Upload
jonas-short
View
233
Download
2
Tags:
Embed Size (px)
Citation preview
A traffic accident between a pickup and an 8,200 gallon gasoline tanker left two fatalities and the
bridge beyond repair
Friday, JANUARY 21, 2011
• 3:30 PM accident occurred.• 6:30 PM start setting up MOT to allow traffic past the site
via exit and entrance ramps closing SR-3• 8:30 PM DOT was allowed access to inspect the structure. • 10:00 PM DOT determines that 2 out of 3 spans on each
bridge need replacement.• Contractors were called to attend a pre-bid conference at
noon on Saturday 1/22/2011 for the replacement of two spans and one pier on both bridges and all repair associated with accident.
• 10:30 PM start developing contract.
Saturday, January 22, 2011
• 7:00AM to 11:00 AM Scope of work and MOT plan are complete
• 12:00 PM pre- bid conference on the bridge site with Leware Construction, Johnson Brothers and Lane Construction.
• 2:00 PM to 10: 00 PM receive and answer contractors bid questions.
Sunday, January 24, 2011
• 8:00 AM DOT opened bids. Lane apparent low bidder at $2,191,000.00 and 25 days.
• 8:30 AM contact awarded to Lane Construction.• 25 Days to have bridge Open with three
additional weeks for cleanup.• $50,000 per day user cost penalty if traffic not
re-opened by the 25th day, February 16th.• Sunday PM Lane starts mobilizing.
Traffic Control
A detour was set up to send Beachline traffic across the closed SR-3. To increase capacity the ramps were widened with temporary pavement.
February 8 Day 17
Start deck pour 9:00 AM Eastbound complete 3:30 Westbound starting
Completion 6:30 PM, flying out the Bidwell
February 10 - 14 Day 19 - 23
• Project work continued on Day 19 through opening on February 14, Day 23 with bridge rails, deck grooving, milling and resurfacing of roadway approaches damaged by fuel spill and fire, and final striping of the bridge and roadway.