Tanks Installation Manual

Embed Size (px)

Citation preview

  • 7/31/2019 Tanks Installation Manual

    1/53

    Process Engineering and Contracting Division

    NARGAN

    ASALUYE

    C2+ RECOVERY ANDFRACTIONATION PLANT

    PARS

    PETROCHEMICAL

    COMPANY

    Linde Project No.: 21101055 NARGAN Proj-No.: N-178 Owner Project No.: 3910

    Linde Job Code: Asaluye NARGAN Job Code: Owner Job Code: PPC-RFPLinde Doc. No.: BMM50005 Owner Doc. No.: 10-VD-A4-PV-014-084-L

    Installation ManualTP-000-16

    (Page 1-32)

    and

    attachment:Welding Sequence Bottom and Shell

    (Page 1- 13)and

    attachment:Assembly Procedure of Erection Openings

    (Page 1- 3)

    Tk-No. 10-TK-0661-PropaneTk-No. 10-TK-0662-Butane

    Inner Tank Dia: 40 000 mmOuter Tank Dia: 42 200 mm

    Linde P.O. No.: 2 DE 466

    04 01.11.02 49 Stelck Tacke R. Schulte revised per comments

    P 03 27.08.02 30 Stelck Tacke R. Schulte revised per comments

    P 02 26.04.02 30 Stelck Tacke R. Schulte revised per commentsP 01 21.03.02 30 Stelck Tacke van Ommen

    Status Issue Date Pages Prepared Checked Approved Remarks

    Intellectual property rights reserved.

  • 7/31/2019 Tanks Installation Manual

    2/53

    a d a p t GmbH

    the project manager

    for cryogenic and atmospheric tanks

    ERECTION SEQUENCE

    TANK 0661 / 0662

    a d a p t GmbH Project

    P - 01-1021

    150

    Outer tank

    annular plate

    Outer tank

    bottom

    Foundation Slab

    Leveling course

    X Ray 25%

    min 150mm

    Field painting - Coating before

    in position.

    Reference:

    Anchor straps Drawing Inner Tank No: 19

    Outer Tank No: 18

    Bottom of outer tank No: 07

    Welding : according to applicable WPS

    Inspection: X-Ray ( 25%), visual and Vacuum-Box-Test

    acc. to T.i.P. TP-000-06, Length of X-Ray-film : min 150mm ( 6 in)

    Client: Linde Process Engineering and Contracting division

    Project No.: 2110 1055 ASALUYE

    Linde Doc.No.: BMM 50005

    Owner Doc. No.: 10-VD-A4-PV-014-084L

    Page 1 of 32

    TP-000-16, Rev. 04

  • 7/31/2019 Tanks Installation Manual

    3/53

    a d a p t GmbH

    the project manager

    for cryogenic and atmospheric tanks

    ERECTION SEQUENCE

    TANK 0661 / 0662

    a d a p t GmbH Project

    P - 01-1021

    about 100

    Erection of outer tank

    shell course 1

    Erection of outer tank shell course 1

    A) in about 100 mm lifted position

    1. Welding vertical weld seams as per applicable WPS

    2. X -Ray and visual Examination as per T.i.P. (TP-000-06)

    B) positioning

    3. Put down

    4. Annular plate and shell plate tack weld

    Client: Linde Process Engineering and Contracting division

    Project No.: 2110 1055 ASALUYELinde Doc.No.: BMM 50005

    Owner Doc. No.: 10-VD-A4-PV-014-084L

    Page 2 of 32

    TP-000-16, Rev. 04

  • 7/31/2019 Tanks Installation Manual

    4/53

    a d a p t GmbH

    the project manager

    for cryogenic and atmospheric tanks

    ERECTION SEQUENCE

    TANK 0661 / 0662

    a d a p t GmbH Project

    P - 01-1021

    353

    350

    188

    min. 300

    891

    1100

    1388

    min. 300 4.300

    see drawing no. 21: Temporary Erection Opening in shell course 1

    after welding of shell course 2

    Step 1 = 4300 x height of course 1

    Step 2 = 2700 x height of course 1 - 300+891 = 1100mm

    after water hydrotest for outer tank

    Erection of outer tank

    shell course 2

    Welding of outer tank shell course 2 vertical weld seamsand horizontal weld seam acc. to applicable WPS,

    Inspection: Visual, 100% X-Ray vertical joints,

    100% X-Ray of all intersections of joints, Spot X-Ray and

    Magnetic-Particle Examination of horizontal joints as per T.i.P ( TP-000-06 )

    Step 2Step 1

    Step 2

    Outer tank anchor

    course 1

    course 2

    Client: Linde Process Engineering and Contracting division

    Project No.: 2110 1055 ASALUYELinde Doc.No.: BMM 50005

    Owner Doc. No.: 10-VD-A4-PV-014-084L

    Page 3 of 32

    TP-000-16, Rev. 04

  • 7/31/2019 Tanks Installation Manual

    5/53

    a d a p t GmbHthe project manager

    for cryogenic and atmospheric tanks

    ERECTION SEQUENCE

    TANK 0661 / 0662

    a d a p t GmbH Project

    P - 01-1021

    about 100

    150

    2m

    1.) inner tank annular plate2.) inner tank shell

    place Steel Blocks free of

    bottom welds

    Distance between the blocks = 2,0m

    X Ray 25%

    min 150mm

    Welding acc. to applicable WPS

    Inspection acc. to T.i.P ( TP-00-20 )

    visual, X-Ray and Vacuum- Box

    Welding of Shell Course 1 to annular plate

    after erection of course 2 acc. to appl. WPS

    Inspection acc. to T.i.P ( TP-000-06 )

    visual, Vacuum Box Test

    and Magnetic Penetrant Test.

    3.) inner tank shell course 1 with annular plate tack weldDistance between the top of O.T

    annular plate to the below of

    I.T.annular plate = 450mmsee Drawing No.T-0661-01

    max load (dead

    weight) from inner

    tank shell

    2,50 tos / m

    Tolerances of inner tank annular

    plates: see Drawing No. T-0661-18

    Tolerances of Foundation

    Client: Linde Process Engineering and Contracting division

    Project No.: 2110 1055 ASALUYE

    Linde Doc.No.: BMM 50005

    Owner Doc. No.: 10-VD-A4-PV-014-084L

    Page 4 of 32

    TP-000-16, Rev. 04

  • 7/31/2019 Tanks Installation Manual

    6/53

    a d a p t GmbH

    the project manager

    for cryogenic and atmospheric tanks

    ERECTION SEQUENCE

    TANK 0661 / 0662

    a d a p t GmbH Project

    P - 01-1021

    4.300

    max. about 45

    45,00 m radius

    Erection of outer tank course 3 thru 12

    and compression bar,

    and outer shell stiffeners

    Erection-welder cages

    2 x for Erection and welding

    1 x for Inspections and Tests

    Scaffolding for shell in annular space

    Temporary Erection Opening of

    inner tank shell, see drawing no. 22

    Erection of inner tank shell course 3 thru 11

    and top shell stiffener

    Welding: All welding shall be carried out acc. to applicable

    WPS

    Inspection acc. T.i.P ( TP-00-20 )

    Visual Inspection of all welds

    Radiographic Examination.

    Vacuum Box- Examination

    Storm Guys required

    above this level

    ( course 4 )

    Storm guy 13,0mm dia

    wire rope for wind blow

    in. Position 15 anchor

    points equally spaced at

    55mtrs radius

    100 x 5 Flat Tie Bar

    Make provision for

    temporary ties between

    inner tank and outer

    tank-to installed hen

    high wind is forecast

    Erection of-inner shell top stiffener

    A) positioning on shell

    1) Welding radial weld seams acc WPS

    2) Welding horizontal weld seams acc toWPS

    1)2)

    Erecting of insert plates for Nozzle N03 at

    inner and outer tank

    Client: Linde Process Engineering and Contracting division

    Project No.: 2110 1055 ASALUYELinde Doc.No.: BMM 50005

    Owner Doc. No.: 10-VD-A4-PV-014-084L

    Page 5 of 32

    TP-000-16, Rev. 04

  • 7/31/2019 Tanks Installation Manual

    7/53

    a d a p t GmbH

    the project manager

    for cryogenic and atmospheric tanks

    ERECTION SEQUENCE

    TANK 0661 / 0662

    a d a p t GmbH Project

    P - 01-1021

    Erection of outer tank shell course 3 thru 12

    and compression bar,

    and outer and inner tank shell stiffener

    Erection of outer tank compression bar

    A)1. Welding acc. to applicable WPS

    2. X- Ray min 25% and visual examination

    B)3.welding inner and outer fillet weld acc. to appl. WPS

    4. Visual Examination

    Client: Linde Process Engineering and Contracting division

    Project No.: 2110 1055 ASALUYELinde Doc.No.: BMM 50005

    Owner Doc. No.: 10-VD-A4-PV-014-084L

    Page 6 of 32

    TP-000-16, Rev. 04

  • 7/31/2019 Tanks Installation Manual

    8/53

    a d a p t GmbH

    the project manager

    for cryogenic and atmospheric tanks

    ERECTION SEQUENCE

    TANK 0661 / 0662

    a d a p t GmbH Project

    P - 01-1021

    clear span 2.310 max =1.400 for the center column

    crown ring ( suspended deck )

    2.400

    1200

    17

    330

    5.686100

    3.000

    1.980

    Erection Opening

    suspended deck

    26.200

    1200

    1200

    45

    safety net

    Erecting platform

    Erection of crown Ring,

    see Drawing No. 33

    Ladder

    stay rope rope /6x13,0mm

    central support support for

    max 1/3 dead weight roof

    round (60 tons)

    Height to top of outer

    shell see

    Drawing No.: 01 / 08

    Plate 20mm 300x300

    collumns HEB 140

    bracket U 300

    diagonals L 80x80x8

    filler plate rd.100mm

    Client: Linde Process Engineering and Contracting division

    Project No.: 2110 1055 ASALUYE

    Linde Doc.No.: BMM 50005

    Owner Doc. No.: 10-VD-A4-PV-014-084L

    Page 7 of 32

    TP-000-16, Rev. 04

  • 7/31/2019 Tanks Installation Manual

    9/53

    a d a p t GmbH

    the project manager

    for cryogenic and atmospheric tanks

    ERECTION SEQUENCE

    TANK 0661 / 0662

    a d a p t GmbH Project

    P - 01-1021

    Weight 18 segment 1 segment

    T-0661-23 5439 kg 302 kg

    T-0661-24 5033 kg 280 kg

    T-0661-25 6457 kg 359 kg

    16929 kg 941 kg

    50 365

    6633

    top of Roof

    R = 1050 31.911

    365 25

    R = 19100 30

    R = 2325 5.686

    6.789

    top of O.T.Shell top of O.T.Shell

    26.200 8123 26.200

    1.468 24.732

    6

    R =

    18.050 1050

    R = 19.100

    Outer Tank

    A

    A

    section A-A

    1/18 segment-suspended- deck

    acc.drawing no.:T-0661-23

    Roof Rafters

    RAFTER

    RAFTER

    RAFTER

    RAFTER

    Client: Linde Process Engineering and Contracting division

    Project No.: 2110 1055 ASALUYE

    Linde Doc.No.: BMM 50005

    Owner Doc. No.: 10-VD-A4-PV-014-084L

    Page 8 of 32

    TP-000-16, Rev. 04

  • 7/31/2019 Tanks Installation Manual

    10/53

    a d a p t GmbH

    the project manager

    for cryogenic and atmospheric tanks

    ERECTION SEQUENCE

    TANK 0661 / 0662

    a d a p t GmbH Project

    P - 01-1021

    270 90

    180

    0

    A

    A

    SECTION A - A

    1 / 18 segment of

    suspended deckHangers only for erection

    1 / 18 segment of

    suspended deck

    1 / 18 segment of

    suspended deck

    and 3 x raffters

    Client: Linde Process Engineering and Contracting divisionProject No.: 2110 1055 ASALUYE

    Linde Doc.No.: BMM 50005

    Owner Doc. No.: 10-VD-A4-PV-014-084L

    Page 9 of 32

    TP-000-16, Rev. 04

  • 7/31/2019 Tanks Installation Manual

    11/53

    a d a p t GmbH

    the project manager

    for cryogenic and atmospheric tanks

    ERECTION SEQUENCE

    TANK 0661 / 0662

    a d a p t GmbH Project

    P - 01-1021

    17

    271

    8123 R = 10.978

    2444 271

    50 299 2026

    6633 365

    2444

    top of Roof 271

    R = 1050 31.911

    25

    365

    2444

    R = 2325 5.686

    R = 8.033 6.789

    R =

    21006 2.000

    top of O.T.Shell IPE 300=229

    26.200 IPE 360=281 top of O.T.Shell

    65 IPE 500=404 26.200

    52 1.533

    123 1.468 24.732

    6

    18.050

    R = 6.000

    R = 19.100 1050

    Outer Tank

    A

    A section A-A

    1/18 segment-suspended- deck

    acc.drawing no.:T-0661-23

    with 3 rafters IPE 300 or

    IPE 360 or IPE 500 incuded interm.

    stiffeners Roof Rafters

    RAFTER

    RAFTER

    RAFTER

    RAFTER

    Client: Linde Process Engineering and Contracting division

    Project No.: 2110 1055 ASALUYE

    Linde Doc.No.: BMM 50005

    Owner Doc. No.: 10-VD-A4-PV-014-084L

    Page 10 of 32

    Revision 04

  • 7/31/2019 Tanks Installation Manual

    12/53

    a d a p t GmbH

    the project manager

    for cryogenic and atmospheric tanks

    ERECTION SEQUENCE

    TANK 0661 / 0662

    a d a p t GmbH Project

    P - 01-1021

    Errection of outer tank roof rafters with

    segment of suspended deck stay rope

    6

    7

    8

    Hangers for suspended

    deck, see Drawing no. 23,

    24, 25

    Erecting platform for

    segment of suspended

    deck and roof rafters inground position

    suspended deck

    2

    1

    3

    5

    4

    3 rafters with (3) =

    1/18 suspended deck

    3 rafters with (3) =

    1/18 suspended deck

    3 rafters with (3) =

    1/18 suspended deck

    3 rafters with (3) =

    1/18 suspended deck

    Client: Linde Process Engineering and Contracting divisionProject No.: 2110 1055 ASALUYELinde Doc.No.: BMM 50005Owner Doc. No.: 10-VD-A4-PV-014-084L

    Page 11 of 32

    Revision 04

  • 7/31/2019 Tanks Installation Manual

    13/53

    a d a p t GmbH

    the project manager

    for cryogenic and atmospheric tanks

    ERECTION SEQUENCE

    TANK 0661 / 0662

    a d a p t GmbH Project

    P - 01-1021

    Erection of hangers for suspended deck and

    erecting platform for suspended deck

    Welding acc. to applicable WPS

    Visual inspection acc to T.i.P. ( TP-000-06 )

    3 Rafters = 1 / 18

    Client: Linde Process Engineering and Contracting divisionProject No.: 2110 1055 ASALUYELinde Doc.No.: BMM 50005Owner Doc. No.: 10-VD-A4-PV-014-084L

    Page 12 of 32

    Revision 04

  • 7/31/2019 Tanks Installation Manual

    14/53

    a d a p t GmbH

    the project manager

    for cryogenic and atmospheric tanks

    ERECTION SEQUENCE

    TANK 0661 / 0662

    a d a p t GmbH Project

    P - 01-1021

    1.)Erection of tank roof plates, see Drawing

    No. 10

    2.) Continue welding acc. to appl. WPS

    3.) Visual Inspection according to

    T.i.P ( TP-000-06 )

    safety net

    WALKING ON THE SUSPENDED DECK

    general max loads at roof plates a = 100,0 kg/m2

    scaffold board - wood

    scaffold board -wood

    max load with Scaffold board (

    wood ) a two person or max100 kg/m2

    max load without Scaffold board (

    plywood) a one person

    Client: Linde Process Engineering and Contracting divisionProject No.: 2110 1055 ASALUYELinde Doc.No.: BMM 50005Owner Doc. No.: 10-VD-A4-PV-014-084L

    Page 13 of 32

    Revision 04

  • 7/31/2019 Tanks Installation Manual

    15/53

    a d a p t GmbH

    the project manager

    for cryogenic and atmospheric tanks

    ERECTION SEQUENCE

    TANK 0661 / 0662

    a d a p t GmbH Project

    P - 01-1021

    15mm

    813 x 12,7Temporary Erection Openig welding,

    100% X Ray acc. to T.i.P ( TP-000- 06

    )

    and visual Inspection; Vacuum / MP

    Erecting of inner shell ladder

    erecting of horizontal and

    vertical stiffeners

    erecting of pads for piping +anchor

    pads +water spray +steel structure

    ++++

    Welding acc. to appl. WPS

    Inspection acc. T.i.P ( TP-000-06 )

    Visual; Magnetic Penetrant Examination

    Opening for Pump Suction

    Nozzle N03 on shell, see

    drawing no. 43

    use Nozzle N03 for water

    test and draining

    Note to Field:

    Use Leftover from

    Field Cutting Sketch

    drawing no.-30

    Client: Linde Process Engineering and Contracting divisionProject No.: 2110 1055 ASALUYE

    Linde Doc.No.: BMM 50005

    Owner Doc. No.: 10-VD-A4-PV-014-084L

    Page 14 of 32

    Revision 04

  • 7/31/2019 Tanks Installation Manual

    16/53

    a d a p t GmbH

    the project manager

    for cryogenic and atmospheric tanks

    ERECTION SEQUENCE

    TANK 0661 / 0662

    a d a p t GmbH Project

    P - 01-1021

    For Outer Tank Hydrostatic Testand Filling Height, refer to

    Procedure No............

    welding of outer anchors as perWPS at partial water filling,see Drawing No. 18.Inspection acc. to T.i.P: visual and

    Magnetic-Penetrant Examination.

    after Hydrostatic Test perform

    vacuum box test of bottom welds

    Client: Linde Process Engineering and Contracting divisionProject No.: 2110 1055 ASALUYE

    Linde Doc.No.: BMM 50005Owner Doc. No.: 10-VD-A4-PV-014-084L

    Page 15 of 32

    Revision 04

  • 7/31/2019 Tanks Installation Manual

    17/53

  • 7/31/2019 Tanks Installation Manual

    18/53

    a d a p t GmbH

    the project manager

    for cryogenic and atmospheric tanks

    ERECTION SEQUENCE

    TANK 0661 / 0662

    a d a p t GmbH Project

    P - 01-1021

    Height between inner

    and outer bottom see

    Drawing No. 0661(2)-01

    hydraulic press min = 25 to nns pressure

    wood cotter to install

    Concrete layer 100 mm to install

    length of one shell plate

    to install of hard wood blocks

    Client: Linde Process Engineering and Contracting division

    Project No.: 2110 1055 ASALUYE

    Linde Doc.No.: BMM 50005

    Owner Doc. No.: 10-VD-A4-PV-014-084L

    Page 17 of 32

    Revision 04

  • 7/31/2019 Tanks Installation Manual

    19/53

    a d a p t GmbHthe project managerfor cryogenic and atmospheric tanks

    ERECTION SEQUENCE

    TANK 0661 / 0662

    a d a p t GmbH Project

    P - 01-1021

    60

    wood cotter

    40 40 x 60 x 480

    30

    505 Stck pro Tank

    480

    60

    wood cotter

    60 70 x 60 x 500

    70

    505 Stck pro Tank

    500

    wood cotter wood cotter

    Hight of inner tank

    bottom see drawing:

    T 0661-1 / T 0662-1

    crack / round 10 - 30 mm

    hydraulik press min = 25 tonns pressure

    wood cotter to install

    lenght of one shell plate

    to install of hard wood blocks

    Client: Linde Process Engineering and Contracting division

    Project No.: 2110 1055 ASALUYE

    Linde Doc.No.: BMM 50005

    Owner Doc. No.: 10-VD-A4-PV-014-084L

    Page 18 of 32

    Revision 04

  • 7/31/2019 Tanks Installation Manual

    20/53

    a d a p t GmbH

    the project manager

    for cryogenic and atmospheric tanks

    ERECTION SEQUENCE

    TANK 0661 / 0662

    a d a p t GmbH Project

    P - 01-1021

    place base layer of concrete

    leveling layer

    Erecting of roof nozzles and

    manhole

    Client: Linde Process Engineering and Contracting divisionProject No.: 2110 1055 ASALUYELinde Doc.No.: BMM 50005Owner Doc. No.: 10-VD-A4-PV-014-084L

    Page 19 of 32

    Revision 04

  • 7/31/2019 Tanks Installation Manual

    21/53

  • 7/31/2019 Tanks Installation Manual

    22/53

    a d a p t GmbH

    the project manager

    for cryogenic and atmospheric tanks

    ERECTION SEQUENCE

    TANK 0661 / 0662

    a d a p t GmbH Project

    P - 01-1021

    1.) Erection of inner tank bottom1a) welding acc. to applicable WPS

    1b) Inspection acc. T.i.P: visual and Vacuum-Box-Test

    2.) Erect inner tank internal

    piping and ladder

    2a) Welding acc to appl. WPS

    2b) Inspection acc to T.i.P

    Visual and Magnetic Particle Test

    Solution Test of Reinfocement plates

    Nozzles

    Client: Linde Process Engineering and Contracting divisionProject No.: 2110 1055 ASALUYELinde Doc.No.: BMM 50005Owner Doc. No.: 10-VD-A4-PV-014-084L

    Page 21 of 32

    Revision 04

  • 7/31/2019 Tanks Installation Manual

    23/53

    a d a p t GmbH

    the project manager

    for cryogenic and atmospheric tanks

    ERECTION SEQUENCE

    TANK 0661 / 0662

    a d a p t GmbH Project

    P - 01-1021

    Erection of steel structure on roof

    and outer shell stairway

    Closing of access opening at inner tank shell.

    Welding according to applicable WPS

    Inspection: Visual and 100% X-Ray acc. to T.i.P ( TP-000-06 )

    Weather Protection

    Erect of Suction Nozzle NO3

    Welding according to applicable WPS

    Inspection: Visual 100% X-Ray acc. to T.i.P ( TP-000-06 )

    and Vacuum

    Client: Linde Process Engineering and Contracting divisionProject No.: 2110 1055 ASALUYELinde Doc.No.: BMM 50005Owner Doc. No.: 10-VD-A4-PV-014-084L

    Page 22 of 32

    Revision 04

  • 7/31/2019 Tanks Installation Manual

    24/53

  • 7/31/2019 Tanks Installation Manual

    25/53

    a d a p t GmbH

    the project manager

    for cryogenic and atmospheric tanks

    ERECTION SEQUENCE

    TANK 0661 / 0662

    a d a p t GmbH Project

    P - 01-1021

    Hydro-water-test

    without Over pressure

    Welding of inner tank anchors

    to be done during partial water filling of

    inner tank (see Drawing No. 19), but

    before applying any air pressure.

    Hight Level of water filling see

    HPT- TP-000-08

    acces openig

    Client: Linde Process Engineering and Contracting divisionProject No.: 2110 1055 ASALUYELinde Doc.No.: BMM 50005Owner Doc. No.: 10-VD-A4-PV-014-084L

    Page 24 of 32

    Revision 04

  • 7/31/2019 Tanks Installation Manual

    26/53

  • 7/31/2019 Tanks Installation Manual

    27/53

  • 7/31/2019 Tanks Installation Manual

    28/53

  • 7/31/2019 Tanks Installation Manual

    29/53

    a d a p t GmbH

    the project manager

    for cryogenic and atmospheric tanks

    ERECTION SEQUENCE

    TANK 0661 / 0662

    a d a p t GmbH Project

    P - 01-1021

    PU - Insulation at inside of

    outer tank shell

    after PU - Insulation

    erretion of piping in shell

    annular space on wood

    erecting oppening.

    one roof plate

    After PU - Insulation

    close the erretion

    opening

    welding acc.

    TIP -TP-000-06 WPS

    100% X Ray and

    visual,vacuum

    Foam maschins and Foam

    components on the floor.Alternativ on top of platform

    Client: Linde Process Engineering and Contracting division

    Project No.: 2110 1055 ASALUYE

    Linde Doc.No.: BMM 50005

    Owner Doc. No.: 10-VD-A4-PV-014-084L

    Page 28 of 32

    Revision 04

  • 7/31/2019 Tanks Installation Manual

    30/53

    a d a p t GmbH

    the project manager

    for cryogenic and atmospheric tanks

    ERECTION SEQUENCE

    TANK 0661 / 0662

    a d a p t GmbH Project

    P - 01-1021

    Roof plate oppening

    0

    PU - Insulation at inside of

    outer tank shell in part of

    errection opening

    Client: Linde Process Engineering and Contracting divisionProject No.: 2110 1055 ASALUYELinde Doc.No.: BMM 50005Owner Doc. No.: 10-VD-A4-PV-014-084L

    Page 29 of 32

    Revision 04

  • 7/31/2019 Tanks Installation Manual

    31/53

    a d a p t GmbH

    the project manager

    for cryogenic and atmospheric tanks

    ERECTION SEQUENCE

    TANK 0661 / 0662

    a d a p t GmbH Project

    P - 01-1021

    0

    close suspended deckannular space

    Client: Linde Process Engineering and Contracting divisionProject No.: 2110 1055 ASALUYELinde Doc.No.: BMM 50005Owner Doc. No.: 10-VD-A4-PV-014-084L

    Page 30 of 32

    Revision 04

  • 7/31/2019 Tanks Installation Manual

    32/53

    a d a p t GmbH

    the project manager

    for cryogenic and atmospheric tanks

    ERECTION SEQUENCE

    TANK 0661 / 0662

    a d a p t GmbH Project

    P - 01-1021

    0

    Insulation of suspended

    deck

    Client: Linde Process Engineering and Contracting divisionProject No.: 2110 1055 ASALUYELinde Doc.No.: BMM 50005Owner Doc. No.: 10-VD-A4-PV-014-084L

    Page 31 of 32

    Revision 04

  • 7/31/2019 Tanks Installation Manual

    33/53

  • 7/31/2019 Tanks Installation Manual

    34/53

    a d a p t GmbH

    the project manager

    for cryogenic and atmospheric tanks

    ERECTION SEQUENCE

    TANK 0661 / 0662

    a d a p t GmbH Project

    P - 01-1021

    5000 5000

    2026 9820 9156

    150

    150

    27090

    180

    0

    A

    A

    SECTION A - A

    1 / 18 segment of

    suspended deckHangers only for erection

    1 / 18 segment of

    suspended deck

    1 / 18 segment of

    suspended deck

    and 3 x raffters

    centroid

    centroid

    Client: Linde Process Engineering and Contracting divisionProject No.: 2110 1055 ASALUYE

    Linde Doc.No.: BMM 50005

    Owner Doc. No.: 10-VD-A4-PV-014-084L

    Page 1 of 4

    Revision 04

  • 7/31/2019 Tanks Installation Manual

    35/53

    a d a p t GmbH

    the project manager

    for cryogenic and atmospheric tanks

    ERECTION SEQUENCE

    TANK 0661 / 0662

    a d a p t GmbH Project

    P - 01-1021

    17

    271

    8123 R = 10.978

    2444 271

    50 299 2026

    6633 365

    2444

    top of Roof 271

    R = 1050 31.911

    25

    365

    2444

    R = 2325 5.686

    R = 12.085 6.789

    R =

    21006 2.000

    top of O.T.Shell IPE 300=229

    26.200 IPE 360=281 R = 11.850 top of O.T.Shell

    65 IPE 500=404 26.200

    52 1.533

    123 1.468 24.732

    6

    18.050

    R = 6.000

    R = 19.100 1050

    Outer Tank

    A

    A section A-A

    1/18 segment-suspended- deck

    acc.drawing no.:T-0661-23

    with 3 rafters IPE 300 or

    IPE 360 or IPE 500 incuded interm.

    stiffeners Roof Rafters

    RAFTER

    RAFTER

    RAFTER

    RAFTER

    centroid susp.

    centroid raffters

    centroid (3xraffters+1/18suspended deck)

    150

    Client: Linde Process Engineering and Contracting division

    Project No.: 2110 1055 ASALUYE

    Linde Doc.No.: BMM 50005

    Owner Doc. No.: 10-VD-A4-PV-014-084L

    Page 2 of 4

    Revision 04

  • 7/31/2019 Tanks Installation Manual

    36/53

  • 7/31/2019 Tanks Installation Manual

    37/53

  • 7/31/2019 Tanks Installation Manual

    38/53

    Process Engineering andContracting Division

    NARGANCOMPANY

    ASALUYE

    C2+ RECOVERY ANDFRACTIONATION PLANT

    PARS

    Petrochemical

    Company

    Linde Project No.: 2110 1055 NARGAN Project No.: N-178 Owner Project No.: 3910Linde Job Code: Asaluye NARGAN Job Code: Owner Job Code.: PPC-RFP

    Linde Doc. No.: Owner Doc. No.:

    Page 1 of 13

    Installation ManualTP-000-16

    attachment:Welding Sequence Bottom and Shell

    (Page 1 13)

    10-TK-0661and

    10-TK-0662

    P.O. No. 2DE466

    01 01.11.02 13 Tacke D. Hensel Stelck

    Status Issue Date Description Pages Prepared Checked Approved

  • 7/31/2019 Tanks Installation Manual

    39/53

  • 7/31/2019 Tanks Installation Manual

    40/53

  • 7/31/2019 Tanks Installation Manual

    41/53

  • 7/31/2019 Tanks Installation Manual

    42/53

    ASALUYE C2+ RECOVERY AND FRACTIONATION PLANT

    attachment:Welding Sequence Bottom and Shell

    a d a p t Doc. No. :Issue 1

    Process Engineering andContracting Division

    a d a p t Ref.:P 01-1021,

    Rev. 2 attachment to TP-000-16 Page 5 of 13

    PARSPetrochemical

    Company

    6.0 Inner BottomFor layout see drawing no. T-0661-/2-13.The bottom plates will be single-Vee-groove welded on back up bars.

    The sequence of welding is as follow (attachment 5):a) Start up with welding all back up bars before placing the inner bottom plates.b) Start welding the transverse joint in the centre and thereafter the next weld joint in

    the same row on both sides (A1 A2 A3).c) The next row will be welded in the same sequence till all transverse joints are

    completely welded, row by row from centre to outside (B1 B2 up to H1 H2H3 H4).

    d) The longitudinal weld joints shall be welded from the centre outwards on both sidesof the centre row (attachment 6). Leave the fourth longitudinal weld joint either sideof the centre to act as a closing seam. Do not tack these seams.

    e) At least weld closing seams of the bottom from centre to outside (attachment 8)

    f) The connection between the annular plates and the bottom plates shall not betacked, only wedged, will be welded after the bottom is completely welded.

    Start with welding the seam bottom to annular plate on at least four places. If it isnecessary and possible, back step welding shall be used (attachment 7).

    7.0 RemarksThe welding supervisor shall observe the welding and may change the sequence ofwelding, if necessary.

  • 7/31/2019 Tanks Installation Manual

    43/53

  • 7/31/2019 Tanks Installation Manual

    44/53

  • 7/31/2019 Tanks Installation Manual

    45/53

  • 7/31/2019 Tanks Installation Manual

    46/53

  • 7/31/2019 Tanks Installation Manual

    47/53

  • 7/31/2019 Tanks Installation Manual

    48/53

  • 7/31/2019 Tanks Installation Manual

    49/53

  • 7/31/2019 Tanks Installation Manual

    50/53

  • 7/31/2019 Tanks Installation Manual

    51/53

  • 7/31/2019 Tanks Installation Manual

    52/53

  • 7/31/2019 Tanks Installation Manual

    53/53

    ASALUYE C2+ RECOVERY AND FRACTIONATION PLANT

    attachment:Assembly Procedure of Erection Openings

    a d a p t Doc. No. :Issue 1

    Process Engineering andContracting Division

    a d a p t Ref.:P 01-1021,

    Rev. 2 attachment to TP-000-16 Page 3 of 3

    PARSPetrochemical

    Company

    7.1.10 Carry out the back welding of the lower horizontal weld joint after grinding.

    7.2 Round Erection Opening

    7.2.1 The weld joint preparation of the erection opening shall be the same as for the verticalweld joint of course 1.

    7.2.2 Fit up the plate with equal gap all around and tack the plate.

    7.2.3 Start with welding from the top to the bottom (3G down) at both sides.

    7.2.4. Thereafter weld 3 or 4 passes vertical up (both sides), position 3G up.

    7.2.5 Back welding shall be carried out after grinding from inside.

    7.2.6 Finish welding from outside.

    7.3 All welding shall be carried out by string beads.

    7.4 The inter-pass temperature shall not exceed 150C (302 F).

    8.0 Non-Destructive-Testing

    8.1 The root pass shall be examined by LP-Test or MP-Test after grinding of the back sideand before back welding.

    8.2 After finish welding, the following examinations shall be carried out:

    8.2.1 After Hydrostatic Test, but before Pneumatic Test: - 100 % Visual Examination- 100 % Radiographic Examination

    8.2.2 After Hydrostatic and Pneumatic Test: - 100 % Visual Examination- 100 % Vacuum Examination- 100 % Magnetic Particle Examination

    - 100 % Radiographic Examination

    8.3 All NDE-Tests shall be reported and signed.