21/06/2016 Page 1MTR Corporation
Harbourfront Commission21 June 2016
Shatin to Central Link (SCL) Progress Update
Purpose of Today’s Briefing
• Update on the latest progress of SCL
• Current land requirement for SCL construction
Page 2
Scope of SCL
Interchange Station
East West Corridor
• Concession approach – owned by the Government and MTR has been entrusted with its planning, design and construction
• Overall length: 17km
• Comprising two railway corridors:
East West Corridor (11km)• SCL (Tai Wai to Hung Hom Section)• Ma On Shan Line• West Rail LineTarget completion in 2019
North South Corridor (6km)• SCL (Hung Hom to Admiralty Section)• East Rail LineTarget completion in 2021
North South Corridor
Page 3
> 7000 >70
Day after night…
Night after day…
SCL is progressing in full swing
Covering 14 districtsfrom NT to HK Island
Works sitesworkers
East West Corridor completion
North South Corridor completion
Construction commencement
Page 4
Page 5
East West Corridor (over 60% complete) Topped out 3 stations (Hin Keng,
Diamond Hill, Kai Tak) Tunneling works nearly completed
North South Corridor (over 20% complete) First tunnel boring machine started Exhibition Station construction commenced
Hin Keng Station
Tunnel under Lion RockTunnel boring machine
through Ma Tau Wai Station
Page 6
SCL Progress in Kai Tak Area• Archaeological discoveries at To Kwa Wan Station site resulted in a delay
of 11 months for tunneling and station works• Station structure under construction; tunnel breakthrough in 2nd half 2016
To Kwa Wan Station and tunnel works sites
To Kwa Wan Station and tunnel works sites
Page 7
SCL Progress in Kai Tak Area
Kai Tak StationKai Tak Station
• Kai Tak Station was topped out• Adjoining tunnel structures nearly completed
Page 8
Land Requirement in Kai Tak Area
• Major civil structures gradually completed
• Works sites are being returned to Government progressively starting from mid-2016
Kai Tak StationTo Kwa
Wan Station
Land required for SCL construction
SCL tunnels (East West Corridor)
Page 9
SCL Progress in Hung Hom Area• Hung Hom Station
2nd Phase Concourse Modification in progress New station box structure under construction
• Adjoining tunnel structures under construction
Renovated concourse at Hung Hom StationRenovated concourse at Hung Hom Station
Tunnels linking Cross Harbour Section at Hung Hom
Tunnels linking Cross Harbour Section at Hung Hom
Land requirement in Hung Hom Area
• Land requirement unchanged
• The existing flyover footpath connecting Tsim Sha Tsui Promenade to Hung HomPromenade remains operational during the entire construction period.
Hung HomStation
Page 10
Land required for SCL construction
SCL tunnels (East West Corridor)
SCL tunnels (North South Corridor)
Tsim ShaTsui East
Existing flyover footpath remains operational Existing flyover footpath
Page 11
SCL Progress in Causeway Bay Area• Construction works in Causeway Bay Typhoon Shelter (CBTS) in
progress
• First tunnel boring machine (TBM) launched. Mining from CBTS towards Exhibition Station
TBM mining towards Exhibition StationTBM mining towards Exhibition Station Causeway Bay Typhoon ShelterCauseway Bay Typhoon Shelter
CWB works
SCL works
Page 12
SCL Progress in Wan Chai East Area
Fleming RoadFleming Road
WDIIworks site
WDIIworks site
SCL works site
SCL works site
• First major temporary traffic diversion at Convention Avenue implemented to facilitate construction of Exhibition Station
Exhibition Station footprint
Page 13
SCL Progress in Wan Chai West Area
• Construction of shafts and walls for tunnels from Exhibition Station to Admiralty Station in progress
SCL works siteSCL works site
WDII works site
WDII works site
Page 14
Optimized Land Requirement on HK Island
Causeway Bay Typhoon Shelter
Causeway Bay Typhoon Shelter
Causeway Bay Typhoon Shelter
• Optimized land requirement on HK Island with reduction of 2.6 hectares
• Sites to be taken up and returned progressively
• Coordinate with development plans under the Urban Design Study for HarbourfrontAreas
Land no longer required
Current land requirement
SCL tunnels (North South Corridor)
WDII works site
WDII works site
SCL works site
SCL works site
Traffic Diversion in stages in Wan Chai North
Exhibition Station footprint
Land to be handed over to SCL for traffic diversion in stages and Road P2 construction
Page 15
Pedestrian Connectivity Maintained At All Times
Page 16
Star Ferry Pier
To Golden Bauhinia Square
Connectivity between inland and waterfront
maintained during and after construction
Page 17
Summary
1. East West Corridor: Construction in full swing. Target completion in 2019North South Corridor: Works in early stage. Target completion in 2021
2. Harbour Planning Principles have been taken into account:
Land intake needed for construction works minimized
Land requirement periodically reviewed to strive for returning the land progressively
Maintain connectivity to waterfront with clear signage and favourable pedestrian environment during and after construction
Keep the public and Harbourfront Commission posted of the SCL works progress and land requirement
3. On-going coordination with development plans under the Urban Design Study for the Wan Chai North and North Point Harbourfront Areas
Page 18
Thank You