SP Services' Implementation of a New Billing
System for Contestable Customers
Lawrence Lee
Director (Operations)
SP Services Ltd
Copyright © SP Services Ltd 2012
Confidential Information. Not to be reproduced without written permission from SP Services Ltd
Installation
Metering
Consolidated Billing
Payment Collection
Customer Services
Debt Management
1-Stop Service
Regulated
Business
Non-Regulated
Business
• Market Support Services
Licensee
• Supplier for NCC
• Retail Settlement /
Switching
• Billing and Collection
Agent
1-Stop Service
Scope of Business
Copyright © SP Services Ltd 2012
Confidential Information. Not to be reproduced without written permission from SP Services Ltd
Key Statistics
Send 1.3 million bills monthly
Read 3.2 million electricity, water and gas
meters bi-monthly
Receive 75,000 calls monthly
Copyright © SP Services Ltd 2012
Confidential Information. Not to be reproduced without written permission from SP Services Ltd
Key Statistics
Process $6billion in utility payments annually
Disconnect / Re-connect 14,500 accounts
monthly
Process 31,000 move-in / move-out requests
monthly
Copyright © SP Services Ltd 2012
Confidential Information. Not to be reproduced without written permission from SP Services Ltd
National Electricity Market
Copyright © SP Services Ltd 2012
Confidential Information. Not to be reproduced without written permission from SP Services Ltd
Background
Legacy MSSL IT System was implemented in Jan 2003
Retailers
MSSL
Contestable
Consumers
Wholesale Market Retail Market
Daily
Metering File
Price File
Generation
Companies
Copyright © SP Services Ltd 2012
Confidential Information. Not to be reproduced without written permission from SP Services Ltd
Rationale for Upgrade
Upgraded
MSSL IT System
MSSL IT System
1. In use for more than 8 years
2. Migrate to SAP platform
3. Drive new efficiencies
4. Support growing customer base
Copyright © SP Services Ltd 2012
Confidential Information. Not to be reproduced without written permission from SP Services Ltd
Project Objectives
Project Objectives Target
1. Implement MSSL on SAP Platform Successfully • On time and on budget
• Without impacting business operations
√
2. Improve Operational Efficiency • Integration between functions
• Improve, Streamline and Automate existing processes
√
3. Review & Identify Existing Processes for
Improvement and Automation √
4. Achieve Scalability • Provide a scalable platform to support growing number
of contestable customers
√
Copyright © SP Services Ltd 2012
Confidential Information. Not to be reproduced without written permission from SP Services Ltd
Project Governance
Project Leaders
Working Committee
Steering Committee
SP Services Board
Project Leaders
Project Management Office
Internal Audit
Risk Management
Copyright © SP Services Ltd 2012
Confidential Information. Not to be reproduced without written permission from SP Services Ltd
Project Implementation Plan
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
2010 2010 2011 2011 2012 Timeline
Blueprint Completed
Warranty
Go - Live and Documentation Accepted
Warranty Period
Completed
Key Milestone
Market Trial
Pre - Roll - Out
Parallel Run
UAT Accepted
Data Migration Accepted
Stress / Load Test & Technical Test Completed
Testing
SIT 1 SIT 2 SIT 3
Regression Test
System Integration Test (SIT) accepted
System Go - Live
Blueprint: 6 months
Major activities
• Conduct User Workshop • Dev. Change Management Approach • Dev. Conversion Approach • Dev. Technical Arch Approach • Dev. Business Process Design • Dev. Solution Paper • Dev. Functional Design
Realization: 6 months
Major activities • Dev. Functional Design • Dev. Report, Interface, Conversion, Enhancement, Form, Workflow • Conduct Unit Test • Configure System • Develop Training Material
Testing: 7 months Major activities • Execute System Integration Test • Execute User Acceptance Test • Execute regression Test on EBS • Conduct Mock Conversion • Conduct Stress / Load Test • Conduct High Availability Test • Conduct Disaster Recovery Test • Preparation for Parallel Run and
Market Trial
Pre - Roll - Out: 4 months Major activities
• Conduct Training • Conduct Dress Rehearsals • Conduct Parallel Run • Conduct Market Trial
Major activities
Blueprint
• Fix defect
Realization Realization Completed
Develop RICEFW
UAT 1
UAT 2
UAT 3
Copyright © SP Services Ltd 2012
Confidential Information. Not to be reproduced without written permission from SP Services Ltd
Project Risk Management
Lifecycle Project Risk Management adopted from early
planning stage to implementation phase
Early Planning Stage
1. Follow Large IT
Procurement procedure
2. Include Audit and Group
Risk Management in the
Steering Committee
3. Detailed scoping of
requirements
4. Focus on core modules to
minimise customisation
Tendering & Contract
Negotiation
1. Stringent vendor
selection process
2. Require vendor to
include risk management
approach in tender
document
3. Establish project risk
register
Implementation Stage
1. Monthly Steering
Committee Meeting
2. Fortnightly Working
Committee Meeting
3. Various stages of testing
requirements
4. Stringent Exit Criteria
5. Regular assessment of
project risks
6. Implementation of risk
mitigations
Copyright © SP Services Ltd 2012
Confidential Information. Not to be reproduced without written permission from SP Services Ltd
Project Risk Management
Quality
Assurance
SAP
Solution
Review
Integration Review
Deliverable Review
• Carried out quarterly by vendor’s independent
Senior Executives
• Review conducted at blueprint & parallel run
• Review of Blueprint Solution by SAP
• Review of integrated solution by Solution
Architect
• Review carried out internally on an on-going
basis within project team and Steering
Committee
Copyright © SP Services Ltd 2012
Confidential Information. Not to be reproduced without written permission from SP Services Ltd
Project Risk Management
System Integration Test UAT Pre-Rollout
5 Months 3 Months 2 Months
SIT
Cycle 1
SIT
Cycle 2
SIT
Cycle 3
Test functionalities within
specific functional areas:
• Finance
• Billing
• Metering Data Management
• Market Interactions
UAT
Cycle 1
UAT
Cycle 2
UAT
Cycle 3
Test functionalities within
specific areas &
integration testing based
on user-defined
scenarios
Parallel
Run
Market
Trial
DR 1
• Validate system
functionalities against
legacy
• Test connectivity with
retailers & EMC
• Prepare environment to
test technical data &
validate cutover plan to
ensure predictability of
project
DR 2
Copyright © SP Services Ltd 2012
Confidential Information. Not to be reproduced without written permission from SP Services Ltd
Project Roll Out
Copyright © SP Services Ltd 2012
Confidential Information. Not to be reproduced without written permission from SP Services Ltd
3 Golden Rules
No Hard Coding
Ensure SQL Statements are Well Written and Efficient
No Unauthorised Modification
ACTION: As part of the code review process, an automated tool that searches for instances of hard coding was run and potential issues highlighted. Any hard coding found was addressed by the development team.
ACTION: As part of the code review process, a senior member of the development team will review SQL statements relating to the 15 biggest tables. Issues such as loops within loops and inefficient select statements were reported to the developer and addressed.
ACTION: Modification of core functionalities require an access key from SAP. No developer has this key and any request to obtain it will go through the Steering Committee.
Copyright © SP Services Ltd 2012
Confidential Information. Not to be reproduced without written permission from SP Services Ltd
Technical Architecture Design
Key Solution Elements
1. Re-alignment to standard
functionality
2. Leverage on SAP’s Best Practices
3. Support future growth and
business evolution
4. Improve operational efficiency
Testing Requirements
1. Support multiple parallel streams
of testing
Conversion Requirements
1. Accuracy in converting historical
data
Batch Requirements
1. Support integrated batch
schedule for MSSL
Key Tech Arch Considerations
1. Minimise implementation risk
2. Uphold system performance
objectives
3. Optimise system reliability,
maintainability and
scalability
Technical
Architecture
Design
Copyright © SP Services Ltd 2012
Confidential Information. Not to be reproduced without written permission from SP Services Ltd
Test Methodology
Key Solution Elements
1. Re-alignment to standard
functionality
2. Leverage on SAP’s Best Practices
3. Support future growth and
business evolution
4. Improve operational efficiency
Lesson Learned
1. Early Involvement of users in
System Integration Test (SIT)
2. Multiple environments for testing
to avoid unnecessary impact to
the project schedule
3. Focus on critical business
scenarios first
Key Test Methodology
Considerations
1. System is up-to-date with the
latest enhancement pack
2. MSSL operations not
adversely affected
3. MSSL processes and objects
are thoroughly tested
4. Capitalise on lessons learned
from implementation of
existing non-contestable and
legacy MSSL systems
Test
Approach
Copyright © SP Services Ltd 2012
Confidential Information. Not to be reproduced without written permission from SP Services Ltd
Conversion & Cutover Strategy
Key Solution Elements
1. Re-alignment to standard
functionality
2. Leverage on SAP’s Best Practices
3. Support future growth and
business evolution
4. Improve operational efficiency
Lesson Learned
1. Proven mock conversions,
dress rehearsal and fall-back
approaches
2. Data reconciliation and
verification approaches and
expectation
3. Complexity in data extraction
from proprietary data sources
Conversion and Cutover
Strategy Considerations
1. Minimal impact to production
environment & Market
Participants
2. Integrity of MSSL data is not
compromised
3. Capitalise on lessons learned
from implementation of
existing non-contestable and
legacy MSSL systems
Conversion
Data Model
Data
Extraction
Approach
Verification
And
Reconciliation
Approach
Cutover
Approach
Copyright © SP Services Ltd 2012
Confidential Information. Not to be reproduced without written permission from SP Services Ltd
Conversion & Cutover Strategy
Data Conversion Approach 1. Accuracy and quality of conversion
2. Data integrity is not compromise
Data Extraction Approach Challenges:
1. Large data volume
2. Complex data formats
3. Data exist in different systems
4. Data extraction logic to handle exception scenarios
Verification and Reconciliation Approach Adopted from previous implementation experience
• Reconciliation checkpoints throughout conversion process
• Multiple reconciliation methodology:
i. Checksum
ii. Eyeballing
iii. Finance reconciliation
iv. Auto Reconciliation reports
File
Extract Transform CRM
R
C
1
Recon
Report
R
C
2
R
C
3
Load File (Transformed
data)
Recon
Report
R
C
4
MSSL
Extract Legacy Transform Load
CIA BRM
EBT DMS
Kinetiq
Copyright © SP Services Ltd 2012
Confidential Information. Not to be reproduced without written permission from SP Services Ltd
Stress Test
Objective
To ensure system can perform
within the set targets
Process
Integration CRM IS-U
Scope Test Set Up Results
Online Stress
Test
a. 26 key online transactions across
functions with processes integrated
between systems
b. Peak load at 168 virtual users with
additional 20 online active users
Online performance met
target with response time
< 1s
Batch Test
a. Generate 13,000 invoices
b. Daily main stream batch jobs
Batch performance met
production requirements
Copyright © SP Services Ltd 2012
Confidential Information. Not to be reproduced without written permission from SP Services Ltd
Retailers’ Participation
Activities Timeline Scope
Connectivity Testing Apr - Jul 11 Connectivity testing and sending of sample
messages (inbound and outbound)
UAT (Inc. Mini
Market Trial) Aug – Sept 11
Testing of one message of each type per
retailer (inbound and outbound)
Parallel Run Oct – Nov 11
Limited involvement from Retailers / EMC
submitting transactions that occurred in “real
life”
Dress Rehearsal DR1 Sept 11
DR2 Nov 11
Rehearse connectivity switch and testing as
part of simulated cutover
Market Trial Sept – Dec 11 Testing and verification of market messages
generated during the market trial period
Go-live 3 Jan 12 Final connectivity switch as part of
actual cutover
Copyright © SP Services Ltd 2012
Confidential Information. Not to be reproduced without written permission from SP Services Ltd
Cutover Readiness
Copyright © SP Services Ltd 2012
Confidential Information. Not to be reproduced without written permission from SP Services Ltd
Project Dashboard
Work Stream Schedule Scope Resources Issues /
Risks Remarks
1. Overall Programme Completed
2. Functional Team Completed
2.1 Business Process Design Completed
2.2 Solution Paper Completed
2.3 Functional Design Completed
3. Data Conversion Completed
4. Change Management Completed
5. Basis & Authorisation Completed
6. Development Completed
7. Mock Conversion Completed
G G G G
G G G G
G G G G
G G G G
G G G G
G G G G
G G G G
G G G G
G G G G
G G G G
Copyright © SP Services Ltd 2012
Confidential Information. Not to be reproduced without written permission from SP Services Ltd
Project Dashboard
Work Stream Schedule Scope Resources Issues /
Risks Remarks
8. Development of Training
Material Completed
9. System Integration Test Completed
10. User Acceptance Test Completed
11. Dress Rehearsal Completed
12. Parallel Run Completed
13. Market Trial Completed
14. User Training Completed
15. Go Live & Warranty Period In Progress
G G G G
G G G G
G G G G
G G G G
G G G G
G G G G
G G G G
G G G G
Copyright © SP Services Ltd 2012
Confidential Information. Not to be reproduced without written permission from SP Services Ltd
Key Risks & Mitigations
Key Risks Mitigation Status
Delay in Project
implementation
1. Regular assessment & reporting
• Fortnightly Working Committee Meeting
• Monthly Steering Committee Meeting
2. Strict control over customisation
Cost Overrun 1. Optimise re-use functionalities
2. Efficient resource allocation
3. Strict control over change requests
Failure to reconcile
data in old
and new system after
data
conversion
1. Conduct mock-conversion exercise
2. Eyeballing of data
3. Users performed detailed checking on
migrated data in UAT Cycle 1, 2 and 3
Poor quality of
deliverables &
assumptions not
validated
1. Various checkpoints and sign-off processes
2. Regular QA review by SAP
3. Close work relationships between users and
SI
4. Prior screening of SI for key personnel
G
G
G
G
Copyright © SP Services Ltd 2012
Confidential Information. Not to be reproduced without written permission from SP Services Ltd
Communications Plan
Communications Strategy 1. To engage the relevant stakeholders to facilitate a smooth cutover
2. To manage strategic communications with the public should there be
any complications
Non-Contestable Customers
• Cutover should be a non-event to non-contestable customers
• No publicity / media release for this segment
Market participants / Stakeholders
• A targeted approach to reach out to Retailers, EMC, EMA, SPPG,
contestable customers
• Communications through the respective service touch points
• Templates, FAQs and media drawer statement prepared in readiness on
possible scenarios / complications
Copyright © SP Services Ltd 2012
Confidential Information. Not to be reproduced without written permission from SP Services Ltd
Communications Plan
Audience Activity Key Objectives
SP Services Market
Participants
(Retailers)
• Market participant’s
briefing
• Communicate Project and key phase
objectives / high level approach
• Project timelines
• Extent of involvement and when
Transmission Licensee
(SP PowerGrid (SPPG))
• Transmission Licensee
briefing
• Communicate Project and key phase
objectives / high level approach
• Project timelines
• Extent of involvement and when
SP Services Partners
(3rd party suppliers - banks)
• 3rd party meetings • Communicate Project and key phase
objectives / high level approach
• Project timelines
• Extent of involvement and when
Market Operator
(EMC)
• Market operator
briefing
• Communicate Project and key phase
objectives / high level approach
• Key phase activity timeline
• Extent of involvement expected during
Testing phase (UAT)
Regulator
(EMA)
• Regulator briefing
• Communicate Project and key phase
objectives / high level approach
• Key phase activity timeline
• Cutover / Fallback / Contingency plans
Copyright © SP Services Ltd 2012
Confidential Information. Not to be reproduced without written permission from SP Services Ltd
Cutover
Copyright © SP Services Ltd 2012
Confidential Information. Not to be reproduced without written permission from SP Services Ltd
Cutover Timeline
December 2011 January 2012
We 21 Th 22 Fr 23 Sa 24 Su 25 Mo 26 Tu 27 We 28 Th 29 Fr 30 Sa 31 Su 1 Mo 2 Tu 3 We 4
Cutover Prep Pre-Load
Period MD
Pre-Load Period
Historical Data Cutover Period
Post
Cutover
Checkpoints
MSSL
SAP
MSSL
Legacy
0 1 2 3A 3B 3C 3D 3E 4 5 6 7
Conv.
Data
Prep
System
Prep.
Manual tracking of transactions that change master data
converted in Pre-Load Period Master Data
Load master
data and
recon
Load 4 years of meter readings and recon
Load trans
data and
recon
Connectivity
Switch and
test
Man
ual C
atc
h-u
p
Catc
h-u
p B
atc
h
Batc
h f
ile In
c.
Sett
lem
en
t fi
le
fro
m 2
3-2
6 D
ec Process
EBT
transaction
Update master data
Generation of Settlement and Usage files
Market Message Transactions
Hold MDA, Refund Request and SD Review
Prep.
extraction
environment
Extract master
data
Legacy System Freeze
Prepare cutover
extraction
Cutover
extraction
Business
Conversion
Technical
Copyright © SP Services Ltd 2012
Confidential Information. Not to be reproduced without written permission from SP Services Ltd
Fallback Action Plan
December 2011 January 2012
We 21 Th 22 Fr 23 Sa 24 Su 25 Mo 26 Tu 27 We 28 Th 29 Fr 30 Sa 31 Su 1 Mo 2 Tu 3 We 4
Cutover Prep Pre-Load
Period MD
Pre-Load Period
Historical Data Cutover Period
Post
Cutover
Checkpoints 0 1 2 3A 3B 3C 3D 3E 4 5 6 7
Trigger point to fallback to the legacy system, rollback activities:
1. Manual catch-up on frozen transactions such as MDA, refund
requests, open Lotus Notes workflow
Trigger point to fallback to the legacy system, rollback activities:
1. Manual catch-up on frozen transactions such as MDA, refund
requests, open Lotus Notes workflow
2. Connectivity switch back to retailers
3. Run catch up batch
4. Open access to legacy MSSL system
5. Restart normal batch
Trigger point to fallback to the legacy system, rollback activities:
1. Manual catch-up on frozen transactions such as MDA, refund requests, open
Lotus Notes workflow
2. Connectivity switch back to retailers
3. Run catch up batch
4. Open access to legacy MSSL system
5. Restart normal batch
6. Continue to process settlement file in DMS for 23 - 26 Dec
Legend
• Go-live Go / No-Go checkpoint
• Point-of-no return checkpoint
• Go-live date: 3rd Jan 2012
• Fallback target: Generate
Settlement & Usage file by 5pm
on 3rd Jan 2012
6
7
Copyright © SP Services Ltd 2012
Confidential Information. Not to be reproduced without written permission from SP Services Ltd
Settlement / Usage Files
3 January 2012
Hours 00 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23
MV90
MSSL
SAP
MSSL
Legacy
Collect Meter
Data
Run batch to
generate
Settlement &
Usage files
Check
against
DMS
Export Meter
Data & Comm.
Log to Stage
Verification
DMS: Run
batch to
generate
Settlement &
Usage files
CIA
sc
he
du
ler
run
Checkpoint 7:
Point of No
Return
Buffer
Settlement & Usage File
submission
Catch up batch
Payment, Returns, Dunning, CIA scheduler,
PV2 Stage, Masterfile
Catch up manual transactions:
refund requests, MDA, LN
workflow
Connectivity
Switch
Catch up market
messages
Legacy ready
to start the
regular batch
Copyright © SP Services Ltd 2012
Confidential Information. Not to be reproduced without written permission from SP Services Ltd
Post Go-Live
EDM processing 5 days of meter
readings
Onsite support during batch run
1 x EDM Func. Support
1 x Developer
1st Month End
Onsite support
during batch run
1 x FI Func.
Support
1 x Developer
Dunning Activated
Ops to confirm dunning
jobs are activated
1st Aggregated Bill
Onsite support during batch run
1 x BI Func. Support
1st Billing Month End Report
Onsite support during batch run
1 x BI Func. Support
1 x Developer
1st Settlement File & EBT
Messages
Onsite support of
1 x EDM Func. Support
1 x CS Func. Support
1 x Developer
1 x PI Developer
1st MSSL Bill
Onsite support from Jetform
Dec January February
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5
MSSL BP 20 25 01 05 10 15
Agg. BP 20 25 01 05 10 15
Generation of 5 days of settlement
files
Onsite support during batch run
1 x EDM Func. Support
1 x Developer 1
2
3
4
5
6
7
8
Copyright © SP Services Ltd 2012
Confidential Information. Not to be reproduced without written permission from SP Services Ltd
Post Go-Live
1. Post Go-live checkpoint meetings were held daily
2. Performance on key business activities were monitored daily i. Key reports generated were monitored and verified
ii. All inbound and outbound files were monitored
iii. All inbound and outbound messages were tracked
3. Daily settlement and usage files were held back for users’
verification before sending out
4. 100% bill checking for two full billing cycles
Level MSSL Customers Retailers
1 : General Bill Alignment with
Simple Calculation
100% Hardcopy Bills -
2 : Detailed Bill Checking with
Reference to System
100% Online Bills 100% Online Bills
Copyright © SP Services Ltd 2012
Confidential Information. Not to be reproduced without written permission from SP Services Ltd
Post Go-Live
4. Key dates identified that may impact settlement & usage
files - Interim process of holding settlement and usage files for users’
verification before sending out
5. 100% bill checking for key dates identified
Special Scenario Date Reading Date Settlement-Ready Date
Leap year 29 Feb 1 Mar 7 Mar
New Price 1 Apr 2 Apr 9 Apr
New TLF value 1 Apr 2 Apr 9 Apr
New SSAF 1 Apr 2 Apr 9 Apr
Copyright © SP Services Ltd 2012
Confidential Information. Not to be reproduced without written permission from SP Services Ltd
Key Success Factors
Change Management
User Involvement & Communication
Senior Management Commitment & Support
Timely Decision Making, Sign Off & Resolution
Joint Effort to Transfer Skills & Knowledge
Adhere to Deadlines
Leverage on Best Practices
Work as ONE Team