24
SoW – Integrated Waste Management Completed by: Andreas Shikesho Date: January/February 2019 Rio Tinto Company Representative/s: Ann-August Shikongo, Iganatius Shaduka, Andreas Shikesho Scope Title Integrated Waste Management Context Rössing as a firmly established company must have integrated waste management programme to direct different waste streams in terms of temporary storage and, eventually, final disposal. In the past waste management was not truly integrated. Whereas domestic waste was disposed of at the Landfill Site, now there is a possibility to take it offsite and eventually close down the Landfill Site. Whereas the luggerbin services have been carried out by different Service Providers, this scope seeks to combine all the services and have them delivered by a single Service Provider. And whereas in the past Rössing provided some equipment and machinery to Service Providers, this revised scope aims to request the Service Providers to provide their own. It also aims to tap into the Service Provider’s expertise in terms of current and best practice relating to HSE and waste management, i.e. the Service Provider must advise Rössing as to the latest waste management methods and strategies in order to better manage the various waste streams. Purpose The purpose of this scope is to guide in a rounded and integrated manner the various waste streams by managing their flow to temporary storage and final disposal destinations. The ultimate aim is to comply both with own waste management rules and regulations as well as with national legislation and international agreements and best practices in the waste management space. Category of work

SoW - Waste Management Contract-Revised.Feb2019-FINAL of Interest... · 2019. 3. 1. · SoW – Integrated Waste Management Completed by: Andreas Shikesho Date: January/February 2019

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: SoW - Waste Management Contract-Revised.Feb2019-FINAL of Interest... · 2019. 3. 1. · SoW – Integrated Waste Management Completed by: Andreas Shikesho Date: January/February 2019

SoW – Integrated Waste Management

Completed by: Andreas Shikesho

Date: January/February 2019

Rio Tinto Company Representative/s: Ann-August Shikongo, Iganatius Shaduka, Andreas Shikesho

Scope Title

Integrated Waste Management

Context

Rössing as a firmly established company must have integrated waste management programme to direct different waste streams in terms of temporary storage and, eventually, final disposal. In the past waste management was not truly integrated. Whereas domestic waste was disposed of at the Landfill Site, now there is a possibility to take it offsite and eventually close down the Landfill Site. Whereas the luggerbin services have been carried out by different Service Providers, this scope seeks to combine all the services and have them delivered by a single Service Provider. And whereas in the past Rössing provided some equipment and machinery to Service Providers, this revised scope aims to request the Service Providers to provide their own. It also aims to tap into the Service Provider’s expertise in terms of current and best practice relating to HSE and waste management, i.e. the Service Provider must advise Rössing as to the latest waste management methods and strategies in order to better manage the various waste streams.

Purpose

The purpose of this scope is to guide in a rounded and integrated manner the various waste streams by managing their flow to temporary storage and final disposal destinations. The ultimate aim is to comply both with own waste management rules and regulations as well as with national legislation and international agreements and best practices in the waste management space.

Category of work

Page 2: SoW - Waste Management Contract-Revised.Feb2019-FINAL of Interest... · 2019. 3. 1. · SoW – Integrated Waste Management Completed by: Andreas Shikesho Date: January/February 2019

Category of Contractor (circle):

1 2

3

Outcome (complete section A or B, depending on engagement type)

Section A - Cat 3 outcome engagement

Outcome

Legacy waste cleared. All waste segregated at source. All waste streams managed according to best practice.

Section B - Cat 3 time and materials engagement, or a Cat 1 Engagement

Task

The scope is structured into key tasks. The services to be delivered include the management and service

delivery aspects in order to fulfil a successful and efficient service to the Rössing operations. Moreover, it

integrates both waste removal and dust removal (Primary and Fine Crushing).

2.1 Management and planning services

The management and planning aspects will include the following high-level items:

• Overall management of all waste disposal functions at Rössing;

• Development of optimised

o waste management strategies and

o improvement plans;

• Coordination of transportation arrangements and liaison with third parties involved in waste

management;

• Development and setting a safety strategy for the work to be performed at Rössing (strategy to be

Page 3: SoW - Waste Management Contract-Revised.Feb2019-FINAL of Interest... · 2019. 3. 1. · SoW – Integrated Waste Management Completed by: Andreas Shikesho Date: January/February 2019

presented at commencement of contract);

• Development and review of all safe systems of work associated with the scope under this contract

(Service Provider to present results to the client (Rössing);

• Detailed reporting of waste stream volumes and weights

o Daily (e.g. trip sheets and compliance to schedule of previous day)

o Weekly (weekly summary report of previous week)

o monthly (month-end report) and

o annually (year-end report outlining challenges encountered and suggesting improvements)

2.2 Operational services

The operational service delivery aspects are detailed below in the various subtasks as listed.

2.2.1 Sorting, cutting, loading and removal of recyclable waste materials and scrap (see

Annexure 1 for Procedure JE50/WMP/001 and Annexure 2 for procedure JE50/WMP/002 for more

details)

The contractor shall purchase and remove identified scrap and other waste from the Rössing site once one

truck load (27 tons +) of such waste become available. The contractor may establish a scrap depot, off-site

for stockpiling and/or storage, to which scrap can be removed. Identified scrap and other waste are the

following:

• Scrap metal (aluminium, brass, copper, steel, lead, etc.)

• Paper

• Cardboard / Boxes

• Timber

• Scrap conveyor belting

• Metal containers

• Plastic containers

• Electric motors (0-75KW)

• Electric cables

• Industrial copper (ICW)

• Insulated aluminium cable (ICW)

• HDPE piping

Page 4: SoW - Waste Management Contract-Revised.Feb2019-FINAL of Interest... · 2019. 3. 1. · SoW – Integrated Waste Management Completed by: Andreas Shikesho Date: January/February 2019

• Rubber lined pipes

• Stainless steel

• Scrap batteries

• Mixed electrical (scrap switchboards, with switchgear)

• Steel wire armoured copper cables

• Plastics (PVC stripping)

2.2.1.1 General handling of scrap and waste

• For the duration of the contract, a suitable truck shall be used to load scrap material and transport it

offsite where applicable.

• The contractor will provide all equipment used, which will include the following:

i) a dedicated lugger bin truck for dust removal in the Reduction Section (PC & FC)

ii) a dedicated lugger bin truck for general waste (domestic, scrap, hazardous etc.)

iii) a dedicated lugger bin truck for legacy waste (not needed after the removal of this waste is

completed)

• All scrap shall be removed from Rössing site by road trucks unless it has been agreed in writing that

the scrap may be removed by rail truck. The Contractor is responsible for all transport arrangements,

logistics and legal compliance.

• Non-ferrous metals shall after sorting be stored in a secure area prior to despatch by truck.

• Vehicles utilised in removing scrap from site shall pass over Rössing’s weighbridge unladen and

laden. The difference between the two mass readings shall be the mass of scrap removed from site.

• Road haulers and trucks may only be laden with one category of scrap at a time.

• The certificate issued by the Rössing weighbridge facility shall be used in determining the weight of

each individual load by multiplying the mass reflected on the certificate by the rate (to be agreed on)

for the particular category of scrap.

• No materials may be removed from site before it has been cleared by Rössing for release (e.g.

signed removal permit).

• Without being asked, the Contractor must supply Rössing with correct safe disposal certificates from

the approved disposal site(s) at the end of every month.

• The Contractor shall keep records and a detailed register of the destination of all scrap removed from

site. Unprompted, the Contractor shall submit copies of such records to the Rössing representative

and be available to the relevant government department.

Page 5: SoW - Waste Management Contract-Revised.Feb2019-FINAL of Interest... · 2019. 3. 1. · SoW – Integrated Waste Management Completed by: Andreas Shikesho Date: January/February 2019

• The Contractor shall be expected to report any defects observed or found that can adversely affect

the intended operation of the equipment or plant in any way.

2.2.1.2 Waste and scrap collection

• The area of the Old Acid Plant (decommissioned, all parts removed and fenced off) will be the

designated area of responsibility of the appointed Contractor.

• This area shall accommodate the office and lunch room containers as well as machinery such as a

bailers etc. No unsightly waste will be permanently stored in the area.

• All sorting, cutting and loading activities for scrap that must leave the Mine site will still take place at

the Old Acid Plant Yard.

• The Contractor is required to clear the current Salvage Yard on Waste Dump 2 of all legacy waste

while operating on the Old Acid Plant area.

• Unless otherwise specified, the points below will be the waste collection points.

Waste Type Collection Point Waste Container

Scrap Metal To be delivered to

Salvage Yard by the

Contractor

Green lugger bin

Hazardous

hydrocarbon waste

Workshops and every

other area that generates

it

Brown lugger bin or other

container

Paper, cardboard,

boxes

Workshops and every

other area that generates

it

Paper cages and yellow

cages

Timber Stores Receiving areas

and some Workshops

Stored next to lugger bins

Scrap conveyor

belting

Rubber lining workshop

and conveyors

Stored in the open

Metal and plastic

drums (210L) and

Workshops and every

other area that generates

Stored in the open in

designated areas

Page 6: SoW - Waste Management Contract-Revised.Feb2019-FINAL of Interest... · 2019. 3. 1. · SoW – Integrated Waste Management Completed by: Andreas Shikesho Date: January/February 2019

Plastic containers (20

L & 25L)

it

• The Contractor will load and transport scrap metal from designated collection points to the Salvage

Yard.

• Under no circumstances may the Contractor remove waste from any other than designated areas

unless authorised in writing by the relevant Superintendent. In such cases the scrap for removal shall

be clearly marked and demarcated for removal.

• The Contractor’s planning shall be as such that the truck or any other vehicle meant for loading scrap

in the collection area shall do so during day light only and shall enter and exit the Mine premises on

the same day.

• Where waste is collected by the Contractor by means of road transport, it shall be the responsibility of

the Contractor to ensure that the necessary permit in terms of the Road Transportation Act (Road

Traffic and Transport Act 22 of 1999) is held by the Contractor or where applicable the Contractor’s

agents or distributors or where applicable by the road haulier employed for this purpose. The

Contractor shall in this case indemnify Rössing against any loss suffered (including confiscation of

the waste) as a result of non-compliance with the said Act.

• All scrap collected by the Contractor onto the road or rail vehicle, will be at the sole risk of the

Contractor.

2.2.1.3 Sorting of materials

• All scrap shall be cut and reduced to manageable sizes.

• Materials shall be sorted into separate sorting bays according to the categories under 2.2.1.

• Hazardous waste shall be sorted for disposal at the Rössing contaminated waste site at the Tailings

Storage Facility (TSF). TSF leadership to clearly identify and assign this site to the Mine for the

purpose of sorting, cutting and disposal to the Contaminated Yard. Station 6 is the site in discussion

unless TSF leadership specifies otherwise.

• Contaminated scrap shall be cut or flattened with the objective to eliminate all void spaces that could

create tailings subsidence after deposition in the tailings facility.

• Contaminated scrap as prepared according to the objectives stated above shall be transported to the

tailings facility and arranged in a defined way in the disposal areas. This relates to the location of

Page 7: SoW - Waste Management Contract-Revised.Feb2019-FINAL of Interest... · 2019. 3. 1. · SoW – Integrated Waste Management Completed by: Andreas Shikesho Date: January/February 2019

disposal, the extent of the area assigned and the direction the scrap has to be arranged in the

deposition area. Rössing will develop suitable procedures for this purpose.

2.2.1.4 Yard management

The Contractor shall be responsible for managing the complete Salvage Yard, including:

• Sorting of scrap and waste materials

• Cutting steel work to size and shape

• Loading of trucks

• General housekeeping duties

• Controlling of material

• Booking of road trucks

• Capturing and monitoring scrap that enters the Yard on a daily basis

• Ensuring the firefighting equipment is checked and tested monthly

• Any appropriate health, safety and security measures and precautions required.

2.2.1.5 Collection of hazardous materials and arranging for disposal at the Walvis Bay hazardous

waste (or alternative) site

The Contractor shall collect hazardous waste on site, arrange for disposal at the Walvis Bay hazardous

waste (or alternative) site and transport the waste to Walvis Bay (or alternative site). Hazardous waste

consists of

• Old oil, old grease, fluorescent tubes, used air and oil filters, etc.

2.2.1.5.1 The following will be managed and set in place when transporting hazardous chemical substances

for disposal by the transporter:

a) Method of transport that minimises potential for accidental releases through:

i) Conducting a route risk assessment,

ii) Evaluate and implement security, safety, training and emergency response

responsibilities,

Page 8: SoW - Waste Management Contract-Revised.Feb2019-FINAL of Interest... · 2019. 3. 1. · SoW – Integrated Waste Management Completed by: Andreas Shikesho Date: January/February 2019

iii) Route emergency contact numbers,

iv) Procedure and method of communication in emergencies;

b) Arrangements in place for external responders, medical facilities, communities and roles and

responsibilities and emergency response plan;

c) Contractual service level agreement explaining the client and contractor/ transporter

accountabilities;

d) Competency of drivers - trained (HAZMAT), qualified and appropriately licensed (public drivers

permit, etc.);

e) Suitability of transport equipment and packaging (e.g. hazardous substance compatibilities,

packaging, etc.);

f) Maintenance records of transport vehicles and trailers and verification of adequacy for safe

working loads;

g) Methods in place to prevent overloading;

h) Maintaining load integrity;

i) Appropriate legislative placards and signage to be used on transport vehicles;

j) Medical fitness of drivers and drug abuse prevention program;

k) Method of tracking transporters where appropriate or required;

l) Inventory and chain of custody documents/procedure (way-bills, hazardous waste site disposal

certificate, etc.);

m) MSDS documents and TREM-cards available where applicable;

n) Required personal protective equipment;

o) Required emergency spill kit(s) and first response/containment procedures;

p) Any other applicable requirements observed will be amended in the service level agreement

between the client and the contractor.

Rössing will review the above requirements to satisfy themselves that all appropriate measures have been

taken and implemented to safely manage the transportation of hazardous substances. The following

ordinance will be applied for transportation, handling and management of all Hazardous Substances:

Hazardous Substances Ordinance 1974.

2.2.2 Collection and disposal of non-recyclable waste (see Annexure 1 for Procedure

JE50/WMP/001, Procedure JK65/PRD/003, and Procedure JK65/PRD/007)

Most areas on site have lugger bins for their waste collection. Some areas share lugger bins, for example

Page 9: SoW - Waste Management Contract-Revised.Feb2019-FINAL of Interest... · 2019. 3. 1. · SoW – Integrated Waste Management Completed by: Andreas Shikesho Date: January/February 2019

office buildings. These lugger bins are colour-coded for the different types of waste to be disposed in them.

The disposal requirement of each type of waste is explained in detail in the procedures mentioned above.

The table below shows waste types and their disposal areas. Lugger bins are collected by the “garbage

truck”, emptied and returned to the area where they came from on a weekly basis. The activities include

weighing of waste and reporting of incorrect waste segregation and are scheduled for one specific day of

the week.

Colour of

lugger bin

Type of waste Disposal area Frequency

(minimum)

Yellow Domestic waste Swakopmund or

elsewhere

Weekly

Brown Hydrocarbon contaminated soil

and sludge

Sludge Farm Weekly

Oil filters

Contaminated waste site

[Tailings Storage Facility

(TSF)] Hydraulic hoses

Green Scrap steel Contractor Recycling

Yard

Weekly

White Processing – radioactively

contaminated waste

Contaminated waste site

[Tailings Storage Facility

(TSF)]

Weekly

Black Mining – hydrocarbon

contaminated waste

2.2.3 Management of waste oils (see Annexure 1 for procedure JE50/WMP/002)

Used hydrocarbons in the work areas are discarded into empty 210L drums. These hydrocarbons are

stored in the used oil temporary storage yard (radioactively uncontaminated hydrocarbons), and next to

rodmills in the processing area (radioactively contaminated hydrocarbons).

Page 10: SoW - Waste Management Contract-Revised.Feb2019-FINAL of Interest... · 2019. 3. 1. · SoW – Integrated Waste Management Completed by: Andreas Shikesho Date: January/February 2019

Drums are brought to these yards by mine personnel or prior arrangements can be agreed upon between

mine personnel and yard supervisor. The used oil temporary storage yard is opened for storage of drums

for 2 (two) days in a week.

The following is required for waste oil management:

• Ensure that no drums are accepted at the yard that are not clearly labelled with the area name and

content, cleaned, and sealed.

• Arrange with Procurement for the removal of used oil for recycling.

• Arrange with the Municipality of Walvis Bay hazardous waste (or alternative) site in advance when a

load of non-recyclable hazardous waste (including hydrocarbons, fluorescent tubes, etc.) can be

expected to ensure that there are encapsulation cells available.

• Arrange with Wesbank (or any suitable and applicable transport company) for the transport of the

non-recyclable hazardous waste to the Walvis Bay Municipality Hazardous waste site. After disposal

a waste manifest and disposal certificate clearly stating the volumes and tons disposed shall be

submitted to the Environmental Section. Wesbank Transport will bill Rössing directly under the

existing transport contract for the waste transport services rendered. Rössing will enter into a

transporting contract with any appropriate and qualifying transport company.

• Provide final quantities of total weight of loaded drums to the Environmental Section.

• Submit a copy of the certificates of disposal to the Environmental Section.

• Inspect and maintain the condition of the yard. Good housekeeping is of utmost importance.

2.2.4 Management of bioremediation facility (sludge farm) (see Annexure 1 for procedure

JE50/WMP/014, chapter 6)

This activity includes the removal and treatment of all oil sludge from workshop sumps and other oil/diesel

contaminated ground to be removed from site.

• The site supervisor is responsible for inspecting the area to ensure that the bioremediation facility

(sludge farm) is operated according to the procedure and operating conditions are maintained as

Page 11: SoW - Waste Management Contract-Revised.Feb2019-FINAL of Interest... · 2019. 3. 1. · SoW – Integrated Waste Management Completed by: Andreas Shikesho Date: January/February 2019

specified.

• The site supervisor ensures that oil sludge is removed on a scheduled basis and that the necessary

equipment is readily available.

• The site supervisor also notifies the Tailings Operations Foreman before the delivery of contaminated

sludge/soil to the sludge farm.

• Delivery and mixing of sludge - The delivery procedure depends on the water content of the oil

sludge. Generally wet sludge pumped from oil sumps is delivered in a special vehicle and discharged

from a ramp at the sludge farm. The sludge is left to dry until most of the water has evaporated. The

operator then removes any foreign material. The material collected from the sludge is taken to the

contaminated waste site on the Tailings Dam. The sludge is spread out in a layer of about 200mm

and fertiliser/ Bio remediation chemicals is applied. The sludge layer is mixed with the underlying soil

to achieve a total thickness of the treatment layer of 300mm.

• Dry contaminated soil or sludge is transported in open trucks and dumped directly onto the treatment

area. Spreading, mixing and fertilising/adding bioremediation chemicals are carried out as described

above.

• Moisture addition - While micro-organisms can tolerate a wide range of soil moisture, they are most

active at higher moisture contents. The soil moisture should be adjusted at process commissioning

and then controlled within the target range of 70-80% of field capacity (field capacity is the amount of

water a soil can hold). The sludge should not be allowed to dry out at any time. At low soil moisture

the micro-organisms are inhibited or even destroyed. Higher moisture contents exceeding 80% of

field capacity should also be avoided as soil pores filled with water keep out oxygen.

• Nutrient addition - The soil at the sludge farm is nutrient deficient such as nitrogen (N) and

phosphorus (P). The addition of hydrocarbons increases the imbalance between carbon (C), N and P.

Under most conditions a C:N ratio of 10-30:1 is recommended, and an N:P ratio of 5-10:1. The N and

P demand is calculated from the hydrocarbon content of the sludge. Agricultural water-soluble or

slow-release fertilisers such as Urea or MAP (Mono - Ammonium Phosphate) can be applied. The

initial sampling results showed that the current type of sludge needs 50 kg of Urea every two months.

• Soil mixing and aeration - The soil must be mixed regularly for aeration, as most micro-organisms

thriving on hydrocarbons require oxygen. Mixing is achieved either by hand or with a rotary cultivator.

The whole treatment layer should be mixed, but not compacted. The soil should not be mixed

immediately after irrigation or rainfall. The frequency has to be determined during operation. An initial

weekly frequency is recommended and should be reviewed after 6-8 weeks.

Page 12: SoW - Waste Management Contract-Revised.Feb2019-FINAL of Interest... · 2019. 3. 1. · SoW – Integrated Waste Management Completed by: Andreas Shikesho Date: January/February 2019

• Soil pH - The pH of the contaminated soil has to be determined after the material has been delivered

to the bioremediation facility (sludge farm). It should be in the near neutral range of 6-8. If it is lower

or higher, lime or sulphur can be added to adjust the pH. The pH is determined by putting a small

amount of soil into a sample container and mixing it with tap water. The pH of the solution is

measured with a portable calibrated pH meter.

2.2.5 Operation of hydraulic press for both oil and air filters (see Annexure 1 for Hydraulic Press

Operating Procedure)

The Contractor, shall provide their own hydraulic press or come up with an alternative method of flattening

or pressing the oil and air filters to prepare these for disposal at the TSF.

This activity covers all oil filters for vehicles, gearboxes, transmission, hydraulic systems, etc. Whenever

maintenance is carried out on any vehicle/equipment at the maintenance workshop or in the field, the

oil/diesel filters need to be changed. The oil/diesel filters should be drained (filters taken out in the field

should be taken to the workshop) in an oil drip tray for at least 24 hours. After this draining period, the filter

is disposed of into the brown lugger bin provided for this purpose.

Activities include

• Collection of brown lugger bin from the area

• Putting all filters through the available hydraulic press (18 ton, double acting hydraulic press) to

reduce size.

• Once pressed, obtaining radiation clearance in order to take filters off-site for recycling.

• If radiation reading is too high, clearance will be rejected and filters should be disposed of at the

contaminated waste yard on the Tailings Storage Facility.

2.2.6 Operation of road sweeper and honey sucker

• The Contractor will provide own road sweeper and put it on a schedule to operate during weekdays.

The sweeping schedule is shown below. Operation includes the disposal of swept dust at the

Page 13: SoW - Waste Management Contract-Revised.Feb2019-FINAL of Interest... · 2019. 3. 1. · SoW – Integrated Waste Management Completed by: Andreas Shikesho Date: January/February 2019

contaminated waste site on the tailings storage facility and arranging for all daily and scheduled

maintenance activities.

Monday Radioactively contaminated areas at Processing and Mining

Tuesday Fine crushing and Occupational health section and contractor yards

Wednesday Engineering workshops and Stores

Thursday CMC and other Processing areas

Friday Mine maintenance, Mining engineering and Transport centre

• The “honey sucker”, to be supplied by the Service Provider, will be used to empty wash down sumps

in the workshop areas. This machine will be operated on an ad hoc or on demand basis for four hours

per week. As part of the operation the machine needs to be emptied at the oil separation plant. This

piece of equipment, like any other equipment owned by the Service Provide, must be subjected to

regular maintenance as per C3 Standard.

2.2.7 Ad hoc waste management tasks

Description of ad hoc waste:

During times of non-routine maintenance work large amounts of waste is generated. Ad hoc waste may

include tanks, pipes or any other bulky material that do not fit in lugger bins. The Contractor is responsible

for planning and coordinating, with co-operation of the company representative, regarding the handling and

disposal of such waste. The Planning Section of the Maintenance Department will involve the Waste

Management Contractor during the planning and execution of any non-routine maintenance work where

large amounts of waste will be likely generated. This may include activities during

o project related work (Projects)

o weekly shutdowns (module days)

o and breakdowns

Page 14: SoW - Waste Management Contract-Revised.Feb2019-FINAL of Interest... · 2019. 3. 1. · SoW – Integrated Waste Management Completed by: Andreas Shikesho Date: January/February 2019

Quantity

Identified scrap and other waste are the following:

• Scrap metal (aluminium, brass, copper, steel, lead, etc.)

• Paper

• Cardboard / Boxes

• Timber

• Scrap conveyor belting

• Metal containers

• Plastic containers

• Electric motors (0-75KW)

• Electric cables

• Industrial copper (ICW)

• Insulated aluminium cable (ICW)

• HDPE piping

• Rubber lined pipes

• Stainless steel

• Scrap batteries

• Mixed electrical (scrap switchboards, with switchgear)

• Steel wire armoured copper cables

• Plastics (PVC stripping)

The table below shows waste types and their disposal areas. Lugger bins are collected by the “garbage

truck”, emptied and returned to the area where they came from on a weekly basis. The activities include

weighing of waste and reporting of incorrect waste segregation and are scheduled for one specific day of

the week.

Colour of

lugger bin

Type of waste Disposal area Frequency

(minimum)

Yellow Domestic waste Swakopmund or Weekly

Page 15: SoW - Waste Management Contract-Revised.Feb2019-FINAL of Interest... · 2019. 3. 1. · SoW – Integrated Waste Management Completed by: Andreas Shikesho Date: January/February 2019

elsewhere

Brown Hydrocarbon contaminated soil

and sludge

Sludge Farm Weekly

Oil filters

Contaminated waste site

[Tailings Storage Facility

(TSF)] Hydraulic hoses

Green Scrap steel Contractor Recycling Yard Weekly

White Processing – radioactively

contaminated waste

Contaminated waste site

[Tailings Storage Facility

(TSF)]

Weekly

Black Mining – hydrocarbon

contaminated waste

Quality

Testing and Quality Management

A quality assurance and quality control management program must be provided for by the Contractor and

approved by the Engineer and Employer on establishment prior to kick off.

It will be the full responsibility of the Contractor to undertake appropriate quality control and quality

assurance measures on site. The Engineer shall audit the Contractor’s QA system on a regular basis to

ensure that adequate independent checks and test are being carried out and to ensure that the contractor’s

own controls are sufficient to identify any possible quality problems which could cause a delay on the

programme.

The contractor will ensure that, at a minimum, quarterly scheduled HSE audits are conducted internally and

Page 16: SoW - Waste Management Contract-Revised.Feb2019-FINAL of Interest... · 2019. 3. 1. · SoW – Integrated Waste Management Completed by: Andreas Shikesho Date: January/February 2019

where required reviewed and confirmed by a third party auditor. All audit reports must be submitted to the

Engineer. It is up to the discretion of the Engineer to call for an audit at any appropriate time, outside of the

normal audit schedule.

Reporting

In order to carry out an optimised waste management function and to conform to internal standards, it is

required that comprehensive measuring and reporting of all waste streams are carried out. The contractor is

required to report the following on a monthly and annual basis.

• Waste source; • Waste type handled;

• Volume and weight of waste handled;

• Weight of recyclable waste taken off site; • Point of disposal;

• Equipment hours;

• Consumables used; • Maintenance carried out;

• Any other statistics or client specific requests that will be required from time to time. The Designated Rössing representative (DL) will capture this information in the Rössing SAP system.

Also refer to the KPI section

Resources (contractor)

Page 17: SoW - Waste Management Contract-Revised.Feb2019-FINAL of Interest... · 2019. 3. 1. · SoW – Integrated Waste Management Completed by: Andreas Shikesho Date: January/February 2019

Equipment & machinery

1) 3x luggerbin trucks

- 1x for Primary Crushing & Fine Crushing (dust collection)

- 1x for waste removal

- 1x for legacy waste

2) 1x garbage truck

3) 1x honey sucker

4) 1x road sweeper

5) 1x baler 6) 1x TLB

7) 1x hydraulic press for oil and air filters

8) 1x drum crusher

9) 1x wood chipper

Vehicles

1) 2x minibus

2) 1x bakkie/sedan

People (29 heads)

1) 1x Site Manager – with some tertiary qualification in waste management

2) 1x Planner/Technical Advisor – with some tertiary qualification in waste management

3) 2x Office Administrator/Gate Controller

4) 1x Gate Controller

5) 5x Driver/Operator

6) 4x Cutters

7) 1x SHE Representative

8) 1x SHE Assistant

9) 13x General Worker

Page 18: SoW - Waste Management Contract-Revised.Feb2019-FINAL of Interest... · 2019. 3. 1. · SoW – Integrated Waste Management Completed by: Andreas Shikesho Date: January/February 2019

Measurement/Success criteria

Key Performance Indicators (KPIs) – only operational (see embedded spreadsheet for all KPIs) Performanc

e Element

What’s

Measured

Category Waste Stream Annual Target

(tonnes)

Monthly Target

(tonnes)

Rating/Score Reference

Operational

Services

Performance on

set targets for a

year (period to

be determined)

Recyclable

waste material

and scrap

management

Scrap metal 600 50 100 % or equivalent to tonnes

generated

Schedule D

Paper & cardboard 50 4 100 % or equivalent to tonnes

generated

Timber (pellets etc.) 47 4 100 % or equivalent to tonnes

generated

Scrap conveyor belting 329 27 100 % or equivalent to tonnes

generated

Garden & building Rubbles 250 21 100 % or equivalent to tonnes

generated

All plastics drums & containers 7 1 100 % or equivalent to tonnes

generated

Rubber waste (tyres, conveyor

etc.)

150 13 100 % or equivalent to tonnes

generated

Used oil & Grease 100 8 100 % or equivalent to tonnes

generated

Metal and plastic drums &

containers

30 3 100 % or equivalent to tonnes

generated

Yard

management All Conforms to best

practices of

waste

management

Conforms to best

practices of

waste

management

Yard in good arrangement and

all wastes managed according

to categories

Collection,

handling and

Storage/dispos

al of non-

recyclable

waste

Domestic waste 120 10 100 % or equivalent to tonnes

generated

Hydrocarbons contaminated soil

and sludge ( including managing

bioremediation facility)

300 25 100 % or equivalent to tonnes

generated

Medical waste 1 0 100 % or equivalent to tonnes

generated

Asbestos 20 2 100 % or equivalent to tonnes

generated

Page 19: SoW - Waste Management Contract-Revised.Feb2019-FINAL of Interest... · 2019. 3. 1. · SoW – Integrated Waste Management Completed by: Andreas Shikesho Date: January/February 2019

Used rags 100 8 100 % or equivalent to tonnes

generated

Fluorescent tubes 5 0.4 101 % or equivalent to tonnes

generated

Redundant chemicals 130 11 100 % or equivalent to tonnes

generated

Sewage waste 5 0.4 101 % or equivalent to tonnes

generated

Oil filters and hydraulic hoses 200 17 100 % or equivalent to tonnes

generated

Contaminated waste 1500 125 100 % or equivalent to tonnes

generated

Historical

waste (Paynes

Metals Waste

Sorting Yard

(Salvage yard))

Scrap metal, wood palettes,

contaminated , garden,

domestic waste and few others

15000 1250 100 %

Equipment

provision

Availability of equipment listed

in the contract

Availability of

the equipment

Availability of

the equipment

100 % availability and in usable

state

Input_ KPIs New Contract Scope_ Waste.xlsx

Page 20: SoW - Waste Management Contract-Revised.Feb2019-FINAL of Interest... · 2019. 3. 1. · SoW – Integrated Waste Management Completed by: Andreas Shikesho Date: January/February 2019

Resources (internal)

Rössing Org Structure

RUL Designated Leader

RUL Supervisor

Waste Management Contractor

Contractor Employees (29 x)

Time

The Service Provider must familiarise himself with RUL working conditions as well as with the three shifts, namely: day, afternoon and night shift. Day shift starts at 08h00, afternoon shift starts at 16h00 and night shift starts at midnight (00h00).

Shift Start End Comment Day 08h00 16h00 Afternoon 16h00 00h00 Night 00h00 08h00

Page 21: SoW - Waste Management Contract-Revised.Feb2019-FINAL of Interest... · 2019. 3. 1. · SoW – Integrated Waste Management Completed by: Andreas Shikesho Date: January/February 2019

Inclusions / Exclusions

Inclusions Responsibilities of the Service Provider

1. The safe operation and maintenance of temporary waste storage areas including their

housekeeping and access control. These areas include the Oil Storage Yard, the Contaminated Oil Storage Yard and the Contractor’s Salvage Yard as well as the new Yard at the Old Acid Plant.

2. The safe operation and maintenance of waste storage areas include: a. the Contaminated Waste Yard on the tailings facility (TSF), b. the bioremediation facility on the tailings storage facility

3. Historically domestic waste was exposed of at the Landfill Site. However, the Landfill Site will be de-commissioned and closed down. Consequently, domestic waste shall be disposed of in Swakopmund or alternatively, in any other town with a suitable waste recycling facility.

4. The operation of the Contractor’s own waste management equipment, including the luggerbin trucks, garbage truck, road sweeper, honey sucker, filter press etc. It is the Contractor’s responsibility to make arrangements for planned and preventive maintenance on own equipment.

5. The Contractor is responsible for the maintenance of the Contractor owned equipment operated on site. Maintenance facilities and maintenance parts will not be supplied through Rössing’s Stores system and the Contractor will be responsible for all his maintenance related expenses.

6. The Contractor needs to supply all equipment required to carry out the tasks contained in this scope. The rates charged for the equipment shall preferably be wet rates.

7. A tool, equipment and material list shall be drawn up listing the tools and equipment to be brought

on site and the list will be presented at the Security Control Point.

8. Any tools, equipment and materials brought on to Rössing site without obtaining the correct

Security Clearance will not be released from Rössing site.

9. The Contractor is responsible for the planned and unplanned maintenance and scheduled servicing of the supplied (i.e. own) equipment.

10. Diesel fuel will be made available for purchase to the Contractor.

11. The Contractor will be required to provide a messing facility, change house and office facilities at

the Yard (on the Rössing site) in the form of temporary containers and/or prefabricated structures

fitted for this purpose.

Page 22: SoW - Waste Management Contract-Revised.Feb2019-FINAL of Interest... · 2019. 3. 1. · SoW – Integrated Waste Management Completed by: Andreas Shikesho Date: January/February 2019

12. Advise Rössing on waste management, including bioremediation.

13. Set up offsite auction centres for waste streams such as conveyor belts, timber (e.g. palettes) etc.

This way waste removal from Rössing site will be accelerated.

14. Find and implement a lasting disposal solution to historical garden waste (clearing the waste stored

at the Landfill Site) and to future disposal of garden waste generated by the horticultural Contractor.

15. Find and implement a lasting disposal solution to the following:

- manganese bags at the Manganese Plant

- ammonium nitrate bags at the Explosives Storage Building

- dried sewage from the SATEC Plant

- tyres mine wide

16. Decontaminate lugger bins if and when required by Rössing and dedicate lugger bins to where ad

hoc waste is generated, such as when shutdowns (weekly, yearly) take place.

17. Provide a properly qualified Site Manager with knowledge and skills in integrated waste

management, including bioremediation.

18. The Service Provider to support weekly cleaning campaigns (i.e. awareness, waste collection and

coordination)

19. The Service Provider to coordinate and organise two annual cleaning campaigns offsite (Arandis

town , RUL private road and B1 national road, 20km stretch)

20. t

Exclusions Responsibilities of Rössing Uranium

The following items will fall under the responsibility of Rössing Uranium as part of supporting these services

and in order for the Service Provider to execute his duties as stipulated:

1. Identify and appoint a relevant Rössing representative designated as the Contract Coordinator (i.e.

Designated Leader) accountable for the control and administration of this Contract;

2. Identify and appoint the relevant Rössing Foreman designated as the Contract Coordinator

responsible for the control and administration of this Contract;

3. Afford the Service Provider’s personnel access to the site and waste management sites as well as

the weighbridge at all reasonable times to enable them to comply with this Contract;

4. Hold formal feedback and follow-up meetings with the Service Provider Management, the frequency

Page 23: SoW - Waste Management Contract-Revised.Feb2019-FINAL of Interest... · 2019. 3. 1. · SoW – Integrated Waste Management Completed by: Andreas Shikesho Date: January/February 2019

of which must be at least once a month;

5. Provide Permit to Work clearances when required; and supply electricity, water and sewage points.

6. Where and if needed, supply civils works at the new waste facility for concrete slabs, wash bay and

roof covering for sorting area.

7. Dedicate a minimum of two (2) days per week just for contaminated waste.

8. Provide a lowbed/flatbed and a mobile crane when needed by the Contractor.

9. Invite the Contractor to planning meetings prior to anticipated generation of ad hoc waste so the

Contractor can arrange for dedicated lugger bins the purpose of containing the ad hoc waste.

10. Where ad hoc waste is too large or bulky such as tanks, provide a site where this waste can

temporarily be disposed of and reduced to manageable pieces that comply with the disposal

requirements at the Contaminated Yard.

Permits / Constraints

Technical & IT Specifications

No requirements –

Page 24: SoW - Waste Management Contract-Revised.Feb2019-FINAL of Interest... · 2019. 3. 1. · SoW – Integrated Waste Management Completed by: Andreas Shikesho Date: January/February 2019