67
Act ID Activity Name Duration Start Finish Expan Expansion of Bhilai Steel Plant (Rev - 6A-3) Expansion of Bhilai Steel Plant (Rev - 6A-3) Expansion of Bhilai Steel Plant (Rev - 6A-3) Expansion of Bhilai Steel Plant (Rev - 6A-3) 001 Principal Approval for BSP Expansion 0 03-Apr-07 A 003 Stage - II Approval (Progress ively ) 240 14-Mar-08 A 29-Dec-14 004 Overall Completion of BSP Expansion 0 04-Sep-16 Pkg 0 Pkg 060 Augmentation of Ore Handling Plant Part - A Pkg 060 Augmentation of Ore Handling Plant Part - A Pkg 060 Augmentation of Ore Handling Plant Part - A Pkg 060 Augmentation of Ore Handling Plant Part - A 369 Issue Draft TS (Issued) 0 01-May-07 A 370 Discussion with BSP 14 02-May-07 A 15-May-07 A 371 Issue Final TS (Issued) 15 16-May-07 A 30-Aug-07 A 372 Issue of NIT (Issued ) 8 31-Aug-07 A 07-Sep-07 A 373 Recpt of Tender at Bhilai 45 10-Sep-07 A 20-Nov-07 A 374 Recpt of Tender at Ranc hi 4 21-Nov-07 A 23-Nov-07 A 375 Scrutiny, Discussions & Tender Finalisation 75 10-Dec-07 A 30-Jan-08 A 376 Firming-up of price of the package & stage -II approval 45 31-Jan-08 A 14-Mar-08 A 376.1 Issue of LOI 0 25-Mar-08 A 377 Signing of contract with M/s HEC (24 months schedule) 0 09-Apr-08 A 378 Engg., Supply, Execution, Testing & Comm.- Ore Handl. plant (Part A) 730 10-Apr-08 A 01-Dec-14 Pkg 0 Pkg 061 New Ore Handling Plant Part-B Pkg 061 New Ore Handling Plant Part-B Pkg 061 New Ore Handling Plant Part-B Pkg 061 New Ore Handling Plant Part-B 380 Issue Draft TS (Issued) 0 08-Jun-07 A 381 Discussion with BSP 10 01-Sep-07 A 10-Sep-07 A 382 Issue Final TS (Issued ) 14 12-Sep-07 A 25-Sep-07 A Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 Steel Authority of India Limited Bhilai Steel Plant Expansion Project PERT Network Schedule of All Packages STATUS AS ON 30th Sep 2014 Early Bar Critical Bar Milestone Summary Page 1 of 67 © 2014 - MECON limited. All rights reserved Start Date: 03-Apr-07; Finish Date : 28-Sep-16 Data Date : 30-Sep-14; Run Date: 05-Nov-14 © Primavera Systems, Inc.

Steel Authority of India Limited Bhilai Steel Plant ... Mt... · Act ID Activity Name Duration Start Finish Expansion of Bhilai Steel Plant (Rev - 6A-3) 001 Principal Approval for

  • Upload
    others

  • View
    18

  • Download
    0

Embed Size (px)

Citation preview

Act ID Activity Name Duration Start Finish

Expansion of Bhilai Steel Plant (Rev - 6A-3)Expansion of Bhilai Steel Plant (Rev - 6A-3)Expansion of Bhilai Steel Plant (Rev - 6A-3)Expansion of Bhilai Steel Plant (Rev - 6A-3)Expansion of Bhilai Steel Plant (Rev - 6A-3)

001 Principal Approval for BSP Expansion 0 03-Apr-07 A

003 Stage - II Approval (Progress ively ) 240 14-Mar-08 A 29-Dec-14

004 Overall Completion of BSP Expansion 0 04-Sep-16

Pkg 060 Augmentation of Ore Handling Plant Part - APkg 060 Augmentation of Ore Handling Plant Part - APkg 060 Augmentation of Ore Handling Plant Part - APkg 060 Augmentation of Ore Handling Plant Part - APkg 060 Augmentation of Ore Handling Plant Part - A

369 Issue Draft TS (Issued) 0 01-May-07 A

370 Discussion with BSP 14 02-May-07 A 15-May-07 A

371 Issue Final TS (Issued) 15 16-May-07 A 30-Aug-07 A

372 Issue of NIT (Issued ) 8 31-Aug-07 A 07-Sep-07 A

373 Recpt of Tender at Bhilai 45 10-Sep-07 A 20-Nov-07 A

374 Recpt of Tender at Ranc hi 4 21-Nov-07 A 23-Nov-07 A

375 Scrutiny, Discussions & Tender Finalisation 75 10-Dec-07 A 30-Jan-08 A

376 Firming-up of price of the package & stage -II approval 45 31-Jan-08 A 14-Mar-08 A

376.1 Issue of LOI 0 25-Mar-08 A

377 Signing of contract with M/s HEC (24 months schedule) 0 09-Apr-08 A

378 Engg., Supply, Execution, Testing & Comm.- Ore Handl. plant (Part A)

730 10-Apr-08 A 01-Dec-14

Pkg 061 New Ore Handling Plant Part-BPkg 061 New Ore Handling Plant Part-BPkg 061 New Ore Handling Plant Part-BPkg 061 New Ore Handling Plant Part-BPkg 061 New Ore Handling Plant Part-B

380 Issue Draft TS (Issued) 0 08-Jun-07 A

381 Discussion with BSP 10 01-Sep-07 A 10-Sep-07 A

382 Issue Final TS (Issued ) 14 12-Sep-07 A 25-Sep-07 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 1 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

383 Issue of NIT 5 26-Sep-07 A 15-Oct-07 A

384 Recpt of Tender at Bhilai 45 05-Nov-07 A 14-Dec-07 A

385 Recpt of Tender at Ranc hi 5 15-Dec-07 A 19-Dec-07 A

386 Scrutiny & Discussions 30 20-Dec-07 A 16-Apr-08 A

386.1 Issue Final TS (Retendered) 14 01-Sep-08 A 24-Oct-08 A

386.2 Issue of NIT 5 25-Oct-08 A 27-Oct-08 A

386.3 Recpt of Tender at Bhilai 45 28-Oct-08 A 20-Jan-09 A

386.4 Recpt of Tender at Ranc hi 5 21-Jan-09 A 26-Jan-09 A

386.5 Scrutiny & Discussions & Tender Finalis ation 30 28-Jan-09 A 26-Jun-09 A

387 Firming-up of price of the package & Stage-II approval 45 27-Jun-09 A 19-Mar-10 A

387.1 Issue of LOI 0 01-Apr-10 A

388 Signing of contract with M/s Engg. Projects India Ltd.(24 months schedule)

0 30-Apr-10 A

389 Engg., Supply, Execution, Testing & Comm.- Ore Handl. plant (Part B)

731 30-Apr-10 A 18-Sep-15

Pkg 062 New Coal Handling PlantPkg 062 New Coal Handling PlantPkg 062 New Coal Handling PlantPkg 062 New Coal Handling PlantPkg 062 New Coal Handling Plant

391 Issue Draft TS (Issued) 0 22-Jun-07 A

392 Discussion with BSP 8 09-Jul-07 A 30-Jul-07 A

393 Issue Final TS (Issued ) 14 24-Aug-07 A 06-Sep-07 A

394 Issue of NIT (Issued ) 10 09-Sep-07 A 18-Sep-07 A

395 Recpt of Tender at Bhilai 45 19-Sep-07 A 30-Nov-07 A

396 Recpt of Tender at Ranc hi 5 03-Dec-07 A 07-Dec-07 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 2 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

397 Scrutiny, Discussions & Tender Finalisation 75 08-Dec-07 A 26-Feb-08 A

398 Firming-up of price of the package & stage-II approval 40 27-Feb-08 A 02-Sep-08 A

398.1 Issue of LOI 0 03-Sep-08 A

399 Signing of contract with M/s HEC (30 months schedule) 0 20-Sep-08 A

400 Engg., Supply, Execution, Testing & Comm.- New Coal Handling Plant

912 20-Sep-08 A 17-Mar-15

Pkg 064 Augmentation of Fuel & flux crushing faci litiesPkg 064 Augmentation of Fuel & flux crushing faci litiesPkg 064 Augmentation of Fuel & flux crushing faci litiesPkg 064 Augmentation of Fuel & flux crushing faci litiesPkg 064 Augmentation of Fuel & flux crushing faci lities

390 Issue Draft TS 0 24-Apr-08 A

401 Discussion with BSP 6 25-Apr-08 A 05-Jun-08 A

402 Issue Final TS 40 06-Jun-08 A 16-Jun-08 A

413 Issue of NIT 10 17-Jun-08 A 12-Aug-08 A

424 Recpt of Tender at Bhilai 45 13-Aug-08 A 27-Sep-08 A

425 Recpt of Tender at Ranc hi 3 28-Sep-08 A 30-Sep-08 A

436 Scrutiny, Discussions & Tender Finalisation ( Retendered) 75 01-Oct-08 A 07-Dec-08 A

436.1 Issue Final TS 21 10-Mar-09 A 20-Mar-09 A

436.11 Issue of NIT 5 21-Mar-09 A 28-Mar-09 A

436.2 Recpt of Tender at Bhilai 45 30-Mar-09 A 30-May-09 A

436.3 Recpt of Tender at Ranc hi 5 31-May-09 A 04-Jun-09 A

436.4 Scrutiny, Discussions & Tender Finalisation 60 05-Jun-09 A 02-Sep-09 A

436.5 Firming-up of price of the package 45 03-Sep-09 A 15-Jan-11 A

436.6 Issue of LOI 0 01-Feb-11 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 3 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

436.7 Signing of contract with M/s EPI (22 months schedule) 0 15-Feb-11 A

436.8 Engg., Supply, Execution, Testing & Comm.- Fuel & flux crushing facilities

669 16-Feb-11 A 19-Oct-15

Pkg 090-A Laboratory Equipment & BuildingPkg 090-A Laboratory Equipment & BuildingPkg 090-A Laboratory Equipment & BuildingPkg 090-A Laboratory Equipment & BuildingPkg 090-A Laboratory Equipment & Building

12620 Issue Final TS 12 01-Aug-14 A 11-Oct-14

12630 Issue of NIT 10 13-Oct-14 22-Oct-14

12640 Recpt of Tender at Bhilai 30 23-Oct-14 21-Nov-14

12650 Recpt of Tender at Ranc hi 5 22-Nov-14 26-Nov-14

12660 Scrutiny, Discussions & Tender Finalisation 45 27-Nov-14 10-Jan-15

12670 Firming-up of price of the package & Mngt. Approval 30 11-Jan-15 09-Feb-15

12675 Issue of LOI 0 17-Feb-15

12680 Signing of Contract 0 19-Mar-15

12690 Engg., Supply, Execution, Testing & Comm.- Lab eqpt (Imp) 181 20-Mar-15 16-Sep-15

Pkg 010 4060 cu.m. Blast FurnacePkg 010 4060 cu.m. Blast FurnacePkg 010 4060 cu.m. Blast FurnacePkg 010 4060 cu.m. Blast FurnacePkg 010 4060 cu.m. Blast Furnace

041 Issue Draft TS (Issued) 0 25-Apr-07 A

042 Discussion with BSP 20 26-Apr-07 A 15-May-07 A

043 Issue Final TS (Issued) 16 18-May-07 A 11-Jun-07 A

044 Issue of NIT (Issued) 1 12-Jun-07 A 02-Jul-07 A

045 Recpt of Tender at Bhilai 43 03-Jul-07 A 22-Sep-07 A

046 Recpt of Tender at Ranc hi 3 24-Sep-07 A 26-Sep-07 A

047 Scrutiny, Discussions & Tender Finalisation 75 24-Oct-07 A 15-Feb-08 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 4 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

048 Firming-up of price of the package 30 16-Feb-08 A 14-Aug-08 A

048.1 Issue of LOI (Retendered) 0 15-Aug-08 A

048.2 Issue of NIT 5 02-Jul-09 A 06-Jul-09 A

048.3 Recpt of Tender at Bhilai 43 07-Jul-09 A 04-Aug-09 A

048.4 Recpt of Tender at Ranc hi 3 05-Aug-09 A 07-Aug-09 A

048.5 Scrutiny, Discussions & Tender Finalisation 45 08-Aug-09 A 04-Dec-09 A

048.6 Firming-up of price of the package 20 05-Dec-09 A 03-Aug-10 A

048.7 Issue of LOI 0 04-Aug-10 A

048.8 Signing of Contract with M/s PWIT/L&T (28 months schedule)

0 30-Aug-10 A

050 Engg., Supply, Execution, Testing & Comm.- BF 8 851 31-Aug-10 A 24-Nov-15

Pkg 011-01 Boiler, STG & Balance of Plant (DMWP, CWS & Elec.(Package split))Pkg 011-01 Boiler, STG & Balance of Plant (DMWP, CWS & Elec.(Package split))Pkg 011-01 Boiler, STG & Balance of Plant (DMWP, CWS & Elec.(Package split))Pkg 011-01 Boiler, STG & Balance of Plant (DMWP, CWS & Elec.(Package split))Pkg 011-01 Boiler, STG & Balance of Plant (DMWP, CWS & Elec.(Package split))

052 Issue Draft TS (Issued) 0 01-Jun-07 A

053 Discussion with BSP 7 02-Jun-07 A 09-Jun-07 A

054 Issue Final TS (Issued ) 14 11-Sep-07 A 29-Sep-07 A

055 Issue of NIT 14 30-Sep-07 A 23-Oct-07 A

056 Recpt of Tender at Bhilai 45 14-Oct-07 A 15-Jan-08 A

057 Recpt of Tender at Ranc hi 6 16-Jan-08 A 24-Jan-08 A

058 Scrutiny, Discussions & Tender Finalisation ( Retendered) 75 25-Jan-08 A 20-Mar-09 A

074 Issue Final TS (Issued ) 14 18-Mar-09 A 20-Mar-09 A

075 Issue of NIT 14 21-Mar-09 A 11-Jun-09 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 5 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

076 Recpt of Tender at Bhilai 45 12-Jun-09 A 15-Jul-09 A

077 Recpt of Tender at Ranc hi 6 16-Jul-09 A 15-Aug-09 A

078 Scrutiny, Discussions & Tender Finalisation 60 16-Aug-09 A 25-Nov-10 A

079 Firming-up of price of the package & stage-II approval (Retendered)

30 26-Nov-10 A 14-Feb-11 A

Pkg 011-01A BoilersPkg 011-01A BoilersPkg 011-01A BoilersPkg 011-01A BoilersPkg 011-01A Boilers

10520 Issue Final TS 14 04-Mar-11 A 07-Mar-11 A

10530 Issue of NIT 8 08-Mar-11 A 10-Mar-11 A

10540 Recpt of Tender at Bhilai 45 11-Mar-11 A 06-May-11 A

10550 Recpt of Tender at Ranc hi 5 07-May-11 A 11-May-11 A

10560 Scrutiny, Discussions & Tender Finalisation 30 12-May-11 A 18-Dec-11 A

10570 Firming-up of price of the package & Mngt. Approval 30 19-Dec-11 A 01-Mar-12 A

10570.1 Issue of LOI 0 06-Mar-12 A

10580 Signing of Contract with M/s Fujian LongKing Co. Ltd. (20 months schedule)

0 24-Mar-12 A

10590 Engg., Supply, Execution, Testing & Comm.-Boilers 610 25-Mar-12 A 09-Apr-16

10800 commissioning of Bolier 1 0 10-Nov-15

10810 commissioning of Boiler 2 0 10-Jan-16

10820 commissioning of Boiler 7 0 09-Apr-16

Pkg 011-01B STG, Cooling water system and balance of plantPkg 011-01B STG, Cooling water system and balance of plantPkg 011-01B STG, Cooling water system and balance of plantPkg 011-01B STG, Cooling water system and balance of plantPkg 011-01B STG, Cooling water system and balance of plant

10600 Issue Draft TS 0 17-Mar-11 A

10610 Discussion with BSP 12 18-Mar-11 A 21-Mar-11 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 6 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

10620 Issue Final TS 14 22-Mar-11 A 26-Mar-11 A

10630 Issue of NIT 8 28-Mar-11 A 02-Apr-11 A

10640 Recpt of Tender at Bhilai 25 04-Apr-11 A 14-May-11 A

10650 Recpt of Tender at Ranc hi 5 16-May-11 A 25-May-11 A

10660 Scrutiny, Discussions & Tender Finalisation 30 26-May-11 A 23-Sep-11 A

10670 Firming-up of price of the package & Mngt. Approval 30 24-Sep-11 A 12-Dec-11 A

10671 Issue of LOI 0 19-Dec-11 A

10680 Signing of Contract with M/s Triv eni Turbines (18 months schedule)

0 19-Jan-12 A

10690 Engg., Supply, Execution, Testing & Comm.-STG & BPTG 547 19-Jan-12 A 10-Nov-15

10695 Commissioning of cooling water system 0 13-Apr-15*

Pkg 011-01C DM waterPkg 011-01C DM waterPkg 011-01C DM waterPkg 011-01C DM waterPkg 011-01C DM water

10700 Issue Draft TS 0 28-Apr-11 A

10710 Discussion with BSP 8 29-Apr-11 A 06-May-11 A

10720 Issue Final TS 14 07-May-11 A 20-May-11 A

10730 Issue of NIT 8 21-May-11 A 26-May-11 A

10740 Recpt of Tender at Bhilai 30 27-May-11 A 27-Jun-11 A

10750 Recpt of Tender at Ranc hi 5 28-Jun-11 A 05-Jul-11 A

10760 Scrutiny, Discussions & Tender Finalisation 30 06-Jul-11 A 15-Dec-11 A

10770 Firming-up of price of the package & Mngt. Approval 30 16-Dec-11 A 25-Jan-12 A

10771 Issue of LOI 0 01-Feb-12 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 7 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

10780 Signing of Contract with Technofab Engg. Ltd. (12 months schedule)

0 25-Feb-12 A

10790 Engg., Supply, Execution, Testing & Comm.- DM water system

365 27-Feb-12 A 12-Aug-15

Pkg 011-02 Enabling works for Boiler,STG,BOPPkg 011-02 Enabling works for Boiler,STG,BOPPkg 011-02 Enabling works for Boiler,STG,BOPPkg 011-02 Enabling works for Boiler,STG,BOPPkg 011-02 Enabling works for Boiler,STG,BOP

062 Issue Draft TS 0 04-Feb-10 A

073 Discussion with BSP 7 05-Feb-10 A 13-Feb-10 A

084 Issue Final TS 14 14-Feb-10 A 26-Feb-10 A

085 Issue of NIT 14 27-Feb-10 A 10-Mar-10 A

096 Recpt of Tender at Bhilai 30 11-Mar-10 A 30-Apr-10 A

096.02 Scrutiny, Discussions & Tender Finalisation 30 01-May-10 A 22-Jul-10 A

129 Firming-up of price of the package 15 23-Jul-10 A 01-Sep-10 A

131 Signing of contract 0 18-Sep-10 A

272 Enabling works for Boiler,STG,BOP 152 19-Sep-10 A 25-Oct-12 A

Pkg 011-03 Relocation of SMS Repair shop & SMS Testing laboratoryPkg 011-03 Relocation of SMS Repair shop & SMS Testing laboratoryPkg 011-03 Relocation of SMS Repair shop & SMS Testing laboratoryPkg 011-03 Relocation of SMS Repair shop & SMS Testing laboratoryPkg 011-03 Relocation of SMS Repair shop & SMS Testing laboratory

10830 Issue Draft TS 0 18-Oct-10 A

10840 Discussion with BSP 8 19-Oct-10 A 10-Feb-11 A

10850 Issue Final TS 14 17-Feb-11 A 07-Mar-11 A

10860 Issue of NIT 8 08-Mar-11 A 04-Apr-11 A

10870 Recpt of Tender at Bhilai 45 05-Apr-11 A 02-May-11 A

10880 Recpt of Tender at Ranc hi 5 03-May-11 A 10-May-11 A

10890 Scrutiny, Discussions & Tender Finalisation 30 10-May-11 A 16-Jul-11 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 8 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

10900 Firming-up of price of the package & Mngt. Approval 30 18-Jul-11 A 25-Aug-11 A

10905 Issue of LOI 0 30-Aug-11 A

10910 Signing of Contract 0 23-Sep-11 A

10920 Engg., Supply, Execution, Testing & Comm.- Relocation of SMS Repair shop & SMS Testing laboratory

365 24-Sep-11 A 30-Oct-14

Pkg 012 Turbo Blowers & Auxil iariesPkg 012 Turbo Blowers & Auxil iariesPkg 012 Turbo Blowers & Auxil iariesPkg 012 Turbo Blowers & Auxil iariesPkg 012 Turbo Blowers & Auxil iaries

063 Issue Draft TS (Issued) 0 24-May-07 A

064 Discussion with BSP 8 24-May-07 A 15-Jun-07 A

065 Issue Final TS (Issued) 11 20-Jun-07 A 11-Sep-07 A

066 Issue of NIT (Issued ) 10 12-Sep-07 A 15-Sep-07 A

067 Recpt of Tender at Bhilai 45 16-Sep-07 A 15-Nov-07 A

068 Recpt of Tender at Ranc hi 5 16-Nov-07 A 19-Nov-07 A

069 Scrutiny, Discussions & Tender Finalisation 75 20-Nov-07 A 31-Jul-08 A

070 Firming-up of price of the package & stage-II approval 45 01-Aug-08 A 30-Sep-10 A

070.1 Issue of LOI 0 12-Oct-10 A

071 Signing of contract with M/s BHEL (27 months schedule) 0 11-Nov-10 A

072 Engg., Supply, Execution, Testing & Comm.- Turbo-Blowers 823 11-Nov-10 A 17-Nov-15

Pkg 020 Second Sintering M/c (360 sqm) in SP-3Pkg 020 Second Sintering M/c (360 sqm) in SP-3Pkg 020 Second Sintering M/c (360 sqm) in SP-3Pkg 020 Second Sintering M/c (360 sqm) in SP-3Pkg 020 Second Sintering M/c (360 sqm) in SP-3

086 Issue Draft TS (Issued) 0 25-Apr-07 A

087 Discussion with BSP 15 26-Apr-07 A 10-May-07 A

088 Issue Final TS (Issued) 9 11-May-07 A 15-Jun-07 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 9 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

089 Issue of NIT (Issued) 11 16-Jun-07 A 30-Jun-07 A

090 Recpt of Tender at Bhilai 45 03-Jul-07 A 16-Oct-07 A

091 Recpt of Tender at Ranc hi 8 20-Oct-07 A 25-Oct-07 A

092 Scrutiny & Discussions 75 12-Nov-07 A 17-Feb-08 A

092.1 Issue Final TS (Retendered ) 9 11-Aug-08 A 19-Aug-08 A

092.2 Issue of NIT 11 20-Aug-08 A 22-Aug-08 A

092.3 Recpt of Tender at Bhilai 45 23-Aug-08 A 15-Sep-08 A

092.4 Recpt of Tender at Ranc hi 8 16-Sep-08 A 23-Sep-08 A

092.5 Scrutiny, discussion & tender finalisation 8 24-Sep-08 A 16-Dec-08 A

093 Firming-up of price of the package 30 17-Dec-08 A 03-Aug-10 A

093.1 Issue of LOI 0 04-Aug-10 A

094 Signing of contract with M/s Outotec/ L&T (28 months schedule)

0 28-Aug-10 A

094.5 Engg., Supply, Execution 791 28-Aug-10 A 20-Nov-14

095 Testing & Comm.- SP-3 60 20-Aug-15 19-Oct-15

Pkg 021-A New Cold Sinter Screening systemPkg 021-A New Cold Sinter Screening systemPkg 021-A New Cold Sinter Screening systemPkg 021-A New Cold Sinter Screening systemPkg 021-A New Cold Sinter Screening system

097 Issue Draft TS (Issued ) 0 16-Sep-08 A

098 Discussion with BSP 12 17-Sep-08 A 20-Sep-08 A

099 Issue Final TS 20 22-Sep-08 A 26-Sep-08 A

100 Issue of NIT 37 27-Sep-08 A 02-Oct-08 A

101 Recpt of Tender at Bhilai 43 03-Oct-08 A 29-Nov-08 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 10 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

102 Scrutiny, Discussions & Tender Finalisation ( Being handled by Mecon, Bhilai)

60 01-Dec-08 A 31-Jul-09 A

11320 Signing of contract with M/s PGEW 0 06-May-10 A

11330 Engg., Supply, Execution, Testing & Comm.- Lime dosing 273 06-May-10 A 15-Nov-14

Pkg 021-B Lime dosing & bunker liningPkg 021-B Lime dosing & bunker liningPkg 021-B Lime dosing & bunker liningPkg 021-B Lime dosing & bunker liningPkg 021-B Lime dosing & bunker lining

107 Issue Draft TS (Issued ) 0 04-Sep-08 A

107.1 Discussion with BSP 12 05-Sep-08 A 10-Sep-08 A

107.2 Issue Final TS 20 11-Sep-08 A 20-Sep-08 A

107.3 Issue of NIT 37 21-Sep-08 A 25-Sep-08 A

121 Recpt of Tender at Bhilai 43 26-Sep-08 A 29-Nov-08 A

132 Scrutiny, Discussions & Tender Finalisation 60 01-Dec-08 A 14-May-09 A

133 Firming-up of price of the package & Mngt. Approval 30 15-May-09 A 05-May-10 A

134 Signing of contract with M/s PGEW 0 05-Jun-10 A

135 Engg., Supply, Execution, Testing & Comm.- Lime dosing 273 07-Jun-10 A 04-Nov-11 A

Pkg 021-C Electrics & Automation System under modernization of SP-IIPkg 021-C Electrics & Automation System under modernization of SP-IIPkg 021-C Electrics & Automation System under modernization of SP-IIPkg 021-C Electrics & Automation System under modernization of SP-IIPkg 021-C Electrics & Automation System under modernization of SP-II

157.3 Issue of NIT 37 05-Jan-09 A 13-Jan-09 A

157.4 Recpt of Tender at Bhilai 43 14-Jan-09 A 12-Mar-09 A

157.5 Scrutiny, Discussions & Tender Finalisation 60 14-Mar-09 A 01-Feb-10 A

163 Firming-up of price of the package & Mngt. Approval 30 02-Feb-10 A 04-Mar-10 A

164 Signing of contract with M/s Siemens 0 06-May-10 A

165 Engg., Supply, Execution, Testing & Comm.- BWF 547 07-May-10 A 29-Oct-14

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 11 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

Pkg 021-D ESP based dedustingPkg 021-D ESP based dedustingPkg 021-D ESP based dedustingPkg 021-D ESP based dedustingPkg 021-D ESP based dedusting

287.3 Issue of NIT 42 22-Oct-08 A 27-Oct-08 A

287.4 Recpt of Tender at Bhilai 43 28-Oct-08 A 31-Dec-08 A

287.5 Scrutiny, Discussions & Tender Finalisation 60 01-Jan-09 A 04-May-09 A

287.6 Firming-up of price of the package & Mngt. Approval 30 05-May-09 A 19-May-10 A

287.8 Signing of contract with M/s Scintillant 0 19-Jun-10 A

289 Engg., Supply, Execution, Testing & Comm.- Plant Dedusting 547 21-Jun-10 A 20-Nov-14

Pkg 038-01 Augmentation Facili ties of MH system for SMS-2Pkg 038-01 Augmentation Facili ties of MH system for SMS-2Pkg 038-01 Augmentation Facili ties of MH system for SMS-2Pkg 038-01 Augmentation Facili ties of MH system for SMS-2Pkg 038-01 Augmentation Facili ties of MH system for SMS-2

267 Issue Draft TS (Issued ) 0 22-Jun-07 A

278 Discussion with BSP 7 23-Jun-07 A 30-Jun-07 A

279 Issue Final TS 14 02-Jul-07 A 22-Jan-08 A

290 Issue of NIT 10 23-Jan-08 A 17-Mar-08 A

301 Recpt of Tender at Bhilai 45 18-Mar-08 A 30-Jun-08 A

312 Recpt of Tender at Ranc hi 5 01-Jul-08 A 04-Jul-08 A

323 Scrutiny, Discussions & Tender Finalisation 60 05-Jul-08 A 26-Mar-09 A

334 Firming-up of price of the package (Retendered ) 25 27-Mar-09 A 01-Feb-11 A

334.1 Issue of LOI 0 16-Feb-11 A

345 Signing of contract with Anupam Industries Ltd. (9 months schedule)

0 15-Mar-11 A

356 Engg., Supply, Execution, Testing & Comm.- SMS 2 Augm. 273 16-Mar-11 A 28-Nov-14

Pkg 038-03 Gas Cleaning plant rectification (SMS-II)Pkg 038-03 Gas Cleaning plant rectification (SMS-II)Pkg 038-03 Gas Cleaning plant rectification (SMS-II)Pkg 038-03 Gas Cleaning plant rectification (SMS-II)Pkg 038-03 Gas Cleaning plant rectification (SMS-II)

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 12 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

367 Issue Draft TS (Issued ) 0 13-Sep-07 A

368 Discussion with BSP 7 14-Sep-07 A 31-Mar-08 A

379 Issue Final TS 14 01-Apr-08 A 05-Apr-08 A

480 Issue of NIT 10 06-Apr-08 A 31-May-08 A

481 Recpt of Tender at Bhilai 45 01-May-10 A 10-May-10 A

482 Recpt of Tender at Ranc hi 5 11-May-10 A 15-May-10 A

483 Scrutiny, Discussions & Tender Finalisation (Retendered ) 60 17-May-10 A 21-May-11 A

483.1 Issue final TS 14 20-Jul-12 A 12-Jun-13 A

483.2 Issue of NIT 10 05-Dec-13 A 16-Dec-13 A

483.3 Recpt of Tender at Bhilai 45 17-Dec-13 A 07-Mar-14 A

483.4 Recpt of Tender at Ranc hi 5 10-Mar-14 A 14-Mar-14 A

483.5 Scrutiny, Discussions & Tender Finalisation 60 14-Mar-14 A 29-Oct-14

484 Firming-up of price of the package & Mngt. Approval 25 30-Oct-14 23-Nov-14

484.1 Issue of LOI 0 01-Dec-14

485 Signing of contract 0 31-Dec-14

486 Engg., Supply, Execution, Testing & Comm.- SMS 2 Augm. 456 01-Jan-15 31-Mar-16

Pkg 038-05 Combined blowing of argon / nitrogen in convertersPkg 038-05 Combined blowing of argon / nitrogen in convertersPkg 038-05 Combined blowing of argon / nitrogen in convertersPkg 038-05 Combined blowing of argon / nitrogen in convertersPkg 038-05 Combined blowing of argon / nitrogen in converters

787 Issue Draft TS (Issued ) 0 15-Sep-07 A

788 Discussion with BSP 7 16-Sep-07 A 25-Sep-07 A

789 Issue Final TS 14 26-Sep-07 A 20-Nov-07 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 13 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

790 Issue of NIT 10 21-Nov-07 A 18-Dec-07 A

791 Recpt of Tender at Bhilai 45 19-Dec-07 A 05-Mar-08 A

792 Recpt of Tender at Ranc hi 5 06-Mar-08 A 10-Mar-08 A

793 Scrutiny, Discussions & Tender Finalisation ( retendered ) 60 11-Mar-08 A 11-Apr-11 A

793.1 Issue Final TS 14 01-Jun-11 A 13-Nov-14

793.2 Issue of NIT 10 15-Nov-14 24-Nov-14

793.3 Recpt of Tender at Bhilai 30 25-Nov-14 24-Dec-14

793.4 Recpt of Tender at Ranc hi 5 25-Dec-14 29-Dec-14

793.5 Scrutiny, Discussions & Tender Finalisation 30 30-Dec-14 28-Jan-15

794 Firming-up of price of the package & Mngt. Approval 15 29-Jan-15 12-Feb-15

794.1 Issue of LOI 0 20-Feb-15

795 Signing of contract 0 22-Mar-15

796 Engg., Supply, Execution, Testing & Comm.- SMS 2 Augm. 517 23-Mar-15 20-Aug-16

Pkg 038-06 Modernisation of BOF automation system (SMS-II)Pkg 038-06 Modernisation of BOF automation system (SMS-II)Pkg 038-06 Modernisation of BOF automation system (SMS-II)Pkg 038-06 Modernisation of BOF automation system (SMS-II)Pkg 038-06 Modernisation of BOF automation system (SMS-II)

797 Issue Draft TS 0 29-Oct-07 A

798 Discussion with BSP 7 30-Oct-07 A 06-Nov-07 A

799 Issue Final TS 14 07-Nov-07 A 03-Mar-08 A

800 Issue of NIT 14 04-Mar-08 A 08-May-08 A

801 Recpt of Tender at Bhilai 45 09-May-08 A 20-Jul-08 A

802 Recpt of Tender at Ranc hi 5 21-Jul-08 A 28-Jul-08 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 14 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

803 Scrutiny, Discussions & Tender Finalisation 60 29-Jul-08 A 07-Apr-11 A

804 Firming-up of price of the package & Mngt. Approval (Package Retendered)

25 08-Apr-11 A 03-May-11 A

804.01 Issue Draft TS 0 03-Apr-12 A

804.02 Discussion with BSP 7 04-Apr-12 A 09-May-12 A

804.03 Issue Final TS 14 10-May-12 A 22-May-12 A

804.04 Issue of NIT 14 23-May-12 A 04-Aug-12 A

804.05 Recpt of Tender at Bhilai 45 06-Aug-12 A 03-Dec-12 A

804.06 Recpt of Tender at Ranc hi 5 04-Dec-12 A 14-Dec-12 A

804.07 Scrutiny, Discussions & Tender Finalisation 45 15-Dec-12 A 13-Nov-14

804.08 Firming-up of price of the package & Mngt. Approval 25 14-Nov-14 08-Dec-14

804.09 Issue of LOI 0 16-Dec-14

804.10 Signing of contract 0 16-Dec-14

804.11 Engg., Supply, Execution, Testing & Comm.- SMS 2 Augm. 547 17-Dec-14 15-Jun-16

Pkg 038-12 Dedusting of lime facilities at + 47m levelPkg 038-12 Dedusting of lime facilities at + 47m levelPkg 038-12 Dedusting of lime facilities at + 47m levelPkg 038-12 Dedusting of lime facilities at + 47m levelPkg 038-12 Dedusting of lime facilities at + 47m level

617 Issue Draft TS (Issued ) 0 14-Sep-07 A

628 Discussion with BSP 7 15-Sep-07 A 25-Sep-07 A

639 Issue Final TS 14 26-Sep-07 A 23-Jan-08 A

650 Issue of NIT 10 24-Jan-08 A 18-Feb-08 A

765 Signing of contract 0 19-Jun-10 A

766 Engg., Supply, Execution, Testing & Comm.- SMS 2 Augm. 273 19-Jun-10 A 28-Sep-12 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 15 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

Pkg 025 BOF Shop Technological Package (SMS-3)Pkg 025 BOF Shop Technological Package (SMS-3)Pkg 025 BOF Shop Technological Package (SMS-3)Pkg 025 BOF Shop Technological Package (SMS-3)Pkg 025 BOF Shop Technological Package (SMS-3)

108 Issue Draft TS (Issued) 0 25-Apr-07 A

109 Discussion with BSP 10 26-Apr-07 A 05-May-07 A

110 Issue Final TS (Issued) 13 06-May-07 A 09-Jun-07 A

111 Issue of NIT (Issued) 9 11-Jun-07 A 02-Jul-07 A

112 Recpt of Tender at Bhilai 46 20-Jul-07 A 20-Nov-07 A

113 Recpt of Tender at Ranc hi 5 21-Nov-07 A 25-Nov-07 A

114 Scrutiny, Discussions & Tender Finalisation 90 26-Nov-07 A 08-Apr-08 A

115 Firming-up of price of the package 35 09-Apr-08 A 14-Aug-08 A

115.1 Issue of LOI 0 15-Sep-08 A

116 Signing of Contract with M/s Siemens VAI (33.5 months schedule)

0 24-Oct-08 A

116.1 Engg, Procurement & Supply 865 25-Oct-08 A 14-Oct-14

116.2 Erection of Eqpt, Ref of BOF (SVAI SCOPE) 456 11-Oct-11 A 30-Apr-16

117 Testing & Comm.- BOF 121 30-Apr-16 29-Aug-16

118 Commissioning of Converter - 1 0 31-May-16

119 Commissioning of Converter - 2 0 15-Jul-16

120 Commissioning of Converter - 3 0 29-Aug-16

Pkg 025A Secondary Steel RefiningPkg 025A Secondary Steel RefiningPkg 025A Secondary Steel RefiningPkg 025A Secondary Steel RefiningPkg 025A Secondary Steel Refining

900 Issue Draft TS (Issued) 0 15-Jun-07 A

901 Discussion with BSP 10 20-Jun-07 A 30-Jun-07 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 16 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

902 Issue Final TS (Issued) 13 08-Jul-07 A 20-Jul-07 A

903 Issue of NIT (Issued) 9 06-Aug-07 A 14-Aug-07 A

904 Recpt of Tender at Bhilai 46 15-Aug-07 A 15-Dec-07 A

905 Recpt of Tender at Ranc hi 4 16-Dec-07 A 19-Dec-07 A

906 Scrutiny, Discussions & Tender Finalisation 75 20-Dec-07 A 04-Nov-08 A

907 Firming-up of price of the package & stage-II approval 45 05-Nov-08 A 27-Feb-10 A

908 Signing of Contract with M/s Wisdri (30.5 months schedule) 0 08-Mar-10 A

909 Engg., Supply, Execution, Testing & Comm.- SRU 927 08-Mar-10 A 28-Sep-16

910 Commissioning of ARS - 1& LF1 0 31-May-16

911 Commissioning of ARS2 &LF2 0 30-Jun-16

912 Commissioning of ARS 3 & LF 3 0 30-Jul-16

9660 Commissioning of RH Degasser 0 28-Sep-16

Pkg 026 Continuous Casting Shop - Technological PackagePkg 026 Continuous Casting Shop - Technological PackagePkg 026 Continuous Casting Shop - Technological PackagePkg 026 Continuous Casting Shop - Technological PackagePkg 026 Continuous Casting Shop - Technological Package

122 Issue Draft TS (Issued) 0 05-May-07 A

123 Discussion with BSP 10 06-May-07 A 15-May-07 A

124 Issue Final TS (Issued) 16 16-May-07 A 16-Jun-07 A

125 Issue of NIT (Issued ) 6 29-Jun-07 A 04-Jul-07 A

126 Recpt of Tender at Bhilai 45 05-Jul-07 A 06-Dec-07 A

127 Recpt of Tender at Ranc hi 6 07-Dec-07 A 12-Dec-07 A

128 Scrutiny , Discussions & tender finalisation 90 13-Dec-07 A 28-Jul-08 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 17 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

128.1 Firming-up of price of the package 45 29-Jul-08 A 30-Mar-09 A

128.2 Issue of LOI 0 31-Mar-09 A

128.3 Signing of Contract with M/s SVAI (33 months schedule) 0 18-Apr-09 A

128.31 Engg , Supply of equipments, ref of CCP 699 19-May-09 A 25-Dec-14

128.32 Erection of Eqpts, Ref of CCP (SVAI Scope) 211 05-Jun-15 02-Jan-16

128.4 Testing & Comm. of casters 121 30-Apr-16 29-Aug-16

128.5 Billet caster-1 0 31-May-16

128.6 Billet Caster -2 0 15-Jul-16

128.7 Bloom Caster 0 29-Aug-16

128.8 Beam blank Caster 0 29-Aug-16

Pkg 027 Hot Metal Desulphurisation (2 nos)Pkg 027 Hot Metal Desulphurisation (2 nos)Pkg 027 Hot Metal Desulphurisation (2 nos)Pkg 027 Hot Metal Desulphurisation (2 nos)Pkg 027 Hot Metal Desulphurisation (2 nos)

136 Issue Draft TS (Issued ) 0 18-Jun-07 A

137 Discussion with BSP 8 19-Jun-07 A 26-Jun-07 A

138 Issue Final TS (Issued ) 15 27-Jun-07 A 11-Jul-07 A

139 Issue of NIT (Issued ) 8 07-Aug-07 A 14-Aug-07 A

140 Recpt of Tender at Bhilai 45 16-Aug-07 A 22-Nov-07 A

141 Recpt of Tender at Ranc hi 5 15-Nov-07 A 20-Nov-07 A

142 Scrutiny, Discussions & Tender Finalisation 60 21-Nov-07 A 28-Feb-08 A

143 Firming-up of price of the package & stage-II approval 45 29-Feb-08 A 01-Sep-08 A

143.1 Issue of LOI 0 05-Sep-08 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 18 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

144 Signing of contract with M/s Beekay (24 months schedule) 0 06-Oct-08 A

145 Engg., Supply, Execution, Testing & Comm.- HM Desulph. 730 06-Mar-09 A 08-Nov-15

Pkg 028 Lime Calcination Plant (RMP-3)Pkg 028 Lime Calcination Plant (RMP-3)Pkg 028 Lime Calcination Plant (RMP-3)Pkg 028 Lime Calcination Plant (RMP-3)Pkg 028 Lime Calcination Plant (RMP-3)

150 Issue of NIT 8 20-Feb-09 A 28-Feb-09 A

151 Recpt of Tender at Bhilai 45 02-Mar-09 A 15-Apr-09 A

152 Recpt of Tender at Ranc hi 6 16-Apr-09 A 17-Apr-09 A

153 Scrutiny, Discussions & Tender Finalisation 45 18-Apr-09 A 22-Jun-09 A

154 Firming-up of price of the package 30 23-Jun-09 A 25-Nov-09 A

154.1 Issue of LOI 0 02-Dec-09 A

155 Signing of contract M/s SPCL (27 months schedule) 0 09-Dec-09 A

156 Engg., Supply, Execution, Testing & Comm.- Lime Calc. Plant

820 09-Dec-09 A 28-Apr-15

Pkg 029A1 Main Cranes for BOF and CCP (+ 120t - 7 Nos priority crane)Pkg 029A1 Main Cranes for BOF and CCP (+ 120t - 7 Nos priority crane)Pkg 029A1 Main Cranes for BOF and CCP (+ 120t - 7 Nos priority crane)Pkg 029A1 Main Cranes for BOF and CCP (+ 120t - 7 Nos priority crane)Pkg 029A1 Main Cranes for BOF and CCP (+ 120t - 7 Nos priority crane)

158 Issue Draft TS (Issued ) 0 22-Jun-07 A

159 Discussion with BSP 12 28-Jun-07 A 09-Jul-07 A

160 Issue Final TS (Issued ) 14 24-Jul-07 A 31-Oct-07 A

161 Issue of NIT 16 01-Nov-07 A 16-Nov-07 A

161.3 Scrutiny, Discussions & Tender Finalisation 30 24-Sep-08 A 05-Mar-09 A

162 Firming up of price & Stage-II approval 45 06-Mar-09 A 13-May-09 A

162.1 Issue of LOI 0 29-May-09 A

166 Signing of contract with M/s HEC (24 months schedule) 0 29-Jun-09 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 19 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

167 Engg., Supply, erection, Testing & Comm.- Large Cranes forSMS-3

730 29-Jun-09 A 10-Jul-15

Pkg 029A2 Main Cranes for BOF and CCP (+120 t- 10 nos. crane)Pkg 029A2 Main Cranes for BOF and CCP (+120 t- 10 nos. crane)Pkg 029A2 Main Cranes for BOF and CCP (+120 t- 10 nos. crane)Pkg 029A2 Main Cranes for BOF and CCP (+120 t- 10 nos. crane)Pkg 029A2 Main Cranes for BOF and CCP (+120 t- 10 nos. crane)

238.4 Scrutiny, Discussions & Tender Finalisation 30 20-Aug-09 A 17-Oct-10 A

262 Firming up of price & Stage-II approval 15 18-Oct-10 A 27-Jan-11 A

262.1 Issue of LOI 0 29-Jan-11 A

366 Signing of contract with M/s HEC (24 months schedule) 0 12-Feb-11 A

447 Engg., Supply, Erection, Testing & Comm.- Large Cranes forSMS-3

731 13-Feb-11 A 02-Dec-15

Pkg 029B Main Cranes for BOF and CCP ( below 120 t)Pkg 029B Main Cranes for BOF and CCP ( below 120 t)Pkg 029B Main Cranes for BOF and CCP ( below 120 t)Pkg 029B Main Cranes for BOF and CCP ( below 120 t)Pkg 029B Main Cranes for BOF and CCP ( below 120 t)

168 Issue Draft TS (Issued ) 0 22-Jun-07 A

179 Discussion with BSP 12 28-Jun-07 A 09-Jul-07 A

190 Issue Final TS (Issued ) 14 24-Jul-07 A 25-Oct-07 A

201 Issue of NIT 2 26-Oct-07 A 27-Oct-07 A

212 Recpt of Tender at Bhilai 28 28-Oct-07 A 10-Jan-08 A

233 Recpt of Tender at Ranc hi 4 11-Jan-08 A 14-Jan-08 A

234 Scrutiny, Discussions & Tender Finalisation (Retendered) 30 15-Jan-08 A 01-Oct-09 A

234.1 Issue Final TS 14 16-Oct-09 A 10-Feb-10 A

234.2 Issue of NIT 2 11-Feb-10 A 15-Feb-10 A

234.3 Recpt of Tender at Bhilai 28 16-Feb-10 A 12-May-10 A

234.4 Recpt of Tender at Ranc hi 4 13-May-10 A 14-May-10 A

234.5 Scrutiny, Discussions & Tender Finalisation (Package split into two packages)

30 15-May-10 A 30-Apr-11 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 20 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

Pkg 029B1 EOT CRANES FOR BOF & CCP OF SMS-IIIPkg 029B1 EOT CRANES FOR BOF & CCP OF SMS-IIIPkg 029B1 EOT CRANES FOR BOF & CCP OF SMS-IIIPkg 029B1 EOT CRANES FOR BOF & CCP OF SMS-IIIPkg 029B1 EOT CRANES FOR BOF & CCP OF SMS-III

11050 Issue Draft TS (Issued ) 0 03-May-11 A

11060 Discussion with BSP 12 04-May-11 A 30-Jun-11 A

11070 Issue Final TS (Issued ) 14 01-Jul-11 A 20-Jul-11 A

11080 Issue of NIT 16 21-Jul-11 A 05-Aug-11 A

11080.1 Scrutiny, Discussions & Tender Finalisation 30 01-Sep-11 A 26-Feb-12 A

11080.2 Firming up of price & Stage-II approval (Re-tendered) 45 27-Feb-12 A 25-Jun-12 A

11080.21Issue of NIT 10 26-Jun-12 A 02-Jul-12 A

11080.22Scrutiny, Discussions & Tender Finalisation 30 01-Aug-12 A 26-Nov-12 A

11080.23Firming up of price & Stage-II approval (Re-tendered) 45 27-Nov-12 A 24-Dec-12 A

11080.33Issue of NIT 10 02-Apr-13 A 12-Apr-13 A

11080.43Scrutiny, Discussions & Tender Finalisation 30 01-Jun-13 A 26-Aug-13 A

11080.53Firming up of price & Stage-II approval 45 27-Aug-13 A 17-Jan-14 A

11080.6 Issue of LOI 0 30-Jan-14 A

11090 Signing of contract 0 18-Feb-14 A

11100 Engg., Supply, erection, Testing & Comm.- EOT cranes for BOF & CCP for SMS-III

547 19-Feb-14 A 18-Aug-15

Pkg 029B2 EOT CRANES, REPAIR TROLLIES & UNDER SLUNG CRANES FOR BOF & CCP OF SMS-IIIPkg 029B2 EOT CRANES, REPAIR TROLLIES & UNDER SLUNG CRANES FOR BOF & CCP OF SMS-IIIPkg 029B2 EOT CRANES, REPAIR TROLLIES & UNDER SLUNG CRANES FOR BOF & CCP OF SMS-IIIPkg 029B2 EOT CRANES, REPAIR TROLLIES & UNDER SLUNG CRANES FOR BOF & CCP OF SMS-IIIPkg 029B2 EOT CRANES, REPAIR TROLLIES & UNDER SLUNG CRANES FOR BOF & CCP OF SMS-III

11120 Issue Draft TS (Issued ) 0 10-May-11 A

11130.1 Discussion with BSP 12 11-May-11 A 30-Jun-11 A

11140 Issue Final TS (Issued ) 14 01-Jul-11 A 20-Jul-11 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 21 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

11140.01Issue of NIT 16 21-Jul-11 A 05-Aug-11 A

11140.13Scrutiny, Discussions & Tender Finalisation 30 01-Oct-11 A 02-May-12 A

11140.23Firming up of price & Stage-II approval 45 03-May-12 A 14-Jul-12 A

11140.33Issue of LOI 0 16-Jul-12 A

11170 Signing of contract (M/s MUKAND) 0 08-Aug-12 A

11180 Engg., Supply, erection, Testing & Comm.- EOT Cranes, repair trollies& under slung cranes for BOF & CCP

547 09-Aug-12 A 28-Apr-15

Pkg 029C Lift in SMS-IIIPkg 029C Lift in SMS-IIIPkg 029C Lift in SMS-IIIPkg 029C Lift in SMS-IIIPkg 029C Lift in SMS-III

11290 Issue Draft TS 0 28-Mar-14 A

11291 Discussion with BSP 12 29-Mar-14 A 10-May-14 A

11292 Issue Final TS 14 12-May-14 A 14-Aug-14 A

11293 Issue of NIT 16 30-Sep-14 15-Oct-14

11294 Scrutiny, Discussions & Tender Finalisation 30 15-Nov-14 14-Dec-14

11295 Firming up of price & Stage-II approval 30 15-Dec-14 13-Jan-15

11296 Issue of LOI 0 14-Jan-15

11300 Signing of contract 0 13-Feb-15

11310 Engg., Supply, erection, Testing & Comm.- Lift in SMS-III 273 13-Feb-15 12-Nov-15

Pkg 030 Hoisting & Handling facilities in BRM & URMPkg 030 Hoisting & Handling facilities in BRM & URMPkg 030 Hoisting & Handling facilities in BRM & URMPkg 030 Hoisting & Handling facilities in BRM & URMPkg 030 Hoisting & Handling facilities in BRM & URM

169 Issue Draft TS 0 21-Dec-10 A

170 Discussion with BSP 8 31-Jan-11 A 07-Feb-11 A

171 Issue Final TS 12 08-Feb-11 A 19-Feb-11 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 22 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

172 Issue of NIT 10 01-Mar-11 A 10-Mar-11 A

173 Recpt of Tender at Bhilai 45 11-Mar-11 A 11-Apr-11 A

174 Recpt of Tender at Ranc hi 5 12-Apr-11 A 15-Apr-11 A

175 Scrutiny, Discussions & Tender Finalisation 60 16-Apr-11 A 12-Nov-11 A

176 Firming-up of price of the package & Mngt. Approval 25 13-Oct-11 A 21-Dec-11 A

176.1 Issue of LOI 0 31-Dec-11 A

177 Signing of Contract with M/s HEC 0 21-Jan-12 A

178 Engg., Supply, Execution, Testing & Comm.-Hoisting & handling facilities in BRM & URM

547 23-Jan-12 A 17-Aug-15

Pkg 031 Hot Metal Handling System (Torpedo Ladles)Pkg 031 Hot Metal Handling System (Torpedo Ladles)Pkg 031 Hot Metal Handling System (Torpedo Ladles)Pkg 031 Hot Metal Handling System (Torpedo Ladles)Pkg 031 Hot Metal Handling System (Torpedo Ladles)

180 Issue Draft TS 0 17-Oct-07 A

181 Discussion with BSP 8 18-Oct-07 A 10-Dec-07 A

182 Issue Final TS 10 11-Dec-07 A 15-Jan-08 A

183 Issue of NIT 4 16-Jan-08 A 16-Feb-08 A

184 Recpt of Tender at Bhilai 43 17-Feb-08 A 30-Apr-08 A

185 Recpt of Tender at Ranc hi 5 01-May-08 A 10-May-08 A

186 Scrutiny, Discussions & Tender Finalisation (Retendered) 60 11-May-08 A 09-Mar-09 A

186.1 Issue Final TS 10 18-Apr-09 A 21-May-09 A

186.2 Issue of NIT 4 22-May-09 A 25-Jul-09 A

186.3 Recpt of Tender at Bhilai 43 26-Jul-09 A 22-Sep-09 A

186.4 Recpt of Tender at Ranc hi 5 24-Sep-09 A 05-Oct-09 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 23 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

186.5 Scrutiny, Discussions & Tender Finalisation 30 06-Oct-09 A 14-Jun-10 A

187 Firming-up of price of the package & Mngt. Approval 25 15-Jun-10 A 09-Aug-10 A

187.1 Issue of LOI 0 10-Aug-10 A

188 Signing of Contract with M/s AIFL (20 months schedule) 0 10-Sep-10 A

189 Engg., Supply, Execution, Testing & Comm.- Torpedo ladles 608 10-Sep-10 A 11-Apr-15

Pkg 032 Propane Storage and Distribution SystemPkg 032 Propane Storage and Distribution SystemPkg 032 Propane Storage and Distribution SystemPkg 032 Propane Storage and Distribution SystemPkg 032 Propane Storage and Distribution System

191 Issue Draft TS 0 29-Jan-10 A

192 Discussion with BSP 8 30-Jan-10 A 25-Feb-10 A

193 Issue Final TS 7 26-Feb-10 A 09-Mar-10 A

194 Issue of NIT 17 10-Mar-10 A 03-Apr-10 A

195 Recpt of Tender at Bhilai 45 05-Apr-10 A 04-May-10 A

196 Recpt of Tender at Ranc hi 5 05-May-10 A 07-May-10 A

197 Scrutiny, Discussions & Tender Finalisation 55 08-May-10 A 15-Feb-11 A

198 Firming-up of price of the package & Mngt. Approval 25 24-Feb-11 A 03-Mar-11 A

198.1 Issue of LOI 0 16-Mar-11 A

199 Signing of Contract with M/s OGPE (12 months schedule) 0 06-Apr-11 A

200 Engg., Supply, Execution, Testing & Comm.- LPG Storage 365 07-Apr-11 A 06-Mar-15

Pkg 033-A2 Civil Work for BOF & CCP ShopPkg 033-A2 Civil Work for BOF & CCP ShopPkg 033-A2 Civil Work for BOF & CCP ShopPkg 033-A2 Civil Work for BOF & CCP ShopPkg 033-A2 Civil Work for BOF & CCP Shop

202 Issue Draft TS (Issued ) 0 24-Aug-07 A

203 Discussion with BSP 7 03-Sep-07 A 17-Sep-07 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 24 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

204 Issue Final TS 10 21-Sep-07 A 26-Oct-07 A

205 Issue of NIT 5 27-Oct-07 A 13-Nov-07 A

206 Recpt of Tender at Bhilai 45 14-Nov-07 A 30-Dec-07 A

207 Recpt of Tender at Ranc hi 4 31-Dec-07 A 03-Jan-08 A

208 Scrutiny, Discussions & Tender Finalisation ( Retendered) 40 04-Jan-08 A 08-Jun-08 A

275 Issue of NIT 5 17-Apr-09 A 28-Apr-09 A

276 Recpt of Tender at Bhilai 45 29-Apr-09 A 30-Apr-09 A

276.1 Recpt of Tender at Ranc hi 4 01-May-09 A 02-May-09 A

276.2 Scrutiny, Discussions & Tender Finalisation 30 04-May-09 A 31-Oct-09 A

276.3 Firming-up of price of the package 20 02-Nov-09 A 20-Nov-09 A

276.4 Issue of LOI 0 24-Nov-09 A

276.5 Signing of Contract 0 05-Dec-09 A

276.50A Civil Work for BOF & CCP Shop 577 05-Dec-09 A 19-Feb-11 A

276.51A Signing of Contract with HSCL (20 months schedule) 0 21-Feb-11 A

276.52 Civil Work for BOF & CCP Shop (HSCL) stopped 577 21-Feb-11 A 31-Dec-12 A

276.53 Signing of Contract with Simplex (14 months schedule) 0 28-Feb-13 A

276.61 Civil Work for BOF & CCP Shop (Simplex) 425 01-Mar-13 A 09-Dec-14

Pkg 033A1 Piling work for BOF & CCP ShopPkg 033A1 Piling work for BOF & CCP ShopPkg 033A1 Piling work for BOF & CCP ShopPkg 033A1 Piling work for BOF & CCP ShopPkg 033A1 Piling work for BOF & CCP Shop

284 Issue Final TS 10 28-Jul-09 A 05-Aug-09 A

285 Issue of NIT 5 06-Aug-09 A 10-Aug-09 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 25 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

286 Recpt of Tender at Bhilai 30 11-Aug-09 A 27-Aug-09 A

328 Scrutiny, Discussions & Tender Finalisation 30 28-Aug-09 A 11-Nov-09 A

329 Firming-up of price of the package 15 12-Nov-09 A 31-Dec-09 A

330 Issue of LOI 0 01-Jan-10 A

331 Signing of Contract with M/s ERA (20 months schedule) 0 23-Jan-10 A

332 Piling Work for BOF & CCP Shop 273 25-Jan-10 A 16-Nov-14

Pkg 033-B Structural Work for BOF & CCP ShopPkg 033-B Structural Work for BOF & CCP ShopPkg 033-B Structural Work for BOF & CCP ShopPkg 033-B Structural Work for BOF & CCP ShopPkg 033-B Structural Work for BOF & CCP Shop

242 Issue Draft TS (Issued ) 0 24-Aug-07 A

243 Discussion with BSP 7 30-Aug-07 A 06-Sep-07 A

244 Issue Final TS 10 07-Sep-07 A 31-Oct-07 A

245 Issue of NIT 5 01-Nov-07 A 13-Nov-07 A

246 Recpt of Tender at Bhilai 22 14-Nov-07 A 25-Dec-07 A

247 Recpt of Tender at Ranc hi 4 26-Dec-07 A 31-Dec-07 A

247.1 Scrutiny, Discussions & Tender Finalisation (Retendered) 40 01-Jan-08 A 28-Aug-08 A

475 Issue of NIT 5 07-Mar-09 A 12-Mar-09 A

476 Recpt of Tender at Bhilai 22 13-Mar-09 A 15-Apr-09 A

477 Recpt of Tender at Ranc hi 4 16-Apr-09 A 27-Apr-09 A

477.1 Scrutiny, Discussions & Tender Finalisation 40 28-Apr-09 A 25-May-09 A

479 Firming-up of price of the package 40 26-May-09 A 15-Sep-09 A

479.1 Issue of LOI 0 16-Sep-09 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 26 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

479.2 Signing of Contract with M/s ERA (24 months schedule) 0 30-Sep-09 A

479.21 Structural Fabrication for BOF Shop 517 01-Oct-09 A 27-Oct-14

479.22 Structural Fabrication for CCP Shop 517 01-Oct-09 A 11-Nov-14

479.3 Structural Work for BOF Shop 547 06-Oct-11 A 02-Jun-15

479.4 Structural Work for CCP Shop 547 06-Oct-11 A 03-Feb-15

Pkg 036 Mobile equipment ( By BSP directly)Pkg 036 Mobile equipment ( By BSP directly)Pkg 036 Mobile equipment ( By BSP directly)Pkg 036 Mobile equipment ( By BSP directly)Pkg 036 Mobile equipment ( By BSP directly)

273 Issue Draft TS 0 30-Sep-14

274 Discussion with BSP 6 01-Oct-14 06-Oct-14

322 Issue Final TS 14 07-Oct-14 20-Oct-14

355 Issue of NIT 9 21-Oct-14 29-Oct-14

487 Recpt of Tender at Bhilai 43 30-Oct-14 11-Dec-14

487.1 Tender scrutiny, discussion & tender finalisation 45 12-Dec-14 25-Jan-15

487.11 Signing of contract 0 25-Jan-15

496 Supply of mobile equipment 547 26-Jan-15 25-Jul-16

Pkg 037 Centralised telecommunication system for full expansionPkg 037 Centralised telecommunication system for full expansionPkg 037 Centralised telecommunication system for full expansionPkg 037 Centralised telecommunication system for full expansionPkg 037 Centralised telecommunication system for full expansion

253 Issue Draft TS 0 20-Jun-08 A

254 Discussion with BSP 6 21-Jun-08 A 31-Mar-10 A

255 Issue Final TS 14 01-Apr-10 A 20-Apr-10 A

256 Issue of NIT 9 21-Apr-10 A 30-Apr-10 A

257 Recpt of Tender at Bhilai 43 01-May-10 A 11-Jun-10 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 27 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

257.1 Recpt of Tender at Ranc hi 6 12-Jun-10 A 18-Jun-10 A

257.2 Scrutiny, Discussions & Tender Finalisation (retendered) 60 19-Jun-10 A 22-Jan-11 A

257.20 Issue Final TS 14 10-Feb-11 A 23-May-11 A

257.21 Issue of NIT 5 24-May-11 A 24-Jun-11 A

257.22 Recpt of Tender at Bhilai 30 25-Jun-11 A 26-Jul-11 A

257.23 Recpt of Tender at Ranc hi 4 27-Jul-11 A 02-Aug-11 A

257.24 Scrutiny, Discussions & Tender Finalisation 30 03-Aug-11 A 17-Mar-12 A

257.3 Firming-up of price of the package & Mngt. Approval 15 19-Mar-12 A 16-May-12 A

257.4 Issue of LOI 0 17-May-12 A

257.5 Signing of Contract 0 12-Jul-12 A

257.6 Engg., Supply, Execution, Testing & Comm-Telecommunication system

456 13-Jul-12 A 31-Mar-16

Pkg 046 Bar and Rod MillPkg 046 Bar and Rod MillPkg 046 Bar and Rod MillPkg 046 Bar and Rod MillPkg 046 Bar and Rod Mill

291 Issue Draft TS (Issued) 0 25-Apr-07 A

292 Discussion with BSP 15 26-Apr-07 A 10-May-07 A

293 Issue Final TS (Issued) 14 11-May-07 A 15-Jun-07 A

294 Issue of NIT (Issued) 8 16-Jun-07 A 02-Jul-07 A

295 Recpt of Tender at Bhilai 47 03-Jul-07 A 29-Sep-07 A

296 Recpt of Tender at Ranc hi 5 01-Oct-07 A 03-Oct-07 A

297 Scrutiny, Discussions & Tender Finalisation(Pkg retendered) 60 15-Nov-07 A 05-Mar-08 A

297.1 Recpt of Tender at Ranc hi 5 01-Dec-09 A 04-Jan-10 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 28 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

297.2 Scrutiny, Discussions & Tender Finalisation 60 05-Jan-10 A 31-Mar-10 A

298 Firming-up of price of the package 30 01-Apr-10 A 26-Jul-10 A

298.1 Issue of LOI 0 27-Jul-10 A

299 Signing of Contract with M/s Denieli (24 months schedule) 0 25-Aug-10 A

300A Engg., Manufacture & supply 486 26-Aug-10 A 30-Oct-14

300B Erection of equipment 303 18-Feb-13 A 14-Jun-15

300C Testing & commissioning-BRM 60 11-Apr-16 10-Jun-16

Pkg 047 Universal Rail MillPkg 047 Universal Rail MillPkg 047 Universal Rail MillPkg 047 Universal Rail MillPkg 047 Universal Rail Mill

302 Issue Draft TS (Issued) 0 28-May-07 A

303 Discussion with BSP 9 29-May-07 A 11-Jun-07 A

304 Issue Final TS (Issued) 14 22-Jun-07 A 11-Sep-07 A

305 Issue of NIT (Issued ) 8 05-Sep-07 A 12-Sep-07 A

306 Recpt of Tender at Bhilai 57 13-Sep-07 A 20-Jan-08 A

307 Recpt of Tender at Ranc hi 6 21-Jan-08 A 26-Jan-08 A

308 Scrutiny, Discussions & Tender Finalisation 60 27-Jan-08 A 20-Aug-08 A

309 Firming-up of price of the package & stage-II approval ( Retendered )

45 21-Aug-08 A 28-Feb-09 A

315 Issue of NIT (Issued ) 8 16-Mar-09 A 19-Mar-09 A

316 Recpt of Tender at Bhilai 57 20-Mar-09 A 11-May-09 A

317 Recpt of Tender at Ranc hi 6 12-May-09 A 14-May-09 A

318 Scrutiny, Discussions & Tender Finalisation 45 15-May-09 A 20-Aug-09 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 29 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

319 Firming-up of price of the package & stage-II approval 30 21-Aug-09 A 26-Jul-10 A

319.1 Issue of LOI 0 27-Jul-10 A

319.2 Signing of Contract with M/s SMS MEER (34 months schedule)

0 23-Aug-10 A

319.21 Engg., Manufacture & supply 486 24-Aug-10 A 01-Nov-14

319.22 Erection of equipment 303 18-Feb-13 A 09-Jul-15

319.3 Testing & Comm. - URM 60 06-Jul-16 04-Sep-16

Pkg 047-01 Drop Test Facility for URMPkg 047-01 Drop Test Facility for URMPkg 047-01 Drop Test Facility for URMPkg 047-01 Drop Test Facility for URMPkg 047-01 Drop Test Facility for URM

11210 Issue Final TS 14 01-Jun-11 A 15-Jun-11 A

11220 Issue of NIT 9 28-Jun-11 A 05-Jul-11 A

11230 Recpt of Tender at Bhilai 43 06-Jul-11 A 31-Oct-11 A

11240 Recpt of Tender at Ranc hi 6 01-Nov-11 A 10-Nov-11 A

11250 Scrutiny, Discussions & Tender Finalisation (Package Retendered)

60 11-Nov-11 A 26-Apr-12 A

11250.03Issue of Final TS 14 19-May-12 A 24-May-12 A

11250.04Issue of NIT 9 15-Jun-12 A 22-Jun-12 A

11250.05Recpt of Tender at Bhilai 43 23-Jun-12 A 30-Jul-12 A

11250.06Recpt of Tender at Ranc hi 6 31-Jul-12 A 08-Aug-12 A

11250.07Scrutiny, Discussions & Tender Finalisation 60 09-Aug-12 A 16-Aug-12 A

11260 Firming-up of price of the package & Mngt. Approval 25 17-Aug-12 A 06-Sep-13 A

11265 Issue of LOI 0 09-Sep-13 A

11270 Signing of Contract 0 13-Sep-13 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 30 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

11280 Engg., Supply, Execution, Testing & Comm Drop Test Facilityfor URM

365 13-Sep-13 A 31-Dec-14

Pkg 049-01 Reheating Furnace for BRMPkg 049-01 Reheating Furnace for BRMPkg 049-01 Reheating Furnace for BRMPkg 049-01 Reheating Furnace for BRMPkg 049-01 Reheating Furnace for BRM

554 Issue Draft TS 0 11-Dec-08 A

557 Issue of NIT 7 12-Dec-08 A 27-Jan-09 A

558 Recpt of Tender at Bhilai 30 28-Jan-09 A 30-Apr-09 A

559 Recpt of Tender at Ranc hi 5 01-May-09 A 02-May-09 A

559.1 Scrutiny, Discussions & Tender Finalisation ( Retendered ) 45 05-Jul-09 A 30-Oct-09 A

559.10 Issue of NIT 7 01-Jun-10 A 04-Jun-10 A

559.11 Recpt of Tender at Ranc hi 5 21-Jul-10 A 24-Jul-10 A

559.12 Scrutiny, Discussions & Tender Finalisation 45 26-Jul-10 A 30-Nov-10 A

559.2 Firming-up of price of the package & stage-II approval 30 01-Dec-10 A 15-Dec-10 A

559.3 Issue of LOI 0 10-Jan-11 A

559.4 Signing of Contract with M/s Fivestein (21 months schedule) 0 09-Feb-11 A

559.5 Engg., Supply, Execution, Testing & Comm.- RH Fces 638 10-Feb-11 A 17-Jun-15

Pkg 049-03 Reheating Furnace for URMPkg 049-03 Reheating Furnace for URMPkg 049-03 Reheating Furnace for URMPkg 049-03 Reheating Furnace for URMPkg 049-03 Reheating Furnace for URM

614 Issue Draft TS 0 19-Dec-08 A

614.102 Issue of NIT 7 20-Dec-08 A 24-Feb-09 A

614.112 Recpt of Tender at Bhilai 30 25-Feb-09 A 30-Apr-09 A

614.122 Recpt of Tender at Ranc hi 5 01-May-09 A 02-May-09 A

614.132 Scrutiny, Discussions & Tender Finalisation (Retendered) 45 04-May-09 A 30-Jun-10 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 31 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

614.2 Issue final TS 0 26-Nov-10 A

614.3 Issue of NIT 7 27-Nov-10 A 04-Dec-10 A

614.4 Recpt of Tender at Bhilai 30 23-Dec-10 A 10-Jan-11 A

614.5 Recpt of Tender at Ranc hi 5 11-Jan-11 A 16-Jan-11 A

614.6 Scrutiny, Discussions & Tender Finalisation 45 17-Jan-11 A 01-Jun-11 A

614.9 Signing of Contract with M/s Fivestein (21 months schedule) 0 13-Jul-11 A

614.92 Engg., Supply, Execution, Testing & Comm.- RH Fces 638 14-Jul-11 A 26-May-15

Pkg 051A/1 Civil Work for BRMPkg 051A/1 Civil Work for BRMPkg 051A/1 Civil Work for BRMPkg 051A/1 Civil Work for BRMPkg 051A/1 Civil Work for BRM

599 Issue of NIT 8 04-Jun-09 A 12-Jun-09 A

600.1 Recpt of Tender at Bhilai 15 13-Jun-09 A 11-Jul-09 A

606 Recpt of Tender at Ranc hi 5 13-Jul-09 A 31-Jul-09 A

607 Scrutiny, Discussions & Tender Finalisation 20 01-Aug-09 A 07-Oct-09 A

608 Firming-up of price of the package 15 08-Oct-09 A 11-Dec-10 A

609 Issue of LOI 0 19-Dec-10 A

609.1 Signing of Contract with M/s HSCL (20 months schedule) 0 30-Dec-10 A

609.2 Civil Work for BRM 608 30-Dec-10 A 04-Dec-14

Pkg 051B/1 Structural Work fo BRMPkg 051B/1 Structural Work fo BRMPkg 051B/1 Structural Work fo BRMPkg 051B/1 Structural Work fo BRMPkg 051B/1 Structural Work fo BRM

899 Issue of NIT 8 04-Jun-09 A 12-Jun-09 A

940 Recpt of Tender at Bhilai 20 13-Jun-09 A 10-Jul-09 A

951 Recpt of Tender at Ranc hi 5 11-Jul-09 A 31-Jul-09 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 32 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

952 Scrutiny, Discussions & Tender Finalisation 20 02-Aug-09 A 09-Sep-09 A

958 Firming-up of price of the package 15 10-Sep-09 A 25-Jul-10 A

960 Effective date of Contract 0 07-Sep-10 A

960a Signing of Contract with M/s HSCL (21 months schedule) 0 16-Sep-10 A

961 Structural Work for B&RM 608 08-Sep-10 A 03-Jan-15

Pkg 052-A Civil Work for URMPkg 052-A Civil Work for URMPkg 052-A Civil Work for URMPkg 052-A Civil Work for URMPkg 052-A Civil Work for URM

357 Issue Draft TS (Issued ) 0 01-Sep-07 A

358 Discussion with BSP 4 03-Sep-07 A 06-Sep-07 A

359 Issue Final TS 12 07-Sep-07 A 26-Oct-07 A

360 Issue of NIT 10 27-Oct-07 A 16-Nov-07 A

361 Recpt of Tender at Bhilai 45 17-Nov-07 A 25-Dec-07 A

362 Recpt of Tender at Ranc hi 5 26-Dec-07 A 31-Dec-07 A

363 Scrutiny, Discussions & Tender Finalisation ( Retendered) 60 01-Jan-08 A 08-Jun-08 A

470 Issue of NIT 10 16-Apr-09 A 27-Apr-09 A

471 Recpt of Tender at Bhilai 45 28-Apr-09 A 30-Apr-09 A

472 Recpt of Tender at Ranc hi 5 01-May-09 A 02-May-09 A

473 Scrutiny, Discussions & Tender Finalisation 60 04-May-09 A 16-Jun-09 A

473.1 Firming-up of price of the package & stage-II approval 20 17-Jun-09 A 29-Jul-10 A

473.3 Signing of Contract M/s HSCL (18 months schedule) 0 09-Aug-10 A

473.4 Civil work for Universal Rail Mill 578 09-Aug-10 A 18-Nov-14

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 33 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

Pkg 052-B Structural Work for URMPkg 052-B Structural Work for URMPkg 052-B Structural Work for URMPkg 052-B Structural Work for URMPkg 052-B Structural Work for URM

857 Issue Draft TS (Issued ) 0 01-Sep-07 A

858 Discussion with BSP 4 03-Sep-07 A 06-Sep-07 A

859 Issue Final TS 12 07-Sep-07 A 26-Oct-07 A

860 Issue of NIT 10 27-Oct-07 A 15-Nov-07 A

861 Recpt of Tender at Bhilai 45 16-Nov-07 A 31-Dec-07 A

862 Recpt of Tender at Ranc hi 5 01-Jan-08 A 05-Jan-08 A

863 Scrutiny, Discussions & Tender Finalisation (Retendered) 60 06-Jan-08 A 08-Jun-08 A

930 Issue of NIT 10 20-Apr-09 A 28-Apr-09 A

9390 Recpt of Tender at Bhilai 45 29-Apr-09 A 30-Apr-09 A

9400 Recpt of Tender at Ranc hi 5 01-May-09 A 02-May-09 A

941.1 Scrutiny, Discussions & Tender Finalisation (Retendered ) 30 04-May-09 A 16-Jan-10 A

941.2 Issue of NIT 10 28-Jan-10 A 01-Feb-10 A

941.3 Recpt of Tender at Bhilai 45 02-Feb-10 A 03-Mar-10 A

942 Recpt of Tender at Ranc hi 5 17-Mar-10 A 24-Mar-10 A

943 Scrutiny, Discussions & Tender Finalisation 30 25-Mar-10 A 27-Oct-10 A

944 Firming-up of price of the package & stage-II approval 15 28-Oct-10 A 11-Nov-10 A

945 Issue of LOI 0 25-Nov-10 A

946 Signing of Contract with M/s HSCL (20 months schedule) 0 10-Dec-10 A

947 Structural work for Universal Rail Mill 609 10-Dec-10 A 10-May-15

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 34 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

Pkg 070 Augmentation of MSDS - I, III, IV, V & VI incl. HT network, etcPkg 070 Augmentation of MSDS - I, III, IV, V & VI incl. HT network, etcPkg 070 Augmentation of MSDS - I, III, IV, V & VI incl. HT network, etcPkg 070 Augmentation of MSDS - I, III, IV, V & VI incl. HT network, etcPkg 070 Augmentation of MSDS - I, III, IV, V & VI incl. HT network, etc

403 Issue Draft TS (Issued ) 0 13-Jul-07 A

404 Discussion with BSP 20 20-Jul-07 A 08-Aug-07 A

405 Issue Final TS (Issued ) 15 27-Aug-07 A 15-Sep-07 A

406 Issue of NIT (Issued ) 24 16-Sep-07 A 29-Sep-07 A

407 Recpt of Tender at Bhilai 45 01-Oct-07 A 15-Dec-07 A

408 Recpt of Tender at Ranc hi 5 16-Dec-07 A 20-Dec-07 A

409 Scrutiny, Discussions & Tender Finalisation 60 21-Dec-07 A 07-Apr-08 A

410 Firming-up of price of the package & stage-II approval 30 08-Apr-08 A 02-Sep-08 A

410.1 Issue of LOI 0 03-Sep-08 A

411 Signing of Contract with M/s AREVA (24 months schedule) 0 25-Sep-08 A

412 Engg., Supply, Execution, Testing & Comm.- MSDS Augm. 730 26-Sep-08 A 08-Nov-14

Pkg 070A Augmentation of MSDS (Additional)Pkg 070A Augmentation of MSDS (Additional)Pkg 070A Augmentation of MSDS (Additional)Pkg 070A Augmentation of MSDS (Additional)Pkg 070A Augmentation of MSDS (Additional)

11640 Issue Draft TS 0 28-Nov-11 A

11650 Discussion with BSP 10 29-Nov-11 A 30-Jun-12 A

11660 Issue Final TS 15 02-Jul-12 A 04-Apr-14 A

11670 Issue of NIT 10 05-May-14 A 15-May-14 A

11680 Recpt of Tender at Bhilai 45 16-May-14 A 13-Nov-14

11690 Recpt of Tender at Ranc hi 5 14-Nov-14 18-Nov-14

11700 Scrutiny, Discussions & Tender Finalisation 60 19-Nov-14 17-Jan-15

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 35 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

11710 Firming-up of price of the package & stage-II approval 30 18-Jan-15 16-Feb-15

11715 Issue of LOI 0 17-Feb-15

11720 Signing of Contract 0 19-Mar-15

11730 Engg., Supply, Execution, Testing & Comm.- MSDS Augm. (Additional)

365 20-Mar-15 18-Mar-16

Pkg 071A All Distribution HT Sub-Stations located near Main Tech. PkgsPkg 071A All Distribution HT Sub-Stations located near Main Tech. PkgsPkg 071A All Distribution HT Sub-Stations located near Main Tech. PkgsPkg 071A All Distribution HT Sub-Stations located near Main Tech. PkgsPkg 071A All Distribution HT Sub-Stations located near Main Tech. Pkgs

414 Issue Draft TS 0 29-Jan-09 A

417 Issue of NIT 9 23-Jan-10 A 01-Feb-10 A

418 Recpt of Tender at Bhilai 45 02-Feb-10 A 08-Mar-10 A

419 Recpt of Tender at Ranc hi 5 09-Mar-10 A 29-Mar-10 A

420 Scrutiny, Discussions & Tender Finalisation (Retendered ) 30 30-Mar-10 A 18-Sep-10 A

420.1 Issue of TS 0 30-Sep-10 A

420.2 Issue of NIT 9 01-Oct-10 A 16-Oct-10 A

420.3 Recpt of Tender at Bhilai 45 18-Oct-10 A 10-Nov-10 A

420.4 Recpt of Tender at Ranc hi 5 11-Nov-10 A 17-Nov-10 A

420.5 Scrutiny, Discussions & Tender Finalisation 30 18-Nov-10 A 22-Feb-11 A

421 Firming-up of price of the package & Mngt. Approval 30 23-Feb-11 A 29-Jul-11 A

422 Signing of Contract with M/s ABB (20 months s chedule) 0 02-Sep-11 A

423 Engg., Supply, Execution, Testing & Comm.- HT S/s 608 02-Sep-11 A 24-May-15

9650 Engg., Supply, Execution, Testing & Comm.- HT S/s (Part) 0 15-Feb-15

Pkg 075 Interplant Fuel Gas & Industrial Gas Piping for all UnitsPkg 075 Interplant Fuel Gas & Industrial Gas Piping for all UnitsPkg 075 Interplant Fuel Gas & Industrial Gas Piping for all UnitsPkg 075 Interplant Fuel Gas & Industrial Gas Piping for all UnitsPkg 075 Interplant Fuel Gas & Industrial Gas Piping for all Units

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 36 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

429 Issue of NIT 9 01-Mar-10 A 13-Mar-10 A

430 Recpt of Tender at Bhilai 45 15-Mar-10 A 30-Apr-10 A

431 Recpt of Tender at Ranc hi 5 01-May-10 A 03-May-10 A

432 Scrutiny, Discussions & Tender Finalisation 60 04-May-10 A 01-Oct-10 A

433 Firming-up of price of the package & Mngt. Approval 30 02-Oct-10 A 01-Nov-10 A

433.1 Issue of LOI 0 21-Dec-10 A

434 Signing of Contract with TATA Projects (15 months schedule)

0 22-Jan-11 A

435 Engg., Supply, Execution, Testing & Comm.- I/P Gas Piping 456 21-Jan-11 A 25-Apr-15

Pkg 075A Energy monitoring systemPkg 075A Energy monitoring systemPkg 075A Energy monitoring systemPkg 075A Energy monitoring systemPkg 075A Energy monitoring system

433.11 Issue of draft TS 0 26-Nov-10 A

433.31 Issue of final TS 0 10-Mar-11 A

9670 Issue of NIT 9 11-Mar-11 A 04-May-11 A

9680 Recpt of Tender at Bhilai 30 05-May-11 A 25-Jun-11 A

9690 Recpt of Tender at Ranc hi 5 27-Jun-11 A 30-Jun-11 A

9700 Scrutiny, Discussions & Tender Finalisation 60 30-Jun-11 A 16-Mar-12 A

9710 Firming-up of price of the package & Mngt. Approval 30 17-Mar-12 A 29-May-12 A

9720 Signing of Contract 0 30-May-12 A

9730 Engg., Supply, Execution, Testing & Comm.-Energy monitoring system

547 01-Jun-12 A 04-Sep-16

Pkg 075B Storage vessel and PRMS for O2,N2Pkg 075B Storage vessel and PRMS for O2,N2Pkg 075B Storage vessel and PRMS for O2,N2Pkg 075B Storage vessel and PRMS for O2,N2Pkg 075B Storage vessel and PRMS for O2,N2

433.21 Issue of draft TS 0 11-Nov-10 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 37 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

433.41 Issue of final TS 0 28-Dec-10 A

9740 Issue of NIT 9 18-Jan-11 A 27-Jan-11 A

9750 Recpt of Tender at Bhilai 45 28-Jan-11 A 10-Mar-11 A

9760 Recpt of Tender at Ranc hi 5 11-Mar-11 A 15-Mar-11 A

9770 Scrutiny, Discussions & Tender Finalisation 60 16-Mar-11 A 09-Feb-12 A

9780 Firming-up of price of the package & Mngt. Approval 30 10-Feb-12 A 30-Jun-12 A

9790 Signing of Contract with M/s Blue Star 0 07-Jul-12 A

9800 Engg., Supply, Execution, Testing & Comm.-Storage vessel 547 09-Jul-12 A 12-Aug-15

Pkg 076 Gas Mixing & Boosting StationPkg 076 Gas Mixing & Boosting StationPkg 076 Gas Mixing & Boosting StationPkg 076 Gas Mixing & Boosting StationPkg 076 Gas Mixing & Boosting Station

437 Issue Draft TS 0 04-Nov-08 A

438 Discussion with BSP 8 05-Nov-08 A 31-Mar-10 A

439 Issue Final TS 14 01-Apr-10 A 10-Apr-10 A

440 Issue of NIT 7 12-Apr-10 A 13-Apr-10 A

441 Recpt of Tender at Bhilai 45 14-Apr-10 A 18-Jun-10 A

442 Recpt of Tender at Ranc hi 5 19-Jun-10 A 24-Jun-10 A

443 Scrutiny, Discussions & Tender Finalisation (Retendered) 60 25-Jun-10 A 09-Feb-11 A

443.1 Issue Final TS 14 10-Feb-11 A 25-Feb-11 A

443.2 Issue of NIT 2 28-Feb-11 A 04-Apr-11 A

443.3 Recpt of Tender at Bhilai 45 05-Apr-11 A 26-Apr-11 A

443.4 Recpt of Tender at Ranc hi 4 27-Apr-11 A 29-Apr-11 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 38 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

443.5 Scrutiny, Discussions & Tender Finalisation 60 30-Apr-11 A 29-Sep-11 A

444 Firming-up of price of the package & Mngt. Approval 20 30-Sep-11 A 21-Nov-11 A

444.1 Issue of LOI 0 28-Nov-11 A

445 Signing of Contract with M/s NICCO 0 05-Jan-12 A

446 Engg., Supply, Execution, Testing & Comm.- Gax Mix Stn 365 27-Dec-11 A 28-Oct-14

Pkg 077-01 Water Supply System for BOF& CCPPkg 077-01 Water Supply System for BOF& CCPPkg 077-01 Water Supply System for BOF& CCPPkg 077-01 Water Supply System for BOF& CCPPkg 077-01 Water Supply System for BOF& CCP

448 Issue Draft TS 0 15-Apr-10 A

449 Discussion with BSP 8 16-Apr-10 A 22-Nov-10 A

450 Issue Final TS 14 26-Nov-10 A 10-Dec-10 A

451 Issue of NIT 9 02-Jan-11 A 11-Jan-11 A

452 Recpt of Tender at Bhilai 30 31-Jan-11 A 18-Feb-11 A

453 Recpt of Tender at Ranc hi 5 18-Feb-11 A 22-Feb-11 A

454 Scrutiny, Discussions & Tender Finalisation (Retendered) 45 23-Feb-11 A 02-Apr-11 A

454.1 Issue Final TS 14 04-Apr-11 A 07-Jun-11 A

454.2 Issue of NIT 9 08-Jun-11 A 16-Jun-11 A

454.3 Recpt of Tender at Bhilai 30 17-Jun-11 A 16-Jul-11 A

454.4 Recpt of Tender at Ranc hi 5 18-Jul-11 A 02-Aug-11 A

454.5 Scrutiny, Discussions & Tender Finalisation 30 03-Aug-11 A 17-Mar-12 A

455 Firming-up of price of the package & Mngt. Approval 30 19-Mar-12 A 28-Jun-12 A

456 Signing of Contract 0 29-Jun-12 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 39 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

457 Engg., Supply, Execution, Testing & Comm.- Water Supply system

456 30-Jun-12 A 17-Aug-15

Pkg 077-02 Water Supply System for BRM & URM incl. RHFPkg 077-02 Water Supply System for BRM & URM incl. RHFPkg 077-02 Water Supply System for BRM & URM incl. RHFPkg 077-02 Water Supply System for BRM & URM incl. RHFPkg 077-02 Water Supply System for BRM & URM incl. RHF

9530 Issue Draft TS 0 31-Mar-11 A

9540 Discussion with BSP 8 01-Apr-11 A 01-Jun-11 A

9550 Issue Final TS 14 02-Jun-11 A 16-Jun-11 A

9560 Issue of NIT 9 17-Jun-11 A 04-Jul-11 A

9570 Recpt of Tender at Bhilai 30 05-Jul-11 A 24-Aug-11 A

9580 Recpt of Tender at Ranc hi 5 25-Aug-11 A 30-Aug-11 A

9590 Scrutiny, Discussions & Tender Finalisation 30 01-Sep-11 A 30-May-12 A

9600 Firming-up of price of the package & Mngt. Approval 30 31-May-12 A 16-Jun-12 A

9610 Signing of Contract 0 22-Sep-12 A

9620 Engg., Supply, Execution, Testing & Comm.- Water Supply 456 24-Sep-12 A 17-Aug-15

Pkg 078 Make-up Water Supply System AugmentationPkg 078 Make-up Water Supply System AugmentationPkg 078 Make-up Water Supply System AugmentationPkg 078 Make-up Water Supply System AugmentationPkg 078 Make-up Water Supply System Augmentation

459 Issue Draft TS 0 31-Jul-09 A

460 Discussion with BSP 10 01-Aug-09 A 31-Aug-09 A

461 Issue Final TS 14 01-Sep-09 A 23-Apr-10 A

462 Issue of NIT 7 24-Apr-10 A 03-Jun-10 A

463 Recpt of Tender at Bhilai 45 04-Jun-10 A 07-Aug-10 A

464 Recpt of Tender at Ranc hi 5 09-Aug-10 A 13-Aug-10 A

465 Scrutiny, Discussions & Tender Finalisation (retendered) 60 14-Aug-10 A 01-Dec-10 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 40 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

465.1 Issue Final TS 14 04-Dec-10 A 16-Dec-10 A

465.2 Issue of NIT 2 17-Dec-10 A 18-Dec-10 A

465.3 Recpt of Tender at Bhilai 45 19-Dec-10 A 03-Feb-11 A

465.4 Recpt of Tender at Ranc hi 4 03-Feb-11 A 07-Feb-11 A

465.5 Scrutiny, Discussions & Tender Finalisation 30 05-Feb-11 A 27-Jul-11 A

466 Firming-up of price of the package & Mngt. Approval 20 28-Jul-11 A 25-Aug-11 A

466.1 Issue of LOI 0 08-Sep-11 A

467 Signing of Contract with M/s Vishwa infrastructures 0 01-Oct-11 A

468 Engg., Supply, Execution, Testing & Comm.- Make-up Water 456 02-Oct-11 A 02-Aug-15

Pkg 095-B All internal rail networkPkg 095-B All internal rail networkPkg 095-B All internal rail networkPkg 095-B All internal rail networkPkg 095-B All internal rail network

878 Issue Draft TS 0 29-Mar-08 A

878.1 Discussion with BSP 14 30-Mar-08 A 13-Jan-09 A

920 Issue Final TS 14 14-Jan-09 A 27-Oct-09 A

921 Issue of NIT 38 28-Oct-09 A 15-Dec-09 A

922 Recpt of Tender at Bhilai 45 16-Dec-09 A 30-Jan-10 A

922.1 Recpt of Tender at Ranc hi 5 01-Feb-10 A 05-Feb-10 A

922.2 Scrutiny, Discussions & Tender Finalisation 45 06-Feb-10 A 14-May-10 A

925 Firming-up of price of the package & Mngt. Approval 30 15-May-10 A 19-Jul-10 A

925.2 Signing of Contract with M/s ISC projects P Ltd. 0 18-Aug-10 A

925.3 All internal network 912 19-Aug-10 A 30-Jun-15

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 41 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

Pkg 098-2 Track mobile locomotivePkg 098-2 Track mobile locomotivePkg 098-2 Track mobile locomotivePkg 098-2 Track mobile locomotivePkg 098-2 Track mobile locomotive

601 Issue Draft TS 0 25-Jan-08 A

602 Discussion with BSP 10 26-Jan-08 A 03-Jun-08 A

603 Issue Final TS 14 04-Jun-08 A 12-Jun-08 A

604 Issue of NIT ( Direct procurement by BSP) - (Package re-tendered)

8 13-Jun-08 A 25-Jun-11 A

605 Issue of Draft TS 0 25-Dec-12 A 31-Dec-12 A

615 Discussion with BSP 10 01-Jan-13 A 10-Jan-13 A

625 Issue Final TS 15 11-Jan-13 A 28-Jan-13 A

635 Issue of NIT 8 29-Jan-13 A 30-Aug-13 A

635.17 Recpt of Tender at Bhilai 35 02-Sep-13 A 08-Nov-13 A

635.27 Recpt of Tender at Ranc hi 5 09-Nov-13 A 09-Dec-13 A

635.37 Scrutiny, Discussions & Tender Finalisation 60 10-Dec-13 A 23-Jun-14 A

635.47 Firming-up of price of the package & Mngt. Approval 25 30-Sep-14 24-Oct-14

635.57 Issue of LOI 0 01-Nov-14

635.67 Signing of Contract 0 01-Dec-14

635.77 Procurement of Mobile road tenasport Equipmets (Truck, Damper)

243 02-Dec-14 01-Aug-15

Pkg 098-3 Mobile Fire fighting equipmentsPkg 098-3 Mobile Fire fighting equipmentsPkg 098-3 Mobile Fire fighting equipmentsPkg 098-3 Mobile Fire fighting equipmentsPkg 098-3 Mobile Fire fighting equipments

611 Issue Draft TS 0 10-Jul-08 A

612 Discussion with BSP 10 11-Jul-08 A 05-Jan-10 A

613 Issue Final TS 14 06-Jan-10 A 27-Sep-10 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 42 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

644 Issue of NIT 8 28-Sep-10 A 20-Jan-11 A

644.1 Recpt of Tender at Bhilai 35 21-Jan-11 A 11-Mar-11 A

644.2 Recpt of Tender at Ranc hi 5 12-Mar-11 A 19-Mar-11 A

644.3 Scrutiny, Discussions & Tender Finalisation ( Direct procurement by BSP)

60 21-Mar-11 A 13-Dec-13 A

Pkg 099 60T Weigh Bridge / 150T Rail Weigh bridgePkg 099 60T Weigh Bridge / 150T Rail Weigh bridgePkg 099 60T Weigh Bridge / 150T Rail Weigh bridgePkg 099 60T Weigh Bridge / 150T Rail Weigh bridgePkg 099 60T Weigh Bridge / 150T Rail Weigh bridge

572 Issue Draft TS 0 08-Feb-08 A

573 Discussion with BSP 14 09-Feb-08 A 05-Jun-08 A

574 Issue Final TS 15 06-Jun-08 A 18-Jun-08 A

574.1 Issue of Revised FTS 15 15-Feb-11 A 21-Mar-11 A

575 Issue of NIT 10 22-Mar-11 A 25-May-11 A

576 Recpt of Tender at Bhilai 45 26-May-11 A 08-Jul-11 A

577 Recpt of Tender at Ranc hi 5 09-Jul-11 A 13-Jul-11 A

578 Scrutiny, Discussions & Tender Finalisation (Retendered)- Pkg split into two packages

45 14-Jul-11 A 24-Feb-12 A

Pkg 099A Rail and Road Weigh bridgePkg 099A Rail and Road Weigh bridgePkg 099A Rail and Road Weigh bridgePkg 099A Rail and Road Weigh bridgePkg 099A Rail and Road Weigh bridge

11340 Issue Draft TS 0 03-Mar-12 A

11350 Discussion with BSP 14 05-Mar-12 A 19-Mar-12 A

11360 Issue Final TS 15 20-Mar-12 A 30-Jul-12 A

11370 Issue of NIT 10 31-Jul-12 A 01-Sep-12 A

11380 Recpt of Tender at Bhilai 45 03-Sep-12 A 30-Sep-12 A

11390 Recpt of Tender at Ranc hi 5 02-Oct-12 A 17-Oct-12 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 43 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

11392 Scrutiny, Discussions & Tender Finalisation (Retendered) 45 18-Oct-12 A 31-Aug-13 A

11393 Issue Final TS 15 02-Sep-13 A 12-Sep-13 A

11395 Recpt of Tender at Bhilai 5 19-Dec-13 A 30-Dec-13 A

11396 Recpt of Tender at Ranc hi 5 31-Dec-13 A 04-Jan-14 A

11400 Scrutiny, Discussions & Tender Finalisation 45 06-Jan-14 A 18-Aug-14 A

11410 Firming-up of price of the package & Mngt. Approval 10 30-Sep-14 09-Oct-14

11415 Issue of LOI 0 17-Oct-14

11420 Signing of Contract 0 27-Oct-14

11430 Engg., Supply, Execution, Testing & Comm.- Rail & Road Weigh Bridge

365 27-Oct-14 26-Oct-15

Pkg 099B Hot Metal Rail Weigh bridgePkg 099B Hot Metal Rail Weigh bridgePkg 099B Hot Metal Rail Weigh bridgePkg 099B Hot Metal Rail Weigh bridgePkg 099B Hot Metal Rail Weigh bridge

11440 Issue Draft TS 0 03-Mar-12 A

11450 Discussion with BSP 14 05-Mar-12 A 19-Mar-12 A

11460 Issue Final TS 15 20-Mar-12 A 30-Jul-12 A

11470 Issue of NIT 10 31-Jul-12 A 24-Aug-12 A

11480 Recpt of Tender at Bhilai 45 25-Aug-12 A 07-Oct-12 A

11490 Recpt of Tender at Ranc hi 5 08-Oct-12 A 15-Oct-12 A

11500 Scrutiny, Discussions & Tender Finalisation 45 16-Oct-12 A 08-Dec-12 A

11510 Firming-up of price of the package & Mngt. Approval 10 10-Dec-12 A 31-Mar-14 A

11515 Issue of LOI 0 16-Apr-14 A

11520 Signing of Contract 0 15-May-14 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 44 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

11530 Engg., Supply, Execution, Testing & Comm.- Hot Metal Rail Weigh Bridge

365 16-May-14 A 31-May-15

Pkg 100-2 Road works & road culvert over Tandula canalPkg 100-2 Road works & road culvert over Tandula canalPkg 100-2 Road works & road culvert over Tandula canalPkg 100-2 Road works & road culvert over Tandula canalPkg 100-2 Road works & road culvert over Tandula canal

10380 Signing of Contract with M/s HSCL 0 25-Feb-10 A

10390 Construction of road works & road culvert over Tandula canal

365 26-Feb-10 A 31-Dec-14

Pkg 100-3 Storm water drainage system ( merged with 100-4)Pkg 100-3 Storm water drainage system ( merged with 100-4)Pkg 100-3 Storm water drainage system ( merged with 100-4)Pkg 100-3 Storm water drainage system ( merged with 100-4)Pkg 100-3 Storm water drainage system ( merged with 100-4)

10400 Issue Draft TS 0 09-Dec-11 A

10410 Discussion with BSP 10 10-Dec-11 A 25-Feb-12 A

10420 Issue Final TS 11 27-Feb-12 A 07-Mar-12 A

10430 Issue of NIT 10 30-Sep-14 09-Oct-14*

10440 Recpt of Tender at Bhilai 35 10-Oct-14 13-Nov-14

10450 Recpt of Tender at Ranc hi 5 14-Nov-14 18-Nov-14

10460 Scrutiny, Discussions & Tender Finalisation 45 19-Nov-14 02-Jan-15

10470 Firming-up of price of the package & Mngt. Approval 20 03-Jan-15 22-Jan-15

10470.1 Issue of LOI 0 30-Jan-15

10480 Signing of Contract 0 01-Mar-15

10490 Construction of storm water drainage system 303 02-Mar-15 29-Dec-15

Pkg 110 Part- A Survey of New Sites & Soil TestingPkg 110 Part- A Survey of New Sites & Soil TestingPkg 110 Part- A Survey of New Sites & Soil TestingPkg 110 Part- A Survey of New Sites & Soil TestingPkg 110 Part- A Survey of New Sites & Soil Testing

618 Issue Draft TS (Issued) 0 28-May-07 A

619 Discussion with BSP 5 29-May-07 A 01-Jun-07 A

620 Issue Final TS (Issued ) 8 02-Jun-07 A 05-Jun-07 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 45 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

621 Issue of NIT (Issued ) 5 07-Jun-07 A 30-Jul-07 A

622 Recpt of Tender at Bhilai 45 01-Aug-07 A 15-Sep-07 A

623 Recpt of Tender at Ranc hi 5 17-Sep-07 A 22-Sep-07 A

624 Scrutiny, Discussions & Tender Finalisation 45 23-Sep-07 A 02-Jan-08 A

626 Signing of Contract 0 03-Jan-08 A

627 Survey work and Submission of report and Soil Test ing 180 04-Jan-08 A 16-Oct-08 A

Pkg 110 Part B Survey of New Sites & Soil TestingPkg 110 Part B Survey of New Sites & Soil TestingPkg 110 Part B Survey of New Sites & Soil TestingPkg 110 Part B Survey of New Sites & Soil TestingPkg 110 Part B Survey of New Sites & Soil Testing

838 Issue Draft TS (Issued) 0 28-May-07 A

839 Discussion with BSP 5 01-Jun-07 A 02-Jun-07 A

840 Issue Final TS (Issued ) 8 03-Jun-07 A 05-Jun-07 A

841 Issue of NIT (Issued ) 5 06-Jun-07 A 31-Jul-07 A

844 Scrutiny, Discussions & Tender Finalisation 50 01-Aug-07 A 02-Jan-08 A

846 Signing of Contract 0 03-Jan-08 A

847 Survey work and Submission of report and Soil Test ing 180 04-Jan-08 A 28-Aug-08 A

Pkg 111-01 Construction of Fly-overs & Road NetworkPkg 111-01 Construction of Fly-overs & Road NetworkPkg 111-01 Construction of Fly-overs & Road NetworkPkg 111-01 Construction of Fly-overs & Road NetworkPkg 111-01 Construction of Fly-overs & Road Network

879 Issue Draft TS 0 14-Sep-07 A

880 Discussion with BSP 10 15-Sep-07 A 25-Sep-07 A

881 Issue Final TS 10 26-Sep-07 A 07-Jan-08 A

882 Issue of NIT 8 08-Jan-08 A 13-Mar-08 A

883 Recpt of Tender at Bhilai 45 14-Mar-08 A 21-Apr-08 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 46 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

884 Recpt of Tender at Ranc hi 5 22-Apr-08 A 29-Apr-08 A

885 Scrutiny, Discussions & Tender Finalisation 60 30-Apr-08 A 19-Feb-09 A

885.1 Firming-up of price of the package & Mngt. Approval 30 20-Feb-09 A 29-Jun-09 A

885.11 Issue of NIT (Retendered) 8 20-Jul-09 A 31-Jul-09 A

885.12 Firming-up of price of the package & Mngt. Approval 30 01-Sep-09 A 17-Jun-10 A

885.13 Issue of LOI 0 18-Jun-10 A

885.2 Signing of Contract with M/s SP Singla construction (24 months schedule)

0 14-Jul-10 A

885.3 Construction of Fly-overs & Road Network 730 15-Jul-10 A 16-Feb-16

Pkg 113 Relocation of TSS and Construction PowerPkg 113 Relocation of TSS and Construction PowerPkg 113 Relocation of TSS and Construction PowerPkg 113 Relocation of TSS and Construction PowerPkg 113 Relocation of TSS and Construction Power

651 Issue Draft TS (Issued ) 0 27-Jun-07 A

652 Discussion with BSP 10 05-Jul-07 A 14-Jul-07 A

653 Issue Final TS (Issued ) 14 05-Aug-07 A 04-Sep-07 A

654 Issue of NIT (Issued ) 8 14-Sep-07 A 21-Sep-07 A

655 Recpt of Tender at Bhilai 45 24-Sep-07 A 14-Nov-07 A

656 Recpt of Tender at Ranc hi 5 15-Nov-07 A 19-Nov-07 A

657 Scrutiny, Discussions & Tender Finalisation 60 20-Nov-07 A 02-Mar-08 A

658 Firming-up of price of the package & Mngt. Approval 25 03-Mar-08 A 27-Mar-08 A

659 Signing of Contract with M/s ABB 0 01-May-08 A

659.1 Contractual Finish 0 31-Mar-09 A

660 Relocation of TSS and Construction Power 303 02-May-09 A 28-Nov-14

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 47 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

Pkg 114 New Centralised Compressed Air StationPkg 114 New Centralised Compressed Air StationPkg 114 New Centralised Compressed Air StationPkg 114 New Centralised Compressed Air StationPkg 114 New Centralised Compressed Air Station

662 Issue Draft TS (Issued) 0 01-May-07 A

663 Discussion with BSP 15 22-May-07 A 05-Jun-07 A

664 Issue Final TS (Issued) 15 06-Jun-07 A 21-Jun-07 A

665 Issue of NIT (Issued ) 4 22-Jun-07 A 25-Jun-07 A

666 Recpt of Tender at Bhilai 45 28-Aug-07 A 31-Oct-07 A

667 Recpt of Tender at Ranc hi 4 01-Nov-07 A 03-Nov-07 A

668 Scrutiny, Discussions & Tender Finalisation 75 30-Nov-07 A 01-Feb-08 A

669 Firming-up of price of the package & stage-II approval 30 02-Feb-08 A 14-Mar-08 A

669.1 Issue of LOI 0 22-Mar-08 A

670 Signing of Contract 0 21-Apr-08 A

671 Engg., Supply, Execution, Testing & Comm.- Central CAS 730 22-Apr-08 A 05-Mar-11 A

Pkg 114A Centralised Compressed Air Station for MillsPkg 114A Centralised Compressed Air Station for MillsPkg 114A Centralised Compressed Air Station for MillsPkg 114A Centralised Compressed Air Station for MillsPkg 114A Centralised Compressed Air Station for Mills

11540 Issue Draft TS (Issued) 0 27-Jul-11 A

11550 Discussion with BSP 15 04-Aug-11 A 02-Jan-12 A

11560 Issue Final TS (Issued) 15 03-Jan-12 A 04-Apr-12 A

11570 Issue of NIT 4 14-May-12 A 17-May-12 A

11580 Recpt of Tender at Bhilai 45 18-May-12 A 28-Jun-12 A

11590 Recpt of Tender at Ranc hi 4 29-Jun-12 A 11-Jul-12 A

11600 Scrutiny, Discussions & Tender Finalisation 75 12-Jul-12 A 01-Dec-12 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 48 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

11610 Firming-up of price of the package & stage-II approval 30 03-Dec-12 A 15-May-13 A

11615 Issue of LOI 0 30-May-13 A

11620 Signing of Contract 0 07-Jun-13 A

11630 Engg., Supply, Execution, Testing & Comm.- Central CAS (Retendered)

240 07-Jun-13 A 26-Nov-13 A

12701 Issue Final TS (Issued) 15 02-Dec-13 A 16-Dec-13 A

12702 Issue of NIT 4 06-Jan-14 A 10-Jan-14 A

12703 Recpt of Tender at Bhilai 45 11-Jan-14 A 20-Feb-14 A

12704 Recpt of Tender at Ranc hi 4 21-Feb-14 A 26-Feb-14 A

12705 Scrutiny, Discussions & Tender Finalisation 75 27-Feb-14 A 09-Jul-14 A

12706 Firming-up of price of the package & stage-II approval 30 10-Jul-14 A 09-Oct-14

12707 Issue of LOI 0 10-Oct-14

12708 Signing of Contract 0 09-Nov-14

12709 Engg., Supply, Execution, Testing & Comm.- Central CAS 240 09-Nov-14 06-Jul-15

Pkg 115 Construction Water ( By BSP as enabl ing works)(Package Dropped)Pkg 115 Construction Water ( By BSP as enabl ing works)(Package Dropped)Pkg 115 Construction Water ( By BSP as enabl ing works)(Package Dropped)Pkg 115 Construction Water ( By BSP as enabl ing works)(Package Dropped)Pkg 115 Construction Water ( By BSP as enabl ing works)(Package Dropped)

673 Issue Draft TS 0 25-Feb-08 A

674 Discussion with BSP 7 26-Feb-08 A 23-May-08 A

675 Issue Final TS 10 24-May-08 A 19-Jun-08 A

676 Issue of NIT 8 20-Jun-08 A 24-Jun-08 A

677 Recpt of Tender at Bhilai 45 25-Jun-08 A 20-Aug-08 A

678 Recpt of Tender at Ranc hi 5 21-Aug-08 A 27-Aug-08 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 49 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

679 Scrutiny, Discussions & Tender Finalisation 45 28-Aug-08 A 01-Jan-09 A

Pkg 116 A Relocation of PSS storesPkg 116 A Relocation of PSS storesPkg 116 A Relocation of PSS storesPkg 116 A Relocation of PSS storesPkg 116 A Relocation of PSS stores

684 Issue Draft TS (Issued ) 0 02-Jun-07 A

685 Discussion with BSP 10 10-Jun-07 A 19-Jun-07 A

686 Issue Final TS (Issued ) 14 05-Jul-07 A 21-Jul-07 A

687 Issue of NIT (Issued ) 7 05-Sep-07 A 11-Sep-07 A

688 Recpt of Tender at Bhilai 45 12-Sep-07 A 20-Oct-07 A

689 Recpt of Tender at Ranc hi 5 21-Oct-07 A 26-Oct-07 A

690 Scrutiny, Discussions & Tender Finalisation 45 26-Oct-07 A 30-Nov-07 A

691 Firming-up of price of the package & Mngt. Approval 25 01-Dec-07 A 26-Dec-07 A

692 Signing of Contract 0 08-Jan-08 A

692.1 Contractual Finish 0 07-Aug-09 A

693 Dismantling & Relocation of PSS stores 580 09-Jan-08 A 20-Sep-12 A

Pkg 116 B1 Tap Hole Mass ShopPkg 116 B1 Tap Hole Mass ShopPkg 116 B1 Tap Hole Mass ShopPkg 116 B1 Tap Hole Mass ShopPkg 116 B1 Tap Hole Mass Shop

715 Discussion with BSP 10 10-Jun-07 A 19-Jun-07 A

716 Issue Final TS 14 05-Jul-07 A 11-Jan-08 A

717 Issue of NIT 4 12-Jan-08 A 29-Jan-08 A

718 Recpt of Tender at Bhilai 45 30-Jan-08 A 30-Jun-08 A

749 Recpt of Tender at Ranc hi 5 01-Jul-08 A 04-Jul-08 A

750 Scrutiny, Discussions & Tender Finalisation 50 05-Jul-08 A 13-Jul-08 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 50 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

751 Firming-up of price of the package & Mngt. Approval 30 14-Jul-08 A 15-Oct-08 A

751.1 Issue of LOI 0 22-Oct-08 A

752 Signing of Contract 0 22-Nov-08 A

753 Dismantling & Relocation of tap hole mass shop 273 23-Nov-08 A 16-Aug-12 A

Pkg 116 B2 LT substation for tap hole mass shopPkg 116 B2 LT substation for tap hole mass shopPkg 116 B2 LT substation for tap hole mass shopPkg 116 B2 LT substation for tap hole mass shopPkg 116 B2 LT substation for tap hole mass shop

914 Issue Draft TS (Issued ) 0 17-Dec-07 A

914.1 Discussion with BSP 10 18-Dec-07 A 25-Feb-08 A

914.2 Issue Final TS 14 26-Feb-08 A 18-Mar-08 A

914.3 Issue of NIT 4 19-Mar-08 A 26-Apr-08 A

931 Firming-up of price of the package & Mngt. Approval 30 18-Jan-09 A 25-Mar-09 A

931.1 Issue of LOI 0 31-Mar-09 A

931.2 Signing of Contract 0 31-Mar-09 A

931.3 Dismantling & Relocation of LT substation 580 01-Apr-09 A 29-Mar-14 A

Pkg 117 Project Building, Other Site offices & StoresPkg 117 Project Building, Other Site offices & StoresPkg 117 Project Building, Other Site offices & StoresPkg 117 Project Building, Other Site offices & StoresPkg 117 Project Building, Other Site offices & Stores

695 Issue Draft TS 0 27-Nov-07 A

696 Discussion with BSP 10 28-Nov-07 A 20-Dec-07 A

697 Issue Final TS 14 21-Dec-07 A 18-Jan-08 A

698 Issue of NIT 5 19-Jan-08 A 27-Mar-08 A

699 Recpt of Tender at Bhilai 45 28-Mar-08 A 15-May-08 A

700 Recpt of Tender at Ranc hi 5 16-May-08 A 20-May-08 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 51 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

701 Scrutiny, Discussions & Tender Finalisation 45 21-May-08 A 16-Jul-08 A

702 Firming-up of price of the package & Mngt. Approval 25 17-Jul-08 A 24-Sep-08 A

702.1 Issue of LOI 0 01-Oct-08 A

703 Signing of Contract 0 18-Oct-08 A

704 Construction of New Project Building, Other Site offices & Stores

730 20-Oct-08 A 31-Jan-11 A

Pkg 117A Data network & intranet servicesPkg 117A Data network & intranet servicesPkg 117A Data network & intranet servicesPkg 117A Data network & intranet servicesPkg 117A Data network & intranet services

10980 Issue of NIT 5 26-Apr-10 A 30-Apr-10 A

10990 Recpt of Tender at Bhilai 45 01-May-10 A 10-Jul-10 A

11000 Recpt of Tender at Ranc hi 5 12-Jul-10 A 16-Jul-10 A

11010 Scrutiny, Discussions & Tender Finalisation 45 17-Jul-10 A 08-Nov-10 A

11020 Firming-up of price of the package & Mngt. Approval 25 09-Nov-10 A 15-Mar-11 A

11025 Issue of LOI 0 21-Mar-11 A

11030 Signing of Contract with M/s HCL Infosystem 0 30-Apr-11 A

11030.1 Contractual Finish 0 29-Aug-11 A

11040 Engg., supply ,erection & commissioning of data network & intranet services

121 30-Apr-11 A 31-Dec-14

Pkg 118-A Dismantling Works-Part-APkg 118-A Dismantling Works-Part-APkg 118-A Dismantling Works-Part-APkg 118-A Dismantling Works-Part-APkg 118-A Dismantling Works-Part-A

915 Issue Draft TS (Issued) 0 25-Apr-07 A

915.2 Issue Final TS (Issued) 2 26-Apr-07 A 27-Apr-07 A

915.3 Issue of NIT (Issued ) 5 28-Apr-07 A 07-May-07 A

915.4 Recpt of Tender at Bhilai 45 08-May-07 A 30-May-07 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 52 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

915.5 Signing of Contract 0 28-Jun-07 A

915.6 Dismantling of Existing Bldgs 180 29-Jun-07 A 20-Jun-08 A

Pkg 118-B Dismantling Works Part-BPkg 118-B Dismantling Works Part-BPkg 118-B Dismantling Works Part-BPkg 118-B Dismantling Works Part-BPkg 118-B Dismantling Works Part-B

705 Issue Draft TS (Issued) 0 25-Apr-07 A

706 Discussion with BSP 1 26-Apr-07 A 10-May-07 A

707 Issue Final TS (Issued) 2 11-May-07 A 16-May-07 A

708 Issue of NIT (Issued ) 5 20-Jul-07 A 24-Jul-07 A

709 Recpt of Tender at Bhilai 45 25-Jul-07 A 09-Sep-07 A

713 Signing of Contract with M/s HSCL 0 16-Jan-08 A

714 Dismantling of Existing Bldgs 180 17-Jan-08 A 25-Jun-12 A

Pkg 119-01 Relocation of mech. repair shop-civil/ strl / GLT dismantlingPkg 119-01 Relocation of mech. repair shop-civil/ strl / GLT dismantlingPkg 119-01 Relocation of mech. repair shop-civil/ strl / GLT dismantlingPkg 119-01 Relocation of mech. repair shop-civil/ strl / GLT dismantlingPkg 119-01 Relocation of mech. repair shop-civil/ strl / GLT dismantling

9153 Issue Final TS 2 10-Mar-09 A 14-Mar-09 A

9154 Issue of NIT 5 15-Mar-09 A 07-Apr-09 A

9155 Recpt of Tender at Bhilai 45 08-Apr-09 A 30-May-09 A

9157 Scrutiny, Discussions & Tender Finalisation 45 01-Jun-09 A 14-Aug-09 A

9158 Firming-up of price of the package & Mngt. Approval 25 15-Aug-09 A 30-Sep-09 A

9158.1 Issue of LOI 0 30-Oct-09 A

9159 Placement of Order by BSP 0 09-Jan-10 A

9160 Execution 365 11-Jan-10 A 30-Nov-14

Pkg 119-02 Electrical power & ventilation facilities for Mechanical & quenching car repair shopPkg 119-02 Electrical power & ventilation facilities for Mechanical & quenching car repair shopPkg 119-02 Electrical power & ventilation facilities for Mechanical & quenching car repair shopPkg 119-02 Electrical power & ventilation facilities for Mechanical & quenching car repair shopPkg 119-02 Electrical power & ventilation facilities for Mechanical & quenching car repair shop

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 53 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

9164 Issue of NIT 5 24-Jun-09 A 29-Jun-09 A

9165 Recpt of Tender at Bhilai 45 30-Jun-09 A 30-Jul-09 A

9166 Recpt of Tender at Ranc hi 5 01-Aug-09 A 04-Oct-09 A

9167 Scrutiny, Discussions & Tender Finalisation 45 05-Oct-09 A 18-Nov-09 A

9168 Firming-up of price of the package & Mngt. Approval 25 19-Nov-09 A 13-Dec-09 A

9168.1 Issue of LOI 0 21-Dec-09 A

9169 Placement of Order by BSP 0 09-Jan-10 A

9170 Electrical power & vetilation for mech. & quenching car shop 273 11-Jan-10 A 30-Dec-14

Pkg 119-03 Relocation of mech. repair shop-Technological servicesPkg 119-03 Relocation of mech. repair shop-Technological servicesPkg 119-03 Relocation of mech. repair shop-Technological servicesPkg 119-03 Relocation of mech. repair shop-Technological servicesPkg 119-03 Relocation of mech. repair shop-Technological services

9173 Issue Final TS 2 20-Apr-09 A 30-Apr-09 A

9174 Issue of NIT 5 01-May-09 A 12-May-09 A

9175 Recpt of Tender at Bhilai 45 13-May-09 A 17-Jun-09 A

9176 Recpt of Tender at Ranc hi 5 18-Jun-09 A 30-Jun-09 A

9177 Scrutiny, Discussions & Tender Finalisation 45 01-Jul-09 A 19-Aug-09 A

9178 Firming-up of price of the package & Mngt. Approval 25 20-Aug-09 A 30-Sep-09 A

9178.1 Issue of LOI 0 06-Oct-09 A

9179 Placement of Order by BSP 0 13-Oct-09 A

9180 Relocation of Mech. repair shop 182 14-Oct-09 A 30-Dec-14

Pkg 121 Rail welding lines for long railsPkg 121 Rail welding lines for long railsPkg 121 Rail welding lines for long railsPkg 121 Rail welding lines for long railsPkg 121 Rail welding lines for long rails

9351 Issue Draft TS (Issued) 0 18-Mar-08 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 54 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

9352 Discussion with BSP 5 19-Mar-08 A 10-May-08 A

9353 Issue Final TS 5 11-May-08 A 19-May-08 A

9354 Issue of NIT 5 20-May-08 A 25-Jun-08 A

9355 Recpt of Tender at Bhilai 45 26-Jun-08 A 15-Sep-08 A

9356 Recpt of Tender at Ranc hi 5 16-Sep-08 A 23-Sep-08 A

9357 Scrutiny, Discussions & Tender Finalisation 45 24-Sep-08 A 17-Aug-10 A

9358 Firming-up of price of the package & stage-II approval 25 18-Aug-10 A 10-Jan-11 A

9358.1 Issue of LOI 0 17-Jan-11 A

9359 Signing of Contract 0 05-Feb-11 A

9360 Rail Welding Lines for Long Rails-commissioning 608 06-Feb-11 A 15-Nov-14

Pkg 001-SE-01 Coke Oven Battery -11Pkg 001-SE-01 Coke Oven Battery -11Pkg 001-SE-01 Coke Oven Battery -11Pkg 001-SE-01 Coke Oven Battery -11Pkg 001-SE-01 Coke Oven Battery -11

848 Issue Draft TS (Issued) 0 27-Oct-07 A

849 Discussion with BSP 5 28-Oct-07 A 01-Nov-07 A

850 Issue Final TS 11 02-Nov-07 A 10-Nov-07 A

851 Issue of NIT 15 11-Nov-07 A 15-Nov-07 A

852 Recpt of Tender at Bhilai 45 16-Nov-07 A 15-Jan-08 A

853 Recpt of Tender at Ranc hi 5 16-Jan-08 A 21-Jan-08 A

854 Scrutiny, Discussions & Tender Finalisation 60 22-Jan-08 A 19-Mar-08 A

855 Firming-up of price of the package 20 20-Mar-08 A 02-Sep-08 A

855.1 Issue of LOI 0 03-Sep-08 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 55 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

856 Signing of Contract 0 16-Sep-08 A

866 Engg., Supply, Execution , testing & commissioning of coke oven battery

851 17-Sep-08 A 16-Apr-15

Pkg 001-SE-02 Oven Machines for COB-11Pkg 001-SE-02 Oven Machines for COB-11Pkg 001-SE-02 Oven Machines for COB-11Pkg 001-SE-02 Oven Machines for COB-11Pkg 001-SE-02 Oven Machines for COB-11

2001 Issue Draft TS (Issued) 0 27-Oct-07 A

2002 Discussion with BSP 10 28-Oct-07 A 06-Nov-07 A

2003 Issue Final TS 7 07-Nov-07 A 11-Nov-07 A

2004 Issue of NIT 15 12-Nov-07 A 15-Nov-07 A

2005 Recpt of Tender at Bhilai 45 29-Nov-07 A 15-Jan-08 A

2006 Recpt of Tender at Ranc hi 5 16-Jan-08 A 21-Jan-08 A

2007 Scrutiny, Discussions & Tender Finalisation 60 22-Jan-08 A 19-Mar-08 A

2008 Firming-up of price of the package 45 20-Mar-08 A 02-Sep-08 A

2008.1 Issue of LOI 0 03-Sep-08 A

2009 Signing of Contract 0 19-Sep-08 A

2010 Engg., Supply, Execution , testing & commissioning of coke oven machines

730 20-Sep-08 A 16-Apr-15

Pkg 001-SR-03 Silica bricks & Mortar for COB-11Pkg 001-SR-03 Silica bricks & Mortar for COB-11Pkg 001-SR-03 Silica bricks & Mortar for COB-11Pkg 001-SR-03 Silica bricks & Mortar for COB-11Pkg 001-SR-03 Silica bricks & Mortar for COB-11

2011 Issue Draft TS (Issued ) 0 27-Oct-07 A

2012 Discussion with BSP 10 28-Oct-07 A 07-Nov-07 A

2013 Issue Final TS 7 08-Nov-07 A 14-Nov-07 A

2014 Issue of NIT ( Direct procurement by BSP) 15 15-Nov-07 A 30-Nov-07 A

Pkg 001-SR-04 Fire clay bricks & Mortar for COB-11Pkg 001-SR-04 Fire clay bricks & Mortar for COB-11Pkg 001-SR-04 Fire clay bricks & Mortar for COB-11Pkg 001-SR-04 Fire clay bricks & Mortar for COB-11Pkg 001-SR-04 Fire clay bricks & Mortar for COB-11

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 56 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

2021 Issue Draft TS (Issued ) 0 27-Oct-07 A

2022 Discussion with BSP 10 28-Oct-07 A 07-Nov-07 A

2023 Issue Final TS 7 08-Nov-07 A 14-Nov-07 A

2024 Issue of NIT ( Direct procurement by BSP) 44 15-Nov-07 A 30-Nov-07 A

Pkg 001-SR-05 Insulation bricks & Mortar for COB-11Pkg 001-SR-05 Insulation bricks & Mortar for COB-11Pkg 001-SR-05 Insulation bricks & Mortar for COB-11Pkg 001-SR-05 Insulation bricks & Mortar for COB-11Pkg 001-SR-05 Insulation bricks & Mortar for COB-11

2031 Issue Draft TS (Issued ) 0 27-Oct-07 A

2032 Discussion with BSP 10 28-Oct-07 A 07-Nov-07 A

2033 Issue Final TS 7 08-Nov-07 A 15-Nov-07 A

2034 Issue of NIT ( Direct procurement by BSP) 44 16-Nov-07 A 30-Nov-07 A

Pkg 002 Coke Dry Cooling Plant for COB-11Pkg 002 Coke Dry Cooling Plant for COB-11Pkg 002 Coke Dry Cooling Plant for COB-11Pkg 002 Coke Dry Cooling Plant for COB-11Pkg 002 Coke Dry Cooling Plant for COB-11

2041 Issue Draft TS 0 29-Oct-07 A

2042 Discussion with BSP 7 30-Oct-07 A 05-Nov-07 A

2043 Issue Final TS 7 06-Nov-07 A 10-Nov-07 A

2044 Issue of NIT 7 11-Nov-07 A 15-Nov-07 A

2045 Recpt of Tender at Bhilai 45 01-Dec-07 A 10-Jan-08 A

2046 Recpt of Tender at Ranc hi 5 11-Jan-08 A 14-Jan-08 A

2047 Scrutiny, Discussions & Tender Finalisation 60 15-Jan-08 A 22-Feb-08 A

2048 Firming-up of price of the package 30 23-Feb-08 A 02-Sep-08 A

2048.1 Issue of LOI 0 03-Sep-08 A

2049 Signing of Contract 0 18-Sep-08 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 57 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

2050 Engg., supply , Execution , testing & commissioning of CDCP

760 19-Sep-08 A 16-Apr-15

Pkg 003A By- product PlantPkg 003A By- product PlantPkg 003A By- product PlantPkg 003A By- product PlantPkg 003A By- product Plant

2051 Issue Draft TS 0 04-Dec-07 A

2052 Discussion with BSP 14 05-Dec-07 A 08-Dec-07 A

2053 Issue Final TS 15 09-Dec-07 A 12-Dec-07 A

2054 Issue of NIT 8 13-Dec-07 A 28-Dec-07 A

2055 Recpt of Tender at Bhilai 45 29-Dec-07 A 25-Apr-08 A

2056 Recpt of Tender at Ranc hi 5 26-Apr-08 A 01-May-08 A

2057 Scrutiny, Discussions & Tender Finalisation 60 02-May-08 A 02-Nov-08 A

2058 Firming-up of price of the package (Retendered) 30 03-Nov-08 A 09-Mar-09 A

2084 Issue of NIT 8 05-Apr-09 A 08-Apr-09 A

2085 Recpt of Tender at Bhilai 45 09-Apr-09 A 12-May-09 A

2086 Recpt of Tender at Ranc hi 5 13-May-09 A 25-May-09 A

2087 Scrutiny, Discussions & Tender Finalisation (Retendered) 60 26-May-09 A 30-Nov-09 A

2087.1 Issue of NIT 8 21-Dec-09 A 25-Dec-09 A

2087.2 Recpt of Tender at Bhilai 28 26-Dec-09 A 20-Jan-10 A

2087.3 Recpt of Tender at Ranc hi 5 21-Jan-10 A 30-Jan-10 A

2087.4 Scrutiny, Discussions & Tender Finalisation 60 31-Jan-10 A 25-Apr-10 A

2088 Firming-up of price of the package 15 26-Apr-10 A 20-Mar-11 A

2088.2 Signing of Contract 0 20-Apr-11 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 58 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

2088.3 Engg., Supply , Execution , Tes ting & commiss ioning of By product plant

730 21-Apr-11 A 16-Apr-15

Pkg 003C BOD PlantPkg 003C BOD PlantPkg 003C BOD PlantPkg 003C BOD PlantPkg 003C BOD Plant

2071 Issue Draft TS 0 26-Dec-07 A

2072 Discussion with BSP 14 27-Dec-07 A 28-Feb-08 A

2073 Issue Final TS 15 29-Feb-08 A 30-May-08 A

2074 Issue of NIT 8 31-May-08 A 08-Jul-08 A

2075 Recpt of Tender at Bhilai 45 09-Jul-08 A 31-Aug-08 A

2076 Recpt of Tender at Ranc hi 5 01-Sep-08 A 05-Feb-09 A

2077 Scrutiny, Discussions & Tender Finalisation (Retendered) 60 06-Feb-09 A 29-Jul-09 A

2077.1 Issue of NIT 8 14-Sep-09 A 24-Sep-09 A

2077.2 Recpt of Tender at Bhilai 45 25-Sep-09 A 31-Dec-09 A

2077.4 Recpt of Tender at Ranc hi 5 01-Jan-10 A 05-Jan-10 A

2077.5 Scrutiny, Discussions & Tender Finalisation 60 06-Jan-10 A 30-Apr-10 A

2078 Firming-up of price of the package 30 01-May-10 A 20-May-10 A

2078.1 Issue of LOI 0 26-May-10 A

2079 Signing of Contract 0 25-Jun-10 A

2080 Engg., Supply , Execution , Tes ting & commiss ioning of BOD plant

365 26-Jun-10 A 27-Dec-14

Pkg 123 Ferroalloys storage yardPkg 123 Ferroalloys storage yardPkg 123 Ferroalloys storage yardPkg 123 Ferroalloys storage yardPkg 123 Ferroalloys storage yard

10940 Issue of Draft TS 0 11-Mar-11 A

888 Issue of Final TS 10 12-Sep-12 A 12-Dec-12 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 59 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

888.1 Scrutiny, Discussions & Tender Finalisation 45 30-Apr-13 A 30-Sep-13 A

888.12 Issue of Final TS (Retendered) 10 01-Dec-13 A 12-Dec-13 A

888.13 Scrutiny, Discussions & Tender Finalisation 45 30-Apr-14 A 14-Jul-14 A

916 Signing of Contract 0 30-Sep-14

926 Engg., Supply & Execution 365 30-Sep-14 29-Sep-15

Pkg 124 Refractories for BOF & CCPPkg 124 Refractories for BOF & CCPPkg 124 Refractories for BOF & CCPPkg 124 Refractories for BOF & CCPPkg 124 Refractories for BOF & CCP

2083 Issue of final TS 0 11-Feb-14 A 15-Oct-14 A

2083.1 Scrutiny, Discussions & Tender Finalisation 45 14-Nov-14* 28-Dec-14

2083.2 Signing of Contract 0 13-Jan-15

2083.3 Engg.& Supplyof refractories 91 14-Jan-15 14-Apr-15

Pkg 125-01 ACVS for BOF & CCPPkg 125-01 ACVS for BOF & CCPPkg 125-01 ACVS for BOF & CCPPkg 125-01 ACVS for BOF & CCPPkg 125-01 ACVS for BOF & CCP

2090 Issue of Draft TS 0 19-Apr-11 A

2091 Issue of Final TS 0 30-Jul-11 A

2091.1 Issue of NIT 8 01-Aug-11 A 09-Aug-11 A

2092 Scrutiny, discussion & tender finalisation 45 15-Oct-11 A 30-Jul-12 A

2093 Signing of contract 0 31-Aug-12 A

2094 Engg., supply & execution 547 01-Sep-12 A 31-Mar-15

Pkg 125-02 ACVS for B& RM, URM & rail weldingPkg 125-02 ACVS for B& RM, URM & rail weldingPkg 125-02 ACVS for B& RM, URM & rail weldingPkg 125-02 ACVS for B& RM, URM & rail weldingPkg 125-02 ACVS for B& RM, URM & rail welding

9410 Issue of final TS 0 14-Aug-12 A

9420 Scrutiny, discussion & tender finalisation 45 01-Nov-12 A 20-Mar-13 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 60 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

9430 Signing of contract 0 25-Jun-13 A

9440 Engg., supply & execution 456 25-Jun-13 A 31-Mar-15

Pkg 126-01 Fire fighting system for BOF & CCPPkg 126-01 Fire fighting system for BOF & CCPPkg 126-01 Fire fighting system for BOF & CCPPkg 126-01 Fire fighting system for BOF & CCPPkg 126-01 Fire fighting system for BOF & CCP

2101 Issue of draft TS 0 02-Jul-11 A

2101.1 Issue of Final TS 0 29-Sep-11 A

2101.2 Issue of NIT 8 30-Dec-11 A 07-Jan-12 A

2102 Scrutiny, discussion & tender finalisation 45 02-Apr-12 A 22-Mar-13 A

2103 Signing of contract 0 02-Apr-13 A

2104 Engg., supply and commissioning 365 02-Apr-13 A 30-Jun-15

Pkg 126-02 Fire fighting system for B&RM & URMPkg 126-02 Fire fighting system for B&RM & URMPkg 126-02 Fire fighting system for B&RM & URMPkg 126-02 Fire fighting system for B&RM & URMPkg 126-02 Fire fighting system for B&RM & URM

9450 Issue of final TS 0 13-Mar-12 A

9460 Scrutiny, discussion & tender finalisation 45 24-Jul-12 A 01-May-13 A

9470 Signing of contract 0 15-May-13 A

9480 Engg., supply and commissioning 365 15-May-13 A 30-Jun-15

Pkg 127 Illumination, earthing & lightning protection system for SMS-3Pkg 127 Illumination, earthing & lightning protection system for SMS-3Pkg 127 Illumination, earthing & lightning protection system for SMS-3Pkg 127 Illumination, earthing & lightning protection system for SMS-3Pkg 127 Illumination, earthing & lightning protection system for SMS-3

2111.3 Issue Final TS 15 01-Jun-11 A 17-Jun-11 A

2111.4 Issue of NIT 8 18-Jun-11 A 21-Jun-11 A

2111.5 Recpt of Tender at Bhilai 45 22-Jun-11 A 20-Sep-11 A

2111.6 Recpt of Tender at Ranc hi 5 21-Sep-11 A 26-Sep-11 A

2112 Scrutiny, discussion & tender finalisation (Retendered) 45 27-Sep-11 A 08-May-12 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 61 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

2112.01 Issue Final TS 15 25-Sep-12 A 12-Mar-13 A

2112.02 Issue of NIT 8 13-Mar-13 A 18-Mar-13 A

2112.03 Recpt of Tender at Bhilai 45 19-Mar-13 A 24-Apr-13 A

2112.04 Recpt of Tender at Ranc hi 5 25-Apr-13 A 15-May-13 A

2112.05 Scrutiny, discussion & tender finalisation (Retendered 2nd time)

45 16-May-13 A 02-Dec-13 A

2112.10 Issue Final TS 15 10-Jan-14 A 20-Jan-14 A

2112.15 Issue of NIT 8 05-Mar-14 A 12-Mar-14 A

2112.25 Recpt of Tender at Bhilai 45 13-Mar-14 A 06-May-14 A

2112.35 Recpt of Tender at Ranc hi 5 02-May-14 A 07-May-14 A

2112.45 Scrutiny, discussion & tender finalisation 45 08-May-14 A 11-Aug-14 A

2113 Signing of contract 0 30-Sep-14

2114 Engg., supply & execution 365 01-Oct-14 30-Sep-15

Pkg 128 Illumination, earthing & lightning protection for BRM, URM & rail weldingPkg 128 Illumination, earthing & lightning protection for BRM, URM & rail weldingPkg 128 Illumination, earthing & lightning protection for BRM, URM & rail weldingPkg 128 Illumination, earthing & lightning protection for BRM, URM & rail weldingPkg 128 Illumination, earthing & lightning protection for BRM, URM & rail welding

2121 Issue of TS 0 23-Mar-12 A

2121.1 Scrutiny, Discussions & Tender Finalisation 60 11-Sep-12 A 06-May-13 A

2121.2 Signing of Contract 0 21-May-13 A

2121.3 Engg., supply , Execution , testing & commissioning 273 21-May-13 A 10-May-15

Pkg 131 Equipment erection for BOF & CCPPkg 131 Equipment erection for BOF & CCPPkg 131 Equipment erection for BOF & CCPPkg 131 Equipment erection for BOF & CCPPkg 131 Equipment erection for BOF & CCP

12520 Issue of TS 0 29-Sep-10 A

12530 Scrutiny, Discussions & Tender Finalisation 45 24-Jan-11 A 26-Jul-11 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 62 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

12540 Issue of LOI 0 10-Oct-11 A

12550 Signing of Contract (Retendered) 0 03-Nov-11 A

12560 Erection of BOF & CCP equipment (Retendered) 426 04-Nov-11 A 01-Jul-13 A

Pkg 131A Equipment erection for BOF & CCPPkg 131A Equipment erection for BOF & CCPPkg 131A Equipment erection for BOF & CCPPkg 131A Equipment erection for BOF & CCPPkg 131A Equipment erection for BOF & CCP

12561 Issue of Revised TS 0 07-Sep-13 A

12570 Issue of NIT 0 16-Sep-13 A

12580 Scrutiny, Discussions & Tender Finalisation 45 19-Oct-13 A 27-Nov-13 A

12581 Issue of LOI 0 22-Feb-14 A

12590 Signing of Contract 0 12-Mar-14 A

12600 Erection of BOF equipment 426 13-Mar-14 A 31-Mar-16

12610 Erection of CCP Equipment 426 13-Mar-14 A 03-Dec-15

Pkg 134 Pneumatic conveying for sample conveyingPkg 134 Pneumatic conveying for sample conveyingPkg 134 Pneumatic conveying for sample conveyingPkg 134 Pneumatic conveying for sample conveyingPkg 134 Pneumatic conveying for sample conveying

2146 Issue of Draft TS 0 03-May-11 A

2146.1 Issue of Final TS 0 31-Aug-11 A

2146.11 Issue of Revised Final TS 0 14-Sep-11 A

2147 Scrutiny, Discussions & Tender Finalisation 60 07-Dec-11 A 23-May-13 A

2149 Signing of Contract 0 25-Jun-13 A

2150 Engg., Supply , Execution , Tes ting & commiss ioning 456 26-Jun-13 A 31-Dec-14

Pkg 136 Area lighting of plant premisesPkg 136 Area lighting of plant premisesPkg 136 Area lighting of plant premisesPkg 136 Area lighting of plant premisesPkg 136 Area lighting of plant premises

2166 Issue of TS 0 20-May-11 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 63 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

2166.11 Issue of Final TS 0 16-Oct-14*

2167 Scrutiny, Discussions & Tender Finalisation 45 10-Nov-14 24-Dec-14

2169 Signing of Contract 0 24-Jan-15

2170 Engg., Supply , Execution , Tes ting & commiss ioning 365 25-Jan-15 24-Jan-16

Pkg 137 Procurement of wagons (24 nos.)Pkg 137 Procurement of wagons (24 nos.)Pkg 137 Procurement of wagons (24 nos.)Pkg 137 Procurement of wagons (24 nos.)Pkg 137 Procurement of wagons (24 nos.)

2176 Issue of TS 0 23-Feb-11 A

2176.1 Issue of final TS 0 30-Mar-11 A

2177 Issue of NIT 60 01-Aug-11 A 20-Dec-11 A

2178 Scrutiny, Discussions & Tender Finalisation 45 23-Jan-12 A 11-Jul-12 A

2179 Signing of Contract 0 11-Aug-12 A

2180 Engg., Supply , Execution , Tes ting & commiss ioning 365 11-Aug-12 A 29-Sep-15

Pkg 138 Fire Station BuildingPkg 138 Fire Station BuildingPkg 138 Fire Station BuildingPkg 138 Fire Station BuildingPkg 138 Fire Station Building

0433.81 Issue of TS 0 16-Jun-12 A

10180 Issue of NIT 9 18-Jun-12 A 04-Sep-12 A

10190 Recpt of Tender at Bhilai 45 05-Sep-12 A 10-Nov-12 A

10200 Recpt of Tender at Ranc hi 5 12-Nov-12 A 15-Nov-12 A

10210 Scrutiny, Discussions & Tender Finalisation 45 16-Nov-12 A 18-May-13 A

10220 Firming-up of price of the package & Mngt. Approval (Retendered)

30 20-May-13 A 29-Jan-14 A

10225 Issue of FTS 0 01-Aug-14 A

10226 Issue of NIT 9 01-Aug-14 A 11-Aug-14 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 64 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

10227 Recpt of Tender at Bhilai 45 12-Aug-14 A 30-Sep-14 A

10228 Recpt of Tender at Ranc hi 5 30-Sep-14 A 04-Oct-14

10229 Scrutiny, Discussions & Tender Finalisation 45 05-Oct-14 18-Nov-14

10229.5 Firming-up of price of the package & Mngt. Approval 30 19-Nov-14 18-Dec-14

10230 Signing of Contract 0 19-Dec-14

10240 Engg., Supply and construction of building 365 20-Dec-14 19-Dec-15

Pkg 140 Pipe conveyor from RMP-III to RMP-IIPkg 140 Pipe conveyor from RMP-III to RMP-IIPkg 140 Pipe conveyor from RMP-III to RMP-IIPkg 140 Pipe conveyor from RMP-III to RMP-IIPkg 140 Pipe conveyor from RMP-III to RMP-II

2206 Issue of NIT 0 15-Jan-10 A

2207 Scrutiny, Discussions & Tender Finalisation 60 15-Feb-10 A 10-Jul-10 A

2208 Firming-up of price of the package & Mngt. Approval 30 11-Jul-10 A 03-Jan-11 A

2208.1 Issue of LOI 0 12-Jan-11 A

2209 Signing of Contract 0 04-Feb-11 A

2210 Engg., Supply , Execution , Tes ting & commiss ioning 454 05-Feb-11 A 28-Dec-14

Pkg 142 Roll shop for URMPkg 142 Roll shop for URMPkg 142 Roll shop for URMPkg 142 Roll shop for URMPkg 142 Roll shop for URM

2226 Issue Draft TS 0 29-Dec-10 A

2226.1 issue of final TS 0 29-Mar-11 A

2226.2 Issue of NIT 10 30-Mar-11 A 04-Apr-11 A

2226.3 Recpt of Tender at Bhilai 35 05-Apr-11 A 12-Apr-11 A

2226.4 Recpt of Tender at Ranc hi 5 13-Apr-11 A 20-Apr-11 A

2227 Scrutiny, Discussions & Tender Finalisation (Splitted into twopackages)

60 21-Apr-11 A 30-Apr-12 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 65 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

Pkg 142-01 CNC Roll & Ring Turning Lathes for URMPkg 142-01 CNC Roll & Ring Turning Lathes for URMPkg 142-01 CNC Roll & Ring Turning Lathes for URMPkg 142-01 CNC Roll & Ring Turning Lathes for URMPkg 142-01 CNC Roll & Ring Turning Lathes for URM

11740 Issue Draft TS 0 01-Jun-12 A

11742 issue of final TS 0 13-Jun-12 A

11743 Issue of NIT 10 14-Jun-12 A 11-Jul-12 A

11744 Recpt of Tender at Bhilai 35 12-Jul-12 A 12-Aug-12 A

11745 Recpt of Tender at Ranc hi 5 13-Aug-12 A 21-Aug-12 A

11750 Scrutiny, Discussions & Tender Finalisation 60 22-Aug-12 A 31-May-13 A

11760 Signing of Contract 0 21-Jun-13 A

11770 Engg., Supply , Execution , Tes ting & commiss ioning 365 21-Jun-13 A 29-Jan-15

Pkg 142-02 Roll & Repair Shop Equipment for URMPkg 142-02 Roll & Repair Shop Equipment for URMPkg 142-02 Roll & Repair Shop Equipment for URMPkg 142-02 Roll & Repair Shop Equipment for URMPkg 142-02 Roll & Repair Shop Equipment for URM

11780 Issue Draft TS 0 25-Jul-12 A

11781 issue of final TS 0 18-Aug-12 A

11782 Issue of NIT 10 18-Aug-12 A 20-Aug-12 A

11783 Recpt of Tender at Bhilai 35 20-Aug-12 A 30-Aug-12 A

11784 Recpt of Tender at Ranc hi 5 31-Aug-12 A 04-Sep-12 A

11790 Scrutiny, Discussions & Tender Finalisation 60 05-Sep-12 A 24-Apr-13 A

11800 Signing of Contract 0 26-Sep-13 A

11810 Engg., Supply , Execution , Tes ting & commiss ioning 365 26-Sep-13 A 27-Mar-15

Pkg 144 Rerouting of existing ash slurry pipelinePkg 144 Rerouting of existing ash slurry pipelinePkg 144 Rerouting of existing ash slurry pipelinePkg 144 Rerouting of existing ash slurry pipelinePkg 144 Rerouting of existing ash slurry pipeline

10290 Issue Draft TS 0 15-Sep-10 A

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 66 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.

Act ID Activity Name Duration Start Finish

9490 Issue of final TS 0 27-Dec-10 A

9490.1 Issue of NIT 0 06-Jun-11 A

9500 Scrutiny, Discussions & Tender Finalisation 60 15-Jul-11 A 16-Nov-11 A

9510 Signing of Contract with M/s Manish Pipe 0 17-Nov-11 A

9520 Engg., Supply , Execution , Tes ting & commiss ioning 182 29-Feb-12 A 29-Mar-14 A

Pkg 145 PWN connectivityPkg 145 PWN connectivityPkg 145 PWN connectivityPkg 145 PWN connectivityPkg 145 PWN connectivity

10250 Issue Draft TS 0 18-May-11 A

10255 Issue of final TS 0 08-Jan-14 A 11-Sep-14 A

10260 Scrutiny, Discussions & Tender Finalisation 60 26-Oct-14* 24-Dec-14

10270 Signing of Contract 0 09-Jan-15

10280 Engg., Supply , Execution , Tes ting & commiss ioning 365 10-Jan-15 09-Jan-16

Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

Steel Authority of India Limited

Bhilai Steel Plant Expansion Project

PERT Network Schedule of All Packages

STATUS AS ON 30th Sep 2014

Early Bar

Critical Bar

Milestone

Summary Page 67 of 67

© 2014 - MECON limited. All rights reserved

Start Date: 03-Apr-07; Finish Date : 28-Sep-16

Data Date : 30-Sep-14; Run Date: 05-Nov-14

© Primavera Systems, Inc.