27
1 ACOUSTIC/VIBRATION ASSESSMENT 46 & 50 Tattersall Road, Kings Park, NSW PREPARED FOR: Claron Consulting PTY LTD OUR REFERENCE: REP-18 6328-A1 ISSUE DATE: 5 th September 2018

‘Site and Soil Evaluation’ Report Template

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: ‘Site and Soil Evaluation’ Report Template

1

ACOUSTIC/VIBRATION ASSESSMENT

46 & 50 Tattersall Road, Kings Park, NSW

PREPARED FOR: Claron Consulting PTY LTD

OUR REFERENCE: REP-18 6328-A1 ISSUE DATE: 5th September 2018

Page 2: ‘Site and Soil Evaluation’ Report Template

ENVIROTECH PTY. LTD.

2

CONTROLLED DOCUMENT

DISTRIBUTION & REVISION REGISTER

DISTRIBUTION LIST

Copy No. Custodian Location

1 Original Daniel Mathew ENVIROTECH PTY. LTD (Filed)

2 Soft Copy (PDF,

emailed) Claron Consulting PTY LTD [email protected]

Note: This register identifies the current custodians of controlled copies of the subject document.

DOCUMENT HISTORY

Document No. Revision No. Issue Date

632818 A1 05/09/2018

AUTHOR TECHNICAL REVIEWER

Simon Doberer BS(Env)

Environmental Scientist – Team Leader

Daniel Mathew

Environmental Engineer / Managing Director

B.Eng. (ENV.)(Hons.)

COPYRIGHT © 2018 ENVIROTECH PTY. LTD.

The report is protected by copyright law and may only be reproduced, in electronic of hard copy

format, if it copied and distributed in full with the prior written permission of EnviroTech Pty. Ltd.

Page 3: ‘Site and Soil Evaluation’ Report Template

ENVIROTECH PTY. LTD.

3

TABLE OF CONTENTS

1. INTRODUCTION ............................................................................................................... 4

2. NOISE ASSESSMENT CRITERIA ............................................................................................ 8

3. BACKGROUND & AMBIENT NOISE MEASUREMENTS ............................................................ 13

4. NOISE GOALS ................................................................................................................ 14

5. NOISE SOURCE MODELS ................................................................................................. 14

6. NOISE ASSESSMENT ....................................................................................................... 16

7. VIBRATION ASSESSMENT ................................................................................................. 17

8. CONCLUSION ............................................................................................................ 17

9. GRAPHED DATA ............................................................................................................ 18

…………………………………………………………………………………………

Page 4: ‘Site and Soil Evaluation’ Report Template

4

1. INTRODUCTION

EnviroTech has been requested by Claron Consulting PTY LTD to undertake an acoustic assessment

of the proposed expansion and operation of a resource recovery facility, at 46 & 50 Tattersall Road,

Kings Park, NSW (hereafter referred to as the site).

The purpose of this assessment is to accurately predict potential noise levels generated by the

proposal and to assess the impact of these noise levels on the nearest commercial receptors, in

accordance with the NSW Government’s relevant noise criteria.

This assessment has been prepared in accordance with:

• NSW Protection of the Environment Operations Act 1997 (POEO Act)

• Environmental Planning and Assessment Act (1979)

• Noise Policy for Industry (2017)

• The Noise Guide for Local Government (DECCW, 2009)

• State Environmental Planning Policy (Infrastructure) 2007

• NSW Department of Planning “Development near rail corridors and busy roads” 2008

• Assessing Vibration: a technical guideline (DECC 2006).

• Building Code of Australia

Proposal

The study site is 46 & 50 Tattersall Road, Kings Park NSW 2148 (Lots 13 & 14 of DP 220004). The

layout of the site and surrounding land use is illustrated in Figure 1. It can be identified as a square

shaped allotment on Tattersall Road.

The proposal is for an expansion and operation of a resource recovery facility with a processing capacity of 28,000 tonnes per year of solid or liquid organic waste (Figure 2).

In accordance with the EPAs Industrial Noise Policy (INP), the surrounding noise amenity of the site

is classified as Industrial.

The activities proposed to be undertaken on this site are limited to receiving and processing the

collected materials within the existing building.

Below is an outline of all stages of the proposed activities.

Sorting

As soon as the materials are received on site, the covers are removed from the truck/trailer and

materials are unloaded at the either the de-watering bay if they are wet or at a new stockpile if they

are either dry or semi-wet. Using a normal front-end loader.

Page 5: ‘Site and Soil Evaluation’ Report Template

ENVIROTECH PTY. LTD.

5

Dewatering

All materials transported from all sources are placed into a dedicated bay and bunker which is

designed in such a way to assist in the removal of liquids by gravity. No mechanical or thermal

intervention is required during this stage.

Stockpiling

Following the dewatering of materials, they are placed in different stockpiles to assist in the

processing and mixing.

Screening

The materials are then processed through a screening tumble.

Pasteurisation

Pasteurisation occurs when the materials are turned over several times in accordance with current

best industry management and the EPA’s guidelines associated with pasteurisation.

The site will also be used for the storage of empty trucks, trailers, screener, car parking and vehicle

maneuvering. Minor maintenance and service of machinery will be undertaken within the site.

Major maintenance and service of plant/equipment and other vehicles will be undertaken by

professional companies.

Page 6: ‘Site and Soil Evaluation’ Report Template

ENVIROTECH PTY. LTD.

6

Figure 1: aerial photograph of the site, showing the (Sixmaps, 2018). Red star indicates logger

placement.

The proposal is to be located within a current industrial area in Kings Park. There are a number of

neighboring industrial receptors in vicinity of the site. The closest industrial property boundary from

the proposed is 1m to the north and west.

Page 7: ‘Site and Soil Evaluation’ Report Template

ENVIROTECH PTY. LTD.

7

Figure 2: Site plan of the proposed

Figure 3: Area of noise logger location.

Page 8: ‘Site and Soil Evaluation’ Report Template

ENVIROTECH PTY. LTD.

8

2. NOISE ASSESSMENT CRITERIA

This section reviews the NSW Government criteria for other noise sources and developments. These

may be used as a basis for realistic noise goals from meeting halls to residential receivers.

NSW Government Criteria

The NSW Government, via the Office of Environment & Heritage provides guidelines for many

industrial, commercial and domestic types of noise sources. The primary aim of environmental noise

control is to minimise the occurrence of offensive noise in the community.

Offensive noise is defined in the NSW Protection of the Environment Operations Act 1997 (POEO

Act) as being noise:

a) That, by reason is of its level, nature, character or quality, or the time at which it is made, or

other circumstances:

i. is harmful to (or is likely to be harmful to) a person who is outside the premises from which

it is emitted, or

ii. interferes unreasonably with (or is likely to Interfere unreasonably with) the comfort or

repose of a person who is outside the premises from which it is emitted, or

b) That, is of a level, nature, character or quality prescribed by the regulations or that is made at

a time or in other circumstances, prescribed by the regulations.

The NSW Government also state that social surveys have indicated that noise from any particular

source will be audible to many people in the community when that noise exceeds the background

level by more than 5 decibels (dB). The noise may have characteristics which are pleasant or

unpleasant to the listener.

Technically the background is found from the noise level that is present for 90% of the time of the

measurement periods (usually 15 minutes each) and this is known as the LA90, 15 minute.

The source noise is found from the ‘equivalent continuous A-weighted sound pressure level’ (again

usually 15 minutes samples), which is known as the LAeq, 15 minute.

The Noise Guide for Local Government

The Noise Guide for Local Government published by the NSW Department of Environment, Climate

Change and Water (2004 updated 2009) states:- ‘A noise source is generally considered to be

intrusive if noise from the source, when measured over a 15 minute period exceeds the background

noise by more than 5 dB’. It is assessed at the most affected point on or within the neighbouring

residential property (unless that residence is more than 30 metres from the boundary). Intrusive

noise can represent offensive noise. However, it is stated in the Noise Guide for Local Government

that this is not always the case and it can depend upon the source of the noise, noise characteristics

and cumulative noise levels.

Page 9: ‘Site and Soil Evaluation’ Report Template

ENVIROTECH PTY. LTD.

9

Noise Policy for Industry

The Noise Policy for Industry 2017 is used to assess noise from industrial noise sources, scheduled

under the Protection of the Environment Operations Act 1997. This is a statutory document referred

to by consultants when attempting to control short-term intrusive impacts upon sensitive receptors

(i.e. nearby residents), and when attempting to maintain noise level amenities for particular land

uses.

In accordance with the NPI, there are two criteria which need to be considered when assessing

industrial noise. These are:

1) Intrusive Noise Criterion

2) Noise Amenity Criteria.

Both of these criterions need to be satisfied under the NPI. In this situation the cumulative impact

over the day and evening periods would be significantly less than the peak periods which would

cover continuous activity over any one 15 minute period. Therefore, the Amenity Noise Criterion

would be the most stringent of the two noise criteria.

Intrusive Noise Criterion

The intrusiveness criterion is primarily used to limit short term noise impacts, and is summarized as

follows:

LAeq, 15 minutes ≤ rating background noise level + 5dB

The intrusiveness of an industrial noise source is generally considered acceptable if the equivalent

continuous (A weighted) noise level LAeq, 15 minutes does not exceed the rated background noise level

by more than 5dB(A).

Noise Amenity Criteria

The Noise Amenity Criteria is used to limit the potential of noise annoyance over longer periods,

which may occur as a result of continual increases in background noise.

The Noise Policy for Industry states that ‘To limit continuing increases in noise levels from

application of the intrusiveness level alone, the ambient noise level within an area from all industrial

noise sources combined should remain below the recommended amenity noise levels specified in

Table 2.2 where feasible and reasonable.

Page 10: ‘Site and Soil Evaluation’ Report Template

ENVIROTECH PTY. LTD.

10

TABLE 2 – RECOMMENDED NOISE LEVELS FROM INDUSTRIAL NOISE SOURCES.

Type of Receiver

Indicative

Noise Amenity

Area

Time of

Day

Recommended LAeq Noise

Level (dBA)

Acceptable Recommended

Maximum

Residence

Rural

Day

Evening

Night

50

45

40

55

50

45

Suburban

Day

Evening

Night

55

45

40

60

50

45

Urban

Day

Evening

Night

60

50

45

65

55

50

Urban/Industrial

Interface – for existing

situations only

Day

Evening

Night

65

55

50

70

60

55

School Classroom -

Internal All

Noisiest 1-hour

period when in use 35 40

Active Recreation Area

(e.g. playground) All When in use 55 60

Commercial premises All When in use 65 70

Industrial premises All When in use 70 75

Notes:

- Daytime is defined as between 07:00 hours and 18:00 hours

- Evening time is defined as between 18:00 hours and 22:00 hours

- Night time is defined as between 22:00 hours and 07:00 hours

Vibration

Human Comfort

Criteria for assessment of the effects of vibration on human comfort are set out in British Standard 6472-1992. Methods and criteria in that Standard are used to set “preferred” and “maximum” vibration levels in the document “Assessing Vibration: A Technical Guideline” (2006) produced by the NSW EPA.

Page 11: ‘Site and Soil Evaluation’ Report Template

ENVIROTECH PTY. LTD.

11

Acceptable values of human exposure to continuous vibration, such as that associated with drilling, are dependent on the time of day and the activity taking place in the occupied space (e.g. workshop, office, residence or a vibration-critical area). Guidance on preferred values for continuous vibration is set out below in Table 4

Table 4: Acceptable vibration dose values for intermittent vibration (m/s 1.75)

Criteria for building structures

When assessing potential vibration impacts on building structures, the velocity and direction of the

movement is measured. The measurement is referred to as the Peak Particle Velocity (PPV),

presented in mm/s.

Vibration from construction activities, with regard to building damage, is assessed using the German

standard DIN 4150: Part 3 – 1999 Effects of Vibration on Structures (DIN Guideline). The DIN

Guideline values for PPV measured at the foundation of various structures are summarised in Table

5 below.

Table 5: Guideline Values of vibration velocity for evaluating the effects of vibration.

Page 12: ‘Site and Soil Evaluation’ Report Template

ENVIROTECH PTY. LTD.

12

From the guidelines outlined above the following vibration criteria have been determined for the

Project.

Page 13: ‘Site and Soil Evaluation’ Report Template

ENVIROTECH PTY. LTD.

13

3. BACKGROUND & AMBIENT NOISE MEASUREMENTS

1. Determination Method: Long-term continuous sampling

2. Noise Logger Location: See Site Plan, figure 1

3. Survey Period: 2nd August 2018 – 9th August 2018

4. Assessment Time Period: All Times

5. Monitoring Conditions: No adverse weather conditions

No unusual circumstances or activities

6. Instrumentation: ‘ARL’ - Type 2 Environmental Noise Logger (EL-215)

(Serial number 194678), This instrument conforms to

Australian Standard 1259 "Acoustics - Sound Level Meters",

(1990) and has an accuracy suitable for both field and

laboratory use. The logger was set for the ‘A’ frequency

weighting and ‘fast’ time weighting.

7. Calibration: The environmental noise logger and calibrator have been

checked, adjusted and aligned before and after the

measurement period, to conform to the Bruel and Kjrer or

RTA factory specifications. Both have been issued with

conformance certificates within the last 24 months as

required by the regulations. The internal test equipment

used is traceable to the National Measurement Laboratory

at C.S.I.R.O., Lindfield, NSW, Australia. No significant system

drift occurred over the measurement periods. Current

calibration certificate in appendix

Page 14: ‘Site and Soil Evaluation’ Report Template

ENVIROTECH PTY. LTD.

14

8. Results:

The recorded LA90 levels determine the Rating Background Level (RBL). The RBL is defined as the

median value of the tenth percentile value for the recorded LA90 levels for the complete monitoring

period. The tenth percentile is also referred to as the Assessment Background Level (ABL).

The resultant RBL (LA90) and ambient (LAeq) levels for each period are summarised below in Table 3

and 4. Appendix A contains a geographical presentation of the background noise levels generated

from the monitoring period.

TABLE 4 – Summary of existing noise levels

4. NOISE GOALS

TABLE 5 – Noise goal for the neighboring industrial premise

Time Of Day Amenity Criteria

All Times 70 dBA LAeq

5. NOISE SOURCE MODELS This section provides details of the calculations used for predicting noise levels and the resulting

noise levels at the potentially affected industrial receptors. The below calculation is of a worst case

scenario if all noise generating sources emitting noise at the one time. Whilst this maybe highly

unlikely it is best practice to calculate and model this scenario to show noise compliance at

neighboring receivers whilst the proposed is at full noise capacity.

Predicted Noise Levels

The major noise sources for the proposed are listed below.

Mini Excavator – 85 dBA

Screening Tumble – 88.1 dBA

Truck Deliveries/Pickup– 90 dBA

Front End Loader– 90 dBA

Staff x 4 talking loudly – 80 dBA

Generator for high pressure cleaner – 60 dBA

Rating Background

Noise Level (L90) dBA

Log Average Existing Ambient Noise Levels (LAeq)

dBA

55.52 64.69

Page 15: ‘Site and Soil Evaluation’ Report Template

ENVIROTECH PTY. LTD.

15

The below calculation was determined on a worst-case scenario of all the staff talking and all of the

noise generating sources in use.

Total 15 minute average - Daytime 94.86 dBA

The calculated maximum worst case noise level of the proposed is 94.86 dBA.

Predicted External Noise Levels

The source noise has been modelled using the International Standard ISO 9613-2

(1996(E)) 'Acoustic - Attenuation of sound during propagation outdoors Part 2 General method of

calculation '. This Standard specifies methods for the description of noise outdoors in community

environments. The method described in the Standard is general in the sense that it may be applied

to a wide variety of noise sources, and covers the major mechanism of attenuation. The method

allows for downwind propagation conditions namely:

- Wind direction within an angle of ± 45° of the direction connecting the centre of the

dominant sound source and the centre of the specified receiver region with the wind

blowing from source to receiver,

- Wind speed between approximately 1 m/s and 5 m/s measured at a height of 3 m to 11 m

above the ground.

Basic Noise Modelling Equations

The equivalent continuous downwind sound pressure level (LAeq) at each receiver point has been

calculated using the equation below:-

Page 16: ‘Site and Soil Evaluation’ Report Template

16

6. NOISE ASSESSMENT

The calculation of noise emission to the environment takes into account the surface area of the

development radiating noise, the sound reduction index of the structural component and distance

to the receiver location. The distance is measured from the proposed noise sources to the nearest

industrial receivers.

With the recommendations correctly implemented, as specified in Section 7 below and discussion of

existing building materials below, the activities from within the proposal are predicted to be noise

compliant at neighboring industrial properties.

The noise emission dBA to the nearest industrial receptor was calculated as follows:

The nearest sensitive receptor property boundaries are located to the north and west of the site

which are neighbouring industrial allotments. From the centre of the proposed working area to

these property boundaries is approximately 14m.

94.86 – 20 LOG (14 / 1) = 71.94dBA

Therefore, the minimum required ‘Weighted Sound Reduction Index (Rw) from the proposed to the

nearest industrial receptor is 1.94 dBA.

This attenuation is currently being provided via existing building materials at the subject site. The

approximate 3m high concrete wall surrounding the external portion of the proposed is currently

and will provide the necessary attenuation.

Road Traffic Noise

The NSW Road Policy (2011) is applicable to the subject development and applies different noise

limits dependent upon the development category and receptor type.

Land use

developments with

potential to create

additional traffic on

local roads

Day 7am –

10pm dBA

LAeq(1hr)55

Night 10pm –

7am dBA

LAeq(1hr)50

Where feasible and reasonable, existing

noise levels should be mitigated to meet

the noise criteria. Examples of applicable

strategies include appropriate location of

private access roads; regulating times of

use; using clustering; using ‘quiet’

vehicles; and using barriers and acoustic

treatments.

In all cases, traffic arising from the

development should not lead to an

increase in existing noise levels of more

than 2 dBA.

Page 17: ‘Site and Soil Evaluation’ Report Template

ENVIROTECH PTY. LTD.

17

The potential traffic arising from the development will not lead to an increase in existing noise levels

of more than 2 dB. The increase in noise levels of traffic can be calculated using the following

formula suggested within the NSW Road Policy: Log10 (Future Traffic/Existing Traffic) per hour.

This development will not lead to an increase in existing noise levels of more than 2 dBA.

Proposed Truck Routes

From the major thoroughfare’s servicing the proposed development truck movement do not pass

through residential areas between the major thoroughfare’s and the subject site.

7. VIBRATION ASSESSMENT

The existing screening tumbler is to be stored externally of the building onsite. The transmission of

any vibration through the concrete slab will be minimal at neighbouring receivers and well below

allowable thresholds within table 5 above.

8. CONCLUSION

The acoustic assessment the of the proposed expansion and operation of a resource recovery

facility, at 46 & 50 Tattersall Road, Kings Park, has determined that the noise generated will be

negligible once attenuation recommendations are put into place at the industrial receivers.

A sound reduction of 1.94 dBA for the proposed is needed to the nearest industrial receptor after

calculations were finalised. This attenuation is currently being provided via existing building

materials at the subject site. The approximate 3m high concrete wall surrounding the external

portion of the proposed is currently and will provide the necessary attenuation.

It is concluded that the proposed development is predicted to comply with the relevant noise goals.

Page 18: ‘Site and Soil Evaluation’ Report Template

ENVIROTECH PTY. LTD.

18

9. GRAPHED DATA

Measured background noise levels.

Page 19: ‘Site and Soil Evaluation’ Report Template

ENVIROTECH PTY. LTD.

19

Page 20: ‘Site and Soil Evaluation’ Report Template

ENVIROTECH PTY. LTD.

20

Page 21: ‘Site and Soil Evaluation’ Report Template

ENVIROTECH PTY. LTD.

21

Appendix I – Site Overlay

Page 22: ‘Site and Soil Evaluation’ Report Template

45.8

46

46.2

4

6

.4

46

.6

47

4

7

47.4

47.6

4

7

.8

4

8

48.2

48.4

48.6

4

8

.

6

METAL

BAR

FENCE

(CONCRETE RAMP)

METAL AWNING

ST

EP

IN

CO

NC

RE

TE

BD

Y - 2

7.4

3

CO

NC

RE

TE

BLO

CK

WA

LL

CONCRETE

BLOCKWALL

METAL

BARFENCE

CONCRETE PAVEMENT

BD

Y - 27.43

BDY - 60.96

CONCRETE PAVEMENT

METAL AWNING

BDY - 60.96

LO

W B

RIC

K W

ALL

BRICK

PIER

METAL AWNING

LO

W B

RIC

K W

ALL

LOT 14

DP. 220004

1672m²

T A

T

T

E

R

S

A

L

L

R

O

A

D

LIN

E O

F R

OO

F O

VE

R

METAL ROOF

DR

AIN

AG

E G

RA

TE

DRAINAGE

PIT

CONCRETE

BLOCK

BUILDING

BRICK

BUILDING

BRICK

BUILDING

CONCRETE

BLOCK

BUILDING

ST

EP

IN

CO

NC

RE

TE

CONCRETE

BLOCK

WALL

CO

NC

RE

TE

K

ER

B &

G

UT

TE

R

POWER

POLE

BM PLACED

NAIL IN KERB

RL 45.87

LOT 12

DP. 220004

RO

LL

ER

S

HU

TT

ER

ROLLER SHUTTER

SH

WC

SW

IT

CH

B

RD

KIT

.

shelving

shelving

shelving

shelving

RECEIVED MATERIAL

STORAGE AREA

(15m x 6m)

2.4m HIGH WALLS

RA

CK

S

HE

LV

IN

G

EXISTING

FACTORY

BENCH MARK NAIL

IN CONCRETE

RL50.00 ASSUMED

27

9° 2

7'

27

.4

3

189° 27'60.96

9° 27'

60.96

99

° 2

7'

27

.4

3

5

2

.0

0

5

2

.

0

0

5

3

.0

0

53.00

52.50

52.50

BLOCK WALL BLOCK WALL

BLOCK WALL

M

E

T

A

L

A

W

N

I

N

G

M

E

T

A

L

A

W

N

I

N

G

CONCRETE

T A

T

T

E

R

S

A

L

L

R

O

A

D

LOT 13

DP. 220004

1672m²

CO

NC

RE

TE

K

ER

B &

G

UT

TE

R

10m³ HOOK BIN

FOR TIP WASTE

VEHICLE TURNING

AREA & PARKING

(CONCRETE HARDSTAND)

TR

OM

ME

L S

CR

EE

N

UNDERCOVER

TIP-OFF AREA

(BUNDED)

PUMP WELL

30,000L WATER TANK ON STAND WITH STORAGE

UNDER. (WATER TO GO OFF-SITE)

8000L

WATER TANK

CO

NC

RE

TE

BITUMEN

FRESH WATER STORAGE TANK FOR WASH-DOWN

1

CO

NC

RE

TE

VE

HIC

LE

C

RO

SS

IN

G

BITUMEN

BITUMEN

CO

NC

RE

TE

D

IS

H D

RA

IN

GRATED DRAIN

RO

LL

ER

S

HU

TT

ER

PROCESSING

AREA

CONCRETE BARRIER WITH CURTAIN OVER

DUST MISTERS OVER

PROCESSING & TIP-OFF

AREAS INDICATED THUS

VE

HIC

LE

C

RO

SS

IN

G

SP

EE

D H

UM

P

SPEED HUMP

SP

EE

D H

UM

PS

PE

ED

H

UM

P

SINGLE WEIGHBRIDGE

3m X 9m

TO MANUFACTURER'S DETAIL

LOW ROLLED KERB TO

FORM EDGE OF DISH

DRAIN

PIT B

PIT C

PIT D

PIT A

PIT F

TOP OF PIT 51.45

IL 50.05

TOP OF PIT 51.43

IL 50.23

TOP OF PIT 51.43

IL 50.73

TOP OF PIT 51.40

IL 50.70

CONSTRUCT NEW COUNCIL

STANDARD GULLY PIT

TOP OF PIT 51.00

IL 50.30

PIT E

TOP OF PIT 50.10

IL 49.40

PIT G

TOP OF PIT 49.71

IL 49.01

NE

W S

LID

IN

G G

AT

E

SK

IP

B

IN

S

TO

RA

GE

A

RE

A

COVERED GREEN WASTE

GR

EE

NW

AS

TE

BA

GG

ED

S

TO

RA

GE

TR

UC

K B

AY

TR

UC

K B

AY

1

2

3

4

5

6

VIS

IT

OR

TRUCK BAY

TRUCK BAY

WA

TE

R

TR

EA

TM

EN

T

NE

W F

RO

NT

F

EN

CE

MATERIAL PROCESSING

OFFICE & ADMIN.

TRUCK MAINTENANCE

AMENDMENTS

A --

SITE PLAN

1:100@A1

31.3.18

SB

---

DA1.01 A

SCALE:

DATE:

DRAWN:

PROJECT #:

ENVIROCIVIL Pty Ltd

52 TATTERSALL ROAD, KINGS PARK

LOT 14 IN DP220004

CONSULTING PTY LTDPO Box 115

Castle Hill NSW 1765m 0418 242 738

CLARON

T

N

AutoCAD SHX Text
50.96
AutoCAD SHX Text
51.44
AutoCAD SHX Text
TK 45.81
AutoCAD SHX Text
45.94
AutoCAD SHX Text
45.94
AutoCAD SHX Text
46.02
AutoCAD SHX Text
46.04
AutoCAD SHX Text
46.20
AutoCAD SHX Text
46.22
AutoCAD SHX Text
46.22
AutoCAD SHX Text
46.15
AutoCAD SHX Text
46.13
AutoCAD SHX Text
46.09
AutoCAD SHX Text
45.93
AutoCAD SHX Text
45.96
AutoCAD SHX Text
TK 45.83
AutoCAD SHX Text
TK 45.85
AutoCAD SHX Text
TK 45.89
AutoCAD SHX Text
TK 45.86
AutoCAD SHX Text
46.11
AutoCAD SHX Text
45.82
AutoCAD SHX Text
46.16
AutoCAD SHX Text
46.21
AutoCAD SHX Text
46.85
AutoCAD SHX Text
47.06
AutoCAD SHX Text
47.38
AutoCAD SHX Text
47.07
AutoCAD SHX Text
47.08
AutoCAD SHX Text
47.03
AutoCAD SHX Text
46.99
AutoCAD SHX Text
46.88
AutoCAD SHX Text
46.86
AutoCAD SHX Text
46.90
AutoCAD SHX Text
46.91
AutoCAD SHX Text
46.91
AutoCAD SHX Text
46.90
AutoCAD SHX Text
46.91
AutoCAD SHX Text
46.75
AutoCAD SHX Text
46.90
AutoCAD SHX Text
46.90
AutoCAD SHX Text
46.90
AutoCAD SHX Text
46.90
AutoCAD SHX Text
46.88
AutoCAD SHX Text
46.89
AutoCAD SHX Text
46.89
AutoCAD SHX Text
46.64
AutoCAD SHX Text
46.27
AutoCAD SHX Text
46.25
AutoCAD SHX Text
45.79
AutoCAD SHX Text
45.79
AutoCAD SHX Text
46.28
AutoCAD SHX Text
46.21
AutoCAD SHX Text
46.37
AutoCAD SHX Text
46.19
AutoCAD SHX Text
47.13
AutoCAD SHX Text
47.11
AutoCAD SHX Text
49.02
AutoCAD SHX Text
47.11
AutoCAD SHX Text
47.11
AutoCAD SHX Text
47.12
AutoCAD SHX Text
47.13
AutoCAD SHX Text
47.13
AutoCAD SHX Text
47.17
AutoCAD SHX Text
46.54
AutoCAD SHX Text
46.83
AutoCAD SHX Text
46.12
AutoCAD SHX Text
51.10
AutoCAD SHX Text
49.15
AutoCAD SHX Text
47.38
AutoCAD SHX Text
47.56
AutoCAD SHX Text
47.50
AutoCAD SHX Text
47.82
AutoCAD SHX Text
47.86
AutoCAD SHX Text
48.06
AutoCAD SHX Text
48.74
AutoCAD SHX Text
48.74
AutoCAD SHX Text
48.73
AutoCAD SHX Text
48.62
AutoCAD SHX Text
48.39
AutoCAD SHX Text
48.11
AutoCAD SHX Text
47.59
AutoCAD SHX Text
47.21
AutoCAD SHX Text
47.20
AutoCAD SHX Text
47.21
AutoCAD SHX Text
47.22
AutoCAD SHX Text
47.22
AutoCAD SHX Text
47.23
AutoCAD SHX Text
47.21
AutoCAD SHX Text
47.23
AutoCAD SHX Text
47.40
AutoCAD SHX Text
47.68
AutoCAD SHX Text
47.61
AutoCAD SHX Text
47.60
AutoCAD SHX Text
47.52
AutoCAD SHX Text
47.91
AutoCAD SHX Text
47.80
AutoCAD SHX Text
47.68
AutoCAD SHX Text
48.18
AutoCAD SHX Text
48.67
AutoCAD SHX Text
48.67
AutoCAD SHX Text
48.38
AutoCAD SHX Text
48.36
AutoCAD SHX Text
48.39
AutoCAD SHX Text
48.73
AutoCAD SHX Text
48.72
AutoCAD SHX Text
48.54
AutoCAD SHX Text
48.64
AutoCAD SHX Text
FL. 47.21
AutoCAD SHX Text
FL. 47.93
AutoCAD SHX Text
FL. 48.74
AutoCAD SHX Text
T
AutoCAD SHX Text
45.8
AutoCAD SHX Text
FL. 48.75
AutoCAD SHX Text
51.45
AutoCAD SHX Text
51.44
AutoCAD SHX Text
51.47
AutoCAD SHX Text
51.46
AutoCAD SHX Text
51.39
AutoCAD SHX Text
51.45
AutoCAD SHX Text
51.37
AutoCAD SHX Text
51.29
AutoCAD SHX Text
50.99
AutoCAD SHX Text
50.60
AutoCAD SHX Text
50.09
AutoCAD SHX Text
50.16
AutoCAD SHX Text
50.49
AutoCAD SHX Text
50.88
AutoCAD SHX Text
51.12
AutoCAD SHX Text
51.53
AutoCAD SHX Text
51.52
AutoCAD SHX Text
51.55
AutoCAD SHX Text
51.49
AutoCAD SHX Text
51.83
AutoCAD SHX Text
51.84
AutoCAD SHX Text
52.01
AutoCAD SHX Text
52.09
AutoCAD SHX Text
51.54
AutoCAD SHX Text
51.51
AutoCAD SHX Text
51.52
AutoCAD SHX Text
50.13
AutoCAD SHX Text
50.02
AutoCAD SHX Text
TK49.86
AutoCAD SHX Text
LIP49.68
AutoCAD SHX Text
49.93
AutoCAD SHX Text
50.06
AutoCAD SHX Text
52.14
AutoCAD SHX Text
51.69
AutoCAD SHX Text
51.62
AutoCAD SHX Text
51.60
AutoCAD SHX Text
51.67
AutoCAD SHX Text
51.62
AutoCAD SHX Text
51.63
AutoCAD SHX Text
51.53
AutoCAD SHX Text
51.69
AutoCAD SHX Text
51.86
AutoCAD SHX Text
52.05
AutoCAD SHX Text
52.30
AutoCAD SHX Text
52.08
AutoCAD SHX Text
52.09
AutoCAD SHX Text
52.14
AutoCAD SHX Text
52.20
AutoCAD SHX Text
52.21
AutoCAD SHX Text
52.12
AutoCAD SHX Text
52.53
AutoCAD SHX Text
52.56
AutoCAD SHX Text
52.54
AutoCAD SHX Text
52.54
AutoCAD SHX Text
52.63
AutoCAD SHX Text
52.60
AutoCAD SHX Text
53.01
AutoCAD SHX Text
53.04
AutoCAD SHX Text
53.08
AutoCAD SHX Text
53.01
AutoCAD SHX Text
52.99
AutoCAD SHX Text
SWO IL49.90
AutoCAD SHX Text
SWO IL49.81
AutoCAD SHX Text
GRATE SL51.44 IL51.25
AutoCAD SHX Text
DISH DRAIN
AutoCAD SHX Text
IL51.38
AutoCAD SHX Text
IL51.41
AutoCAD SHX Text
FL51.48
Page 23: ‘Site and Soil Evaluation’ Report Template

ENVIROTECH PTY. LTD.

22

Appendix II –Site Photos

Page 24: ‘Site and Soil Evaluation’ Report Template

ENVIROTECH PTY. LTD.

23

Screening Tumbler onsite

Approximately 3m high concrete wall along the property boundary of the site

Page 25: ‘Site and Soil Evaluation’ Report Template

ENVIROTECH PTY. LTD.

24

Front-end Loader onsite

Mini excavator onsite

Page 26: ‘Site and Soil Evaluation’ Report Template

ENVIROTECH PTY. LTD.

25

Appendix III –Sound Level out of subject user manual for a Portafill 4000T

Page 27: ‘Site and Soil Evaluation’ Report Template

ENVIROTECH PTY. LTD.

26