Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
Masahiro IMBE
Association for Rainwater Storage and Infiltration Technology (ARSIT)
ARSIT
Regional Workshop on
Eco-Efficient Water Infrastructuretowards Sustainable Urban Development and Green Economy in Asia and the Pacific
12-13 December 2013Bangkok, Thailand
Stormwater Treatment from the Road in Japan
Today’s Presentation
1
ARSIT
1. Background
2. Typical Examples
3. Experimental Study
4. Experimental Results
5. Issues and Scope
◎ Well-balanced Hydrological System● Applied for a unit of River Basin
● Well-balanced among Flood Control, Water Use
and Aqua-environment
● Promotion of Rainwater Storage and Infiltration
Facilities and Rainwater Utilization
◎ Low Impact Development = LID【USA】
◎ Sustainable Urban Drainage Systems = SUDS【UK】◎ Decentralized Urban Design = DUD【Germany】◎ Water Sensitive Urban Design =WSUD【Australia】
● Applied for Specified Area, Community or Development Area● Well-balanced among Water Quantity, Quality, and Amenity● Source Control/Green Infrastructure = GI
Japan
WesternCountries
Country-specific Approaches for Sound Water Cycle
ARSIT
1. Background
4
2
ARSIT
1. Background
12.50%
2.50%
12.50%
10.00%
12.50%
42.50%
7.50%
30万人以上
20万人以上
10万人以上
5万人以上
3万人以上
1万人以上
1万人以下
Size of Population
Percentage of Cities in Japan by Size of Population where the Localized Torrential Rain (≧100mm/hr) occurred in the past
≧300,000
≧200,000
≧100,000
≧ 50,000
≧ 30,000
≧ 10,000
< 10,000
Almost 30 %
5
ARSIT
1. Background
Runoff % correspond to Land Utilization in Tokyo(assuming the precipitation to be 100mm for 1 hour)
Road23 %
Commerce & Industry
16 %
Housing Complex 15 %
IndependenceHouse 20 %
Water Surface 17 %
School6 %
3
5
Flood Control Plan for Kanda River located in Central TokyoLarge scale private facilities:600m3/ha
Existing or newly constructedprivate facilities: 300m3/ha
Public facilities(Sidewalk):200m3/ha
Public facilities(Roadway):290m3/ha
Public facilities(Building, Park):600m3/ha
No measure
Required Storage Volume determined by Tokyo Metropolitan GovernmentBasic Principal : 10mm/hr for basin wide allotment
where, 75mm/hr for total measure
ARSIT
1. Background
6
ARSIT
1. Background
1. The big tree is symbolic. Street trees provide shaded areas.
2. Coloration technique on the road surface is effective for the thermal insulation.
3. The conventional drainage system should not be applied. The rainwater is stored around the road and infiltrated. So this kind of drainage is called “Road of River” in our group.
Cooling of Road Environment against Heat Island
Road of River
7
ARSIT
1. BackgroundThe image of “Road of River”
Sidewalk Roadway
River
Roadway
Surface : Permeable
Structure of Road Bed :Inclined gravel void storage
Sidewalk
The wet vegetation ditch under the sidewalk
connected to the inclined gravel void storage under
the roadway
1. Purification by contact oxidation of gravel void storage2. Huge volume of storage3. The conventional drainage system is not necessary.
ARSIT
2. Typical Examples2.1 Street Permeable Box
Street Permeable Box
8
9
Various Buckets for Removal
ARSIT
2. Typical Examples 2.1 Street Permeable Box
Bucket for Removal Plastic Filter Bucket Filter
Inlet
10
Inlet Filter and Bottom Filter
ARSIT
2. Typical Examples2.1 Street Permeable Box
Pipe
Inlet Filter Fitting
The inlet filter is attached to the pipe insertedto the permeable trench which is connected to the permeable inlet.
Hook Sedimentation and Rubbish
11
Sewer
Permeable Box
Inlet
Void Storage and Infiltration
ARSIT
2. Typical Examples2.2 Combination of Permeable Box and Void Storage
Perforated Pipe
12
ARSIT
2. Typical Examples2.3 Rainwater Storage and Infiltration beside Road
(implemented in Mitaka city)
Inlet
Permeable SheetSewer
Rainwater Storage and Infiltration Tank
Inspection Manhole
12
Road
Permeable Pavement along Sidewalk
Permeable Pavement along Sidewalk
Sidewalk
PermeableAsphalt Concrete
Crusher-run
ARSIT
2. Typical Examples2.4 Permeable Pavement along Sidewalk
13Permeable Pavement along Sidewalk at Tsukuba
Photo taken on Aug.8 in 2012
ARSIT
2. Typical Examples2.4 Permeable Pavement along Sidewalk
14
ARSIT
2. Typical Examples2.5 EGSM Construction Method
Grating
ExistingConnection
Box
Filter
Road
Permeable Cylinder
SewerWater Area
Adjacent Land
EGSM:EasyGroundSpeedMachine
Attached Pipe
Sludge Pit
PermeableStructure
Permeable Sheet
Crushed Stone
15
ARSIT
2. Typical Examples2.5 EGSM Construction Method
Filter is attached in the connection box.
Connection Box
Permeable pipe is installed under the bottom of the connection box.
Permeable Pipe
Filtering Cap
16
ARSIT
2. Typical Examples2.5 EGSM Construction Method
Borehole Machine to install the permeable pipe
19
ARSIT
2. Typical Examples2.6 Utilization of Underpass no longer Required
(implemented in Gifu city)
Inflow from street gutter
Floating Intake
1.Watering for plant2 times/week, 20 min./day : 0.64 m3/week
2.Infiltration into ground3.Reduction of temperature on road surface
Pump
Pump
Filter
Pump
Water depth≧25cm : Watering for plantWater depth≧60cm : Drain to street gutterWater depth = 50cm : Stop pumping
Drain to street gutter0.3 m3/min.
WateringSensor
Storage for wateringon road surface
17
Birds-eye View Cross Section
Image of New Drainage System applied for Road
ARSIT
2. Typical Examples2.7 Roadway Trench
Rain Cyclical Road Surface Drainage System : RACSUS
18
Experimental facility Observed data in rainfall and runoff
Time (Oct.19-20, 2004)
Rainfall Intensity(mm/30min.)
Infiltration Intensity(mm/30min.)
Runoff Height(mm/30min.)
(mm/30min.)
ARSIT
2. Typical Examples2.7 Roadway Trench
20
25
Evaporation
Sidewalk (Interlocking)
Capillary Pillars (Diatom Earth)
Storage TankCrushed Stone
Subgrade
Inlet
Overflow
Permeable Ditch
Image of PRaCS
Pavement of Rainwater Cyclical System (PRaCS)ARSIT
3. Experimental Study
Supporting Platform Capillary Pillarinside Storage Tank
26
ARSIT
3. Experimental Study
30
ARSIT
4.Experimental Results
0
5
10
15
20
25
30
35
40
0
10
20
30
40
50
60
70
80
日雨量(mm)
温度(℃)
月 日
北本市の平成23年8月の日雨量と日最大温度
日雨量 プララックス表面温度 アスファルト表面温度 外気温
14℃
アスファルト舗装に較べプラック
スの表面温度は、最大で約14℃低下している
The surface temperature of PRaCSis cooler in max.14℃ than that ofthe ordinary asphalt pavement.
Ordinary Asphalt Pavement
Surface Temperature of PRaCS
Air Temperature
Tem
pera
ture
Daily
Rain
fall
Aug. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Date
Change in surface temperature of PRaCS
in 2011
Daily Rainfall
32
ARSIT
5. Issues and Scope
The followings are issues and scope to be solved for the future.
1. First flash containing non-point source should be cleared up.
2. The system should be cleaned regularly to remove the rubbish and leaves and so on.
3. Cleaning system should be operated easily and economically.
4. The coalition with the road administrator is necessary for both construction and maintenance.
5. The easy reconstruction method for the infiltration should be developed.
6. The sound water cycle related to flood control, water utilization and improvement of water quality should be considered.
Thank you for your attention
ARSIT
33ARSIT Home Page: http://www.arsit.or.jp