Standard Specification for Roadworks - JKR-SPJ-1988

Embed Size (px)

Citation preview

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    1/270

    Roads BranchPublic Works Department Malaysia

    Jalan Sultan Salahuddin50582 Kuala Lumpur

    JKR/SPJ/1988

    5.0m0m

    7.0m0m

    StandardSpecifications For

    Roadworks

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    2/270

    Page 1

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    KERAJAAN MALAYSIA

    JABATAN KERJA RAYA MALAYSIA

    CAWANGAN JALAN KETUA PENGARAH KERJARAYAIBU PEJABAT JABATAN KERJARAYA MALAYSIA JABATAN KERJARAYA MALAYSIAJALAN SULTAN SALAHUDDIN, JALAN SULTAN SALAHUDDIN 50582 KUALA LUMPUR. 50582 KUALA LUMPUR

    FOR INTERNAL USE ONLY

    STANDARD SPECIFICATION

    FOR

    ROAD WORKS

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    3/270

    Page 2

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    FOR INTERNAL USE ONLY

    ADDENDUM NO. 1

    This Addendum shall be made part of the JKR Standard Specification For Roads Works

    1. Table 4.8 - Gradation Limit For Asphaltic Concrete Clause 4.2.4.2, page S4 21

    should read as follows :

    Mix Type Wearing Course Binder Course

    MixDesignation

    ACW 20 ACB 28

    B.S Sieve % Passing by weight

    37.5 mm

    28.0 mm

    20.0 mm

    14.0 mm

    10.0 mm

    5.0 mm

    3.35 mm

    1.18 mm

    425 um

    150 um

    75 um

    100

    76 -- 100

    64 -- 89

    56 -- 81

    46 -- 71

    32 -- 58

    20 -- 42

    12 -- 28

    6 -- 16

    4 -- 8

    100

    80 -- 100

    72 -- 93

    58 -- 82

    50 -- 75

    36 -- 58

    30 -- 52

    18 -- 38

    11 -- 25

    5 -- 14

    3 -- 8

    2. Table 4.9- Design Bitumen Contents Clause 4.2.4.3, page S4 - 23 should read as follows :

    ACW 20 - Wearing Course 4.5 -- 6.5 %

    ACW 28 - Binder Course 4.0 -- 6.0

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    4/270

    Page 3

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    FOR INTERNAL USE ONLY

    ADDENDUM NO. 2

    This Addendum shall be made part of the JKR Standard Specification For Roads Works

    6.2.5.5 Sign Faces

    Sign faces for permanent traffic sign shall be as

    shown on the Drawing and shall comply with

    the Malaysian Standard Specification for

    Reflective Sign Faces Materials (MS 1216). All

    retro-reflective sheeting shall be fixed in accor-

    dance with the manufacturers instruction.

    Unless otherwise agreed by the S.O., sign

    faces shall be formed from a single piece of

    retro-reflective sheeting.

    Where, with the aggrement of the S.O., morethan one retro-reflective sheeting is used, the

    number of sheets shall be kept to a minimum.

    All faces up to 1 m in size shall be produced

    with a single sheet and no joint will be

    accepted.

    Only vertical and horizontal joint shall be per-

    mitted and all join in retro-reflective shetting

    shall be overlapped by not less than 6 mm. The

    overlap in the horizontal joint shall be from the

    top and the vertical joint shall be from the left;but joints will be only be accepted for prismatic

    retro-reflective sheeting.

    Retro-reflective sheeting shall be applied

    evenly over the whole surface of the sign plate

    and shall adhere fully. it shall be free from

    twists, cracks, folds or cuts, air bubbles and

    other blemishes.

    All retro-reflective sheeting used on the same

    sign shall be carefully matched for colour toproduce a uniform appearance both by day and

    by night. Non-uniform shades of colour on any

    one sign will not be accepted.

    The edges of all the retro-reflective sheeting

    shall be properly fitted to ensure no

    delimination of the sheeting from the base

    substrate.

    where shetting is applied to the extruded

    section by pressure roller, it shall extend over

    the top and bottom edges of this sections by not

    less than 3 mm.

    Any cut-outlet letters, numerals, symbols and

    borders shall be of material compatible with the

    sheeting to which they are applied. They shall

    be applied in accordance with the sheeting

    manufacturers instruction.

    The finish of all sign faces shall be capable of

    passing the tests described in MS 1216, and

    and standard of fabrication and workmanship

    shall be such that under normal conditions of

    service and proper maintenance, the sign faces

    shall last not less than 5 years without any

    seriousblemishes or defects for Engineering

    Grade retro-reflective sheeting and 8 years for

    High Intensity and prismatic retro-reflective

    sheeting.

    The Contractor shall furnish to the S.O. a letterof warranty for the specified period for all sign

    faces from the manufacturer of the sheeting or

    the sign fabricator.

    The retro-reflective sheeting manufacturer shall

    furnish the S.O. written warranty that the fluo-

    rescent colours shall be durable for a minimum

    3 years for temporary signs.

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    5/270

    Page 4

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    6.2.6.1.2 Requirements

    i) Photometric - Coefficient of

    Retroreflection RA

    when the sheeting applied on aluminium

    test panels is measured in accordance

    wth ASTM E 810, it shall have

    minimum coefficient of retro-reflectivevalue as shown in Table I. The rotation

    angle shall be *90 , the observation

    angles shall be 0.2 and 0.5, the

    entrance angles and +50, and the

    entrance angle (component 1) shall be

    - 4, +30, and +50, and the entrance

    angle component 2 = 0.

    FOR INTERNAL USE ONLY

    ADDENDUM NO. 3

    This Addendum shall be made part of the JKR Standard Specification For Roads Works

    6.2.6.1 FLUORESCENT ORANGE WIDE ANGLE PRISMATIC RETRO-

    REFLECTIVE SHEETING FOR THE WORK ZONE

    6.2.6.1.1 Description

    The flurescent orange wide angle prismatic

    retro-reflective sheeting is specifically designed

    for use on rigid substrade work zone signs to

    provide high visual impact under nighttime and

    daytimedriving condition, including low

    visibility periods such as dawn, dusk, and

    overcast days. The sheeting shall consist ofprismatic lenses formed in a transparent

    flurescent orange synthetic resin, sealed, and

    baked with and aggressive presure sensitive

    adhesive protected by a removable liner. The

    sheeting shall have a smooth surface with a

    distinctive interlocking diamond seal pattern

    and orrientation marks visible from the face.

    TABLE I

    Minimum Coefficient of Retroreflection RA

    (Candelas per footcandle per square foot)

    (90 Rotation Angle*)

    Observation Angle ( ) Entrance Angle ( ) Orange

    0.20.20.2

    1.5

    0.50.5

    - 4+30+50

    -4

    +30+50

    20012050

    80

    5020

    * The datum mark (arrow) imprinted on the face of the sheeting shall be the datum mark for test

    purposes. For the specified 90 rotation angle, the sheeting shall be positioned on the goniometer

    so that the direction of this datum mark is perpendicular to the observation plane (this geometry is

    equivalent to a 90 orientation angle with a presentation angle of 0 in the measurement geometry

    described in Fed. Test Method Standard 370).

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    6/270

    Page 5

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    i) Daytime Color

    Color shall conform to the reqiurement

    of Table II. Daytime color and

    maximum spectral radiance factor (peak

    reflectance) of sheeting mounted onaluminium test panels shall be

    determined instrumentally in accordance

    with ASTM E 991.

    The value shall be determined on a HunterLab

    Labscan 6000 0/45 spectrocolorimeter with

    option CMR 559 [or approved equal 0/45

    (45/0) instrument withcircumferential viewing(illumination)]. Computation shall be done in

    accordance with ASTM E 308 for the 2

    observer.

    FOR INTERNAL USE ONLY

    TABLE IIColor Specification Limit ** (Daytime)

    Color 1 2 3 4 ReflectanceLimit Y (%)

    X Y X Y X Y X Y Min. Max.

    Orange(New)

    Orange(Weathered)

    .583

    .583

    .416

    .416

    .523

    .523

    .397

    .397

    .560

    .560

    .360

    .360

    .631

    .631

    .369

    .369

    30

    20

    -

    45

    Maximum spectral radiance factor, new : 110%, min.weathered : 60%, min.

    iii) Nighttime Color.

    Nighttime color of the sheeting applied to alumium test panel shall be determined

    instrumentally in accordance with ASTM E 881 and calculated in the u, v coordinate

    system in accordance with ASTM E 308. Sheeting shall be measured at 0.33 observation

    and - 4 entrance at 90 rotation. Color shall conform to the requirements of Table III.

    ** The four pairs of chromaticity coordinates determine the acceptable color in terms of the CIE

    1931 standard colorimetric system measured with standard illuminatant D65.

    TABLE IIColor Specification Limit ** (Nighttime)

    Color 1 2 3 4

    u v u v u v u v

    Orange(New and

    Weathered)

    .400 .540 .475 .529 .448 .522 .372 .534

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    7/270

    Page 6

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    iv) Resistance to Accelerated Weathering.

    The retro-reflective surface of the sheeting

    shall be weather resistant and show no

    appreciable cracking, blistering, crazing, or

    dimensional change after 1 yearsunprotected outdoor exposure in south

    Florida, south-facing and inclined 45

    from the vertical, or after 1500 hours

    exposure in a xenon arc weatherometer in

    accordance with ASTM G 26, Type B,

    Method A. Following exposure, panels

    shall be washed in a 5% HCL solution for

    45 seconds, rinsed throughly with clean

    water, blotted with a soft clean cloth and

    brought to equilibrium at standard

    conditions. After cleaning, the coefficient

    of retroreflection shall be not less than 100

    when measured as in D.2, below, and the

    color is expected conform to the

    requirements of Table II and III for

    weathered sheeting. The sample shall :

    a) Show no appreciable evidence of

    cracking, scaling, pitting, blistering,

    edge lifting or curling or more than 1/32

    inch (0.08 cm) shrinkage or expansion.

    b) Be measured only at angles of 0.2observation, - 4 entrance and 90

    rotation. Where more than one panel of

    a color is measure, the coefficient or

    retroreflection shall be the averange of

    all determinations.

    v) Impact Resistance.

    The retroreflective sheeting applied

    according to the sheeting manufacturersrecommendations to a test panel of alloy

    6061-T6, 0.040 (0.10 cn) by 3 (7.6 cm)

    by 5 (12.7 cm) and conditioned for 24

    hours, shall show no cracking outside the

    impact of 100 inch-pounds (11.3Nm) using

    a weight with a 5/8 in. (15.8 mm) diameter

    rounded tip dropped from a height

    necessary to generate an impact of 100

    inch-pounds, at test temperatures of both

    32 F (0 C) and 72 F (22 C).

    vi) Resistance to Heat.

    The retroreflective sheeting, applied to a

    test panel as in E., above and conditioned

    for 24 hours, shall be measured in

    accordance with paragraph. A. at 0.2observation and - 4 entrance angles at 90

    rotation and exposed to 170 + 5F (77 +

    3C) for 24 hours in an air circulating

    oven. After heat exposure the sheeting

    shall retain a minimum of 70% of the

    original coefficient of retroreflection.

    vii) Field Performance

    Retroreflective sheeting processed and

    applied to sign blank materials in

    accodance with the sheeting

    manufacturers recommendations, is

    expected to perform effectively for a

    minimum of 3 years. the retroreflective

    sheeting will be considered unsatisfactory

    if it has deteriorated due to natural causes

    to the extent that : (1) the sign is ineffective

    for its intended purposed when viewed

    from a moving vehicle under normal day

    and night driving conditions; or (2) the

    coefficient of retroreflection is less than100 when measured at 0.2 observation

    and - 4 entrance at 90 rotation. All

    measurements shall be made after sign

    cleaning according to the sheeting

    manufacturers recommendations.

    FOR INTERNAL USE ONLY

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    8/270

    Page 7

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    FOR INTERNAL USE ONLY

    STANDARD SPECIFICATION FOR ROADS WORKS

    CONTENT PAGE

    SECTION 1 General S1-11 to S1-31

    SECTION 2 Earthworks S2-1 to S2-20

    SECTION 3 Drainage Works S3-1 to S3-31

    SECTION 4 Flexible Pavement S4-1 to S4-55

    SECTION 5 Portland Cement Concrete Pavement S5-1 to S5-21

    SECTION 6 Road Funiture S6-1 to S6-22

    SECTION 7 Street Lighting S7-1 to S7-19

    SECTION 8 Traffic Signals S8-1 to S8-33

    SECTION 9 Concrete S9-1 to S9-39

    SECTION 10 Piling Works S10-1 to S10-35

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    9/270

    Page 8

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    FOR INTERNAL USE ONLY

    SECTION 1

    GENERAL

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    10/270

    Page 9

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    FOR INTERNAL USE ONLY

    SECTION 1 - GENERALPage

    1.1 GENERAL DESCRIPTION OF THE PROJECT S1-11

    1.2 SCOPE OF WORKS S1-111.3 NOTES, ABBREVIATIONS AND UNITS OF MEASUREMENT S1-11

    1.3.1 Notes S1-11

    1.3.2 Abbreviations S1-11

    1.3.3 Units of Measurement S1-11

    1.4 PROGRAMME OF WORKS S1-12

    1.5 LIMITATION OF SITE S1-12

    1.6 SUPPLY OF MATERIALS S1-12

    1.7 MATERIALS OF MALAYSIAN ORIGIN S1-12

    1.8 SETTING OUT S1-13

    1.9 DIMENSIONS AND LEVELS S1-13

    1.10 PROTECTION OF WORKS S1-13

    1.11 DESIGN OF TEMPORARY WORKS BYTHE CONTRACTOR S1-13

    1.12 CONTRACTOR'S SUPERINTENDENCE S1-14

    1.13 INSPECTION AND TESTS S1-14

    1.14 COVERING UP OF WORK S1-14

    1.15 OFFICE ACCOMMODATION FOR S.O. AND HIS STAFF S1-14

    1.16 VEHICLES FOR THE S.O.'S STAFF S1-16

    1.17 CONTRACTOR'S OFFICE AND ACCOMODATION S1-16

    1.18 MATERIAL TESTING LABORATORY AND STAFF S1-16

    1.19 PROVISION FOR SURVEY INSTRUMENTS AND CHAINMEN S1-17

    1.20 MAINTENANCE OF EXISTING ROADS AND PROTECTION

    OF TRAFFIC S1-17

    1.20.1 Maintenance of Existing Roads, Bridges, Culverts, etc. S1-17

    1.20.2 Temporary Diversions S1-17

    1.20.3 Half-width Construction and Traffic Control S1-18

    1.20.4 Temporary Traffic Signs S1-19

    1.20.5 Temporary Works S1-19

    1.21 LOCATION, TEMPORARY PROTECTION AND TEMPORARY

    DIVERSION OF PUBLIC UTILITY INSTALLATIONS AND

    OTHER SERVICES S1-19

    1.22 WATER AND ELECTRICITY SUPPLY S1-20

    1.23 PROJECT SIGNBOARD S1-20

    1.24 PHOTOGRAPHIC RECORD OF WORKS S1-20

    1.25 AS-BUILT DRAWINGS AND MICROFILMING S1-211.26 CLEARING UP OF SITE S1-21

    1.27 OPPORTUNITIES FOR OTHER CONTRACTORS S1-21

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    11/270

    Page 10

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    FOR INTERNAL USE ONLY

    Page

    APPENDIX 1A GENERAL DESCRIPTION OF PROJECT S1-22

    APPENDIX 1B SCOPE OF WORKS S1-23

    APPENDIX 1C VEHICLES FOR S.O. AND HIS STAFF S1-24

    APPENDIX 1D LIST OF LABORATORY EQUIPMENT

    (a) Soil Testing Equipment S1-25

    (b) Concrete Testing Equipment S1-27

    (c) Flexible Pavement Testing Equipment S1-27

    APPENDIX 1E SURVEY EQUIPMENT S1-30

    FIGURE 1-1 APERTURE CARD FOR MICROFILM S1-31

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    12/270

    Page 11

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    SECTION 1 - GENERAL

    1.1 GENERAL DESCRIPTION OFTHE PROJECT

    The general description of the project is as

    given in Appendix 1A.

    1.2 SCOPE OF WORKS

    The Works covered in this Contract comprise

    the provision by the Contractor at his own risk

    and cost of all materials, tools, plants, labour,

    transport and everything else necessary for the

    construction and completion of the Works as

    given in Appendix 1B all to the approval of the

    S.O.

    1.3 NOTES, ABBREVIATIONS ANDUNITS OF MEASUREMENT

    1.3.1 Notes

    i) Any clause in this Specification which

    relates to work or materials not included

    in the Works shall be deemed not

    applicable.

    ii) Unless stated to the contrary, any

    dimension of material described means

    the finished or fully compacted

    dimension.

    iii) All Standards and Codes of Practice

    referred to in this Specification shall be

    deemed to be the editions current at the

    time of Tender. If the Malaysian

    Standard exists, which the S.O. deems to

    be equivalent to the British or otherStandard specified, then the Malaysian

    Standard shall be followed.

    In the event of any discrepancy between

    the provision of this Specification and

    the provision within the relevant

    Standards or Codes of Practice as

    mentioned in this Specification, then the

    provision of this Specification shall take

    precedence.

    iv) The terms "Engineer" and

    "Superintending Officer" shall be

    synonymous.

    1.3.2 Abbreviations

    a) M.S. means Malaysian Standards

    published by the Scientific and

    Industrial Research Institute of

    Malaysia (SIRIM).

    b) B.S. means British Standards

    published by the British Standard

    Institution.

    c) A.A.S.H.T.O. means The American

    Association of State Highway and

    Transportation Officials.

    d) A.S.T.M. means The American

    Society for Testing and Materials.

    e) M.D.D. means Maximum Dry

    Density.

    f) O.M.C. means Optimum Moisture

    Content.

    g) C.B.R. means California Bearing

    Ratio.

    h) S.O. means Superintending Officer.

    i) B.Q. means Bill of Quantities.

    1.3.3 Units of Measurement

    All units of measurement used in thisSpecification and in the Bill of

    Quantities shall be in accordance with

    the metric system unless otherwise

    stated.

    Where British Imperial units are shown

    or stated the following conversions shall

    apply :-

    FOR INTERNAL USE ONLY

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    13/270

    Page 12

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    1 inch = 25.40 millimetres

    1 foot = 0.3048 metres

    1 lb = 0.4536 kilograms

    1 gallon = 4.5461 litres

    1 lb/sq.in = 6.895 x 10-3 N/sq.mm

    1.4 PROGRAMME OF WORKS

    Within thirty (30) days after the receipt

    of the Letter of Acceptance of Tender,

    the Contractor shall submit to the S.O.

    for his approval a programme showing

    the order of work activities and time

    schedule in which the Contractor

    proposes to carry out the Works and

    shall, whenever required by the S.O. or

    the S.O.'s representative, furnish in

    writing, particulars of the Contractor's

    arrangement for carrying out such works

    and of the construction plants and

    temporary works, if any, which the

    Contractor intends to supply, use or

    construct as the case may be. The

    submission to and approval by the S.O.

    or the S.O.'s representative of such a

    programme or the furnishing of such

    particulars shall not relieve the

    Contractor of any of his duties orresponsibilities under the Contract.

    If at any time it should appear to the

    S.O. that the actual progress of the

    Works does not conform to the approved

    programme referred to herein before, the

    Contractor shall submit for approval, a

    revised programme showing the

    modifications to the previously

    approved programme necessary to

    ensure the completion of the wholeWorks within the time set for

    completion.

    1.5 LIMITATION OF SITE

    The Contractor shall ensure that all his

    plants, materials, temporary workshops,

    stores and offices are kept within the

    Site at locations approved by the S.O.

    Should the Contractor require additional

    land outside the Site for his workyards,

    stores, offices, temporary haul roads or

    any other temporary structures, he shall,

    on his own, purchase or rent any

    additional area he may need.

    Areas or area to be rendered as part of

    the Site shall be subject to the S.O.'s

    approval.

    1.6 SUPPLY OF MATERIALS

    The Contractor shall place orders for

    specified materials at such times as

    will enable him to execute the Works in

    accordance with his approved

    programme.

    If the Contractor's failure to supply any

    material causes any interruption or delay

    in the progress of the Works, the

    Government may supply any portion

    or all of the materials and the cost

    borne by the Contractor shall be either

    that as calculated at the current market

    rates or the actual cost to the

    Government at the date of supply,

    including overheads or any othercharges, whichever is the greater.

    Any costs incurred under this Section

    shall be deducted from the Contract

    Sum. No claim for loss of profit under

    the conditions of this Contract shall be

    deemed to have arisen. No action taken

    under this Section shall in any way

    affect or modify the right of the

    Government to claim for damages in the

    event of the Contractor's failure tocomplete the Works by the agreed date.

    1.7 MATERIALS OF MALAYSIANORIGIN

    Materials of Malaysian origin where

    available must be used by the Contractor

    to the exclusion of imported materials

    and this requirement shall be allowed

    for in his tender.

    FOR INTERNAL USE ONLY

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    14/270

    Page 13

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    Under no circumstances shall the

    Contractor be permitted to use imported

    materials unless he can prove to the

    satisfaction of the S.O. that the

    materials are not available locally, or if

    available are not of an acceptablestandard.

    1.8 SETTING OUT

    Before commencing the Works at any

    location, the Contractor shall provide

    and install precast concrete reference

    beacons on both sides of the road

    centre-line at a spacing of 300 metres.

    The beacons shall be firmly sited at right

    angles to the centre-line at a distance

    from the centre-line of 15 metres or such

    other distance as directed by the S.O.

    The beacons shall be not less than 75

    mm square in plan and shall project at

    least 600 mm above the surrounding

    ground. Each beacon shall be clearly

    marked with its chainage and elevation

    above datum.

    The Contractor shall take all practicable

    steps to safeguard the beacons includingfencing and concreting-in where

    necessary in the opinion of the S.O. and

    shall immediately replace any damaged

    beacons. The Contractor shall give the

    S.O. not less than 24 hours notice of his

    intention to set out or give levels for

    any part of the Works in order that

    arrangements may be made for

    checking.

    1.9 DIMENSIONS AND LEVELS

    All temporary benchmarks, reference

    markers and levels as shown on the

    Drawings shall be checked on the Site

    by the Contractor at his own expense

    and be confirmed by the S.O.

    Before the Works or any part thereof are

    commenced, the Contractor shall verify

    the levels of the existing ground surface

    within areas where earthworks are to be

    performed and the locations and bed

    levels of water-courses. These maydiffer from the locations and levels

    shown on the Drawings owing to

    changes which could have taken place

    during the interval between the original

    survey and construction.

    The levels and dimensions taken by the

    Contractor jointly with the S.O. shall

    form the basis of measurement of the

    relevant work quantities.

    1.10 PROTECTION OF WORKS

    From the commencement of the Works

    to the date the Works are taken over by

    the Government, the Contractor shall

    take full responsibility for the care there

    of together with all temporary works

    and in case any damage, loss or injury

    shall happen to the Works or to any part

    thereof or to any temporary works from

    any cause whatsoever, he shall at hisown cost repair and make good the

    same so that at completion, the Works

    shall be in good order and condition and

    in conformity in every respect with the

    requirements of the Contract and the

    S.O.'s instructions. The Contractor shall

    also be liable for any damage to the

    Works occasioned by him in the course

    of any operations carried out during the

    Defects Liability Period.

    1.11 DESIGN OF TEMPORARYWORKS BY THE CONTRACTOR

    Unless otherwise provided in the

    Drawings, the Contractor shall submit to

    the S.O. for his approval, 2 copies of all

    working or shop drawings produced by

    him including all drawings made by his

    approved sub-contractors for all

    temporary works.

    FOR INTERNAL USE ONLY

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    15/270

    Page 14

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    Such submission shall be made at least

    two weeks before the temporary work is

    scheduled to commence.

    Notwithstanding the approval by the

    S.O., the Contractor is solely responsible

    for the adequacy and safety of his workand for any necessary modification or

    addition whenever found necessary by

    the S.O.

    1.12 CONTRACTOR'SSUPERINTENDENCE

    The Contractor shall provide all

    necessary superintendence during the

    execution of the Works and as long

    thereafter as the S.O. may consider

    necessary for the proper fulfillment of

    the Contractor's obligations under the

    Contract.

    A competent Site Agent, whose

    appointment shall be approved by the

    S.O., shall be employed by the

    Contractor for management on Site.

    The Site Agent shall have the authority

    to receive instructions from the S.O. and

    to act on behalf of the Contractor. TheSite Agent shall be stationed on Site for

    the whole duration of the Contract and

    shall not be replaced without the

    approval of the S.O.

    If the Site Agent needs to be absent from

    Site for more than three (3) consecutive

    days, he shall give prior notice to the

    S.O. who may require the Contractor to

    temporarily appoint another Site Agent.

    1.13 INSPECTION AND TESTS

    The S.O. or his representative may at

    any stage of the Works carry out

    inspection, measurement and tests on

    any part of the Works to ensure

    compliance with the requirements of this

    Specification and of the Drawings.

    The Contractor shall provide the

    necessary attendance whenever required

    by the S.O. or his representative.

    Notwithstanding any tests which may

    have been carried out off the Site, theS.O. shall be empowered to order

    further tests of any materials or goods to

    be made on the Site and to reject such

    materials or goods should they fail to

    pass such tests on Site.

    When required by the S.O., the

    Contractor shall submit a copy of the

    result of any quality control test carried

    out by the Contractor on his own during

    the progress of the Works.

    1.14 COVERING UP OF WORK

    Before any part of the Works is

    permanently covered up, the Contractor

    shall give due notice to the S.O. for the

    inspection and measurement of

    dimensions. The S.O. shall attend

    without unreasonable delay for the

    purpose of examination and

    measurement unless he considers it

    unnecessary and advises the Contractoraccordingly.

    1.15 OFFICE ACCOMMODATION FORS.O. AND HIS STAFF

    The Contractor shall provide and

    maintain a site office for the use of the

    S.O. and his supervisory staff, all in

    accordance with the relevant Drawings

    inclusive of all furniture and fittings as

    shown on the Drawings.

    The Contractor is permitted to provide a

    relocatable site office as an alternative to

    the JKR designed type shown on the

    Drawings.

    FOR INTERNAL USE ONLY

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    16/270

    Page 15

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    The quality of such a relocatable site

    office shall be of equivalent standard but

    not inferior to the JKR designed type

    and shall be equipped with similar

    furniture and fittings as indicated in the

    JKR designed site office.

    Where a relocatable site office is to be

    provided, the Contractor shall submit

    details of the relocatable site office

    together with his tender. Such details

    should include the name of the

    manufacturer, floor area and layout, list

    of furniture and fittings and brochures if

    available. The Contractor shall also

    indicate whether the proposed site office

    is new or otherwise.

    Unless otherwise shown on the

    Drawings, the site office is to be sited,

    constructed and positioned as approved

    by the S.O.

    The Contractor shall make proper

    arrangements for and pay all charges in

    connection with conservancy. The site

    office shall comply with local building

    by-laws. It shall be erected or provided

    by the Contractor within four (4) weeksfrom the date of possession of Site.

    On completion of the Works, the

    Contractor shall further maintain the site

    office till the end of the Defects Liability

    Period unless otherwise directed by the

    S.O. and thereafter remove from the Site

    the site office with all furniture and

    fittings which become the property of

    the Contractor.

    Where electricity and piped water are

    available from public utility authorities,

    the Contractor shall arrange for the site

    office to be connected to the electricity

    and water supplies.Otherwise, the

    Contractor shall supply the site office

    with electric power from generators and

    shall provide an adequate supply of

    water for washing and potable filtered

    water for drinking purposes.

    Sanitary facilities with disposal to

    septic tanks located not nearer than 5 m

    from the building shall be provided.

    The office shall be illuminated by

    fluorescent fittings giving a general levelof illumination of at least 2 lumens/

    sq.m. Additional lighting in the form of

    wall or deck lamps shall be provided

    where required by the S.O. Lighting to

    toilets and corridors may be by tungsten

    filament bulbs.

    Thermostatically controlled air-

    conditioners capable of maintaining a

    temperature below 23C in the office

    shall be provided.

    The Contractor shall arrange for the

    installation of a telephone with a

    separate connection to the telephone

    exchange for the exclusive use of the

    S.O. at all times. The telephone shall

    also be be fitted with 4 extensions unless

    not required by the S.O. The Contractor

    shall be responsible for the connection

    to such exchange and the payment of

    rental for the telephone services but the

    Government shall reimburse theContractor for the cost of making calls.

    Where a telephone exchange is not

    within practical distance, an automatic

    mobile telephone such as the ATUR

    (Automatic Telephone Using Radio)

    service shall be provided.

    The Contractor shall keep the offices

    accessible at all times and in every way

    habitable for working purposesthroughout the duration of the Contract.

    The Contractor shall also provide such

    labour and cleaning materials as are

    required to maintain the site office in a

    thoroughly clean and sanitary condition.

    FOR INTERNAL USE ONLY

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    17/270

    Page 16

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    1.16 VEHICLES FOR THE S.O.'SSTAFF

    The Contractor shall provide new

    vehicles as listed in the B.Q. and

    Appendix 1C for the sole use of the S.O.and his staff at all times. All necessary

    fuel, oil and lubricants, general

    maintenance, comprehensive insurances

    and roadtax shall be provided by the

    Contractor together with a licensed and

    competent driver for every vehicle.

    Replacement vehicles shall be provided

    when normal vehicles are not available

    such as during periods of servicing,

    maintenance or repair. The vehicles will

    revert to the Contractor at the

    completion of the Contract unless

    otherwise stated in the B.Q.

    1.17 CONTRACTOR'S OFFICE ANDACCOMODATION

    The Contractor shall provide and

    maintain a suitable office for himself

    and his staff in a position or positions to

    be approved by the S.O.

    In addition, the Contractor shall provideand maintain temporary accomodation

    and living facilities, stores, workshops,

    etc., including all necessary services for

    water supply, drainage and lighting for

    his staff. Before any work can

    commence the Contractor shall submit

    to the S.O. details of the proposed

    buildings and services and shall obtain

    the S.O.'s approval together with any

    necessary approval in writing from the

    relevant statutory authority.

    The Contractor shall be responsible for

    all fees and other charges or expenses

    incurred in connection with such office

    and housing and shall keep the whole

    area in a clean, tidy and well drained

    condition.

    When instructed by the S.O., the

    Contractor shall remove all such

    buildings and appurtenant works from

    the Site, clean up the area and restore it

    to its original condition.

    The Contractor shall provide adequate

    first aid facilities appropriate to the size

    and composition of his staff and labour

    force. The Contractor shall afford the

    S.O.'s site staff full use of the services

    and facilities as and when required.

    1.18 MATERIAL TESTINGLABORATORY AND STAFF

    The Contractor shall provide and

    maintain a laboratory at the Site

    throughout the duration of the Contract.

    Earthworks and pavement construction

    will not be permitted to commence until

    the laboratory and necessary equipment

    have been provided.

    The said laboratory shall be in

    accordance with the Drawings and shall

    be equipped as indicated in Appendix

    1D. It shall be maintained in a clean

    and tidy condition to the satisfaction ofthe S.O. The laboratory shall be

    adequately supplied with water and

    electricity.

    The laboratory shall be used exclusively

    by the S.O. and his staff. However the

    Contractor shall provide helpers to assist

    the S.O. as and when requested.

    All laboratory equipment shall become

    the property of the Contractor oncompletion of the Works.

    On completion of the Works, the

    building shall be removed from the Site

    and the Site left in a neat and tidy

    condition.

    FOR INTERNAL USE ONLY

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    18/270

    Page 17

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    1.19 PROVISION FOR SURVEYINSTRUMENTS AND CHAINMEN

    The Contractor shall provide for the sole

    use of the S.O. and his staff all such

    instruments, equipment and chainmen asthe S.O. may require to enable him to

    check the accuracy of the Contractor's

    setting out and any measurements taken.

    The chainmen shall have knowledge of

    Bahasa Malaysia or English and as far

    as possible the same men shall be

    provided throughout the Contract

    period.

    The instruments and equipment to be

    provided are as listed in Appendix 1E.

    The Contractor shall be responsible

    throughout the Contract period for all

    such instruments, equipment and

    chainmen and shall ensure that the

    instruments and equipment are at all

    times in good working condition and

    adjustment. All instruments and

    equipment shall remain the property of

    the Contractor on completion of the

    Works.

    1.20 MAINTENANCE OF EXISTINGROADS AND PROTECTIONOF TRAFFIC

    1.20.1 Maintenance of Existing Roads,

    Bridges, Culverts, etc.

    The Contractor shall maintain all

    sections of existing roads and all

    bridges, drains and culverts includedtherein within the Site to the

    conditions at the time of possession

    of Site for the full duration of the

    Contract. Such maintenance shall

    include routine activities such as

    grass cutting, clearing of drains,

    patching of potholes, etc.

    He shall also be responsible for

    maintaining the free flow of traffic on

    these sections of existing road.

    The Contractor shall arrange for the

    conveyance of materials and plants so asto cause minimum damage to existing

    roads and installations and minimum

    inconvenience to the public. He shall

    not deposit any earth, rubbish or

    materials upon any road, street,

    pavement or footway to cause hindrance

    or obstruction of vehicles or pedestrians.

    The Contractor shall be responsible for

    any damage caused by any work carried

    out by him or by construction traffic to

    any existing roads or installations from

    whatsoever cause arising thereof and

    shall repair, maintain and reinstate the

    same to their original condition to the

    satisfaction of the S.O. The Contractor

    shall also keep such roads clear of

    slurry, boulders and loose earth which

    may be dropped in the course of

    transportation.

    Upon failure on the part of the

    Contractor to fulfill his obligationsunder this Section, the S.O. may take

    whatever action and any means

    necessary to satisfy the requirements

    and all costs incurred by the S.O. shall

    be deducted from any monies due or to

    become due to the Contractor under this

    Contract.

    1.20.2 Temporary Diversions

    Temporary diversions shall beconstructed wherever the Site is

    intersected by existing roads, footpaths,

    cycle tracks, access to properties, etc.

    Such diversion ways shall be of a

    standard of construction at least

    equivalent to that of the original road,

    path, track or access.

    FOR INTERNAL USE ONLY

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    19/270

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    20/270

    Page 19

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    The electrical signal lights shall be

    automatic in operation, but the

    S.O. may, at any time, require them

    to be hand operated by a competent

    operator.

    The Contractor shall make suitable

    arrangements for emergency

    servicing of the electrically operated

    traffic signals to be available at all

    times. Manually operated "Stop/Go"

    signs shall only be used with the

    prior approval of the S.O.; and shall,

    if so approved, be of the size, colour

    and type as shown on the Drawings

    and complying with the requirements

    of the ARAHAN TEKNIK(JALAN)

    2C/85 (Manual on Traffic Control

    Devices for Temporary Signs and

    Work Zones Control), published by

    Cawangan Jalan, Ibu Pejabat JKR,

    Kuala Lumpur.

    At least fourteen (14) days notice in

    writing of any proposed single-way

    traffic system shall be given to the

    S.O. for his approval before such a

    system can be implemented.

    1.20.4 Temporary Traffic Signs

    The Contractor shall at all times take

    full and sufficient precautions to

    ensure the safety of all traffic

    through and around the Work Site

    and of traffic that is diverted owing

    to the Works.

    To this end the Contractor shall erect

    and maintain on the Site and atprescribed points on the approaches

    to the Site, all traffic signs, signals

    and warning lights necessary for the

    direction and control of traffic. The

    sizes of all such signs and the

    lettering and wording thereon shall

    be as shown on the Drawings and

    approved by the S.O. before erection.

    Construction and excavation shall be

    sign posted and, during periods of

    darkness, shall be lit to the approval

    of the S.O.

    Temporary traffic signals shallcomply with the requirements of the

    ARAHAN TEKNIK (JALAN)

    2C/85 published by Cawangan

    Jalan, Ibu Pejabat JKR, Kuala

    Lumpur and shall be reflectorised

    and kept clean and legible at all

    times.

    The Contractor shall position, cover

    or remove these signs as may be

    directed by the S.O.

    1.20.5 Temporary Works

    The Contractor shall provide,

    maintain and remove on completion

    of the Works all temporary works

    including diversion ways, tracks,

    staging, bridging, etc., and shall

    make them safe and suitable in every

    respect for carrying all plants and

    materials and for all purposes related

    to the Works.

    1.21 LOCATION, TEMPORARYPROTECTION ANDTEMPORARY DIVERSION OFPUBLIC UTILITYINSTALLATIONS AND OTHERSERVICES

    The Contractor shall be responsible for

    locating the positions of all public utility

    installations, including water mains,overhead and underground cables, pipes,

    sewers and drains and all service

    connections to buildings, and where

    necessary, shall adopt such methods of

    excavation as may be required by the

    appropriate authorities or owners to

    ensure that no damage is caused to

    them.

    FOR INTERNAL USE ONLY

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    21/270

    Page 20

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    The Contractor shall make good, at his

    own expense, any damage caused by him

    to the existing services to the approval of

    and in accordance with the instruction of

    the appropriate authority or owner

    concerned, and shall keep the Governmentindemnified at all times from all claims,

    costs and expenses which may arise on

    account of any damage (whether

    permanent, temporary or recurring) to the

    said services.

    All such installations which are

    encountered in the course of the Works

    shall be adequately supported, slung-up,

    strutted or otherwise protected from injury

    to the satisfaction of the respective

    authority.

    The temporary diversion or relocation of

    any service within or outside the Works to

    permit the construction of the Works shall

    be the responsibility of the Contractor.

    Where a service is required to be

    interrupted or relocated the Contractor

    shall inform and obtain the approval of the

    S.O. who shall notify the appropriate

    authority or owner of the required removal

    and/or relocation.

    Temporary diversion shall mean works

    involved in the diversion of services that

    will be reinstated to their original position

    and condition on completion of the works

    in the affected areas. In planning his work

    for the diversion or relocation of services,

    the Contractor shall make reasonable

    allowance for the time necessary to obtain

    the S.O.'s approval for the work and for the

    appropriate authorities or owners toauthorise the work, obtain the necessary

    materials and carry out the work.

    The Contractor shall not be entitled to any

    extension of time due to his failure to

    allow for a reasonble period of time

    necessary for obtaining approval and

    completing the work.

    1.22 WATER AND ELECTRICITYSUPPLY

    The Contractor shall provide at his own

    risk and cost all water, lighting and

    electric power where required for use inthe Works and shall pay all costs, fees

    and charges and comply with all safety

    regulations and statutes in connection

    therewith.

    The Contractor shall also provide and

    maintain temporary water storage

    together with any distribution piping

    which may be necessary.

    1.23 PROJECT SIGNBOARD

    The Contractor shall provide, erect and

    maintain signboards at locations to be

    decided by the S.O. and pay all charges

    in connection with this, including

    obtaining permission, licences and fees,

    etc. Each sign board shall comply with

    the design and specification as shown on

    the Drawings. On completion of the

    project, the Contractor shall dismantle

    and clear away the signboards asdirected by the S.O.

    1.24 PHOTOGRAPHIC RECORD OFWORKS

    The Contractor shall provide a camera

    of reasonable quality for the purpose of

    taking record photographs and slides of

    the Works as and when directed by the

    S.O. The Contractor shall bear the costs

    of providing the film, development offilm, printing two (2) copies of each

    exposure in 3R size and documenting

    the photographs in suitable albums.

    The negatives of the photographs shall

    be the property of the Government and

    no prints from these negatives may be

    supplied to any person or persons except

    with the approval of the S.O.

    FOR INTERNAL USE ONLY

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    22/270

    Page 21

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    A suitably typed caption shall be affixed

    to the reverse side of each photograph

    describing the subject and the time at

    which it was taken. One copy of each

    photograph shall be signed by the

    Contractor and the S.O.

    1.25 AS-BUILT DRAWINGS ANDMICROFILMING

    Drawings for recording as-built

    construction details of the Works shall

    be prepared by the Contractor and shall

    be certified by the S.O. or his

    representative. The originals, in good

    quality transparencies, and two (2)

    printed copies of all as-built drawings

    shall be supplied by the Contractor to

    the S.O. progressively as sections of the

    Works become completed. All drawings

    shall be completed within one month

    after the completion of the respective

    section.

    As-built drawings shall be A1 size (838

    mm x 584 mm) unless otherwise

    approved by the S.O.

    The Contractor shall also microfilm the

    as-built drawings using 35.0 mm film

    with the aperture card format as shown

    in Figure 1-1 and submit the same to the

    S.O.

    1.26 CLEARING UP OF SITE

    The Contractor shall make every effort

    to keep the Site in a reasonably cleanand tidy condition for the duration of the

    Works. He shall, in addition, from time

    to time on the completion of any area of

    the Works or where directed by the S.O.,

    remove rubbish, surplus materials, or

    any other construction debris from such

    areas as may be attributable to his work

    under this Contract and generally leave

    them in a satisfatory condition, to the

    approval of the S.O.

    On completion of the Works, the

    Contractor shall remove all rubbish,

    debris and surplus materials from the

    Site and leave the whole Site in a neat

    and tidy condition to the satisfaction of

    the S.O.

    1.27 OPPORTUNITIES FOR OTHERCONTRACTORS

    The Contractor shall, when required by

    the S.O., afford all reasonable

    opportunity to any other Contractors

    employed by the Government and their

    workmen and to the workmen of the

    Government and of any other duly

    constituted authorities who may be

    employed in the execution on or near

    the Site of any work not included in the

    Contract.

    FOR INTERNAL USE ONLY

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    23/270

    Page 22

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    FOR INTERNAL USE ONLY

    APPENDIX 1A

    GENERAL DESCRIPTION OF PROJECT

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    24/270

    Page 23

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    FOR INTERNAL USE ONLY

    APPENDIX 1B

    SCOPE OF WORKS

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    25/270

    Page 24

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    FOR INTERNAL USE ONLY

    APPENDIX 1C

    VEHICLES FOR S.O. AND HIS STAFF

    All vehicles shall be NEW and of the types listed below :-

    Type A - 2000 c.c. four-door, air-conditioned saloon car;

    Type B - 1600 c.c. five-door, air-conditioned estate car;

    Type C - 1500 c.c. four-door, air-conditioned Proton Saga;

    Type D - 2000 c.c. four-wheel-drive, air-conditioned Trooper or equivalent with hard top;

    Type E - 2250 c.c. four-wheel-drive, air-conditioned long-wheel- base Land Rover or

    equivalent with hard top.

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    26/270

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    27/270

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    28/270

    Page 27

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    FOR INTERNAL USE ONLY

    (b) Concrete Testing Equipment

    No.

    (1) 152 mm x 152 mm x 152 mm standard concrete test cube steel moulds

    as specified in B.S. 1881. 6

    (2) Slump cones with tamping rods as specified in B.S. 1881. 2

    (3) Compacting factor apparatus as specified in B.S. 1881. 1

    (4) Tank for curing of concrete specimens to accomodate 50 Nos. x 152 mm

    cubes in layers not more than 50 mm deep. 1

    (c) Flexible Pavement Testing Equipment

    (1) Metal tray, 0.6 m square or similar suitable for measuring spray rates of

    bituminous materials and spread rates of cover aggregate for surface dressing. 4

    (2) Metal thickness gauge (or set of slotted sleeves) as specified in M.S. 30 for

    determination of aggregate flakiness index. 1

    Additional items required for asphaltic concrete and/or bituminous Macadam :-

    (3) Balance of 2 kg capacity, accurate to 0.1 g suitable for weighing samples

    suspended in liquid. 1

    (4) Steel moulds for Marshall test specimens (100 mm diameter) with base,

    extension collar, extraction collar and extraction plate as specified in B.S. 598. 6

    (5) Extractor for removing Marshall test specimens from moulds without distortion

    or shock as specified in B.S. 598. 1

    (6) Compaction hammer and automatic compactor for Marshall test specimens as

    specified in B.S. 598. 1 of each

    (7) Compaction pedestal and mould holder for Marshall test as specifiedin B.S. 598. 1 of each

    (8) Thermostatically controlled hot plate. 1

    (9) Thermometers for use in laboratory and in asphaltic mixes for Marshall test as

    specified in B.S. 598. 2 of each

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    29/270

    Page 28

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    FOR INTERNAL USE ONLY

    No.

    (10) Rubber and heat resistant gloves. 2 pairs of each

    (11) Filter papers - 100 mm diameter. As needed

    (12) Containers for heating aggregates and bituminous materials. As needed

    (13) Pavement coring machine of the thin-walled diamond bit type for

    obtaining 100 mm diameter samples of bituminous surfacings. 1

    (14) 100 mm diameter thin-walled diamond bits for use with pavement

    coring machine. As needed

    (15) Tools for cutting and trimming pavement cores. As needed

    (15) Metal bottles of suitable capacity for bitumen extraction by direct

    determination as specified in B.S. 598. As needed

    (16) Machine to rotate the bottles about their longitudinal axes at a speed of

    between 10 rev/min to 30 rev/min as specified in B.S. 598. 1

    (18) Volumetric flasks of suitable capacity. As needed

    (19) Centrifuge capable of developing an acceleration of 25,000 m/sq.

    second as specified in B.S. 598. 1

    (20) Filtration apparatus for extraction of bitumen by direct determination asspecified in B.S. 598. 1

    (21) Recovery apparatus for extraction of bitumen by direct determination

    as specified in B.S. 598.

    (22) Pressure filter of appropriate size, air pump and funnel for extraction

    of bitumen by direct determination as specified in B.S. 598. 1 of each

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    30/270

    Page 29

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    FOR INTERNAL USE ONLY

    No.

    Further items required for asphaltic concrete :-

    (23) Wire basket of 6.5 mm or smaller mesh with wire hanger as specified inM.S. 30, for determination of specific gravity and water absorption

    of aggregates. 1

    (24) Airtight container of similar capacity as wire basket above. 1

    (25) Gas jar - 1.5 litre. 1

    (26) Pyconometer - 1 litre. 1

    (27) Warm air blower. 1

    (28) Mechanical mixer of 2 kg capacity, for preparation of asphaltic concrete mixtures. 1

    (29) Thermostatically controlled water bath for Marshall test specimens as

    specified in B.S. 598. 1

    (30) Steel Marshall testing head as specified in B.S. 598. 1

    (30) Compression testing machine with proving ring, capable of applying loads of

    up to at least 22 kN at a constant rate of strain of 50 mm + 3 mm per minute

    and recording the maximum load achieved as specified in B.S. 598. 1

    (31) Dial gauge and mounting assembly for measuring Marshall test flows of up to10 mm with accuracy of + 0.1 mm as specified in B.S. 598. 1

    Testing which is specifically required in the Contract and any test defined in quoted British

    Standard Specifications which are required to ensure compliance with the Contract but cannot be

    done in the Site testing laboratory shall be carried out at approved laboratories off the Site. These

    tests shall be carried out as directed by the S.O. The cost incurred by the Contractor shall be

    deemed to have been included in the tendered rates.

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    31/270

    Page 30

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    FOR INTERNAL USE ONLY

    APPENDIX 1E

    SURVEY EQUIPMENT

    The Contractor shall provide and maintain the following instruments and equipment for the

    purpose of measurements and setting out. These shall become the property of the Contractor at the

    end of the Contract :-

    1 No. Theodolite of direct read out accurate to 1 second.

    2 No. Automatic levels - Wild NA2 or Koni 007 or equivalent.

    2 No. Levelling staves - 5 m aluminium.

    1 No. 50 m x 5 mm steel measuring band divided throughout and numbered at 5 m intervals.

    Divided over first 30 m at 1 m intervals. Divided over first 5 m at 50 mm intervals.

    1 No. Repair set for the same.

    2 No. 30 m steel box tapes, white face.

    2 No. 30 m fibreglass box tapes.

    10 No. 2.5 m ranging rods.

    2 No. 1 m spirit level, steel or aluminium.

    2 No. Survey umbrellas.

    Templates, straightedges, canvas bags, pegs, hammers, parangs, etc.

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    32/270

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    33/270

    Page 32

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    FOR INTERNAL USE ONLY

    SECTION 2

    EARTHWORKS

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    34/270

    Page 33

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    FOR INTERNAL USE ONLY

    SECTION 2 - EARTHWORKS

    Page

    2.1 CLEARING, GRUBBING AND STRIPPING TOPSOIL S2-35

    2.1.1 Description S2-35

    2.1.1.1 Clearing S2-35

    2.1.1.2 Grubbing S2-35

    2.1.1.3 Stripping Topsoil S2-35

    2.1.2 Construction Methods S2-35

    2.1.2.1 Areas To Be Cleared S2-35

    2.1.2.2 Areas To Be Cleared, Grubbed and Stripped Of Topsoil S2-36

    2.1.2.3 Topsoil S2-36

    2.1.2.4 Timber S2-36

    2.1.2.5 Structures S2-37

    2.1.2.6 Disposal Of Material S2-37

    2.2 EARTHWORKS S2-38

    2.2.1 Definitions S2-38

    2.2.2 General Requirements S2-39

    2.2.3 Roadway Excavation S2-39

    2.2.3.1 Dimensional Tolerances S2-39

    2.2.3.2 Separation and Stockpiling of Suitable Material S2-40

    2.2.3.3 Removal of Excavated Material From Site S2-40

    2.2.3.4 Removal of Unsuitable Material S2-402.2.3.5 Replacement of Unsuitable Material Under Standing Water S2-40

    2.2.3.6 Widening Cuts S2-40

    2.2.3.7 Excavation of Rock S2-41

    2.2.3.8 Storage and Handling of Explosives S2-42

    2.2.3.9 Blasting S2-42

    2.2.3.10 Safety Measures S2-42

    2.2.3.11 Insecure Material S2-43

    2.2.4 Earth Embankment S2-43

    2.2.4.1 Material S2-43

    2.2.4.2 Borrow Pits S2-432.2.4.3 Placement of Fill Material S2-43

    2.2.4.4 Compaction S2-44

    2.2.5 Rock fill Embankment S2-45

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    35/270

    Page 34

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    FOR INTERNAL USE ONLY

    Page

    2.2.6 Embankment Over Soft Ground S2-462.2.6.1 Foundation Treatment S2-46

    2.2.6.2 Surcharge and Staged Construction S2-46

    2.2.6.3 Settlement Markers S2-46

    2.2.6.4 Settlement Records S2-47

    2.2.7 Subgrade S2-47

    2.2.8 Protective Vegetation for Erosion Control S2-48

    2.2.8.1 Topsoil S2-48

    2.2.8.2 Turfing S2-48

    2.2.8.3 Seeding S2-48

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    36/270

    Page 35

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    SECTION 2 - EARTHWORKS

    2.1 CLEARING, GRUBBING ANDSTRIPPING TOPSOIL

    2.1.1 Description

    This work shall consist of clearing,

    grubbing and stripping topsoil in the

    areas designated hereunder and/or

    shown on the Drawings and/or

    directed by the S.O., and of clearing

    only in other areas designated here

    under and/or shown on the Drawings

    and/or directed by the S.O., all as

    specified herein and as required by

    the S.O. The work shall also include

    the demolition and disposal of

    structures in said areas, except where

    otherwise provided for in the

    Contract, as specified herein and as

    required by the S.O.

    2.1.1.1 Clearing

    Clearing shall consist of the

    cutting and/or taking down,

    removal and disposal ofeverything above ground

    level, including objects

    overhanging the areas to be

    cleared such as tree branches,

    except such trees, vegetation,

    structures or parts of structures,

    and other things which are

    designated in the Contract to

    remain, or be removed by others,

    or which the S.O. directs are to

    be left undisturbed. The materialto be cleared shall include but not

    necessarily be limited to trees,

    stumps (parts above ground),

    logs, brush, undergrowth, long

    grasses, crops, loose vegetable

    matter and structures (except

    those structures whose removal

    or clearance is otherwise

    provided for in the Contract).

    Clearing shall also include the

    levelling of obsolete dikes,

    terraces, ditches, etc., unless

    otherwise directed by the S.O.

    2.1.1.2 Grubbing

    Grubbing shall consist of the

    removal and disposal of surface

    vegetation, the bases of stumps,

    roots, the underground parts of

    structures, and other obstructions

    to a depth of at least 0.50 metre

    below ground level, all to the

    satisfaction of the S.O.

    2.1.1.3 Stripping Topsoil

    Stripping topsoil shall consist of

    the removal of topsoil to an

    average depth of at least 100 mm

    below ground level, and its

    stockpiling for use in the Works,

    and/or its disposal, as directed by

    the S.O.

    2.1.2 Construction Methods

    2.1.2.1 Areas To Be Cleared

    The entire road reserve area shall

    be cleared as described above,

    unless otherwise shown on the

    Drawings and/or directed by the

    S.O.

    Clearing shall be carried out to

    the extents deemed necessary and

    approved or directed by the S.O.

    in areas outside the road reservewhere channel excavation or

    other work is required.

    In areas which are to be cleared

    only, and in which grubbing and

    stripping topsoil are not required,

    the methods of work shall be

    such as will not unduly damage

    the surface vegetation and

    topsoil, and care shall be taken

    FOR INTERNAL USE ONLY

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    37/270

    Page 36

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    not to disturb the topsoil and the

    root systems of grasses and other

    surface vegetation. No topsoil

    shall be removed from such

    areas, except as directed by the

    S.O., and any topsoil, grasses andother surface vegetation other

    wise removed or disturbed shall

    be replaced and made good at the

    Contractor's own expense, all to

    the satisfaction of the S.O.

    2.1.2.2 Areas To Be Cleared,Grubbed

    and Stripped Of Topsoil

    Except as otherwise shown on

    the Drawings and/or directed by

    the S.O., clearing, grubbing and

    stripping topsoil shall be carried

    out in all areas of roadway

    excavation and in all areas where

    embankment is to be constructed,

    except that grubbing and

    stripping topsoil shall not be

    carried out in those areas where :-

    i) embankment is to be

    constructed on earth

    designated as swamp or softground;

    ii) embankment is to be

    constructed to a height at the

    centre-line of 1.50 metres or

    more on ground with a

    cross-slope of not more than 1

    (vertical) to 30 (horizontal).

    Clearing, grubbing and stripping topsoil shall

    be carried out to the extents deemed necessaryand approved or directed by the S.O. in areas

    both inside and outside the road reserve where

    channel excavation or other work is required.

    Except where further excavation is required,

    holes and cavities in the ground surface after

    clearing, grubbing and stripping topsoil shall be

    filled with materials similar to the adjacent

    ground, and such fill shall be compacted to a

    dry density similar to that of the surrounding

    material, all to the satisfaction of the S.O.

    This work shall be considered

    incidental to the work of clearing,

    grubbing and stripping topsoil,

    and shall not be measured for

    payment.

    2.1.2.3 Topsoil

    Topsoil to be stockpiled for the

    Works shall be sufficiently fertile

    to promote and support the

    growth of vegetation, and shall be

    taken from such areas where

    clearing, grubbing and stripping

    topsoil is required as approved or

    directed by the S.O. Before

    stockpiling, topsoil shall be

    separated from objectionable

    materials, all to the satisfaction of

    the S.O. The Contractor shall

    arrange for stockpile sites either

    within or outside the road

    reserve, at his own expense, and

    all to the satisfaction of the S.O.

    Otherwise, topsoil removed

    during grubbing and stripping

    operations shall be separated

    from objectionable materials andspread within the road reserve or

    borrow areas, or otherwise

    disposed of, as approved or

    directed by the S.O.

    2.1.2.4 Timber

    The ownership of timber is

    vested in the Government.

    Saleable timber shall be trimmed

    and stacked in accordance withthe requirements of the

    appropriate Government agency,

    in accessible places within the

    road reserve as approved or

    directed by the S.O.

    The Contractor shall have the

    right to use unsaleable timber (or

    saleable timber when permission

    is granted in writing by the

    FOR INTERNAL USE ONLY

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    38/270

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    39/270

    Page 38

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    Incombustible material, including

    where appropriate the remains of

    burning, shall be disposed of in a

    safe and tidy manner at solid

    waste dumps outside the Site,

    unless otherwise approved ordirected by the S.O. The

    Contractor shall be solely

    responsible for making the

    necessary agreements, and paying

    expenses and claims arising from

    the use of such solid waste

    dumps whether on Government

    or private land.

    2.2 EARTHWORKS

    2.2.1 Definitions

    (a) Formation Level

    Formation level means the top

    surface of the subgrade.

    (b) Subgrade

    Subgrade means that part of the

    embankment or existing groundin cutting which is immediately

    below the subbase or lower

    subbase of the road pavement

    and shoulders.

    (c) Common Excavation

    Common excavation shall mean

    excavation in any materials

    which are not rock or artificial

    hard materials as defined inSub-Sections 2.2.1 (f) and (g).

    (d) Unsuitable Materials

    Unsuitable materials shall

    include :-

    i) running silt, peat, logs,

    stumps, perishable or toxic

    material, slurry or mud, or

    ii) any material

    - consisting of highly

    organic clay and silt;

    - which is clay having aliquid limit exceeding

    80% and/or a plasticity

    index exceeding 55%;

    - which is susceptible to

    spontaneous combustion;

    - which has a loss of weight

    greater than 2.5% on

    ignition;

    - containing large amounts

    of roots, grass and other

    vegetable matter.

    Materials that are soft or unstable

    merely because they are too wet

    or too dry for effective

    compaction are not to be

    classified as unsuitable, unless

    otherwise classified by the S.O.

    (e) Suitable Materials

    Suitable materials shall mean

    those materials other than the

    unsuitable materials defined in

    Sub-Section 2.2.1 (d) above.

    (f) Rock

    Rock shall mean material found

    in ledges or masses in its original

    position which would normallyhave to be loosened either by

    blasting or by pneumatic tools or,

    if excavated by hand, by wedges

    and sledge hammers. It shall not

    include material which can be

    loosened with a track-type tractor

    with mounted and drawn ripper

    of the following descriptions :-

    FOR INTERNAL USE ONLY

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    40/270

    Page 39

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    i) Tractor Unit : Equipment with a

    minimum weight of 20 tonnes

    and nett horse power rating of

    200 brake horse power or more.

    The tractor unit is to be in good

    condition and operated byexperienced personnel skilled in

    the use of ripping equipment;

    ii) Ripping Unit : The ripper to be

    attached to the tractor shall be the

    most efficient parallelogram type

    recommended by the tractor or

    ripper manufacturer. The ripper

    shall have a single shank in good

    working condition with

    sharpened cutting point.

    Boulders or detached pieces shall only be

    regarded as rock if they individually

    exceed 0.5 cubic metre.

    (g) Artificial Hard Material

    This shall mean any hard artificial

    material which would require the use

    of blasting or approved pneumatic

    tools for its removal but shall

    exclude individual masses less than0.5 cubic metre.

    2.2.2 General Requirements

    The work shall include the

    excavation of all types of material,

    backfilling, compaction, forming

    embankments and slopes, etc., as is

    necessary for the completion of the

    Works up to the formation levels, in

    accordance with the lines, grades,dimensions, shapes and typical

    cross- sections shown on the

    Drawings and to the approval of the

    S.O.

    The Contractor shall provide where

    necessary temporary water courses,

    ditches, drains, pumping or other means of

    maintaining the earthworks free from

    water. Such provision shall include

    carrying out the work of forming thecuttings and embankments in such a

    manner that their surfaces have at all times

    a sufficient gradient to enable them to shed

    water and prevent ponding.

    In pumping out excavations and in the

    lowering of water tables the Contractor

    shall pay due regard to the stability of all

    structures.

    Adequate means for trapping silt shall be

    provided on all temporary drainage

    systems. Similar arrangements shall be

    made for all earthworks including

    excavations whether for pile trenches,

    foundations or cuttings.

    Should the surface of completed areas be

    damaged by erosion or by any other cause

    the Contractor shall at his own cost make

    good such areas to the satisfaction of the

    S.O.

    The Contractor shall exercise care in

    preventing wastage of suitable material

    needed for embankment or fill

    construction.

    2.2.3 Roadway Excavation

    2.2.3.1 Dimensional Tolerances

    Slopes in cutting shall be

    trimmed mechanically to neatand even surfaces which shall

    have gradients not steeper than

    that shown on the Drawings.

    Widths of excavations shall not

    exceed the dimensions shown on

    the Drawings by more than 300

    mm, unless otherwise approved

    by the S.O.

    FOR INTERNAL USE ONLY

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    41/270

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    42/270

    Page 41

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    TABLE 2.1 - GRADING LIMITS OFMATERIALS FORREPLACEMENT OFUNSUITABLE MATERIAL

    Where the rock is of satisfactory

    quality, the Contractor may elect to

    crush and screen it to produce

    aggregates required for concrete,

    roadbase, subbase, or other purposes.

    Excavated rock needed for earthwork construction which the

    Contractor elects so to use for

    producing select materials shall be

    replaced at the Contractor's own

    expense by borrow of satisfactory

    quality approved by the S.O.

    Otherwise, excavated rock shall be

    used in the construction of

    embankment and fill, to the fullest

    practical extent, in either of the two

    following ways :-

    i) excavated rock shall be broken

    down to a maximum particle size

    of 400 mm and used as rock fill

    as described in Sub-Section 2.2.5;

    ii) excavated rock shall be broken

    down to a maximum particle size

    of 150 mm, blended with suitable

    earth fill material in a proportionnot exceeding 1 rock to 1 earth,

    and used as common fill.

    The Contractor may only waste

    excavated rock with the approval of the

    S.O. Excavated rock needed for

    earthwork construction which the

    Contractor elects to waste shall be

    replaced at the Contractor's own expense

    by borrow of satisfactory quality

    approved by the S.O.

    FOR INTERNAL USE ONLY

    B.S. Sieve Size % Passing ByWeight

    Crushed Rock orGravel

    63.0 mm37.5 mm20.0 mm10.0 mm

    10085 - 1000 - 200 - 5

    Sand

    10.0 mm5.0 mm1.18 mm300 um150 um

    10090 - 10045 - 8010 - 302 - 10

    2.2.3.7 Excavation of Rock

    Rock excavation shall be carried

    out by methods appropriate toSite requirements as approved by

    the S.O. Where explosives shall

    be used, the relevant security

    regulations dealing with

    purchase, transport, handling,

    storage and usage of explosives

    shall be complied with.

    All material from rock

    excavations shall be used as far

    as is practicable in the Works.

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    43/270

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    44/270

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    45/270

    Page 44

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    Where embankment is to be

    constructed on ground with a

    cross-slope flatter than 1

    (vertical) to 10 (horizontal) but

    steeper than 1 (vertical) to 30

    (horizontal), the foundationmaterial, except where this is

    rock, shall be scarified to a depth

    of 100 mm, blended with

    embankment fill material and

    compacted as described in Sub-

    Section 2.2.4.4.

    Where embankment is to be

    constructed against existing

    embankment or on ground with a

    cross-slope of 1 or more (vertical)

    to 10 (horizontal), the foundation

    shall be excavated in all materials

    (including hard rock) to form

    benches with horizontal and

    vertical faces from which con

    struction of the embankment shall

    proceed. The benches shall be

    contiguous beneath the full width

    of the embankment, and shall be

    of a suitable width to accomodate

    construction equipment such as

    motor-graders, trucks, rollers, etc.Scarifying of the horizontal and

    vertical faces of the benches shall

    not normally be required, and the

    material excavated in forming the

    benches may normally be used as

    fill in the embankment as

    approved by the S.O.

    2.2.4.4 Compaction

    (a) General

    All materials used in

    embankments and as fill

    elsewhere shall be compacted

    as soon as practicable after

    being placed and spread.

    Compaction shall be

    undertaken to the

    requirements of this Section

    by plant approved by the S.O.

    All compaction requirements

    shall be controlled by meansof field density measurement.

    For compaction of

    embankment slope, the

    Contractor may either extend

    each compacted layer beyond

    the design slope surface by at

    least 600 mm and then trim

    back to the required slope

    angle, or he may employ a

    tow type roller to compact the

    sloping surface.

    (b) Compaction Trials

    The B.S. 1377 Compaction

    Test (4.5 kg rammer method)

    shall be used in determining

    the moisture versus density

    relation of soil.

    The Contractor shall submit to

    the S.O. for his approval theproposed method of

    compaction for each main

    type of material to be used in

    the embankment. This shall

    include the type of

    compaction plant for each

    type of material and the

    number of passes in relation

    to the loose depth of material

    to achieve desired

    compaction. The maximumcompacted thickness for fill

    shall be limited to 300 mm

    unless otherwise approved by

    the S.O. The Contractor shall

    carry out field compaction

    trials, supplemented by any

    necessary laboratory

    investigations, as required by

    the S.O.

    FOR INTERNAL USE ONLY

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    46/270

    Page 45

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    This shall be done by using the

    procedures proposed by the

    Contractor for earthworks and

    shall satisfy the S.O. that all the

    specified requirements regarding

    compaction can be achieved.Compaction trials with the main

    types of material likely to be

    encountered shall be completed

    before the works with the

    corresponding materials will be

    allowed to commence. Each trial

    area shall be not smaller than

    8 m x 15 m.

    (c) Degree of Compaction

    The whole of the embankment

    below the top 300 mm of the

    subgrade shall be compacted to

    not less than 90% (for cohesive

    material) or 95% (for

    cohesionless material) of the

    maximum dry density determined

    in the B.S. 1377 Compaction Test

    (4.5 kg rammer method).

    (d) Field Density Testing

    Field density tests on each layer

    of compacted earth fill shall be

    carried out using the sand

    replacement method in

    accordance with B.S. 1377 or by

    using other means of testing of

    comparable accuracy approved

    by the S.O.

    (e) Moisture Control

    Each layer of earth fill shall be

    processed as necessary to bring

    its moisture content to a uniform

    level throughout the material,

    suitable for compaction. The

    optimum moisture content as

    determined by the B.S. 1377

    Compaction Test (4.5 kg rammer

    method) shall be used as a guide

    in determining the proper

    moisture content at which each

    soil type shall be compacted.

    Water shall be added, or the

    material aerated and dried to

    adjust the soil to the proper

    moisture content to obtain therequired density. A satisfactory

    method and sufficient equipment

    as approved by the S.O. shall be

    used for the furnishing and

    handling of water.

    If the natural water content of

    suitable materials is too high for

    the proper compaction to be

    carried out, the Contractor can

    either bring down the moisture

    content by aeration or drying or

    alternatively replace it with

    suitable materials of compactable

    moisture range at his own cost.

    2.2.5 Rock fill Embankment

    Rock used in rock fill

    embankments shall be of maximum

    particle size of 400 mm so that it can

    be deposited in horizontal layers,

    each not exceeding 500 mm incompacted depth and extending over

    the full width of the embankment

    except for any specified external

    cover to slopes or new formation

    level. The materials shall be spread

    and levelled by a crawler tractor

    weighing not less than 15 tonnes.

    Each layer shall consist of

    reasonably well graded rock and all

    large voids shall be filled with

    broken fragments before the nextlayer is placed. The top surface and

    side slopes of embankments so

    formed shall be thoroughly blinded

    with approved fine graded material

    to seal the surface.

    FOR INTERNAL USE ONLY

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    47/270

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    48/270

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    49/270

    Page 48

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    crushed rock or gravel, regulated

    and blinded.

    ii) Where rock outcrop occurs over

    part of the formation only:-

    The rock outcrop shall be cut

    down to a level not less than 300

    mm below the formation level.

    The surface shall then be brought

    up to level with suitable subgrade

    material.

    2.2.8 Protective Vegetation for Erosion

    Control

    2.2.8.1 Topsoil

    Topsoil stockpiled for the Works

    in accordance with Sub- Sections

    2.1.1.3 and 2.1.2.3 shall be spread

    and lightly compacted to an even

    thickness of 50 mm as directed

    by the S.O. in areas to be turfed

    and/or seeded, or used as the S.O.

    shall otherwise direct for tree

    planting and other purposes.

    2.2.8.2 Turfing

    Turfing shall be carried out as

    soon as practicable on all earth

    slopes and other areas as shown

    on the Drawings and/or where

    directed by the S.O. The type of

    turf shall be as indicated on the

    Drawings or other alternative

    type as approved by the S.O. and

    shall be free of lallang and

    essentially free of weeds.

    Turf shall be obtained in

    unbroken sods with a substantial

    amount of topsoil and shall be

    approximately 250 mm x 250

    mm in size and 100 mm thick,

    from an approved source, and

    shall be placed in position as

    soon as practicable after cutting.

    Turf sods shall be stacked and

    watered when they cannot be

    laid immediately after cutting.

    The surfaces to be turfed shall

    be trimmed and thoroughlywetted. The turf shall then be

    carefully laid to form a complete

    and uniform cover as shown on

    the Drawings. Turf laid on slopes

    steeper than 1 (vertical) and 3

    (horizontal) shall be pegged

    down with bamboo stakes

    approximately 250 mm in length.

    Approved fertiliser shall be

    applied after placing of turf at

    suitable times and at rates of

    application approved by the S.O.

    All turf shall be regularly

    watered and fertilised to the

    satisfaction of the S.O. until

    the vegetation is satisfactorily

    established. Any dead turf

    shall be replaced with new

    turf at the Contractor's own

    expense.

    2.2.8.3 Seeding

    Seeding or hydroseeding shall be

    carried out as soon as practicable

    on slopes and other areas as

    shown on the Drawings and/or

    directed by the S.O.

    The Contractor shall submit to

    the S.O. for his consideration and

    approval, at least four (4) weeksin advance of the proposed work,

    full details of his proposed

    method of seeding or

    hydroseeding. The information

    submitted shall include, but not

    necessarily be limited to, a full

    description of the following

    aspects of the work :-

    FOR INTERNAL USE ONLY

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    50/270

    Page 49

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    i) the preparation of the areas to be

    seeded or hydroseeded, including

    if appropriate the amount of top

    soil to be used and its method of

    application;

    ii) the details and results of

    investigations to determine which

    types of grass and legume are

    compatible with the soil in the

    areas to be seeded;

    iii) the types of grass and legume (if

    any) and strains of seed to be

    used, and the function, root and

    growth characteristics of each

    type;

    iv) the rates of application of the

    grass and legume seeds;

    v) the composition of fertiliser to be

    used at the time of seeding and its

    rate of application;

    vi) the composition of fertiliser to be

    used after seeding, the times of

    application after seeding, and the

    rates of application;

    vii) the type of mulch to be used and

    its method and rate of

    application;

    viii) the amounts of lime or other

    chemicals (if any) to be applied

    to improve the soil before,

    during and/or after seeding;

    ix) the type and amounts of bindingagent to be applied with the

    seeds, mulch, fertiliser, etc.,

    as appropriate.

    x) the proportions and methods of

    preparation of the seeding mix;

    xi) the equipment and methods to be

    used in preparing and placing the

    seeding mix and other materials;

    xii) the cultivation and after-care of

    the seeded areas, including rates

    and frequencies of watering,

    fertilising, grass cutting and

    general maintenance for at least 1

    year after seeding;

    xiii) the time after seeding required for

    establishing permanent, dense

    growth of grasses, which will

    require minimal maintenance;

    xiv) guarantees of the success of the

    seeding work.

    All grass shall be regularly watered until

    the vegetation is satisfactorily

    established to the satisfaction of the S.O.

    Any dead grass shall be replaced at the

    Contractor's own expense.

    FOR INTERNAL USE ONLY

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    51/270

    Page 50

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    FOR INTERNAL USE ONLY

    SECTION 3

    DRAINAGE WORKS

  • 8/3/2019 Standard Specification for Roadworks - JKR-SPJ-1988

    52/270

    Page 51

    Standard Specification For Road Works

    Cawangan Jalan, Ibu Pejabat JKR, K.L

    FOR INTERNAL USE ONLY

    SECTION 3 - DRAINAGE WORKS

    Page

    3.1 GENERAL S3-54

    3.2 EXCAVATION AND BACKFILLING FOR DRAINAGE WORKS S3-54

    3.2.1 Description S3-54

    3.2.2 Materials S3-54

    3.2.2.1 Excavation S3-54

    3.2.2.2 Granular Bedding Material S3-54

    3.2.2.3 Concrete Bedding S3-54

    3.2.2.4 Ordinary Backfill Material S3-54

    3.2.2.5 Granular Backfill Material S3-54

    3.2.2.6 Concrete Back