SIZEWELL C COMMUNITY FORUM
26 July 2018
Sizewell C Community Forum 2018 © NOT PROTECTIVELY MARKED 2
Sizewell C Community Forum – July 2018
Sizewell C Community Forum 2018 © NOT PROTECTIVELY MARKED 3
Agenda • Chairs introduction • Minutes of the last forum – available on website • Project Directors Report • Project Update • Community Update • Questions and answers • Next meeting
SIZEWELL C PROJECT DIRECTORS REPORT Jim Crawford Sizewell C Project Development Director & Deputy CEO, Bradwell B
Sizewell C – The Journey So Far…
Sizewell C Community Forum 2018 © NOT PROTECTIVELY MARKED 5
Stage 3 Consultation – Early 2019
Sizewell C Community Forum 2018 © NOT PROTECTIVELY MARKED 6
§ Public Consultations events from early 2019
§ Public events across the area including Leiston, Theberton, Middleton, Sizewell, Wickham Market and Darsham – detailed confirmation later this year
§ Based on latest thinking on transport, workforce & accommodation aimed at minimising disruption & ensuring positive legacy benefits
Why Sizewell C Should be Next
Sizewell C Community Forum 2018 © NOT PROTECTIVELY MARKED 7
The case for building Sizewell C is getting stronger. The development of the station is necessary for the UK’s energy future: § Sizewell C will be competitive with other low-carbon technologies § The risk (hence the cost of finance) will be reduced with four reactors of same design operating by the time construction would begin § The cost of building Sizewell C will be reduced by using a mature UK supply chain. High % of UK companies in Sizewell C supply chain – much higher than other technologies § Sizewell C will provide highly skilled and well-paid employment & contracts for local businesses § Sizewell C will have very low connection cost.
Benefits for the East of England
Sizewell C Community Forum 2018 © NOT PROTECTIVELY MARKED 8
§ Sizewell C will be a catalyst for development of top-end engineering, construction and manufacturing across the region
§ The East of England is the only region with the potential for two new nuclear projects
§ UK businesses secured 64% of total construction spend on Hinkley Point C
§ The Sizewell C project could create 1000 apprenticeships during construction
§ So far, 1,300 companies from this region have registered on our supply chain portal
§ Regional economic benefit could be up to £200m per year during construction with total of £4 billion over the lifetime.
Sizewell C Planning Update
§ At the last Community Forum we reported on feedback received from Sizewell C Stage 2 Consultation.
§ That feedback has now been fully reviewed and will be taken into
account for Sizewell C Stage 3 Consultation.
§ The following slides provide an overview of the work currently being undertaken to inform Stage 3 Consultation.
§ We will not be commenting on what proposals may be included at Stage 3 Consultation.
Sizewell C Community Forum 2018 © NOT PROTECTIVELY MARKED 9
Community Engagement and Outreach
Sizewell C Community Forum 2018 © NOT PROTECTIVELY MARKED 10
§ The SZC team has been busy since the last Community Forum meeting stakeholders with an interest in the project development.
§ We met more than 4,000 people at this year’s Suffolk Show.
§ The team ran an exhibition stand and took part in a Science centre led by the County Council.
§ We also engaged with a wide range of stakeholders including the County and District Councils, the Chamber of Commerce, local landowners and representatives from the region’s leading colleges.
Community Engagement and Outreach
Sizewell C Community Forum 2018 © NOT PROTECTIVELY MARKED 11
§ Since the last Community Forum the SZC team has engaged in more than 200 meetings, events and conferences.
§ Jim Crawford made a keynote speech at the region’s largest energy conference, and the team discussed the project with more than 400 supply chain companies at the event.
§ The team continues to support community events and has just contacted 18 successful applicants to the SZC Community Fund.
§ The team can be contacted at the Leiston office, or via [email protected]
SIZEWELL C PROJECT UPDATE
Richard Bull
Ongoing Work to Inform Sizewell C Stage 3 Assessment Location / Reference Output
Engineering Technical Studies Main Development Site Construction sequencing, Material requirements, Site masterplans, noise and lighting levels
Strategic Traffic Modelling Modelled area Traffic flows (base, reference case , with-development), highway network impacts
Road Safety Assessments Modelled area Road safety impacts arising from with-development traffic flows
Rail capacity requirements / Network Rail
East Suffolk line / Branch line Defines requirements for rail upgrades – track, signalling, level crossings, structures
Landscape and Visual Assessment Main Development Site and associated developments
Impacts on AONB, Special Landscape Areas and on views from agreed viewpoints
Design – Significant Structures Main Development Site Design and impact of key buildings and structures
Accommodation Strategy
Non-home based workers Review Stage 2 assumptions and alternatives, proposed strategy for Stage 3
Sizewell C Community Forum 2018 © NOT PROTECTIVELY MARKED 13
Assessment Location / Reference Output
Noise and Vibration Main Development Site Boundary Treatments Landscaping requirements
Noise and Vibration Local Road Network Traffic impacts to inform mitigation requirements
Air Quality Main Development Site Emissions report, Construction Dust Assessment
Air Quality Local Road Network Air quality impacts from traffic movements
Groundwater and Surface Water
Main Development Site Environmental impacts, mitigation options, drainage principles
Flood Risk Assessment Main Development Site Flooding impacts, mitigation options
Flood Risk Assessment Desk Study
Associated Development locations
Preliminary assessment of flood risk and mitigation options
Public Rights of Way Survey Main Development Site
Inform overall rights of way strategy and any diversions
Sizewell C Community Forum 2018 © NOT PROTECTIVELY MARKED 14
Ongoing Work to Inform Sizewell C Stage 3
Assessment Location / Reference Output
Terrestrial Ecology – ecological assessment
Main Development Site and associated developments
Ecological impacts from construction and operation, including impacts on Sizewell Marshes SSSI
Ecology – Habitat Regulation Assessment
Main Development Site Impacts on adjacent and nearby European Sites (Special Protection Areas – for birds; Special Areas of Conservation),
Marine Navigation Marine traffic data Preliminary navigation risk assessment of design proposals
Coastal Geomorphology Field sampling and numerical modelling
Topographic surveys of the shore, shingle tracking, climate change impacts
Marine Water and Sediment Quality
Sampling around Sizewell Toxicity assessments, baseline water quality conditions, longer term management needs
Marine Ecology and Fisheries Field sampling and laboratory assessment
Underwater noise assessments, review of fishing activity, fish impingement
Sizewell C Community Forum 2018 © NOT PROTECTIVELY MARKED 15
Ongoing Work to Inform Sizewell C Stage 3
Assessment Location / Reference Output
Skills Eastern Institute of Technology EDF Energy is a supporting the establishment to become a hub to deliver curriculum for the National College of Nuclear
Education Suffolk Promote STEM (Science, Technology, Engineering and Mathematics) programme in schools
Tourism Local area Focus groups to examine some concerns raised at Stage 2
Economic Development Local area How local businesses can benefit from the project
Community Meetings Local area Emergency services, social care, education capacity, public health, sports facilities
Sizewell C Community Forum 2018 © NOT PROTECTIVELY MARKED 16
Ongoing Work to Inform Sizewell C Stage 3