Upload
vodang
View
216
Download
2
Embed Size (px)
Citation preview
Copyright © 2010 CLP Power Hong Kong Limited.
Strive for Safety Excellence in Contractor Management
CLP Power experience
Strive for Safety Excellence in Contractor Management
CLP Power experience
16 April 201016 April 2010
2 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
ContentsContents1.1. Contracting Works in CLPPContracting Works in CLPP2.2. Our Beliefs, Values and Objectives in Our Beliefs, Values and Objectives in
Contractor SafetyContractor Safety3.3. Safety OrganizationSafety Organization4.4. Our StrategiesOur Strategies5.5. Key ProcessesKey Processes6.6. Achievements & RecognitionsAchievements & Recognitions7.7. Conclusions & Way AheadConclusions & Way Ahead
3 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
1.1. Contracting Works in CLPPContracting Works in CLPP
4 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
Major Contracting WorksMajor Contracting Works
Overhead line installation and maintenance
Substation construction
Cable trenching, laying and jointingSwitchgear and plant installation and maintenance
Minor civil construction Cable tunnel construction
Our contractors are providing services in a wide variety of works including new projects, routine operations and maintenance, and other servicing activities
5 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
• Total contract sum in contracting works in 2009> HK$ 7 billion (new projects, O&M, servicing/minor works)
• Total contractor manpower in 2009 > 5,000 (average no. of workers on site per day)> 300 work sites per day
0100020003000400050006000
'06 '07 '08 '09Contractor Manpower
(average no. of workers on site per day)
Contracting Works in CLPPContracting Works in CLPP
0
2
4
6
8
10
'06 '07 '08 '09Total Contract Sum (in billions of HK$)
Managing our contractors to work safely is therefore an integral part of CLPP’s established Safety Management System
6 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
Contracting Works in CLPPContracting Works in CLPP
• Large varieties of construction activities in CLPP projects
• Large quantities of relatively small and medium size contracting works – insufficient motivation to contractors to invest themselves in safety
• Uneven work volume / distribution of work activities over the year
• Fluctuated work volumes driven by project / budget plan and system outage constraints
• Demand for specialized skills / craftsmanship
• Relatively low safety standard in construction safety due to industry norm and new / inexperienced workers
• Multiple working contractors working in congested work sites that could impose risks to site safety
7 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
2.2. Our Beliefs, Values and Our Beliefs, Values and Objectives in Contractor SafetyObjectives in Contractor Safety
8 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
Mr. Richard Lancaster,Managing Director – CLP Power
One of our important commitments is our commitment to care for people, which is also one of the core values of our Company, and we have a public commitment that says we are aiming for “Zero Incidents”.
Contractors’ CEO ForumDecember 2009
Management MessageManagement Message
9 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
Why Contractor Safety are important?Why Contractor Safety are important?
Increase productivity and savings
Minimize operational interruptions
Minimize legal impacts
Minimize financial losses
Enhance corporate image
Take accountability for “safe operations”
Most important of all…
We CARE for people
Most important of all…
We CARE for peopleOur employees and
contractors’ staff are equally important to
us!
Our employees and contractors’ staff are equally important to
us!
10 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
Our Policy
Foster long term relationship with contractors who demonstrate SHEQ competencies and compliance with other performance requirements
Requiring all contractors to achieve the same level of SHEQ standard when conducting business with CLP Power
– Addressing our vision and expectation for all contractors
Our Beliefs, Values and Objectives in Contractor SafetyOur Beliefs, Values and Objectives in Contractor Safety
11 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
Working safely is a condition of employment
We care about the safety of our contractors and the public
Our Safety Principles
Our Beliefs, Values and Objectives in Contractor SafetyOur Beliefs, Values and Objectives in Contractor Safety
– Stating our beliefs on safety which shall be applied at all times and in all places
12 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
• Same safety standards
• Same measurement KPI on Safety Performance
• Same goals – Zero injuries, Nobody gets hurt
Our Objectives
We provide “real” support to our contractors in achieving these objectives
Our Beliefs, Values and Objectives in Contractor SafetyOur Beliefs, Values and Objectives in Contractor Safety
13 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
3.3. Safety OrganizationSafety Organization
14 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
Safety OrganizationSafety OrganizationManaging Director
Chief Operating Officer
Business Group
Directors
Corporate SHEQ Steering
Committee
BG Level SHEQ Steering
Committee
Department Level SHEQ Committees
Central Safety Team
Departmental Management
Clear Definition of Accountabilities andResponsibilities on Safety• Line managers / location
managers are accountable for the overall safety performance of their employees and contractors
• Safety personnel perform the role of internal advisors who shall provide specialized safety supports to line managers and to bring in advanced safety management concepts and skill into the organization
Driving from the Top to Enhance Safety
15 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
Safety OrganizationSafety Organization
Co-operation & Empowerment of Key Personnel in Contractor Safety
Department Management
Supervisors &Frontliners
ProcurementSpecialists
SafetyAdvisors
Main Contractor
Project Engineers
Nominated Sub-Contractors
Sub- Contractors
Contractor Responsible Officer (CRO)
Trade-based
SHEQ Committees(CLPP + Contractors)
Department
SHEQ Committee
(CLPP)
16 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
4.4. Our StrategiesOur Strategies
17 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
Our StrategiesOur Strategies
Monitoring of Performance
Needs for Contractor Services
Contractor Management• Policies, Principles & Requirements• Commitment & Leadership• Training & Development• Implementation, Promotion &
Enhancement
Selection of Contractors(Partners with Shared Vision)
• Selecting partners with near vision & values
• Alignment of tenderers on safety expectations
• Setting clear vision & objectives• Alignment of leadership & common beliefs• Sharing of knowledge & practices• Same application of systems• Alignment of roles & enhancement of skills• Sharing the pain & glory• Knowing the specifics & sharing our
experiences• Knowing our partners
• Sharing the responsibilities in safety monitoring
Contractor Management ModelContractor Management Model
18 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
Our StrategiesOur StrategiesSetting clear vision & objectives Sharing the pain
& glory
Alignment of leadership & common beliefs
Sharing of knowledge & practices
Same application of systems
Alignment of roles & enhancement of skills
Sharing the responsibilities in safety monitoring
Knowing our partners
Knowing the specifics & sharing our experiences
19 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
Partner is a “chain” which includes CLP, contractors, sub-contractors, and workers.
Our StrategiesOur Strategies
Contractors’ CEO ForumDecember 2009
20 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
Our StrategiesOur Strategies
1. We aim for a truly cooperative relationship (on management of projects, construction and services/minor works) based on mutual trust and benefits
• Eliminate disputes• Reduce contract administrative
efforts• Sharing the same business value
on “Care for People”• Encourage self motivation and
commitments on safety• Synergy effect on individual’s
management strength and expertise
21 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
Our StrategiesOur Strategies
2. Consolidate numerous works into bulk contracts or outline agreements
3. Incentives and regular two-way feedback communications on partners’ performance (Contractor Performance Management System, Supplier Assessment System, partnering forums etc.)
22 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
5.5. Key ProcessesKey Processes
23 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
Project planning include critical consideration on:• Realistic timing and duration, set aside buffer for critical process such as public
consultation, acquisition of lands and wayleave, statutory approvals• Resources availability• Contingency on cost fluctuation• Shortage of labour force on specialized skills are supplemented by imported
labour e.g. cable jointers, linesmen, high pressure welders
Risk assessment / mitigation is conducted for every project including:• Specific site environment and condition• Neighboring / surrounding hazards• Site access• Construction Management Plan / specific site program in addressing the
known risks
Key Process Key Process –– Project PlanningProject Planning
24 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
Key Process Key Process –– Selection of ContractorsSelection of Contractors
Contractor selection is the key in the tendering process for each and every project:• Select only capable contractors for contracting works in CLPP• Establish long term contracts with good performers• Pre-tender qualification and evaluations, including pre-tender site checks,
job references, interviews etc.• Tender evaluation does not necessarily rely on the lowest tendered price,
but instead very strong emphasis is placed on safety
25 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
Key Process Key Process –– Design for SafetyDesign for Safety
Standard Design Protocol in place forincorporating Safety consideration:• Partnering workgroups are in place with
consultants/contractors for discussing and resolving safety issues through joint efforts e.g. Technical Development Working Committee
• Additional risk assessments are required for specific projects with site constraints e.g. construction works in operating plants and facilities
• Constructability studies and risk avoidance/mitigation workshops with design consultants/contractors are organized e.g. slope/foundation stabilization and super typhoon projects for OHL towers
• Construction & Design Management (CDM) are currently adopted for design of new civil projects and gradually extending to other projects
26 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
Safety tools are derived with training provided for implementation by all contractors:• Safe Systems of Work
• Job Safety Analysis
• Written Safe Work Procedures
• Pre-work Risk Assessment
• Behavioural-based Safety
Key Process Key Process –– Safety ToolsSafety Tools
27 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
Contractors’ CEO Forums• Contractors’ senior executives meet
periodically to exchange safety commitments and strategies for excellence in safety management
• Contractors are encouraged to implement the same high safety standards consistently in projects with their other clients
Key Process Key Process –– Alignment of Safety ValuesAlignment of Safety Values
Safety Leadership Training for Contractor Management• Offered to contractor management to strengthen
and align their safety beliefs, values and accountability (ownership) as a leader for driving safety in their organizations
• Similar trainings are provided for new contractors
28 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
Management Visits• CLPP senior management pay periodic caring visits
to contractors’ worksites
• Objective of reinforcing management commitment to safety and CLPP’s expectations for a safe work environment
• Take every opportunity in coaching contractors’ management for stronger commitment in safety
Key Process Key Process –– Alignment of Safety ValuesAlignment of Safety Values
29 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
Regular briefing and communication workshops organized for Clerks of Works / Independent Safety Inspectors
Refresher training for registered contractor site supervisors
Contract Responsible Officers’ Forums• Sharing of experiences and best practices on contractor management for CROs• Alignment in roles and responsibilities for effective contractor management
Key Process Key Process –– Enhancing Responsibilities and Enhancing Responsibilities and CompetencyCompetency
30 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
Frontline employees and site supervisors are delegated with clear responsibilities for monitoring contractors’ safety
Site personnel are empowered to issue instruction for rectifying safety irregularities and non-compliance
Stop work instructions shall be issued to contractors whenever necessary for the sake of their safety
Key Process Key Process –– Enhancing Responsibilities and Enhancing Responsibilities and EmpowermentEmpowerment
31 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
Key Process Key Process –– Knowledge SharingKnowledge SharingSharing of safety knowledge and best practices amongst contractors and CLPP through• Trade-based contractor forums• Sharing notes and alerts• Safety documents and handbooks• Contractors’ seminars• Induction training / Competent Person
and Authorized Person trainings
Safety Resources Centre• Provision of additional learning resources and
technical support to our contractors• Safety resources include educational materials
(booklets, videos), training, talks, and forums etc.• Provision of specific themes talks and displays
32 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
CLP Power introduced a number of enhancement initiatives for raisingthe safety standards on site• Contractor Site Supervisors Registration Scheme
• Safety Leaders / Champions
• Taskforce on Participation Model
• Safety Climate Survey
Key Process Key Process –– Safety Enhancement InitiativesSafety Enhancement Initiatives
33 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
Key Process Key Process –– Motivation and PromotionMotivation and Promotion
Contractors Safety
Management Efforts
Contractors Safety
Management Process
Contractors Safety
Performance
Recognition on Contractor’s safety efforts
Incentive payment on contractors’ safety performance
Input Output
34 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
Key Process Key Process –– Motivation and PromotionMotivation and Promotion
Awards for Good Performers• Best sub-contractors• Best site supervisors
Contractor SHE Quiz• Organize Contractor SHE Quiz and provide
IT platform to encourage contractors’ active participation
• 20 companies participated in 2009
5S Good Housekeeping• Encourage contractors to adopt 5S good
housekeeping practice on site• Adopt Construction Management Plan for planning
and implementation of good housekeeping arrangements for major construction projects
35 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
CROs accountable for ensuring contracting works implemented in accordance with pre-agreed specifications by means of auditing and regular site checks
Key Process Key Process –– Performance MonitoringPerformance Monitoring
Contractor Performance Management System (CPMS) – Contract-based• Structured assessment on contractors’ performance based on line users’ feedback• Safety implementation being a key element in the periodic assessment• Significant influence on contractors’ credibility for assignment of current jobs and bidding
for future contracts
Suppliers Assessment System (SAS) – Contractor-based• Built upon the existing CPMS, the SAS is implemented for consolidation and evaluation
of the overall safety performance by individual contractors under different contracts• Serves as a platform for ranking the overall performance status of the individual
contractors in determining their qualification for future tendering opportunities
Relationship Meetings• Regular meetings between CLP Directors and Contractor Executives
36 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
Safety Audits• Regular safety audits conducted by internal audit
teams for monitoring of actual site compliance and practices
• Opportunity taken during visits to communicate and coach on safety requirements on site
Key Process Key Process –– Performance MonitoringPerformance Monitoring
37 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
Predictive (Leading) Indicators in addition to Lagging Indicators• Leading indicators are used to measure safety efforts inputted by contractors
• Supplement to reactive indicators such as accident rates
• Boosting employees’ participation and management’s involvement in safety
Key Process Key Process –– Performance MonitoringPerformance Monitoring
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
1.8
2
Quality of Toolbox Talks
Quality of PWRA
Housekeeping Standard
No. of Observations per ExposedEmployee
No. of Management Involvement perExposed Employee
No. of PWRA per Exposed Employees
Provisional Targets
Performance in Aug '09
Performance in Sep '09
Housekeeping Standard
0
1
2
3
4
5
May-07
Jun-0
7Ju
l-07
Aug-07
Sep-07
Oct-07
Nov-07
Dec-07
Jan-0
8Fe
b-08
Mar-08
Apr-08
May-08
Jun-0
8Ju
l-08
Aug-08
Sep-08
Oct-08
Nov-08
Dec-08
Jan-0
9Fe
b-09
Mar-09
Apr-09
May-09
Jun-0
9Ju
l-09
Aug-09
No.
of I
ncid
ents
0
20
40
60
80
100
Hou
seke
epin
g St
anda
rd
No. of Incidents Housekeeping Standard Acceptable Level
38 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
6.6. Achievements & RecognitionsAchievements & Recognitions
39 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
ContractorsContractors’’ Safety PerformanceSafety Performance
• CLPP measures contractors’ safety performance for assessing the effectiveness of current control programs
• CLPP’s performance compares favourably with those in the construction industry
CLPP Contractor DIIRin 2009 = 1.7i.e. < 2 injury per 1,000 workers involved in the loss of > 1 working day in 2009 (CLPP employees = 0.2)
51.7
44.6
37.4
31.3 31.5 30.6 31.529.3
27.2
1.0
11.2
6.5 6.6 5.2 4.52.0
55.1
0.52.9 0.71.31.82.43.43.14.43.9
1.72.30.5
3.32.7
0
10
20
30
40
50
60
'99 '00 '01 '02 '03 '04 '05 '06 '07 '08 '09
Acci
dent
Rat
e
HK Industrial Accident RateCLPP Contractor Accident RateCLPP Contractor DIIR
CLPP Accident Rate - per 1,000 workers(Each accident involved in the loss of more than 3 working days )
Hong Kong Industrial Accident Rate - per 1,000 workers(Each accident involved in the loss of more than 3 working days )
Notes:
CLPP DIIR (Disabling Injury Incidence Rate) - per 1,000 workers(Each accident involved in the loss of more than 1 working day or any bone fracture)
40 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
External Achievements/RecognitionsExternal Achievements/Recognitions
External Awards• CLPP encourages contractors to share their
experiences with the industry• 23 honours attained by our contractors in
2008/09 external awards for CLPP projects:−
Construction Industry Safety Award Scheme−
Considerate Contractors Site Award Scheme−
Hong Kong Occupational Safety & Health Award
41 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
Recognition from Our ContractorsRecognition from Our Contractors
Mr. Gary Ko, Chief Operating Officer,Kum Shing (K.F.) Construction Co. Ltd.
CLP is our major client. We have common values, and we both take safety seriously.
July 2007
42 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
Recognition from Our ContractorsRecognition from Our Contractors
Mr. C.K. Wong, Senior Construction Manager,Hip Hing Construction Co. Ltd.
Hip Hing and CLP have a common objective to achieve “Zero incidents” as our goal.
43 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
Recognition from Our ContractorsRecognition from Our Contractors
Mr. Patrick Lo, Contracts Manager,Shui On Building Contractors Ltd.
Throughout these years, CLP, Shui On and our sub-contractors have established a partnering relationship.
44 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
Recognition from Our ContractorsRecognition from Our Contractors
Mr. Humphrey Ling, Vice President,Siemens Ltd.
“Care for People” is CLP’s value in promoting safety culture, which is also Siemens’ core value.
45 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
7.7. The Way Ahead & The Way Ahead & ConclusionConclusion
46 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
The Way AheadThe Way Ahead
• Strengthen existing systems on contractor management to strive for world class standard and continuous improvement
• Take every efforts and opportunities to educate and motivate our contractors for achieving safety excellence in safety
• Evaluate foreseeable shrinking labour force in specific job trades in local market and evaluate possible solutions in addressing the issues
• Joint hands with key contractors and other organizations in steering and influencing the industry for higher safety standard
47 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
ConclusionsConclusions
• We see contractors as part of our CLP family
• We move away from “Master and Slave” to partnership arrangement for safety enhancement
• We foster long-term relationship with the good performers
• We believe that all injuries can be prevented – we adopt zero tolerance for any unsafe practices and place continuous efforts on incident prevention
• We encourage our contractors to adopt the same safety standard for all their clients
• Our ultimate goal – “Zero Injuries”
48 16 April 2010Copyright © 2010 CLP Power Hong Kong Limited.
Thank youThank you