Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Highlights This Month:
• The commercial integration of ATCO Pipelines (AP) into the Alberta System occurred on October 1, 2011. The throughput data reported for the Alberta system includes ATCO Pipeline System flows as of October 1, 2011. The Summer 2011 seasonal design capabilities were maintained pre- integration levels and applied for the majority of the Summer 2011 season.
The average actual flow for the dominant flow condition in each of the Alberta design areas is compared against the corresponding design capability to obtain a measure of pipeline utilization. Consequently, design capability utilization is measured as Average Actual Flow / Seasonal Design Capability.
FT Receipt Availability over a 3 month average from May 1, 2012 – July 31, 2012 was deemed to be 100% available in all pipe segments.
Border Availability at Empress/McNeill, Gordondale and Alberta/BC, over a 3 month average from May 1, 2012 – July 31, 2012 were all deemed 100% available.
The Firm Transportation service contract utilization table (page 3 of this report) illustrates the FT and TF + IT utilization for receipts and deliveries.
SYSTEM UTILIZATION AND RELIABILITYMONTHLY REPORT
for the month endingJuly , 2012
)( NOVA Gas Transmission Ltd.
Published date:September 10, 2012
2
TABLE OF CONTENTS
If you have any questions on the content of this report, contact Chiu Chow at (403) 920-5313 or via fax at (403) 920-2379.
MONTHLY FEATURES PAGE Firm Transportation Service Contract Utilization ..................................................................... . 3 Design Capability Utilization Ft. McMurray Area – Flow Within………………………………………………………………. 4 Kirby Area – Flow Within……………………………………………………………………….. 5 North of Bens Lake – Flow Within ............................................................................................. .. 6 North & South of Bens Lake – Flow Within…………………………………………………….. 7 Upper Peace River ...................................................................................................................... .. 8 Upper & Central Peace River ..................................................................................................... . 9 Peace River Design ..................................................................................................................... .10 Marten Hills ................................................................................................................................ .11 Upstream James River ................................................................................................................ .12 South & Alderson ....................................................................................................................... .13 Rimbey Nevis – Flow Within ................................................................................................... .14 Eastern Alberta Mainline (James River to Princess) .................................................................. .15 Medicine Hat - Flow Within ....................................................................................................... .16 Eastern Alberta Mainline (Princess to Empress/McNeill) .......................................................... .17 Western Alberta Mainline (AB/BC & AB/Montana Borders) ................................................... .18 Historical Transportation Service Availability (3 Month Average) ........................................ .19 Future Firm Transportation Service Availability....................................................................... .20 How to Use This Report ................................................................................................................ .21 REFERENCES NGTL Design Areas Map ............................................................................................................. 23 NGTL Pipeline Segments Map ..................................................................................................... 24 Definition of Terms ........................................................................................................................ 25
3
FIRM TRANSPORTATION SERVICE1 CONTRACT UTILIZATION3
By NGTL Pipeline Segments
Jul CD Jul CDSegment Contract Utilization (TJ/d) Utilization (MMcf/d) UPRM FT 9% 25.4 86% 88
FT + IT2 11% 92%
LPRM FT 0% 0.0 0% 0FT + IT 0% 0%
PRLL FT 29% 48.1 89% 149FT + IT 29% 96%
NWML FT 0% 0.0 64% 373FT + IT 0% 67%
GRDL FT 9% 4.7 75% 1,213FT + IT 10% 77%
WRSY FT 0% 0.0 77% 25FT + IT 0% 94%
WAEX FT 22% 42.4 69% 388FT + IT 38% 91%
JUDY FT 27% 16.6 93% 71FT + IT 27% 106%
GPML FT 21% 167.6 79% 3,083FT + IT 34% 84%
CENT FT 65% 9.8 90% 849FT + IT 65% 108%
LPOL FT 20% 82.6 95% 551FT + IT 26% 120%
WGAT FT 65% 3,462.5 75% 497FT + IT 66% 81%
ALEG FT 29% 315.3 95% 911FT + IT 40% 118%
SLAT FT 12% 178.3 94% 257FT + IT 12% 108%
MLAT FT 60% 262.1 84% 231FT + IT 65% 95%
BLEG FT 49% 142.6 95% 618FT + IT 49% 107%
EGAT FT 97% 3,686.9 97% 45FT + IT 116% 112%
MRTN FT 13% 28.1 88% 85FT + IT 15% 99%
LIEG FT 81% 803.1 67% 52FT + IT 101% 97%
KIRB FT 81% 781.8 79% 48FT + IT 89% 121%
SMHI FT 49% 12.1 84% 49FT + IT 49% 123%
REDL FT 42% 13.1 91% 51FT + IT 45% 117%
COLD FT 54% 56.8 93% 31FT + IT 100% 120%
EDM FT 34% 1,709.4 81% 82FT + IT 36% 114%
NLAT FT 18% 16.0 94% 183FT + IT 18% 113%
WAIN FT 3% 0.5 83% 12FT + IT 3% 108%
ELAT FT 61% 256.5 85% 168FT + IT 61% 110%
TOTAL SYSTEM FT 69% 12,122.6 83% 10,110FT + IT 78% 95%
*NOTE:
billed volumes divided by applicable receipt or delivery Contract level.
Delivery Receipt
July 2012
1. FT includes all receipt and delivery Firm Transportation Services: FTR, FTRN, 2. IT includes all receipt and delivery Interruptible Services: ITR, FRO, ITD1, ITD2, 3. Utilization data is based on billed monthly volumes. Percent utilization calculated
DESIGN CAPABILITY UTILIZATION FT. McMURRAY AREA – FLOW WITHIN
% Design Capability Utilization Monthly Average Area Deliveries as a Percentage of Design Capability
Average Flow/ Design Capability
Feb
60
Mar
62
Apr
64
May
54
Jun
55
Jul
57
4
Throughput vs. Design CapabilityFt. McMurray Area - Delivery Capability
0
5,000
10,000
15,000
20,000
25,000
30,000
35,000
40,000
45,000
50,000
Nov-10
Dec-10
Jan-11
Feb-11
Mar-11
Apr-11
May-11
Jun-11
Jul-11
Aug-11
Sep-11
Oct-11
Nov-11
Dec-11
Jan-12
Feb-12
Mar-12
Apr-12
May-12
Jun-12
Jul-12
Aug-12
Sep-12
Oct-12
Date
103m3/d
0
200
400
600
800
1000
1200
1400
1600
MMcf/d
Throughput Capability
41% 58% 58%Ave LF : 61 %
DESIGN CAPABILITY UTILIZATION KIRBY AREA – FLOW WITHIN
% Design Capability Utilization Monthly Average Area Deliveries as a Percentage of Design Capability
Average Flow/ Design Capability
Feb
84
Mar
89
Apr
82
May
79
Jun
87
Jul
86
Throughput vs. Design CapabilityKirby Area - Delivery Capability
0
5,000
10,000
15,000
20,000
25,000
30,000
Nov-10
Dec-10
Jan-11
Feb-11
Mar-11
Apr-11
May-11
Jun-11
Jul-11
Aug-11
Sep-11
Oct-11
Nov-11
Dec-11
Jan-12
Feb-12
Mar-12
Apr-12
May-12
Jun-12
Jul-12
Aug-12
Sep-12
Oct-12
Date
103m3/d
0
200
400
600
800
1000
MMcf/d
Throughput Capability
83%Ave LF : 81 %
83% 82%
5
6
DESIGN CAPABILITY UTILIZATION NORTH OF BENS LAKE – FLOW WITHIN
% Design Capability Utilization Monthly Average Area Deliveries as a Percentage of Design Capability
Average Flow/ Design Capability
Feb
75
Mar
73
Apr
73
May
63
Jun
63
Jul
64
Throughput vs. Design CapabilityNorth of Bens Lake - Delivery Capability
0
20,000
40,000
60,000
80,000
100,000
120,000
Nov-10
Dec-10
Jan-11
Feb-11
Mar-11
Apr-11
May-11
Jun-11
Jul-11
Aug-11
Sep-11
Oct-11
Nov-11
Dec-11
Jan-12
Feb-12
Mar-12
Apr-12
May-12
Jun-12
Jul-12
Aug-12
Sep-12
Oct-12
Date
103m3/d
0
500
1000
1500
2000
2500
3000
3500
4000
MMcf/d
Throughput Capability
60%73%Ave LF :
68 %66%
7
DESIGN CAPABILITY UTILIZATION NORTH & SOUTH OF BENS LAKE – FLOW WITHIN
% Design Capability Utilization Monthly Average Actual Area Deliveries as a Percentage of Design Capability
Average Flow/ Design Capability
Feb
74
Mar
72
Apr
76
May
67
Jun
67
Jul
67
Throughput vs. Design CapabilityNorth and East - Delivery Capability
0
20,000
40,000
60,000
80,000
100,000
120,000
Nov-10
Dec-10
Jan-11
Feb-11
Mar-11
Apr-11
May-11
Jun-11
Jul-11
Aug-11
Sep-11
Oct-11
Nov-11
Dec-11
Jan-12
Feb-12
Mar-12
Apr-12
May-12
Jun-12
Jul-12
Aug-12
Sep-12
Oct-12
Date
103m3/d
0
500
1000
1500
2000
2500
3000
3500
4000
MMcf/d
Throughput Capability
Ave LF : 70 % 61%
72% 69%
8
DESIGN CAPABILITY UTILIZATION UPPER PEACE RIVER
% Design Capability Utilization Monthly Average Actual Flow as a Percentage of Design Capability
Average Flow/ Design Capability
Feb
63
Mar
57
Apr
50
May
50
Jun
48
Jul
45
Throughput vs. Design CapabilityUpper Peace River
0
5,000
10,000
15,000
20,000
25,000
30,000
35,000
Nov-10
Dec-10
Jan-11
Feb-11
Mar-11
Apr-11
May-11
Jun-11
Jul-11
Aug-11
Sep-11
Oct-11
Nov-11
Dec-11
Jan-12
Feb-12
Mar-12
Apr-12
May-12
Jun-12
Jul-12
Aug-12
Sep-12
Oct-12
Date
103m3/d
0
200
400
600
800
1000
1200
MMcf/d
Throughput Capability
Ave LF : 67 % 74% 62% 48%
9
DESIGN CAPABILITY UTILIZATION UPPER and CENTRAL PEACE RIVER
% Design Capability Utilization Monthly Average Actual Flow as a Percentage of Capability
Average Flow/ Design Capability
Feb
72
Mar
65
Apr
67
May
63
Jun
63
Jul
62
Throughput vs. Design CapabilityUpper and Central Peace River
0
10,000
20,000
30,000
40,000
50,000
60,000
70,000
Nov-10
Dec-10
Jan-11
Feb-11
Mar-11
Apr-11
May-11
Jun-11
Jul-11
Aug-11
Sep-11
Oct-11
Nov-11
Dec-11
Jan-12
Feb-12
Mar-12
Apr-12
May-12
Jun-12
Jul-12
Aug-12
Sep-12
Oct-12
Date
103m3/d
0
500
1000
1500
2000
MMcf/d
Throughput Capability
Ave LF : 59 %
80% 68% 64%
10
DESIGN CAPABILITY UTILIZATION PEACE RIVER DESIGN(Upper, Central and Lower Peace River)
% Design Capability Utilization Monthly Average Actual Flow as a Percentage of Design Capability
Average Flow/ Design Capability
Feb
81
Mar
75
Apr
76
May
73
Jun
71
Jul
72
Throughput vs. Design CapabilityPeace River Design
0
20,000
40,000
60,000
80,000
100,000
120,000
140,000
160,000
180,000
Nov-10
Dec-10
Jan-11
Feb-11
Mar-11
Apr-11
May-11
Jun-11
Jul-11
Aug-11
Sep-11
Oct-11
Nov-11
Dec-11
Jan-12
Feb-12
Mar-12
Apr-12
May-12
Jun-12
Jul-12
Aug-12
Sep-12
Oct-12
Date
103m3/d
0
1000
2000
3000
4000
5000
6000
MMcf/d
Throughput Capability
Ave LF : 80 %
84% 79% 73%
11
DESIGN CAPABILITY UTILIZATION MARTEN HILLS
% Design Capability Utilization Monthly Average Actual Flow as a Percentage of Design Capability
Average Flow/ Design Capability
Feb
32
Mar
31
Apr
30
May
30
Jun
29
Jul
28
Throughput vs. Design CapabilityMarten Hills
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
9,000
10,000
Nov-10
Dec-10
Jan-11
Feb-11
Mar-11
Apr-11
May-11
Jun-11
Jul-11
Aug-11
Sep-11
Oct-11
Nov-11
Dec-11
Jan-12
Feb-12
Mar-12
Apr-12
May-12
Jun-12
Jul-12
Aug-12
Sep-12
Oct-12
Date
103m3/d
0
50
100
150
200
250
300
350
MMcf/d
Throughput Capability
Ave LF : 28 % 34% 32% 29%
12
DESIGN CAPABILITY UTILIZATIONUPSTREAM JAMES RIVER (Edson Mainline, Peace River Design and Marten Hills)
% Design Capability Utilization Monthly Average Actual Flow as a Percentage of Design Capability
Average Flow/ Design Capability
Feb
89
Mar
83
Apr
82
May
79
Jun
78
Jul
79
Throughput vs. Design CapabilityUpstream James River
0
50,000
100,000
150,000
200,000
Nov-10
Dec-10
Jan-11
Feb-11
Mar-11
Apr-11
May-11
Jun-11
Jul-11
Aug-11
Sep-11
Oct-11
Nov-11
Dec-11
Jan-12
Feb-12
Mar-12
Apr-12
May-12
Jun-12
Jul-12
Aug-12
Sep-12
Oct-12
Date
103m3/d
0
1000
2000
3000
4000
5000
6000
7000
MMcf/d
Throughput Capability
Ave LF : 89 % 90%
86% 80%
13
DESIGN CAPABILITY UTILIZATION SOUTH and ALDERSON
% Design Capability Utilization Monthly Average Actual Flow as a Percentage of Design Capability
Average Flow/ Design Capability
Feb
40
Mar
42
Apr
44
May
45
Jun
46
Jul
46
Throughput vs. Design CapabilitySouth and Alderson
0
5,000
10,000
15,000
20,000
25,000
30,000
Nov-10
Dec-10
Jan-11
Feb-11
Mar-11
Apr-11
May-11
Jun-11
Jul-11
Aug-11
Sep-11
Oct-11
Nov-11
Dec-11
Jan-12
Feb-12
Mar-12
Apr-12
May-12
Jun-12
Jul-12
Aug-12
Sep-12
Oct-12
Date
103m3/d
0
200
400
600
800
1000
MMcf/d
Throughput Capability
Ave LF : 49 % 61% 41% 45%
14
DESIGN CAPABILITY UTILIZATION RIMBEY-NEVIS – FLOW WITHIN
% Design Capability Utilization Monthly Average Area Deliveries as a Percentage of Design Capability
Average Flow/ Design Capability
Feb
67
Mar
56
Apr
59
May
43
Jun
34
Jul
36
Throughput vs. Design CapabilityRimbey Nevis - Delivery Capability
0
5,000
10,000
15,000
20,000
25,000
30,000
Nov-10
Dec-10
Jan-11
Feb-11
Mar-11
Apr-11
May-11
Jun-11
Jul-11
Aug-11
Sep-11
Oct-11
Nov-11
Dec-11
Jan-12
Feb-12
Mar-12
Apr-12
May-12
Jun-12
Jul-12
Aug-12
Sep-12
Oct-12
Date
103m3/d
0
200
400
600
800
1000
MMcf/d
Area Deliveries Capability
Ave LF : 72 % 38% 65% 43%
15
DESIGN CAPABILITY UTILIZATION EASTERN ALBERTA MAINLINE (James River to Princess)
% Design Capability Utilization Monthly Average Actual Flow as a Percentage of Design Capability
Average Flow/ Design Capability
Feb
79
Mar
69
Apr
72
May
68
Jun
64
Jul
66
Throughput vs. Design CapabilityEastern Alberta Mainline - James River to Princess
0
50,000
100,000
150,000
200,000
250,000
Nov-10
Dec-10
Jan-11
Feb-11
Mar-11
Apr-11
May-11
Jun-11
Jul-11
Aug-11
Sep-11
Oct-11
Nov-11
Dec-11
Jan-12
Feb-12
Mar-12
Apr-12
May-12
Jun-12
Jul-12
Aug-12
Sep-12
Oct-12
Date
103m3/d
0
1000
2000
3000
4000
5000
6000
7000
8000
MMcf/d
Throughput Capability
Ave LF : 79 % 75% 75% 68%
16
DESIGN CAPABILITY UTILIZATION MEDICINE HAT – FLOW WITHIN
Throughput vs. Design CapabilityMedicine Hat - Delivery Capability
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
9,000
10,000
Nov-10
Dec-10
Jan-11
Feb-11
Mar-11
Apr-11
May-11
Jun-11
Jul-11
Aug-11
Sep-11
Oct-11
Nov-11
Dec-11
Jan-12
Feb-12
Mar-12
Apr-12
May-12
Jun-12
Jul-12
Aug-12
Sep-12
Oct-12
Date
103m3/d
0
50
100
150
200
250
300
350
MMcf/d
Area Deliveries Capability
Ave LF : 80 % 90% 82% 71%
% Design Capability Utilization Monthly Average Area Deliveries as a Percentage of Design Capability
Average Flow/ Design Capability
Feb
87
Mar
82
Apr
80
May
79
Jun
59
Jul
68
17
DESIGN CAPABILITY UTILIZATION EASTERN ALBERTA MAINLINE (Princess to Empress / McNeill)
% Design Capability Utilization Average Actual Flow as a Percentage of Design Capability
Average Flow /
Design Capability
Feb
63
Mar
55
Apr
58
May
56
Jun
55
Jul
55
Throughput vs. Design CapabilityEastern Gate - Empress & McNeill Borders
0
50,000
100,000
150,000
200,000
250,000
Nov-10
Dec-10
Jan-11
Feb-11
Mar-11
Apr-11
May-11
Jun-11
Jul-11
Aug-11
Sep-11
Oct-11
Nov-11
Dec-11
Jan-12
Feb-12
Mar-12
Apr-12
May-12
Jun-12
Jul-12
Aug-12
Sep-12
Oct-12
Date
103m3/d
0
1000
2000
3000
4000
5000
6000
7000
8000
MMcf/d
Throughput Capability
Ave LF : 78 % 65% 60% 56%
% Design Capability Utilization Average Actual Flow as a Percentage of Design Capability
Average Flow /
Design Capability
Feb
78
Mar
73
Apr
65
May
63
Jun
73
Jul
74
18
DESIGN CAPABILITY UTILIZATIONWESTERN ALBERTA MAINLINE (Alberta/B.C. and Alberta/Montana Borders)
Throughput vs. Design CapabilityWestern Gate - Alberta / BC & Alberta / Montana Borders
0
10,000
20,000
30,000
40,000
50,000
60,000
70,000
80,000
90,000
100,000
Nov-10
Dec-10
Jan-11
Feb-11
Mar-11
Apr-11
May-11
Jun-11
Jul-11
Aug-11
Sep-11
Oct-11
Nov-11
Dec-11
Jan-12
Feb-12
Mar-12
Apr-12
May-12
Jun-12
Jul-12
Aug-12
Sep-12
Oct-12
Date
103m3/d
0
500
1000
1500
2000
2500
3000
3500
MMcf/d
Throughput Capability
Ave LF : 72 % 60% 74% 69%
19
Receipt Area IT-R Service Firm Service Firm Service Causes/Comments (3)
Available Available Restriction
Segment (% of time) (% of time) (% of time) Max Average
Peace River UPRM 1 100 100 0 0 0
PRLL 2 100 100 0 0 0
NWML 3 100 100 0 0 0
GRDL 4 100 100 0 0 0
WAEX 5 100 100 0 0 0
JUDY 24 100 100 0 0 0
WRSY 26 100 100 0 0 0
LPRM 27 100 100 0 0 0
GPML 7 100 100 0 0 0
Central CENT 8 100 100 0 0 0
LPOL 9 100 100 0 0 0
North & East Upstream LIEG 10 100 100 0 0 0
of Bens Lake KIRB 11 100 100 0 0 0
MRTN 6 100 100 0 0 0
SMHI 12 100 100 0 0 0
REDL 13 100 100 0 0 0
COLD 14 100 100 0 0 0
Downstream of NLAT 15 100 100 0 0 0
Bens Lake ELAT 16 100 100 0 0 0
WAIN 23 100 100 0 0 0
Rimbey/Nevis ALEG 17 100 100 0 0 0
Eastern Mainline BLEG 18 100 100 0 0 0
EGAT 19 100 100 0 0 0
MLAT 20 100 100 0 0 0
SLAT 22 100 100 0 0 0
Western Mainline WGAT 21 100 100 0 0 0
HISTORICAL TRANSPORTATION SERVICE AVAILABILITY May 1, 2012 to July 31, 2012 (3 Month Average)
% CD
Restricted(1)
FUTURE FIRM TRANSPORTATION SERVICE AVAILABILITY (MAINLINE RESTRICTIONS)
If your needs for firm transportation service arise after the above dates to “Authorize Firm Transportation Service By”, NGTL will evaluate your new receipt firm transportation service or firm service transfer requests on a date-stamped basis.
Receipt and Delivery Firm Transportation Guidelines
Estimated Firm Transportation Service Availability
Please refer to the following web site for
current FT-R Availability Map:
http://www.transcanada.com/customerexpress/ docs/ab_ftr_availability_map/external_map.pdf
Firm
Transportation Location
Authorize Firm Transportation
Service By
To Ensure Firm Transportation
Service By
Summer construction (generally south of Edmonton)
Winter construction (generally north of Edmonton)
November 2012
November 2012
November 2014
April 2015
Please consult with your Customer Sales Representative to discuss your Firm Transportation Service needs.
20
Please refer to the following web site for
current FT-D Availability Map:
http://www.transcanada.com/customerexpress/ docs/ab_ftd_availabilty_map/mapavailability.p df
HOW TO USE THIS REPORT
21
Overview
This report contains recent historical information on the level of utilization of firm transportation Service Agreements on the NGTL system, relative usage of interruptible service, level of utilization of design pipeline capacity, and the availability of transportation services as an indication of system reliability.
Data is reported either by Pipeline Segment (26 on the system) or Design Area (13 on the system). Maps of both are included in the reference section.
Firm Transportation Service Contract Utilization
The Firm Transportation Service Contract Utilization report shows the percent utilization for each of the 26NGTL pipeline segments and 3 major export delivery points comprising the total system. The utilization data is based on billed monthly volumes. Percent utilization is calculated as firm transportation service and firm transportation service + interruptible service divided by applicable receipt or delivery contract level. Historical Data involving billed volumes lags the current date by approximately two months.
Design Capability Utilization
The load factor/segment flow graphs show actual flow versus design capability values for various NGTL system areas. The graphs also show seasonal (winter/summer) design capability and average load factors for each season. Data used in these reports lags the current date by one month.
Design Flow Capability utilization is a function of several factors that include:
Total market demand for Alberta natural gas.Seasonal changes in market demand for Alberta natural gas.Receipt nominating practices of customers individually and in aggregate to meet that level of demand.Effect of scheduled maintenance on actual flow requirement in a design area at any given time.Design assumptions used in determining required segment flow requirement.
HOW TO USE THIS REPORT - continued
22
Historical Transportation Service Availability
Transportation Service Availability is a system utilization measure that identifies the degree to which firm and interruptible transportation services are available on the NGTL system. It includes the historical frequency of service restriction experienced by the gas transmission network by service type and by pipeline segment.
The data shows the percentage of a given time period that a service type was available for a given section of the system. Service availability less than 100 percent means that some level of transportation service has been restricted for a portion of the time period.
Priority of transportation service on the NGTL system is firm transportation service, and then interruptible (IT). If transportation is restricted within a segment, all service within that segment of a lower priority will be affected.
Service availability is affected by a number of factors including scheduled and unscheduled maintenance, construction or other outages.
As a monthly feature the Historical Transportation Service Availability is shown as a three-month rolling average of transportation availability.
Future Firm Transportation Service Availability
The Future Firm Transportation Service Availability report presents guidelines and timing for all future firm transportation service requests.
23
Calgary
Edmonton
Calgary
Edmonton
NGTL Design Areas
Upper Peace River
Central Peace River
Lower Peace River
Marten Hills
Edson Mainline
Rimbey-Nevis
Eastern Alberta Mainline (James River to Princess)
Western Alberta Mainline
North of Bens Lake
South of Bens Lake
Medicine Hat
South and Alderson
(Last updated Nov 2011)
Calgary
Edmonton
Calgary
Edmonton
NGTL Design Areas
Upper Peace River
Central Peace River
Lower Peace River
Marten Hills
Edson Mainline
Rimbey-Nevis
Eastern Alberta Mainline (James River to Princess)
Western Alberta Mainline
North of Bens Lake
South of Bens Lake
Medicine Hat
South and Alderson
(Last updated Nov 2011)
Eastern Alberta Mainline (PrincessTo Empress/ McNeill)
24
NGTL Pipeline Segments
13. REDL14. COLD
15. NLAT
16. ELAT
17. ALEG
18. BLEG
20. MLAT
23. WAIN
24. JUDY
Calgary
Edmonton
Calgary
Edmonton
3. NWML
1. PRML
2. PRLL
4. GRDL
5. WAEX
26. WRSY
7. GPML
8. CENT
9. LPOL
10. LIEG
11. KIRB
12. SMHI
21. WGAT
22. SLAT
6. MRTN
28. EDM
(Last updated Nov 2011)
Calgary
Edmonton
Calgary
Edmonton
3. NWML
1. PRML
2. PRLL
4. GRDL
5. WAEX
26. WRSY
7. GPML
8. CENT
9. LPOL
10. LIEG
11. KIRB
12. SMHI
21. WGAT
22. SLAT
6. MRTN
28. EDM
(Last updated Nov 2011)
19. EGAT
Design Capability Utilization Actual Flow The amount of gas flowing within or out of our design area. Design Capability The volume of gas that can be transported at various points on the pipeline system considering design assumptions.
AVGLF (Average Load Factor) The ratio between average Actual Flow and Design Capability. It is calculated for every design season (summer/winter) as shown on the graphs.
Intra-Alberta Deliveries The amount of sales gas flowing off the system within an area. Receipt Flow Aggregate of actual receipts within an area and the Actual Flow of the upstream area.
Historical Transportation Service Availability Average % CD Restricted The average percentage of the entire segment receipt contract demand restricted during periods of restriction. Firm Service Available The percentage of time that all requested firm transportation service requests were transported within a segment.
Firm Service Restriction Percentage of time firm service is restricted. IT-2 Service Available The percentage of time that IT-2 service requests were transported.
Max % CD Restricted The maximum percentage to which the entire segment contract demand was restricted.
Other System Load Factor The volume weighted average of the Average Load Factor (AVGLF) of all design areas on the system
DEFINITION OF TERMS
25