Upload
others
View
8
Download
0
Embed Size (px)
Citation preview
Spillways Project - Wagerup Hydrological and Ecological Review Alcoa of Australia
TE18077 Alcoa spillway Wagerup.1d March 2019 | Page 1
Assets | Engineering | Environment | Noise | Spatial | Waste
Spillways Project - Wagerup
Hydrological and Ecological Review
Prepared for Alcoa of Australia
March 2019
Project Number: TE18077
Spillways Project - Wagerup Hydrological and Ecological Review Alcoa of Australia
TE18077 Alcoa spillway Wagerup.1d March 2019 | Page i
DOCUMENT CONTROL
Version Description Date Authors Reviewer
0a Internal Review GBa/SW/GBo JM
1a Draft report for client 18/12/2018 GB AM
1b Final report 4/1/2019 GB GB
1c Minor edits 4/1/2019 GB DD
1d Minor edit 20/3/2019 GB
Approval for Release
Name Position File Reference
Dr Greg Barrett Senior Environmental Consultant TE18077 Alcoa spillway Wagerup.1d
Signature
Copyright of this document or any part of this document remains with Talis Consultants Pty Ltd and cannot be used,
transferred or reproduced in any manner or form without prior written consent from Talis Consultants Pty Ltd.
Spillways Project - Wagerup Hydrological and Ecological Review Alcoa of Australia
TE18077 Alcoa spillway Wagerup.1d March 2019 | Page ii
Executive Summary Alcoa’s Australian operations represent one of the world’s largest integrated bauxite mining, alumina
refining and aluminium smelting systems.
In Western Australia, Alcoa operates two bauxite mines (Huntly and Willowdale) and three refineries
(Kwinana, Pinjarra and Wagerup). As part of the refining process, each refinery has residue storage
facilities (RSAs) and water storage dams for fresh water and process contaminated water.
Alcoa has recently reviewed the management of its RSAs against regulatory guidelines, Australian
technical standards (ANCOLD) and international standards (ICOLD) for the design and management of
RSAs and dams. This review process has identified that best practice management of these dam
facilities should include the installation of a spillway so that, should overtopping occur under
exceptional circumstances, it occurs in a controlled manner and significantly reduces the risk of a
major loss of containment event through dam wall failure.
Alcoa has now completed the preliminary design engineering works on the spillways and are finalising
the detailed design. As part of the preliminary design engineering works on the spillways, Alcoa also
completed a hydrological assessment of the likelihood of a discharge occurring from each spillway at
Kwinana and Pinjarra and the likely downstream inundation zones that may result. An assessment to
determine the spillway location and dimensions at Wagerup has been conducted.
The objective of this assessment was to evaluate the potential hydrological and ecological impacts
associated with the fitting of a spillway at Wagerup.
The spillway assessment identified the optimal locations for the spillway and the likely rainfall events
and scenarios under which it would operate. Engagement of the spillway would only occur under
extreme rainfall conditions.
The approach to identifying the spillway location at Wagerup appears sound and is consistent with
ANCOLD guidelines. Should the spillway be engaged, the discharge would be directed to a perimeter
drain and then to surrounding farmland (held by Alcoa). The farmland contains some remnant
vegetation that is likely to support some conservation significant fauna from time to time.
The assessment does not consider runoff from outside of the catchment of the RSAs. Under the rainfall
conditions considered in developing the spillway design, very significant runoff could be expected
from the broader catchment area. We conclude that the installation of a spillway at Wagerup is
unlikely to lead to environmental impacts in its own right, and may reduce risk to the environment by
reducing the potential for an embankment wall failure.
Spillways Project - Wagerup Hydrological and Ecological Review Alcoa of Australia
TE18077 Alcoa spillway Wagerup.1d March 2019 | Page iii
Table of Contents 1 Introduction ......................................................................................................................... 1
1.1 Background ............................................................................................................................. 1
1.2 About this assessment ............................................................................................................ 1
2 General approach ................................................................................................................. 3
3 Review of spillway design report ........................................................................................... 4
4 Ecological characteristics of potential discharge areas ........................................................... 6
4.1 Wagerup.................................................................................................................................. 6
4.2 Threatened Ecological Communities ...................................................................................... 6
4.3 Rare and Priority flora ............................................................................................................. 6
4.4 Rare and Priority Fauna .......................................................................................................... 7
4.5 Other environmental features of significance ........................................................................ 7
4.6 Heritage values ....................................................................................................................... 7
5 Conclusions .......................................................................................................................... 9
6 References ......................................................................................................................... 10
Tables Table 5-1: Summary of spillway location and sizing study
Table 5-2: Key environmental features of discharge area
Spillways Project - Wagerup Hydrological and Ecological Review Alcoa of Australia
TE18077 Alcoa spillway Wagerup.1d March 2019 | Page iv
Figures Figure 1-1: Wagerup Residue Storage Area – layout and surrounds
Figure 3-1: Wagerup ROWS pond – proposed spillway location
Figure 4-1: Wagerup – environmental values of the area west of the ROWS
Spillways Project - Wagerup Hydrological and Ecological Review Alcoa of Australia
TE18077 Alcoa spillway Wagerup.1d March 2019 | Page 1
1 Introduction
1.1 Background
Alcoa’s Australian operations represent one of the world’s largest integrated bauxite mining, alumina
refining and aluminium smelting systems.
In Western Australia, Alcoa operates two bauxite mines (Huntly and Willowdale) and three refineries
(Kwinana, Pinjarra and Wagerup). As part of the refining process, each refinery has residue storage
facilities (RSAs) and water storage dams for fresh water and process contaminated water. The
refineries are licensed under Part V of the Western Australian Environmental Protection Act 1986 as
follows:
L5245/1967/14 (Kwinana);
L5271/1983/14 (Pinjarra); and
L6217/1983/15 (Wagerup).
Alcoa has recently reviewed its management of its RSAs against regulatory guidelines, Australian
technical standards (ANCOLD) and international standards (ICOLD) for the design and management of
RSAs and dams. The Australian National Committee on Large Dams (ANCOLD) issues various
guidelines which are applicable for water or tailings dams with the potential to cause loss of life or
significant environmental or physical damage through operation or failure. Although prepared for
dams which would normally be at least 10 to 15 m high, ANCOLD guidelines can also be used to assist
with decisions on smaller dams, particularly where a dam or series or dams creates the potential for
loss of life or significant damage. These guidelines include risk assessment and dam design modules.
This review process has identified that best practice management of these dam facilities should
include the installation of a spillway so that, should overtopping occur under exceptional
circumstances, it occurs in a controlled manner and significantly reduces the risk of a major loss of
containment event through embankment wall failure.
Alcoa has now completed the preliminary design engineering works on the spillways and are finalising
the detailed design. As part of the preliminary design engineering works on the spillways, Alcoa also
completed a hydrological assessment of the likelihood of a discharge occurring from each spillway at
Kwinana and Pinjarra and the likely downstream inundation zones that may result. An assessment to
determine the spillway location and dimensions at Wagerup has also been conducted.
1.2 About this assessment
The objective of this assessment was to evaluate the potential hydrological and ecological impacts
associated with the fitting of a spillway at the RSA at Wagerup (Figure 1-1). The assessment will
support a submission to the WA Department of Water and Environmental Regulation (DWER) in
relation to the licensing requirements under Part V of the EP Act.
Document Path: \\server\talis\SECTIONS\Environment\Projects\TE2018\TE18077 - Alcoa spillways ecological reviews\GIS\Maps\TE18077_1-1_Wagerup_Locality_RevA.mxd
Harvey RiverMain Drain
Samson SouthDiversion Drain
Yalup BrookDrain
South
Wes
tern H
wy
Willowdale Rd
Bristol Rd
Some
rs Rd
ROWS
ResidueStorage
Area
BullerNature
Reserve
390,000
390,000
392,000
392,000
394,000
394,000
396,000
396,000
398,000
398,000
6,356
,000
6,356
,000
6,358
,000
6,358
,000
6,360
,000
6,360
,000
6,362
,000
6,362
,000
LEGEND
© Talis Consultants Pty Ltd ("Talis") Copyright in the drawings, information and datarecorded in this document ("the information") is the property of Talis. This document andthe information are solely for the use of the authorised recipient andthis document may not be used, transferred or reproduced in whole or partfor any purpose other than that which it is supplied by Talis withoutwritten consent. Talis makes no representation, undertakes no duty andaccepts no responsibility to any third party who may use or rely upon thisdocument or the information.
Perth
Pinjarra
Wagerup
Kwinana
0 40 80 120 16020km
LOCALITY
LOCALITYWAGERUP RESIDUE
STORAGE DAMSSpillways Project
Alcoa Australia
0 300 600 900 1,200Metres
¤ Coordinate System: GDA 1994 MGA Zone 50Projection: Transverse Mercator, Datum: GDA 1994
A MackG BarrettReviewed:
Checked:Prepared: F Walker Date: 3/01/2019
Revision:
Scale @ A3:1:30,528
Project No: TE18077A
Data source: Roads - Main Roads WA, 2018. Imagery - Landgate, 2018
Figure
1-1
Major RiverDrainNature ReserveRemnant NativeVegetation
P: PO Box 454, Leederville WA 6903 | A: Level 1 660 Newcastle St, Leederville WA 6007 | T: 1300 251 070 | W: www.talisconsultants.com.au
Spillways Project - Wagerup Hydrological and Ecological Review Alcoa of Australia
TE18077 Alcoa spillway Wagerup.1d March 2019 | Page 3
2 General approach
The steps involved in undertaking this assessment were as follows:
A desktop review of spillway design work undertaken by Alcoa and its consultants for the
Wagerup operation, including requests for further information;
A brief site visit to view the expected spillway location and adjoining area;
A desktop assessment of the ecological values of the expected areas that would be inundated
should a discharge from the spillway occur; and
Synthesis of this information and formulation of some broad conclusions as to the risks posed.
Spillways Project - Wagerup Hydrological and Ecological Review Alcoa of Australia
TE18077 Alcoa spillway Wagerup.1d March 2019 | Page 4
3 Review of spillway design report
The following spillway design report was available:
Wagerup Alumina Refinery ROWS Pond Spillway (Advisian 2018).
This report was primarily aimed at determining the location and size of the proposed spillway. Unlike
spillway investigations undertaken for Kwinana and Pinjarra, a potential area of inundation was not
determined.
Storm events considered were 1 in 100 AEP (72 hours) through to Probable Maximum Precipitation
(PMP) (120 hours).
Three scenarios were considered:
Rainfall directly on the Runoff Water Storage (ROWS) pond only (Scenario 1);
Rainfall directly on the Runoff Water Storage (ROWS) pond plus runoff from the refinery
catchment (Scenario 2); and
Rainfall directly on the Runoff Water Storage (ROWS) pond plus runoff from the refinery
catchment plus water pumped from the ROCP2 and RSAs (Scenario 3).
The outcome of the report was a recommended spillway location and size for the ROWS pond. A
separate document (Alcoa 2016) notes that all ponds are designed to contain a 1 in 100 year AEP 72
hour event. A spillway would only be engaged toward the end of an extremely wet winter (a wet
season with a rainfall in excess of a 1 in 100 Annual Exceedance Probability).
The preferred spillway location is the south-western corner of the ROWS pond where the discharge
would be directed to a perimeter drain and then to surrounding farmland (held by Alcoa) (see Figure
3-1). Surface water across the general area west of the RSA is controlled by a network of drains (Figure
1-1), the nearest of which is the Yalup Brook Drain which connects with the Harvey River Main Drain
and ultimately to the Harvey River.
The recommendation for a spillway is supported. The general premise that installation of spillways at
each operation reduces the risk of embankment wall failure and consequently more serious
environmental outcomes compared with discharge from a spillway is sound.
One aspect that has not been addressed is the effect that an extreme rainfall event in the surrounding
catchment would have on any discharge occurring from Alcoa’s operations. It is likely that such an
event would result in significant adverse environmental impacts (flooding, erosion) in its own right
without any consideration of discharge from the RSAs.
The quality of any discharge over a spillway at Wagerup has not been considered. Assuming discharge
from the spillway at Wagerup would occur in conjunction with a very significant rainfall event, dilution
is likely to render water quality impacts such that they would be inconsequential relative to the event
itself.
Document Path: \\server\talis\SECTIONS\Environment\Projects\TE2018\TE18077 - Alcoa spillways ecological reviews\GIS\Maps\TE18077_1-2_Wagerup_InundationArea_RevA.mxd
ROWS
ResidueStorage Area
394,000
394,000
396,000
396,000
6,356
,000
6,356
,000
6,358
,000
6,358
,000
LEGEND
© Talis Consultants Pty Ltd ("Talis") Copyright in the drawings, information and datarecorded in this document ("the information") is the property of Talis. This document andthe information are solely for the use of the authorised rec ipient andthis document may not be used, t ransferred or reproduced in whole or partfor any purpose other than that which it is supplied by Talis withoutwritten consent. Talis makes no representat ion, undertakes no duty andaccepts no respons ibility to any third party who may use or rely upon thisdocument or the information.
Perth
Pinjarra
Wagerup
Kwinana
0 40 80 120 16020km
LOCALITY
INUNDATION AREAWAGERUP RESIDUE
STORAGE DAMSSpillways Project
Alcoa Australia
0 150 300 450 600Metres
¤ Coordinate System: GDA 1994 MGA Zone 50Projection: Transverse Mercator, Datum: GDA 1994
A MackG BarrettReviewed:
Checked:Prepared: F Walker Date: 14/12/2018
Revision:
Scale @ A3:1:15,000
Project No: TE18077A
Data source: Roads - Main Roads WA, 2018. Imagery - Landgate, 2018
Figure
3-1
Spillway
P: PO Box 454, Leederville WA 6903 | A: Level 1 660 Newcastle St, Leederville WA 6007 | T: 1300 251 070 | W: www.talisconsultants.com.au
View from proposed spillway location looking west
Spillways Project - Wagerup Hydrological and Ecological Review Alcoa of Australia
TE18077 Alcoa spillway Wagerup.1d March 2019 | Page 6
4 Ecological characteristics of potential discharge areas
The information in this section was compiled by searching the following databases:
Threatened and Priority Flora Database (TPFL) and WA Herbarium database (WAHerb)
(through DBCA);
Threatened Fauna Databases (DBCA);
Threatened Ecological Communities database (DBCA);
The Commonwealth Government’s Directory of Important Wetlands; and
Other relevant documentation.
Also considered were heritage values assessed by interrogating:
The Heritage Council’s Inherit database; and
The Aboriginal Heritage Inquiry System (AHIS) (Department of Planning, Lands and Heritage).
4.1 Wagerup
4.2 Threatened Ecological Communities
The following Priority Ecological Community (PEC) occurs in remnant vegetation within farmland west
of the RSA:
Banksia-dominated Woodlands of the Swan Coastal Plain IBRA Region (P3).
This PEC extends from Jurien Bay in the north to Dunsborough in the south and has been impacted by
land clearing and fragmentation. It commonly occurs north-west of the Wagerup RSA. It is listed as
Endangered under the Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act).
Other TECs occur in the area around the Wagerup operations but were not recorded on the database
in the area west of the RSA. Furthermore, the majority of trees occurring near the RSA have been
planted as wind breaks and generally occur along fence lines and roads (Alcoa 2012). These vegetated
areas will not have the conservation value of remnant vegetation.
Given the likelihood of any discharge, should it occur, would be restricted to farmland near the RSA
(bounded by the Samson South Diversion Drain to the north and the Yalup Brook Drain to the south),
the risk to vegetation communities of conservation significance appears low.
4.3 Rare and Priority flora
The database search did not identify any flora of conservation significance occurring in the area west
(between the Samson South Diversion Drain to the north and the Yalup Brook Drain to the south). The
search did record some species of conservation significance occurring in remnant vegetation east of
the refinery and in the Buller Nature Reserve north west of the RSA (Figure 4-1). Neither of these areas
would be affected by any discharge from the RSA.
Spillways Project - Wagerup Hydrological and Ecological Review Alcoa of Australia
TE18077 Alcoa spillway Wagerup.1d March 2019 | Page 7
4.4 Rare and Priority Fauna
The database search identified one fauna species of conservation significance occurring in the area
west of the RSA (between the Samson South Diversion Drain to the north and the Yalup Brook Drain
to the south) (Figure 4-1). There was a single record of the South-western Brush-tailed Phascogale, or
Wambenger (Phascogale tapoatafa subsp. wambenger) recorded in remnant vegetation near Somers
Road. This species is Specially Protected under the Biodiversity Conservation Act 2016 (BC Act).
While not recorded in the immediate area, other species that could utilise remnant vegetation include:
Forest Red-tailed Black Cockatoo (Calyptorhynchus banksii subsp. naso) (Vulnerable under BC
Act and EPBC Act);
Baudin's Cockatoo (Calyptorhynchus baudinii), (Endangered under the BC Act and EPBC Act);
and
Carnaby's Cockatoo (Calyptorhynchus latirostris), (Endangered under the BC Act and EPBC
Act).
It appears very unlikely any discharge from the spillway under extreme rainfall conditions would result
in direct impacts on any of these species.
4.5 Other environmental features of significance
The Buller Nature Reserve occurs to the north of the potential discharge area (Figure 1-1) but would
not be affected. There are no other known environmental features of significance.
4.6 Heritage values
The site lies within Native Title held land under the Gnaala Karla Booja People Indigenous Land-Use
Agreement (ILUA), issued on the 8 June 2015.
The AHIS records one Registered Aboriginal Site (ID 3232) - Wagerup 1 (artefacts/scatter) - as located
south of the RSA, on the southern side of the Yalup Brook diversion drain (see Figure 1-1). Alcoa have
advised that these materials were recovered from the site under an approval from the Registrar of
Aboriginal Sites in 1978. No other Aboriginal sites are known in the area immediate west of the
Wagerup RSA.
There are no known sites of importance to European heritage in the area.
Document Path: \\server\Talis\SECTIONS\Environment\Projects\TE2018\TE18077 - Alcoa spillways ecological reviews\GIS\Maps\TE18077_1-3_Wagerup_Environmental_RevA.mxd
South W
estern
Hwy
ROWS
ResidueStorage
Area
390,000
390,000
392,000
392,000
394,000
394,000
396,000
396,000
6,356
,000
6,356
,000
6,358
,000
6,358
,000
6,360
,000
6,360
,000
6,362
,000
6,362
,000
LEGEND
Perth
Pinjarra
Wagerup
Kwinana
0 40 80 120 16020km
LOCALITY
0 310 620 930 1,240Metres
¤ Coordinate System: GDA 1994 MGA Zone 50Projection: Transverse Mercator, Datum: GDA 1994
A MackG BarrettReviewed:
Checked:Prepared: F Walker Date: 14/12/2018
Revision:
Scale @ A3:1:30,000
Project No: TE18077A
Data source: Roads - Main Roads WA, 2018. Imagery - Landgate, 2018
Figure
4-1
SpillwayFauna
Calyptorhynchus banksiinasoCalyptorhynchus baudiniiCalyptorhynchus latirostrisGeotria australisHydromys chrysogasterIsoodon fusciventerNotamacropus irmaPhascogale tapoatafawambenger
FloraBoronia capitata subsp.gracilisCaladenia huegeliiConostylis pauciflorasubsp. paucifloraDrakaea elasticaSynaphea odocoileopsSynaphea stenolobaSynaphea sp. Serpentine(G.R. Brand 103)
P: PO Box 454, Leederville WA 6903 | A: Level 1 660 Newcastle St, Leederville WA 6007 | T: 1300 251 070 | W: www.talisconsultants.com.au
ENVIRONMENTALFEATURES
WAGERUP RESIDUESTORAGE AREASpillways Project
Alcoa Australia
Spillways Project - Wagerup Hydrological and Ecological Review Alcoa of Australia
TE18077 Alcoa spillway Wagerup.1d March 2019 | Page 9
5 Conclusions
Engagement of the spillway would only occur under extreme rainfall conditions (Table 5-1).
Table 5-1: Summary of spillway location and sizing study
Site Optimal spillway
location
Event required to engage
spillway Likely discharge area
Wagerup
Run Off Water
Storage (ROWS)
(south western
corner)
An extremely wet winter (a wet
season with a rainfall in excess of
a 1 in 100 Annual Exceedance
Probability).
Initial discharge to
perimeter drain, then to
surrounding farmland (held
by Alcoa).
Should the spillway be engaged and the discharge extends to the farmland, Table 5-2 outlines the key
environmental features of the area receiving the discharge.
Table 5-2: Key environmental features of discharge area
Location Likely discharge area Environmental features
Wagerup
Farmland west of the RSA,
including amenity tree plantings
and some remnant vegetation.
Some remnant vegetation, with potential for
discharge to enter drainage system - the Yalup
Brook Drain which connects with the Harvey
River Main Drain and ultimately to the Harvey
River.
Runoff from outside of the catchment of the RSA has not been considered. Under the rainfall
conditions considered in developing the spillway design, very significant runoff could be expected
from the broader catchment area. We conclude that the proposed installation of the spillway at
Wagerup is unlikely to lead to environmental impacts in its own right, and may reduce risk to the
environment by reducing the potential for an embankment failure.
Spillways Project - Wagerup Hydrological and Ecological Review Alcoa of Australia
TE18077 Alcoa spillway Wagerup.1d March 2019 | Page 10
6 References
Advisian (2018). Wagerup Alumina Refinery ROWS Pond Spillway. Hydrology and Spillway Sizing.
Report for Alcoa of Australia Ltd, 7 September 2018.
Alcoa (2012). Long Term Residue Management Strategy – Wagerup 2012 (PDF). Retrieved from
https://www.alcoa.com/australia/en/pdf/2012_wagerup_refinery_ltrms.pdf