TASK 2 FINAL REPORT.pdf

Embed Size (px)

Citation preview

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    1/94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,BOKPOORT

    TECHNICAL ADVISOR FOR A

    CSP PROJECT IN SOUTH AFRICA

    Task 2

    Owner Technical Specification Revision andPlant Configuration Study

    Final Report

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    2/94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,BOKPOORT

    DOCUMENT REVIEW

    Review Date Changes

    0 13/12/2010 Document Creation

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    3/94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,BOKPOORT

    CONTENTS

    1 OVERVIEW ........................................................................................................... 5

    2 DNI ASSESSMENT ............................................................................................... 6

    2.1 Available data ................................................................................................. 6

    2.1.1 Satellite derived data analysis ............................................................... 8

    2.2 Alternative sources of data .............................................................................. 9

    2.2.1 Analysis of alternative sources of data ................................................ 13

    2.3 Generation of PoE scenarios for annual hourly DNI data sets ....................... 14

    3 PLANT CONFIGURATION DESIGN .................................................................... 16

    3.1 General Design Parameters .......................................................................... 16

    3.2 Power block design ....................................................................................... 17

    3.2.1 Steam cycle considerations ................................................................. 17

    3.2.2 Different cooling alternatives considered ............................................. 19

    3.3 Solar field design .......................................................................................... 25

    3.3.1 Main equipment consideration ............................................................. 25

    3.3.2 Solar field configuration ....................................................................... 25

    3.3.3 Solar field alternatives studied ............................................................. 26

    3.4 Performance models ..................................................................................... 27

    3.4.1 Solar radiation ..................................................................................... 27

    3.4.2 Solar Field ........................................................................................... 28

    3.4.3 Power Plant availability ....................................................................... 30

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    4/94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,BOKPOORT

    3.5.4 Auxiliary cooling circuit's replacement ................................................. 34

    3.5.5 Services water..................................................................................... 34

    3.5.6 Potable water ...................................................................................... 35

    3.5.7 Fire Protection System Water .............................................................. 35

    4 POWER PLANT CALCULATIONS ....................................................................... 36

    4.1 Power Block .................................................................................................. 36

    4.1.1 Heat and mass balances ..................................................................... 36

    4.1.2 Power block efficiencies ...................................................................... 36

    4.1.3 Water Balances ................................................................................... 39

    4.2 Comparative Solar Advisor Model / Propietary Model ................................... 39

    4.3 Performance results ...................................................................................... 40

    4.3.1 Option 1: LFO used only for anti-freezing and gland steam generation 41

    4.3.2 Option 2: LFO firing up to 15%. ........................................................... 51

    5 POWER PLANT OPTIMIZATION ........................................................................ 61

    5.1 Methodology ................................................................................................. 61

    5.2 Assessment CAPEX & OPEX ....................................................................... 61

    5.3 LCOE ............................................................................................................ 63

    5.4 Best configuration ......................................................................................... 64

    5.4.1 Detailed results ................................................................................... 64

    5.5 Radiation scenarios ...................................................................................... 71

    ANNEX 1: WATER BALANCES .................................................................................. 77

    ANNEX 2: CAPEX ...................................................................................................... 78

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    5/94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,BOKPOORT

    1 OVERVIEW

    The main objective of this report it is to show the results of the CSP power plant sizing

    that, ACWA Power is developing in Bokpoort, North Cape Region in South Africa.

    This report covers all topics included in Task 2 of the contract for Technical Adviser fora CSP project in South Africa, celebrated among ACWA Power and SOLIDA. Namely,

    those topics can be summarized as follows:

    1. Assessment of yearly DNI PoE scenarios for the plant site, located in

    Bokpoort, South Africa. Yearly time series must be derived by SOLIDA based

    on the available data and following their best criteria. As pointed out by ACWA

    Power, it is better at this stage to play a conservative approach in this regard

    and make sure that the DNI values utilized are not higher than those confirmedonce the actual year-round time series are available from the meteo station.

    2. Assessment of yearly LFO usage. It is not yet clear the approach to be

    followed by the South African government regarding maximum yearly

    consumption of fossil fuels in CSP plants under the REFIT scheme. In addition

    to that, LFO costs at the plant site are very high. For those reasons, ACWA

    Power has indicated that it is necessary to evaluate two different alternatives:

    Option 1: LFO usage only for anti-freezing labors and gland steamgeneration, in order to minimize LFO consumption.

    Option 2:LFO usage to enhance the yearly output, using auxiliary LFO

    heaters.

    3. Assessment of different cooling options in plant performance.It is not yet

    clear what will be the outcome of the water concession permitting for the CSP

    plant in Bokpoort. All options, going from wet cooling tower to air cooledcondenser, are considered and compared in this report.

    The report is structured so that the different topics are covered in chronological order,

    i.e. the order in which SOLIDA has confronted each of them. The starting point is the

    DNI assessment, where thorough explanations are given regarding the available data

    and the PoE scenarios derived by SOLIDA After that different plant configuration

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    6/94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,BOKPOORT

    2 DNI ASSESSMENT

    2.1 Available data

    SOLIDA has had access to the following sources of data concerning solar resource

    evaluation at the site:

    - Satellite derived data:

    o NASA Data Base: Monthly values of global horizontal radiation (Ghi) and

    normal direct radiation (DNI).

    0

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

    Daily average radiation (kWh/m2)

    DNI (KWh/m2) NASA Ghi(KWh/m2) NASA

    The representative daily average values for each month of the typical

    year are shown in section2.2 of this document. The resulting annual value of

    DNI for this set of data is 2.733,21 kWh/m2.

    o NREL Data Base: Monthly values of global horizontal radiation (Ghi) and

    normal direct radiation (DNI).

    Daily average radiation (kWh/m2)

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    7/94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,BOKPOORT

    The representative daily average values for each month of the typical

    year are shown in section2.2 of this document. The resulting annual value of

    DNI for this set of data is 2.832,47 kWh/m2.

    o HELIOCLIM3 Data Base: Monthly and hourly values of global horizontal

    radiation (Ghi) and normal direct radiation (DNI).

    The representative daily average values for each month of the typical

    year are shown in section2.2 of this document. The resulting annual value of

    DNI for this set of data is 2.194,21 kWh/m2.

    - Hourly data from a measuring station located on the site (lat 28.738S, long

    21.972E).

    From May the 28thto July, the ground station located on the site was measuring

    global horizontal radiation (Ghi) and diffused irradiation (Di) with two separate

    (t CMP 6 t f th ith h d b d i t ll d)

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    8/94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,BOKPOORT

    The table below shows the DNI monthly values measured at the site:

    Month DNI (KWh/m2)

    Jun 226,47

    Jul 185,27

    Aug 234,30

    Sep 234,30

    Oct 245,37

    Nov 289,47

    2.1.1 Satellite derived data analysis

    Performing a simple analysis of the available data during the measured period it seems

    obvious that the different sources of available data correlate rather differently with the

    actually measured data.

    0,00

    50,00

    100,00

    150,00

    200,00

    250,00

    300,00

    350,00

    Jun Jul Aug Sep Oct Nov

    Monthly radiation (kWh/m2)

    DNI (KWh/ 2) NREL DNI (KWh/ 2) NASA

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    9/94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,BOKPOORT

    6,23

    6,71

    7,56 7,7

    7,42

    9,11

    6,686,89

    7,49 7,43

    7,72

    8,38

    4,20

    5,10

    5,90

    6,38

    6,76

    7,10

    7,55

    5,98

    7,567,81 7,92

    9,65

    4

    5

    6

    7

    8

    9

    10

    Jun Jul Aug Sep Oct Nov

    DNI average daily values (kWh/m2)

    DNI (KWh/m2) NREL

    DNI (KWh/m2) NASA

    DNI (KWh/m2) HC3DNI (KWh/m2) MEASURED

    As it is show in the previous graphics, the measured data trend is very similar to

    NASA/NREL data. At first sight, it my be concluded that if the current trend continues

    for the rest of the year, the expected values of annual DNI may well be above 2800

    kWh/m2.

    On the other hand, Helioclim3 data looks very conservative, providing an annual DNI

    value of around 2200 kWh/m2, more than 20% below the other satellite sources of data.

    SOLIDA has decided to discard this set of data f as input for our analysis, since the

    deviation range for Helioclim is too high and there are other sources of data which

    seem to correlate much better with the measured data.

    SOLIDA has already established contact with the Helioclim-3 support services (SoDa)

    in order to solve this problem by sharing with them the ground-measured data, so thatthe parameters of satellite estimation can be fine-tuned against actually measured data

    at the location. Our preliminary conclusion is that their algorithim may be using a Linke

    turbidity factor which is too high for this location, thereby underestimating severely the

    higher values of DNI which mostly occur around noon. This underestimation yields a

    very conservative yearly sum of DNI If our preliminary conclusion is correct correcting

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    10/94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,BOKPOORT

    satisfactorily with the actually measured data. Although alternative sources of data

    have been produced, our recommendation is that the problem be fixed and that a

    consistent, long term series of DNI data is obtained for this site. Otherwise, bankability

    of this site may be compromised.

    Through a combination of the NASA database and the Meteonorm tool, SOLIDA hasderived a DNI series of data which correlates reasonably with themeasured data. A

    description of Meteonorm tool/database and NASA database is provided below.

    METEONORM

    Meteonorm is a comprehensive climatological database for solar energy applications. It

    has a broad base of meteorological stations through which provides hourly radiation

    data.

    The generation of hourly values is based on the model of Aguiar and Collares-Pereira(1992) (TAGmodel: Time dependent, Autoregressive, Gaussian model). This modelconsists of two parts: the first part calculates an average daily profile; the second partsimulates the intermittent hourly variations by superimposing an autoregressiveprocedure of the first order (AR(1)-procedure) (Box etal., 1994).

    In the used version, Meteonorm 6.1, satellite data is used for radiation interpolation in

    remote areas. Where no radiation measurement is nearer than 300 km satellite

    information is used. If the nearest site is more than 50 km away, a mixture of ground

    and satellite information is used.

    For the selected site, Bokpoort, Meteonorm provides hourly values radiation through

    the interpolation between three weather stations near the power plant and satellite

    information.

    Therefore Meteonorm used sources for obtaining radiation data on the selected site are

    the following:

    - Upington, situated 77 km from the site (In that station temperature data has

    been measured from 1961 to 2005 and radiation data from 1961 to 1970)

    - Kimberley situated 273 km from the site. (In that station temperature data has

    been measured from 1961 to 2005 and radiation data from 1961 to 1970)

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    11/94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,BOKPOORT

    Meteonorm does not provide maximum and minimum values, which prevent the

    generation of the PoE15 and the PoE85 scenarios.

    NASA

    NASA, through its' Science Mission Directorate, has long supported satellite systems

    and research providing data important to the study of climate and climate processes.These data include long-term estimates of meteorological quantities and surface solar

    energy fluxes. Release 6.0 extends the temporal coverage of the solar and

    meteorological data from 10 years to more than 22 years (e.g. July 1983 through June

    2005).

    The radiation data provided by the NASA belongs to a period of 22 years, with the

    following values:

    - Monthly averaged global insolation incident on a horizontal surface

    (kWh/m2/day).

    - Minimum and Maximum difference from monthly averaged global insolation (%).

    - Monthly averaged diffuse radiation incident on a horizontal surface

    (kWh/m2/day)

    - Minimum and Maximum values from monthly averaged diffuse insolation(kWh/m2/day).

    - Monthly averaged Direct Normal Radiation (kWh/m2/day)

    - Minimum and Maximum difference from monthly averaged Direct Normal

    Radiation insolation (%).

    Global radiation (kWh/m2/day)

    Average Minimun MaximunJan 7,93 7,45 8,56

    Feb 6,96 6,19 7,73

    Mar 5,95 5,36 6,55

    Apr 4,80 3,98 5,52

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    12/94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,BOKPOORT

    Diffuse radiation (kWh/m2/day)

    Average Minimun Maximun

    Jan 2,00 1.68 2.19

    Feb 1,91 1.57 2.17

    Mar 1,59 1.33 1.80Apr 1,21 0.87 1.47

    May 0,84 0.61 1.05

    Jun 0,69 0.48 0.91

    Jul 0,72 0.58 0.93

    Aug 0,87 0.68 1.17

    Sep 1,28 1.00 1.51

    Oct 1,68 1.42 1.93Nov 1,93 1.51 2.23

    Dec 1,99 1.62 2.32

    Direct Normal radiation (kWh/m2/day)

    Average Minimun Maximun

    Jan 8,63 8,46 9,23

    Feb 7,49 6,89 8,24

    Mar 6,88 6,40 7,43

    Apr 6,41 5,58 7,18

    May 6,56 6,04 7,02

    Jun 6,59 5,93 6,92

    Jul 6,84 6,09 6,91

    Aug 7,44 6,55 7,51

    Sep 7,39 6,95 7,83

    Oct 7,69 7,15 8,07

    Nov 8,36 7,86 9,11

    Dec 9,03 8,40 9,57

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    13/94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,BOKPOORT

    2.2.1 Analysis of alternative sources of data

    In order to find out which of the hourly radiation series available better represents the

    actually measured data, SOLIDA has calculated the coefficient of determination (R2).

    The coefficient of determination is a statistical method that explains how much of the

    variability of a factor can be caused or explained by its relationship to another factor.Used in trend analysis, it is computed as a value between 0 (0 percent) and 1 (100

    percent) higher the value, better the fit. Symbolized by 'R2' because it is square of

    'Pearsons coefficient of correlation' symbolized by 'r', it is an important tool in

    determining thedegree of linear-correlation ofvariables inregression analysis.

    Coefficient of determination R2

    Meteonorm data Nasa data

    June 0,88 0,85

    July 0,76 0,66

    August 0,88 0,85

    September 0,69 0,52

    October 0,63 0,59

    The table above shows the coefficient of determination between satellite derived data

    and ground station measured data. It is important to note the following issues:

    1. September seems to have been a rather irregular month as measured by themeteo station.

    2. In theory, running correlations between actually measured data and averaged

    data (which is what both Meteonorm and NASA provide) can never yield high

    correlations as they are representing somewhat different phenomena.

    http://www.businessdictionary.com/definition/method.htmlhttp://www.businessdictionary.com/definition/variability.htmlhttp://www.businessdictionary.com/definition/factor.htmlhttp://www.businessdictionary.com/definition/relationship.htmlhttp://www.businessdictionary.com/definition/trend-analysis.htmlhttp://www.businessdictionary.com/definition/value.htmlhttp://www.businessdictionary.com/definition/percent.htmlhttp://www.businessdictionary.com/definition/coefficient-of-correlation-r.htmlhttp://www.businessdictionary.com/definition/tool.htmlhttp://www.businessdictionary.com/definition/degree.htmlhttp://www.businessdictionary.com/definition/variable.htmlhttp://www.businessdictionary.com/definition/regression-analysis-RA.htmlhttp://www.businessdictionary.com/definition/regression-analysis-RA.htmlhttp://www.businessdictionary.com/definition/variable.htmlhttp://www.businessdictionary.com/definition/degree.htmlhttp://www.businessdictionary.com/definition/tool.htmlhttp://www.businessdictionary.com/definition/coefficient-of-correlation-r.htmlhttp://www.businessdictionary.com/definition/percent.htmlhttp://www.businessdictionary.com/definition/value.htmlhttp://www.businessdictionary.com/definition/trend-analysis.htmlhttp://www.businessdictionary.com/definition/relationship.htmlhttp://www.businessdictionary.com/definition/factor.htmlhttp://www.businessdictionary.com/definition/variability.htmlhttp://www.businessdictionary.com/definition/method.html
  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    14/94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,BOKPOORT

    asset at this stage, due to the uncertainty of the different sources of data

    and the short period for which actual measurements are available.

    b. NASA data offer average daily DNI data as well as actually registered

    maximum and minimum data, which are key for estimating standard

    deviation of the monthly series and therefore inferring Probability ofExceedance scenarios.

    2.3 Generation of PoE scenarios for annual hourly DNI data sets

    As previously mentioned in this report, PoE scenarios can be derived for a sample of

    data for which sample size, average, maximum and minimum values are known. In the

    case of NASA data set, as shown in section 2.2, all those data are available. Theprocedure followed to derive PoE scenarios using the available data is described below

    and the results are attached to this report as an annex.

    The methodology is based on the assumption that DNI values follow a normal

    distribution. There is a statistical relationship (Patnaik, 1946) between the mean range

    for data from a normal distribution and , the standard deviation of that distribution.

    This relationship depends only on the sample size, n. The mean of R is d2 , where

    the value of d2 is also a function of n. An estimator of is therefore R /d2.

    Where:

    s: Standard deviation

    R: range of maximum and minimum values

    d2: Factor to calculate the standard deviation from the sample size.

    Sample size (n) 2 3 4 5 6 7 8 9 10 15 20 24 25

    d2 1,128 1,693 2,059 2,326 2,534 2,704 2,847 2,97 3,078 3,472 3,375 3,895 3,931

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    15/94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,BOKPOORT

    For simplicity purposes, we have chosen the following PoEs:

    p85 which corresponds to 1

    p15 which corresponds to + 1

    The corresponding values of daily DNI are calculated (shown in table below) and usedas input to Meteonorm software, which in turn derives the corresponding hourly series

    of data. The complete p15 and p85 series of data are attached as annexes 3 and 4 to

    this report.

    Monthly Averaged Direct Normal Irradiation (kWh/m2

    m)

    Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

    P15 274,15 220,11 222,08 205,53 211,75 205,86 219,04 238,89 229,02 246,26 261,15 289,94

    P50 267,53 209,72 213,28 192,30 203,36 197,70 212,04 230,64 221,70 238,39 250,80 279,93

    P85 260,91 199,33 204,48 179,07 194,97 189,54 205,04 222,39 214,38 230,52 240,45 269,92

    The tables below show the correlation of the different series of data generated against

    the ground station measured data.

    Coefficient of determination R2

    SITE SITE SITE SITE

    METEONORM METEO_NASA_P15 METEONORM_NASA_P50 METEO_NASA_P85June 0.88 0.90 0.85 0.87

    July 0.76 0.80 0.66 0.70

    August 0.88 0.88 0.85 0.83

    September 0.69 0.59 0.52 0.55

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    16/94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,BOKPOORT

    3 PLANT CONFIGURATION DESIGN

    3.1 General Design Parameters

    The following parameters and concepts have been considered when designing the

    layout for the CSP Solafrica project.

    Minimize the occupied land area.

    Avoid potential impacts in:

    - Roads- Railways- Hydrological channels- Environmental protected areas

    Avoid the occupation of abrupt areas of the land farm in order to minimize theearth movement.

    The slope of the site is an important factor to be taken into account. Based onthis point, the solar field could be designed in one or several terraces.

    Situation of the electrical infrastructure of the power plant respect to theevacuation substation. The location of the BOP and especially the maintransformer and overhead line route should be defined based on this criterion.

    Situation of the water supply source (when wet or hybrid cooling system isused). The location of the raw water supply and effluent disposal system intothe BOP should be defined based on this criterion.

    Availability of access roads. The situation of the main access to the power plantand solar fields should be defined based on this criterion.

    Separation distances required between solar sub-fields, which are required for

    laying out the heat transfer fluid pipes and the thermal expansion lyres.

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    17/94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,

    BOKPOORT

    3.2 Power block design

    3.2.1 Steam cycle considerations

    SOLIDA has utilized THERMOFLEX software to evaluate the steam power cycleefficiency.

    THERMOFLEX is a modular program with a graphical interface that allows assembling

    a model from icons representing different components. The program covers both

    design and off-design simulation, modeling all types of commercial power plants.

    The 55 MW SST 700 Siemens steam turbine has been used as an input to derive the

    84 MW gross power output cycle that has served as the basis for the present study.

    This steam turbine is a tandem-compound reheat condensing unit, with high

    speed/high pressure section connected by a speed reduction gear to a single-flow-

    single-casing low pressure reheat section.

    The turbine has two rotors (high and low pressure) connected to each other through

    the speed reduction gear and to the generator rotor with a solid bolted coupling. Therotors are supported by journal bearings and located axially by thrust bearings.

    The steam is admitted to the HP turbine via an emergency stop valve and a control

    valve.

    SST-700 General Parameters:

    a. Admission conditions HP-module

    Admission pressure

    Rated 105.0 bara/ 1522.9 psia

    Normal 105.0 bara/ 1522.9 psia

    Admission temperature

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    18/94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,

    BOKPOORT

    c. Exhaust conditions, HP-module

    Exhaust (back pressure) pressure

    Normal 20.7 bara/ 300.2 psia

    Alarm high 21.7 bara/ 314.7 psia

    Trip high 22.8 bara/ 330.7 psia Exhaust temperature

    Normal 214.0 C/ 417.2 F

    Alarm high (max 1 h operation) 250.0 C/ 482.0 F

    Automatic shutdown 360.0 C/ 680.0 F

    d. Exhaust conditions, LP-module

    Exhaust (condenser) pressure

    Normal 0.066 bara/ 0.96 psia/ 1.9 "HgA

    Alarm high 0.16 bara/ 2.3 psia/ 4.7 "HgA

    Trip high 0.23 bara/ 3.3 psia/ 6.8 "HgA

    Exhaust temperature at blade row L-1

    Normal 57.0 C/ 134.6 F

    Alarm high (max 1.0 h operation) 180.0 C/ 356.0 FAutomatic shutdown 200.0 C/ 392.0 F

    Exhaust temperature at blade row L-0

    Normal 34.0 C/ 93.2 F

    Alarm high (max 1.0 h operation) 85.0 C/ 185.0 F

    Automatic shutdown 105.0 C/ 221.0 F

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    19/94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,

    BOKPOORT

    Curve 1: Rated temperature HP-turbine inlet (390C)

    Curve 2: Rated pressure HP-turbine inlet (105 bara)

    Curve 3: HP-turbine exhaust moisture limitation (VWO)

    Curve 4: HP start-up limit (50C) superheatCurve 5: HP start-up limit low boiler pressure (35 bara)

    Curve 6: Rated temperature LP-turbine inlet (390C)

    Curve 7: Rated pressure LP-turbine inlet (19 bara)

    Curve 8: LP-turbine exhaust moisture limitation (VWO)

    Curve 9: LP start-up limit (50C) superheatCurve 10: LP low inlet temperature (200C)

    3.2.2 Different cooling alternatives considered

    In the course of this task, SOLIDA has considered the following cooling options based

    on ACWA Power requirements: Wet Cooling Tower

    Air Cooled Condenser

    Hybrid Cooling Tower

    Combine Wet Cooling Tower with Air Cooled Refrigerants

    WET COOLING TOWER

    This cooling system is based on the use of evaporative cooling tower, induced draft

    and countercurrent flow.

    Thi li t b d fi d h t h ti d di t t t

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    20/94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,

    BOKPOORT

    The air can enter through one or more sides of the tower, it is achieved reducing the

    height of air inlet.

    In this type of tower, the hot water from the condenser enters the upper part of the

    tower and it is sprayed on the filler material of the tower, coming into contact with the

    air that rises through the tower. This causes a portion of the water evaporates and theother is driven by the air induced. The cooling capacity of the tower is directly

    proportional to the surface and to the air-water contact time.

    The cooled water is collected in a collect located at the base of the tower from where

    this water is sent to the condenser. The control system can automatically control the

    cooling water temperature by regulating the ventilation.

    The basin of cooled water must have the necessary accessories to measure the

    excess effluent, based on which we calculate the concentration of chemicals dosed inthe cooling system.

    A water supply line arrives from the chemical dosing system of tower. The chemical

    dosing system incorporates additives continuously or periodically to remove the

    encrustations of dissolved salts, inhibit the corrosion and prevent the deposit formation

    and the proliferation of organic matter. The losses occurring in the cooling water circuit,

    due to the evaporation, the blowdown and the drag in the cooling tower are replaced

    with the water through a supply line.

    Therefore, the cooling tower has two different parts: the cooling zone and the basin

    water.

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    21/94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,

    BOKPOORT

    Allow great flexibility in its operation and it can work at more or less capacity

    depending on the specific requirements of the plant

    The wet cooling towers are able to work with low condensate temperatures

    achieving higher cycle efficiency than other cooling technologies.

    It is the cheapest cooling technology solution.

    And the main disadvantages are:

    The main disadvantage of this system is that it needs a high water make-up

    consumption derived from the evaporation and drift losses.

    It is necessary to use chemicals and biocides for the water treatment, which

    increase the operation cost.

    The power consumption of the system is higher than the other cooling

    technologies evaluated, due to cooling water pumps and fan motors.

    AIR COOLED CONDENSER

    The operation of the air cooled condenser is based on the cooling of the steam by the

    basic principle of convection cooling, using the airflow as a refrigerant. It is based onthe exchange of heat between the atmospheric air and steam from the exhaust turbine.

    The steam is passed through a heat exchanger composed of finned tube bundles that

    increase the contact surface of the steam. It grouped into modules and mounted on a

    steel support structure. The tubes bundles of the heat exchanger seem to be a house

    roof. In the lower part the fans are positioned so that the air transversely flows through

    the heat exchanger. The fluid is cooling with the metal contact of the air cooled

    condenser, which in turn it is cooled by the airflow generate by the fans.This type of air cooled condenser uses a condensation process in two stages First, the

    steam is guided from the steam turbine to the air cooled condenser where it enters in

    parallel flow to the tube panels in the top part. The steam is partially condensed in the

    flow parallel modules, the remaining steam is guided through the down heads in

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    22/94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,

    BOKPOORT

    Air coo led condens er (Source:GEA)

    The main advantages are:

    It is only used air as a refrigerant, no water consumption for cooling. It can be

    applied in situations where the water availability is limited.

    Can be applied in situations where the plume formation is not acceptable.

    The power consumption is lower than the consumption of wet cooling towers,

    because the system does not employ cooling water pumps.

    The main disadvantages are:

    The initial capital cost is higher.

    Large heat transfer surfaces are necessary. Therefore the space requirementfor installation is high.

    If winter temperatures are too low it can cause freezing problems in the

    process.

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    23/94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,

    BOKPOORT

    It is a combination of a wet and dry cooling tower or, in other words, of an evaporative

    and a convection process. The hybrid cooling tower can be operated either as a pure

    wet cooling tower or as a combined wet/dry cooling tower, depending on the ambient

    temperature. The heated cooling water first passes through a dry section of the cooling

    tower, where part of the heat load is removed by an air current, which is often induced

    by a fan. After passing the dry section, water is further cooled in the wet section of thetower, which functions similarly to an open recirculating tower. The heated air from the

    dry section is mixed with the steam from the wet section in the upper part of the tower,

    thus lowering the relative humidity before the air current leaves the cooling tower,

    which completely reduces plume formation above the tower.

    Hybr id Coo l ing Tow er (Source: Eurelectr ic)

    The main advantages are:

    Less water consumption than wet cooling tower technology

    Plume abatement

    The main disadvantages are:

    The investment cost is higher than wet cooling tower solutions

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    24/94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,

    BOKPOORT

    The combination of a wet cooling system and a dry cooling system in parallel

    allows keeping the power plant working in case no water is available.

    The main disadvantages are:

    Large heat transfer surfaces are required. Therefore the space requirement for

    installation within the power block is high (around 10.000 m2for a plant of thismagnitude).

    More complexity in the power plant control when working in air refrigerant

    mode. This is due to the variation of condensing pressure.

    More complexity in the cooling system control based on the redundancy of

    cooling equipment.

    More complexity in the cooling piping lay-out.

    The following table shows a comparison of the three possible options of cooling

    Wet Cooling

    TowerHybrid Cooling Tower

    Air Cooling

    Condenser

    Site Near the water Near the water No restriction

    Operation Easy More Difficult Easy

    Maintenance Low High Low

    Water treatment Yes Yes No

    Plume Yes No (reduced) Never

    Noise Yes YesSound attenuation

    equipment

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    25/94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,

    BOKPOORT

    3.3 Solar field design

    3.3.1 Main equipment consideration

    A field of distributed parabolic trough collectors collects direct radiation from the sun

    and transfers it to a HTF circulating through heat collecting elements located in thefocal line of the parabolic collector.

    The solar system is built up from solar collector assemblies (SCAs), each one

    consisting of a row of individual trough collectors driven by a single train. The mirrored

    parabolic troughs concentrate direct radiation onto the heat collection element (HCE),

    which is a steel pipe with a special selective coating surrounded by an evacuated

    annulus to enhance performance.

    3.3.2 Solar field configuration

    SOLIDA proposes two main alternatives for this solar field configuration. A four (4)

    subfields configuration and a three (3) subfields configuration.

    The following pictures show the solar field expansion options for ach alternative.

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    26/94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,

    BOKPOORT

    mainly based on the HTF piping system sizing. In the four sub-fields configuration the

    piping system must be previously prepared for the final configuration.

    3.3.3 Solar field alternatives studied

    SOLIDA has determined different solar field sizes that could be set at the site.

    Due to the clients premises, we have analyzed only the possibility of a power plant

    without thermal storage.

    The different solar field configurations studied are the following:

    Row-to-row spacing: 17 m

    - Solar field size: 96 loops

    - Number of subfields: 3

    - Sub-field 1: 32 loops

    - Sub-field 2: 32 loops

    - Sub-field 3: 32 loops

    - Solar field size: 120 loops

    - Number of subfields: 3

    - Sub-field 1: 40 loops

    - Sub-field 2: 40 loops

    - Sub-field 3: 40 loops

    - Solar field size: 132 loops

    - Number of subfields: 3

    - Sub-field 1: 44 loops

    - Sub-field 2: 44 loops

    Sub field 3: 44 loops

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    27/94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,

    BOKPOORT

    - Sub-field 1: 52 loops

    - Sub-field 2: 52 loops

    - Sub-field 3: 52 loops

    - Solar field size: 168 loops

    - Number of subfields: 3

    - Sub-field 1: 56 loops

    - Sub-field 2: 56 loops

    - Sub-field 3: 56 loops

    - Solar field size: 180 loops

    - Number of subfields: 3

    - Sub-field 1: 60 loops

    - Sub-field 2: 60 loops

    - Sub-field 3: 60 loops

    - Solar field size: 204 loops

    - Number of subfields: 3

    - Sub-field 1: 68 loops

    - Sub-field 2: 68 loops

    - Sub-field 3: 68 loops

    3.4 Performance models

    SOLIDA has performed its calculations using its proprietary performance model. In

    order to give higher reassurance to ACWA Power, the same calculations have been

    derived using SAM

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    28/94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,

    BOKPOORT

    MONTH Ghi(kWh/m2) Dh(kWh/m2) DNI (kW/m2)

    Jan 244,76 61,75 266,43

    Feb 193,85 53,09 205,49

    Mar 183,63 49,10 208,80

    Apr 143,93 35,99 194,04

    May 124,19 26,03 189,32

    Jun 108,01 20,16 184,43

    Jul 119,74 22,32 197,13

    Aug 148,81 26,03 226,55

    Sep 172,80 38,16 222,42

    Oct 209,79 52,08 233,66

    Nov 228,91 56,87 249,04

    Dec 253,66 61,01 276,82

    2.132,06 502,58 2.654,12

    A representation of the estimated radiation data monthly distribution can be seen in the

    graphic below:

    50

    100

    150

    200

    250

    300

    kWh

    /m2

    Ghi(kWh/m2)

    Dh(kWh/m2)

    DNI (kW/m2)

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    29/94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,

    BOKPOORT

    For efficiency calculations the incidence angle modifier expression, given in the final

    report of the European project 'Eurotrough - II', has been used.

    3.4.2.2 Parabolic reflectors

    The mission of these mirrors is to reflect the incident radiation, projecting and

    concentrating it on the absorber. Therefore their properties are very important in the

    solar radiation collection:

    Reflective aperture area: 817,5 m2

    Mirror cleanliness factor: 97% (taking into account the periodic cleaning cycles)

    Mirror reflectivity: 92,5%

    It is considered a nominal value of the intercept factor, which decreases with

    wind speed.

    o IAM = 1(a * IA + b*IA^2)/cosIA

    o IAM, ET II, factor a: 0,000278005

    o IAM, ETII, factor b: 0,000042806

    3.4.2.3 Absorbers

    Absorbers are one of the main elements of the collector. These elements have

    important repercussion in the high collection efficiency of solar radiation.

    Number of absorbers per collector: 36

    Collecting surface: 0,89 m2/absorber

    Nominal absorptivity of the selecting coating: 95% Glass transmisivity: 96%

    Estimation of losses derived of the connections between absorbers.

    For emissivity losses calculations, it is used a mean temperature difference

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    30/94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,

    BOKPOORT

    3.4.2.6 Efficiency of the collector loops

    It is calculated as the ratio between the net absorbed thermal power in the loop and the

    incident radiation.

    The following graphic shows the loop efficiency variation as a function of the solar

    radiation incidence angle.

    0,0%

    10,0%

    20,0%

    30,0%

    40,0%

    50,0%

    60,0%

    70,0%

    0 10 20 30 40 50 60 70

    1050 kWh/m2

    900 kWh/m2

    750 kWh/m2

    600 kWh/m2

    450 kWh/m2

    300 kWh/m2

    3.4.3 Power Plant availability

    It has been set at 98% of the percentage time when the power plant is available for

    normal operation.

    This parameter takes into account the scheduled stops for maintenance labors and

    those forced shutdown due to unavoidable reasons.

    3.4.4 Configuration of power block

    The production model require the introduction of the power cycle parameters that allow

    perform the conversion between the thermal energy collected in the solar field and the

    electric energy produced in the generator terminals.

    As it was described in previous sections, the model has taken as reference the SST-

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    31/94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,

    BOKPOORT

    1. Freezing prevention (anti freezing): These heaters can supply heat to the HTF

    system to prevent HTF freezing.

    2. Gland steam: a small boiler can be used to supply supplemental steam. It can

    be avoided; some CSP plants in Spain have managed to skip it. Also some of

    the SEGS plants do not have it. However for guarantee reasons vis a vis the

    turbine manufacturer and hence due to bankability issues, it seems necessary

    to consider this boiler.

    Option 2: LFO firing up to 15%.

    CSP power plants can operate in three modes:

    Solar only mode: in this mode the HTF collect the thermal energy necessary in

    the steam generator flowing only through the solar field.

    Hybrid model (solar and fuel): The auxiliary fuel-fired HTF heater acts, in

    parallel to the solar field, as and additional source to heat the HTF. This mode

    is useful for reducing start-up time in the morning, as a booster in the event of

    inclement meteorological conditions and for extending solar operating time in

    evening hours.

    Fuel only mode: in this case the auxiliary fuel fired HTF heater is the only

    source of energy to produce turbine inlet steam. The HTF flow by-passes thesolar field entirely and circulates between the HTF heater and the steam

    generator. This mode allows the production of electricity independently from

    solar insolation or during solar field shutdowns.

    This kind of plant has specific needs of conventional fuel due to the following reasons:

    1. Enhancement of yearly output: during periods of low solar insolation and in the

    evenings when electrical generation is planned, the supplemental fossil-fired

    HTF heater can be operated to provide energy to produce turbine steam (solar

    and fuel mode). The supplemental fossil-fired HTF heater can also be operated

    alone to provide energy to produce turbine steam (fuel only mode).

    2. Freezing prevention (anti freezing): These heaters can supply heat to the HTF

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    32/94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,

    BOKPOORT

    Firing strategy: Top up solar field plus stand-alone firing if necessary to reach

    15% limit.

    The type of conventional fuel source considered is LFO. Light Fuel Oil (LFO) is a crude

    oil distillated. It is light in color and has on average a specific gravity in the range of

    0.82 to 0.86. LFO is usually composed mostly of carbon (86% wt.), hydrogen (13%

    wt.) and sulphur (0.1 to 0.2% wt.). It also contains trace amounts of ash and sediments.

    Density 0.85 - 0.86 kg/litre

    Kinematic Viscosity 1 - 3 cSt

    Boiling Point 340-400 C

    Calorific value 44 MJ/kg typical

    Ashes 0.05 %wt maximum

    3.4.6 Energy losses

    Energy losses that are been taken into account are described below:

    Daytime and nighttime losses of the HTF piping system. These include thermal

    losses of the steam generator system, HTF pipes and the expansion and

    overflow tanks.

    Heat losses in collector loops: the model calculates these losses as the

    difference between the theoretical maximum power that could be absorbed in

    the collector loops and the power actually absorbed due to the efficiency.

    - The model considers the selective coating emissivity variation as a

    function of the temperature.

    Shading: the model is able to calculate the quantity of energy that the solar field

    is unable to collect due to the projected shadows on the adjacent collectors.

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    33/94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,

    BOKPOORT

    A CSP power plant presents the self-supply power of a conventional

    thermoelectric power plant, namely, pumping of condensate, feedwater pumps,

    cooling water pumping, fans etc.

    3.5 Water Consumption Model

    The water balance of the plant has been carried out for an optimized plant without

    thermal storage.

    In order to carry out the study of the needs of raw water and the volume of the

    generated discharge in the Solafrica Solar Thermoelectric Power Plant, the calculation

    has been structured in two phases:

    Phase I: Study of the water flows consumed and the discharges generated by

    the different configurations of the power plant in nominal operating conditions.

    Phase II: Definition of the power plant consumptions and discharge total

    volumes.

    The main water consumptions for the proper functioning of Solar Thermoelectric Power

    Plant are as follows:

    3.5.1 Cooling system water necessities

    Three possible cooling system alternatives have been considered for the power plant:

    Wet cooling towers.

    Air cooling condenser.

    Hybrid cooling towers.

    A simulation of water consumption has been made for each different cooling system,

    using Thermoflex softwarebalances and SOLIDAs proprietary model.

    3.5.1.1 Wet cooling towers

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    34/94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,

    BOKPOORT

    Considering a cooling system for the power plant with hybrid cooling tower, the

    operation of the towers has been modeled taking into account the functioning of the

    power block, the expected environmental conditions (conditions of the evaporation

    process and drift losses that happen inside the towers) and the system blowdowns.

    3.5.1.3 Air cooled condenserIn order to simulate the cooling with air cooled condensers, the functioning of the power

    block and the expected environmental conditions (conditions of dry cooling process)

    have been considered.

    3.5.2 Washing mirrors water

    The water used for periodic cleaning of the solar fields mirrors, it is water from the

    demineralization system of the power plant. In order to carry out the calculations of

    flows and volumes consumed annually in performing this task, the following

    considerations have been taken into account:

    3 times a month (1 time per week) a low-pressure washing will be carried out

    - Amount of water needed: 2,80 l/m2.

    - Frequency: three weeks a month.

    1 time per month, a high-pressure washing will be carried out

    - Volume of water required: 2,24 l/m2.

    - Frequency: one week per month.

    3.5.3 Blowdowns water replacement

    The continuous blowdowns and venting that are conducted in different points of thewater-steam circuit, imply the need to replace the circuit with the same amounts of

    water in the condenser.

    The water consumption results for the water-steam system, have been obtained from

    the simulation made with the software "Thermoflex" and a proprietary model.

    DOC CODE

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    35/94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,

    BOKPOORT

    Therefore, based on the estimated annual operating hours of the plant, it is obtained

    the total volume of services water consumed.

    3.5.6 Potable water

    Based on other power plants with the same staff (40 people) and considering an

    average consumption of 300 liters per person and day, the annual consumption ofpotable water in the power plant is estimated.

    3.5.7 Fire Protection System Water

    The flow required for the fire protection system of the power plant, is considered to be

    intermittent, so that for the total water consumption of the power plant, it will be

    considered a first filling of the system.

    DOC CODE SO DV 1006

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    36/94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,

    BOKPOORT

    4 POWER PLANT CALCULATIONS

    4.1 Power Block

    4.1.1 Heat and mass balances

    The analyzed power plant is based on a conventional Rankine steam cycle with reheat,but with solar energy as the heat source to generate the steam to drive the turbine.

    All the heat balances are for a steam cycle with two-casing reheat turbine and six

    turbine extractions leading to two high pressure feedwater heaters, three low pressure

    feedwater heaters and a deaerator.

    The following balances are included in the attached file Heat&Mass_balances:

    Rankine cycle with wet cooling tower analyzed at different loads: 100-90-75-50-40%

    Rankine cycle with wet cooling tower analyzed at full load with different

    temperatures: 35-25-15 C

    Rankine cycle with air cooling condenser analyzed at different loads: 100-90-

    75-50-40%

    Rankine cycle with air cooling condenser analyzed at full load with differenttemperatures: 35-25-15 C

    Rankine cycle with hybrid cooling tower analyzed at different loads: 100-90-75-

    50%

    Rankine cycle with hybrid cooling tower analyzed at full load with different

    temperatures: 35-25-15 C

    4.1.2 Power block efficiencies

    SOLIDA has utilized THERMOFLEX software to evaluate the steam turbine efficiency.

    The outputs of the steam turbine for the 84 MW gross power output have been derived

    from the 55 MW SST 700 Siemens steam turbine

    DOC CODE SO-DV-1006

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    37/94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,

    BOKPOORT

    The following graphic shows the curve described by the data presented in the table and

    the curve traced by the model to simulate the operation of the turbine. As shown the

    equation that calculates the model fits perfectly with the actual operation of the turbine.

    0,0%

    5,0%

    10,0%

    15,0%

    20,0%

    25,0%

    30,0%

    35,0%

    40,0%

    45,0%

    0 20 40 60 80 100 120 140 160

    55 MW Steam Turbine Efficiency

    The following graphics simulate the operation of the turbine depending on the cooling

    system used.

    Wet cooling system

    Q (MWth) P(MWe) Efficiency (%)

    79 29 36,1%

    102 38 37,1%

    156 60 38,5%

    189 74 38,9%

    211 82 39,0%

    DOC. CODE SO-DV-1006

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    38/94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    OC CO SO DV 1006

    REVIEW 0

    South Africa, North Cape Region,

    BOKPOORT

    Dry cooling system

    Q (MWth) P(MWe) Efficiency (%)

    31 8 25,2%

    63 19 30,7%

    113 39 34,3%164 58 35,4%

    215 77 36,0%

    Hybrid cooling system

    Q (MWth) P(MWe) Efficiency (%)

    31 8 25,6%

    63 20 31,2%

    113 39 34,9%

    164 59 36,0%

    215 79 36,6%

    TECHNICAL ADVISOR FOR A CSPDOC. CODE SO-DV-1006

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    39/94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA REVIEW 0

    South Africa, North Cape Region,

    BOKPOORT

    4.1.3 Water Balances

    Based on an estimation of the power plant's operation during a year, and taking into

    account the criteria indicated in previous paragraphs, the water balances for the

    different configurations of the power plant have been calculated. They include the

    nominal flows for the different consumption currents of the power plant. In addition to

    that, for each evaluated case, the total water consumption has been included.

    The different water balances analyzed are shown in Annex 01 to this report.

    4.2 Comparative Solar Advisor Model / Propietary Model

    In order to give higher reassurance to ACWA Power, SOLIDA has performed the

    calculation of the power plant energy production for Option 1 (LFO used only for anti-freezing and gland steam generation) and wet cooling tower, using the Solar Advisor

    Model.

    The following table shows the obtained values of both models:

    Net Power Output (GWhe)_P50

    Solar Field Size SAM PROPIETARY

    96 114,2 123,8

    120 144,9 150,7

    132 156,4 160,5

    144 166,2 168,7

    156 174,2 175,4

    168 181,4 181,4180 187,3 186,7

    204 196,4 193,2

    TECHNICAL ADVISOR FOR A CSPDOC. CODE SO-DV-1006

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    40/94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA REVIEW 0

    South Africa, North Cape Region,

    BOKPOORT

    For 168 loops solar field size, SOLIDA has evaluated monthly values:

    Net Power Output (GWhe)_P50

    SAM PROPIETARY

    JAN 19,6 20,0

    FEB 15,3 14,6

    MAR 14,0 14,5

    APR 13,6 13,3

    MAY 11,8 11,5

    JUN 9,1 9,7

    JUL 10,8 11,2

    AUG 16,5 15,5SEP 16,8 16,6

    OCT 17,0 17,3

    NOV 17,7 18,0

    DEC 19,2 19,3

    Both series presents a coefficient of determination (R2) of 97,63%.

    4.3 Performance results

    As it is described below, SOLIDA has performed its calculations using its own

    proprietary performance model.

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    41/94

    South Africa, North Cape Region,BOKPOORT

    Page 41

    4.3.1 Option 1: LFO used only for anti-freezing and gland steam generation

    The results are shown below:

    RESULTS WET COOLING TOWER 96 120 132 144 156 168 180 204

    Total Gross electricity production GWhe 146 177 188 198 207 214 221 230

    Total Auxiliary consumptions GWhe 17 20 21 23 24 25 26 29

    Total Net Electricity production GWhe 129 157 167 176 183 189 194 201

    Maximum net power output MWe 74,6 75,1 75,1 75,1 75,0 75,0 75,0 74,9

    LFO Heaters

    % LFO usage, base thermal input % 0,0% 0,0% 0,0% 0,0% 0,0% 0,0% 0,0% 0,0%

    Equivalent hours steam turbine h 1.737 2.103 2.243 2.360 2.462 2.549 2.626 2.738

    Thermal Efficiency annual Solar Field 46,6% 44,5% 43,0% 41,4% 39,7% 38,1% 36,6% 33,6%

    Solar-Electric Efficiency Annual 15,5% 15,1% 14,6% 14,1% 13,5% 13,0% 12,4% 11,4%

    DNI kWh/m2 2.654 2.654 2.654 2.654 2.654 2.654 2.654 2.654

    Availability 98% 98% 98% 98% 98% 98% 98% 98%

    Electricity losses 2% 2% 2% 2% 2% 2% 2% 2%

    Net electricity injected to the grid GWhe 124 151 160 169 175 181 187 193

    Net equivalent hours of CSP plant h 1.659 2.008 2.138 2.247 2.339 2.418 2.488 2.581

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    42/94

    South Africa, North Cape Region,BOKPOORT

    Page 42

    RESULTS AIR COOLING CONDENSER 96 120 132 144 156 168 180 204

    Total Gross electricity production GWhe 134 162 173 182 190 197 203 211

    Total Auxiliary consumptions GWhe 15 19 21 22 24 25 26 29

    Total Net Electricity production GWhe 119 143 153 160 167 172 177 183

    Maximum net power output MWe 68,3 68,3 68,2 68,2 68,2 68,1 68,1 68,0

    LFO use

    % LFO usage, base thermal input % 0,0% 0,0% 0,0% 0,0% 0,0% 0,0% 0,0% 0,0%

    Equivalent hours steam turbine h 1.596 1.934 2.062 2.170 2.263 2.343 2.414 2.518

    Thermal Efficiency annual Solar Field 46,6% 44,5% 43,0% 41,4% 39,7% 38,1% 36,6% 33,6%

    Solar-Electric Efficiency Annual 14,2% 13,8% 13,3% 12,8% 12,3% 11,8% 11,3% 10,3%

    DNI kWh/m2 2.654 2.654 2.654 2.654 2.654 2.654 2.654 2.654

    Availability 98% 98% 98% 98% 98% 98% 98% 98%

    Electricity losses 2% 2% 2% 2% 2% 2% 2% 2%

    Net electricity injected to the grid GWhe 114 138 147 154 160 165 170 176

    Net equivalent hours of CSP plant h 1.668 2.018 2.148 2.256 2.348 2.425 2.492 2.583

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    43/94

    South Africa, North Cape Region,BOKPOORT

    Page 43

    RESULTS HYBRID COOLING TOWER 96 120 132 144 156 168 180 204

    Total Gross electricity production GWhe 138 167 178 187 195 202 208 217

    Total Auxiliary consumptions GWhe 15 18 19 20 22 23 24 26

    Total Net Electricity production GWhe 122 149 158 167 173 179 184 191

    Maximum net power output MWe 70,2 70,7 70,6 70,7 70,6 70,6 70,6 70,4

    LFO use

    % LFO usage, base thermal input % 0,0% 0,0% 0,0% 0,0% 0,0% 0,0% 0,0% 0,0%

    Equivalent hours steam turbine h 1.639 1.984 2.116 2.227 2.322 2.404 2.477 2.583

    Thermal Efficiency annual Solar Field 46,6% 44,5% 43,0% 41,4% 39,7% 38,1% 36,6% 33,6%

    Solar-Electric Efficiency Annual 14,7% 14,3% 13,8% 13,3% 12,8% 12,3% 11,8% 10,8%

    DNI kWh/m2 2.654 2.654 2.654 2.654 2.654 2.654 2.654 2.654

    Availability 98% 98% 98% 98% 98% 98% 98% 98%

    Electricity losses 2% 2% 2% 2% 2% 2% 2% 2%

    Net electricity injected to the grid GWhe 117 143 152 160 166 172 177 183

    Net equivalent hours of CSP plant h 1.672 2.023 2.154 2.264 2.356 2.435 2.505 2.598

    TECHNICAL ADVISOR FOR A CSPDOC. CODE SO-DV-1006

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    44/94

    PROJECT IN SOUTH AFRICA REVIEW 0

    South Africa, North Cape Region,

    BOKPOORT

    4.3.1.1 Gross and net electricity production

    The annual electricity output results for the different configurations evaluated are

    included hereafter.

    TECHNICAL ADVISOR FOR A CSPDOC. CODE SO-DV-1006

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    45/94

    PROJECT IN SOUTH AFRICA REVIEW 0

    South Africa, North Cape Region,

    BOKPOORT

    4.3.1.2 Solar/Electrical efficiency

    The solar/electrical efficiency results for the different configurations evaluated are

    included hereafter.

    4.3.1.3 Total water consumptions

    The following results determine the water consumptions, for a production of the solar

    power plant without use of LFO.

    Wet cooling tower results

    Th t t bl i di t th t i t t t ti f th l t f

    TECHNICAL ADVISOR FOR A CSPDOC. CODE SO-DV-1006

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    46/94

    PROJECT IN SOUTH AFRICA REVIEW 0

    South Africa, North Cape Region,

    BOKPOORT

    Total 635,567.14 737,438.92 778,291.44 813,328.87 845,745.24 875,055.94 901,570.28 944,980.02

    As shown in the diagram below, the water consumption increases with increasing the

    number of the solar field loops. In turn, it is observed that the most important water

    consumption it is produced by the cooling system.

    The following graph shows the monthly water consumption evolution of the power plant

    for the different solar field sizes and a cooling system based on wet cooling tower. At

    the same time, it is possible to see how the water consumption increases with the solar

    field size.

    TECHNICAL ADVISOR FOR A CSPDOC. CODE SO-DV-1006

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    47/94

    PROJECT IN SOUTH AFRICA REVIEW 0

    South Africa, North Cape Region,

    BOKPOORT

    Air cooling condenser results

    The next table indicates the most important and totals water consumptions of thepower plant for the different solar field sizes based on an air cooling condenser system.

    Water Consumption-Air Cooling Condenser (m)

    ConsumptionLoops

    96 120 132 144 156 168 180 204

    Power Cycle Water 16,820.16 16,820.16 16,820.16 16,820.16 16,820.16 16,339.38 17,888.64 16,820.16

    Mirror Washing Water 43,636.36 54,545.45 60,000.00 65,454.55 70,909.09 76,363.64 81,818.18 92,727.27

    Others 26,880.00 26,880.00 26,880.00 26,880.00 26,880.00 26,880.00 26,880.00 26,880.00

    Blowdown Water Treatment 37,367.66 43,960.46 47,256.86 50,553.26 53,849.66 56,855.51 61,088.19 67,035.27

    Total 124,704.18 142,206.07 150,957.02 159,707.97 168,458.91 176,438.53 187,675.01 203,462.70

    As shown in the diagram below the water consumption increases with increasing the

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    48/94

    PROJECT IN SOUTH AFRICA REVIEW 0

    South Africa, North Cape Region,

    BOKPOORT

    The following graph shows the monthly water consumption evolution of the power plant

    for the different solar field sizes and a cooling system based on air cooling condenser.

    At the same time, it is possible to see how the water consumption increases with thesolar field size.

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    49/94

    PROJECT IN SOUTH AFRICA REVIEW 0

    South Africa, North Cape Region,

    BOKPOORT

    Hybrid cooling tower results

    The following table indicates the most important water consumptions of the power plant

    for the different solar field sizes based on a hybrid cooling tower system.

    Water Consumption-Hybrid Cooling Tower (m)

    Consumption Loops96 120 132 144 156 168 180 204

    Power Cycle Water 402,454.93 440,215.51 461,909.52 474,727.34 486,428.52 497,787.97 506,026.02 518,817.71

    Mirror Washing Water 43,636.36 54,545.45 60,000.00 65,454.55 70,909.09 76,363.64 81,818.18 92,727.27

    Others 26,880.00 26,880.00 26,880.00 26,880.00 26,880.00 26,880.00 26,880.00 26,880.00

    Blowdown Water Treatment 49,907.18 57,667.84 61,635.19 65,328.02 68,986.31 72,634.04 76,185.23 83,173.65

    Total 522,878.47 579,308.80 610,424.71 632,389.90 653,203.92 673,665.65 690,909.43 721,598.63

    As shown in the diagram below, the water consumption increases with increasing the

    number of the solar field loops. In turn, it is observed that the most important water

    consumption is produced by the cooling system, decreasing slightly against the wet

    cooling system.

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    50/94

    PROJECT IN SOUTH AFRICA REVIEW 0

    South Africa, North Cape Region,BOKPOORT

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    51/94

    Sout ca, o t Cape eg o ,BOKPOORT

    Page 51

    4.3.2 Option 2: LFO firing up to 15%.

    RESULTS WET COOLING TOWER 96 120 132 144 156 168 180 204

    Total Gross electricity production GWhe 175 211 225 237 248 256 263 274

    Total Auxiliary consumptions GWhe 19 23 24 26 28 29 30 33

    Total Net Electricity production GWhe 155 189 201 211 220 227 234 242

    Maximum net power output MWe 74,6 75,1 75,1 75,1 75,0 75,0 75,0 75,0

    LFO Heaters

    Hours in operation, Fuel only mode h 0 0 0 0 0 150 290 510

    % Electricity production (solar and fuel mode) 15,0% 15,0% 15,0% 15,0% 15,0% 13,2% 11,7% 9,4%

    % Electricity production (fuel only mode) 0,0% 0,0% 0,0% 0,0% 0,0% 1,8% 3,3% 5,6%

    % Electricity production total 15,0% 15,0% 15,0% 15,0% 15,0% 15,0% 15,0% 15,0%

    LFO Total Consumption GWh th 81,3 97,4 103,9 109,6 114,2 119,3 123,5 130,2

    Equivalent hours steam turbine h 2.083 2.515 2.682 2.825 2.947 3.047 3.136 3.264

    Thermal Efficiency annual Solar Field 46,4% 44,4% 42,9% 41,3% 39,7% 38,1% 36,6% 33,6%

    Solar-Electric Efficiency Annual 18,7% 18,1% 17,5% 16,9% 16,2% 15,3% 14,4% 12,8%

    DNI kWh/m2 2.654 2.654 2.654 2.654 2.654 2.654 2.654 2.654

    Availability 98,0% 98,0% 98,0% 98,0% 98,0% 98,0% 98,0% 98,0%

    Electricity losses 2,0% 2,0% 2,0% 2,0% 2,0% 2,0% 2,0% 2,0%

    Net electricity injected to the grid GWhe 149 181 193 203 211 218 224 232

    Net equivalent hours of CSP plant h 2.001 2.414 2.570 2.703 2.815 2.910 2.993 3.096

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    52/94

    BOKPOORT

    Page 52

    RESULTS AIR COOLING CONDENSER 96 120 132 144 156 168 180 204

    Total Gross electricity production GWhe 159 193 206 217 226 234 241 251

    Total Auxiliary consumptions GWhe 17 20 22 23 25 26 27 30

    Total Net Electricity production GWhe 142 172 184 194 202 208 214 221

    Maximum net power output MWe 67,9 67,9 68,1 68,1 68,1 68,0 67,9 67,9

    LFO Heaters

    Hours in operation, Fuel only mode h 0 0 0 0 0 150 290 520

    % Electricity production (solar and fuel mode) 15,0% 15,0% 15,0% 15,0% 15,0% 13,2% 11,7% 9,4%

    % Electricity production (fuel only mode) 0,0% 0,0% 0,0% 0,0% 0,0% 1,7% 3,3% 5,6%

    % Electricity production total 15,0% 15,0% 15,0% 15,0% 15,0% 15,0% 15,0% 15,0%LFO Total Consumption GWh th 81,3 97,4 103,9 109,6 114,2 119,3 123,5 130,2

    Equivalent hours steam turbine h 1.893 2.294 2.449 2.582 2.696 2.784 2.865 2.984

    Thermal Efficiency annual Solar Field 46,4% 44,4% 42,9% 41,3% 39,7% 38,1% 36,6% 33,6%

    Solar-Electric Efficiency Annual 17,0% 16,6% 16,0% 15,5% 14,9% 14,0% 13,2% 11,8%

    DNI kWh/m2 2.654 2.654 2.654 2.654 2.654 2.654 2.654 2.654

    Availability 98,0% 98,0% 98,0% 98,0% 98,0% 98,0% 98,0% 98,0%

    Electricity losses 2,0% 2,0% 2,0% 2,0% 2,0% 2,0% 2,0% 2,0%

    Net electricity injected to the grid GWhe 136 166 177 186 194 200 205 212Net equivalent hours of CSP plant h 2.001 2.438 2.592 2.730 2.843 2.939 3.025 3.125

    Maximum net power output MWe 70,2 70,7 70,6 70,7 70,6 70,6 70,6 70,4

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,BOKPOORT

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    53/94

    BOKPOORT

    Page 53

    RESULTS HYBRID COOLING TOWER 96 120 132 144 156 168 180 204

    Total Gross electricity production GWhe 163 198 211 222 232 240 247 257

    Total Auxiliary consumptions GWhe 18 20 22 23 25 26 27 30

    Total Net Electricity production GWhe 146 177 189 199 207 214 220 227

    Maximum net power output MWe 70,2 70,3 70,3 70,4 70,1 70,0 70,0 70,0

    LFO Heaters

    Hours in operation, Fuel only mode h 0 0 0 0 0 150 290 520

    % Electricity production (solar and fuel mode) 15,0% 15,0% 15,0% 15,0% 15,0% 13,2% 11,7% 9,4%

    % Electricity production (fuel only mode) 0,0% 0,0% 0,0% 0,0% 0,0% 1,7% 3,3% 5,6%

    % Electricity production total 15,0% 15,0% 15,0% 15,0% 15,0% 15,0% 15,0% 15,0%

    LFO Total Consumption GWh th 81,3 97,4 103,9 109,6 114,2 119,3 123,5 130,2

    Equivalent hours steam turbine h 1.942 2.354 2.512 2.648 2.764 2.857 2.940 3.061

    Thermal Efficiency annual Solar Field 46,4% 44,4% 42,9% 41,3% 39,7% 38,1% 36,6% 33,6%

    Solar-Electric Efficiency Annual 17,5% 17,0% 16,5% 15,9% 15,3% 14,4% 13,6% 12,1%

    DNI kWh/m2 2.654 2.654 2.654 2.654 2.654 2.654 2.654 2.654

    Availability 98,0% 98,0% 98,0% 98,0% 98,0% 98,0% 98,0% 98,0%

    Electricity losses 2,0% 2,0% 2,0% 2,0% 2,0% 2,0% 2,0% 2,0%

    Net electricity injected to the grid GWhe 140 170 182 191 199 206 211 218

    Net equivalent hours of CSP plant h 1.992 2.422 2.583 2.718 2.841 2.938 3.018 3.119

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    54/94

    REVIEW 0

    South Africa, North Cape Region,BOKPOORT

    4.3.2.1 Gross and net electricity production

    The annual electricity output results for the different configurations evaluated are

    included hereafter.

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    55/94

    South Africa, North Cape Region,BOKPOORT

    4.3.2.2 Solar/Electrical efficiency

    The solar/electrical efficiency results for the different configurations evaluated are

    included hereafter.

    4.3.2.3 Total water consumptions

    The following results determine the water consumptions, for a production of the solar

    power plant with use of LFO.

    Wet cooling tower results

    The next table indicates the most important and totals water consumptions of the

    power plant for the different solar field sizes, based on a wet cooling tower system.

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    56/94

    South Africa, North Cape Region,BOKPOORT

    As shown in the diagram below, the water consumption increases with increasing the

    number of the solar field loops. In turn, it is observed that the most important water

    consumption is produced by the cooling system.

    The following graph shows the monthly water consumption evolution of the solar power

    plant for the different solar field sizes and a cooling system based on wet cooling tower.

    At the same time, it is possible to see how the water consumption increases with the

    solar field size.

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    57/94

    South Africa, North Cape Region,BOKPOORT

    Air cooling condenser results

    The next table indicates the most important and totals water consumptions of the

    power plant for the different solar field sizes based on an air cooling condenser system.

    Water Consumption-Air Cooling Condenser (m)

    ConsumptionLoops

    96 120 132 144 156 168 180 204

    Power Cycle Water 18,155.76 18,155.76 18,155.76 18,155.76 18,155.76 17,674.98 18,155.76 18,155.76

    Mirror Washing Water 43,636.36 54,545.45 60,000.00 65,454.55 70,909.09 76,363.64 81,818.18 92,727.27

    Others 26,880.00 26,880.00 26,880.00 26,880.00 26,880.00 26,880.00 26,880.00 26,880.00

    Blowdown Water Treatment 38,174.81 44,767.62 48,064.02 51,360.42 54,656.82 57,662.67 61,249.62 67,842.43

    Total 126,846.94 144,348.83 153,099.78 161,850.72 170,601.67 178,581.28 188,103.57 205,605.46

    As shown in the diagram below, the water consumption increases with increasing the

    number of the solar field loops. Unlike other cooling systems, this is due to the mirror

    washing system consumption.

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    58/94

    South Africa, North Cape Region,BOKPOORT

    Hybrid cooling tower results

    The next table indicates the most important water consumptions of the power plant for

    the different solar field sizes based on a hybrid cooling tower system.

    Water Consumption-Hybrid Cooling Tower (m)

    ConsumptionLoops

    96 120 132 144 156 168 180 204

    Power Cycle Water 435,752.31 475,289.38 500,698.21 515,565.77 538,612.76 544,605.08 548,957.75 555,465.73

    Mirror Washing Water 43,636.36 54,545.45 60,000.00 65,454.55 70,909.09 76,363.64 81,818.18 92,727.27

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    59/94

    South Africa, North Cape Region,BOKPOORT

    The following graph shows the monthly water consumption evolution of the solar power

    plant for the different solar field sizes and a cooling system based on hybrid cooling

    tower. At the same time, it is possible to see how the water consumption increases withthe solar field size.

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    60/94

    South Africa, North Cape Region,BOKPOORT

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    61/94

    South Africa, North Cape Region,BOKPOORT

    5 POWER PLANT OPTIMIZATION

    5.1 Methodology

    The definition of the best solar field configuration is based on a Levelized Cost of

    Electricity (LCOE) model calculation.

    This LCOE requires:

    CAPEX estimation for each configuration

    OPEX estimation for each configuration

    Tariff: (REFIT)

    Basic plant parameters (% degradation, LFO costs, etc)

    Financial parameters (inflation, discount rate)

    5.2 Assessment CAPEX & OPEX

    For each configuration of those considered in the former section, SOLIDA has

    estimated CAPEX and OPEX values.

    The initial spares cost is included in our CAPEX figures. Regular spares are included in

    OPEX.

    The main assumptions for the execution of this subtask are as follows:

    1. All costs are in $ and referred to updated prices in the Spanish market

    2. Earth movement has been estimated with a value of 1 m3 for each 1 m2 of

    power plant area.

    3. Civil works has been estimated based on a typical BOP lay-out, with building

    areas of a 55 MW CSP plant in Spain.

    4. Main equipment has been estimated based on a typical BOP lay-out.

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,BOKPOORT

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    62/94

    Page 62

    CAPEX ($) 96 120 132 144 156 168 180 204WCT 262.597.090 289.819.781 302.958.149 317.706.272 331.257.767 344.766.511 358.446.258 386.660.374

    HYB 267.777.955 295.000.646 308.139.015 322.887.138 336.438.632 349.947.376 363.627.123 391.841.239

    ACC 276.188.289 303.410.980 316.549.349 331.297.472 344.848.967 358.357.711 372.037.457 400.251.574

    WCT_LFO 269.359.877 296.582.568 309.720.936 324.469.060 338.020.554 351.529.298 365.209.045 393.423.161

    HYB_LFO 276.494.462 303.717.153 316.855.522 331.603.645 345.155.140 358.663.884 372.343.630 400.557.747

    ACC_LFO 284.904.797 312.127.488 325.265.856 340.013.979 353.565.474 367.074.218 380.753.964 408.968.081

    OPEX ($) 96 120 132 144 156 168 180 204

    WCT 6.861.600 7.028.482 7.111.172 7.186.483 7.256.049 7.315.205 7.380.721 7.504.157

    HYB 6.772.044 6.902.294 6.977.214 7.042.093 7.118.721 7.168.257 7.212.614 7.325.898

    ACC 6.453.931 6.553.487 6.610.560 6.664.893 6.721.942 6.766.676 6.811.033 6.912.425

    WCT_LFO 11.105.539 12.393.864 12.917.102 13.360.726 13.773.569 14.180.816 14.522.744 15.077.329

    HYB_LFO 11.015.714 12.290.205 12.800.186 13.263.047 13.625.381 14.030.204 14.370.175 15.077.329

    ACC_LFO 10.757.498 11.986.584 12.492.332 12.941.206 13.303.540 13.704.194 14.041.538 14.589.202

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    63/94

    South Africa, North Cape Region,BOKPOORT

    5.3 LCOE

    The definition of the best solar field configuration is based on a Levelized Cost of

    Electricity (LCOE) model calculation.

    The financial assumptions are:

    Inflation: 2%

    Discount Rate: 10%

    Other assumptions:

    % degradation: 0,7 %

    REFIT ($/MWh): 417,62

    LCOE ($/MWh) 96 120 132 144 156 168 180 204

    WCT 303,03 270,53 263,86 261,22 260,41 260,43 261,72 269,91

    HYB 323,91 288,37 281,11 278,13 277,28 277,16 278,34 286,97

    ACC 338,39 302,96 295,24 292,34 290,99 291,35 292,99 301,53

    WCT_LFO 290,13 264,27 258,96 256,76 256,31 257,19 258,76 266,62

    HYB_LFO 314,76 285,03 278,79 276,17 275,14 276,12 277,84 286,92

    ACC_LFO 328,39 296,72 290,06 287,03 285,68 286,85 288,53 296,94

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    64/94

    South Africa, North Cape Region,BOKPOORT

    5.4 Best configuration

    5.4.1 Detailed results

    At it is show in the previous section there are no sensible variations of LCOE for 144

    loops cases to 168 loops cases. SOLIDA has determined to study the 168 loops case

    in depth.

    Option 1: LFO used only for anti-freezing and gland steam generation

    168 L WCTDNI P gross Auxiliary P net

    kWh/m2 MWhe MWhe MWhe

    JAN 266,43 23.655 2.862 20.794

    FEB 205,49 17.324 2.112 15.213

    MAR 208,80 17.176 2.053 15.123APR 194,04 15.664 1.764 13.900

    MAY 189,32 13.451 1.482 11.969

    JUN 184,43 11.382 1.267 10.114

    JUL 197,13 13.133 1.445 11.687

    AUG 226,55 18.115 2.014 16.101

    SEP 222,42 19.477 2.238 17.239

    OCT 233,89 20.435 2.455 17.980

    NOV 249,04 21.337 2.613 18.724

    DEC 276,82 22.935 2.855 20.080

    168 L ACCDNI P gross Auxiliary P net

    kWh/m2 MWhe MWhe MWhe

    JAN 266,43 21.751 2.857 18.894

    FEB 205,49 15.930 2.114 13.816

    MAR 208,80 15.794 2.041 13.753

    APR 194,04 14.403 1.723 12.680

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    65/94

    South Africa, North Cape Region,BOKPOORT

    168 L HYBDNI P gross Auxiliary P net

    kWh/m2 MWhe MWhe MWhe

    JAN 266,43 22.317 2.616 19.701

    FEB 205,49 16.344 1.932 14.412

    MAR 208,80 16.205 1.875 14.330

    APR 194,04 14.778 1.601 13.176MAY 189,32 12.690 1.342 11.348

    JUN 184,43 10.738 1.149 9.589

    JUL 197,13 12.390 1.309 11.081

    AUG 226,55 17.091 1.826 15.264

    SEP 222,42 18.376 2.036 16.340

    OCT 233,66 19.279 2.243 17.036

    NOV 249,04 20.130 2.392 17.738

    DEC 276,82 21.638 2.617 19.020

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    66/94

    South Africa, North Cape Region,BOKPOORT

    Water Consumption-168 Loops (m)

    ConsumptionsWet

    CoolingTower

    HybridCoolingTower

    AirCooling

    Condenser

    Power Cycle Water 693,136.56 497,787.97 16,339.38

    Mirror Washing Water 76,363.64 76,363.64 76,363.64Others 26,880.00 26,880.00 26,880.00

    Blowdown Water Treatment 78,675.75 72,634.04 56,855.51

    Total 875,055.94 673,665.65 176,438.53

    As shown in the diagram below, the higher water consumption of the solar power plant

    occurs with the wet cooling tower option. Moreover, it can also be seen that the air

    cooled condenser option reduces notably the yearly water consumption.

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    S h Af i N h C R i

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    67/94

    South Africa, North Cape Region,BOKPOORT

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa North Cape Region

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    68/94

    South Africa, North Cape Region,BOKPOORT

    Option 2: LFO firing up to 15%.

    168 L WCTDNI P gross Auxiliary P net

    kWh/m2 MWhe MWhe MWhe

    JAN 266,43 26.483 3.095 23.388

    FEB 205,49 19.386 2.284 17.102

    MAR 208,80 19.272 2.223 17.049

    APR 194,04 18.738 2.021 16.717

    MAY 189,32 16.737 1.757 14.980

    JUN 184,43 16.556 1.704 14.853

    JUL 197,13 17.098 1.776 15.321

    AUG 226,55 21.269 2.280 18.989SEP 222,42 22.451 2.486 19.964

    OCT 233,66 23.449 2.704 20.746

    NOV 249,04 24.058 2.840 21.218

    DEC 276,82 25.889 3.100 22.790

    168 L ACC DNI P gross Auxiliary P netkWh/m2 MWhe MWhe MWhe

    JAN 266,43 24.210 2.809 21.401

    FEB 205,49 17.721 2.076 15.645

    MAR 208,80 17.616 2.013 15.603

    APR 194,04 17.132 1.813 15.319

    MAY 189,32 15.300 1.569 13.731

    JUN 184,43 15.136 1.516 13.620

    JUL 197,13 15.632 1.583 14.049

    AUG 226,55 19.446 2.040 17.405

    SEP 222,42 20.522 2.235 18.287

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa North Cape Region

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    69/94

    South Africa, North Cape Region,BOKPOORT

    168 L HYBDNI P gross Auxiliary P net

    kWh/m2 MWhe MWhe MWhe

    JAN 266,43 24.840 2.812 22.029

    FEB 205,49 18.182 2.076 16.106

    MAR 208,80 18.074 2.016 16.058

    APR 194,04 17.577 1.821 15.757MAY 189,32 15.698 1.578 14.120

    JUN 184,43 15.530 1.526 14.004

    JUL 197,13 16.038 1.593 14.446

    AUG 226,55 19.952 2.052 17.900

    SEP 222,42 21.056 2.245 18.810

    OCT 233,66 21.992 2.452 19.540

    NOV 249,04 22.566 2.582 19.984DEC 276,82 24.282 2.822 21.460

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa North Cape Region

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    70/94

    South Africa, North Cape Region,BOKPOORT

    Water Consumption-168 Loops (m)

    ConsumptionsWet

    CoolingTower

    HybridCoolingTower

    AirCooling

    Condenser

    Power Cycle Water 787,746.41 544,605.08 17,674.98

    Mirror Washing Water 76,363.64 76,363.64 76,363.64Others 26,880.00 26,880.00 26,880.00

    Blowdown Water Treatment 81,601.83 74,081.99 57,662.67

    Total 972,591.87 721,930.70 178,581.28

    As shown in the diagram below, the higher water consumption of the solar power plant

    occurs with the wet cooling tower option. Moreover, it can also be seen that the aircooled condenser option reduces notably the yearly water consumption.

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    71/94

    South Africa, North Cape Region,BOKPOORT

    5.5 Radiation scenarios

    Option 1: LFO used only for anti-freezing and gland steam generation

    RESULTS WET COOLING TOWER (168L) P15 P50 P85

    Total Gross electricity production GWhe 227 214 203

    Total Auxiliary consumptions GWhe 26 25 24

    Total Net Electricity production GWhe 201 189 179

    LFO Heaters

    % LFO usage, base thermal input % 0,0% 0,0% 0,0%

    Equivalent hours steam turbine h 2.708 2.549 2.417

    Thermal Efficiency annual Solar Field 39,3% 38,1% 37,6%

    Solar-Electric Efficiency Annual 13,4% 13,0% 12,8%

    DNI kWh/m2 2.728 2.654 2.556

    Availability 98% 98% 98%

    Electricity losses 2% 2% 2%Net electricity injected to the grid GWhe 193 181 172

    Net equivalent hours of CSP plant h 2.572 2.418 2.293

    TECHNICAL ADVISOR FOR A CSP

    PROJECT IN SOUTH AFRICA

    DOC. CODE SO-DV-1006

    REVIEW 0

    South Africa, North Cape Region,

  • 7/25/2019 TASK 2 FINAL REPORT.pdf

    72/94

    , p g ,BOKPOORT

    RESULTS AIR COOLING CONDENSER (168 L) P15 P50 P85

    Total Gross electricity production GWhe 209 197 187

    Total Auxiliary consumptions GWhe 26 25 24

    Total Net Electricity production GWhe 183 172 163

    LFO Heaters

    % LFO usage, base thermal input % 0,0% 0,0% 0,0%

    Equivalent hours steam turbine h 2.490 2.343 2.223

    Thermal Efficiency annual Solar Field 39,3% 38,1% 37,6%

    Solar-Electric Efficiency Annual 12,2% 11,8% 11,6%

    DNI kWh/m2 2.728 2.654 2.556

    Availability 98% 98% 98%

    Electricity losses 2% 2% 2%

    Net electricity injected to the grid GWhe 176 165 157

    Net equivalent hours of CSP plant h 2.580 2.425 2.299

    TECHNICAL ADVISOR FOR A CSP

    PRO