Silver Lake Trail, Phase 1
Steering CommitteeMeeting 1: Kick‐offFebruary 5, 2020
Agenda
• Introductions• Steering Committee Members• Steering Committee Role• Project Team• Overview of Design Process• Key Issues and Concerns• Stakeholder/Public Outreach • Next Steps
Steering Committee
1. Eleanor Jacobs, Village of Perry ‐ Chair2. Matt Jensen, Village of Perry3. Rick Hauser (Jacquie Billings), Village of Perry4. Eric Kelly, Village of Perry5. Bert Gallmon, Silver Lake Association6. Rachel Richter, Perry Main Street Association7. Mike Bellamy, Perry Main Street Association8. Ernie Lawrence, Town of Perry9. Keith Granger, Town of Castile10. Ralph Field, Perry Tree Board11. Todd Gadd, Wyoming County12. Rich Eliasz, Perry Lake Association13. Ray Bzduch, Resident
Steering Committee Role
• Represent (two‐way communication)• owner• municipal constituents • organization members • trail users
• Provide data/information• Provide input on design options/priorities• Advise on potential impacts• Review draft documents• Advise on stakeholder/community outreach• Participate in Committee Meetings (4)• Support public meetings and outreach events
Project Team
Design Process
Preliminary DesignPreliminary Design• Committee Meeting 1 (Jan)• Survey• Data Collection• Traffic Studies• Environmental Assessments• Cultural Resources Review• Committee Meeting 2 (April)• Public Meeting 1 (late April)• Draft Design Report• Public Meeting 2 (early August)• NYSDOT Review
• Committee Meeting 1 (Jan)• Survey• Data Collection• Traffic Studies• Environmental Assessments• Cultural Resources Review• Committee Meeting 2 (April)• Public Meeting 1 (late April)• Draft Design Report• Public Meeting 2 (early August)• NYSDOT Review
Spring/Summer 2020
Final DesignFinal Design• Draft Contract Documents• NYSDOT Review• Final Contract Documents• Final Estimate• Share Breakdown
• Draft Contract Documents• NYSDOT Review• Final Contract Documents• Final Estimate• Share Breakdown
Fall 2020
Design ApprovalAugust 2020
Final PS&EDecember 2020
Construction
Bid & AwardBid & Award• Advertise• Bid Opening• Award
• Advertise• Bid Opening• Award
Construction CompleteOctober 2021
ConstructionConstruction• Start - March• Complete - Oct• Start - March• Complete - Oct
Spring‐Fall 2021Winter 2021
AwardFebruary 2021
Ribbon CuttingNovember 2021
Design Process
• Feasibility Study• Phase 1:
• Silver Lake to Village• $1.2 million in trail improvements
• Confirm vision and objectives• Consideration of design options• Development of plans and specifications• Bid & Award• Construction
Feasibility Study
Design Options
Design Options
Design Options
Design Options
Design Options
Design Options
Design Options
Design Options
Key Issues and Concerns
Stakeholder/Public Outreach
•Manage ExpectationsInform
• Institutional KnowledgeConsult
• Support ImplementationInvolve
Recognize Diversity
Steering Committee/Stakeholders
Public
Public
Inform
• Contact cards• Semi‐permanent display• Website/Facebook Page
Involve
• Project email: [email protected]• Survey
• Web‐based• February• Promote
• Municipal websites• Organization e‐blasts/newsletters
• Comment Sheets
Involve
• Public Meetings1. Late April
o Issues, needs, and alternativeso Presentation/stations for each segment
2. Early/mid‐Augusto Encourage seasonal resident participation
o Community feedback, proposed plan, construction schedule
o Presentation/Q&A
Involve
• Other Outreach Events1. Last Night – Monday, 12/31/19, Perry schools, 6pm‐midnight
o “Get Involved”o C&S provide materials – board and contact cards o Village/Committee to staff
2. Farmer’s Market – Saturday, 6/20/20, South Main Street’s downtown Festival Plaza (between Borden and Dolbeer), 8:30am‐12:30pm o Alternative feedback/prioritieso C&S provide materials – board and contact cards o Village/Committee to staff
3. Chalk Art Festival – Saturday in mid‐July TBDo Alternative feedback/prioritieso C&S provide materials – board and contact cards o C&S and Village/Committee to staff
4. Pioneer Picnic – August TBDo Proposed Plano Village/Committee to staff
Next Steps
Steering Committee• Submit comments on survey by 2/14• Promote the project• Encourage survey participation
• website link• Newsletter e‐blast
C&S• Finalize and implement survey • Progress survey, data collection, studies• Develop alternativesMeetings• Committee – early April• Public – late April