Upload
nurul-islam-faruk
View
224
Download
2
Embed Size (px)
Citation preview
1
1
Diagnostic Techniques for Diagnostic Techniques for Condition Monitoring Condition Monitoring
of Transformersof Transformers
Young Zaidey bin Yang GhazaliYoung Zaidey bin Yang GhazaliTechnical ExpertTechnical Expert
(Transformer Performance & Diagnostic)(Transformer Performance & Diagnostic)Engineering DepartmentEngineering Department
TNB Distribution DivisionTNB Distribution DivisionARSEPE 2008ARSEPE 2008
2
1. INTRODUCTION
� Electrical distribution equipment is generally designed for a certain economic service life.
� Equipment life is dependent on operating environment, maintenance program and the quality of the original manufacture and installation.
� Beyond this service life period they are not expected to render their services up to expectation with desired efficiency.
2
3
1. INTRODUCTION
� Generally due to poor quality of raw material, workmanship and manufacturing techniques or due to frequent electrical, mechanical and thermal stresses during the operation, many equipment fail much earlier than their expected economic life span.
� The concept of simple replacement of failed power equipments in the system either before or after their economic service life, is no more valid in the present scenario of financial constraints.
4
1. INTRODUCTION
� Explore new approaches/techniques of monitoring, diagnosis, life assessment and condition evaluation, and possibility of extending the life of existing assets (i.e. circuit breaker, cables, transformers, etc.)
� Minimization of the service life cycle cost is one of the stated tasks of the electrical power system engineers. For electrical utilities this implies for example to fulfill requirements from customers and authorities on reliability in power supply at a minimal total cost.
� The main goal is therefore to reach a cost effective solution using available resources which is captured by the concept of Asset Management.
3
6
ASSET MANAGEMENT
Operate Operate Operate Operate
efficientlyefficientlyefficientlyefficiently
High PerformanceHigh PerformanceHigh PerformanceHigh Performance
Reasonable Reasonable Reasonable Reasonable
returnsreturnsreturnsreturns
Low CostLow CostLow CostLow Cost
• SAIFI, SAIDI
• Power quality
• Power availability
• Reduced Loss etc.
• Investment
• O&M
• Stocking etc.
Balancing cost, risk,
and performance in
the context of asset
full life cycle
Asset Management Mechanism
7
T&D ASSET MANAGEMENT
4
8
Maintenance Management� With the increasing age of the population of power
system equipment utilities are making efforts to
assess the internal condition of the equipment while
in service before catastrophic failures can take place
� Different types of maintenance being done on
equipment are:
� Breakdown maintenance
� Time or Calendar Based maintenance
� Condition based maintenance
� Reliability centered maintenance
9
� Today the paradigm has changed from traditional
calendar based to condition based maintenance and
efforts are being channeled to explore techniques to
monitor, diagnose and assess condition of power
system equipment
� This has led to the development of various on- and
off-line non-intrusive tests in recent years that allow
diagnosing the integrity of power system equipment
to optimize the maintenance effort thereby ensuring
maximum availability and reliability
Maintenance Management
5
10
Why ‘Condition Based’?
� Ageing asset population
� Age by itself is not a good predictor of
future performance
� Must be able to fully justify decisions in
terms of proven engineering principles
� Cannot make sound asset management
decisions unless you understand asset
condition!
11
What is CBM?
� Combining all available practical and theoretical
knowledge and experience of assets to:
�Define current condition and use this to estimate future
condition and performance
�Provide a sound engineering basis for evaluating risks and
benefits of potential investment strategies
� Uses a well developed methodology (with practical
experience of successful application)
Provides a framework for continual improvement
(information and definition of condition)
6
12
Why condition based?� Ageing asset population
� Pressures to maintain/improve performance and to
reduce costs
� Age (by itself) is not an acceptable reason to replace
assets
� Must demonstrate need and consequences, condition
and future performance
� Cannot make good Asset Management decisions
unless you understand asset condition!
13
Condition Based Management
� Define asset condition (Health Index)
� Link condition to performance & probability of failure
(PoF)
� Calibrate Health Index/PoF against historic fault rates
� Estimate future condition and performance
� Evaluate effect of investment programmes on future
condition and performance
� Provides an ENGINEERING basis to evaluate risk and
determine investment requirements
7
14
Defining condition and future performance� Need understanding of:
Degradation and failure processes
Condition assessment techniques
Practical knowledge of assets,
Operating context
� Everything is related back to physical condition and
degradation processes - maximising the value of
available experience of the assets
15
A health index is:� A consistent and logical means of combining
relatively complex information
� A way to rank assets (on basis of proximity to
EOL or probability of failure)
� Relatively simplistic
� It is NOT a substitute for engineering expertise
and judgement it is an additional aid to
engineers
8
16
Health Index Mechanism
A Health Index is a means to define proximity to EOL
by combining varied and relatively complex condition
information as a single number
� Define significant condition criteria
� Code information numerically,
� Apply weightings
� Develop a simple algorithm to generate a HI for
each asset
� Rank and apply calibration
17
Health Index - Ranking
Condition Remnant Life (years) Probability of
failure
5 - 10Poor
Fair
Good
At EOL (<5 years)Bad
10 - 20
>20
High
Medium
Low
Very Low
10
0
9
18
0 3 5 10
MMeeaass uurraabbll ee ddee tt eerrii oorraatt iioonn bbuutt nnoo
ss iiggnnii ffii ccaanntt ii nnccrreeaass ee iinn PP(( ff))
SSii ggnnii ffii ccaanntt ddeett eerrii oorraatt iioonn ssmmaall ll
ii nnccrreeaass ee iinn PP(( ff))
SSeerrii oouuss ddeett eerrii oorraatt iioonn ssii ggnnii ffii ccaanntt
ii nnccrr ee aass ee iinn PP(( ff))
Probability of failure (Pf)
Health Index
19
Information to derive a condition based Health Index
� Actual condition information
� Risk factors with direct condition implications -
failure rates, specific or generic problems,
design issues etc
Other non condition based risk factors can be
mapped on later to evaluate overall risk
(Criticality, load, obsolescence etc)
10
20
Condition based health index
� Means of determining probability of failure
� It does not consider consequences of failure
� Ultimately require combination of both to
evaluate overall risk
� CBHI is the 1st step (phase 1)
� Phase 2 use of results in a risk model
21
Phase 1 - Condition and Probability of Failure (for each asset group)
Define
Assets
Define
EOL
Issues
Review
Condition
Assessment
Techniques
Data and
Information
Analysis
Formulation
and Population
of HI
HI to
Probability
of Failure
Change of
HI (PF) with
time
Documentation
Conclusions
Report
CONSEQUENCES
Phase 2
Define
Assets
Define
EOL
Issues
Review
Condition
Assessment
Techniques
Data and
Information
Analysis
Formulation
and Population
of HI
HI to
Probability
of Failure
Change of
HI (PF) with
time
Documentation
Conclusions
Report
CONSEQUENCES
Phase 2
1
1
Diagnostic Techniques for Diagnostic Techniques for Condition Monitoring Condition Monitoring
of Transformersof Transformers
Young Zaidey bin Yang GhazaliYoung Zaidey bin Yang GhazaliTechnical ExpertTechnical Expert
(Transformer Performance & Diagnostic)(Transformer Performance & Diagnostic)Engineering DepartmentEngineering Department
TNB Distribution DivisionTNB Distribution DivisionARSEPE 2008ARSEPE 2008
2
Transformer Design& Construction
2
3
Transformer Design & Construction
Types of Transformers
� Core Type
� Shell Type
Oil-Immersed Type,
Dry Type
4
Transformer Design & Construction
Core Type Transformers
3
5
Transformer Design & Construction
Shell Type Transformers
6
Transformer Design & Construction
Typical Winding Connections
� Delta – Star
� Star - Delta
� Star – Star
� Delta – Delta
4
7
Transformer Design & Construction
Other Winding Connections
� Zig – Zag Connections
� Tertiary Windings
� Double Secondary
� Scott (T-T) Connections
� Autotransformers
Earthing Transformers
8
DESIGN CONCEPT
The transformer has been designed,
manufactured and tested according to
IEC 60076 part 1 to 5. Power Transformer
It consist of : core, winding, insulation, core
and winding assembly, tank.
5
9
CORE
� Grain Oriented Electrical Steel
� Type M5 (0.3mm), M4 (0.27mm) and ZDKH
(0.23mm)
10
WINDING
� Are designed to meet three fundamental requirement :
1. Electrical
2. Mechanical
3. Thermal
6
11
• Round, Oval or rectangular in shape
and are wound concentrically.
• LV winding is wound with foil
conductor (Distribution)
• HV winding is wound with rectangular
strip conductor.
• HV winding is wound on LV winding.
WINDING
12
INSULATION
� The interlayer insulation are of high quality epoxy
coated kraft paper (DDP)
� Corrugated pressboards are placed within the
coil for cooling within the coil.
� Thickness of layer insulation
in accordance with voltage
and number of layers.
7
13
CORE & WINDING ASSEMBLY
� Arrangement of windings with respect to the core :
CORE - LV WINDING - HV WINDING
� For tapping lead connection normally use stranded copper or
round conductor.
� Bushing Lead :-
1. HV - stranded copper
2. LV - copper bar or flexible copper base on LV rated
current.
14
TANK
� It is hermetically sealed type and full fill with insulation liquid.
� Oil expansion or contraction due to the change in the
transformer load is accommodated by the corrugated finwall
of the transformer tank.
� Corrugated fins are use to
provide sufficient cooling
surface to dissipate the heat
generated by the windings.
8
15
TERMINATION
� Both HV & LV is open bushing termination.
� Cable Box
16
MANUFACTURING PROCESS FLOW CHART
Core Cutting
Core
Building
Tanking
Process
Despatch Finishing Testing
Paper Covering
High Voltage
Winding
Drying
Process
1. Rectangular copper
2. Foil Sheet
Fabrication
Vacuum & Oil
Filling
Low Voltage
Winding
Core Winding
Assembly
9
17
Transformer Design & Construction
Phasor Relationships
� Transformer winding connections
produced a Phase Shift between primary
& secondary
� Angle of phase shift depend upon the
winding connection method adopted for
primary and secondary
18
Transformer Design & Construction
Phasor Relationships
Eg.
� Phase Shift of secondary
windings is +30 wrt primary
designated with Dyn11
� Significant of Phase Shift –
Paralleling of Transformer &
interconnection of system
10
19
Transformer Design & Construction
Tapping & Tap Changers
20
Transformer Design & Construction
Tapping & Tap Changers – Functions
� To compensate for changes in the applied voltage on bulk supply
� To compensate for regulation within the transformer & maintain the output voltage constant
� To assist in the control of system VArs flows
� To allow for compensation for factors not accurately known at the time of planning
� To allow for future changes in system conditions
11
21
Transformer Design & Construction
Type of Tap Changers
� On-Load Tap Changer (OLTC)
� Off Circuit Tap Changer (OCTC)
Tap Changer Mounting
� Internal (In-tank)
� External (Side mounted)
22
Transformer Design & Construction
OLTC Technology
� Oil Type OLTC
� Vacuum Type OLTC (Vacutap)
12
23
Transformer Design & Construction
OLTC Main Components
� Tap Selector
� Diverter Switch
� Selector Switch
� Change-over selector
� Transition Impedance
24
Transformer Design & Construction
Motor Drive Mechanism to operate OLTC
� Step-by-step control
� Tap Position Indicator
� Limiting Devices
� Parallel Control Devices
� Emergency Tripping Device
� Overcurrent Blocking Device
� Restarting Device
13
25
Transformer Ancillary Equipment
Pressure Relief Device
26
Transformer Ancillary Equipment
Gas & Oil Actuated Relays (Buchholz)
14
27
Transformer Ancillary Equipment
Temperature Indicators
� Winding HV & LV
� Top Oil
Fans Control
28
Transformer Ancillary Equipment
Oil Level Indicators
15
29
Transformer Ancillary Equipment
Other Ancillary Equipment
� Conservator Tank
� Cooling System/Radiators
� Bushings
� Cable Box
� Oil Valves
� Thermometer Pockets
1
1
Diagnostic Techniques for Diagnostic Techniques for Condition Monitoring Condition Monitoring
of Transformersof Transformers
Young Zaidey bin Yang GhazaliYoung Zaidey bin Yang GhazaliTechnical ExpertTechnical Expert
(Transformer Performance & Diagnostic)(Transformer Performance & Diagnostic)Engineering DepartmentEngineering Department
TNB Distribution DivisionTNB Distribution DivisionARSEPE 2008ARSEPE 2008
2
Transformer Insulating Oil
& Paper Diagnostics
2
3
Oil & Paper Tests in Main Tank & OLTC
1. Oil Quality Test
� Physical Properties
� Visual Appearance
� Colour
� Flash Point
� Viscosity
� Density
� Pour Point
� IFT
� Particle Count
4
Oil & Paper Tests in Main Tank & OLTC
1. Oil Quality Test
� Chemical Properties
� Moisture Content
� Acidity
� Corrosive Sulphur
� Oxidation Stability
� Sludge Sediment
3
5
Oil & Paper Tests in Main Tank & OLTC
1. Oil Quality Test
� Electrical Properties
� Breakdown Voltage
� Dissipation Power Factor
2. DGA
6
Insulation Condition Assessment
Life Span of Power Transformers Depends on Integrity of Insulation
Most Commonly Used Insulations for Power Transformers
OIL
• Provides overall insulation to the transformers
• Acts as coolant in extinguishing arcs
• Provides the means to monitor insulation condition and operation of
transformers
PAPER
Provides insulation to the conductor in the transformer windings
4
7
Insulation Condition Assessment
PRIMARY STRESSES
1. Stresses applied on the transformer due to normal
operation:
• Thermal
• Electrical
• Mechanical
2. Application of these stresses can be:
• Continuous
• Cyclic
• Intermittent
8
SECONDARY STRESSES
1. Factors that can influence the ageing rate when primary
stresses are applied
2. Simply known as Ageing Factors
Examples of these Ageing Factors can be:
3. Operational factors of the transformers
• Environmental factors i.e. radiation, moisture or
water, oxidative agents and corrosive materials
• Technological factors i.e. type of oil and paper used
• Tests done on the transformers that can influence
the performance of the insulation system
Insulation Condition Assessment
5
9
Oil Insulation Deterioration – Reversible
1. Oil insulation condition can be reversed through on-line filtration
2. Can reduce the effect of the Ageing Factors
3. Can prolong serviceability of the oil insulation
Insulation Condition Assessment
10
Paper Insulation Degradation – Irreversible
• Paper insulation degradation is irreversible
• Oil filtration has negligible effect on reversibility of paper
degradation
• Ageing of paper directly linked to its mechanical
strength
• Loss of mechanical strength eventually leads to loss of
dielectric strength
• Once paper loses its dielectric strength, the transformer
is deemed to have reached the end of its service life
• Thus, the life of a transformer can be effectively
determined by the life of its paper insulation
Insulation Condition Assessment
6
11
Three most common degradation factors of cellulose:
Thermal
1. When exposed to heat up to 220ºC, the glycosidic bond tend to
break and open the glucose molecule rings
2. By-products:
• Free glucose
• H20
• CO
• CO2
• Organic acids
Glycosidic
bonds broken
and glucose
rings opened
Generates the
following:
H20 CO CO2
H
O
OH
Heat
Insulation Condition Assessment
12
Three most common degradation factors of cellulose:
Oxidative
1. Presence of oxygen promotes oxidation
2. Glycosidic bond weakens
3. Causes scission to the cellulose chain
4. By-products include H20
Hydrolytic
1. Presence of water and acids
2. Glycosidic bond exposed to slicing
3. Causes scission to the cellulose chain
4. By-products include free glucose
Glycosidic
bonds
weakened
and
moisture
produced
CH2OH
COOH COOH
CHO
O2
Free glucose
produced
HO OH
CH2OH
H20 or acids
Insulation Condition Assessment
7
13
Degradation By-Products
1. It can be observed that by-products related to paper degradation
can include the followings:
• CO
• CO2
• H2O
• Organic acids
• Free glucose molecules
2. With H2O and organic acids present in the oil, the free glucose
molecules can degrade to 5-hydroxymethyl-2-furfuryl or 5H2F
Insulation Condition Assessment
14
Degradation By-Products
3. 5H2F is an unstable free glucose molecule and can decompose
further to other furaldehyde as follows:
• 2-furfuryl alcohol (2FOL)
• 2-furaldehyde (2FAL)
• 2-acetyl furan (2ACF)
• 5-methyl-2-furfuryl (5M2F)
4. All these 5 compounds of glucose or degradation of glucose are
known as Furans.
5. 2FAL is the most stable in the group
6. Furan generation is exclusively due to paper degradation unlike
CO, CO2, H2O or acids which can also be produced through oil
oxidation or breakdown.
Insulation Condition Assessment
8
15
Insulation Condition Assessment
� When taking an oil sample from a sealed tank transformer, ensure that the transformer is not under vacuum by checking the vacuum/pressure gauge
� Use a clean glass syringe/beaker (provided by the laboratory) and follow the proper sampling procedure –ASTM D923 & D3613 (IEC 60475 & IEC 60567)
� Interpret the quantified results to help determine the relative health of the transformer, offer clues to the origin of potential problems and develop a strategy to avoid catastrophic failure – IEEE C57.106
16
Insulation Condition Assessment
Important factors to be considered prior to taking a sample:
1. Sample Containers
2. Sampling Technique
3. Weather condition
4. Sample storage and transport
9
17
Insulation Condition Assessment
� Characteristic of Sample Containers:
� 500 ml or 1 liter (Duplicate)
� Syringe – DGA
� Seal the sample from external contamination
� Store samples in the dark to prevent from photo-degradation
� Cleaning and preparation of valves
� Avoid liquid spillage, some oil may still contains PCBs� Identification of the sample and apparatus information
� Sampling outdoors in rain, strong wind and night time
should be avoided
� Should not be stored longer than a few days before
sending to the laboratory for analysis
18
Insulation Condition Assessment
Dark Brown
Bottle
500 mL
Valve
Adaptor
Plastic
tube Cap
Transformer
Seal
Waste
Vessel
Filled
Sample
bottle
Use correct vessel (good cap and seal)
Sufficient sample
10
19
Insulation Condition Assessment
Valve
Adaptor
Plastic
tubeSyringeTransformer
Waste
Vessel
Sufficient sample
20
Insulation Condition Assessment
� To effectively interpret DGA results requires insights in
the characteristics of dissolved gas in oil evolution, an
understanding of transformer design, and knowledge of
materials used by transformer manufacturer and
operating conditions – ASTM D3612
� ASTM D3612 Test methods for analysis of dissolved
gases by gas chromatography
� IEEE C57.104 Guide for interpretation of gases
11
21
On-Line Assessment of Insulation Condition
1. Oil Quality Tests – to assess the physical, electrical and
chemical properties of the oil
2. Dissolved Gas-in-oil Analysis – to detect and identify
incipient faults
3. Furan Compound Analysis – to detect and identify
degradation of paper insulation (on-line test)
4. Degree of Polymerization Test – to measure
degradation of paper insulation (intrusive mechanism)
Insulation Condition Assessment
22
Oil Screening Tests
1. Colour – serious contamination
2. IFT – moisture in oil (> 15 mN/ m)
3. Neutralization Number – level of acidity (< 0.2 mg KOH / gm)
4. Dielectric Strength – contaminants (water & conducting
particles) ( > 30 kV)
5. 5. Water Content – amount of dissolved water in ppm
(< 30 ppm)
Insulation Condition Assessment
12
23
Insulation Condition Assessment
IEEE C57.106 Limits – Oil Quality Tests
� Colour – 0.5
� IFT – > 25 mN/ m for ≤ 69 kV
� Neutralization Number – < 0.2 mg KOH / gm
� Dielectric Strength – > 20 kV for ≤ 69 kV for 1 mm gap
� Water Content – < 27 ppm for ≤ 69 kV at 50 0C
24
Other Oil Quality Tests
• Specific Gravity
• Viscosity
• Power Factor
• Resistivity
• Flash Point
• Visual
• PCB Content
• Inhibitor Content
Insulation Condition Assessment
13
25
Oil Quality Screening Tests
� Water Content (D 1533 / IEC 733) A low water content is necessary to obtain and maintain acceptable electrical strength and low dielectric losses in insulation systems.
� Color (D 1500) The color of a new oil is generally accepted as an index of the degree of refinement. For oils in service, an increasing or high color number is an indication of contamination, deterioration, or both.
� Dielectric Breakdown (D 877 / D 1816 / IEC 156) It is a measure of the ability of an oil to withstand electrical stress at power frequencies without failure. A low value for the dielectric-breakdown voltage generally serves to indicate the presence of contaminants such as water, dirt, or other conducting particles in the oil.
26
Oil Quality Screening Tests
� Neutralization Number, NN (D 664) A used oil having a high neutralization number indicates that the oil is either oxidized or contaminated with materials such as varnish, paint, or other foreign matter.
� Interfacial Tension, IFT (D 971) The interfacial tension of an oil is the force in dynes per centimeter or millinewton per meter required to rupture the oil film existing at an oil-water interface. When certain contaminants such as soaps, paints, varnishes, and oxidation products are present in the oil, the film strength of the oil is weakened, thus requiring less force to rupture. For oils in service, a decreasing value indicates the accumulation of contaminants, oxidation products, or both.
14
27
Oil Quality Screening Tests
� Index = IFT/NN. This index provides a more sensitive and reliable guide in determining the remaining useful life of a transformer oil. A Index below 100 indicates that the oil is significantly oxidized and that the oil needs to be replaced in the near future.
28
Insulation Condition Assessment
� Non-fault gases - Oxygen (O2) & Nitrogen (N2)
Note: If the ratio O2/N2 is less than 0.3 then it indicates overheating
of oil. This is not a standard, use with caution.
� Fault gases - Hydrogen (H2), Acetylene (C2H2)
Carbon Monoxide (CO), Carbon Dioxide
(CO2) Ethylene (C2H4), Ethane (C2H6)
Methane (CH4)
15
29
Insulation Condition Assessment
30
Insulation Condition Assessment
16
31
Dissolved Gas-in-oil Analysis
Fault Condition Key Gases
Overheated Oil Methane, Ethane & Ethylene
Partial Discharge Hydrogen & Acetylene
Overheated Cellulose Carbon Monoxide & Carbon
Dioxide
Non-Fault Gases are Oxygen & Nitrogen
Insulation Condition Assessment
32
Insulation Condition Assessment
Dissolved Gas-in-oil Analysis
Fault Condition Key Gases
� Thermal Oil Major – Ethylene & Methane
Minor – Ethane & Hydrogen
� Electrical – low energy Major – Hydrogen & Methane
Minor – Ethane & Ethylene
� Electrical – high energy Major – Acetylene & Hydrogen
Minor – Ethylene & Methane
� Thermal Cellulose Major – Carbon monoxide & Carbon dioxide
Minor – Methane & Ethylene
17
33
Insulation Condition Assessment
IEEE Limit
� Hydrogen (H2) 100 ppm
� Oxygen (O2) N/A
� Nitrogen (N2) N/A
� Carbon Monoxide (CO) 350
� Methane (CH4) 120
� Carbon Dioxide (CO2) 2500
� Ethylene (C2H4) 50
� Ethane (C2H6) 65
� Acetylene (C2H2) 35
34
Dissolved Gas-in-oil Analysis
Ratio Method is used for fault analyzing, not for fault detection.
Ratio Method Ratios
Roger’s C2H2/C2H4 , CH4/H2 & C2H4/ C2H6
IEEE CH4/H2, C2H2/C2H4, C2H2/ CH4, C2H6/ C2H2, C2H4/ C2H6
Never make a decision based on only ratio. Take into consideration
the gas generation rates and amount of total combustible gases.
Insulation Condition Assessment
18
35
Insulation Condition Assessment
� Roger’s Ratio comparison methods look at pairs of gases, and develop a coding system to help define potential fault conditions
� Roger’s Ratio Code
C2H2 / C2H4 CH4 / H2 C2 H4 / C2H6
< 0.1 0 1 0
0.1 -<1.0 1 0 0
1.0 - <=3.0 1 2 1
> 3.0 2 2 2
36
Insulation Condition Assessment
IEC DGA Ratios
C2H2 CH4 C2H4
Case C2H4 H2 C2H6
0 0 0 0 No Fault, Normal
1 0 1 0 Partial discharges of low energy
2 1 1 0 Partial discharges of high energy density
3 1 0 1 Discharges of low energy, Arcing
3 2 0 1 Discharges of low energy, Arcing
3 2 0 2 Discharges of low energy, Arcing
4 1 0 2 Discharges of high energy, Arcing
5 0 0 1 Thermal Fault, 150 C, Conductor Overheating
6 0 2 0 Thermal Fault, 150 - 300 C, Oil Overheating, Mild
7 0 2 1 Thermal Fault, 300 - 700 C, Oil Overheating, Moderate
8 0 2 2 Thermal Fault, 700 C, Oil Overheating, Severe
19
37
Insulation Condition Assessment
TDCG (ppm) Status Remark
≤ 720 Condition 1 Transformer working satisfactorily. Look
for individual gas exceeding respective limit.
721-1920 Condition 2 Faults may be present. Additional
investigation required based on individual
gas exceeding respective limit.
1921-4630 Condition 3 Faults probably present. Additional
investigation required based on individual
gas exceeding respective limit.
> 4630 Condition 4 Continued operation could result in failure of
the transformer
As per IEEE C57.104
38
Insulation Condition Assessment
� CO2/ CO ratio indicates cellulose degradation
CO2 / CO ratio Condition of Cellulose
< 3 Severe Arcing & Short circuit damage
3 -<5 Indicates concern
5 - <=11 Normal
> 11 Indicates damage due to general
overheating
According to IEEE C57.104 the normal value is 7
20
39
Exercise (Oil Condition)
Transformer Gas Analysis
Component ppm in oil
HYDROGEN (H2) 10
OXYGEN (O2) 26200
NITROGEN (N2) 48500
CARBON MONOXIDE (CO) 41
METHANE (CH4) 5
CARBON DIOXIDE (CO2) 570
ETHYLENE (C2H4) 2
ETHANE (C2H6) 2
ACETYLENE (C2H2) 1
40
Transformer Gas Analysis
Component ppm in oil
HYDROGEN (H2) 720
OXYGEN & ARGON (O2 + A) 17000
NITROGEN (N2) 45400
CARBON MONOXIDE (CO) 405
METHANE (CH4) 1310
CARBON DIOXIDE (CO2) 6050
ETHYLENE (C2H4) 5200
ETHANE (C2H6) 1810
ACETYLENE (C2H2) 256
Exercise (Oil Condition)
21
41
Transformer Gas Analysis
Component ppm in oil
HYDROGEN (H2) 105
OXYGEN & ARGON (O2) 18000
NITROGEN (N2) 33400
CARBON MONOXIDE (CO) 870
METHANE (CH4) 400
CARBON DIOXIDE (CO2) 12,100
ETHYLENE (C2H4) 260
ETHANE (C2H6) 28
ACETYLENE (C2H2) 52
ppb in oil
2FAL 195
Exercise (Paper Condition)
42
Transformer Gas Analysis
Component ppm in oil
HYDROGEN (H2) 103
OXYGEN & ARGON (O2 + A) 16762
NITROGEN (N2) 20458
CARBON MONOXIDE (CO) 0
METHANE (CH4) 814
CARBON DIOXIDE (CO2) 1816
ETHYLENE (C2H4) 109
ETHANE (C2H6) 75
ACETYLENE (C2H2) 118
ppb in oil
2FAL 225
Exercise (Oil + Paper Condition)
22
43
Furanic Compound Analysis
Fault Condition Furan Compound
Overheating or Short circuit 2FAL
Excessive Moisture 2FOL
Lightning Strikes 2ACF
Intense Overheating 5M2F
Oxidation 5H2F
Concentration limits of furan compounds must be supported by
CO2/CO Ratio to assess paper degradation
Insulation Condition Assessment
44
Insulation Condition Assessment
2FAL limits (ppb in oil):
58 – 292 – Normal Aging
654 – 2021 – Accelerated Aging
2374 – 3277 – Excessive Aging
3851 – 4524 – High Risk of Failure
23
45
Criteria to select transformers for further investigation
• Transformer Age
• Operational Criterion – number of faults, switching, lightning, etc.
• DGA Criterion (oil) – Individual concentrations of CH4, C2H2,
C2H4, C2H6 & H2 in ppm & Roger’s/IEEE Ratio
• DGA Criterion (paper) – Individual concentrations of CO2 & CO in
ppm & CO2/CO Ratio
• Furan Criterion – 2FAL concentration in ppb & others if detected
Insulation Condition Assessment
46
Correlation between TS, DP and Furan
• Ageing of paper insulation is related to the decrease in
TS.
• TS is directly related to DP – ASTM D 4243.
• Decrease in DP is directly related to the increase in
Furan.
• Thus, as paper aged, it loses its TS. Loss of TS
indicates decrease of DP. Decrease of DP causes
increase in Furan in the insulating oil. It can be deduced
that as paper aged towards its end of service life, the
level of Furan content increases.
Insulation Condition Assessment
24
47
Degree of Polymerization
• One of the most dependable means of determining
paper deterioration and remaining life of the cellulose.
• The cellulose molecules is made up of a long chain of
glucose rings which form the mechanical strength of the
molecule and the paper.
• DP is the average number of these rings in the
molecule.
• As paper ages or deteriorates from heat, acids, oxygen
and water the number of these rings decrease.
Insulation Condition Assessment
48
Degree of Polymerization
Following Table has been developed by EPRI to estimate
remaining paper life
1. New insulation 1000 DP to 1400 DP
2. 60% to 66% life remaining 500 DP
3. 30% life remaining 300 DP
4. 0 life remaining 200 DP
Insulation Condition Assessment
25
49
• The life of a transformer can be effectively determined by the life of its
paper insulation.
• DP is considered direct approach to determine the paper insulation
condition but it is intrusive. Some are skeptical since integrity of paper
insulation may be disturbed and may further damage the paper insulation.
• Alternatively, it can be achieved through the use of paper degradation by-
products e.g. CO, CO2, CO2/CO, 2 FAL, H2 as indicators. It is non-intrusive
and requires only samples of the transformer oil which can be obtained
without any shutdown.
• The challenge is to develop a Mathematical Model to Estimate DP Value of
Paper Insulation based on the Paper Degradation By-Products i.e.
DP = f (CO, CO2, CO2/CO, 2 FAL, H2)
Insulation Condition Assessment
50
LTC – OIL ANALYSIS� By plotting the relative percentages of methane, ethylene and acetylene onto a special triangular coordinate system, a graphical output of the likely cause of gassing is generated.
� The causes are categorized as follows.
• D1 – Discharges of low energy
• D2 – Discharges of high energy
• T1 – Thermal faults < 300°C
• T2 – Thermal faults 300°C to 700°C
• T3 - Thermal faults > 700°C
• DT – Mixture of thermal and electrical faults
• PD – Partial discharge (No samples indicated this type of fault)
26
51
Case Study
� The following gas levels were detected via DGA on the
oil from the load tap changer:
– 42 ppm of methane
– 17 ppm of Ethylene
– 0 ppm of acetylene
� Calculate percentages of each gas and use Duval’s
triangle approach to find the cause
52
LTC – OIL ANALYSIS
27
53
LTC – OIL ANALYSIS
Guideline set by an US Utility
� When the acetylene or hydrogen reaches a threshold level of
500ppm the unit is put to monthly DGA testing schedule
� DGA monthly testing schedule
Hydrogen > 1500 ppm
Acetylene > 1000 ppm
Ethylene > 1000 ppm
� When Ethylene level exceeds the maximum value the unit is
removed from service
54
Exercise
� The following gas levels were detected via DGA on the
oil from the load tap changer:
– 319 ppm of methane
– 181 ppm of Ethylene
– 1351 ppm of acetylene
� Calculate percentages of each gas and use Duval’s
triangle approach to find the cause
1
1
Diagnostic Techniques for Diagnostic Techniques for Condition Monitoring Condition Monitoring
of Transformersof Transformers
Young Zaidey bin Yang GhazaliYoung Zaidey bin Yang GhazaliTechnical ExpertTechnical Expert
(Transformer Performance & Diagnostic)(Transformer Performance & Diagnostic)Engineering DepartmentEngineering Department
TNB Distribution DivisionTNB Distribution DivisionARSEPE 2008ARSEPE 2008
2
Transformer Basic On-Site & Off Line Diagnostic Testing
2
3
Electrical Tests
1. Basic Electrical Tests
� Insulation Resistance• Traditional Polarization Index (PI) test
to detect moisture content
� Tan Delta• To detect water in cellulose
and chemical contamination
� Winding Resistance• To detect open or short circuits or poor electrical connection in
the windings
� Turns Ratio
• To detect Shorted Turns
Insulation Condition
Assessment
4
Electrical Tests
2. Advanced DiagnosticTests
� Frequency Response Analysis (FRA)
� Recovery Voltage Measurement (RVM)
� Polarization Depolarization (PDC)
� Frequency Dielectric Spectroscopy (FDS)
� Partial Discharge (PD)
� OLTC Motor Current Signature Analysis (MCSA)
� OLTC Vibration Signature Analysis (VSA)
3
5
Categorization of On-site Tests
� Destructive off-line tests are “go/no go” tests
� Non destructive off-line tests are diagnostic
tests
� Non destructive on-line tests are condition
monitoring tests
On-site Testing
6
� These on-site tests are performed individually or in
combination :
� Before energizing a new equipment as a
commissioning test
� After maintenance
� After network alteration
On-site Testing
4
7
Damaging Factors of Insulation
8
Fig 4-4
5
9
105
130
155
180
220
Class A Class B Class F Class H Class C100
125
150
175
200
225
250
Degrees C
entigrade
Insulation Classes by Degrees Centigrade
Class SClass R
240 240+
Class N
200
Thermal Withstandibility of Insulation Medium According to Classes
10
Insulation Condition Assessment
� Insulation resistance test (a)
� Insulation current test (b)
� Power factor (c)
� DC voltage withstand (d)
� AC voltage with-stand (e)
6
11
Insulation Condition Assessment
� Method (e) is primarily used in factory tests
� Method (d) is primarily used as commissioning test
� Practically all routine field tests are made using
nondestructive methods (a), (b) and (c)
� Methods (a) and (c) must also be used as
commissioning test
� No single test method can be relied upon for
indicating all conditions of weakened insulation
12
Basic Electrical TestsInsulation Resistance
Reading corrected to 20oC
� Insulation resistance varies inversely with temperature for
most insulting materials
� To properly compare periodic measurements of insulation
resistance, it is necessary either to take each measurement
at the same temperature, or to convert each measurement to
the same base temperature i.e. 200C
� Polarisation Index is the ratio of the IR reading after 10
minutes to the IR reading after 1minute
� PI is used as an index of dryness
� Discharge the winding after a Polarisation Index Test for
sufficient time before handling or performing other tests
7
13
Basic Electrical TestsPolarization Index
Interpretation of Polarization Index (PI) Measurements
PI Value Interpretation
> 4.0 Healthy
4.0 – 2.0 OK
2.0 – 1.5 Marginal Pass
1.5 – 1.0 Deteriorated condition
< 1.0 Failure
14
Basic Electrical Tests
8
15
Insulation Resistance Test
16
Insulation Resistance Test
Volume Current
Insulation Resistance
Tester
Surface leakage
current
9
17
Insulation Resistance Test
Capacitive
Current
Dielectric
Absorption
Current
Conduction
Current
Total
current
Time
µA
18
Insulation Resistance Test
10
19
Guard Connections
20
3 Terminal Insulation Resistance Tester
11
21
Spot Any Difference? Why?
22
Inaccuracies can occur during IR measurement due to the following
� Effect of Previous Charge
� Effect of Temperature
� Effect of Moisture
� Effect of Age and Curing
12
23
Test procedures
� Hot resistance test - at least 4 hours after shutdown from full-load operation, or until temperature is stabilized:
� Disconnect the equipment to be tested from other equipment
� Ground the winding to be tested for at least 10 minutes
� Remove the ground connection and connect the insulation resistance tester
� Take readings at 1 -minute and at 10 minutes
� Record the temperature of equipment being tested
� Ground the winding again for at least 10 minutes
� Cold resistance test - Four to eight hours after the hot resistance test or when equipment has cooled to approximately ambient temperature
� Use same procedure as outlined for the hot resistance test
24
Spot Reading
13
25
Temperature Correction
� Dry type insulation 40ºC ambient
� Liquid type insulation 20ºC ambient
� Insulating materials have negative resistance
characteristics
� Spot test reading must be corrected to a base
temperature
26
Conversion Factors For Converting
Insulation Resistance Test Temperature to 20°°°°C
Temperature Multiplier
°°°°C °°°°F
Apparatus
Containing Immersed
Oil Insulations
Apparatus
Containing Solid
Insulations
0 32 0.25 0.40
5 41 0.36 0.45
10 50 0.50 0.50
15 59 0.75 0.75
20 68 1.00 1.00
25 77 1.40 1.30
30 86 1.98 1.60
35 95 2.80 2.05
40 104 3.95 2.50
45 113 5.60 3.25
50 122 7.85 4.00
55 131 11.20 5.20
60 140 15.85 6.40
65 149 22.40 8.70
70 158 31.75 10.00
75 167 44.70 13.00
80 176 63.50 16.00
14
27
28
Polarization Index
� Polarization index = R10/R1 = I1/I10
(keeping voltage constant)
where:
R10 = megohms insulation resistance at 10 minutes
R1 = megohms insulation resistanceI at 1 minute
I1 = insulation current at 1 minute
I10 = insulation current at 10 minutes
15
29
Polarization Index
30
INSULATION 60/30 SECOND RATIO 10/1 MINUTE RATIO
CONDITION Dielectric Absorption Ratio Polarization Index
Dangerous Less than 1 Less than 1
Poor Less than 1.1 Less than 1.5
Questionable 1.1 to 1.25 1.5 to 2
Fair 1.25 to 1.4 2 to 3
Good 1.4 to 1.6 3 to 4
Excellent Above 1.6 Above 4
Interpretation
16
31
Step Voltage Test
32
Step Voltage Test
17
33
PI & DLF
PI
If a PI falls by 30% or more from the previous value then remedial
action such as cleaning, oil-filtering or further investigation should
be considered.
Tan Delta
If the IFT and oil moisture content exceed their respective limits
then Tan Delta test is recommended. This is a good complement to
PI test and as remedial action drying is usually performed.Field test results must be corrected to 20o C before comparison.
Basic Electrical Tests
34
Tan Delta (DLF) test
• In on site tan delta measurement there are two modes namely Grounded
Specimen Test (GST) and Ungrounded Specimen Test (UST). During GST
mode, the dielectric loss of insulation between one of the windings to
ground will be measured depending on the winding that is being excited.
Under UST mode, dielectric loss of insulation between the two windings
will be measured irrespective of the winding being excited.
• The ratio obtained from the field test should agree with nameplate
value within 0.2% for the insulation system between the high
voltage and low voltage winding at all taps. Otherwise, winding
repair is recommended.
• The ratio obtained from the field test should be within the limit of
0.5% for the insulation system between the high voltage winding
and ground. Otherwise, winding repair is recommended.
Basic Electrical Tests
18
35
Power Factor Test
Power Factor = cos θ = ir / it
900 – θ = δ
Dissipation Factor = tan δ = ir / ic
36
Power Factor Test
� For small δ, Cos (90 – δ) = tan δ
� tan δ = ir / ic
� ic = ωCV
� ir = ωCV tan δ
� Power loss (dielectric loss) = V ir = ωCV2 tan δ watt
� Dielectric loss is dependent on voltage and frequency
� Variation of tan δ with voltage is an important diagnostic method and will be part of this course
19
37
Power Factor Test
� Power factor or dissipation factor is a measure of insulation dielectric power loss
� Not a direct measure of dielectric strength
� Power-factor values are independent of insulation area or thickness
� Increase in dielectric loss may accelerate insulation deterioration because of the increased heating
� Insulation power factor increases directly with temperature
� Temperature corrections to a base temperature must be made, usually to 20 degree C
38
Power Factor Test
� Windings not at test potential should be grounded
� Refer to IEEE Standard No. 262, 1973
� Test sets consist of a completely shielded, high-voltage, 50-Hz power supply which applies up to 10 kV to the equipment being tested
� Much simpler and less expensive tester is also available which applies about 80 volts to the equipment being tested but not sufficiently shielded against induced voltages
20
39
40
Power Factor Test Set up
21
41
Temperature correction factors for the power factor of power transformer windings
� From IEEE Standard No. 262, 1973
where:
FP20 = power factor corrected to 20 degree C
FPT = power factor measured at T degree C
T = test temperature
K = correction factor from table
42
Temperature correction factors for the power factor of power transformer windings
22
43
Material Power Factor approx.)
Bakelite 2 - 10%
Vulcanized Fibre 5%
Varnished Cambric 6 - 8%
Mica 2%
Polyethylene 0.03%
New Insulating Oil 0.01-0.2%
Power Factor of Some Common Materials
44
Insulation Current Test
High Voltage DC/AC Test
� The voltage is slowly raised in discrete steps, allowing the leakage current to stabilize for a predetermined time
� A plot of the leakage current as a function of test voltage yields information on the condition of the insulation
� If the curve is a straight line, it indicates good condition of the cable
� If the current begins to increase at a rapid rate, indicates degradation / defects in the cable insulation
� After the completion of the test, the cable under test is grounded for sufficient time to discharge the voltage build up due to effects of absorption currents
23
45
46
Insulation Current Test
HVDC
µA
Applied Voltage (% of Maximum Voltage)
20 40 60 80 100
20
40
60
80
100
120
HealthyIndicates
Concern
24
47
48
HIGH-VOLTAGE, DC/AC TESTS
� Very little supply power is required to operate the DC test set
� The DC test set is portable and smaller than an ac, high-voltage tester
� Disconnect the buswork from the unit
� The dc breakdown voltage may range from 1.41 times the rms ac breakdown voltage to 2.5 times the rms ac puncture voltage
� Cases have indicated that on winding insulation with some deterioration, the application of overpotential tests may cause further deterioration, even though the insulation may not puncture
25
49
Test Procedure
� The machine winding should be grounded for at least 1 hour before conducting the test
� The phases should be separated and tested individually
� Lightning arresters and capacitors must be disconnected
� Cables and/or buswork should be disconnected if it is convenient to do so
� If the separation of phases is difficult then separation is needed once for the benchmark tests, and thereafter the phases may be tested together until deviation from normal is detected
50
Test procedure
� The voltage should be raised abruptly to the first voltage level with the start of timing for the test.
� The ratio of the 1-minute to the l0-minute reading of insulation current will afford useful indication of polarization index
� This gives the test engineer an idea of insulation dryness early in the test
� The test schedules are arranged to include a minimum of three points up to and including the maximum voltage
26
51
Test procedure
� If the insulation microampere versus voltage plots are straight lines, the test may be continued to the maximum test voltages
� The quality of the insulation may be judged by the position of any curvature or knee in the plot of insulation current versus test voltage
� If curvature or knee appears, the test should be stopped
� Upon completion of the dc, high- voltage test, the winding should be discharged through the special discharge resistor usually provided with the test set
� The winding may be solidly grounded when the voltage has dropped to zero or after a few minutes of discharge have occurred
� A winding should remain solidly grounded long enough before restoring the machine to service
52
HIGH-VOLTAGE, DC TESTS - RAMPED VOLTAGE METHOD
� The ramped technique of insulation testing uses a programmable dc, high-voltage test set and automatically ramps the high voltage at a preselectedrate (usually 1 kV/min)
� Insulation current versus applied voltage is plotted on an x-y recorder providing continuous observation and analysis of insulation current response as the test progresses
� The principal advantages of the ramp test over the conventional step method is the elimination of the human factor which makes it much more accurate and repeatable
27
53
Destructive “go/no go” tests
High Voltage DC/AC
� Less capable of revealing voids or cavities left inside the accessories
� Useful in detecting the defects related to contamination along the interface between the different components of the insulation system
� Voltage applied is usually three to four times the nominal phase-to earth voltage for 15 minutes or more
� This is destructive test
54
Turns Ratio test
• This test only needs to be performed if a problem is suspected
from the DGA.
• It indicates shorted turns.
• Shorted turns may result from short circuits or dielectric
(insulation) failures.
• The ratio obtained from the field test should agree with the factory
within 0.5%. Otherwise winding repair is recommended.
Basic Electrical Tests
28
55
Turns Ratio test
Basic Electrical Tests
56
Turns Ratio test
Basic Electrical Tests
29
57
Winding Resistance test
• This test only needs to be performed if there is a high rate of generation
of ethylene and ethane.
• Turns ratio test give indications that winding resistance testing is
warranted.
• Resistances measured in the field can be compared to the original
factory measurements or to sister transformers.
• Agreement within 5% for any of the above comparisons is considered
satisfactory.
• If winding resistances are to be compared to factory values, resistances
measurements will have to be converted to the reference temperature
used at the factory.
Basic Electrical Tests
58
Winding Resistance test
• Since the winding resistance changes with temperature, the winding and oil
temperatures must be recorded at the time of measurement and all test
readings must be converted to common temperature to give meaningful results.
Most factory test data are converted to 75°C which has become the most
commonly used temperature.
Basic Electrical Tests
Rs = Resistance at the factory reference temperature (found in the transformer
manual)
Rm = Resistance you actually measured
Ts = Factory reference temperature (usually 75 °C)
Tm = Temperature at which you took the measurements
Tk = A constant for the particular metal the winding is made from:
• 234.5 °C for copper
• 225 °C for aluminum
30
59
Basic Electrical TestsWinding Resistance test
Four terminal testing set up
V
I
P1 P2C1 C2
Measured Resistance (R) = V/I
1
1
Diagnostic Techniques for Diagnostic Techniques for Condition Monitoring Condition Monitoring
of Transformersof Transformers
Young Zaidey bin Yang GhazaliYoung Zaidey bin Yang GhazaliTechnical ExpertTechnical Expert
(Transformer Performance & Diagnostic)(Transformer Performance & Diagnostic)Engineering DepartmentEngineering Department
TNB Distribution DivisionTNB Distribution DivisionARSEPE 2008ARSEPE 2008
2
Transformer Advanced Off-Line Diagnostic Testing
2
3
Advanced Diagnostic Testing
� Most of the techniques, whether chemical or electrical methods, or destructive or non-destructive methods, only provide partial information about the state of the insulation condition of power transformers.
� More advanced condition monitoring or condition assessment techniques have been developed and are now starting to come into more general use.
� They have been developed in response to the need for new materials assessment methods.
� However, in some advanced diagnotics tools are still in the developmental stage, either in the technical development or, more likely, in the methods of analysis and interpretation of the test data.
4
Advanced Diagnostic Testing
� Recovery Voltage Measurement (RVM)
� Polarization and Depolarization Current Measurement (PDC)
� Frequency Domain Dielectric Spectroscopy (FDS)
� Frequency Response Analysis (FRA)
� Partial Discharge (PD) Measurement
� RVM, PDC & FDS are based on the used of the dielectric response of insulating materials to the application of electric fields – Conductivity, Polarization & Dielectric Response
3
5
Advanced Diagnostic Testing
� When a dielectric material with polar molecular structure is subjected to a DC voltage, the electric dipoles are oriented within the material in response to the applied electric field.
� There is thus a polarization charge induced by the dipole movement and realignment and this will effectively give a voltage across the capacitance. When the dielectric is short circuited, the stored charge in the dielectric capacitance is dissipated by a current discharge with a time constant determined by the effective intrinsic resistance and capacitance.
� During the short circuit the voltage across the dielectric is zero, but when the short circuit is removed before total charge to equilibrium occurs, then a voltage will appear across the dielectric. This measured voltage is known as the recovery voltage.
Recovery Voltage Measurement (RVM)
6
Advanced Diagnostic TestingRecovery Voltage Measurement (RVM)
4
7
Advanced Diagnostic Testing
Recovery Voltage Measurement (RVM) - TETTEX 5461
8
Advanced Diagnostic Testing
� A dielectric material becomes polarized when exposed to an electric field. Polarization is proportional to the intensity of the electric field and by measuring the current, polarization process can be observed. The current density is the sum of the conduction current and the displacement current.
� When the insulating material is exposed to a step voltage, polarization current is obtained. If the step voltage is removed, a reverse polarity current known as depolarization current is obtained. These two currents can be used to determine the response function and the conductivity of the dielectric material.
� The PDC is a DC testing method which determining the polarization spectrum in time constant domain between 10e-3 – 10e3 seconds in which the interface polarization phenomena of long time constant are active. The range of polarization is strongly influenced by the absorbed moisture and the deterioration by –product content of the paper insulation. It applies a 500V step of DC voltage to the high or low voltage winding insulations of transformers. Time of voltage application is typically up to 10000 seconds. Both the polarization and depolarization times are performed for the same period of time.
Polarization & Depolarization Current (PDC)
5
9
Advanced Diagnostic Testing
� The polarization current pulse has a peak magnitude, a final steady state level and a time constant and duration that are determined by the quality of the oil including both the moisturelevel and the electrical conductivity. In genera the electrical conductivity affects the peak current in the first 100 seconds or so of the current pulse. The moisture in the insulation affects the longer term polarization current level after about 1000 seconds.[Figure 8.6]
� Polarization and depolarization current measurement method gives general information about the state of insulation condition. This technique is proved to be a useful testing method in predicting of moisture and development of ageing phenomena.
Polarization & Depolarization Current (PDC)
10
Advanced Diagnostic Testing
� Effect of moisture in oil and cellulose paper on the polarization depolarization current measurement
Polarization & Depolarization Current (PDC)
6
11
Advanced Diagnostic Testing
� In the FDS technique, a known sinusoidal voltage is applied and measured together with the current passing across the insulationmaterial.
� The measurement is repeated for several frequency sweeps -from high frequency to low frequency for minimizing the memory effects.
� Advantage - the complete diagnostic on the property change in the material can be discerned
� By dividing the current by the voltage and comparing the phase difference, both the capacitance and the loss at the particular frequency and amplitude can be calculated.
Frequency Dielectric Spectroscopy Measurement (FDS)
12
Advanced Diagnostic Testing
� The advantage of an analysis of the dissipation factor frequencyas compare at fixed frequency:
� Behaviour of insulation caused by moisture affects can be evaluated.
� At higher frequencies the pressboard and the oil volume determine the dielectric loss, at medium frequencies the oil conductivity is the dominant factor and the lower frequency range is dominated by the pressboard dielectric loss.
Frequency Dielectric Spectroscopy Measurement (FDS)
7
13
Advanced Diagnostic Testing
� Example on how moisture affects the dissipation factor of kraftpaper at 20°C
Frequency Dielectric Spectroscopy Measurement (FDS)
14
Advanced Diagnostic Testing
� Measurement results of the insulation between primary and secondary to tertiary windings on a power transformer.
Frequency Dielectric Spectroscopy Measurement (FDS)
8
15
Advanced Diagnostic Testing
PROGRAMMA IDA 200
Frequency Dielectric Spectroscopy Measurement (FDS)
16
Frequency Response Analysis
How do you know whether you can energize A
TRANSFORMER after transportation to site or
after a protection trip?
Check Mechanical Integrity
9
17
Frequency Response Analysis
When does Mechanical Integrity matter?
� Re-location
� Short Circuit
� Lightning
� Tap-changer fault
Transportation damage can occur if the clamping and restraints are inadequate; such damage may lead to core and winding movement.
Radial buckling or axial deformation may occur due to excessive short circuit forces while in service.
18
Frequency Response Analysis
What you can identify by checking mechanical integrity?
� Core Movement
� Winding Deformation
� Faulty Core Grounds
� Partial Winding Collapse
� Hoop Buckling
� Broken or Loosened Clamping Structures
� Shorted Turns and Open Windings
10
19
Frequency Response Analysis
What Test can be Done?
Frequency response analysis (FRA) using a
low voltage AC wave of varying frequency to
identify changes in natural resonance
20
Frequency Response Analysis
Why FRA?
� FRA Technique: The technique covers the full dynamic range and maintains the same energy level for each frequency, providing results that are repeatable and accurate.
� Impulse Technique: This technique requires high sampling rates and high resolution to obtain a valid measurement. The applied impulse does not produce constant energy across the specified frequency, which can cause poor repeatability that is influenced by the non-linear properties of the test specimen.
11
21
Frequency Response Analysis
What is FRA ?
� FRA is a tool that can give an indication of core or winding movement in transformers.
� This is done by performing a measurement to look at how well a transformer winding transmits a low voltage signal that variesin frequency.
� Transformer does this in relation to its impedance, the capacitive and inductive elements which are intimately related to the physical construction of the transformer.
� Changes in frequency response as measured by FRA techniques may indicate a physical change inside the transformer, the cause of which then needs to be identified and investigated.
22
Frequency Response Analysis
12
23
Frequency Response Analysis
24
Frequency Response Analysis
� Test Equipment
13
25
Frequency Response Analysis
26
Frequency Response Analysis
14
27
Frequency Response Analysis
28
Frequency Response Analysis
What is the frequency range?
� The measured frequency range is normally very large,
which can be from 5Hz up to 10MHz
� This frequency range covers the most important
diagnostic areas:
� Core and Magnetic Properties
� Winding Movement and Deformation
� Interconnections-Leads and Load Tap Changer
15
29
Frequency Response Analysis
30
Frequency Response Analysis
� The magnitude and the angle of the complex transfer function can be obtained using a network-analyzer
� The resulting amplitude of the measurement can be expressed as,
H (dB) = 20 log10 [(ZS)/(ZS+ZT)]
� The resulting phase is defined by
H (φ) = tan-1 [(ZS)/(ZS+ZT)]
16
31
Frequency Response Analysis
32
Frequency Response Analysis
17
33
Frequency Response Analysis
What are the ANALYZING TECHNIQUES?
� Signature
� Difference
� Transfer Function
� Statistical
FRA Signatures are analyzed based on 3 band methods
34
Frequency Response Analysis
What do the 3 Bands mean?
� 5Hz up to 10KHz – defect in core and magnetic
circuit
� 10KHz up to 600KHz – deformation in winding
geometry
� 600KHz up to 10MHz – abnormalities in the
inter-connection and test
system
18
35
Frequency Response Analysis
SIGNATURE TECHNIQUE
36
Frequency Response Analysis
SIGNATURE TECHNIQUE
19
37
Frequency Response Analysis
SIGNATURE TECHNIQUE
38
Frequency Response Analysis
DIFFERENCE TECHNIQUE
(Phase A before)
20
39
Frequency Response Analysis
DIFFERENCE TECHNIQUE
(Phase A after)
40
Frequency Response Analysis
DIFFERENCE TECHNIQUEThis technique can analyze the windings phase by phase, which is not
possible in the signature technique
21
41
Frequency Response Analysis
� Historical data or Baseline Reference are, undoubtedly, the best reference to be used for FRA analysis
� However, it is not practically easy to get historical data due to constraints of outages
� Criteria to choose reference FRA measurements in the absence of historical data or baseline reference
42
Frequency Response Analysis
Different Different Same Same Peer
Different Same Same Same Sister
Same Same Same Same Twin
S/S
LOCATION
MANU-
FACTURER
MVA
RATING
KV RATIOCATEGORY
22
43
Partial Discharge
� What is PD – Electric discharge that do not completely bridge the electrodes
� Discharge magnitude is usually small but can cause progressive deterioration and lead to failure� Overeating of dielectric boundary
� Charges trapped in the surface
� Attack by ultraviolet rays & soft X-rays
� Formation of chemicals such as nitric acid & ozone
� Therefore presence of PD need to be detected in a non-destructive test
44
Partial Discharge� PD Classification
23
45
Partial Discharge� PD Classification
46
Partial Discharge� Occurrence of PD – Inception Voltage
24
47
Partial Discharge� Occurrence of PD – Inception Voltage
48
Partial Discharge
� Occurrence & Recognition
� Detection
� Measurement
� Location
� Evaluation
25
49
Partial Discharge
� Evaluation
� Amplitude in dB
� Energy or charge in pC
� Duration in ms
50
Partial Discharge� On-line acoustic PD Detection - Physical Acoustic DISP-24
26
51
Frequency Response Analysis
Why SFRA in a factory environment?
• Quality assurance
• Baseline reference
• Relocation and commissioning preparation
Manufacturers are using SFRA as part of their quality program to ensure
transformer production is identical between units in a batch
52
Frequency Response Analysis
Why SFRA in a field environment?
• Relocation and commissioning validation
• Post incident: lightning, fault, short circuit, seismic event
etc
Once a transformer arrives on site after relocation it must be tested
immediately, to gain confidence in the mechanical integrity of the
unit prior to commissioning
27
53
Frequency Response Analysis
� Frequency Response Analysis is a very effective tool for
diagnosing transformer mechanical integrity both in the
factory and in the field,
which cannot always be detected using other means
� The best way to obtain baseline reference results is,
undoubtedly, on completion of the manufacturing
process at the factory
� However, in the absence of baseline reference the
proposed criterion of twin, sister, and peer transformers
can be used as references with reasonable degree of
accuracy
54
Transformer Maintenance (Dry Type)� Electrical Tests
� Perform insulation-resistance tests winding-to-winding and each winding-to-ground
� Perform turns ratio tests at the designated tap position
� Perform power-factor or dissipation-factor tests
� Measure the resistance of each winding at the designated tap position
� Measure core insulation-resistance at 500 volts dc if core is insulated
28
55
Insulator Maintenance
� Inspection - look for cracks, dirt etc., tracking, copper wash,
mechanical damage
� Cleaning - Wash, dry wipe
� Repairs - Usually replace except special cases
� Testing - Megger & Power Factor test
� Do not climb on or use for personal support!
56
Transformer Maintenance (Liquid filled)
� Visual inspection
� Inspect physical condition for evidence of moisture and corona
� Verify operation of cooling fans
� Verify operation of temperature and level indicators, pressure relief device, and gas relay
� Verify correct liquid level in all tanks and bushings
� Verify correct equipment grounding
� Verify the presence of transformer surge arresters
� Test load tap-changer
� Inspect all bolted electrical connections for high resistance using one of the following methods:
1. Use of low-resistance ohmmeter
2. Perform thermographic survey
29
57
Transformer Maintenance (Liquid filled)
� Electrical Tests
� Perform turns ratio tests at all tap positions
� Perform power-factor or dissipation-factor tests
� Measure the resistance of each winding at all tap positions
� Perform insulation-resistance tests winding-to-winding and each winding-to-ground
� If core ground strap is accessible, measure core insulation resistance at 500 volts dc
� Remove a sample of insulating liquid in accordance with ASTM D923
� Test for Oil Quality, DGA and Furan
58
• Diagnostic Testing provides a powerful tool for the
complete and economic assessment of the transformer
condition
• There is nevertheless still a lack on how to integrate the
information obtained by the on-line monitoring into the
actions taken onto the service of the transformer
• The supplementary information obtained by the off-line
diagnostic after the detection of an abnormal condition is a
worth-full information to be integrated into future on-line
monitoring systems
Conclusion
1
1
Diagnostic Techniques for Diagnostic Techniques for Condition Monitoring Condition Monitoring
of Transformersof Transformers
Young Zaidey bin Yang GhazaliYoung Zaidey bin Yang GhazaliTechnical ExpertTechnical Expert
(Transformer Performance & Diagnostic)(Transformer Performance & Diagnostic)Engineering DepartmentEngineering Department
TNB Distribution DivisionTNB Distribution DivisionARSEPE 2008ARSEPE 2008
2
Test Results Interpretation
2
3
1. Scoring
� Scoring can be applied to test results to indicate acceptable condition level of transformers.
� Transformer condition indicator scoring is somewhat subjective, relying on transformer condition experts.
� Relative terms are used and compared to industry accepted levels; or to baseline or previous (acceptable) levels on this transformer; or to transformers of similar design, construction, or age operating in a similar environment.
4
2. Weighting Factors
� Weighting factors is used to recognize that some
condition indicators, affects the Condition Index to a
greater or lesser degree than other indicators.
� These weighting factors were arrived at by
consensus among transformer design and
maintenance personnel with extensive experience.
3
5
3. Mitigating Factors
� Every transformer is unique and, therefore cannot
quantify all factors that affect individual transformer
condition.
� It is important that the Transformer Condition Index
arrived at be scrutinized by experts.
� Mitigating factors specific to the utility may determine
the final Transformer Condition Index and the final
decision on transformer replacement or
rehabilitation.
6
1. Tan Delta for Main Tank
Perform appropriate advanced
electrical tests tests as recommended
by the expert or internal inspection of
main tank immediately.
0% tan δ > 5
The monitoring frequency should be
revised to 3 months. Make arrangement
for advanced electrical tests tests.
14 <% tan δ < 5
The monitoring frequency should be
revised to 6 months.
22 <% tan δ < 4
Normal. The monitoring frequency of
24 months can be maintained.
3%tan δ < 2
ActionScoreResults
This test is done on the transformer at regular interval under normal condition. This test results
are considered for condition assessment of an in-service transformer.
4
7
2. Turns-Ratio Test
Perform appropriate advanced
electrical tests tests as recommended
by the expert or internal inspection of
main tank and OLTC tank
immediately.
0% deviation >0.5
The monitoring frequency should be
revised to 3 months. Make
arrangement for advanced electrical
tests tests.
10.3 <% deviation < 0.5
The monitoring frequency should be
revised to 6 months.
20.2 <% deviation < 0.3
Normal. The monitoring frequency of
24 months can be maintained.
3% deviation < 0.2
ActionScoreResults
This test is done on transformer at regular interval of 24 months under normal condition. This
test results are considered for condition assessment of an in-service transformer.
8
3. Winding Resistance Test
Perform appropriate
advanced electrical tests tests
as recommended by the
expert or internal inspection
of main tank immediately.
0More than 10% difference
between phases or from
factory tests
The monitoring frequency
should be revised to 3
months. Make arrangement
for advanced electrical tests
tests.
17 to 10% difference between
phases or from factory tests
The monitoring frequency
should be revised to 6
months.
25 to 7% difference between
phases or from factory tests
Normal. The monitoring
frequency of 24 months can
be maintained.
3No more than 5% difference
between phases or from
factory tests
ActionScoreResults
This test is done on transformer at regular interval of 24 months under normal condition. This
test results are considered for condition assessment of an in-service transformer.
5
9
4. Main Winding Insulation Resistance Test
Perform appropriate advanced electrical tests
tests as recommended by the expert or
internal inspection of main tank
immediately.
0PI value < 1.0
The monitoring periodicity should be revised
to 3 months. Make arrangement for
advanced electrical tests tests.
11.0< PI value < 1.5
The monitoring periodicity should be revised
to 6 months.
21.0< PI value < 3.0
Normal. The monitoring periodicity of 24
months can be maintained.
3PI value ≥ 3.0
ActionScoreResults
This test is done on transformer tail at regular interval of 24 months under normal condition. This
test results are considered for condition assessment of an in-service transformer.
10
5(i). Oil Quality Test
0.2
0.4
0.1
0.3
Weightage
Power factor4
Acidity3
BDV2
Moisture1
CriteriaNo
6
11
5(ii). Oil Quality Test
> 0.5
0.31 – 0.5
0.21 – 0.3
0.11 – 0.2
0.091 – 0.1
0.071 – 0.09
0.051 – 0.07
0.031 – 0.05
0.01 – 0.03
< 0.010
IFT
>0.31
0.25-0.3
0.21-0.24
0.17-0.20
0.13-0.16
0.1-0.12
0.07-0.09
0.05-0.06
0.02-0.04
<0.01
Acidity
<15
15-19
20-24
25-29
30-35
36-40
41-45
46-50
51-55
>56
BDV
(kV)
1>50
246-50
341-45
436-40
531-35
626-30
721-25
816-20
911-15
100-10
Condition Indicator
Score
Moisture
(ppm)
12
6. Fault Gases Limit
> 4000> 1400> 800> 150> 150> 80> 1420Condition 4
1916 -
4000
571 -
1400
401 -
800
101 -
150
101 -
150
46 - 80701 –
1420
Condition 3
721 -
1915
351 -
570
121 -
400
66 -
100
51 - 10036 - 45101 –
700
Condition 2
720350120655035100Condition 1
TDCGCOCH4C2H6C2H4C2H2H2Status
7
13
7. Key Gases Analysis
1
2
2
3
4
5
5
6
7
8
8
9
10
Condition
Indicator Score
7
5-6
3-4
<2Condition 4
7
5-6
3-4
<2Condition 3
7
5-6
3-4
<2Condition 2
0Condition 1
Per unit exceededIndividual fault gases exceed
limit
14
8. Furanic Analysis
1<373>1800
2374-3871601-1800
3388-4041401-1600
4405-4231201-1400
5424-4461001-1200
6447-474801-1000
7475-509601-800
8510-559401-600
9560-645201-400
10646-13000-200
Condition Indicator ScoreEstimated DPFuranic
8
15
9. Oil Quality, Key Gases & Furan Analysis Score
Seek immediate advice from the expert
to perform advanced electrical test or
internal inspection
0Overall ranking ≤ 1.5
The monitoring periodicity should be
revised to 3 months. Make
arrangement for advanced electrical
tests.
11.5 ≤ Overall ranking ≤ 4.0
The monitoring periodicity should be
revised to 6 months.
24.0 ≤ Overall ranking ≤ 7.5
Normal. The monitoring periodicity of
12 months can be maintained.
37.5 ≤ Overall ranking ≤ 10
ActionScoreResults
This test is done on transformer at regular interval under normal condition. This test results are
considered for condition assessment of an in-service transformer.
16
10. FRA
Indicates serious problem requiring immediate
evaluation, additional testing (if applicable)
and immediate consultation with experts
Subtract 1.5Significant deviation
Comparison between phases (using Cross-
correlation Index):
•CCI at low freq zone <0.6
Retest the transformer for FRA after 3
months. Arrange for replacement of defective
section(s).
Subtract 1.0Moderate deviation
Comparison between phases (using Cross-
correlation Index):
•0.6<CCI at low freq zone <1.0
•CCI at mid freq zone < 0.6
Retest the transformer for FRA after 6
months. The monitoring periodicity of all
basic electrical tests tests should be
maintained at 6 months.
Subtract 0.5Minor deviation
Comparison between phases (using Cross-
correlation Index):
•1.0<CCI at low freq zone <2.0
•0.6<CCI at mid freq zone < 1.0
The monitoring periodicity of all basic
electrical tests tests should be maintained at 6
months. Practice FRA test if necessary.
Subtract 0No deviation
Comparison between phases (using Cross-
correlation Index, CCI):
•CCI at low freq zone >2.0
•CCI at mid freq zone > 1.0
•CCI at high freq zone > 0.6
ActionScore
Adjustment
Results
9
17
11. FDS
Indicates serious problem requiring
immediate evaluation, additional
testing (if applicable) and immediate
consultation with experts
Subtract 1.5% moisture in paper > 4
Retest the transformer for FDS after 3
months. Arrange for replacement of
defective section(s).
Subtract 1.02 < % moisture in paper < 4
Retest the transformer for FDS after 6
months. The monitoring periodicity of
all basic electrical tests tests should be
maintained at 6 months.
Subtract 0.51.5 < % moisture in paper < 2
The monitoring periodicity of all basic
electrical tests tests should be
maintained at 6 months. Practice FDS
test if necessary.
Subtract 0% moisture in paper < 1.5
ActionScore
AdjustmentResults
18
12. PD
Indicates serious problem requiring
immediate evaluation, additional
testing and immediate consultation
with expert. Recommendation is to
remove the transformer from service
immediately.
Subtract 1.5Amplitude 80-90 dB
Energy 400-500
Duration 4000 ms-5000 ms
Retest the transformer for PD after 3
months. Arrange for replacement of
defective section(s).
Subtract 1.0Amplitude 70-80 dB
Energy 200-400
Duration 3000 ms-4000 ms
Retest the transformer for PD after 6
months. The monitoring periodicity
of all basic electrical tests tests should
be maintained at 6 months.
Subtract 0.5Amplitude 60-70 dB
Energy 200-300
Duration 200 ms-3000 ms
The monitoring periodicity of all
basic electrical tests tests should be
maintained at 6 months. Practice PD
test if necessary.
Subtract 0Amplitude 40-60 dB
Energy 1-200
Duration 100 ms-2000 ms
ActionScore
AdjustmentResults*
10
19