Session ‘ Effect of FiT on small hydro ’ Adrian Loening Director: M ór Hydro Ltd. M ór Hydro. Micro Hydro development; Investor Technical Design Project Management Due Diligence 2012 Workload 3 Schemes under construction 1 Scheme refurbishment 2 Schemes in development - PowerPoint PPT Presentation
Citation preview
Session
‘Effect of FiT on small hydro’
Adrian Loening
Director: Mór Hydro Ltd
Mór Hydro
Micro Hydro development; Investor Technical Design Project Management Due Diligence
2012 Workload 3 Schemes under construction 1 Scheme refurbishment 2 Schemes in development
Developed from Carbon Trade Ltd – 20 years experience in biogas and hydro development
Feed in Tariff
So far so good!
Band (kW)Current
generation tariffs (p/kWh)
Consultation tariffs from Oct 2012 (p/kWh, 2012 prices)
Final tariffs from 1 Dec
2012 (p/kWh, 2012 prices)
Community energy tariff
=<15 21.9 21 21 21
>15=<100 19.6 19.7 19.6 19.6
>100=<500 12.1 12.1 15.5 15.5
>500=<2000 12.1 12.1 12.1 12.1
Feed in Tariff
Degression Proposal – 5% reduction on;
April 2014 OR when capacity is 55MW April 2015 OR when capacity is 73MW
Descision Baseline degression of 5% per year from 2014 Predicted Annual Deployment Lower degression of 2.5% if less than 75% of Predicted Higher degression of 10% if greater than 150% of
Predicted Even greater degression of 20% of greater than 300% of
Predicted
Feed in Tariff - Degression
Predicted deployment is 16.66MW annually
Degression band
2.5% 5% 10% 20%
≤12.5MW >12.5 – 25.0MW
>25.0 – 50.1MW
>50.1MW
Feed in Tariff - Degression
BHA Annual Conference, 2012
When is Degression triggered? For <50kW sum of DNC Recorded on MCS Database For >50kW sum of TIC recorded on Renewables and
CHP database Note: in neither case is a project necessarily
accredited for FiTs. Early trigger also if deployment exceeds 2/3rds of
annual predicted in first 6 months of each year
Feed in Tariff – Pre-accrediation
BHA Annual Conference, Glasgow
As promised Hydro schemes can be pre-accredited for FiTs Requires;
Planning Consent CAR Licence Acceptance of a ‘Firm’ Grid connection offer
What is a ‘firm’ grid connection offer? Without transmission constraints? Paid the deposit?
Pre-accredited projects count towards degression triggers
Feed in Tariff – Pre-accreditation
BHA Annual Conference, 2012
Projects must pre-accredit by 1st Jan in any year Pre-accreditation between 1st Jan and 31st Mar are
given FiT rate for the following year (inc. any degresssion)
Do not yet know the exact process of pre-accreditation but assume ROO-FIT form minus.
Pre-accreditation lasts for 2 years Pre-accreditation may be withdrawn Decrease in capacity allowed – increase is not Pre-accredited projects count towards degression
triggers
Pre-accrediation
BHA Annual Conference, 2012
Page 108 para. 4
“Tariff lifetimes will apply from the eligibility date.”
Page 108 para. 5
“Tariff lifetimes will still apply from the installation’s commissioning date”
Is it a better FiT?
BHA Annual Conference, Glasgow
So has this made the FiT better or easier? Yes and No! More games to play! Some certainty / some confusion
Pre-accreditation triggers degression So we don’t want lots of pre-accredited projects Do cancelled pre-accredited projects ‘un-trigger’
degression?
Example:
Example:
BHA Annual Conference, 2012
Year 2014 Installed capacity in year is at 22.6MW ‘Abighydro’ project 3.5 MW additional is pre-accredited
before 1st Jan 2015 Year 2015
Tariff reduced by 10% instead of 5% A further 16MW Accredited / Pre-accredited during
year Year 2016
Tariff reduced by further 5%
Example
BHA Annual Conference, Glasgow
2016 – ‘Abighydro’ is cancelled or pre-accreditation lapses
16MW of ‘2015’ vintage hydro have lost 5% of FiT payments.
@40%load factor and £115/MWh FiT around £322K has been lost through no fault.
My guess is there will be no correction for this.
New Questions / New Tricks?
BHA Annual Conference, Glasgow
What happens if you pre-accredit in one band but final commissioned size is lower band? Cancel pre-accreditation and re-accredit – lose the
pre-accreditation benefit What happens at two year limit without
commissioning? Cancel pre-accreditation and re-apply for pre-
accreditation Better still: Pre-accredit on 1st Jan, cancel and re-pre-
accredit on 31st Dec Both potentially adds to degression twice!
Old Tricks
BHA Annual Conference, 2012
Has the new FiT band stopped down-sizing? Some projects >500kW are being downsized No projects = 100kW have been upsized?
Unless you know better!
Is the new FiT band a good thing? Broadly yes – it is what we have been asking for
Does the new FiT mechanism solve uncertainty? Not for marginal projects Not for ‘long development’ projects
Now for something completely different
BHA Annual Conference, Glasgow
Scottish Government targets for low carbon transport
Many Hydro projects are near public roads (typically at bridges)