Bemusterung Online - BeOn
- supplier self training programme -
Creation and Release of ISIR‘s
to
VOLKSWAGEN AG
- Overview -
Version: 2008-07-24 / K-GQS- 4, K-GQS-1
Version 1.6.2
Page 2
Content
• Self training Programmes
• Objective of the system
• Business Process - Structure
• Process Steps
• Rolls and rights
• Characteristics of the system
• Technical requirements
• News of Version 1.6.2
• Contact details of support
Page 3
This presentation should give you
an overview of the objectives,
the process structure,
the rolls, which are taken part in the process,
the characteristics
and the technical requirements of the online
sampling system BeOn.
Page 4
self training programme
-english-
content
• Self Training Programme
• Aims of the system
• business process structure
• process - steps
• roles and authorisations
• characteristics of the system
• technical requirements
• additions in Release 1.5
• outlook to Version 1.6
• contact details support
-spanish-
-czech
-english-
-spanish-
- czech
-english-
Creation ISIR-german-
-spanish-
- czech
-english-
Additional systems and
Forms-german-
-spanish-
- czech
content
• Self Training Programme
• business process - structure
• additional systems
- supplier information
- supplier data base
- UMS
• Forms
- VDA - cover sheet
- VDA - report
- blanc sheet data import
- part history
- EG Safety Data Sheet
- Declaration of Conformity
• Information via Email
- interim Information
- closure of ISIR
Overview
-german-
basics-german-
content
• Self Training Programme
• Aims of the system
• Login logout of the system
• Homepage
• Working Overview
• Search
• Initial Sample
Inspection Report (ISIR)
• Navigation tree/
page structure
• Icons / buttons
content
• Self Training Programme
• business process - structure
• Create ISIR‘s
- Initialising
- Sender and Recipient
- part data
- safety and environment
- IMDS/MISS part
- Test Results
- Documents
- Overview
• Release of ISIR
• Copying ISIR
• Deleting ISIR
• New ISIR
• Further workflow in Group
Page 5
Objectives of the system
• Same Sampling Process throughout VW Group but paperless
• Up - to - date information
• Permanent overview of status and progress of the sampling
• Electronically exchange of data via internet (supplier) and intranet (VW Group)
• Better usage of ISIR relevant information within the sampling process
• optimisation of process flow
• Allocation of all ISIR relevant Information to one process
• Closer cooperation with supplier
Page 6
Business process - Structure
In Processing
Responsible Engineer
In Creation In Release In Checking
External-Creator
External -authoriser
work preparation
Lab
Metrology
Fit & Function
Authorised signatory
supplier VOLKSWAGEN Groupclo
se
d
Preparation for decision
Computer aided ISIR
-VDA conform -
In Accepting To signing
Initial Sampling
BeOn - Bemusterung online
Completely integrated, IT-supported Process
Of Initial Sampling in system BeOn.
Page 7
Process - Steps - 1/8
Initial Sampling
Entry...
...is first status of creating a new Initial Sample Inspection Report through the supplier data base. The creator enters all data of the part, which is
going to be sampled. VDA and VW specific fields and boxes need to be filled in and attachments added.
All entries can be saved during the creation.
BeOn - Bemusterung online
In Processing
Responsible Engineer
Entry Release In Checking
External-Creator
External -authoriser
work preparation
Lab
Metrology
Fit & Function
Authorised signatory
supplier VOLKSWAGEN Group
clo
se
dPreparation for decision
Computer aided ISIR
-VDA conform -
In Accepting To signing
The process in divided in seven process steps. Every step has a status.
Page 8
Process Steps - 2/8
Release...
...is the status after finishing the Entry. It should be seen as a review and a possibility for correction of the entered data. The reports will be forwarded and released to the VW Group for further investigation. All entries will be
„frozen“ and cannot be changed after the release. The status can be as well changed back into „Creation“
Initial Sampling
BeOn - Bemusterung online
In Processing
Responsible Engineer
Entry Release In Checking
External-Creator
External -authoriser
work preparation
Lab
Metrology
Fit & Function
Authorised signatory
supplier VOLKSWAGEN Group
clo
se
dPreparation for decision
Computer aided ISIR
-VDA conform -
In Accepting To signing
The process in divided in seven process steps. Every step has a status.
Page 9
Process - Steps - 3/8
Checking...
...is given after completion of the release, after the supplier has forwarded the ISIR to VW Group. The ISIR will be checked on accuracy and integrity.
Non-conforming or incomplete ISIRs will be sent back to the supplier. The ISIR will be opened and an ISIR Number will be given.
Initial Sampling
BeOn - Bemusterung online
In Processing
Responsible Engineer
Entry Release In Checking
External-Creator
External -authoriser
work preparation
Lab
Metrology
Fit & Function
Authorised signatory
supplier VOLKSWAGEN Group
clo
se
dPreparation for decision
Computer aided ISIR
-VDA conform -
In Accepting To signing
The process in divided in seven process steps. Every step has a status.
Page 1
0
Process - Steps - 4/8
Status Processing...
...is set, after the check of the ISIR was successful. The responsible SQA engineer can now execute single tests (measurement, laboratory, fit and
function). The responsible SQA engineer decides the Total Note. In consultation with the supplier,
the engineer can change details ( parts data, IMDS a.s.o.) of the ISIR.
Initial Sampling
BeOn - Bemusterung online
In Processing
Responsible Engineer
Entry Release In Checking
External-Creator
External -authoriser
work preparation
Lab
Metrology
Fit & Function
Authorised signatory
supplier VOLKSWAGEN Group
clo
se
dPreparation for decision
Computer aided ISIR
-VDA conform -
In Accepting To signing
The process in divided in seven process steps. Every step has a status.
Page 1
1
Process - Steps - 5/8
Accepting...
...is the status after the responsible SQA engineer has completed the Inspection of the ISIR and the samples. The decision-preparator checks the
ISIR for accuracy and integrity and releases the ISIR for final signature. Incorrect or incomplete ISIRs will be sent
back to the responsible SQA engineer.
Initial Sampling
BeOn - Bemusterung online
In Processing
Responsible Engineer
Entry Release In Checking
External-Creator
External -authoriser
work preparation
Lab
Metrology
Fit & Function
Authorised signatory
supplier VOLKSWAGEN Group
clo
se
dPreparation for decision
Computer aided ISIR
-VDA conform -
In Accepting To signing
The process in divided in seven process steps. Every step has a status.
Page 1
2
Process - Steps - 6/8
Signing...
…is the status after the decision-preparator has checked the ISIR, found it correct and released it for the final signature.
The Sole Authorised Signatory releases the ISIR legally binding and closes with his signature the report.
Initial Sampling
BeOn - Bemusterung online
In Processing
Responsible Engineer
Entry Release In Checking
External-Creator
External -authoriser
work preparation
Lab
Metrology
Fit & Function
Authorised signatory
supplier VOLKSWAGEN Group
clo
se
dPreparation for decision
Computer aided ISIR
-VDA conform -
In Accepting To signing
The process in divided in seven process steps. Every step has a status.
Page 1
3
Process - Steps - 7/8
Closed...
...status is reached after the Sole Authorised Signatory has checked and signed the ISIR. The supplier can now view all the sampling results.
Initial Sampling
BeOn - Bemusterung online
In Processing
Responsible Engineer
Entry Release In Checking
External-Creator
External -authoriser
work preparation
Lab
Metrology
Fit & Function
Authorised signatory
supplier VOLKSWAGEN Group
clo
se
dPreparation for decision
Computer aided ISIR
-VDA conform -
In Accepting To signing
The process in divided in seven process steps. Every step has a status.
Page 1
4
Process - Steps - 8/8
Stopped......is an ISIR, which is cancelled or the responsible SQA engineer has
given as a Total Note „-“ ( no Note)
Initial Sampling
BeOn - Bemusterung online
In Processing
Responsible Engineer
Entry Release In Checking
External-Creator
External -authoriser
work preparation
Lab
Metrology
Fit & Function
Authorised signatory
supplier VOLKSWAGEN Group
clo
se
dPreparation for decision
Computer aided ISIR
-VDA conform -
In Accepting To signing
Page 1
5
Rolls and Rights - 1/2
External Creator (EE):
Enters and changes ISIRs on suppliers side. He / she has got read and write rights in status „Entry“ in the pages Overview, Supplier Data, Parts
Data IMDS/MISS, Safety and Environment,Test Results, Documents and Forms.
All people included in the sampling process,named „rolls“ have assigned tasks.
The rolls EE and VEE will be set by the Company administrator.
Initial Sampling
BeOn - Bemusterung online
In Processing
Responsible Engineer
Entry Release In Checking
External-Creator
External -authoriser
work preparation
Lab
Metrology
Fit & Function
Authorised signatory
supplier VOLKSWAGEN Group
clo
se
dPreparation for decision
Computer aided ISIR
-VDA conform -
In Accepting To signing
Page 1
6
Rolls and Rights - 2/2
Authorised External Signatory (VEE):
Is the only one, who can release ISIRs and send them to the VW Group. The Release is even without the handwritten Signature legally binding. The
authorised external signatory has read and write rights in status „Release“ in the pages Overview, Supplier Data, Parts Data IMDS/MISS, Safety and
Environment, Test Results, Documents and Forms.
Initial Sampling
BeOn - Bemusterung online
In Processing
Responsible Engineer
Entry Release In Checking
External-Creator
External -authoriser
work preparation
Lab
Metrology
Fit & Function
Authorised signatory
supplier VOLKSWAGEN Group
clo
se
dPreparation for decision
Computer aided ISIR
-VDA conform -
In Accepting To signing
All people included in the sampling process,named „rolls“ have assigned tasks.
Page 1
7
Characteristics of the system
• Browser based solution
• High availability and scaleable
• Platform independent Client- Software
• Online help
• Multi lingual
• Intuitive Navigation
• Sampling on the supplier data base
• Printing the reports in VDA - Format
• Upload/ Download of documents and data
• Online availability of the reports after closing
Page 1
8
Technical requirements - 1/2
• MS Internet Explorer 5.5 or higher
• Netscape 6.0 or higher
• Resolution 1024x768 or higher, 800x600 is possible
• Activation of Javascript and Cookies
• Acrobat Reader browser based solution
Page 1
9
Technical requirements - 2/2
• Download of documents from
supplier data base and from
Intranet at Explorer 6.0 just after
Change of settings possible,
therefore follow the link:
• http://support.microsoft.com/default.
aspx?scid=kb;en-us;812935&Product=ie600
• In „Extras“ „Internet options“ please select showed setting
Page 2
0
News of Version 1.6.2
• Sampling of multi variant assemblies
– Parts list (Data import possible) with IMDS / MISS functionalityand attaching of documents for inserts
– New VDA Report attachment „resolution of multi variant assemblies
• Certificate sampling
– Approval check on plant, supplier and partnumber
– Just with accepted IMDS or MISS number
– Positive answer of all mandatory questions (like drawing specifications, mandatory technical approval, technical deviation...) is essential
– Attachment of mandatory documents (BMG, deviation permit)
– Assessment through supplier (dimensional, material / surface)
– New VDA - Report attachment “voluntary commitment / assessment”
Page 2
1
Contact Details Support
Page 2
2
This is the end of the Overview.
We hope that we gave you with our illustrations
an first impression of the
IT- beased ISIR process.
We advice you to go to through
the BASICS manual of the system.