Upload
merilyn-walters
View
216
Download
1
Tags:
Embed Size (px)
Citation preview
State of KansasState of Kansas
Financial Management SystemFinancial Management SystemNeeds AssessmentNeeds Assessment
Steering Committee MeetingNovember 30, 2006
2
Meeting AgendaMeeting Agenda
Introductions Project Overview Project Accomplishments Status and Preliminary Findings Upcoming Activities Questions
3
Project Overview Project Overview FMS Needs Assessment – Key ActivitiesFMS Needs Assessment – Key Activities
Update the system requirements for a new integrated FMS
Update the business case analysis associated with implementing a new FMS
Determine whether there is a compelling business case for procuring/implementing an integrated statewide FMS
Submit recommendations regarding• Organizational best practices• Implementation best practices
4
Project AccomplishmentsProject Accomplishments Requirements Validation: StatusRequirements Validation: Status
Conducted Focus Group Kick-Off Meeting • Held 10/09/06 - 75 participants
Total of 140 participants in various Focus Groups• Represents 25 agencies
Outreach sessions directed at non-Focus Group agencies• Held on 11/14/06 and 11/17/06• 27 agencies in attendance
Final draft requirements under review by state agencies• Posted online on 11/17/06• Input due by 12/04/06
5
Project Accomplishments Project Accomplishments Communication/OutreachCommunication/Outreach
Individual visits with 17 stakeholder agencies
Presented project overview/status to:
• Regents Council of Business Officers (COBO) – 10/04/06
• Regents Controllers – 10/06/06
• Information Technology Advisory Board (ITAB) – 10/24/06
• Small Agency Group – 10/25/06 and 11/29/06
• Agency STARS Rapport Association (ASTRA) – 11/09/06
Project web site received over 2200 page views in
the last 60 days
6
Project Accomplishments Project Accomplishments Business Case Validation: StatusBusiness Case Validation: Status
Agency Systems Survey• Briefing to Agency CFOs on 10/03/06 • Received a total of 19 survey responses
Value Pockets Survey• Briefing to Agency CFOs on 11/02/06• Received a total of 12 responses, several
outstanding
Draft of business case report due 11/30/06
7
Preliminary Findings Preliminary Findings Systems SurveySystems Survey
Total of 238 systems identified as performing administrative functions within the scope of this project (e.g., GL, AP, Procurement)• Includes automated tracking tools such as PC-based
spreadsheets and databases• 146 in Dept. of Administration alone
Total of $28,091,912 in Annual Systems Costs reported over 11-year estimating period
Only 9 agencies provided estimates of costs to enhance existing/implement new systems• Approximately $7.2 million in costs• $5.5 million from KDOT alone
8
Preliminary Findings Preliminary Findings Systems SurveySystems Survey
Comparables from Other States:• Kansas (25,000 employees)
– Approximately $3 million per year in ongoing avoided systems cost (so far)
• Minnesota (33,000 employees)– Approximately $5 million
• Tennessee (41,000 employees)– Approximately $16 million
9
Preliminary Findings Preliminary Findings Value Pockets SurveyValue Pockets Survey
Comparables from Other States:• Kansas (25,000 employees)
– Approximately $8.5 million in annual FTE-based Value Pocket benefits; no discounting of this amount has yet been applied
• Minnesota (33,000 employees)– Estimated $4.6 million could potentially be realized
annually in FTE-based Value Pocket benefits
• Tennessee (41,000 employees)– Approximately $6 million in gross FTE-based Value
Pocket benefits; assumed 75% or $4.5 million could be realized annually in time
10
Preliminary Findings Preliminary Findings Proposed Functional ScopeProposed Functional Scope
Driving Factors• Functional Needs• Value Proposition• Mandate / Strategic Initiative• Organizational Change Impact• Project Staffing Considerations• Risk Avoidance / Mitigation• Funding• Prior Track Record with Similar Projects
11
Preliminary Findings Preliminary Findings Proposed Functional ScopeProposed Functional Scope
Modules• General Ledger (including Grant Accounting and
Cost Allocation) • Accounts Payable• Procurement• Asset Management• Budget Development Integration (3 options)• Reporting / Data Warehouse
Issues• SOKI• Set-Off
12
Preliminary Findings Preliminary Findings Proposed Deployment ApproachProposed Deployment Approach
“Big Bang” Deployment
Pros “True” enterprise focus as all agencies “go live” on all FMS
functionality simultaneously Reduced implementation timeframe Potentially least costly strategy as all functionality is implemented
in shorter time period Most efficient approach to data migration from legacy systems Eliminates the need for temporary interfaces that are required
when deployment “phasing” is utilized Less likely to have to implement a new software release before
FMS has been deployed at all state agencies State begins realizing the benefits and efficiencies earlier,
potentially avoiding implementation of new shadow systems for those agencies with compelling functional needs and/or pending software obsolescence
Risk of project team member turnover is reduced substantially due to compressed deployment time period for all state agencies
13
Preliminary Findings Preliminary Findings Proposed Deployment ApproachProposed Deployment Approach
“Big Bang” Deployment (cont.)
Risks Greatest change management impact to organization due to all
functionality going “live” simultaneously Major training impact as high volume of end users must be
provided with “just in time” training within a narrow window of time May require largest project team size User participation is required for a limited but intense period of
time Extensive data migration activities must be completed
simultaneously Higher risk of problems due to compressed timeline and large
functional scope with less margin to correct / mitigate problems that arise
Inability to take advantage of lessons learned from previous phase(s) of deployment
14
Preliminary Findings Preliminary Findings Proposed Deployment ApproachProposed Deployment Approach
“Phased” Deployment
Pros Provides ability to validate the “proof of concept” Provides the ability to fund project over multiple budgetary
periods Change management impact is dispersed across longer
period of time – can be focused on only those agencies that are part of specific deployment phases
Knowledge gained and lessons learned from initial deployment phases can be used for remaining deployments of the FMS throughout state government
Project team focus is on a single phased deployment at a time
15
Preliminary Findings Preliminary Findings Proposed Deployment ApproachProposed Deployment Approach
“Phased” Deployment (cont.)
Risks Requires concurrent operation of legacy systems and new FMS for
long period of time Requires greater timeline to complete entire deployment across
state government Can be very costly to the State due to increased timeline May lead to difficulties in completing deployments for agencies
scheduled for deployment late in project due to possible loss of momentum, lack of funding, and other issues that may arise due to an expanded rollout schedule
Complex data migration from legacy systems and ultimate elimination of legacy system usage due to deployment “phasing”
Requires the use of temporary interfaces due to “phasing” Will take a longer period of time to realize benefits and efficiencies Need may arise to implement a new software release before FMS
has been deployed at all agencies due to extended deployment time period
16
Preliminary Findings Preliminary Findings Proposed Deployment ApproachProposed Deployment Approach
“Phased” Deployment (cont.)
Risks (cont.) Possible inconsistencies in enterprise data and reporting due to the
continued use of the FMS for the agencies participating in the Pilot Project and continued use of legacy systems by the remaining state agencies until all agencies have been deployed on the FMS
All state agencies may be involved in the initial system design and configuration, but may have to wait a considerable period of time before they can actually access to the FMS
Numerous iterations of training must be provided concurrently with deployment phasing, and may require updating due to system enhancements/changes associated with new software releases and “fixes” that are applied during the extended deployment time period
Some agencies may have compelling functional needs and/or pending software obsolescence that may cause them to move forward independent of the FMS project due to lengthy deployment timeline
Major risk of project team member turnover due to lengthy deployment time period could cause problems for state agencies scheduled for the late phases of deployment
17
Preliminary Findings Preliminary Findings Proposed Deployment ApproachProposed Deployment Approach
“Big Bang” deployment strategy recommended
Pre-implementation activities completed over period of 12-18 months
21 – 24 month implementation period Currently reviewing tentative go-live target
(fiscal vs. mid-year)
18
Preliminary Findings Preliminary Findings Proposed Project Organization - State (49)Proposed Project Organization - State (49)
Steering Committee
Project Manager(1)
Deployment Lead(1)
Change Management
(4)
Training(8)
Finance Team Lead(1)
Accounts Payable(2)
Budget Development
(2)
General Ledger /Budget Control
(3)
Project/Grant Accounting
(3)
Purchasing Lead(1)
Asset Management(2)
Purchasing(3)
Project Admin Support
(1)
Technical Lead(1)
Enhancement/Workflow
(5)
Infrastructure(4)
Interface/Conversion
(5)
Report Development
(2)
19
Preliminary Findings Preliminary Findings Proposed Project Organization - Consultants (30)Proposed Project Organization - Consultants (30)
Project Manager(1)
Deployment Lead(1)
Change Management/Deployment
(4)
Training(4.5)
Finance Team Lead(1)
Accounts Payable(1)
Budget Development
(1)
General Ledger /Budget Control
(1)
Project/Grant Accounting
(1)
Purchasing Lead(1)
Asset Management(1)
Purchasing(1)
Project Admin Support
(1)
Technical Lead(1)
Enhancement/Workflow
(3.5)
Infrastructure(2)
Interface/Conversion
(2.5)
Report Development
(1.5)
20
Preliminary Findings Preliminary Findings Pre-Implementation ActivitiesPre-Implementation Activities
Formalize pre-implementation governance structure and organization as a project and staff appropriately
Perform organizational change readiness assessment Develop and initiate staffing approach for
implementation project Benchmark existing financial management and
procurement business processes Document State’s “As Is” business processes Development of existing legacy system reports
inventory Perform data cleansing activities Review and evaluate existing chart of accounts
21
Preliminary Findings Preliminary Findings Pre-Implementation ActivitiesPre-Implementation Activities
Conduct alternative solutions analysis to determine how best to address existing SOKI, Set-Off, and SHARP time and effort functionality
Develop RFP(s) for FMS software and associated implementation services, and evaluation process to be followed
Development of demonstration evaluation scripts to be followed by vendor finalists during their software demonstrations
Proposal evaluation and contract negotiations Plan and prepare re: project logistics (physical space
for project team, etc.)
22
Upcoming ActivitiesUpcoming Activities
Review/Approve Business Case Analysis Catalog Major System interfaces
• Through December 11
Finalize Stakeholder Input and Approval• Through December 4
Deliver Updated Needs Assessment• December 15
Conduct Final Steering Committee Meeting• January 2007