  • Bid No. W1233208C1

    BROWARD COUNTY

    Lyons Road Sidewalk Project

    DRAWINGS

    HIGHWAY CONSTRUCTION AND ENGINEERING DIVISION

    Lyons Road Sidewalk Project

  • SECTION 009500: DRAWINGS INDEX

    Contract plans

    Sheet No. Sheet Description

    1 Key Sheet

    2 Summary of Pay Items

    3 Summary of Quantities

    4 General Notes

    5 -12 Roadway Plans

    13 Special Details

    14 25 Cross Sections

    26 30 Signing and pavement markings

  • N

    0 1 2

    Miles

    HIGHWAY CONSTRUCTION & ENGINEERING DIVISION

    CONTRACT PLANS

    COMPONENTS OF CONTRACT PLANS SET

    KEY SHEET OF EACH COMPONENT

    A DETAILED INDEX APPEARS ON THE

    LINEAR FEET MILES

    EXCEPTIONS

    3,965.00

    3,965.00

    GROSS LENGTH OF PROJECT

    NET LENGTH OF PROJECT

    ROADWAY

    0.75

    BRIDGES

    3,965.00

    0.75

    HAVE CHANGED DUE TO REPRODUCTION.

    NOTE: THE SCALE OF THESE PLANS MAY

    TO BE SUBMITTED TO:

    NO.

    SHEET

    YEAR

    FISCAL

    DESCRIPTIONDATE

    ROADWAY SHOP DRAWINGS

    ROADWAY PLANS

    11:26:26 AM G:\Lyons Road Sidewalk\DESIGN YEAR 2012\MicroStation Files\Roadway\KEYSRD01.DGNabustamante 3/19/2014

    LENGTH OF PROJECT

    01 13

    INDEX OF ROADWAY PLANS

    KEY SHEET REVISIONS

    T 4

    9 S

    Turnpike

    Turnpike

    R 42 E

    STA. 9+95.00

    BEGIN PROJECT

    STA. 49+60

    END PROJECT

    PROJECT MANAGER: MICHAEL HAMMOND, P.E.

    LOCATION

    PROJECT

    PLANS PREPARED BY: CAROLINA BUSTAMANTE, P.E.

    LYONS ROAD SIDEWALK

    BROWARD COUNTY

    PUBLIC WORKS DEPARTMENT

    PLANTATION, FL 33324

    ONE N. UNIVERSITY DRIVE, BOX B300

    HIGHWAY CONSTRUCTION & ENGINEERING DIVISION

    BROWARD COUNTY PUBLIC WORKS

    COUNTY PROJECT NO. 5412

    following web site:

    For Design Standards click on the "Design Standards" link at the

    click on the "Specifications" link at the following web site:

    For the Standard Specifications for Road and Bridge Construction

    GOVERNING STANDARDS AND SPECIFICATIONS:

    http://www.dot.state.fl.us/rddesign/

    http://www.dot.state.fl.us/specificationsoffice/

    Contract Documents.

    Specifications for Road and Bridge Construction, as amended by

    revised Index Drawings as appended herein, and 2013 Standard

    Florida Department of Transportation, 2013 Design Standards and

    PROJECT LENGTH IS BASED ON OF CONSTRU

    FORT WALTON

    BEE LINEEXPRESSWAY

    FLO

    RID

    A S

    TU

    RNPIK

    E

    10

    BEACH

    PANAMACITY

    CHIPLEY

    TALLAHASSEE

    75

    10

    295

    95

    JACKSONVILLE

    ST AUGUSTINE

    GAINESVILLE

    OCALA DAYTONA BEACH

    DELAND4

    NEW PORT RICHEY

    TAMPA

    754

    LAKELAND

    MELBOURNE -COCOA

    ORLANDO

    BARTOWST PETERSBURG

    275

    SARASOTA -

    BRADENTON

    75

    95

    FT PIERCE

    FT MYERS

    WEST PALM

    BEACH

    FT LAUDERDALE

    MIAMI

    75

    75

    NAPLES

    KEY WEST

    CITY

    LAKE PENSACOLA

    ENGINEER OF RECORD:

    P.E. NO.:

    PLANTATION, FL 33324

    ONE N. UNIVERSITY DRIVE, BOX B300

    HIGHWAY CONSTRUCTION & ENGINEERING DIVISION

    BROWARD COUNTY PUBLIC WORKS

    MICHAEL HAMMOND, P.E.

    MICHAEL HAMMOND, P.E.

    SIGNING AND PAVEMENT MARKINGS26 - 30

    CROSS SECTIONS14 - 25

    SPECIAL DETAILS13

    ROADWAY PLAN5 - 12

    GENERAL NOTES4

    SUMMARY OF QUANTITIES3

    SUMMARY OF PAY ITEMS2

    KEY SHEET1

    SHEET DESCRIPTION SHEET NO.

    ROADWAY PLANS

    49534

    (FEDERAL FUNDS)

    PROJECT FM#: 427960-1-58-01

    912

    811

    10

    4

    34

    33

    11

    23

    27

    22

    21

    811A

    811A

    P

    CORAL SPRINGS

    MARGATE

    COCONUT

    CREEK

    LAUDERDALE

    LAUDERHILL

    LAUDERDALELAKES

    OAKLAND PARK

    Pop.

    Pop.

    Pop.

    Pop.

    Pop.

    36,044

    6,288

    18,479

    37,271

    21,939

    ServiceArea #1

    University

    Drive

    Sample Rd.

    Pompano BeachInterchange #24

    Ft. Lauderdale NorthInterchange #20

    Royal

    PalmBoulev

    ard

    NORTH

    D.A.

    D.A.S. POMPANOBEACH

    Est.Pop.

    Est.Pop.

    34,500

    23,800

    FORT LAUDERDALE

    ProspectRoad

    POMPANO BEACH

    EXECUTIVE AIRPORT

    NORTH

    HAWKINS

    Pop.

    816

    870

    817

    834 834

    816

    845

    1817

    AtlanticBlvd.Ext.

    28

    POMPANO BCH.

    (Part of)

    POMPANOBEACH

    11

    Cypress Cr. Canal

    River Canal

    S-37B

    S-36

    Middle

    C-14

    2413

    2413

    86028

    8613086130

    86039

    86070

    86090

    86170

    2413

    2413

    2412

    2497Cyprsess Creek Rd 86009

    2504

    86065

    86065

    2510

    86580

    86580

    2503

    2501

    2901

    25342516

    2501

    2507MAINTENANCE

    2549

    2584

    2102

    2504

    2506

    2510

    2512

    2514

    2507

    2509

    2507

    county map

    2511

    2540

    86220

    (86014)86504

    26032602

    86100

  • 3/19/2014abustamante G:\Lyons Road Sidewalk\DESIGN YEAR 2012\MicroStation Files\Roadway\CESSRD01.DGN11:26:32 AM

    02

    DATE DESCRIPTION

    REVISIONS

    NO.

    SHEET

    SUMMARY OF PAY ITEMS COUNTY PROJECT NO.COUNTY ROAD

    HIGHWAY CONSTRUCTION AND ENGINEERING DIVISION

    PUBLIC WORKS DEPARTMENT

    PLANTATION, FL 33324

    1 NORTH UNIVERSITY DRIVE

    AND ENGINEERING DIVISION

    BROWARD COUNTY HWY. CONSTRUCTION

    LICENSE NO. 49534

    MICHAEL HAMMOND, P.E.

    ENGINEER OF RECORD

    BR WARDCOUNTY

    F L O R I D A LYONS ROAD 5412

    MATERIAL REQUIREMENTS.

    COST OF THE APPROPRIATELY LABELED PULL BOX LID. SEE BCTED WEBSITE FOR

    GROUNDING TO FIT THE NEW PULL BOX ELEVATION AND LOCATION. ALSO INCLUDES

    AND/OR ADDITIONS NECESSARY TO EXISTING CONDUITS, CONDUCTORS, AND

    715-14-12 INCLUDES COST OF NEW PULL BOX INSTALLATION AND ANY/ALL ADJUSTMENTS

    ALL GUARDRAIL RUNS.

    536-1-1 INCLUDES COST OF INSTALLATION OF SPECIAL GUARDRAIL POSTS/HARDWARE FOR

    SPECIAL POST INSTALLATION (SEE DETAIL, SHEET 13).

    522-2 INCLUDES COST OF THICKENED EDGE SIDEWALK REQUIRED FOR GUARDRAIL

    INLET TOP. NEW TOP TO BE ADJUSTED TO MATCH SIDEWALK ELEVATION.

    425-13-55 INCLUDES ALL WORK INVOLVED IN THE REMOVAL AND REPLACEMENT OF EXISTING

    INLET TOP. NEW TOP TO BE ADJUSTED TO MATCH SIDEWALK ELEVATION.

    425-13-25 INCLUDES ALL WORK INVOLVED IN THE REMOVAL AND REPLACEMENT OF EXISTING

    MESH AND GEOTEXTILE FABRIC IS INCLUDED IN THIS PAY ITEM.

    FACE TEXTURE, FINISH, JOINT SEAL, DRAIN PIPES, DRAINAGE LAYER, GALVANIZED

    FIELD CONDITIONS. SEE INDEX 6011 FOR WALL DETAILS. ALL REINFORCING STEEL,

    400-0-11 QUANTITY MAY BE INCREASED OR DECREASED BY ENGINEER TO MATCH EXISTING

    PAY ITEMS NOTES

    SUMMARY OF ROADWAY QUANTITIES

    PAY ITEM ITEM DESCRIPTION UNIT QUANTITYQUANTITY

    TOTAL

    0101 1 Mobilization LS 1

    0102 1 Maintenance of Traffic LS 1

    0102 60 Work Zone Signs ED 2,600

    0102 74 1 Barricade (Types I, II, VP & Drum) ED 9,000

    0102 76 Arrow Board/Advance warning arrow panel ED 200

    0102 77 High Intensity Flashing Lights ED 1,440

    0102 99 Variable Message Sign (Temporary) ED 28

    0104 10 3 Sediment Barrier LF 3,873

    0104 18 Inlet Protection System EA 6

    0110 1 1 Clearing and Grubbing LS 1

    0110 4 Removal of Existing Concrete Pavement SY 121

    0120 1 Regular Excavation CY 290

    0120 6 Embankment CY 253

    0285 709 Optional Base, Base group 09 SY 90

    0334 1 13 Superpave Asphaltic Concrete TN 20

    0337 7 32 Asphalt Concrete Friction Course TN 15

    0400 0 11 Concrete Class I, Gravity Wall CY 177

    0425 13 25 Inlet, Curb, Type P-2, Partial EA 1

    0425 13 55 Inlet, Curb, Type P-5, Partial EA 1

    0515 1 2 Pipe Handrail-Guiderail Aluminum LF 1,130

    0520 1 10 Concrete Curb and Gutter, Type F LF 520

    0522 2 Sidewalk Concrete, 6" Thick SY 2,347

    0536 1 1 Guardrail Roadway W-Beam LF 712

    0536 73 Guardrail Removal LF 793

    0536 6 Pipe Rail for Guardrail LF 712

    0536 85 22 Guardrail End Anchorage Assembly - Flared EA 3

    0536 85 24 Guardrail End Anchorage Assembly - Parallel EA 3

    0570 1 2 Performance Turf, Sod SY 4,294

    700 1 11 Single Post Sign EA 3

    700 1 50 Single Post Sign Relocate EA 1

    700 1 60 Single Post Sign Remove EA 3

    710 11 111 Painted Solid Traffic (6" white) LF 430

    710 11 123 Painted Solid Traffic (12" white) LF 126

    710 11 125 Painted Solid Traffic (24" white) LF 22

    711 11 111 Thermoplastic Solid Traffic Stripe (6" white) LF 430

    711 11 123 Thermoplastic Solid Traffic Stripe (12" white) LF 126

    711 11 125 Thermoplastic Solid Traffic Stripe (24" white) LF 22

    0715 14 12 Pull Box EA 32