study on the variation of mixing temperature and compaction temperature of bituminous concrete

Embed Size (px)

Citation preview

  • 8/12/2019 study on the variation of mixing temperature and compaction temperature of bituminous concrete

    1/22

    1

    Chapter 1

    1.1IntroductionFlexible pavements are those, which on the whole have low or negligible flexural strength and

    are rather flexible in their structural action under the loads. The flexible pavement layers reflect

    the deformation of the lower layers on to the surface of the layer. Thus if the lower layer of the

    pavement or soil subgrade is undulated, the flexible pavement surface also gets undulated. A

    typical flexible pavement consist of four components.

    Bituminous concrete or Asphalt Concrete is a composite material commonly used in construction

    projects such as road surfaces, parking lots, and airports. Asphalt concrete consists

    of asphalt (used as a binder) mixed with mineral aggregate and then laid down in layers and

    compacted. Asphalt concrete was refined and enhanced to its current state by Belgian inventor

    and U.S. immigrant Edward de Smedt.It is increasingly being used as the core of embankment

    dams.

    It is commonly called simply asphalt, blacktop, or paving (particularly in North America). The

    terms "asphalt (or asphaltic) concrete", "bituminous asphalt concrete", and "bituminous mixture"

    are typically used only in engineering and construction documents and literature. The

    abbreviation "AC" is sometimes used for "asphalt concrete" but can also denote "asphalt content"

    or "asphalt cement", referring to the liquid asphalt portion of a bituminous mixture.

    Asphalt concrete pavements are often called just "asphalt" by laypersons who tend to associate

    the term "concrete" with Portland cement concrete only. The engineering definition of concrete

    is any composite material composed of mineral aggregate glued together with a binder, whether

    that binder is Portland cement, asphalt or even epoxy.

    The aim of this project is to study the variation of mixing temperature & compaction temperature

    of bituminous concrete mix.

  • 8/12/2019 study on the variation of mixing temperature and compaction temperature of bituminous concrete

    2/22

    2

    Chapter 2

    Flexible Pavement

    2.1 Cross Section Of Flexible Pavement

    Surface Course ( Wearing Course)

    Surface course of the pavement structure engineered to accommodate and distribute traffic loads,

    provide skid resistance, minimize disintegrating effects of climate, reduce tire/pavement noise,

    improve surface drainage, and minimize infiltration of surface water into the underlying base,

    sub base and subgrade. Sometimes referred to as the surface layer, the surface course may be

    composed of a single layer, constructed in one or more lifts of the same material, or multiple

    layers of different materials. (See fig.1.2)

    Surface course

  • 8/12/2019 study on the variation of mixing temperature and compaction temperature of bituminous concrete

    3/22

    3

    Base Course

    The base course is the layer of material immediately beneath the surface of binder course and it

    provides additional load distribution and contributes to the sub-surface drainage It may be

    composed of crushed stone, crushed slag, and other untreated or stabilized materials.

    Sub-Base Course

    The sub-base course is the layer of material beneath the base course and the primary functions

    are to provide structural support, improve drainage, and reduce the intrusion of fines from the

    sub-grade in the pavement structure If the base course is open graded, then the sub-base course

    with more fines can serve as a filler between sub-grade and the base course A sub-base course is

    not always needed or used. For example, a pavement constructed over a high quality, stiff sub-

    grade may not need the additional features offered by a sub-base course. In such situations, sub-

    base course may not be provided.

    Sub Grade

    The top soil or sub-grade is a layer of natural soil prepared to receive the stresses from the layers

    above. It is essential that at no time soil sub-grade is overstressed. It should be compacted to the

    desirable density, near the optimum moisture content.

    2.2Bituminous ConcreteBituminous concrete orAsphalt Concreteis a composite material commonly used in

    construction projects such as road surfaces, parking lots, and airports. Asphalt concrete consists

    of asphalt (used as a binder) mixed with mineral aggregate and then laid down in layers and

    compacted. Asphalt concrete was refined and enhanced to its current state by Belgian inventor

    and U.S. immigrant Edward de Smedt.

    It is increasingly being used as the core of embankmentdams.

    It is commonly called simply asphalt, blacktop, or paving(particularly in North America). The

    terms "asphalt (or asphaltic) concrete", "bituminous asphalt concrete", and "bituminous mixture"

    are typically used only in engineering and construction documents and literature. The

    abbreviation "AC" is sometimes used for "asphalt concrete" but can also denote "asphalt content"

    or "asphalt cement", referring to the liquid asphalt portion of a bituminous mixture.

    Asphalt concrete pavements are often called just "asphalt" by laypersons who tend to associate

    the term "concrete" with Portland cement concrete only. The engineering definition of concrete

    is any composite material composed of mineral aggregate glued together with a binder, whether

    that binder is Portland cement, asphalt or even epoxy.

  • 8/12/2019 study on the variation of mixing temperature and compaction temperature of bituminous concrete

    4/22

    4

    Chapter 3

    Types of Mixes

    In the mixing process, the aggregates are first blended, heated, and dried. Then the aggregates

    and the asphalt binder are heated to the mixing temperature. All the equipment used for mixing

    are heated to the mixing temperature. Subsequently, the aggregate and the binder are mixed. For

    this process, the asphalt binder should be fluid enough for uniformmixing. There are two typesof mixes

    1. Hot Mix2. Cold Mix

    3.1 Hot Mix

    Hot Mix Asphalt is produced by heating the asphalt binder to decrease its viscosity, and drying

    the aggregate to remove moisture from it prior to mixing.

    Mixing is generally performed with the aggregate at about 300 F (roughly 150 C) for virgin

    asphalt and 330 F (166 C) for polymer modified asphalt, and the asphalt cement at 200 F

    (95 C).

    Paving and compaction must be performed while the asphalt is sufficiently hot. In many

    countries paving is restricted to summer months because in winter the compacted base will cool

    the asphalt too much before it is able to be packed to the required density. HMAC is the form of

    asphalt concrete most commonly used on high traffic pavements such as those on major

    highways, racetracks and airfields.

    Superpave, short for "superior performing asphalt pavement," is a pavement system designed to

    provide longer lasting roadways. Key components of the system are careful selection of binders

    and aggregates, volumetric proportioning of ingredients, and evaluation of the finished product.

    Hot mix asphalt concrete (commonly abbreviated as HMA) is produced by adding either zeolites,

    waxes, asphalt emulsions, or sometimes even water to the asphalt binder prior to mixing. This

    allows significantly lower mixing and laying temperatures and results in lower consumption of

    fossil fuels, thus releasing less carbon dioxide, aerosols and vapors. Not only are working

    conditions improved, but the lower laying-temperature also leads to more rapid availability of the

    surface for use, which is important for construction sites with critical time schedules. The usage

    of these additives in hot mixed asphalt (above) may afford easier compaction and allow cold

    weather paving or longer hauls.

    3.2 Cold Mix

  • 8/12/2019 study on the variation of mixing temperature and compaction temperature of bituminous concrete

    5/22

    5

    Cold mix asphalt concrete is produced by emulsifying the asphalt in water with (essentially) soap

    prior to mixing with the aggregate. While in its emulsified state the asphalt is less viscous and

    the mixture is easy to work and compact. The emulsion will break after enough water evaporates

    and the cold mix will, ideally, take on the properties of cold HMAC. Cold mix is commonly used

    as a patching material and on lesser trafficked service roads.

    3.3 Types of Temperature3.3.1 Mixing Temperature

    It is the temperature of the asphalt at which it mixed together with the aggregates.

    3.3.2 Compaction Temperature

    It is the temperature at which the mixture of asphalt & aggregates is compacted using a roller.

  • 8/12/2019 study on the variation of mixing temperature and compaction temperature of bituminous concrete

    6/22

    6

    Chapter 4

    Distress in Flexible Pavement

    4.1Bleeding4.1.1 Description

    A film of asphalt binder on the pavement surface. It usually creates a shiny, glass-like

    reflecting surface (as in the first photo) that can become quite sticky. Sometimes referred to

    as flushing.

    4.1.2 Problem

    Loss of skid resistance when wet

    4.1.3 Possible Causes

    Bleeding occurs when asphalt binder fills the aggregate voids during hot weather and

    then expands onto the pavement surface. Since bleeding is not reversible during cold

    weather, asphalt binder will accumulate on the pavement surface over time. This can be

    caused by one or a combination of the following: Excessive asphalt binder in the HMA

    (either due to mix design or manufacturing) Excessive application of asphalt binder

    during BST application (as in the above figures) Low HMA air void content (e.g., not

    enough room for the asphalt to expand into during hot weather)

    4.1.4 Repair

    The following repair measures may eliminate or reduce the asphalt binder film on the

    pavements surface but may not correct the underlying problem that caused the bleeding:

    Minor bleeding can often be corrected by applying coarse sand to blot up the excess asphaltbinder. Major bleeding can be corrected by cutting off excess asphalt with a motor grader

    or removing it with a heater planer. If the resulting surface is excessively rough,

    resurfacing may be necessary (APAI, no date given).

  • 8/12/2019 study on the variation of mixing temperature and compaction temperature of bituminous concrete

    7/22

    7

    Bleeding as a result of overasphalting

    4.2 Block Cracking

    4.2.1 Description

    Interconnected cracks that divide the pavement up into rectangular pieces. Blocks range in

    size from approximately 0.1 m2 (1 ft2) to 9 m2 (100 ft2). Larger blocks are generally

    classified as longitudinal and transverse cracking. Block cracking normally occurs over alarge portion of pavement area but sometimes will occur only in non-traffic areas.

    4.2.2 Problem

    Allows moisture infiltration, roughness.

    4.1.2 Possible Causes

    HMA shrinkage and daily temperature cycling. Typically caused by an inability of asphalt

    binder to expand and contract with temperature cycles because of: Asphalt binder aging Poor

    choice of asphalt binder in the mix design .

    4.1.2 Repair

    Strategies depend upon the severity and extent of the block cracking: Low severity cracks ( 1/2 inch wide and cracks with raveled edges).

    Block cracking on a low volume pavement

  • 8/12/2019 study on the variation of mixing temperature and compaction temperature of bituminous concrete

    8/22

    8

    4.3 Raveling

    4.3.1 Description

    The progressive disintegration of an HMA layer from the surface downward as a result of

    the dislodgement of aggregate particles.

    4.3.2 Problem

    Loose debris on the pavement, roughness, water collecting in the raveled locations resulting

    in vehicle hydroplaning, loss of skid resistance.

    4.3.3 Possible Causes

    Several including:

    Loss of bond between aggregate particles and the asphalt binder as a result of:

    A dust coating on the aggregate particles that forces the asphalt binder to bond with the dust

    rather than the aggregate Segregation. If fine particles are missing from the aggregate matrix,

    then the asphalt binder is only able to bind the remaining coarse particles at their relatively

    few contact points.

    Inadequate compaction during construction. High density is required to develop sufficientcohesion within the HMA. The third figure above shows a road suffering from raveling due

    to inadequate compaction caused by cold weather paving.

    Mechanical dislodging by certain types of traffic (studded tires, snowplow blades or tracked

    vehicles). The first and fourth figures above show raveling most likely caused by snow

    plows.

    4.3.4 Repair

    A raveled pavement should be investigated to determine the root cause of failure. Repair

    strategies generally fall into one of two categories: Small, localized areas of raveling.

  • 8/12/2019 study on the variation of mixing temperature and compaction temperature of bituminous concrete

    9/22

    9

    Remove the raveled pavement and patch. Large raveled areas indicative of general HMA

    failure. Remove the damaged pavement and overlay.

    Raveling due to low density

    4.4 Rutting4.4.1 Description

    Surface depression in the wheelpath. Pavement uplift (shearing) may occur along the sides of

    the rut. Ruts are particularly evident after a rain when they are filled with water. There are

    two basic types of rutting: mix rutting and subgrade rutting. Mix rutting occurs when the

    subgrade does not rut yet the pavement surface exhibits wheelpath depressions as a result of

    compaction/mix design problems. Subgrade rutting occurs when the subgrade exhibits

    wheelpath depressions due to loading. In this case, the pavement settles into the subgrade ruts

    causing surface depressions in the wheelpath.

    4.4.2 ProblemRuts filled with water can cause vehicle hydroplaning, can be hazardous because ruts tend

    to pull a vehicle towards the rut path as it is steered across the rut.

    4.4.3 Possible Causes

    Permanent deformation in any of a pavements layers or subgrade usually caused by

    consolidation or lateral movement of the materials due to traffic loading. Specific causes of

    rutting can be:

  • 8/12/2019 study on the variation of mixing temperature and compaction temperature of bituminous concrete

    10/22

    10

    Insufficient compaction of HMA layers during construction. If it is not compacted

    enough initially, HMA pavement may continue to densify under traffic loads.

    Subgrade rutting (e.g., as a result of inadequate pavement structure)

    Improper mix design or manufacture (e.g., excessively high asphalt content, excessive

    mineral filler, insufficient amount of angular aggregate particles)

    Ruts caused by studded tire wear present the same problem as the ruts described here, but

    they are actually a result of mechanical dislodging due to wear and not pavement

    deformation.

    4.4.4 Repair

    A heavily rutted pavement should be investigated to determine the root cause of failure (e.g.

    insufficient compaction, subgrade rutting, poor mix design or studded tire wear). Slight ruts

    (< 1/3 inch deep) can generally be left untreated. Pavement with deeper ruts should be

    leveled and overlayed.

    Severe mix rutting

  • 8/12/2019 study on the variation of mixing temperature and compaction temperature of bituminous concrete

    11/22

    11

    Chapter 5

    Methodology

    5.1 Materials Used

    5.1.1 Aggregates

    Aggregates are inert granular materials such as sand, gravel, or crushed stone that, along with

    water and portland cement, are an essential ingredient in concrete. For a good concrete mix,

    aggregates need to be clean, hard, strong particles free of absorbed chemicals or coatings of

    clay and other fine materials that could cause the deterioration of concrete. Aggregates,

    which account for 60 to 75 percent of the total volume of concrete, are divided into two

    distinct categories-fine and coarse. Fine aggregates generally consist of natural sand or

    crushed stone with most particles passing through a 3/8-inch (9.5-mm) sieve. Coarse

    aggregates are any particles greater than 0.19 inch (4.75 mm), but generally range between

    3/8 and 1.5 inches (9.5 mm to 37.5 mm) in diameter. Gravels constitute the majority of

    coarse aggregate used in concrete with crushed stone making up most of the remainder.

    5.1.2 Filler

    Fillers are particles added to material (plastics, composite material, concrete) to lower the

    consumption of more expensive binder material or to better some properties of the mixtured

    material. Worldwide more than 53 million tons of fillers with a total sum of approximatelyEUR16 billion are used every year in different application areas, such as paper, plastics,

    rubber, paints, coatings, adhesives and sealants. As such, fillers, produced by more than 700

    companies, rank among the world's major raw materials and are contained in a variety of

    goods for daily consumer needs.

    5.1.3 Bitumen

    Bitumen is a sticky, black and highly viscous liquid or semi-solid form of petroleum. It may

    be found in natural deposits or may be a refined product; it is a substance classed as a pitch.

    Until the 20th century, the term asphaltumwas also used.The primary use of

    asphalt/bitumen is in road construction, where it is used as the glue or binder mixed

    with aggregate particles to create asphalt concrete. Its other main uses are for bituminous

    waterproofing products, including production of roofing felt and for sealing flat roofs.

  • 8/12/2019 study on the variation of mixing temperature and compaction temperature of bituminous concrete

    12/22

    12

    The terms asphaltand bitumenare often used interchangeably to mean both natural and

    manufactured forms of the substance. In American English, asphalt (or asphalt cement) is the

    carefully refined residue from the distillation process of selected crude oils. Outside the

    United States, the product is often called bitumen. Geological terminology often prefers the

    term bitumen. Common usage often refers to various forms of asphalt/bitumen as "tar", such

    as at the La Brea Tar Pits. Another term, mostly archaic, refers to asphalt/bitumen as "pitch".

    5.2Tests On Materials5.2.1Aggregate Impact TestIt has been designed to evaluate the toughness or the resistance of the stone aggregates to

    breaking down under repeated application of impact.

    5.2.2Los Angeles Abrasion Test

    It is done to find the percentage wear due to the relative rubbing action between the

    aggregates and steel balls used as abrasive charge.

    5.2.3Aggregate Crushing Value Test

    It is done to find the strength of coarse aggregates or the resistance to crushing of the coarse

    aggregates under the applied load.

    5.2.4 Penetration TestIt is conducted to classify the bitumen into different grades.

    5.3Mix PreparationFor the purpose of mix preparation following methods are used-

    5.3.1 Hveem Method

  • 8/12/2019 study on the variation of mixing temperature and compaction temperature of bituminous concrete

    13/22

    13

    The basic concepts of the Hveem mix design method were originally developed by Francis

    Hveem when he was a Resident Engineer for the California Division of Highways in the late

    1920s and 1930s.

    The Hveem mix design method consists of three basic steps:

    1. Aggregate selection. Different agencies/owners specify different methods of aggregate

    acceptance. Typically, a battery of aggregate physical test is run periodically on each

    particular aggregate source. Then, for each mix design, gradation and size requirements

    are checked. Normally, aggregate from more than one source is required to meet

    gradation requirements.

    2. Asphalt binder selection. HDOT uses the the Superpave PG System. Hawai'i's common

    asphalt binder grade is a PG 64-16.

    3.

    Optimum asphalt binder content determination. In the Hveem method, this step can

    be broken up into 5 substeps:

    o Prepare multiple initial samples, each at a different asphalt binder content. For

    instance, one sample each might be made at 4.5, 5.0, 5.5, 6.0, 6.5 and 7 percent

    asphalt by dry weight for a total of six samples.

    o Compact these trial mixes in the California Kneading Compactor (see Figures 1

    and 2). This compactor is specific to the Hveem mix design method.

    o

    Test the samples for stability and cohesion using the Hveem stabilometer and

    cohesiometer. These tests are specific to the Hveem mix design method. Passing

    values of stability and cohesion depend upon the mix class being evaluated.

    Typically, all samples pass the cohesion test and three or four pass the stability

    test.

    o Determine the density and other volumetric properties of the samples.

    o Select the optimum asphalt binder content. The asphalt binder content

    corresponding to 4 percent air voids is selected as long as this binder content

    passes stability and cohesion requirements.

  • 8/12/2019 study on the variation of mixing temperature and compaction temperature of bituminous concrete

    14/22

    14

    HDOT's California Kneading Compactor.

  • 8/12/2019 study on the variation of mixing temperature and compaction temperature of bituminous concrete

    15/22

    15

    Chapter 6

    Marshall Method Of Mix Design

    The basic concepts of the Marshall mix design method were originally developed by Bruce

    Marshall of the Mississippi Highway Department around 1939 and then refined by the U.S.Army. Currently, the Marshall method is used in some capacity by about 38 states. The

    Marshall method seeks to select the asphalt binder content at a desired density that satisfies

    minimum stability and range of flow values.

    6.1 Marshall Mix Design Procedure

    The Marshall mix design method consists of 6 basic steps:

    1. Aggregate selection.

    2. Asphalt binder selection.

    3. Sample preparation (including compaction).

    4. Stability determination using the Hveem Stabilometer.

    5. Density and voids calculations.

    6. Optimum asphalt binder content selection.

    6.1.1 Aggregate Selection

    Although Hveem did not specifically develop an aggregate evaluation and selection

    procedure, one is included here because it is integral to any mix design. A

    typical aggregate evaluation for use with either the Hveem or Marshall mix design methods

    includes three basic steps:

    1. Determine aggregate physical properties. This consists of running various tests to

    determine properties such as:o Toughness and abrasion

    o Durability and soundness

    o Cleanliness and deleterious materials

    o Particle shape and surface texture

  • 8/12/2019 study on the variation of mixing temperature and compaction temperature of bituminous concrete

    16/22

    16

    2. Determine other aggregate descriptive physical properties. If the aggregate is

    acceptable according to step #1, additional tests are run to fully characterize

    the aggregate. These tests determine:

    o Gradation and size

    o Specific gravity and absorption

    3.

    Perform blending calculations to achieve the mix design aggregate gradation. Often,

    aggregates from more than one source or stockpile are used to obtain the

    final aggregate gradation used in a mix design. Trial blends of these different gradations

    are usually calculated until an acceptable final mix design gradation is achieved. Typical

    considerations for a trial blend include:

    o All gradation specifications must be met. Typical specifications will require the

    percent retained by weight on particular sieve sizes to be within a certain band.

    o

    The gradation should not be too close to the FHWAs 0.45 power maximum

    density curve. If it is, then the VMA is likely to be too low. Gradation should

    deviate from the FHWAs 0.45 power maximum density curve, especially on the

    2.36 mm (No. 8) sieve.

    Asphalt Binder Evaluation

    The Marshall test does not have a common generic asphalt binder selection and evaluation

    procedure. Each specifying entity uses their own method with modifications to determine the

    appropriate binder and, if any, modifiers. Binder evaluation can be based on local

    experience, previous performance or a set procedure. The most common procedure is

    the Superpave PG binder system. Once the binder is selected, several preliminary tests are

    run to determine the asphalt binders temperature-viscosity relationship.

    Sample Preparation

    The Marshall method, like other mix design methods, uses several trial aggregate-

    asphalt binder blends (typically 5 blends with 3 samples each for a total of 15 specimens),

    each with a different asphalt binder content. Then, by evaluating each trial blends

    performance, an optimum asphalt binder content can be selected. In order for this concept to

    work, the trial blends must contain a range of asphalt contents both above and below the

    optimum asphalt content. Therefore, the first step in sample preparation is to estimate an

  • 8/12/2019 study on the variation of mixing temperature and compaction temperature of bituminous concrete

    17/22

    17

    optimum asphalt content. Trial blend asphalt contents are then determined from this

    estimate.

    Optimum Asphalt Binder Content Estimate

    The Marshall mix design method can use any suitable method for estimatingoptimum asphalt content and usually relies on local procedures or experience.

    Sample Asphalt Binder Contents

    Based on the results of the optimum asphalt binder content estimate, samples are typically

    prepared at 0.5 percent by weight of mix increments, with at least two samples above the

    estimated asphalt binder content and two below.

    Compaction with the Marshall Hammer

    Each sample is then heated to the anticipated compaction temperature and compacted with a

    Marshall hammer, a device that applies pressure to a sample through a tamper foot (Figure

    1). Some hammers are automatic and some are hand operated. Key parameters of the

    compactor are:

    Sample size = 102 mm (4-inch) diameter cylinder 64 mm (2.5 inches) in height

    (corrections can be made for different sample heights)

    Tamper foot = Flat and circular with a diameter of 98.4 mm (3.875 inches) corresponding

    to an area of 76 cm2(11.8 in

    2).

    Compaction pressure = Specified as a 457.2 mm (18 inches) free fall drop distance of a

    hammer assembly with a 4536 g (10 lb.) sliding weight.

    Number of blows = Typically 35, 50 or 75 on each side depending upon anticipated

    traffic loading.

    Simulation method = The tamper foot strikes the sample on the top and covers almost the

    entire sample top area. After a specified number of blows, the sample is turned over and

    the procedure repeated.

  • 8/12/2019 study on the variation of mixing temperature and compaction temperature of bituminous concrete

    18/22

    18

    Marshall drop hammers.

    The standard Marshall method sample preparation procedure is contained in:

    AASHTO T 245: Resistance to Plastic Flow of Bituminous Mixtures Using the Marshall

    Apparatus

    The Marshall Stability and Flow Test

    The Marshall stability and flow test provides the performance prediction measure for the

    Marshall mix design method. The stability portion of the test measures the maximum load

    supported by the test specimen at a loading rate of 50.8 mm/minute (2 inches/minute).

    Basically, the load is increased until it reaches a maximum then when the load just begins to

    decrease, the loading is stopped and the maximum load is recorded.

    During the loading, an attached dial gauge measures the specimens plastic flow as a result of

    the loading (figure below). The flow value is recorded in 0.25 mm (0.01 inch) increments at

    the same time the maximum load is recorded.

  • 8/12/2019 study on the variation of mixing temperature and compaction temperature of bituminous concrete

    19/22

    19

    Marshall stability testing apparatus

    Typical Marshall design stability and flow criteria are shown in Table 1.

    Mix Criteria

    Light Traffic

    (< 104ESALs)

    Medium Traffic

    (104

    106ESALs)

    Heavy Traffic

    (> 106ESALs)

    Min. Max. Min. Max. Min. Max.

    Compaction

    (number of blows on each end

    of the sample)

    35 50 75

    Stability (minimum)2224 N

    (500 lbs.)

    3336 N

    (750 lbs.)

    6672 N

    (1500 lbs.)

    Flow (0.25 mm (0.01 inch)) 8 20 8 18 8 16

  • 8/12/2019 study on the variation of mixing temperature and compaction temperature of bituminous concrete

    20/22

    20

    Percent Air Voids 3 5 3 5 3 5

    Table: Typical Marshall Design Criteria (from Asphalt Institute, 1979)

    One standard Marshall mix design procedure is:

    AASHTO T 245: Resistance to Plastic Flow of Bituminous Mixtures Using Marshall

    Apparatus

    Density and Voids Analysis

    All mix design methods use density and voids to determine basic HMA physical

    characteristics. Two different measures of densities are typically taken:

    1.

    Bulk specific gravity (Gmb).2. Theoretical maximum specific gravity (TMD, Gmm).

    These densities are then used to calculate the volumetric parameters of the HMA. Measured

    void expressions are usually:

    Air voids (Va), sometimes expressed as voids in the total mix (VTM)

    Voids in the mineral aggregate (VMA)

    Voids filled with asphalt (VFA)

    Generally, these values must meet local or State criteria.

    Nominal Maximum

    Particle Size Minimum VMA (percent)

    (mm) (U.S.)

    63 2.5 inch 11

    50 2.0 inch 11.5

    37.5 1.5 inch 12

    25.0 1.0 inch 13

    19.0 0.75 inch 14

  • 8/12/2019 study on the variation of mixing temperature and compaction temperature of bituminous concrete

    21/22

    21

    12.5 0.5 inch 15

    9.5 0.375 inch 16

    4.75 No. 4 sieve 18

    2.36 No. 8 sieve 21

    1.18 No. 16 sieve 23.5

    Table :Typical Marshall Minimum VMA

    (from Asphalt Institute, 1979])

    Selection of Optimum Asphalt Binder Content

    The optimum asphalt binder content is finally selected based on the combined results of

    Marshall stability and flow, density analysis and void analysis (Figure

    3). Optimum asphalt binder content can be arrived at in the following procedure (Roberts et

    al., 1996):

    1. Plot the following graphs:

    o Asphalt binder content vs. density. Density will generally increase with

    increasing asphalt content, reach a maximum, then decrease. Peak density usually

    occurs at a higher asphalt binder content than peak stability.

    o

    Asphalt binder content vs. Marshall stability. This should follow one of twotrends:

    o * Stability increases with increasing asphalt binder content, reaches a peak, then

    decreases.

    o * Stability decreases with increasing asphalt binder content and does not show a

    peak. This curve is common for some recycled HMA mixtures.

    o Asphalt binder content vs. flow.

    o Asphalt binder content vs. air voids. Percent air voids should decrease with

    increasing asphalt binder content.

    o Asphalt binder content vs. VMA. Percent VMA should decrease with

    increasing asphalt binder content, reach a minimum, then increase.

    o Asphalt binder content vs. VFA. Percent VFA increases with

    increasing asphalt binder content.

  • 8/12/2019 study on the variation of mixing temperature and compaction temperature of bituminous concrete

    22/22

    22

    2. Determine the asphalt binder content that corresponds to the specifications median air

    void content (typically this is 4 percent). This is the optimum asphalt binder content.

    3. Determine properties at this optimum asphalt binder content by referring to the

    plots. Compare each of these values against specification values and if all are within

    specification, then the preceding optimum asphalt binder content is

    satisfactory. Otherwise, if any of these properties is outside the specification range the

    mixture should be redesigned.

    Plot: Asphalt binder content vs measured values