ISSUES TO BE SOLVED THIS WEEK
ISSUESSOLUTIONREMARKS
GC-21 PACKAGE HOLD BECAUSE OF COATING REPORT (ONE SPOOL)DISCUSS W/ PMC AND CHECK IN THE SITECLEARED
GC-20 PACKAGE PREPARATIONPREPARE IN URGENT BASIS AND HAND OVER TO QC0CLEARED
3L-PE COATING REPAIR IN SITE NCC DO NOT SUPPLY THE MANPOWER FOR REPAIR ACTIVITY TRAINING AND APPROVAL OF IMCO PERSONNEL TRAINING AND APPROVAL OF NCC PERSONNEL
ON-GOING
A1-1 SITE WORK FOR SAND BLASTING SHBC DO NOT WANT TO DO IN THE SITECHECK WITH PMC AND ASK FOR THE ADVISE OTHERWISE SUBMIT TQ TO KOCON-GOING
WMS PREPARATION FOR URGENT LOCATIONS1. STF-A32A2. GC-203. GC-224. BS-150WMS PREPARATION UNTIL 14 APRIL AND DISCUSS TO MICUON-GOING
HBP COATING EXPIRATION AFTER 10 MONTHS OF COATED SPOOLCHECK THE SPOOL STATUS