Site Visit Report #133 DATE: June 19, 2017 PROJECT: Lakewood High School Project: 2014-05 OBSERVATIONS: 1. Curved sidewalk, northeast of NCW – leading to 172nd, is poured. Most of sidewalk north of NCW – along south side of bus parking – is poured. 2. Another seatwall near main entry has been poured. 3. Landscaping crew is working on irrigation lines west of Greenhouse. 4. Main Gym and Aux Gym walls have been coated with block filler. 5. Kitchen and Servery equipment installation in progress. Most equipment has been brought inside from Service Yard. Rolling racks are placed in Dry Storage room. Concrete floor slabs installed in walk-in Cooler and Freezer. 6. Additional joint and fastener finishing visible on GWB-finished walls in Weight Room and Fitness / Wrestling. 7. Rolls of carpet have been delivered to Transitions classroom, NCW 1 st floor. 8. Hoisting beam and equipment for elevator assembly present in elevator shaft. 9. Middle portion of Commons floor – west of Ted Talks platform – is being ground, preparation for polishing and staining. 10. Metal siding workers installing panels on south and east sides of Fly Loft. 11. Workers observed at rooftop HVAC units for NCW and Admin/Advising. 12. Allied has excavated and removed more quarry spalls along southwest and west side of the fill between Aux Gym and parking lot. Excavation of soil is underway in this area. NCW from NE. Recently-poured sidewalk extends to near corner.

Site Visit Report #133 DATE: June 19, 2017 Lakewood … Visit Report #133 DATE: June 19, 2017 PROJECT: Lakewood High School Project: 2014-05 OBSERVATIONS: 1. Curved sidewalk, northeast

Embed Size (px)

Citation preview

Site Visit Report #133 DATE: June 19, 2017 PROJECT: Lakewood High School Project: 2014-05 OBSERVATIONS: 1. Curved sidewalk, northeast of NCW – leading to 172nd, is poured. Most of sidewalk north of NCW –

along south side of bus parking – is poured. 2. Another seatwall near main entry has been poured. 3. Landscaping crew is working on irrigation lines west of Greenhouse. 4. Main Gym and Aux Gym walls have been coated with block filler. 5. Kitchen and Servery equipment installation in progress. Most equipment has been brought inside

from Service Yard. Rolling racks are placed in Dry Storage room. Concrete floor slabs installed in walk-in Cooler and Freezer.

6. Additional joint and fastener finishing visible on GWB-finished walls in Weight Room and Fitness / Wrestling.

7. Rolls of carpet have been delivered to Transitions classroom, NCW 1st floor. 8. Hoisting beam and equipment for elevator assembly present in elevator shaft. 9. Middle portion of Commons floor – west of Ted Talks platform – is being ground, preparation for

polishing and staining. 10. Metal siding workers installing panels on south and east sides of Fly Loft. 11. Workers observed at rooftop HVAC units for NCW and Admin/Advising. 12. Allied has excavated and removed more quarry spalls along southwest and west side of the fill

between Aux Gym and parking lot. Excavation of soil is underway in this area.

NCW from NE. Recently-poured sidewalk extends to near corner.

North side of HS, viewed from north of Main Entry.

Site south of Wrestling/Fitness and Aux Gym.

SCW viewed from SE.

HS viewed from east drive.

East side of Theater viewed from nearby roof.

SCW 1st floor General Science classroom from NE door.

SCW 1st floor Horticulture Lab from NE.

Servery and Kitchen, viewed from north. Kitchen equipment placement underway.

Wrestling / Fitness viewed from east.

Main Gym, viewed from NE.

Main Gym viewed from SW.

Aux Gym viewed from NW.

Theater viewed from Stage.

Site to NE of NCW.

Site east of SCW.

Site SW of Aux Gym, viewed from Wrestling/Fitness roof.

Carpet roll delivery TED Talks platform framing progress

Elevator installation progress Floor grinding, west part of Commons

Curved sidewalk NE of school Secondary entry, between NCW & Administration

Front Loader working west of Aux Gym Re-grading progress SW of Aux Gym

Gravel yard east of Greenhouse Flatwork finishers, north of NCW