18
21/06/2016 Page 1 MTR Corporation Harbourfront Commission 21 June 2016 Shatin to Central Link (SCL) Progress Update

Shatin to Central Link (SCL) Progress Update · 6/21/2016  · MTR Corporation 21/06/2016 Page 1 Harbourfront Commission 21 June 2016 Shatin to Central Link (SCL) Progress Update

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

  • 21/06/2016 Page 1MTR Corporation

    Harbourfront Commission21 June 2016

    Shatin to Central Link (SCL) Progress Update

  • Purpose of Today’s Briefing

    • Update on the latest progress of SCL

    • Current land requirement for SCL construction

    Page 2

  • Scope of SCL

    Interchange Station

    East West Corridor

    • Concession approach – owned by the Government and MTR has been entrusted with its planning, design and construction

    • Overall length: 17km

    • Comprising two railway corridors:

    East West Corridor (11km)• SCL (Tai Wai to Hung Hom Section)• Ma On Shan Line• West Rail LineTarget completion in 2019

    North South Corridor (6km)• SCL (Hung Hom to Admiralty Section)• East Rail LineTarget completion in 2021

    North South Corridor

    Page 3

  • > 7000 >70

    Day after night…

    Night after day…

    SCL is progressing in full swing

    Covering 14 districtsfrom NT to HK Island

    Works sitesworkers

    East West Corridor completion

    North South Corridor completion

    Construction commencement

    Page 4

  • Page 5

    East West Corridor (over 60% complete) Topped out 3 stations (Hin Keng,

    Diamond Hill, Kai Tak) Tunneling works nearly completed

    North South Corridor (over 20% complete) First tunnel boring machine started Exhibition Station construction commenced

    Hin Keng Station

    Tunnel under Lion RockTunnel boring machine

    through Ma Tau Wai Station

  • Page 6

    SCL Progress in Kai Tak Area• Archaeological discoveries at To Kwa Wan Station site resulted in a delay

    of 11 months for tunneling and station works• Station structure under construction; tunnel breakthrough in 2nd half 2016

    To Kwa Wan Station and tunnel works sites

    To Kwa Wan Station and tunnel works sites

  • Page 7

    SCL Progress in Kai Tak Area

    Kai Tak StationKai Tak Station

    • Kai Tak Station was topped out• Adjoining tunnel structures nearly completed

  • Page 8

    Land Requirement in Kai Tak Area

    • Major civil structures gradually completed

    • Works sites are being returned to Government progressively starting from mid-2016

    Kai Tak StationTo Kwa

    Wan Station

    Land required for SCL construction

    SCL tunnels (East West Corridor)

  • Page 9

    SCL Progress in Hung Hom Area• Hung Hom Station

    2nd Phase Concourse Modification in progress New station box structure under construction

    • Adjoining tunnel structures under construction

    Renovated concourse at Hung Hom StationRenovated concourse at Hung Hom Station

    Tunnels linking Cross Harbour Section at Hung Hom

    Tunnels linking Cross Harbour Section at Hung Hom

  • Land requirement in Hung Hom Area

    • Land requirement unchanged

    • The existing flyover footpath connecting Tsim Sha Tsui Promenade to Hung HomPromenade remains operational during the entire construction period.

    Hung HomStation

    Page 10

    Land required for SCL construction

    SCL tunnels (East West Corridor)

    SCL tunnels (North South Corridor)

    Tsim ShaTsui East

    Existing flyover footpath remains operational Existing flyover footpath

  • Page 11

    SCL Progress in Causeway Bay Area• Construction works in Causeway Bay Typhoon Shelter (CBTS) in

    progress

    • First tunnel boring machine (TBM) launched. Mining from CBTS towards Exhibition Station

    TBM mining towards Exhibition StationTBM mining towards Exhibition Station Causeway Bay Typhoon ShelterCauseway Bay Typhoon Shelter

    CWB works

    SCL works

  • Page 12

    SCL Progress in Wan Chai East Area

    Fleming RoadFleming Road

    WDIIworks site

    WDIIworks site

    SCL works site

    SCL works site

    • First major temporary traffic diversion at Convention Avenue implemented to facilitate construction of Exhibition Station

    Exhibition Station footprint

  • Page 13

    SCL Progress in Wan Chai West Area

    • Construction of shafts and walls for tunnels from Exhibition Station to Admiralty Station in progress

    SCL works siteSCL works site

    WDII works site

    WDII works site

  • Page 14

    Optimized Land Requirement on HK Island

    Causeway Bay Typhoon Shelter

    Causeway Bay Typhoon Shelter

    Causeway Bay Typhoon Shelter

    • Optimized land requirement on HK Island with reduction of 2.6 hectares

    • Sites to be taken up and returned progressively

    • Coordinate with development plans under the Urban Design Study for HarbourfrontAreas

    Land no longer required

    Current land requirement

    SCL tunnels (North South Corridor)

  • WDII works site

    WDII works site

    SCL works site

    SCL works site

    Traffic Diversion in stages in Wan Chai North

    Exhibition Station footprint

    Land to be handed over to SCL for traffic diversion in stages and Road P2 construction

    Page 15

  • Pedestrian Connectivity Maintained At All Times

    Page 16

    Star Ferry Pier

    To Golden Bauhinia Square

    Connectivity between inland and waterfront

    maintained during and after construction

  • Page 17

    Summary

    1. East West Corridor: Construction in full swing. Target completion in 2019North South Corridor: Works in early stage. Target completion in 2021

    2. Harbour Planning Principles have been taken into account:

    Land intake needed for construction works minimized

    Land requirement periodically reviewed to strive for returning the land progressively

    Maintain connectivity to waterfront with clear signage and favourable pedestrian environment during and after construction

    Keep the public and Harbourfront Commission posted of the SCL works progress and land requirement

    3. On-going coordination with development plans under the Urban Design Study for the Wan Chai North and North Point Harbourfront Areas

  • Page 18

    Thank You