Upload
lexuyen
View
215
Download
0
Embed Size (px)
Citation preview
State of KansasState of Kansas
Financial Management SystemFinancial Management SystemNeeds Assessment ProjectNeeds Assessment Project
Steering Committee MeetingSeptember 28, 2006
2
Meeting AgendaMeeting Agenda
Introductions Project Governance Project Overview Key Activities
• Requirements Validation• Business Case Analysis
Upcoming Activities Questions
3
Project Governance Project Governance Organizational StructureOrganizational Structure
EXECUTIVE SPONSORS
STEERING COMMITTEE
PROJECT DIRECTORDuncan Friend
PROCUREMENT TEAMChris Howe/Angela Hoobler, Manager
TECHNOLOGY TEAMCathy Jones/Jay
Coverdale, Manager
PROCUREMENT FOCUS GROUP
TECHNOLOGY FOCUS GROUP
PROJECT CONSULTANTSSalvaggio, Teal & Assoc.
ACCOUNTING TEAMBob Mackey/Martin Eckhardt, Manager
ACCOUNTING FOCUS GROUP
ELECTED OFFICIALS
AGENCY SUBJECT MATTER EXPERTS
AGENCY CFOsAGENCY CIOs
4
Project SponsorsProject SponsorsMembershipMembership
Duane Goossen• Secretary of Administration
Carol Foreman• Deputy Secretary of Administration
Denise Moore• Executive Branch Chief Information Technology
Officer
5
Project SponsorsProject SponsorsRoles & ResponsibilitiesRoles & Responsibilities
Actively champion the project Establish and cultivate legislative sponsors
Provide executive level support Steering Committee and Project Team guidance Monitor project progress
Provide clear direction Ensure that the FMS initiative is aligned with the State’s strategic goals
and objectives Empower the team
Steering Committee and the Project Team Assist with issue resolution
Resolve issues in a timely manner per the project issue escalation policy
Assist in removing obstacles Secure required resources
Ensure funding/staff necessary to achieve project objectives
6
Steering CommitteeSteering CommitteeMembershipMembership
Chair - Carol Foreman, Deputy Secretary of Administration Mary Blubaugh, Board of Nursing Alan Conroy, Legislative Research Department Gary Daniels, Department of Social & Rehabilitation Services Elaine Frisbie, Department of Administration; Division of Budget Kathy Greenlee, Department on Aging Mike Hayden, Department of Wildlife and Parks Lynn Jenkins, State Treasurer Deb Miller, Department of Transportation Reginald Robinson, Board of Regents Howard Schwartz, Judicial Administrator Joan Wagnon, Department of Revenue Roger Werholz, Department of Corrections
7
Steering CommitteeSteering CommitteeRoles & ResponsibilitiesRoles & Responsibilities
Actively participate in Steering Committee meetings Remove obstacles to project success Actively champion the project Communicate project status within respective
agencies Review and provide input to final report
December 11 – December 14
8
Sponsor/Steering Committee InvolvementSponsor/Steering Committee InvolvementDecision MakingDecision Making
Key Decisions • Will be presented during mid October – mid November
– Impact analysis will be provided (as appropriate) to facilitate decision making
– Documentation and communication of the decision is critical
Examples of Key Decisions• Proposed funding model• Maximizing return on investment
– Level of agency participation– User agency “shadow” systems – Duplicate copies of FMS software
• Deployment strategy (phased vs. “big bang”)• Functional scope• Procurement strategy
9
Enterprise Resource Planning (ERP) – A comprehensive suite of integrated modules delivered by a single software vendor that provides end-to-end support for statewide administrative services
For purposes of this study, we will use the term ‘Financial Management System’ (FMS) rather than ERP since the scope of the project includes financials and procurement only – due to current / future investment in the SHARP system
FMS is a proposed solution that provides functionality similar to STARS, SOKI, Central Setoff System, and other agency administrative systems, but in a fully integrated manner
Project OverviewProject OverviewWhat is ERP? FMS?What is ERP? FMS?
10
Project Overview Project Overview Why FMS?Why FMS?
Satisfy the needs of the agencies• Eliminate the proliferation of stand-alone agency systems• Avoid the cost associated with new agency administrative
systems • Avoid the cost associated with maintenance/upgrades of
current systems Significantly improve the quality, quantity, and
timeliness of information • Effective decision-making• Efficient and accurate research capabilities • Enhanced ad hoc reporting and inquiry functionality
Streamline processing and control of electronic “documents” through workflow management• Facilitates document routing, review and approval
11
Project Overview Project Overview Why FMS?Why FMS?
Streamline and simplify State’s business processes • Financial• Budgeting• Procurement• Other administrative operations
Improve operational efficiency • Commercially-available FMS systems include many features
representing best management practices Support Web-enabled self-service
• State employees• Vendors conducting business with the State
12
Project Overview Project Overview Why FMS?Why FMS?
Replace existing disparate systems• Costly to maintain• Difficult to administer
Automate and integrate• State’s financial accounting, procurement, asset management,
and other administrative business processes within a single database
Provide single point of entry• Eliminate duplicate points of data entry• Eliminate duplicate databases• Simplify reconciliation
Reduce/eliminate paper documents• Reduce paper and handling costs (e.g., vouchers) • Simplify record retention and audit compliance
13
CORE FINANCIAL• General Ledger /
Budgetary Control• Accounts Payable• Accounts Receivable
& Cash Receipting• Cash Management• Cost Allocation• Grant Accounting• Project Accounting• Asset Management
PROCUREMENT• Solicitations (RFx)• Catalog Procurement• Reverse Auctions• Inventory Management• Commodity Management• Vendor ManagementHR / PAYROLL
• Automated Interfaces to/from SHARP
BUDGET DEVELOPMENT INTEGRATION
• Appropriation Budget
Common Database
Project OverviewProject OverviewProposed FMS functionality for considerationProposed FMS functionality for consideration
14
Key Activities Key Activities FMS Needs AssessmentFMS Needs Assessment
Update the system requirements for a new integrated FMS
Update the business case analysis associated with implementing a new FMS
Determine whether there is a compelling business case for procuring/implementing an integrated statewide FMS
Submit recommendations regarding• Organizational best practices• Implementation best practices
15
Business Case Analysis Report
Sept
Oct Nov Dec
Project Start-
UpValidate the
Business Case
FMS Needs Assessment Update
Key Deliverables
Key Activities Key Activities TimelineTimeline
Validate Functional / Technical
Requirements
Updated Needs Assessment
Organization / Implementation Best Practices
16
Business Case AnalysisBusiness Case AnalysisCost versus Benefits Cost versus Benefits
FMS Costs • Software• Hardware• Implementation• Upgrades• Ongoing Maint. & Mgmt.• Training
FMS Benefits/Avoided CostsSystem Savings• Replacing current systems• Not implementing planned
systemsProcess-Improvement Benefits• Value Pocket benefits
vs.
1 2
3
Standard financial analyses will be performed using dollar-quantifiable costs and benefits: - NPV (Net Present Value) - IRR (Internal Rate of Return) - Payback Period
17
Business Case Analysis Business Case Analysis Information We Need From AgenciesInformation We Need From Agencies
Value Pocket Survey Interviews with State employees
who are process/functional SMEs
Process-Improvement Benefits: Estimated cost savings and other benefits that an FMS system would likely enable/yield
Agency System Survey Interviews with statewide
administrative systems SMEs
System Savings: Estimated cost savings from:
Replacing existing statewide & agency-specific systems
Not implementing planned/anticipated systems
Information provided by vendors and other statewide ERP projects
STA experience
FMS Costs: Estimated costs of implementing, maintaining, and upgrading
Information Needed
Data-Gathering Approach
SMEs = Subject Matter Experts
2
1
3
18
Business Case Analysis Business Case Analysis What Are Value PocketsWhat Are Value Pockets©©??
Value Pockets Most likely sources of value (i.e., cost
savings and other benefits) to be found in each process/functional area within the scope of an FMS implementation
Provide quantified justification STA’s proprietary formulas and calculations
Used to quantify process-improvement benefits obtained through the implementation of a statewide FMS
19
Specific Nature and Source of the Value FMS Enabler Formula for Calculating the Value (i.e., Benefit or
Cost Savings), if applicable Source of Value for Each Variable in the Formula
Business Case Analysis Business Case Analysis Value Pocket ComponentsValue Pocket Components
For each Value Pocket in each process/functional area, we identify:
20
Requirements from 2001 Needs
Assessment Study
STA Requirements
Toolkit
Baseline Requirements
Draft Requirements
Final Requirements
Focus Group
End User Community
Functional and Technical Requirements Development Process
Project Team
Update / Validate FMS RequirementsUpdate / Validate FMS Requirements
21
Functional ComponentsProcurementGrants / ProjectsCash ManagementGeneral Ledger / Cost AllocationAccounts Payable / Accounts ReceivableInventory / Asset ManagementBudget Development / IntegrationHR / Payroll IntegrationData Warehousing / ReportingGeneral and Technical
Project ScopeProject ScopeFMS Needs AssessmentFMS Needs Assessment
22
Sample Functional RequirementsSample Functional Requirements
Business RequirementsVendor
Response CommentsVendor Files
PU 19.00
System provides the ability to track and to report/inquire on vendor performance including delivery, complaints (including complaints about discrimination allegations) and resolution.
PU 20.00
System provides the ability to search for a vendor by commodity code/number/description and by vendor number/name. (Attach vendor to commodity).
PU 21.00System can infer default vendor information from the vendor master file when creating requisitions and purchase orders.
PU 22.00
System provides the ability to automatically carry forward a vendor number to the next transaction (i.e., requisition to PO and PO to invoice), optional on requisition.
PU 23.00
System provides the ability to assign status codes to vendors (i.e., inactive) and this status can vary by agency or facility (i.e., a vendor can be blocked from use by certain agencys/facilities but not blocked for other agencys/facilities).
PU 24.00System maintains pricing information, quantity breaks, freight terms and shipping information for each vendor.
PU 25.00System tracks vendor by performance / history, date added / deleted or inactivated and reason.
PU 26.00System provides the ability to classify one-time vendors and to check whether already on file based on multiple criteria (e.g., FEIN, SSN, etc.).
PU 27.00System can delete or deactivate vendor from vendor listing by date with reason. Historical data would be retained.
PU 28.00
System rates vendor at each event point based on user-defined criteria and these ratings are displayed at each point in the procurement process.
PU 29.00Vendor numbers (numeric and alphanumeric) can be system generated or assigned manually.
Reference Number
23
Obtain Agency (Stakeholder) InputObtain Agency (Stakeholder) Input
Sixteen agencies have been identified as “stakeholder agencies”• Adjutant General• Department on Aging• Department of Agriculture• Department of Administration• Department of Health and Environment• Department of Transportation• Highway Patrol• Department of Labor• Department of Commerce• Juvenile Justice Authority• Department of Corrections• Department of Revenue• Social and Rehabilitation Services• State Treasurer• Judicial Branch• Department of Wildlife and Parks
24
Conduct Agency Outreach SessionsConduct Agency Outreach Sessions
Agencies are invited to participate!Fifty-eight individuals representing twenty-three
(23) agencies are participating in our focus group sessions
Sixteen (16) large agencies are participating in stakeholder meetings
All agencies are invited to review and comment on the draft requirementsPosted to the project website
All agencies are invited to participate in the Cost Benefit Survey
All agencies are invited to participate in the final Agency Briefings
25
Project RisksProject RisksSpecifically related to the FMS Needs AssessmentSpecifically related to the FMS Needs Assessment
Executive Level Sponsorship/Involvement Appropriate Level of Agency Participation
• Timeliness of survey response• Focus Group subject matter expert (SME)
participation Decision Making Process
• Impact of key decisions
26
Upcoming ActivitiesUpcoming Activities
Validate Functional &Technical Requirements• October 2 – November 21
Perform Business Case Analysis• Business Case Report
– November 30 Obtain Stakeholder Input and
Approval• November 30 – December 7
Conduct Agency Outreach Sessions• December 7 – December 14
Updated Needs Assessment• December 11
27
Future MeetingsFuture Meetings
October Meeting• October 25
– 2:00 p.m. – 4:00 p.m.
November Meeting• November 16
– 2:00 p.m. – 4:00 p.m.