Upload
tranhuong
View
216
Download
0
Embed Size (px)
Citation preview
The Speakers
• Olivia Girod
• Seth Wiberg
• Scott Campbell
• Richard Meuret
• Alexandria Moseley
• Adam Strength
Lam Research Confidential Slide - 3 v8
Introduction
▀ Richard Meuret
▀ 1st internship at “Lam Research”
▀ Major: Industrial/Manufacturing Engineering
▀ Entering as a Senior in the fall
Lam Research Confidential Slide - 4 v8
Major Project – (3) Sub-Assembly Lines Background
Potential to increase production capacity is available –Space available for production
A form of continuous production has been an accepted
model previously at Lam Research
Lam Research Confidential Slide - 5 v8
The “Opportunity”
How can we transition from Cell Manufacturing to Continuous Production in Sub Assembly?
Is it even feasible?
(3) Points to Consider
1.) Material/Product mixture feasibility
2.) Workstation feasibility
3.) Spatial Capacity feasibility
Lam Research Confidential Slide - 6 v8
Material/Product Mixture Feasibility Results
How can we route various product through one sub assembly line?
&
What are the similarities between the product/process times?
Multiple similar processes
Very Similar Process times
Lam Research Confidential Slide - 7 v8
Workstation Feasibility Results
Workstations could be designed
highlighting major work
processes between the various
product
After each workstation was established with the amount of workstations needed, footprints for each
workstation were configured.
Lam Research Confidential Slide - 9 v8
Project 3 – Supportive Layout #1
Chamber (Blue): (4) Workstations
Top Plate (Yellow): (3) Workstations
Load Locks (Green): (2) Workstations
Example 1 – (6) Products
Total Idle: 34 hours
Total Assemblers: 9 men
Total TIS: 163 Hours
Cell 1 Cell 5 Cell 8 Cell 2 Cell 3 Cell 4
Sub Assembly
Assembly
Lam Research Confidential Slide - 10 v8
Project 3 – Supportive Layout #2
Chamber (Blue): (2) Workstations
Top Plate (Yellow): (2) Workstations
Load Locks (Green): (2) Workstations
Example 2 – (6) Products
Total Idle: 21 hours
Total Assemblers: 6 men
Total TIS: 156 Hours
Example 2 vs. Example 1
Idle Time: 38% Improvement
Assemblers: 33% Improvement
TIS: 4% Improvement
Given the current average demand of (10) tools per week
This completes all of Sub-assembly components in under (4) days!
Lam Research Confidential Slide - 11 v8
What was learned?
About Lam – Clean-room environments
– Cutting edge Technology/High-tech
– Third largest in the World
• Semi-conductor capital equipment – Stable industry
– Unlimited opportunities
• Intercontinental operations
– World Class Production
About my Working Style – Capable of multi-tasking several projects
– Meet deadlines
– Dedicated and prompt
What would I have done differently? – Less analysis, more data collection
– Less practice for presentations
– Explore more of the geographical area
– Soccer lessons
Background
•Die Prep
• Incoming wafers
• Outgoing die on reels
• Four modules
• ~65 people/ shift
• 4 shifts
• 1 of 3 sites for Intel
• 3 Operations Managers per shift
Captain of the Ship(COS) Role •~60% of my internship
•Single point of contact for factory operations
•Providing direction for task prioritization
• Engineering tool time requests
• Resourcing down tool/s priorities
•Setting up multi-product manufacturing line
• Using Line Management Tool (OMLET)
• Tooling decisions for ~20 different products
COS Duties
•Daily presentations on factory status
• Manufacturing Management
• Engineering
• Technicians/Operators
• Receiving and issuing pass down to outgoing and incoming shifts
• Supporting Lean Manufacturing
• GEMBA Walks
• Leader Standard Work
• Facilitate coordination of pilots for consumables
• Coordinate tape conversions with modules
Project Benefits to Company
•Identified areas of need
•Trained module technician on COS role
• Coverage for OMs
• Improvements to Line Management Tool • Increased efficiency
• Improvements to COS decision making procedures • Decision standardization across shifts
Valuable Learnings
•Variety in semi-conductor field
•Culture differences between campuses
•I enjoyed group work and coordination
•Learned how to not get worked up about issues
•Should have taken advantage of more opportunities within Intel
Interesting Things
•Compressed Work Week
•Large diversity within the company
•Variety of career paths to management
•Complexity of the process
•Prioritization of values
•Intel is Fun! • BBQs/ Picnics
• Volleyball
• 10K
• Workout facilities
• Free fruit, coffee and soda
• Intern wars
• Timbers/ Blazers tickets
INTEL CONFIDENTIAL, FOR INTERNAL USE ONLY
Intel Corporation PC Client Group- Desktop Client Platforms Processor Product Management
Adam Strength
Industrial Engineering with Business Option
Entering Senior year (MECOP schedule)
INTEL CONFIDENTIAL
My Real Job…
• Responsible for testing the quality of In N Out’s in the area on trips to Santa Clara!
• Found this posted all over my cube when I got back
INTEL CONFIDENTIAL
• Assigned the task to create an organized/usable repository for Processor Product Management Training/BKM’s/Tribal knowledge
• Emphasis was process documentation for the team to standardize
training, tool usage, best practices, etc.
• Chose to build a wiki on Intel’s employee network to be used as one central location to document the information.
• Benefits include easily editable, searchable, and secure structure of content.
• The wiki will be owned by my mentor after I leave; the hope is that it will remain a current and useful site for the team.
Project Summary
INTEL CONFIDENTIAL
High Level Learning Intel Corporation • N and M Electronics founded by Gordon Moore and Robert Noyce on
July 18th, 1968. • Nearly 100,000 employees today
Industry • Semiconductors
• My group manages Intel’s product lines amongst upcoming desktop
and server processors
• Worked as the interface between marketing and engineering for product requests, requirements, and capabilities
INTEL CONFIDENTIAL
High Level Learning My Experience • Spent workdays at a desk, attended 6-8 meetings a week
• Multitasking was key in my position- many ongoing and
unrelated tasks to attend to. Communication also very important
• I prefer to have daily/weekly ongoing tasks, while also dividing my time to work on long range projects
• If I could do my internship again, I would have asked for more projects at the beginning. As my time here went on, the group went through some changes and we did not have the time to assign more projects
INTEL CONFIDENTIAL
• Learned how a huge company like Intel functions and the part that my group plays in the big picture
• Experienced the marketing side of things, while remaining closely linked to engineering at Intel
• The internship has given me a great preview of the different fields available to students focused on engineering as well as business
• On my next internship, I hope to experience a technical, Industrial Engineering-focused position so that I can compare it to my Intel experience.
Key Takeaways
INTEL CONFIDENTIAL
• Oregon Interns Program- • Set up events for interns to take part in including: happy hours, game
nights, and Intern Olympics with the Nike interns
• Great Place to Work (GPTW) • Program to ensure that Intel is a great place to work! Fun included:
• Tickets to Blazer games • Tickets to Timbers games • Summer Olympics viewing parties • Intel Great Place to Run (GPTR) 5k/10k • Volunteering at the Umpqua Bank Challenge golf tournament • Discount shopping at Adidas Village • Columbia Sportswear employee store access
• Intel Golf League
• Intel Basketball 3-on-3 League
• Department Quarterlies
• Fun events are planned each quarter to build relationships among organizational units
• My favorite was a river float we flew down to Folsom, CA to take part in!
Fun at Intel
31
System Integration Engineering Department
Scott Campbell MECOP Intern (Junior--Mechanical Engineering) Final Report
Internal
Daimler Trucks North America
Daimler
System Integration Engineering Department 32
Daimler Trucks North America (DTNA)
Daimler Trucks North America
Where is My Department Inside of Daimler?
SIE 34
Daimler AG
Daimler Trucks
Daimler Trucks North America
(DTNA)
Engineering Department
Engineering Services and Vehicle Integration
System Integration
Engineering
Daimler Trucks
Europe/Asia
Daimler Cars
Mercedes Benz etc.
Daimler Trucks North America
Where am I Within DTNA?
Martin
Other VPs
Wilfried
Landon
Mike
Jack Bruce
Brian Arlen
e Barry Michael Karen Craig Peter Scott
Other Managers
Other Directors
SIE 35
Daimler Trucks North America
Where Do I Work?
SIE 37
Mock-up
Center
DTNA Corporate
Headquarters
Swan
Island
Daimler Trucks North America
Project 515 Routing and Clipping
SIE 39
Ask ‘Why?’ 5 Times
Why are our customers unhappy with our product?
Because they experience failures and hassles
with electrical and plumbing systems.
Daimler Trucks North America
Project 515
Because of our inability to manage
routing pathways and excess wiring.
SIE 40
Why are they experiencing failures and hassles with
electrical and plumbing systems?
Because harnesses, power cables, tubes and hoses
are rubbing and wearing through.
Why are harnesses, cables, tubes and hoses wearing through?
Why have we been unable to manage routing pathways and excess wiring?
Because excess wiring and plumbing has been designed into the
system
to account for a lack of pre-defined pathways.
Daimler Trucks North America
Project 515
Department 41
Why do we have a lack of pre-defined pathways?
That’s the problem we are trying to solve!!
This is what we build
today.
This is what we will build
‘tomorrow’.
Daimler Trucks North America
Project 515
My Role In the Project
1. Photograph and document the changes that were necessary to get the P3-113
vehicle to conform to the new bracketing system
SIE 43
Daimler Trucks North America
Project 515
My Role In the Project
1. Photograph and document the changes that were necessary to get the P3-113 vehicle to conform to
the new bracketing system
2. Mock up routing paths to determine a best practice
3. Design and fabricate new brackets as necessary
SIE 44
Daimler Trucks North America
Working at DTNA
The Bad
• Acronyms (IMS, PNDB, EWR, HRIS, 29A, ……. ?!!?)
SIE 47
Daimler Trucks North America
Working at DTNA The Bad
• Acronyms
• IMACS (What century is this?)
SIE 48
Daimler Trucks North America
Working at DTNA
The Bad
• Acronyms
• IMACS (What century is this?)
• Information Flow (sometimes like pulling a loaded truck through a swamp)
SIE 49
Daimler Trucks North America
Working at DTNA The Good
• Commitment to continuous improvement
• Commitment to innovation and industry leadership
• Commitment to employee well being
SIE 50
Bring Your Kid
To Work Day
Daimler Trucks North America
Thank for listening
Questions?
System Integration Engineering Department 51
Advancing Frontline Care TM
Interning at
Welch Allyn
Alexandria Moseley
2nd MECOP Internship
09/13/2012
Advancing Frontline Care TM
I will discuss three main topics
• Welch Allyn Products
• Projects
• Lessons Learned
Advancing Frontline Care TM
Welch Allyn Monitoring Products
Propaq LT
Micropaq
VSM 300
Propaq Encore
Continuous Monitors
Propaq CS
Acuity
CVSM 1500
Spot Check Devices
Advancing Frontline Care TM
I helped plan Highly Accelerated
Stress Screening (HASS) on the CVSM
• 30 minute
HASS
cycle
h t t p : / /www. q ua lmark .c om/p roduc ts / typhoon -30
Advancing Frontline Care TM
I worked in my favorite place in an
organization…
Operations Engineering
Advancing Frontline Care TM
Lessons Learned
• Visual controls can do wonders!
• Hi Tech Industry changes fast.
• Outsourcing is a reality for American
manufacturers.
• Lean is sustained with leadership support.
• Leaders see how their work affects the big
picture.
• When it comes down to it, business is all about
the people.
Visual controls can manage processes
for you. The Hi Tech industry changes
fast.
When it comes down to it,
business is all about the people
Click to edit Master subtitle style
• Warn Industries, Inc. – First Internship
– Mentor: Andrew Skinner
• Senior in Manufacturing and Industrial Engineering this Fall
• Hobbies: Wakeboarding, volleyball, beaver football games, playing with my dogs, hanging out with my family and friends.
Seth Wiberg
62
Click to edit Master subtitle style Overview
• Warn Manufacturing Intern – Work with design engineers to ensure products can be manufactured – Design tooling and fixtures for manufacturing – Develop optimal work procedures
• Work Instructions, Time Study’s, etc.
– Work closely with machine operators on shop floor – Learn to operate particular machines on shop floor to optimize work
flow • Lasers, punch, press brake, tube bender, robotic welders, etc.
• Project List
• Benefits
• Story
• Questions
63
Click to edit Master subtitle style
64
Project List
• Main Projects
– ZeroG Arm*
– Precut Tubing
– TJ,YJ Weld Fixture
– Center Tube Mill
– Fasteners Area
• Minor Projects
– Rear Receiver Wildcat
– BAE Labeling
– TJ Mounting Plate
– 2012 Can Am Renegade 800R Center Plow Mount
– FPM BF750 OE Weld Fixture
– Brace Pivot Weld Fixture
– Facility Layout
Click to edit Master subtitle style
65
ZeroG Arm
Before
• Problems – Operators rotating through the grinding booth
• safety concern • High vibrations
– numbness in arms • No clear training documentation for
proper grinding techniques • Operation taking longer than routings
show
• Initial Assessment – $15,000 initial labor saving
• Moving to pneumatic grinder – Less vibrations – Extended life
• Less rotating of operators
Click to edit Master subtitle style
• Result – 25% labor reduction , Average time saving of 2.53 s
– No need to rotate grinders
– Labor saving average of $7.20 on high volume products
– Part usage per year = 7550
– Safer Work Area
– $52,000 annual saving
– Used time studies to validate routing times
• Elites, TJ, YJ, LG & Mid Frame, JK, Stubby’s
– Wrote work instruction to optimize operator performances
– Gained understanding of the grinding cell and A item products
– Learned how to implement process improvements in manufacturing
• Next Steps! Quote “Work smarter, not harder”
― Carl Barks
ZeroG Arm
67
Click to edit Master subtitle style Lessons and Benefits for me and Warn
• Internship experience was very positive
• Projects were challenging and interesting
• Built on skills I learned at school
• Continuous improvement for me to build on
• Gained experience with in a manufacturing environment
• Gained real life engineering experience ( Tooling and fixture design, process improvement, routing and BOMs, capital cost analysis, RFEAs and ECNs, CAD experiences , Communication, working with other Departments.)
• Total Material and Labor Savings = $ 120,500.00
• Remove safety concerns with process improvement projects
• Had a great Mentor!
• Co-workers were very helpful and deserves a thank you!!!
68
Click to edit Master subtitle style The Evolution of Railroad Standard Gauge
• Standard gauge: 4 Feet, 8 ½ Inches
69
http://www.discoverlivesteam.com/magazine/34/34.html