seven water quality
surveys undertaken by TasWater between 2010 and 2015 (CEE 2010).
As the ammonia dilution requirement for the Project’s effluent will be significantly lower than the
previous effluent as a result of the upgraded treatment system, the current mixing zone is
considered more than sufficient to define the mixing zone for the proposed Project.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 106
In order to maintain the continuity in the water quality monitoring that is undertaken for the
current mixing zone area, it is proposed that the existing mixing zone boundaries are retained
for the Project, with the addition of a 15 m buffer in a radial arc to the east also, to cater for the
terminal ports easterly direction, which was not taken into account when setting the existing
mixing zone.
The substrate within the mixing zone consists of barren sand, with previous surveys (CEE,
2010) not identifying any listed species in the mixing zone, or any other significant ec ological
presence other than benthic infauna. There have been six operational benthic infauna sampling
events undertaken around the outfall between 2010 and 2015 (as well as two baseline events
prior to the outfall extension) (CEE, 2015) to monitor the impacts of the upgraded outfall.
Results have shown a slight difference in the abundance of two infauna families within 10 m of
the diffuser; no additional changes were detected. If these changes were a result of
toxicological effects from the effluent then no additional impacts are expected from the new
Project effluent, as it will have an improved ammonia concentration.
Ammonia concentrations have not been detected above the 0.75 mg/L Project trigger value
during any of the annual water quality monitoring events for the existing diffuser. This includes
sites directly above the diffuser, with the highest concentration measured at this location being
0.137 mg/L in June 2013.
By maintaining ammonia concentrations below 0.75 mg/L at the edge of the proposed mixing
zone (with the easterly modification) the potential for toxic impacts to occur to the marine
ecosystem outside of the mixing zone are considered negligible and therefore the PEVs
associated with aquatic ecosystem protection will not be prejudiced as a result of the Project
from toxicity.
Impacts will be managed and mitigated through maintenance of the effluent quality from the
Project and through the maintenance of the pipeline and diffusers functionality.
Eutrophication
Eutrophication of a waterway is the condition that results from an oversupply of key nutrients to
the environment, namely phosphates and nitrogenous compounds. Eutrophication of a marine
environment can result in a range of impacts to the ecosystem from increased biological
production.
One of the most significant potential impacts as a result of eutrophication is the increased
potential for algal (phytoplankton) blooms to occur. Chemical growth requirements for
phytoplankton are in line with the Redfield ratio of 106C:16N:1P. Within marine environments,
nitrogen is generally the limiting nutrient controlling growth rates, and as mentioned, this is the
case for the Derwent Estuary also (DEP, 2015). Large excessive inputs of nitrogenous
compounds therefore can result in rapid growth of phytoplankton, leading to blooms.
Algal blooms can impact the ecosystem through a number of pathways, including deleterious
effects of toxins produced by phytoplankton, physical obstructions to marine fauna respiratory
systems and through the depletion of oxygen levels in the environment.
Toxins produced from blooms have the potential to harm a variety of marine organisms,
including marine mammals, seabirds and fish. Humans can also be exposed to the toxins
through consumption of filter feeding marine organisms such as oysters. Several bloom events
have affected the Tasmanian shellfish industry in the last decade. Significant fish kills have also
occurred at Atlantic salmon aquaculture facilities within the D’Entrecasteaux Channel and
Tasman Peninsula area as a result of toxic algal blooms.
Secondary impacts to the marine environment from blooms occurs through the depletion of
oxygen as a result of both cellular respiration of the causative algae and through bacterial
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 107
degradation of dead algae and other marine algae dying as a result of the reduction in light
penetration from the bloom. This then leads to impacts to other organisms in the affected
ecosystem.
As the Project effluent will contain various concentrations of phosphates and nitrogenous
compounds, an assessment of the effluent composition, mass loads (of nutrients to be released)
and their subsequent fates, and the capacity for the receiving environment to cope with the
additional nutrients must be investigated.
Mass Loads
In considering mass loads to the Derwent Estuary, first an analysis was of the current and
predicted future mass loads from the existing and upgraded Blackmans Bay STP (including
amalgamation of Margate, Electrona and Howden STPs) was undertaken. These results were
then compared against the overall nutrient loads in the estuary from all existing estuary-based
STPs.
The following table (Table 6-8) shows the calculated mass loads from the existing Blackmans
Bay STP (using 2014 - 2015 data), the predicted future mass loads from the upgraded STP in
the first year of operation (including the amalgamated flows from Margate, Electrona and
Howden) and the predicted future mass loads from the upgraded STP at full capacity. The table
shows mass loads calculated on the basis of median effluent quality. As the Project is
proposing a seasonal discharge of total nitrogen and ammonia, mass loads have been
specifically calculated for each period for these parameters, which included 275 days of ‘normal’
and 90 days of ‘winter’. Result have been provided in both kilograms per day and tonnes per
year in Table 6-8.
Table 6-8 Upgraded Blackmans Bay Treatment Plant Mass Loads into
Derwent Estuary (median effluent quality)
Parameter Unit
Current
Blackmans
Bay STP
2015
Upgraded STP
Initial flows post amalgamation
(4.77ML/day ADWF)
Upgraded STP 2040 flows
post amalgamation
(8.53 ML/day AWDF)
Normal Winter
Total
Tonnes
per yr
Normal Winter
Total
Tonnes
per yr
Ammonia (as
N)
kg/day (ton/yr) 118.8
(43.4) 4.7 (1.2)
14.1
(1.3) 2.6
8.5
(2.3)
25.6
(2.3) 4.6
Total Nitrogen
(as N)
kg/day (ton/yr) 169.8
(62.0) 32.9 (9.0)
70.5
(6.3) 15.4
59.7
(16.4)
128.0
(11.5) 28.0
Total
Phosphorus
kg/day (ton/yr) 34.3 (12.5) 47.0 (17.2) 17.2 85.3 (31.1) 31.1
BOD5 kg/day (ton/yr) 87.7 (32.0) 47.0 (17.2) 17.2 85.3 (31.1) 31.1
TSS kg/day (ton/yr) 61.8 (22.6) 44.0 (17.2) 17.2 85.3 (31.1) 31.1
Oil & Grease kg/day (ton/yr) 5.6 (2.0) 9.4 (3.4) 3.4 17.1 (6.2) 6.2
7 Note – these calculations have been based on f low s of 4.698 ML/day ADWF as the calculated current f lows from combined
plants.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 108
Notes - Results in the above tab le are from calculations made at median effluent quality. For
comparison approximate annual mass loads at 90 th percentile and maximum effluent quality (at full
design capacity – 8.53 ML/day ADWF) are as follows:
Total nitrogen 90th percentile effluent quality – 42.7 tonnes per year)
Total nitrogen at max effluent quality – 62.1 tonnes per year
Total phosphorus at 90th percentile effluent quality – 37.4 tonnes per year
Total phosphorus at max effluent quality – 46.7 tonnes per year
As the table illustrates, the upgraded STP will result in a reduction in annual mass load for all
parameters at initial flows (4.7 ML/day ADWF - immediately post upgrade and amalgamation)
with the exception of phosphorus.
Under design capacity flow conditions (8.53 ML/day ADWF) annual mass loads for ammonia,
nitrogen and BOD will still be less than the current mass loads under the existing STP. At
design capacity (8.53 ML/day ADWF), phosphorus annual mass loads are predicted to be more
than double, TSS increase by approximately 50% and oil and grease treble.
These calculations represent changes in mass loads from Blackmans Bay STP to the Derwent
Estuary and do not consider the significant mass load reductions experienced in North West
Bay (a far more closed system) as a result of decommissioning the Margate, Electrona and
Howden STPs.
In order to understand how the changes in mass load relate to the Derwent Estuary overall,
future contributions from the Project were compared to current mass load contributions from all
Derwent Estuary STPs (which have been taken from State of the Derwent Estuary 2015 (DEP,
2015)). The State of the Derwent Estuary 2015 also provides estimates of total mass loads of
nitrogen and phosphorus to the estuary during 2013 from all sources. This data indicates
approximately 2000 tonnes/year of nitrogen entered the estuary in 2013 from rivers, stormwater,
STPs and industry. Of this total, approximately 25% was from STPs within the estuary (all
STPs, not only Blackmans Bay). Over 60% was from river system inputs and the remainder
stormwater and industry. Similar data is presented for phosphorus which indicates
approximately 180 tonnes/year of phosphorus entered the Derwent Estuary in 2013. Of this just
under 50% was from combined STPs and the remainder from rivers (approx. 30%), stormwater
and industry.
Table 6-9 shows the 2013/2014 total mass loads from all Derwent Estuary STPs as well as the
approximate total mass loads for other additional parameters relating to STP effluent (approx.
only). The existing total mass loads figures for all STPs in 2013-14 were then adjusted with the
calculated future mass load contributions from the Project (including amalgamated plants) to
provide an approximate indication of the predicted future mass load contribution from all
Derwent Estuary STPs. This table represents approximate data and does not allow for change
to any other STP in the future (which in reality is likely) and should be used as a general
indicator of changes over time, not as precise data. Also – the calculated change in mass loads
from Blackmans Bay STP over time is slightly different in Table 6-8 and Table 6-9 as the former
uses measured 2015 flows and the latter uses approximate 2013 flows from the DEP. The input
data for each table therefore is slightly different.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 109
Table 6-9 Approximate Mass Load Contributions to the Derwent Estuary
(median effluent quality)
Parameter Unit Approximate total
mass loads into the
Derwent Estuary
from all sources in
2013 (source: DEP
2015)
Current (2013/14)
mass loads from
all STPs
discharging to
Derwent Estuary
(source: DEP
2015)
Approx future (2040) mass
loads from all STPs discharging
to Derwent Estuary (with
2013/14 DEP data adjusted for
upgraded STP at 8.53 ML/day
ADWF using median effluent
quality)
Ammonia (as N) ton/yr Not available 281 247
Total Nitrogen
(as N)
ton/yr 2,000 492 458
Total
Phosphorus
ton/yr 180 88 108
BOD5 ton/yr 500 396 390
TSS ton/yr 34,000 285 284
The table shows that total ammonia and nitrogen mass loads from combined STPs are
predicted to reduce over time as a result of the Blackmans Bay STP upgrade, despite increased
flows. This is a result of significant improvements in nitrogen treatment as a result of the
upgraded plant. Overall this predicts that nitrogen inputs will reduce significantly as a result of
the Project and hence reduce the risk of eutrophication in the marine environment.
Biochemical oxygen demand and total suspended solids will decrease slightly, which is
significant given that more than double the current effluent volume will be discharged at the
design horizon discharge rate of 8.53 ML/day. Note - these figures are slightly different to the
Table 6-8 as a result of using 2015 vs 2013 input data.
The Project will result in an increase in mass load of total phosphorus. The percentage
contribution from the STP will increase significantly, and the total load to the estuary from all
STPs would increase in mass by over 20% when compared to the 2013-14 mass loads of total
phosphorus to the Derwent Estuary from all sources, including STPs, industry, stormwater and
from river discharge was estimated at ~180 tonnes during 2013 (DEP, 2015). Of this total, the
STPs were estimated to make up the majority source, at almost 50%. Based on these historical
figures, at the design horizon flow of 8.53 ML/day, the total load to the estuary would increase to
~200 tonnes/year, a ~10% increase. This is assuming that no upgrades to any of the existing
STPs occur, which is considered unlikely.
The impacts of this additional phosphorus to the nutrient balance of the waterway are very much
dependent on the input location and the subsequent transport and fate of the additional mass
load. For example, if the additional phosphorus was released in the predominately freshwater
areas in the upper estuary, where phosphorus is the limiting factor in algal growth (especially
during winter were freshwater dominates the water column in these areas), the potential for
impacts would be expected to be significantly more likely than for a release in a
marine/estuarine environment. To qualify this, far-field dispersion modelling that has been
undertaken by the CSIRO was examined for the estuary.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 110
Far-Field Dispersion
To understand the likelihood of potential impacts from the additional phosphorus, numerical
hydrodynamic modelling undertaken by the CSIRO for the Derwent Estuary was analysed
(Herzfeld et al, 2005). The modelling included the simulated continual release of tracers from
point source locations around the estuary to analyse the percentile distributions of the tracer
over an approximate 3-month period during 2003-2004. One of the point source locations
analysed by the model was the pre-extension discharge pipeline at the Blackmans Bay STP (in
~5 m of water). The results therefore provide a reasonable indication of distribution of effluent
that would occur from the Project’s effluent discharge.
Figure 6-12 shows the modelled 50th (median) and 95th percentile concentration in the Derwent
Estuary from the simulated tracer release from the Blackmans Bay STP site after the 3 month
release period (note concentration scales are mg/L). The modelled output suggests that the
majority of the release is concentrated in an area along the Tinderbox coastline, with
concentrations lowering towards the east and to the middle of the estuary rapidly, with the
lowest concentrations in the upper estuary region and within the lower half of the Ralphs Bay
area. With a degree of caution, it can be estimated that the additional phosphorus loads will
follow a similar dispersion pattern, with the majority of loads concentrated around the Project
outfall towards the mouth of the estuary.
Figure 6-12 Modelled 50th
and 95th percentile (left and right respectively)
tracer concentrations from the pre-extension Blackmans Bay STP
marine outfall over a 3-month period from December 2003 - March
2004 (from Herzfeld et al, 2005)
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 111
As the majority of the phosphorus is likely to be concentrated in the lower portion of the estuary,
potential for eutrophication and subsequent algal blooms is considered unlikely owing to
nitrogen being the limiting factor for algal growth in this predominantly marine area, as
discussed previously.
The monitoring program outlined below includes the sampling of chlorophyll -α and phosphorus
in order to monitor ambient phosphorus concentration changes and identify any indications of
eutrophication (i.e. algal concentration increases). If changes in chlorophyll -α are detected in
line with increasing phosphorus levels in the region of the outfall, then further investigations will
be undertaken. If risks of elevated phosphorus are identified, the STP will have additional
phosphorus removal retrofitted and emission limits reviewed in consultation with the EPA.
Impacts to Potential Sensitive Receptors
Potential toxic impacts from the effluent discharge, as discussed, are expected to be restricted
to within several meters either side of the diffuser. As previously identified, the outfall site is
within a sandy habitat and there are no sensitive receptors identified within the mixing zone. The
potential for the listed Spotted handfish or Gunns screw shell to occur in the area has been
assessed as unlikely through marine surveys of the area (CEE, 2009).
The giant kelp forest present at Blackmans Bay is the most significant sensitive receptor
identified in the immediate vicinity of the outfall. As previously discussed, it is theorised that the
persistence of this kelp forest over previously forested locations in the estuary is to some
degree a result of the high nutrients, specifically nitrogenous compounds, supplied by the
current outfall (via the ‘fertiliser ports’ and the diffuser).
As the Project has been designed to meet AMT treatment limits for nitrogenous compounds
(with the exception of the ‘Winter’ period), the resulting effluent stream will contain significantly
lower concentrations of nitrogen compared to the existing effluent stream. Therefore, there is
potential to significantly impact the kelp forest by modifying the nutrient source.
As part of the mixing zone modelling undertaken for the Project (Appendix D), DEP water quality
data from a combination of four sites within the lower estuary area were analysed to estimate
ambient concentrations of nitrogenous compounds in the area. These results were then
compared with the monitoring results collected by TasWater (CEE, 2015a) for the area
surrounding the outfall. This assessment allows a comparison between the available nutrients in
the area that may be impacted (i.e. in the vicinity of the kelp forest) and the ambient conditions
of the general area. This can then be used to determine the order of difference that would likely
result from reducing the nutrient output at the diffuser on nitrogenous compounds, and hence
the potential impacts on the kelp forest. The concentrations of total nitrogen and ammonia for
both areas are displayed in Table 6-10. It is noted that the outfall itself may have an effect on
the ambient concentrations in the lower estuary sites.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 112
Table 6-10 Nitrogenous Compounds Concentration Comparison between
Ambient Lower Derwent Estuary and Outfall Monitoring Sites
Parameter Percentile
Lower Estuary
(2004-2015)
(Source: DEP
data)
Outfall North (2011-2015)
(CEE, 2015a data)
Outfall South (2011-2015)
(CEE, 2015a data)
Distance from Outfall 10 m 100 m 1000 m 10 m 100 m 1000 m
Total
Nitrogen
(mg/L N)
Median 0.270 0.300 0.310 0.280 0.280 0.320 0.255
80th
Percentile
0.316 0.326 0.322 0.370 0.334 0.370 0.320
NHX (mg/L
N)
Median 0.006 0.025 0.011 0.008 0.012 0.010 0.009
80th
Percentile
0.013 0.053 0.019 0.009 0.083 0.054 0.012
The results suggest that total nitrogen concentrations between ambient background sites and
the outfall site are similar. Ammonia is elevated at 10 m and 100 m from the outfall compared to
ambient concentrations, but no large difference is seen at 1000 m.
This analysis (although limited) suggests that there are slightly elevated levels of
ammonia/ammonium directly around the outfall, but total nitrogen is at similar concentrations to
ambient waters around the outfall. No data was available for oxides of nitrogen around the
outfall to compare nitrate/nitrite concentrations to ambient conditions, which is an important
factor in determining the bioavailable fraction of total nitrogen.
Further water quality monitoring around the kelp forest itself would be required to establish a
confident determination of probable impacts from reducing effluent nitrogen concentrations; a
determination of the likely impacts to the kelp forest are therefore difficult to ascertain.
Fertiliser ports on the existing effluent pipeline will remain to deliver a proportion of the available
nitrogen in the Project effluent to the forest. Monitoring will be undertaken (refer below) to
assess any changes in kelp forest over time. If the persistence of the kelp forest is found to be a
direct result of the anthropogenic input of nutrients, it is considered unsustainable in the long-
term to maintain the forest through releasing effluent of a lower quality than AMT standards.
The rocky reef environment along the shoreline and several hundred metres offshore is not
expected to be significantly impacted. A reduction in nutrients may alter the species of algae
that grow on the reef, but the ecosystem as a whole will remain as per surrounding rocky reef
areas (e.g. tinderbox area).
Human Receptors
The key risks for human receptors from the marine environment as a result of STP effluent
include contact with waters containing elevated levels of pathogens (measured as
thermotolerant coliforms and enterococci), primary exposure to toxicants released from algal
blooms (as a result of eutrophication), and exposure to toxicants from consumption of harvested
filter feeding molluscs (e.g. oysters and muscles) that have ingested toxicants from algal
blooms.
With respect to thermotolerant coliforms, ANZECC (2000) Guidelines suggest a safe
concentration of faecal coliforms for primary contact activities (swimming/diving) to be <150
CFU/100 ml (or 35 enterococci 100ml) and <1000 CFU/100 ml (or 230 enterococci/100ml) for
secondary contact (boating/fishing). The proposed emission limits for the upgraded STP are 200
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 113
CFU/100 ml (median), 500 CFU/100 ml (90th percentile) and 750 CFU/100 ml (max). As the
mixing zone analysis shows (Appendix D) at 90th percentile emission limits from the plant
(500CFU /100mL - which is already below the secondary contact trigger) dilution to the primary
contact trigger is achieved within the proposed mixing zone (in fact within approximately 5 m of
the diffusers). As no swimming or diving is permitted within the mixing zone, risks to human
health from contact with pathogens is considered to be low.
The risk of algal bloom (and associated human impacts) is addressed above under
“eutrophication” and is mitigated predominantly as nitrogen is the limiting factor in the marine
environment of the lower estuary and the proposed STP upgrade results in a significant nitrogen
reduction and is not expected to pose any increase risk of algal bloom.
Analysis undertaken for the STP to date and from the trade waste input streams indicates there
are no heavy metals or other parameters of concern likely to occur in the effluent with the
potential to accumulate in filter feeders (hence, posing little risk human receptors).
There are no aquaculture leases within proximity of the existing outfall, with the nearest leases
being in North West Bay. No impacts are expected to these leases as a result of the upgraded
Blackmans Bay STP. Water quality within North West Bay (where the nearest leases lie) will be
significantly improved as a result of the Blackmans Bay Upgrade and eventual decommissioning
of the Electrona and Margate STPs (which currently discharge into North West Bay).
6.8.4 Monitoring, Review, and Adaptive Management
The ambient environment around the current outfall mixing zone is considered to already be
well described following the historic work undertaken by both TasWater and the DEP. The
ecology of the area, the sediments and water quality has been monitored annually since the
extension of the current outfall and the DEP has been monitoring water quality at several
reference sites monthly for a number of years. Therefore, as the existing mixing zone is not
being significantly altered as result of the Project (with the minor exception of the eastern end of
the diffuser), it is considered that sufficient information to characterise ambient conditions has
already been captured, and a full 12-month ambient monitoring program is not warranted in this
instance.
The following monitoring program therefore aims to expand the current monitoring regime to
ensure it is more robust, and to build on it in areas where new potential impacts are present
(e.g. the effects of the nutrient loss to the giant kelp forest).
Water Quality Monitoring
The marine water quality monitoring program for the Project will be based on the existing
program (CEE, 2015a), with the inclusion of additional monitoring sites and parameters. The
methodology for sample collection will remain as per the existing program.
The water quality monitoring sites, parameter groups, and sampling frequencies are shown in
Table 6-11. The parameter groups mentioned in the table refer to those listed in Table 6-12.
Monitoring sites are shown spatially in Figure 6-13.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 114
Table 6-11 Water Quality Monitoring Sites, Parameter Groups and
Monitoring Frequency
Site Name Parameters Depths Frequency
Outfall A**, B, C, D* surface, mid, bottom -biannually prior to
commissioning
(summer / winter) at the
approval of the Project
-Once during the 6
month commissioning
period
-biannually in the year
following
commissioning
-Annually following year
1
North of Outfall (15
m, 50 m, 100 m, 250
m)
A**, B, C, D* 15 m - surface, mid,
bottom
Remaining - mid
South of Outfall (15
m, 50 m, 100 m, 250
m)
A**, B, C, D* 15 m - surface, mid,
bottom
Remaining - mid
East of Outfall (15 m) A**, B, C, D* 15 m - surface, mid,
bottom
Reference Sites 1, 2
(DEP Sites B1 & B2)
A**, B, C, D* mid
Kelp Sites (N, S, O) A**, B surface, mid, bottom
*Group D (Metals) parameters to be ceased following 12-month post-commissioning monitoring if no
difference between pre-commissioning and post-commissioning identified.
**Depth profile of whole water column at 1 m intervals to be collected.
Table 6-12 Water Monitoring Parameters
Parameter
Group A: Physicochemical (in situ)
pH, Temperature, Salinity, Dissolved oxygen, Turbidity
(Instrument sensitivity to suit ANZECC (2000) Guideline physical and chemical stressors
concentration values)
Group B: Nutrients (laboratory)
Total Nitrogen, Ammonia as N, Nitrate as N, Nitrite as N, Total Phosphorus as P, Reactive
Phosphorus as P, Chlorophyll-α
(Lab sensitivity to suit concentrations from ANZECC (2000) Guideline physical and chemical
stressors concentrations)
Group C: Other (laboratory)
Chloride, Oil and Grease, Total Dissolved Solids, Total Suspended Solids, Thermotolerant
Coliforms
Group D: Metals (laboratory)
Dissolved metals suite (Sb, As, Be, B, Cd, Cr, Co, Cu, Pb, Mn, Mo, Ni, Se, Ag, Sn, Zn)
(Lab sensitivity to suit concentrations from ANZECC (2000) Guideline 95% protection for
toxicants where possible)
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 115
Benthic Infauna
Benthic infauna monitoring will be undertaken as per the methodology outlined in CEE (2015b).
Frequency of proposed sampling is identified in Table 6-13. Following the 12-month post
commissioning period, sampling frequency is to be reduced to once every three years as any
impacts detected in the first year following commissioning would not be expected to change as
rapidly. Sampling every three years will follow increases in flows to the design horizon to some
degree. Once full design capacity has been reached, the necessity for benthic infauna sampling
shall be re-assessed in consultation with the EPA.
Table 6-13 Benthic Infauna Site and Frequency
Site Name Frequency
Outfall -Once pre commissioning
-Once during the 6-month commissioning
period
-biannually in the year following
commissioning
-Triennially following first 12 months
North of Outfall (15 m, 50 m, 100 m, 250 m)
South of Outfall (15 m, 50 m, 100 m, 250 m)
East of Outfall (15 m)
Kelp Monitoring
Giant kelp will be monitored by divers swimming four 100 m transects at the sites and
frequencies identified in Table 6-14. Monitoring methodology is proposed as follows:
Number of stipes counted within 1 m of the transect, changing sides every 10 m of the
transect.
Canopy density estimated every 10 m, based on a 0-4 ranking, with 0 being no coverage, 1
being 25% and 4 being 100%.
Table 6-14 Giant Kelp Forest Monitoring Sites
Site Frequency
0-100 m north of fertiliser ports -Once pre commissioning
-Twice in first 12 months following
commissioning
- Annually following year 1 (frequency to be
reviewed three years following
commissioning with the EPA)
0-100 m south of fertiliser ports
0-100 m south (outer) of fertiliser ports
As well as diver surveys, a trial of mapping the kelp forest area using visible fronds on the
water’s surface to delineate the occupancy area will be trialled during the first diver survey, with
TasWater and survey sub-contractors to determine the effectiveness of this methodology. If
successful, mapping will occur during each giant kelp survey.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 116
Review and Adaptive Management
The results of the monitoring program will be provided annually to the EPA with a section in the
report identifying the effectiveness of the program, any noted significant impacts and any
suggested changes to the program and suggested management/mitigation if required.
Should significant results be detected in the first 12-months following the commissioning period
from any of the sampling program components, the EPA will be informed as soon as
practicable.
Adaptive management may include altering the treatment process or methodology, which will be
undertaken with guidance from the EPA. This includes improvements to phosphorus removal
within the upgraded STP, in the event elevated phosphorus levels are identified as having a
detrimental impact in the receiving environment.
Commitment 26 Receiving waters monitoring will be undertaken at 15
sites (as shown in Figure 6-13) biannually pre-commissioning,
during commissioning and in the first year of operation and annual
thereafter.
Commitment 27 Benthic infauna monitoring will be undertaken at 10
sites (as shown in Figure 6-13) once pre-commissioning, once
during commissioning, biannually in the first year and triennially
thereafter.
Commitment 28 Kelp monitoring will be undertaken at 4 sites, once pre-
commissioning, twice in the first year following commissioning
and annually thereafter (until reviewed with the EPA).
Commitment 29 If the monitoring program reveals marine impacts as a
result of phosphorus in the STP discharge, the EPA will be
contacted and phosphorus removal will be retrofitted to the STP
and new emission limits established in consultation with the EPA.
Proposed mixing zone
Giant Kelp
Kel
p N
orth
Kel
p S
outh
Kel
p O
uter
Outfall 15 m East
15 m South
15 m North
50 m South
50 m North
250 m South
250 m North
100 m South
100 m North
the LIST © State of Tasmania
526,800
526,800
527,000
527,000
527,200
527,200
527,400
527,400
5,237
,200
5,237
,200
5,237
,400
5,237
,400
5,237
,600
5,237
,600
5,237
,800
5,237
,800
G:\32\18107\GIS\Maps\MXD\3218107_008_Figure6-12_MarineMonitoring_RevC.mxd
0 40 8020
MetresMap Projection: Transverse Mercator
Horizontal Datum: GDA 1994Grid: GDA 1994 MGA Zone 55 o
© 2016. Whilst every care has been taken to prepare this map, GHD (and DATA CUSTODIAN) make no representations or warranties about its accuracy, reliability, completeness or suitability for any particular purpose and cannot accept liability and responsibility of any kind(whether in contract, tort or otherwise) for any expenses, losses, damages and/or costs (including indirect or consequential damage) which are or may be incurred by any party as a result of the map being inaccurate, incomplete or unsuitable in any way and for any reason.
Tasmanian Water CorporationBlackmans Bay STP DPEMP
Job NumberRevision A
32-18107
08 Aug 2016
Marine Monitoring Sites
Date
Data source: DPIPWE (cadastre, imagery, land tenure, land zoning, waterways, contours), TasWater (proposed infrastructure). Created by: jtoregan
2 Salamanca Square Hobart TAS 7000 Australia T 61 3 6210 0600 F 61 3 6210 0601 E [email protected] W www.ghd.com.au
Paper Size A3
LEGENDWater quality and benthic infaunaWater quality only
Kelp survey transectsDiffuserEffluent Pipeline
Giant KelpProposed mixing zone
Reference East (DEP-B3)
Reference West (DEP-B1)
the LIST © State of Tasmania
Location Easting Northing
250 m North 527367 5237630
100 m North 527367 5237480
50 m North 527367 5237430
15 m North 527367 5237395
Outfall 527367 5237380
15 m South 527367 5237365
50 m South 527367 5237330
100 m South 527367 5237280
250 m South 527367 5237130
15 m East 527413 5237380
Reference West (DEP-B1) 527780 5236750
Reference East (DEP-B3) 530740 5236350
Kelp North 526943 5237430
Kelp South 526943 5237330
Kelp Outer 526993 5237330
Location Easting Northing
Kelp North (start) 526940 5237480
Kelp North (f inish) 526940 5237380
Kelp South (start) 526940 5237380
Kelp South (f inish) 526940 5237280
Kelp Outer (start) 526990 5237380
Kelp Outer (f inish) 526990 5237280
Water quality and benthic infauna sampling
Kelp transects
Figure 6-13
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 118
6.9 Greenhouse Gases and Ozone Depleting Substances
This section considers the potential implications of the proposal on greenhouse gas production
and ozone depleting substances.
6.9.1 Performance Requirements
Climate change and greenhouse gas emissions are currently regulated under the National
Greenhouse and Energy Reporting Act 2007. The National Greenhouse and Energy Reporting
Scheme (NGERS) was formed in 2007 under the Act to provide a reporting framework for
greenhouse emissions. The Act outlines threshold emissions for greenhouse gas and energy
consumption (Section 13 of the Act), under which level companies are not required to report on
energy consumption or greenhouse emissions, these are:
50,000 tonnes of equivalent CO2 per annum (tCO2-e/annum) for a corporate threshold or
25,000 tCO2-e/annum for a facility threshold; and
200 terajoules/annum (TJ/annum) for a corporate threshold or 100 TJ/annum for a single
facility threshold.
6.9.2 Energy Consumption and Emissions
Construction Power and Fuel Consumption
Construction of the project will require several thousand litres of diesel for heavy machinery,
including excavators, cranes and dozers, as well as diesel generators required during
construction. Electricity supply will also be required for a range of features during the
construction phase, as well as the ongoing powering of the existing STP site.
Operation Power and Fuel Consumption
The Project is estimated to have an energy consumption of 6500 kWh/day at the full operating
volume of 8.53 ML/day ADWF. Additionally, there will be the potential to use small volumes of
diesel for emergency power generation.
NGERS Calculations
Table 6-15 displays the emission calculations for the operation of the Project, using the ‘Indirect
emissions from consumption of purchased energy’ calculation (DoE, 2014). Although the
consumption and emissions from the Project do not trigger the ‘facility’ threshold, TasWater’s
combined infrastructure exceeds the corporate threshold reporting requirement and therefore
TasWater are required to submit annual NGERs reports across all their assets. Calculations for
this Project will be included in these reports.
Omitted from the estimates in Table 6-15 are any fuels used in the construction or operation of
the Project, as these are only used for construction and very intermittently in emergency or
shutdown events during operation.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 119
Table 6-15 NGERS Calculations for the Project
Aspect Project NGERS ‘facility’ threshold
Electricity Consumption 6500 kWh/day N/A
Energy Consumed
(TJ/annum)
8.541 100
CO2 Emissions* (tCO2-
e/annum)
474.5 25,000
*Emission factor of 0.2 kg CO2-e/kWh for used for Tasmania from NGA Factors to calculate figure
Ozone Depleting Substances
Ozone depleting substances will be used in insignificant quantities for the Project for
refrigeration facilities for staff (this is no change from current operations).
6.9.3 Management and Mitigation
In order to reduce carbon emissions and implement best practice greenhouse impact
management, the following management and mitigation is proposed for the Project.
To minimise power consumption, the following is proposed where practicable:
Use of energy efficient processing equipment;
Use of energy efficient lighting around the site where suitable (e.g. LEDs); and
Administration spaces built to 5-star energy efficiency code.
6.9.4 Monitoring, Review, and Adaptive Management
Consumption of fuel and power will be recorded monthly and assessed on an annual basis with
any potential improvements in energy efficiency to be investigated and actioned upon. This may
include upgrades to pumps and other equipment if more efficient options become avai lable.
As mentioned, TasWater operates a large number of sewage treatment facilities as well as
other infrastructure and are required to submit annual NGERs reports; the energy consumption
from the Project will be included in the calculations for submission to the Commonwealth
government.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 120
6.10 Heritage
This section considers the potential impacts of the Project on identified Aboriginal and European
heritage values. Assessment of potential impacts to geoheritage sites has also been
undertaken.
6.10.1 Existing Conditions
Aboriginal Heritage
TasWater sought advice from Aboriginal Heritage Tasmania (AHT) in 2012 about Aboriginal
heritage values at the existing Blackmans Bay STP site and immediate surrounds. Advice was
provided by AHT on 25 January 2012 advising that there were no known Aboriginal heritage
sites recorded within, or close proximity to, the Project Site and due to the area being highly
disturbed there was deemed a low probability of Aboriginal heritage being present. AHT
concluded that there was no requirement for an Aboriginal heritage investigation and AHT had
no objection to the Project proceeding.
European Heritage
In 2015 TasWater commissioned a search of the Tasmanian Heritage Register and any places
on the Tasmanian Historic Places Inventory. There were no listed heritage features identified
within or immediately surrounding the Project Site which could be impacted by the Project.
A review of the EPBC Act Protected Matters Search Tool (August 2016) indicates no National
Heritage or World Heritage Places within or immediately surrounding the Site.
A review of the Kingborough Interim Planning Scheme Registers reveals two geoheritage sites
within 1 km of the Project Site as discussed below.
Geoheritage
There is one geoconservation site mapped along the eastern boundary of the Project Site
(Figure 5 3). This site is the Blackmans Bay Dolerite Contact and is related to coastal exposure
of dolerite along the foreshore. The geoconservation site lies outside of the proposed Project
Footprint and is not expected to be impacted by the Project.
The Kingborough Planning Scheme also mentions two geoheritage features (refer Section
6.7.1), namely the Blackmans Bay Geoheritage Site and Blackmans Bay Geological Monument.
The address given for these features is Fossil Drive and they are presumed to be part of the
Fossil Cove Conservation Area, approximately 500 m south of the Project Site. No impacts will
occur to these features as a result of the Project.
6.10.2 Performance Requirements
Aboriginal Heritage
Relevant legislation for the protection of Aboriginal heritage in Australia includes the Aboriginal
Relics Act 1975 at State level in Tasmania and the Aboriginal and Torres Strait Islander
Heritage Protection Act 1984 at a Commonwealth level.
European Heritage
The key legislation in Tasmania relating to European heritage is the Historic Cultural Heritage
Act 1995. This legislation is governed by the Tasmanian Heritage Council (THC), who is
consulted with to identify any places listed on the Tasmanian Heritage Register that may be
affected by a proposal, and to identify any subsequent development approval requirements.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 121
At a Commonwealth level, Declared World Heritage Area properties and values, places listed on
the National Heritage List and any places listed or interim listed on the Register of the National
Estate and values need to be considered.
6.10.3 Potential Effects
Aboriginal Heritage
As noted above there are no known Aboriginal heritage features within or surrounding the Site
and AHT confirmed that no further investigations were required and that they had no objection
to the Project.
No impacts to Aboriginal heritage are anticipated as a result of the Project.
European Heritage
As outlined above there are no known European heritage features within or immediately
surrounding the Project Site and therefore no impacts are expected as a result of the Project.
Geoheritage
There are two geoheritage sites on the Kingborough Interim Planning Scheme Register, which
lie approximately 500 m south of the Project Site and well outside of the Project Footprint. There
will be no impact to these features as a result of the Project.
There is also a geoconservation site mapped on The LIST along the coastline within the Project
Site, however all active construction works for the Project Footprint are outside of this
geoconservation site and no impacts are expected as a result of the Project.
6.10.4 Management and Mitigation
To avoid impact to the known geoconservation site along the coastline (Figure 5-3) the works
for the Project will be contained within the western side of the current fence line of the existing
STP site and within the temporarily fenced construction compound, which are outside of the
mapped geoconservation site.
Although there are no known Aboriginal or European heritage features within the Project
Footprint, there always remains potential for unanticipated discovery of heritage features during
excavation work. To manage this risk, an Unanticipated Discovery Plan (available from
Aboriginal Heritage Tasmania) will be included in the CEMP for the Project and followed by all
contractors.
6.10.5 Monitoring, Review, and Adaptive Management
As outlined above, an Unanticipated Discovery Plan will be included in the Site CEMP and
followed in the event of discovery of previously undetected heritage features.
Commitment 30 An Unanticipated Discovery Plan will be included in the
Site CEMP and followed in the event of discovery of previously
undetected heritage features.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 122
6.11 Land Use and Development
6.11.1 Existing Conditions
The site is an existing sewage treatment plant. The plant has existed since the 1980s and is
subject to a 300m attenuation area under the Interim Scheme, the objective of which is to
protect the site from encroachment from sensitive use. There are existing residences within the
attenuation area to the north and the west.
The adjoining Council land essentially comprises a buffer between the plant and these
residential areas and is used for walking trails.
6.11.2 Performance Requirements
Planning Scheme
The site is located within the Kingborough Municipality. The applicable planning scheme is the
Kingborough Interim Planning Scheme 2015 (the Interim Scheme) and the relevant planning
authority is the Kingborough Council (the Council). An assessment against the relevant
provisions of the Interim Scheme is provided in Section 6.11.3 of this DPEMP.
Environmental Management and Pollution Control Act 1994
The proposed development is level 2 activity under Schedule 1 of EMPCA. Accordingly, the
application is deemed to be discretionary in accordance with Section 57 of the Land Use
Planning and Approvals Act 1993.
Council will refer the application to the EPA for assessment. In accordance with Section 25(2)
of EMPCA, Council is not required to assess any matter addressed in the EPA Board’s
assessment. Relevant to this assessment are environmental matters relating to noise and
odour. Accordingly, a planning assessment has not been undertaken against the planning
scheme requirements for these matters as these are addressed as part of the EPA assessment.
Water and Sewerage Industry Act 2008 & Water and Sewerage (General) Industry
Regulations 2009
Sections 56H and 56I of the Water and Sewerage Industry Act 2008 prescribe that certain
works do not require planning approval, as they are not regarded as development for the
purposes of the Land Use Planning and Approvals Act 1993. This includes:
Subdivision of land necessary to give effect to the acquisition subject to meeting the criteria
prescribed in the Water and Sewerage (General) Industry Regulations 2009; and
Construction of sewerage infrastructure by TasWater in accordance with the above
Regulations.
No subdivision is proposed as part of the proposal, as the whole of Council land is proposed to
be acquired. Accordingly, it is only necessary to identify those sewage infrastructure works that
are not considered to be development, and therefore do not form part of the works to be
assessed by Council as part of the planning approval.
Also, the underground pipelines and pump stations do not form part of the scope of the
development application as per the assessment against Regulation 11 of the Water and
Sewerage (General) Industry Regulations 2009 below.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 123
Table 6-16 Regulation 11 of the Water and Sewerage (General) Industry
Regulations 2009
Clause Regulation Assessment
11. Work that is not
use or development
under Land Use
Planning and
Approvals Act 1993
For section 56I(b) of the Act, the following
are prescribed:
a) the removal, repair, maintenance,
modification, installation, erection or
use of a pump station associated with
the distribution or removal of water or
sewage;
b) the removal, repair, maintenance,
modification, installation, erection or
use of a fluoridation station associated
with the provision of water;
c) the removal, repair, maintenance,
modification, installation, erection or
use of a chlorination station
associated with the provision of water,
if the chlorine used or stored is not at
any time in a gaseous form;
d) the laying, removal, repair,
maintenance, modification or use of
any underground pipeline for the
removal or distribution of water or
sewage;
da) the installation, removal, repair,
maintenance, modification,
replacement or use of a meter for
water infrastructure, whether the
meter is above or below ground, if the
installation, removal, repair,
maintenance, modification,
replacement or use is associated with
the provision of water by a regulated
entity;
e) the clearing or lopping of trees,
branches or other vegetation to the
extent necessary to protect water
infrastructure, sewerage infrastructure
or water quality, except if those trees
are on –
i. the Register of the National
Estate kept by the Australian
Heritage Commission; or
ii. the National Trust Register.
The following works fall
within the scope of
Regulation 11 and do not
require planning approval:
Pump stations -
subclause a)
Underground pipelines -
subclause d)
Vegetation clearance, to
extent required to protect
sewerage infrastructure -
subclause e).
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 124
6.11.3 Assessment of Planning Aspects
The Project is to upgrade and expand the existing Blackmans Bay STP. This will result in an
expansion of the development footprint bringing the plant closer by approximately 10-20 metres
to the three residences located within the Environmental Living Zone to the west. It will also
result in rerouting of the Suncoast Headlands Track during and post construction. As previously
identified, the proposed upgrade works will address deficiencies with the current plant to meet
emission limits and manage odour impacts. The Project aims to significantly improve plant
performance to the Tasmanian EPA’s Accepted Modern Technology (AMT) performance.
Assessment of an Application
In determining a permit application Council must have regard to (Clause 8.10.1 of the Interim
Scheme):
a) all applicable standards and requirements in this planning scheme; and
b) any representations received pursuant to and in conformity with ss57(5) of the Act,
but in the case of the exercise of discretion, only insofar as each such matter is
relevant to the particular discretion being exercised
In determining any discretionary aspects of the proposal Council must in addition to
8.10.1, have regard to 8.10.2:
a) the purpose of the applicable zone;
b) any relevant local area objective or desired future character statement for the
applicable zone;
c) the purpose of any applicable code; and
d) the purpose of any applicable specific area plan.
but only insofar as each such purpose, local area object or desired future character
statement is relevant to the particular discretion being exercised.
The proposal requires exercise of discretion in relation to Utility Zone development standards in
relation to building height, fencing and setbacks; and Environmental Living Zone in relation to
use, use standards, setbacks, design and environmental values. The proposal also requires
discretion under the Potentially Contaminated Land, Stormwater Management and Coastal
Erosion Hazard Area Codes.
An assessment in accordance with subclause 8.10.1(a) and Clause 8.10.2 of the Scheme is
provided below.
Planning Scheme Objectives
The Planning Scheme Objectives applicable to the proposal include:
The efficiency of existing physical infrastructure is maximised.
Physical infrastructure and servicing is planned, co-ordinated and delivered in a timely
manner to support the regional settlement pattern and specific growth management
strategies.
Local infrastructure (roads, water, sewerage etc) is planned and delivered in a manner
that enables the efficient development of land, both now and into the future.
Local infrastructure is constructed so that it provides a safe and convenient service to
users.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 125
Local infrastructure is designed to a high standard and ensures the protection of local
environmental conditions.
Consistent with the above objectives the proposed upgrade works will cater for projected
increase in sewage flow to the Blackmans Bay STP from the immediate catchment. In addition,
the upgrade has been planned as part of a strategic rationalisation of STPs in the broader area
and will be designed to cater for current and projected future loads from the ageing Margate,
Electrona and Howden STPs, which are planned for decommissioning. As well the proposed
works will improve the environmental operation of the existing plant to current standards.
Use Categorisation
The use classification for the proposed use and development is ‘Utilities’ which is defined in
Table 8.2 of the Scheme as follows:
Utilities:
Use of land for utilities and infrastructure including:
a) telecommunications;
b) electricity generation;
c) transmitting or distributing gas, oil or power;
d) transport networks;
e) collecting, treating, transmitting, storing or distributing water; or
f) collecting, treating, or disposing of storm or floodwater, sewage or sullage.
Examples include an electrical sub-station or power line, gas, water or sewerage main,
optic fibre main or distribution hub, pumping station, railway line, retarding basin, road,
sewage treatment plant, storm or flood water drain, water storage dam and weir.
6.11.4 Utilities Zone
Use Table
Utilities are a Permitted use within the Zone.
Use Standards
Clause Interim Scheme Compliance Assessment
28.3 Hours of
Operation, A1
Hours of operation of a use within 50
m of a residential zone must be
within 7.00 am to 7.00 pm, except if:
for office and administrative tasks; or
(ii) a Utilities use.
Complies with subclause (ii)
as the use is Utilities
28.3.2 Noise, A1 Noise emissions measured at the
boundary of a residential zone must
not exceed the following:
55 dB(A) (LAeq) between the hours
of 7.00 am to 7.00 pm;
5dB(A) above the background (LA90)
level or 40dB(A) (LAeq), whichever is
Complies. See summary of
noise assessment report
findings at Section 6.4 of this
DPEMP.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 126
Clause Interim Scheme Compliance Assessment
the lower, between the hours of 7.00
pm to 7.00 am;
65dB(A) (LAmax) at any time.
Measurement of noise levels must be
in accordance with the methods in
the Tasmanian Noise Measurement
Procedures Manual, issued by the
Director of Environmental
Management, including adjustment
of noise levels for tonality and
impulsiveness.
Noise levels are to be averaged
over a 15 minute time interval.
28.3.3 External
Lighting, A1
External lighting (not including street
lighting) within 50 m of a residential
zone must comply with all of the
following:
a) be turned off between 10:00 pm
and 6:00 am, except for security
lighting;
b) security lighting must be baffled
to ensure they do not cause
emission of light outside the
zone.
Not applicable as the
proposed lighting will be
located in excess of 50m
from the boundary with the
General Residential Zone.
There will be new security
and operational lighting
around the new
infrastructure. Lighting will be
free standing and building
mounted and will be angled
towards the building.
28.3.4 Commercial
Vehicle Movements,
A1
Commercial vehicle movements,
(including loading and unloading
and garbage removal) to or from
a site within 50 m of a residential
zone must be within the hours of:
a) 7am to 7pm Monday to Friday
inclusive.
b) 9am to 5pm Saturdays
c) Nil on Sundays and Public
Holidays.
Not applicable as outlined
above the proposed works
are not within 50m of a
‘residential zone’. As outlined
in Section 2.6.2 of the
DPEMP any deliveries will be
conducted during manned
operating hours (0700 to
1700) five to six days a
week.
28.4.1 Building
Height, A1
Building height must be no more
than: 10 m.
Partially Complies. The
maximum building height is
7m, except for the odour
stack which is 12m
28.4.1 Building
Height, P1
Building height must satisfy all of the
following:
Complies. There is not
DFCS (subclause a). The
stack is required for the
functional requirement of the
plant in accordance with
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 127
Clause Interim Scheme Compliance Assessment
a) be consistent with any Desired
Future Character Statements
provided for the area;
b) be compatible with the scale of
nearby buildings unless the
height is necessary for the
functional requirements of
infrastructure;
c) not unreasonably overshadow
adjacent public space;
d) allow for a transition in height
between adjoining buildings,
where appropriate.
subclause b) and will not
result in an unreasonable
impact on the adjoining
council land (subclause c).
The stack will be internal the
site, and given the distance
to the nearest residential
dwelling it is not necessary to
provide for any transition in
height in accordance with
subclause d).
28.4.1 Building
Height, A2
Building height within 10 m of a
residential zone must be no more
than 8.5 m.
Not applicable. No buildings
are within 10m of a
‘residential’ zone.
28.4.2 Setback, A1 Building setback from frontage must
be no less than: 10 m.
Complies. The site is
accessed via a private right
of way arrangement (see
Section 5.1 of the DPEMP).
The nearest road is
Tinderbox Road, which is
located in excess of 10m
from the nearest building.
28.4.2 Setback, A2 Building setback from a residential
zone must be no less than:
a) 5 m;
b) half the height of the wall,
whichever is the greater.
Complies, the buildings are
located in excess of 5m from
the General Residential
Zone.
28.4.4 Outdoor
Storage Areas, A1
Outdoor storage areas for non-
residential uses must comply with all
of the following:
a) be located behind the building
line;
b) all goods and materials stored
must be screened from public
view;
c) not encroach upon car parking
areas, driveways or landscaped
areas.
Complies. No outdoor
storage is proposed, with all
storage internal to the
buildings.
28.4.5 Fencing, A1 Fencing must comply with all of the
following:
Assessment required against
P1.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 128
Clause Interim Scheme Compliance Assessment
a) fences and gates of greater
height than 2.1 m must not be
erected within 10 m of the
frontage;
b) fences along a frontage must
be 50% transparent above a
height of 1.2 m;
c) height of fences along a
common boundary with land in
a residential zone must be no
more than 2.1 m and must not
contain barbed wire.
A new fence will be located
as shown on the site plan
and will be the same as
existing which is 2.4m high
cyclone fencing with 3
strands barbed wire at the
top.
28.4.5 Fencing, P1 Fencing must contribute positively to
the streetscape and not have an
unreasonable adverse impact upon
the amenity of land in a residential
zone which lies opposite or shares a
common boundary with a site, having
regard to all of the following:
a) the height of the fence;
b) the degree of transparency of
the fence;
c) the location and extent of the
fence;
d) the design of the fence;
e) the fence materials and
construction;
f) the nature of the use;
g) the characteristics of the site,
the streetscape and the locality,
including fences;
h) any Desired Future Character
Statements provided for the
area
Complies. The proposed
fencing is for security
purposes and is consistent
with the existing fencing.
The fencing also relates to
an internal site, that is
surrounded by open space,
such that it will not affect the
‘streetscape’.
28.4.6 Environmental
Values, A1
No trees of high conservation value
will be impacted.8
Partly complies as (see
Section 6.7 of DPEMP)
found that as there were:
No trees listed in the
Threatened Species
Protection Act 1995
8 A tree of high conservation value is defined as “means a tree that is of a species that is listed in the Threatened Species Protection Act 1995 or the Environment Protection and Biodiversity Conservation Act 1999 (Cth) and/or provide potential or significant habitat for a threatened species listed in either of those acts”
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 129
Clause Interim Scheme Compliance Assessment
or the Environment
Protection and
Biodiversity
Conservation Act
1999 (Cth) are
impacted.
The surveys found
relatively limited
habitat values for
threatened fauna
species within the
Project Site due to
the highly modified
nature of the site and
its proximity to
densely populated
residential areas; as
well as large areas of
alternative habitat
adjacent to the study
area that are of
much higher quality
The swift parrot could
however potentially nest
and feed within the
eucalypt species found
on site. Some eucalypts
will be impacted by the
Project. Assessment is
therefore required
against P1 in relation to
the potential habitat
values associated with
the trees of high
conservation value
28.4.6 Environmental
Values, P1
Buildings and works are designed
and located to avoid, minimise,
mitigate and offset impacts on trees
of high conservation value.
Complies. The potential
impact is assessed in
Section 6.7 of the DPEMP.
The key outcomes as
relevant to Council’s
Biodiversity Offset Policy are
summarised and expanded
as follows:
The survey and mapping
identified 5 E. globulus trees
with a DBH of 40 or greater
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 130
Clause Interim Scheme Compliance Assessment
have been recorded in the
area that maybe impacted.
There are 128 E. globulus
trees with a DBH of >40
recorded in the study area.
The 2014 ecological work
assessed the threatened
vegetation community within
which the trees are located
as being of low condition.
The assessment of low
condition of the vegetation
communities is based on the
absence of diversity in the
understorey and ground
layer components.
Conservation significance
and overall condition of
vegetation communities was
assessed in accordance with
the TASVEG 2004 and
Regional Forestry
Agreement (RFA)
classification and associated
criteria.
A replanting proposal (at a
ratio of 3:1) is proposed in
accordance with the
commitments outlined in
6.7.4 of DPEMP and
landscaping plan in Appendix
A
6.11.5 Environmental Living Zone
The expansion area is on the adjoining Council land which is zoned Environmental Living. It is
considered that the zoning is not an accurate reflection of the existing land use which is
recreational in nature and essentially a buffer for the existing plant. While there is a dwelling on
the site it is the former caretaker’s cottage for the treatment plant and does not reflect a
historical residential use of the site. The site was formerly zoned Primary Industries and
Environmental Management.
Council officers have indicated that they will not alter the zoning as an urgent amendment, and
as the proposed works can be considered under the current zoning, without a need for an
amendment, the following assessment is provided against the current zoning – although many
of the standards are not relevant to the existing site characteristics. TasWater may seek to alter
the zoning to Utilities to reflect the use of the site via a separate application subsequent to
approval.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 131
Use Table
Utilities are a Discretionary use within the Zone.
Use Standards
Clause Interim Scheme Compliance Assessment
14.3.1 Non
Residential
Use, A1
Hours of operation must be within:
8.00 am to 6.00 pm Mondays to Fridays
inclusive;
9.00 am to 12.00 noon Saturdays;
nil Sundays and Public Holidays;
except for office and administrative tasks or
visitor accommodation..
Assessment required
against P1
The facility is a 24
operation with manned
operating hours (0700 to
1700) five to six days a
week.
14.3.1 Non
Residential
Use, P1
Hours of operation must not have an
unreasonable impact upon the residential
amenity through commercial vehicle
movements, noise or other emissions that
are unreasonable in their timing, duration or
extent.
Complies. Commercial
vehicle movements will be
undertaken during manned
operating hours and will be
accessed via the internal
road arrangements which
are some distance from the
nearest residents along
Tinderbox Road.
The proposal is also
assessed to be acceptable
in terms of noise as per
Scheme standards (see
Section 6.4 of this DPEMP)
and other emissions
including odour, dust and
exhaust (see section 6.1 of
this DPEMP).
14.3.1 Non
Residential
Use, A2
Noise emissions measured at the boundary
of the site must not exceed the following:
a) 55 dB(A) (LAeq) between the hours of
8.00 am to 6.00 pm;
b) 5dB(A) above the background (LA90)
level or 40dB(A) (LAeq), whichever is
the lower, between the hours of 6.00 pm
to 8.00 am;
c) 65dB(A) (LAmax) at any time.
Complies see noise
assessment findings at
Section 6.4 of this DPEMP.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 132
Development Standards
Clause Interim Scheme Compliance Assessment
14.4.1 Building Height,
A1
Building height must be no
more than:
7.5 m.
Complies. The maximum building
height is 7m
14.4.2 Setback, A1 Building setback from
frontage must be no less
than: 30 m.
Complies. The buildings in the
expansion area are located in
excess of 30m from the nearest
road, being Tinderbox Road.
14.4.2 Setback, A2 Building setback from side
and rear setbacks must be no
less than: 30m
Assessment required against P2
as the proposed buildings within
the expansion area are to be built
over the boundary with the
TasWater site. The facility is
however located in excess of 30m
from the boundaries with the
adjoining residential properties
within the Environmental Living
and General Residential Zones.
14.4.2 Setback, P2 Building setback from side
and rear boundaries must
maintain the desirable
characteristics of the
surrounding landscape and
protect the amenity of
adjoining lots, having regard
to all of the following:
a) the topography of the
site;
b) the size and shape of the
site;
c) the location of existing
buildings on the site;
d) the proposed colours and
external materials of the
building;
e) visual impact on skylines
and prominent ridgelines;
f) impact on native
vegetation;
g) be sufficient to prevent
unreasonable adverse
impacts on residential
Complies. The proposed building
setback is required for the
operational requirements of the
plant. The additional footprint is
located immediately adjacent to
the existing site and minimises
the impacts in terms of
excavations and vegetation
clearance required. Additional
revegetation is proposed as
illustrated in the landscaping plan
which will assist in screening the
plant as viewed from the adjoining
properties within the
Environmental Living Zone
(noting that the plant achieves the
necessary setback to these
properties). In addition the
proposed expansion area will be
cut into the slope of the site
minimising the visual appearance
of the building as viewed from the
adjoining residential properties.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 133
Clause Interim Scheme Compliance Assessment
amenity on adjoining lots
by:
i. overlooking and loss
of privacy;
ii. visual impact, when
viewed from
adjoining lots,
through building bulk
and massing.
14.4.3 Design, A1 The location of buildings and
works must comply with any
of the following:
a) be located within a
building area, if provided
on the title;
b) be an addition or
alteration to an existing
building;
c) be located on a site that
does not require the
clearing of native
vegetation and is not on a
skyline or ridgeline.
Assessment required against P1.
because:
The proposed works are not
located within a building area, as
none is provided on title
(subclause a)
The proposal includes new
buildings (subclause b); and
Requires native vegetation
clearance (subclause c).
However the site is not located on
a skyline or ridgeline consistent
with part of subclause c).
14.4.3 Design, P1 The location of buildings and
works must satisfy all of the
following:
a) be located in an area
requiring the clearing of
native vegetation only if:
i. there are no sites
clear of native
vegetation and clear
of other significant
site constraints such
as access difficulties
or excessive slope;
ii. the extent of clearing
is the minimum
necessary to provide
for buildings,
associated works and
associated bushfire
protection measures;
Complies
The vegetation clearance is
minimised to that reasonably
required to accommodate the
proposed expansion immediately
adjacent to the existing plant.
Landscaping of the site post
construction will involve planting
of native tree, shrub and grass
species. An indication of the area
to be landscaped is shown on
Figure 2-2 with more detailed
information provided in the design
drawings in Appendix A. Note that
where landscaping is proposed in
areas of existing vegetation, this
will be to supplement the existing
native vegetation on site and
existing native trees within the
landscaping zones will be
retained.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 134
Clause Interim Scheme Compliance Assessment
iii. the location of
clearing has the least
environmental
impact;
b) Not applicable
c) be consistent with any
Desired Future Character
Statements provided for
the area or, if no such
statements are provided,
have regard to the
landscape.
Subclause b) is not applicable.
There is no DFCS for the Zone
(subclause c).
14.4.3 Design, A2 Exterior building surfaces
must be coloured using
colours with a light
reflectance value not greater
than 40 percent.
Complies. The proposed new
buildings are likely to be
constructed from concrete and
can be conditioned to comply with
this standard.
14.4.3 Design, A3 The combined gross floor
area of buildings must be no
more than:
300 m2..
Complies. The combined GFA of
the building within the
Environmental Zone will be less
than 300m2.
14.4.3 Design, A4 Fill and excavation must
comply with all of the
following:
a) height of fill and depth of
excavation is no more
than 1 m from natural
ground level, except
where required for
building foundations;
b) extent is limited to the
area required for the
construction of buildings
and vehicular access.
Assessment is required against
P4, as the proposed cut exceeds
1m in height.
14.4.3 Design, P4 Fill and excavation must
satisfy all of the following:
a) there is no unreasonable
impact on natural values;
b) does not detract from the
landscape character of
the area;
Complies. The proposed
excavations are limited to that
necessary to accommodate the
proposed expansion area and will
minimise the visual impact of
these structures as viewed from
adjoining residential properties.
The works will be undertaken in
accordance with relevant
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 135
Clause Interim Scheme Compliance Assessment
c) does not unreasonably
impact upon the privacy
of adjoining properties;
d) does not affect land
stability on the lot or
adjoining land.
standards to ensure that they do
not affect land stability.
Outbuildings Not applicable.
14.4.5 Environmental
Values, A1
Development must be located
within a building area on a
plan of subdivision.
Assessment required against P1
as there is no building plan for
this site.
14.4.5 Environmental
Values, P1
The application is
accompanied by an
environmental management
plan for the whole site, setting
out measures to be put in
place to protect flora and
fauna habitats, riparian areas,
any environmental values
identified as part of a site
analysis, and identify
measures to be used to
mitigate and offset adverse
environmental impacts.
Complies. The proposal is a level
2 activity. This DPEMP outlines
the impacts on the environmental
values, including measures to
mitigate and offset impacts. The
EPA conditions will be included
as part of the DA permit in
relation to the environmental
aspects of the proposal.
6.11.6 Codes
Bushfire Prone Areas Code
This land is located within a bushfire prone area being land that is within 100m of an area of
bushfire-prone vegetation equal to or greater than 1 hectare. This Code applies to:
a) development, on land that is located within, or partially within, a bushfire-prone area,
consisting of the subdivision of land; and
b) a use, on land that is located within, or partially within, a bushfire-prone area, that is a
vulnerable use or hazardous use.
The Code does not apply under subclause a) as no subdivision is proposed, and the proposal
does not comprise of a vulnerable use or hazardous use. TasWater has confirmed that
hazardous chemicals will not be stored on site in quantities exceeding that prescribed in the
Regulations.
Also, the EPA will assess the bushfire impacts and mitigation (see Section 6.16 of this DPEMP).
Potentially Contaminated Land Code
This Code applies to the development comprising of land that is, and adjoins an activity listed in
Table E2.2 of the Code as a potentially contaminating activity (existing treatment plant) and is
not identified as an exempt activity. The following Performance Criteria under Clause E2.6.2 of
the Interim Scheme apply to excavation of potentially contaminated sites:
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 136
Excavation does not adversely impact on health and the environment, having regard to:
a) an environmental site assessment that demonstrates there is no evidence the land is
contaminated; or
b) a plan to manage contamination and associated risk to human health and the environment
that includes:
i. an environmental site assessment;
ii. any specific remediation and protection measures required to be implemented before
excavation commences; and
iii. a statement that the excavation does not adversely impact on human health or the
environment.
As detailed in Section 6.5, the vast majority of all excavated material is from areas outside of
and up gradient from the existing STP site. However, a small area along the western side of the
existing STP boundary (up gradient of the existing plant) will be excavated and some ground
disturbance will occur at the new loading/unloading facility. As the existing STP is a “potentially
contaminating activity” risk of contaminated soil being encountered needs to be considered. To
manage this risk a targeted inspection of areas proposed for subsurface excavations will be
undertaken by a Certified Practitioner (Site Contamination Practitioners Australia) prior to
construction. This inspection will review available history for the site and delineate which areas
proposed for excavation would be considered lower risk and therefore not require classification
and which areas are higher risk and therefore need soil testing and classification (for reuse or
disposal). In accordance with this assessment, areas of higher contamination risk (within the
excavation footprint) will be subject to soil testing and classification. Any resulting material from
these areas will be handled, transported and disposed of in accordance with relevant guidelines
and utilising licenced practitioners.
Landslide Code
The site is identified as being partially subject to a landslide hazard area overlay (low and
medium) as illustrated in Figure 6-14 comprising an area with slope of between 11-20 degrees.
Buildings are exempt from the Code within the Low Landslide Hazard Area under Clause E3.4c)
of the Scheme. The proposed buildings are also exempt pursuant to Clause E3.4 e) of the
Scheme within the Medium Landslide Hazard Area as the gross floor area within the hazard
area is no more than 200 m2.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 137
Figure 6-14 Landslide Hazard Area Overlay & Development Site (Low
Landslide Hazard Area on the Left and Medium Hazard Landslide
Area on the Right)
Road and Railway Assets Code
This Code applies as the proposed development will intensify the use of the existing vehicular
access via Tinderbox Road.
Clause Interim Scheme Compliance Assessment
E5.5.1 Existing road
accesses and junctions, A3
The annual average daily
traffic (AADT) of vehicle
movements, to and from a
site, using an existing access
or junction, in an area
subject to a speed limit of
60km/h or less, must not
increase by more than 20%
or 40 vehicle movements per
day, whichever is the
greater.
Complies. As outlined in
Section 6.6.3 of the DPEMP
the AADT vehicle
movements to and from the
site using the existing access
will not be more than 40
vehicle movements per day.
E5.6.2 Road accesses and
junctions, A2
No more than one access
providing both entry and exit,
or two accesses providing
separate entry and exit, to
roads in an area subject to a
speed limit of 60km/h or less.
Complies. No new accesses
are proposed.
Parking and Access Code
This Code applies to all use and development. There is however no car, motorcycle or bicycle
parking requirements for a Utilities.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 138
Clause Interim Scheme Compliance Assessment
E6.7.1 Number of
Vehicular Accesses A1
The number of vehicle access
points provided for each road
frontage must be no more than 1
or the existing number of vehicle
access points, whichever is the
greater.
Complies. No Change
E6.7.4 On-Site Turning,
A1
On-site turning must be provided
to enable vehicles to exit a site in
a forward direction, except where
the access complies with any of
the following
a) it serves no more than two
dwelling units;
Complies. Access and
Parking will be upgraded
consistent with this standard.
Stormwater Management Code
The proposal will involve the upgrade of existing parking and internal road network.
Clause Interim Scheme Compliance Assessment
E7.7.1 Stormwater
Drainage and Disposal,
A1
Stormwater from new impervious
surfaces must be disposed of by
gravity to public stormwater
infrastructure.
Assessment required against
P1 as the site is not
connected to Council’s
stormwater system.
E7.7.1 Stormwater
Drainage and Disposal,
P1
Stormwater from new impervious
surfaces must be managed by
any of the following:
a) disposed of on-site with
soakage devices having
regard to the suitability of the
site, the system design and
water sensitive urban design
principles
b) collected for re-use on the
site;
c) disposed of to public
stormwater infrastructure via
a pump system which is
designed, maintained and
managed to minimise the risk
of failure to the satisfaction of
the Council.
As outlined in Section 2.5.8 of
the DPEMP, the site has
some existing stormwater
collection systems, which
discharge to the onsite creeks
and over the cliffs to the
marine environment.
The intention of the new
design is to minimise
collection and concentration
of stormwater and allow
natural flows to occur
wherever possible. Diversion
drains will be installed around
the upslope edge of new
hardstand areas to direct
clean stormwater away from
the site. Any new roofed
structures will be sloped to
direct rainwater onto adjacent
hardstand areas. New
hardstand areas will be
sloped to direct stormwater
away from the site and into
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 139
Clause Interim Scheme Compliance Assessment
constructed grass swales
before diffuse discharge into
the surrounding environment.
Some of this new stormwater
may report to the existing
collection system by way of
natural ground flows (e.g.
from the new road access).
Detailed drainage designs will
be prepared as part of the
detailed design process.
Contaminated drainage and
stormwater will be collected in
bunded areas and pumped to
the inlet of the treatment plant
for treatment.
Construction surface water
management is addressed
under Section 6.2.3
E7.7.1 Stormwater
Drainage and Disposal
A2
A stormwater system for a new
development must incorporate
water sensitive urban design
principles R1 for the treatment
and disposal of stormwater if any
of the following apply:
a) the size of new impervious
area is more than 600 m2;
b) new car parking is provided
for more than 6 cars;
c) a subdivision is for more
than 5 lots.
Assessment required against
P2 as the size of new
impervious area exceeds
600m2 primarily comprising
the new internal road.
However only 4 new car
parking spaces are provided,
and no subdivision is
proposed.
E7.7.1 Stormwater
Drainage and Disposal,
P2
A stormwater system for a new
development must incorporate a
stormwater drainage system of a
size and design sufficient to
achieve the stormwater quality
and quantity targets in
accordance with the State
Stormwater Strategy 2010, as
detailed in Table E7.1 unless it is
not feasible to do so.
During the detailed design
phase a detailed stormwater
design will be prepared for all
new hardstand and roofed
areas. This detailed design
will comply with the
requirements of the State
Stormwater Strategy 2010 for
new developments (unless it
is not feasible to do so).
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 140
Attenuation Code
The site is subject to a 300 m buffer area over the current plant. The proposal is exempt from
the Code pursuant to Clause 9.4.1a) activities requiring assessment under the Environmental
Management and Pollution Control Act 1994 by the Board of the Tasmanian Environment
Protection Authority.
Biodiversity Code
The site is subject to a Biodiversity Conservation Area. The proposal is exempt from the Code
pursuant to Clause 10.4.1a) clearance and conversion or disturbance associated with a Level 2
Activity under the Environmental Management and Pollution Control Act 1994;.
Waterway and Coastal Protection Code
The site is within a Waterway and Coastal Protection Area. The proposal is exempt from the
Code pursuant to Clause 11.4.1a) development associated with a Level 2 Activity under the
Environmental Management and Pollution Control Act 1994;
Historic Heritage Code
The Code applies as the site contains a heritage listed place: Blackmans Bay Geoheritage Site
& Blackmans Bay Geological Monument; Fossil Cove Drive, Blackmans Bay – Ref No 1. As
outlined in Section 6.10 of this DPEMP the proposal no works are proposed to the site or within
the immediate vicinity. Accordingly, no impacts are anticipated from the proposed works.
Coastal Erosion Hazard Code
This Code applies as the site is within a Coastal Hazard Area as shown on the planning scheme
maps (Figure 6 9). Accordingly, buildings and works must satisfy all of the following:
a) not increase the level of risk to the life of the users of the site or of hazard for
adjoining or nearby properties or public infrastructure
b) erosion risk arising from wave run-up, including impact and material suitability, may
be mitigated to an acceptable level through structural or design methods used to
avoid damage to, or loss of, buildings or works
c) erosion risk is mitigated to an acceptable level through measures to modify the
hazard where these measures are designed and certified by an engineer with
suitable experience in coastal, civil and/or hydraulic engineering
d) need for future remediation works is minimised;
e) health and safety of people is not placed at risk;
f) important natural features are adequately protected;
g) public foreshore access is not obstructed where the managing public authority
requires it to continue to exist;
h) access to the site will not be lost or substantially compromised by expected future
erosion whether on the proposed site or off-site;
i) provision of a developer contribution for required mitigation works consistent with
any adopted Council Policy, prior to commencement of works;
The proposal complies with the above criteria as it is located within the footprint of the existing
plant, will be undertaken in accordance with a construction and environmental management
plan pursuant to subclauses e) and f) and will maintain public foreshore access which are
located outside of the development footprint.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 141
Figure 6-15 Coastal Erosion Hazard Overlay & Development Site
Signs Code
A sign on the new access gate measuring approximately 1200 by 800 mm stating STP Site and
no public access is proposed. There will also be temporary construction signage. The signage
will not be illuminated. The proposed signage is defined as a building site sign and wall sign
under the Code and is exempt under Table 17.1 of the Code.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 142
6.11.7 Effects on Local Land Uses
The Project Site is currently used for recreational walking and will continue to be available to the
public during construction and once the new STP is operational.
The Suncoast Headlands Track traverses the STP site and will be temporarily relocated during
construction and then reinstated slightly west of its current alignment post construction (refer
Figure 2-6). New landscaping will be provided along the western side of the upgraded STP to
provide visual screening of the new STP from the new access track and nearby houses. As the
track will remain open to the public during both construction and operational phases, potential
impacts to this recreational feature are considered to be negligible.
Immediately south of the existing STP site and partially within the new Site is a dog exercise
area. This area will not be impacted in any way by construction activities and will remain
accessible via the current vehicular access and remain connected to the Suncoast Headlands
Track as noted above. There may be minor noise and odour impacts affecting the area but
these will be largely unchanged (if not slightly improved) than current conditions with the
existing STP. As such impacts to this recreational feature are considered to be negligible.
There is a scout hall west of the STP Site, which will not be impacted in any way by the
development.
Residential properties in the areas surrounding the site will be subject to minor changes in
odour and noise and assessed under Sections 6.1 and 6.4 respectively.
There are no tourist activities, camping areas, industries or commercial activities within or
immediately adjacent to the Site which would be impacted by the development. There is no
agricultural use of the Site and no impacts to agriculture are expected.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 143
6.12 Visual Impacts
6.12.1 Existing Conditions
The existing Blackmans Bay STP has been in operation for over 30 years. It pre-dates many of
the adjacent residential properties.
The Project Site is sloped from west to east and contains existing open areas and trees,
providing some visual screening of the proposed infrastructure for surrounding residents.
6.12.2 Performance Requirements
Tasmania’s landscape is an important consideration in any land use planning exercise because
of its cultural, ecological and/or scenic qualities. The proposed Project Footprint is directly
adjacent to and within the existing Blackmans Bay STP.
The key legislative documents addressing visual impacts in the area are the:
Kingborough Interim Planning Scheme 2015
The objectives of the RMPS as set out in Schedule 1 of LUPAA
These two documents deal with the broader issues of maintaining the environmental and social
values of the area (of which the visual landscape is a relevant factor).
6.12.3 Potential Effects, Management and Mitigation
The proposed Project involves retrofitting existing infrastructure as well as construction of new
infrastructure. The most visible new elements at the site will be the two IDEA-SBR tanks. The
tanks will be constructed west of the existing STP within an area of significant ‘cut’. By cutting
into the natural sloped bank to accommodate the new tanks, much of the potential visual impact
is mitigated.
Preliminary visual analysis was undertaken by Lester Frank as part of the Project’s planning
phase. This involved early stage visual representations taken from a series of potential vantage
points around the Project including properties on Suncoast Drive and Tinderbox Road,
immediately west of the Project. These representations provide an indication of the comparative
visual impact of the existing STP and proposed Project, but do not include any existing trees or
those proposed to be planted as part of the Project, so significantly over-represent the overall
visual intrusion.
Review of the images produced shows the proposed Project is just visible from the property at
90 Tinderbox Road (viewing at approx. 1.8 m from existing floor level) in the absence of any
trees. From houses on Suncoast Drive both the existing STP and the Project are visible (in the
absence of any trees), each showing a similar visual footprint, with the Project further up the
slope, but otherwise similar in scale. As noted above these images do not consider the existing
trees on site. As illustrated on the Project site plans (Figure 2-1) there are a large number of
existing trees already on site, sitting in the line of sight between the Project and existing
residential properties. In addition, TasWater propose a new vegetation screen (refer Figure 2-1)
along the entire western boundary of the Project Footprint, providing considerable visual
screening once established (noting that it will take some years for the vegetation to mature).
This vegetation screen is in addition to rehabilitation of all temporarily disturbed areas (i.e.
construction compound) to their original condition, immediately post construction. The Project
will also employ paints and building finishes that blend into the surrounding environment to
minimise visibility.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 144
With the existing and proposed tree screen in place, the overall visibility of the Project from
existing residential properties will be relatively low and largely similar in overall context to the
existing STP.
The Project is not expected to be visible from local public roads, namely Tinderbox Road and
Suncoast Drive, due to topography and existing visual obstructions (houses and trees).
The existing STP is visible to recreational users of the surrounding open space (e.g. walkers).
The Project will be similarly visible, with the exception that proposed vegetation screening will
assist over time with screening of the Project from the Suncoast Headlands Track.
The images from the preliminary visual analysis are available on request.
6.12.4 Monitoring, Review, and Adaptive Management
Along with proactive community consultation leading up to, and during, construction the
TasWater online complaints register will be the main method of recording visual impact
complaints arising from the Project.
Commitment 31 A vegetation screen will be planted along the western
boundary of the Project Footprint as outlined on the Figures in this
DPEMP.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 145
6.13 Socio-economic Issues
The proposed Project involves upgrade of the existing Blackmans Bay STP, providing additional
sewage capacity both for the immediate region, and potentially for the Margate, Electrona and
Howden catchments if the amalgamation of these STP catchment to the Project occurs.
Overall the Project is expected to benefit Kingborough residents, both now and for future
generations, by accommodating regional growth in the area and improving the overall quality of
water discharged to the River Derwent, along with improved odour and noise for residents.
It requires a large capital investment (approximately in the vicinity of $30-40 million) in order to
facilitate long term reliable sewage treatment within the Kingborough LGA and accommodate
future development within the region.
Salient social and economic features of the development include:
Capital investment – in the vicinity of $30 to $40 million.
Annual expenditure – estimated to be approximately $1 million/yr (excluding interest and
capital repayments) and will be obtained via existing rates.
Design horizon – Capacity to treat sewage from existing developments and projected future
growth in the region up to ~2040; catering for the current Blackmans Bay STP catchment,
as well as potentially the Margate, Electrona and Howden STP catchments to
accommodate their potential future amalgamation into the Blackmans Bay STP.
Employment Opportunities:
– Approximately two year construction period followed by a six-month commissioning
period (with some early commissioning work undertaken during construction) during
which time local employment opportunities exist in design, construction, materials
supply and commissioning.
– Once operational the Project will accommodate three local operational staff plus
additional resources during maintenance periods. This is relatively unchanged from
existing conditions.
Materials Supply – Where possible local materials will be sourced for construction, with all
gravel and concrete to be sourced from local quarries and suppliers.
Impacts on local and regional economies – the most significant economic impact from the
Project will be increased reliability of sewage treatment in the region and the opportunity for
future development, which would otherwise be constrained by an ageing and ‘at capacity’
treatment plant.
Impacts on local social and community amenity – The area surrounding the existing STP is
used in a recreational capacity, predominantly by walkers and forms part of the Suncoast
Headlands Track. The proposed upgrade will include a temporary diversion of the access
track around the Construction Compound. Once operational the access track will be
reinstated in a similar alignment to its current position and be improved by proposed
landscaping (refer Figure 2-6). The area surrounding the Project Footprint will continue to
be made available for public recreation.
The Project also facilitates ongoing development of local community assets by providing
reliable sewage treatment with capacity for regional growth.
Impacts on land values – The upgraded STP is not expected to detract from local land
values immediately adjacent to the Project Site as it already contains an operating STP and
although the Project Footprint increases the current STP footprint, amenity impacts such as
odour will be better controlled through more contemporary plant design (refer Section 6.1).
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 146
By upgrading the existing STP the Project also allows for ongoing development within the
region, therefore supporting future growth and land values.
Impacts on local industries – The Project will allow for future growth in local industries by
accommodating future wastewater generation, which would otherwise be limited by the
capacity of the existing STP.
The local amenity issues associated with the Project (noise, odour, slight increase in
footprint) are highly localised and ameliorated by the fact there is already an operating STP
within the Project Site and through controls stipulated in the relevant sections (e.g. odour
control facility, noise mitigations, landscaping etc.).
Overall the Project is expected to have a positive socio-economic effect by increasing capacity
and reliability of wastewater treatment, thereby facilitating regional growth.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 147
6.14 Health and Safety Issues
6.14.1 Legislative, Policy and Performance Requirements
During construction and operation, the Project will demonstrate compliance with:
Workplace Health and Safety Act 2012 and associated Workplace Health and Safety
Regulations 2012;
Relevant Australian Standards (including AS/NZS 4804:2001 Occupational Health and
Safety Management Systems);
Australian Code for the Transport of Dangerous Goods by Road and Rail;
Dangerous Substances (Safe Handling) Act 2005 and associated regulations;
Australian Dangerous Goods Code (7th edition); and
Fair Work Act 2009.
6.14.2 Construction Impacts, Management, and Mitigation
For the construction phase a site specific Health and Safety Management Plan (HSMP) will be
developed prior to construction works.
The construction stage of the proposed Project will be undertaken by construction contractors. It
will be a requirement of the engagement process that the successful contractors will undertake
works in accordance with the Tasmanian Workplace Health and Safety Act 1995 and
Regulations 1998 and AS 4804 Occupational Health and Safety Management Systems.
Additionally, Contractors will be required to:
Prepare and implement a HSMP specific to their role in the proposed Project (this may be
required to be submitted to the Workplace Safety Division) this will include;
– Site control, access, inductions, training and reporting protocols to ensure all
contractors, staff and visitors are registered, inducted, managed on site and recorded
as leaving when vacating the site;
– Road traffic management (including facilitating safe pedestrian crossing of Treatment
Plant Road during construction);
– Speed limit restrictions in required working areas;
– Noise and dust management;
– Provision of personal protective equipment (PPE) for workers and any site visitors;
– Fire prevention and management;
– Specified working arrangements in accordance with the Fair Work Act 2009;
– Proper handling of waste materials;
– Hazardous substance handling and storage, with management of emergency spill
situations (to be managed and mitigated in accordance with those measures outlined
in Section 6.6).
– Fencing off of potentially dangerous areas to the public, in particular the Construction
Compound and main Project Footprint site;
– Use of appropriate signage at all necessary locations in accordance with appropriate
standards and regulations (site entrances, fenced off areas etc.);
– Provide notification of incidents to the relevant competent authority as soon as
reasonably practicable after the occurrence of an accident/incident; and
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 148
– All workers/contractors to be inducted in site specific health and safety aspects prior to
commencing work.
6.14.3 Operational Impacts, Management, and Mitigation
The existing Blackmans Bay STP operates under TasWater’s Work Health and Safety Policy.
The Project will continue to operate under this Policy as well as all relevant legislation.
The Project will be fully fenced with cyclone fencing and two locked security gates. Only
authorised personnel and inducted visitors will be granted access to the site. All chemicals and
hazardous substances will be stored in locked compounds within the dewatering building or the
bulk chemicals store.
A site specific Operations and Maintenance Manual will be prepared for the Project and will
address Health and Safety issues including:
Identification of safety hazards and controls;
Procedures for operational control of potentially hazardous equipment;
Roles and responsibilities for specific management representatives who have a defined role
for occupational health and safety management of the facility;
Development of a competency, training and awareness program for employees associated
with the facility;
Development of an Emergency Response Plan; and
Development of an incident management system.
All workers/contractors will be inducted in site specific health and safety aspects prior to
commencing work.
6.14.4 Monitoring, Review, and Adaptive Management
Health and safety audits will be undertaken on at least a monthly basis with results recorded
and provided to the relevant regulatory authority as required.
Incidents will be managed in accordance with WorkSafe Tasmania requirements, including
reporting of incidents to the required agencies.
If safety issues are identified during construction and operation, works in the area(s) of concern
will be halted until a safe alternative can be developed and implemented.
Commitment 32 A Health and Safety Management Plan (HSMP) will be
prepared for the construction phase and incorporated into the Site
CEMP.
Commitment 33 Health and safety management will be included in the
site specific Operations and Maintenance Manual.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 149
6.15 Hazard Analysis and Risk Assessment
6.15.1 Hazard Identification and Risk Assessment Methodology
A preliminary hazard identification and risk assessment was undertaken for the Project based
on the processes outlined in Australian/New Zealand Standard AS/NZS 4360:1999 Risk
Management.
The hazard identification process involved the following:
Identifying the potential major environmental hazards associated with all aspects of the
Project;
Identifying the potential environmentally detrimental outcomes that could result for each of
these hazards; and
Generating a list of the major hazards and the potential environmental outcomes to be risk
assessed.
Once the key hazards and potential environmental outcomes had been identified, they were
firstly evaluated without considering mitigation strategies and then with strategies in place. In
most cases there was a decrease in risk due to the proposed management and mitigation
measures. Results from the risk assessment are shown in Table 6-21. The likelihood,
consequence and risk ranking criteria are outlined below.
Measures to manage and mitigate against the risks identified in this assessment are included in
the relevant sections of the DPEMP.
Likelihood
For the likelihood of an event occurring, the ranking and associated criteria are presented in
Table 6-17. The likelihood of occurrence assessment takes into account built-in design
functions.
Table 6-17 Likelihood Ranking with Design Control
Ranking Descriptor Detail Description
A Almost Certain Is expected to occur
B Likely Will probably occur
C Possible May occur at some time
D Unlikely Could occur at some time
E Rare May occur only in exceptional circumstances
Consequence
Consequences are based on severity of impacts and recovery times of ‘environmental factors’
which include ecological, landscape and socioeconomic receptors. The ranking and associated
criteria are presented in Table 6-18.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 150
Table 6-18 Environmental Consequence Ranking
Ranking Descriptor Detail Description
1 Insignificant No significant impacts to sensitive environmental factor(s)
2 Minor Short term localised impacts to environmental factor(s), recovery
measured in weeks to months.
3 Moderate Detectable impacts on environmental factor(s) at a local level,
recovery measured in months to years.
4 Major Significant impacts on environmental factor(s) at a regional
scale, recovery measured in years to decades
5 Catastrophic Large scale detrimental effect on environmental factors (s), long
term recovery over decades.
Risk Ranking
Environmental risk is determined using a matrix that incorporates the likelihood and
consequence of the aspect being assessed. The matrix used in this assessment is presented in
Table 6-19, with the definition of each risk colour presented in Table 6-20.
Table 6-19 Risk Matrix
Likelihood
Consequences
1
(Insignificant)
2
(Minor)
3
(Moderate)
4
(Major)
5
(Catastrophic)
A (Almost Certain)
B (Likely)
C (Moderate)
D (Unlikely)
E (Rare)
Table 6-20 Risk Rating Key for Proponent Action and Ultimate
Acceptability
Risk Rank Description
Tolerable Risk reduction not required
Risk Reduction Required Risk reduction measures need to be implemented so that risk is
as low as reasonably practicable
Unacceptable Risk is too great for activity to proceed
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 151
6.15.2 Environmental Hazard Identification and Risk Assessment Outcomes
The environmental hazard identification process and risk assessment procedure has been combined into a single table that assesses all potential major
environmental events in Table 6-21.
Table 6-21 Environmental Hazard Identification and Risk Assessment Outcomes
Major
Environmental
Hazard Event
Potential Environmental Impacts
Risk Ranking
Pre-Management
Risk Mitigation Action
(Prevention or Contingency)
Risk Ranking
Post-Management
Lik
elih
ood
Conseq
uence
Rankin
g
Lik
elih
ood
Conseq
uence
Rankin
g
Clearance
outside of
defined
footprint
Impacts to vegetation and fauna
habitat
C 1 Development footprint delineated on all CEMP mapping,
on-site marking of key sensitive areas, induction and tool
box training for all site staff and visitors and routine audits
of construction footprints.
D 1
Fuel or
chemical spill
Ecological impact on aquatic
flora and fauna in surface
drainage lines and downstream
environment
Contamination of land.
D 3 Fuels and chemicals to be stored in designated roofed,
bunded and secure storage facilities during constriction
(Construction Compound) and operation (within
dewatering building and bulk chemicals store).
Refuelling of equipment during construction to be
undertaken in bunded areas.
Fuel and chemical spill clean-up procedures to be
included in CEMP and OMP documents.
Staff to be trained in spill containment.
D 2
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 152
Major
Environmental
Hazard Event
Potential Environmental Impacts
Risk Ranking
Pre-Management
Risk Mitigation Action
(Prevention or Contingency)
Risk Ranking
Post-Management
Lik
elih
ood
Conseq
uence
Rankin
g
Lik
elih
ood
Conseq
uence
Rankin
g
Burst
treatment
pipelines or
leaking
infrastructure.
Ecological impact on aquatic
flora and fauna in surface
drainage lines and downstream
environment.
Public health and amenity risks.
E 3 Sewage Treatment Plant Contingency Management
Manual developed for the Project with Site Response
Procedures.
Regular infrastructure maintenance, including regular
pipeline flange replacement.
Major
introduction of
weeds or
pathogens
during
construction
phase.
Impacts to existing flora and
fauna values in area.
C 2 Weed and hygiene management and mitigation measures
included in CEMP (e.g. wash-down procedures, staff
training, weed control prior to construction).
D 2
Release of
poorly treated
effluent
through
mechanical
failure or
power outage.
Ecological impacts and potential
human health risks in the
receiving environment
D 3 Redundancy in plant design and emergency generator for
power failures.
Regular maintenance and audits of control systems and
infrastructure by operational staff.
Sewage Treatment Plant Contingency Management
Manual developed for the Project with Site Response
Procedures
Operational staff member on standby when STP is not
manned, with alarm system to automatically notify
standby staff in case of system failure.
D 2
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 153
Major
Environmental
Hazard Event
Potential Environmental Impacts
Risk Ranking
Pre-Management
Risk Mitigation Action
(Prevention or Contingency)
Risk Ranking
Post-Management
Lik
elih
ood
Conseq
uence
Rankin
g
Lik
elih
ood
Conseq
uence
Rankin
g
Release of
substandard
treated effluent
during storm
or large flow
events
Ecological impacts and potential
human health risks in the
receiving environment
A 2 Operational staff onsite or standby staff to alter treatment
methodology to storm mode.
Design capacity of the plant to cater for significantly
increased flows during storm events.
A 1
Large fugitive
odour release
Impacts to amenity of local
residents
C 1 Regular maintenance and audits of odour control systems
and infrastructure by operational staff.
Maintain complaints register and action any complaints
immediately.
D 1
Fire resulting
from
construction or
operation
becomes out
of control or
external fire
Terrestrial habitat destruction
Safety of site personnel and
surrounding residents
D 4 Fire response Site Response Procedure included in
Sewage Treatment Plant Contingency Management
Manual.
Operational and construction staff briefed in emergency
management.
Firefighting equipment on site with staff trained in fire
response.
Vegetation maintenance in proximity to STP.
Bushfire emergency plan will be included in healthy and
safety documentation, including muster points and
firefighting equipment locations.
E 4
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 154
6.15.3 Hazard Analysis Conclusions
The hazard analysis identified fire as the most significant risk to the environment as a result of
the Project. This situation is unchanged from current conditions. Preventative measures and
response procedures are deemed adequate to reduce the risk to as low as reasonably practical.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 155
6.16 Fire Risk
6.16.1 Existing Conditions
The Project Site contains existing trees and is bounded to the west and south by significant
tracts of native vegetation. The closest responding fire brigade to this location would be
Blackmans Bay volunteer brigade.
6.16.2 Performance Requirements
The construction and operation of the Project must fulfil the requirements of the following
legislative and policy requirements in relation to fire risk:
Fire Services Act 1979
Workplace Health and Safety Act 1995
Buildings and associated fire controls must be designed in accordance with the Building Code
of Australia.
6.16.3 Potential Effects, Management and Mitigation
Project Potential Fire Sources
There are a number of potential anthropogenic sources of fire within the Project area both
during construction and operation, including:
Use of vehicle and machinery around dry vegetation (e.g. exhaust system contact);
Hot work around dry vegetation (e.g. welding, electrical work);
Discarded cigarettes;
Electrical faults in facilities (e.g. process plant, administration building, pump stations); and
Storage and use of chemicals and flammable hydrocarbons around site.
These risks (with the exception of elevated risk during the construction phase) are largely
similar to risks from the existing STP (albeit slightly lowered due to decommissioning of the
chlorine gas system).
As well as fires potentially originating from within the Project site, there are a number of external
sources of fire including lighting strikes, arson and burn-offs.
Potential Effects and Management
Any fire originating within or external to the site has the potential to impact on infrastructure,
environmental values and possibly even endanger lives. In addition, any fire event puts
pressure on the State Emergency Services.
The proposed Project poses a small increase in fire risk during construction (new ignition
sources) and a slightly decreased risk once operational due to the decommissioning of the
chlorine gas system which reduces site wide ignition sources. The risk to the infrastructure from
bushfire remains similar.
To manage construction phase fire risk:
All vehicles and machinery will be kept in good working order to minimise the potential for
fires on site;
Any fuels required during the construction phase will be limited in quantity and will be
stored in appropriately bunded facilities;
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 156
Appropriate firefighting equipment will be kept on site during the construction phase and
site staff trained in emergency procedures and use of firefighting equipment; and
Fire risk will be included in the CEMP with emergency protocols clearly defined.
TasWater already has an established Fire Management Plan (covering the existing STP) to
which will be applied to the Project. Site specific measures will include:
Provision of adequate fire hydrants and water for firefighting (in accordance with the
Building Code);
All chemicals and fuels will be correctly stored in purpose-built storage facilities with
appropriate signage and extinguishers present, away from any potential ignition sources;
Site specific fire management will be documented including muster points and emergency
contact details;
Staff and contractor inductions will include a fire safety element, outlining subjects such as
designated smoking areas, site evacuation protocols and muster points; and
Regular fire drills will be undertaken at the site (at least once annually).
6.16.4 Monitoring, Review, and Adaptive Management
Monitoring of fire preparedness will be undertaken through regular annual audits of firefighting
equipment (including water storage and hydrant systems) and through random drill events.
If fire events do occur at the site, actions will be reviewed post-event and changes made to
management and mitigation measures in the original plans where appropriate.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 157
6.17 Infrastructure and off-site Ancillary Facilities
The proposed Project does not involve any changes or upgrades to offsite infrastructure. There
may be some minor modifications to overhead power lines within the Project Site but there will
be no changes to external roads, power lines, pipelines or other infrastructure.
The proposed STP upgrade will involve increased use of existing road networks during the
construction period, with almost no change to operational phase traffic from existing conditions.
Traffic and potential impacts to the regional road network are addressed under Section 6.20 and
are determined to be minimal.
This application relates only to the Project within the Project Site (The Boundaries of the Land)
as delineated in Figure 2-1. The associated decommissioning of Electrona, Margate and
Howden STPs and the piping of sewage from these sites to the newly upgraded Blackmans Bay
STP is excluded from this Project. The Blackmans Bay STP has been sized to accommodate
the potential amalgamation but is not contingent upon it as the current STP requires upgrade to
cater for existing and projected loads from the Blackmans Bay catchment regardless.
In conclusion, there are no measurable impacts to offsite infrastructure anticipated as a result of
the Project.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 158
6.18 Environmental Management Systems
6.18.1 TasWater’s Environmental Management
TasWater operates under a companywide Environmental Policy which sets out the overall
company objectives with respect to environmental management. The Environmental Policy is
approved by the TasWater Board, and the TasWater CEO is responsible for ensuring
companywide compliance with the policy. All staff are required to comply with the spirit and
letter of the policy and its associated procedures. The Policy also requires staff to undertake
training as required, to stay current with the objectives of the Policy.
TasWater also has an Environment and Public Health Committee, whose role is to assist the
Board in fulfilling its responsibilities in relation to environmental and public health management,
performance and compliance. The Committee has a publically available charter and has a role
in assessing emerging environmental and public health issues, overseeing strategic direction,
reviewing the efficacy of the policy and monitoring progress and compliance.
Within this overarching environmental framework this particular project will have a set of
environmental responsibilities during construction and once operational as outlined below.
6.18.2 Construction Environmental Management
Prior to commencement of construction of the Project a CEMP will be prepared which
addresses environmental management during construction and will capture all relevant
management measures and commitments from this DPEMP and associated permits. Based on
the assessment in this DPEMP, the CEMP will provide a tabular summary of the environmental
aspects and impacts of the construction work.
The CEMP will encompass the relevant issues identified in this DPEMP and include, but not be
limited to the following key elements:
Site Management – A system will be developed to manage entry and exit from the site to
ensure that impacts from works do not occur outside the Project area. This includes site
fencing arrangements (as set out in this DPEMP), public access arrangements and fencing
of sensitive vegetation (as set out in this DPEMP).
Erosion Control – The CEMP will include a Soil and Water Management Plan (SWMP) in
accordance with relevant EPA guidance documents, which ensures no significant erosion
or runoff as a result of construction works.
Dangerous Goods – A system will be established for managing the delivery, storage, use
and disposal of all dangerous goods required for construction.
Air Quality – A visual monitoring program to identify unacceptable levels of dust during
construction will be implemented. The CEMP will also outline mitigation measures to be
employed in the event that dust levels are identified as elevated. Such measures may
include the use of water carts, or ceasing work in certain weather conditions.
Noise Management – The CEMP will outline measures for notifying the closest local
residents of noise generating activities, as well as stipulating clear hours of operation (in
accordance with this DPEMP). The CEMP will also outline any necessary controls to
ensure noise levels at the construction site are in accordance with workplace standards,
including measures such as the use of hearing protection if required.
Traffic Management – The CEMP will outline clear procedures for traffic management,
including signage, timing, safety and notification of local area users.
Health and Safety – A system will be developed to manage health and safety on site during
the works.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 159
Waste Management – Procedures for waste management during construction, including the
designation of specific lay-down areas (within the Construction Compound) and transport
and disposal procedures will be developed.
Weed and Disease Control – The CEMP will develop and implement procedures for wash-
down and (if required) disinfection of equipment before entering the site in order to avoid
the introduction of weeds, pest and diseases. This section will also outline weed control
measures to be implemented before and after construction to ensure the works do not
increase the infestation of weeds presently located within the Project Site.
Incident Management – An incident reporting and follow up system will be established in
order to respond effectively and efficiently in the event of an environmental incident.
The CEMP will also set out a program of training. All site staff will undergo a basic
environmental induction to explain the Project Site and Footprint, the Project itself, sensitive
features, risks and impacts, their roles/responsibilities, spill and clean up procedures, reporting
protocols, specific site procedures and environmental issues and features. Additional specific
training may be given to site staff on ad hoc issues identified.
TasWater will appoint a Project Manager for the construction phase. During construction the
Contractor’s Site Manager will be responsible for implementation of the CEMP. Regular
meetings will be held during construction between the TasWater Project Manager and the
Contractors Site Manager to ensure compliance and adherence to the CEMP.
Ultimately, the TasWater CEO will be responsible for ensuring environmental compliance of the
Project.
6.18.3 Operational Environmental Management
Prior to commencement of the operational phase a site specific Operational and Maintenance
(O&M) Manual will be prepared for the upgraded plant. This is a standard TasWater document,
modified to suit the specifics of each STP site.
The O&M Manual will incorporate all salient information from this DPEMP, the commitments in
this DPEMP and resulting permits.
Training will be provided to all site workers with respect to the content of the O&M Manual in
accordance with TasWater’s established training regimes.
The Site Operator will be responsible for day-to-day implementation of the O&M Manual. The
Site Operator reports to the Area Coordinator then to the Manager, Department Manager and
then General Manager. Ultimately, the TasWater CEO will be responsible for ensuring
environmental compliance of the Project.
6.18.4 Monitoring, Review, and Adaptive Management
Monthly audits of compliance against the CEMP will be undertaken during the construction
phase.
The O&M Manual will be reviewed every 5 years once established.
Commitment 34 A site specific Operations and Maintenance Manual will
be prepared and reviewed every five years once established.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 160
6.19 Cumulative and Interactive Impacts
The key discharges from the Project which have the potential for cumulative consideration with
other existing and approved developments in the region are air impacts (odour), noise impacts,
traffic, tree clearance and treated effluent discharge. Each of these matters has been
considered in detail in the relevant sections of this DPEMP. In each of those assessments the
potential for cumulative impacts with existing (ambient) conditions and developments is
provided9. There are no known pending developments in the region that would affect those
assessments.
The most critical cumulative impact to consider with respect to the Project is the discharge of
treated effluent into the marine environment. As outlined in Section 6.8, the Project will
discharge increased flows with significantly improved effluent quality for most parameters
compared to the current Blackmans Bay STP. The Project may also potentially facilitate the
amalgamation of Margate, Electrona and Howden STPs into Blackmans Bay thereby removing
treated effluent from the lower energy North West Bay and transferring it (via the Project effluent
discharge pipeline) into the higher energy Derwent Estuary. The assessment of impact to the
marine environment associated with the Project is provided in Section 6.8 and already takes into
consideration the existing marine environment and its known inputs through the assessment of
available ambient data.
In summary, there are cumulative impacts associated with odour, noise, tree clearance, traffic
and treated effluent discharge but all of these matters have been considered as part of the
detailed assessments in the relevant sections (by including background conditions in each
assessment) and there are no additional cumulative impacts anticipated.
9 E.g. noise assessments consider the background noise environment as part of the modelling, receiving waters
assessments consider the existing conditions in the receiving environment as part of the modelling exercise etc.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 161
6.20 Traffic Impacts
6.20.1 Existing Conditions
The existing Blackmans Bay STP site is accessed from Treatment Plant Road, which is a
subsidiary road of Tinderbox Road East. Under routine operations, the current daily traffic to the
site includes approximately five cars and one to two trucks visiting the site per day.
The local road network can be seen on Figure 2-1.
6.20.2 Potential Effects
Construction
During construction of the Project local traffic is expected to increase and will be composed of
staff vehicles, trucks, utes and vans delivering building materials and equipment. During peak
periods in the construction phase there will be approximately 6-12 trucks visiting the site each
day and 20 trade vehicles and 20 cars or other vehicles. Although the construction phase is up
to two years in duration, peak traffic volumes will only be experienced for very short periods
during this time, when active phases of construction are occurring (e.g. bulk earthworks and
building construction). During the remaining time only small volumes of vehicles will be
accessing the site each day.
During periods of intense vehicular activity to the site the increased traffic volumes (particularly
large vehicles) have the potential to generate noise and dust nuisance to local residents. The
key management measures to alleviate these impacts are restrictions on construction hours,
covering of potentially windblown loads and washing of trucks prior to exit as outlined below.
Construction access to the site will be via Treatment Plant Road, Tinderbox Road and then via
either Algona Road or Roslyn Avenue before reaching the major Highways (Southern Outlet,
Channel Highway, Huon Highway) depending on the direction of travel.
There are no residential properties on Treatment Plant Road and it is understood that
approximately 8,000 vehicles a day currently use Tinderbox Road East. The increase in traffic
caused during the construction process is considered to be both manageable and a relatively
minor impact.
The roads to be used for construction are Council and State Roads and considered to be of
suitable capacity to cater for the proposed temporary increase in traffic.
Operation
The proposed traffic volumes during operation are not expected to be significantly different from
current vehicle movements for the existing STP.
As outlined in Section 2.6.3 the expected traffic to the site once the Project construction is
complete and the plant reaches full capacity (noting truck movements will be less in the
intervening period) is:
Three staff cars per day
One truck per day (on average) collecting biosolids (at max plant capacity);
One truck per week collecting grit and screenings;
Up to three trucks per week delivering chemicals or other supplies.
This equates to approximately three cars and 1-2 trucks per day visiting the Project site during
normal operations; this is almost unchanged from current conditions.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 162
During maintenance periods up to 25 vehicles could visit the site on any one day, but this would
be limited to infrequent events lasting up to one week at a time and is consistent with the current
STP.
Vehicles will be visiting the site during normal operating hours and will not be travelling off-road,
therefore the potential for noise or dust impacts above existing levels is low.
6.20.3 Management and Mitigation
To address the residual impact during construction, the following management measures are
proposed.
All loads entering or leaving the site with potentially windblown materials will be covered
(refer Section 6.1.3).
A wheel wash will be installed at the site entrance and all vehicles with visible mud or dirt
will be washed upon entry and prior to leaving to minimise spread of weeds or dust/mud
onto surrounding roads.
The Contractor will develop a Traffic Management Plan prior to construction which will be
adhered to for the life of the construction phase. This may include the need for specific
traffic management personnel at both the site access and Treatment Plant Road.
The Contractor will also provide sufficient onsite parking (within the Construction
Compound and already cleared areas within the newly fenced Project site) for workers and
deliveries to avoid any offsite parking.
The Contractor will avoid the period of peak traffic (morning and evening) for delivery of
equipment and building materials where practicable.
6.20.4 Monitoring, Review and Adaptive Management
TasWater is committed to proactive community and stakeholder engagement leading up to, and
during, construction. The Contractor will maintain an online complaints register for any traffic
complaints received. Any complaint received will be promptly dealt with including informing the
complainant of the resolution, and keeping a record of the complaint and its resolution.
Commitment 35 The contractor will prepare Traffic Management Plan
(either stand alone or as part of the CEMP) prior to construction.
Commitment 36 An online complaints register will be maintained during
the construction period and any traffic related complaints will be
registered, addressed and reported back to the complainant.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 163
7. EPBC Act Assessment
7.1 Background
The Project has not been referred to the Commonwealth Department of the Environment (DoE)
as it has been assessed as unlikely to significantly impact on any Matters of National
Environmental Significance (MNES) or other matters protected under the EPBC Act. An outline
of the assessment is provided below.
7.2 Matters of National Environmental Significance
The online Protected Matters Search Tool was used to investigate the Project Site and its
surrounds (using a 2 km buffer) for any MNES or other matters present. The EPBC Act
Protected Matters Report generated is included in Appendix B, with findings summarised as
follows:
World Heritage Properties - no world heritage properties within the Project Site or buffer
area queried.
National Heritage Places - no natural heritage places within the Project Site or buffer area
queried.
Wetlands of International Importance - no wetlands of international importance within the
Project Site or buffer area queried.
Listed threatened species - listed species predicted and/or known to occur within 2 km of
the Project Site. Further information is provided below.
Listed Threatened Ecological Communities (TEC) - TEC likely to occur within area. Further
information is provided below.
Migratory species - Potential for migratory species to occur within or nearby to the site.
Further information is provided below.
Commonwealth Reserves - no Commonwealth Reserves within or nearby to the site
Great Barrier Reef Marine Park - No impacts to the Great Barrier Reef.
Nuclear actions - No nuclear actions are proposed.
Water resource in relation to coal seam gas development and large coal mining - not
applicable
Potential impacts on identified protected.
7.3 Listed Ecological Communities
Giant Kelp Marine Forests of South-East Australia are listed as a TEC under the EPBC Act. In
the Derwent Estuary immediately east of the site, and located inshore from the existing outfall
from the STP, is the Blackmans Bay Giant Kelp Forest. In 2014 CEE undertook an ecological
risk assessment to determine whether the kelp forest met the TEC listing criteria to be
considered part of the Giant Kelp Marine Forests of South-East Australia.
CEE (2015)10 found that the Giant Kelp forest at Blackmans Bay fulfils most of the criteria to be
considered part of the TEC, however it does not occur in water more than 8 m deep (one of the
10 CEE 2015, Internal memo - Blackmans Bay STP Upgrade - Assessment of effects on Giant Kelp and North
West Bay ecosystem, January 2015
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 164
defining characteristics). They therefore concluded the kelp forest to not fulfil the TEC definition
for Giant Kelp Marine Forests of South-East Australia.
There are no other EPBCA listed ecological communities within the Project site (or adjacent and
potentially impacted by the Project).
Based on this assessment by CEE, no significant impacts to listed ecological communities are
anticipated.
7.4 Listed Threatened Species and Migratory Species
7.4.1 Flora
There were no EPBC Act listed flora species recorded within the Project Site and given the
timing of the surveys and vegetation communities encountered it is considered unlikely that any
were overlooked. Therefore no impacts to listed flora species are anticipated (Section 6.7.3).
7.4.2 Fauna
As outlined in Section 6.7, a small number of EPBC Act listed threatened and migratory species
may occur within the Project Site. The points below are a summary of pertinent information. A
full assessment is provided in Section 6.7.
Swift parrot (Lathamus discolour)
– The swift parrot may forage and nest within the Project Site, which contains two of their
preferred feeding tree species E. globulus and E. ovata. There are also a small number
of hollow bearing eucalypts within the Project Site but outside of the Project Footprint.
In summary, no hollow bearing trees will be impacted by the proposed works, and only
1.2% (approximately) of the available E. globulus foraging habitat on the Project Site
will be cleared. TasWater have made a commitment to plant new E.globulus for all
mature E.globulus removed at a ratio of 1 to 3. Overall the impacts to swift parrot
through tree clearance are not likely to significantly impact the species.
Eastern barred bandicoot (Perameles gunnii)
– The Eastern barred bandicoot may forage within the grassy eucalypt forest on site,
however the site is unlikely to provide key habitat for this species (in the context of
better quality habitat available in the local area). The loss of up to 1.2% of E. globulus
forest is not expected to significantly impact the Eastern barred bandicoot.
Eastern quoll (Dasyurus viverrinus)
– The Eastern quoll may also occur on site however the site is unlikely to provide key
denning/nesting habitat. The loss of the small area of E. globulus forest will not
significantly impact the Eastern quoll.
The project is considered not likely to have a significant impact on the identified threatened
fauna species potentially occurring, namely the swift parrot (Lathamus discolour), Eastern
barred bandicoot (Perameles gunnii), or the Eastern quoll (Dasyurus viverrinus).
Whilst other EPBC Act listed species fauna (including migratory species) may occur in the
marine environment offshore from the Project the potential for impact to such species is
considered to be low as outlined in Section 6.8 and significant impacts are unlikely.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 165
8. Monitoring and Review
In order to monitor ongoing performance of the STP and success of the mitigation measures in
this DPEMP, the following monitoring is proposed:
Treated effluent monitoring;
Sludge monitoring;
Receiving waters monitoring;
Terrestrial ecology monitoring; and
Construction phase monitoring.
Details of each monitoring programs are provided in the relevant section of this DPEMP and
summarised below. The outlined monitoring programs are proposed and will be subject to EPA
and Council consideration and inclusion in resulting permits. Commitments in relation to this
monitoring are provided below or under the relevant section of this DPEMP.
8.1.1 Treated Effluent Monitoring
Flow meters will be installed on the new STP to measure flows of treated effluent from the plant.
Treated effluent will be sampled immediately prior to discharge (tap on the discharge pipe).
Grab samples will be taken and analysed for a range of parameters as summarised in Table
8-1. Relevant QA/QC samples will be collected also.
The treated effluent is considered to be adequately characterised already and no contaminants
of concern were identified from existing effluent analysis (aside from normal wastewater
toxicants such as ammonia). This analysis also took into account potential additional STP waste
streams and trade waste sources from the potential amalgamation STPs. Therefore, whole of
effluent toxicity (WET) testing is not proposed at this stage.
Table 8-1 Treated Effluent Sampling
Parameter Units of measurement Sampling frequency
Flow (influent) ML/day Continuous (flow meter) (checked
weekly)
Flow (effluent) ML/day Continuous (flow meter) (checked
weekly)
Water quality (in-situ)
pH - Weekly
Temperature °C Weekly
Conductivity µS/cm Weekly
Water quality (grab sample) (Laboratory)
Biochemical Oxygen
Demand
mg/L Weekly
Suspended Solids mg/L Weekly
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 166
Parameter Units of measurement Sampling frequency
Ammonia-Nitrogen mg/L Weekly
Nitrate-Nitrogen mg/L Weekly
Nitrite-Nitrogen mg/L Weekly
Total Nitrogen mg/L Weekly
Total Phosphorus mg/L Weekly
Oil and Grease mg/L Weekly
Thermotolerant Coliforms cfu/100mL Weekly
Enterococci cfu/100mL Weekly
As, Cd, Cr (tot), Cu, Pb,
Mn, Hg, Ni, Se, Zn
mg/L Annually
Commitment 37 Continuous flow monitoring will be undertaken at the
STP to measure inflows and outflows from the plant.
Commitment 38 Weekly and annual treated effluent grab samples will be
collected and analysed for the parameters outlined in Table 8-1.
8.1.2 Sludge/Biosolids monitoring
Biosolids will be monitored in accordance with the Tasmanian Biosolids Reuse Guidelines 1999,
or as otherwise approved by the EPA Director.
Commitment 39 Biosolids will be monitored in accordance with the
Tasmanian Biosolids Reuse Guidelines 1999, or as otherwise
approved by the Director.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 167
8.1.3 Receiving Environment Monitoring
Receiving environment monitoring is outlined in Section 6.8.4, with sampling sites illustrated on
Figure 6-13. The proposed sampling program is summarised below, but for full details refer
back to the relevant section. Water monitoring is conducted at a number of different depths at
each site (refer Section 6.8.4) for details.
Table 8-2 Receiving Environment Monitoring
Monitoring Type Sites Parameter Frequency
Water
Monitoring
Outfall
North of outfall (15m,
50m, 100m and
250m)
South of outfall (15m,
50m, 100m and
250m)
East of Outfall (15m)
Reference sites 1
and 2 (DEP sites B1
& B3)
Physicochemical* (pH,
Temperature, Salinity,
Dissolved oxygen, Turbidity)
Nutrients** (Total Nitrogen,
Ammonia as N, Nitrate as N,
Nitrite as N, Total Phosphorus
as P, Reactive Phosphorus as
P, Chlorophyll a)
Other** (Chloride, Oil and
Grease, Total Dissolved
Solids, Total Suspended
Solids, Thermotolerant
Coliforms)
Dissolved metals suite** (Sb,
As, Be, B, Cd, Cr, Co, Cu, Pb,
Mn, Mo, Ni, Se, Ag, Sn, Zn) to
be ceased 12 months post
commissioning if no difference
pre and post commissioning
detected
-biannually prior to
commissioning
(summer / winter) at
the approval of the
Project
-Once during the 6-
month
commissioning
period
-biannually in the
year following
commissioning
-Annually following
year 1
Kelp sites 1, 2,3 Physicochemical* (pH,
Temperature, Salinity,
Dissolved oxygen, Turbidity)
Nutrients** (Total Nitrogen,
Ammonia as N, Nitrate as N,
Nitrite as N, Total Phosphorus
as P, Reactive Phosphorus as
P, Chlorophyll a)
Benthic Infauna Outfall
North of outfall (15m,
50m, 100m and
250m)
South of outfall (15m,
50m, 100m and
250m)
East of the outfall
(15m)
Collection of benthic infauna
samples as per the
methodology stipulated in CEE
(2015b)
-Once pre
commissioning
-Once during the 6-
month
commissioning
period
-biannually in the
year following
commissioning
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 168
Monitoring Type Sites Parameter Frequency
-Triennially following
first 12 months
Kelp Monitoring 0-100 m north of
fertiliser ports
0-100 m south of
fertiliser ports
0-100 m south of
fertiliser ports (outer)
Diver transects counting
number of stipes within 1m of
transect, changing sides every
10m of transect. Also canopy
density estimated every 10m,
based on a 1-4 ranking with 1
being no coverage, 1 being
25% and 4 being 100%.
-Once pre
commissioning
-Twice in first 12
months following
commissioning
- Annually following
year 1 (frequency to
be reviewed three
years following
commissioning with
the EPA)
* In situ and depth profile of whole water column at 1m intervals to be collected.
** Laboratory
8.1.4 Terrestrial Ecology Monitoring
The following terrestrial ecology monitoring is proposed to manage the risk of weeds/pathogens
at the site as well as measuring the success of proposed revegetation and landscaping:
An initial pre construction weed treatment will be undertaken, followed by 6 monthly weed
surveys during construction, and additional weed control applied as required.
Results of 6 monthly surveys will be documented and provide to TasWater (and regulatory
authorities on request)
A post construction weed, pathogen and revegetation success survey will be undertaken at
the completion of construction, with follow up surveys completed annually thereafter for a
period of 5 years.
The surveys will include the establishment of photo points in the revegetated/landscaped
areas in order to assess long term survival rates of planted species, weed invasions,
success of any watering regimes and requirements for supplementary plantings.
The result of each survey event will be documented and made available to regulatory
authorities on request.
All monitoring will be undertaken by a suitably qualified person with experience in weed and
revegetation monitoring. Any remedial actions as a result of the monitoring program will be
communicated to TasWater and actioned.
8.1.5 Construction Phase Monitoring
During the construction phase routine monitoring will be undertaken (to be stipulated in the
CEMP). As a minimum the following is proposed:
Daily visual inspections of dust from earthworks;
Weekly visual inspections of run-off from works, sedimentation ponds and any diversion or
perimeter drainage lines for integrity and effectiveness;
Regular inspection of machinery for fluid leaks;
Regular (monthly) audits of hazardous material storage, including identification of any non-
compliant storage locations or conditions;
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 169
Regular (monthly) audits of waste management including identification of any windblown
waste, odorous waste or opportunities for recycling;
Surveillance during earthmoving for unanticipated heritage finds;
Construction phase weed surveys (outlined above);
Health and safety monitoring; and
Construction waste monitoring.
All monitoring and audits during construction will be documented and provided to TasWater (or
regulatory authorities) on request.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 170
9. Decommissioning and Rehabilitation
The proposed upgraded Blackmans Bay STP has a design life in the order of 50 to 100 years.
In addition, the planning undertaken by TasWater (and other parties) in recent years has
considered the overall Kingborough sewage network, not only Blackmans Bay in isolation. As a
result, the proposed Blackmans Bay STP upgrade has been designed with capacity up to at
least 2040, including allowance for the future amalgamation of Electrona, Margate and Howden
STPs into Blackmans Bay STP as part of this planning process. This process provides a reliable
indication that the upgraded STP will not be in line for decommissioning for a very long time.
At such time as decommissioning is required, the following broad steps will apply:
Decommission all plant and infrastructure and divert effluent elsewhere (location to be
determined in the future);
Undertake a preliminary Environmental Site Assessment to understand contamination risk;
Disconnect all site services and dismantle and remove all above ground infrastructure;
Undertake intrusive Environmental Site Assessment (if required) and excavate and
remediate any contaminated materials;
Regrade the site to a stable condition;
Landscape the site with local native species to complete the surrounding land; and
Undertake validation sampling and final contamination reporting.
A detailed Decommissioning and Rehabilitation Plan will be prepared for the site at such time as
directed by the EPA.
Commitment 40 A Decommissioning and Rehabilitation Plan will be
prepared for the site at such time as directed by the EPA.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 171
10. Commitments
A summary of commitments is made in Table 10-1 below. The responsible party for all
commitments is TasWater.
Table 10-1 Commitments
No. Commitment Section of DPEMP
1 Trucks with potentially windblown materials will be covered. Air
2 Daily visual monitoring of the site for dust will be untaken
during construction and water sprays applied to roads and
stockpiles if needed.
Air
3 A complaints register will be established for both the
construction and operational phases. All complaints will be
logged, actioned and all outcomes documented.
Air
4 TasWater will undertake community and stakeholder
engagement leading up to, and during, construction.
Air
5 A Construction and Environmental Management Plan
(CEMP) will be developed prior to commencement of
construction.
Surface Water
6 A Soil and Water Management Plan (SWMP) will be
incorporated into the Site Construction and Environmental
Management Plan (CEMP).
Surface Water
7 Weekly monitoring of water and sediment control measures
will be undertaken during the construction period, with
additional monitoring within 24hrs of a storm event.
Surface Water
8 Prior to construction a detailed stormwater design will be
prepared (including review of the existing stormwater
capture) to achieve the stormwater management targets for
new developments as set out in the State Stormwater
Strategy 2010 (unless it is not feasible to do so).
Surface Water
9 Any spills of environmentally harmful liquids greater than 100
L will be reported to the EPA, with commitment to undertake
a groundwater monitoring event if deemed necessary by the
EPA.
Groundwater
10 Noise complaints will be tracked using the online complaints
register. All complaints will be logged, actioned and all
outcomes documented.
Noise
11 Detailed design will address the required noise limits on
equipment and acoustic enclosures as stipulated in this
DPEMP and the Vipac Noise Report (2016); namely 85dBA
or less for the inlet works, 80dBA (at 1m) or less for the
odour control fan, 89dBA or less for the odour control fan
Noise
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 172
No. Commitment Section of DPEMP
inlet duct and 84dBA or less for the exhaust from the odour
control fan.
12 Care will be taken in the development and selection of
enclosures for the IDEA blowers such that tonal noise
emission breakout doesn’t generate potentially intrusive
noise emissions.
Noise
13 A targeted inspection of areas proposed for subsurface
excavations will be undertaken by a Certified Practitioner
(Site Contamination Practitioners Australia) prior to
construction to identify any areas of high risk for land
contamination for subsequent soil testing, classification and
management.
Waste
14 A Sewage Sludge Management Plan (SSMP) will be
developed for the Project.
Waste
15 All hazardous materials will be stored in suitably bunded
areas in accordance with the relevant guidelines.
Dangerous Goods
and Hazardous
Materials
16 Any spilt waste will be immediately reported to the site
manager and clean-up will occur.
Dangerous Goods
and Hazardous
Materials
17 Inspections and audits of environmentally hazardous
material use and storage will be undertaken monthly.
Dangerous Goods
and Hazardous
Materials
18 Dangerous goods and environmentally hazardous materials
storage, handling and clean up procedures will be
incorporated into the site CEMP for the construction phase
and the Operations and Maintenance Manual during the
operational phase.
Dangerous Goods
and Hazardous
Materials
19 All areas of DGL community outside of the immediate
development footprint will be flagged with temporary high
visibility fencing and protected during construction works.
Biodiversity
20 All eucalypts outside of the immediate development footprint
will be flagged with flagged with temporary high visibility
fencing and protected during construction works.
Biodiversity
21 Replacement planting will be undertaken for all mature
Eucalypt trees removed at a ratio of 3:1 as part of the
Landscaping Plan.
Biodiversity
22 Weed and hygiene management will be incorporated into the
site CEMP following the principles outlined in this DPEMP.
Biodiversity
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 173
No. Commitment Section of DPEMP
23 Annual monitoring for the first five years of the landscaped
area to assess success of tree growth, weed invasion and
replacement plantings.
Biodiversity
24 An initial pre construction weed treatment will be undertaken,
followed by 6 monthly weed surveys during construction, and
additional weed control applied as required.
Biodiversity
25 A post construction weed, pathogen and revegetation
success survey will be undertaken at the completion of
construction, with follow up surveys completed annually
thereafter for a period of 5 years.
Biodiversity
26 Receiving waters monitoring will be undertaken at 15 sites
(as shown in Figure 6 12) biannually pre-commissioning,
during commissioning and in the first year of operation and
annual thereafter.
Marine and
Coastal
27 Benthic infauna monitoring will be undertaken at 10 sites (as
shown in Figure 6 12) once pre-commissioning, once during
commissioning, biannually in the first year and triennially
thereafter.
Marine and
Coastal
28 Kelp monitoring will be undertaken at 3 sites; once pre-
commissioning, twice in the first year following
commissioning and annually thereafter (until reviewed with
the EPA).
Marine and
Coastal
29 If the monitoring program reveals marine impacts as a result
of phosphorus in the STP discharge, the EPA will be
contacted and phosphorus removal will be retrofitted to the
STP and new emission limits established in consultation with
the EPA.
Marine and
Coastal
30 An Unanticipated Discovery Plan will be included in the Site
CEMP and followed in the event of discovery of previously
undetected heritage features.
Heritage
31 A vegetation screen will be planted along the western
boundary of the new STP as outlined on the Figures in this
DPEMP.
Visual
32 A Health and Safety Management Plan (HSMP) will be
prepared for the construction phase and incorporated into
the Site CEMP.
Health and Safety
33 Health and safety management will be included in the site
specific Operations and Maintenance Manual.
Health and Safety
34 A site specific Operations and Maintenance Manual will
prepared and reviewed every 5 years once established.
EMS
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 174
No. Commitment Section of DPEMP
35 The contractor will prepare Traffic Management Plan (either
stand alone or as part of the CEMP) prior to construction.
Traffic
36 An online complaints register will be maintained during the
construction period and any traffic related complaints will be
registered, addressed and reported back to the complainant.
Traffic
37 Continuous flow monitoring will be undertaken at the STP to
measure outflows from the plant.
Monitoring
38 Weekly and annual treated effluent grab samples will be
collected and analysed for the parameters outlined in Table
8 1.
Monitoring
39 Biosolids will be monitored in accordance with the
Tasmanian Biosolids Reuse Guidelines 1999, or as
otherwise approved by the Director.
Monitoring
40 A Decommissioning and Rehabilitation Plan will be prepared
for the site at such time as directed by the EPA.
Decommissioning
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 175
11. Conclusion
The Blackmans Bay STP upgrade involves capacity and performance improvements to the
existing Blackmans Bay STP, located in southern Tasmania.
The upgrade will benefit the Kingborough area, both now and for future generations, by
improving capacity and performance of the Blackmans Bay STP and allowing TasWater to
consolidate and enhance the Kingborough sewerage system to accommodate future growth in
the area and centralise waste from local catchments so underperforming STPs at Electrona,
Margate and Howden can be closed - providing long term benefits to North West Bay. It will
also improve overall effluent treatment to improve the quality of water discharged to the
Derwent Estuary and meet EPA compliance requirements.; as well as improving odour and
noise issues for local residents.
The Project involves retrofitting of some existing infrastructure on site, construction of some new
infrastructure and continued use of the existing treated effluent outfall into the Derwent Estuary.
The plant upgrades are crucial to address ageing infrastructure, limits to future capacity, existing
issues with meeting emission limits and ongoing odour issues. The STP upgrade has been
sized to accommodate future amalgamation of Margate, Electrona and Howden STPs into
Blackmans Bay. These plants are also experiencing issues with ageing infrastructure and future
capacity limitations. By closing these plants treated effluent can be removed from North West
Bay (where the plants currently discharge) and redirected through the newly upgraded
Blackmans Bay STP to the higher energy Derwent Estuary. This poses a significant positive
outcome for North West Bay.
For most parameters, the upgraded STP will achieve significantly improved treated effluent
quality. This results in an improvement to the receiving environment, particularly with regard to
nitrogen and ammonia, which are predicted to achieve a reduction in overall mass loads to the
Derwent Estuary even at the full flows from the upgraded STP (8.53 ML/day ADWF) due to the
significant improvement in nitrogen removal from the new plant. Some parameters however will
see a gradual increase in mass loads (particularly phosphorus) to the Derwent Estuary due to
the proposed emission limits and the gradual increase in flows from Blackmans Bay and the
redirection of Margate, Electrona and Howden flows from North West Bay to the Derwent
Estuary. The impact to the receiving environment has been assessed in detail in Section 6.8.
The proposal involves some clearance of mature eucalypt species and a very small area of a
threatened vegetation community but is predominantly focused on already disturbed land.
TasWater has committed to a landscaping program replacing all mature eucalypts removed with
new trees at a ratio of 3 to 1.
There will be some changes to odour and noise impacts from the upgraded STP on the
surrounding properties (refer Sections 6.1 and 6.4) but these are within established guideline
limits and generally represent a similar or improved situation in comparison to current
conditions.
Overall the Project offers a significant improvement in wastewater treatment capacity, quality
and reliability, while posing a relatively small number of environmental and social impacts.
Treatment plant upgrades and expansions are an essential part of maintaining the State’s
wastewater assets for current and projected population growth and the Blackmans Bay site has
been carefully selected and designed to minimise impacts as far as practical whilst allowing the
provision of long term wastewater treatment in the Kingborough region.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 176
12. Limitations
This report: has been prepared by GHD for TasWater and may only be used and relied on by
TasWater for the purpose agreed between GHD and the TasWater for understanding the
environmental and planning implications of the proposed development.
GHD otherwise disclaims responsibility to any person other than TasWater arising in connection
with this report. GHD also excludes implied warranties and conditions, to the extent legally
permissible.
The services undertaken by GHD in connection with preparing this report were limited to those
specifically detailed in the report and are subject to the scope limitations set out in the report.
The opinions, conclusions and any recommendations in this report are based on conditions
encountered and information reviewed at the date of preparation of the report. GHD has no
responsibility or obligation to update this report to account for events or changes occurring
subsequent to the date that the report was prepared.
The opinions, conclusions and any recommendations in this report are based on assumptions
made by GHD described in this report. GHD disclaims liability arising from any of the
assumptions being incorrect.
GHD has prepared this report on the basis of information provided by TasWater and others who
provided information to GHD (including Government authorities)], which GHD has not
independently verified or checked beyond the agreed scope of work. GHD does not accept
liability in connection with such unverified information, including errors and omissions in the
report which were caused by errors or omissions in that information.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 177
13. References
ANZECC & ARMCANZ (2000) National Water Quality Management Strategy: Australian and
New Zealand Guidelines for Fresh and Marine Water Quality.
BOM (2016). http://www.bom.gov.au/climate/averages/tables/cw_094029.shtml (accessed
26/7/2016)
CEE (2007) Kingborough Wastewater Management Strategy, Long Term Strategy Consulting
Environmental Engineers, 2009
CEE (2009a) Development Plan and Environmental Management Plan for Blackmans Bay
Outfall Extension. Consulting Environmental Engineers, 2009.
CEE (2009b) Marine Baseline Study for Blackmans Bay Outfall Extension, Baseline Monitoring
Report: Blackmans Bay Outfall Extension. Consulting Environmental Engineers, December,
2009.
CEE (2015a) Blackmans Bay Outfall: Water Quality Monitoring Program. Consulting
Environmental Engineers, December 2015
CEE (2015b) Blackmans Bay Outfall: Marine Ecological Monitoring Program, Infauna
Community and Giant Kelp, Sixth Operational Survey. Consulting Environmental Engineers,
December 2015
CEE (2015c), Internal memo – Blackmans Bay STP Upgrade – Assessment of effects on Giant
Kelp and North West Bay ecosystem, January 2015.
DEP (2015) Coughanowr C, Whitehead S, Whitehead J, Einoder L, Taylor U and Weeding, B,
2015. State of the Derwent estuary: a review of environmental data from 2009 to 2014. Derwent
Estuary Program
DoE (2014). National Greenhouse Accounts Factors, Australian National Greenhouse Accounts.
Department of the Environment, July 2014.
DPIPWE (2016) Natural Values Atlas, viewed 19/07/2016, Department of Primary Industries,
Parks, Water and Environment (DPIPWE), Hobart.
EPA (2003). Protected Environmental Values (PEVs) for the Derwent Estuary downstream of
the New Norfolk Bridge to Tinderbox/South Arm, EPA, December 2003.
Herzfeld, M., Parslow, J., Margvelashvili, N., Andrewarth, J.R., and Sakov, P. Numerical
Hydrodynamic Modelling of the Derwent Estuary, Final Report. CSIRO, Hobart, March 2005.
Tasflora (2014) Flora and Fauna Assessment – Blackmans Bay Wastewater Treatment Plant
Upgrade, November 2014, Sandy Bay.
Vipac (2016) Blackmans Bay STP Environmental Noise Assessment Report No. 421451-01.
Vipac Engineers & Scientists, Kings Meadows Tasmania, July 2016.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107
Appendices
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 179
Appendix A - Design Drawings
Site plan
Elevations
Landscape Plan
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 180
Appendix B - Ecological Appendices
TasFlora (2014) Flora and Fauna Assessment Blackmans Bay Wastewater Treatment Plant
Upgrade
Natural Values Atlas Report (2016)
EPBCA Protected Matters Search Report (2016)
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 181
Appendix C - Sewage Treatment Plant Contingency Management Manual
TasWater (2015) Sewage Treatment Plant Contingency Management Manual
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 182
Appendix D - Near-field Modelling of Effluent
GHD (2016) Blackmans Bay STP DPEMP Near Field Modelling of Effluent
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 183
Appendix E - Odour Modelling Report
MWH (2016) Blackmans Bay Wastewater Treatment Plant Odour Impact Assessment
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 184
Appendix F - Noise Modelling Report
Vipac (2016) Blackmans Bay STP Environmental Noise Assessment
Vipac (2014) Blackmans Bay STP Stage 1 Acoustic Assessment
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 185
Appendix G - Marine Monitoring Reports
CEE (2015a) Blackmans Bay Outfall: Water Quality Monitoring Program. Consulting
Environmental Engineers, December 2015.
CEE (2015b) Blackmans Bay Outfall: Marine Ecological Monitoring Program, Infauna
Community and Giant Kelp, Sixth Operational Survey. Consulting Environmental Engineers,
December 2015.
CEE (2015c), Internal memo – Blackmans Bay STP Upgrade – Assessment of effects on Giant
Kelp and North West Bay ecosystem, January 2015.
GHD | Report for TasWater - Blackmans Bay STP DPEMP, 3218107 | 186
Appendix H – EPA Project Specific Guidelines
EPA (2014) Final DPEMP Project Specific Guidelines for TasWater Blackmans Bay WWTP
Upgrade, Blackmans Bay, Tasmania
GHD
2 Salamanca Square T: 61 3 6210 0600 F: 61 3 6210 0601 E: [email protected]
© GHD 2016
This document is and shall remain the property of GHD. The document may only be used for the purpose for which it was commissioned and in accordance with the Terms of Engagement for the commission. Unauthorised use of this document in any form whatsoever is prohibited.
3218107-54664/https://projects.ghd.com/oc/Tasmania/blackmansbaystpdpemp/Delivery/Documents/DPEMP - Final.docx
Document Status
Rev No.
Author Reviewer Approved for Issue
Name Signature Name Signature Date
A Various D Elson DRAFT A Jungalwalla
DRAFT 8/8/2016
B Various A Jungalwalla
DRAFT A Jungalwalla
DRAFT 16/8/2016
1 Various A Johnson
A Jungalwalla
25/10/2016
www.ghd.com