Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
SENIOR DESIGN I05009 AIRBORNE SENSING PLATFORM
PRELIMINARY DESIGN REVIEW2/18/05
JONATHAN FENTZKE – TEAM LEAD
JOSEPH O’DAY – MECHANICAL LEAD
ERIC GREENWOOD – AIRFRAME LEAD
JOHN PRIESTLY – RF LEAD
JEAN LAURIN – VISION LEAD
2
EXECUTIVE SUMMARY
This preliminary design report outlines the progress made by the senior design team on
completion of an airborne sensing platform for the Center of Imaging Science.
Recently the government and private industry alike have begun to utilize Unmanned Aerial
Vehicles (UAV) for reconnaissance scenarios both on and off the battlefield. While UAV
technology exists for a wide range of military applications, there is a need by the US Forest
service for UAV technology capable of remote sensing tasks related to wild fires. The goal of
this senior design project is to design and build an airborne sensing platform test bed that will
allow the Center for Imaging Science to display there remote sensing technology.
The team utilized design and analysis methods outlined during the design project
management class and the Senior Design I course to design the airborne sensing platform using a
logical progression of steps. This report discusses the complete process in detail.
First, the team met with the project sponsor and determined the needs of the sponsor. This
information is captured in detail in the Recognize and Quantify the Need section of the PDR.
This section specifically explains the mission statement for the project. It also discusses the
information collected by the team to help them understand the scope of the project and the exact
needs of the sponsor.
The next section involves the concept development for the airborne sensing platform. The team
began by researching current technology available for UAV development and created subsystem
concepts based on the research conducted. After the initial team concept development, the team
conducted trade studies to determine the feasibility of individual subsystems. This information
was presented to the sponsor. Based on sponsor feedback, overall system concepts were
finalized. The Feasibility section of the PDR discusses this information. Pursuant to the concept
3
development with the sponsor, the team in conjunction with the sponsor determined a set of
design objectives and specifications. This information guided the overall system selection and
design parameters to meet sponsor requirements and define measures of project success.
The team took into consideration all the aforementioned information when completing an overall
system design for the airborne sensing platform. This final design information is found in the
Analysis and Synthesis section of the PDR. It contains detailed drawings and pertinent
calculations to demonstrate the overall system design and implementation, as well as subsystem
configurations. The final design is an airborne sensing platform capable of piloted and
autonomous control of the aircraft that provides real time video and sensor feedback to the pilot.
At this time, the team has completed the major design portion of the project. The task to be
undertaken during the spring session of Senior Design II is system integration and testing. As
Senior Design II begins, the team plans to test components as they arrive from vendors and
complete the necessary machining and circuitry associated with the systems designed. Slight
design modification will occur as needed and systems integration into the airframe will then
begin. The completed prototype will undergo testing in preparation for demonstration to the
Center for Imaging Science at the end of Senior Design II in May.
4
TABLE OF CONTENTSTable of Contents ............................................................................................................................. 5 Table of Figures ............................................................................................................................... 8 1.0 Team Organization and Work Breakdown Structure ................................................................ 9 2.0 Recognize and Quantify Need ................................................................................................. 10
2.1 Mission Statement ................................................................................................................ 10 2.2 Project Description ............................................................................................................... 10 2.3 Scope Limitations ................................................................................................................ 11 2.4 Key Business Goals ............................................................................................................. 11 2.5 Primary Market .................................................................................................................... 12 2.6 Secondary Market ................................................................................................................ 12 2.7 Innovation Opportunities ..................................................................................................... 12 2.8 Formal Statement of Work ................................................................................................... 13
3.0 Concept Development .............................................................................................................. 14 3.1 Communication ................................................................................................................... 14
3.1.1 Wireless Communication Scheme ................................................................................ 14 3.2 Guidance and Telemetry System ......................................................................................... 15
3.2.1 Vision Guidance System ............................................................................................... 16 3.2.2 Positioning/Telemetry System ...................................................................................... 17
3.3 Control ................................................................................................................................. 19 3.3.1 Piloted Control .............................................................................................................. 19 3.3.2 Partial Autonomous Control Systems ........................................................................... 20 3.3.3 Fully Autonomous System ............................................................................................ 22
3.4 Sensor Equipment ................................................................................................................ 23 3.4.1 Temperature Sensor ...................................................................................................... 23 3.4.2 Pressure Sensor ............................................................................................................. 23
3.5 Base Station ......................................................................................................................... 23 3.5.1 Base Station Configuration ........................................................................................... 24 3.5.2 Antenna ........................................................................................................................ 25
4.0 Feasibility ................................................................................................................................. 26 4.1 Communication .................................................................................................................... 26
4.1.1 Wireless Communication .............................................................................................. 27 4.2 Guidance and Telemetry System ......................................................................................... 28
4.2.1 Vision Guidance System ............................................................................................... 28 4.2.1.1 Camera Packaging Scheme ........................................................................................ 28 4.2.2 GPS ............................................................................................................................... 30
4.3 Control ................................................................................................................................. 31 4.3.1 Radio Control ................................................................................................................ 32 4.3.2 Partially Autonomous Control System ......................................................................... 33
4.3 System Level Feasibility ...................................................................................................... 35 4.3.1 Piloted Control .............................................................................................................. 37 4.3.2 Autonomous Control Capability ................................................................................... 37 4.3.3 Commercially Available Complete System Solutions .................................................. 39
4.4 Overall System Selection ..................................................................................................... 39 5.0 Objectives and Specifications .................................................................................................. 39
5
5.1 Performance Specifications ................................................................................................. 40 5.2 Design and Implementation Specifications ......................................................................... 40
5.2.1 Platform Durability ...................................................................................................... 40 5.2.2 Fuselage ....................................................................................................................... 41 5.2.3 Dimension ..................................................................................................................... 41
5.3 Stability and Control ............................................................................................................ 41 5.3.1 Control Surfaces ............................................................................................................ 41
5.4 Electrical Systems ................................................................................................................ 42 5.4.1 Video ............................................................................................................................. 42 5.4.2 Global Positioning System (GPS) ................................................................................. 42 5.4.3 Transceiver .................................................................................................................... 42 5.4.4 Base Station .................................................................................................................. 43 5.4.5 Batteries ........................................................................................................................ 43 5.4.6 Possible Platform Features ............................................................................................ 43 5.4.7 Controller ...................................................................................................................... 45 5.4.8 Controller Receiver ....................................................................................................... 45 5.4.9 Onboard Processing ..................................................................................................... 45
5.5 Design Practices ................................................................................................................... 46 5.6 Safety Issues ......................................................................................................................... 47 5.7 Launch .................................................................................................................................. 47 5.8 Pilot ...................................................................................................................................... 47 5.9 Deliverables ......................................................................................................................... 48 5.10 Overall Period of Performance and Schedule .................................................................... 48
6.0 Design Analysis and Synthesis ................................................................................................ 49 6.1 Airframe Analysis ................................................................................................................ 49
6.1.1 #05008 Airframe Stability Analyses and Redesign ...................................................... 49 6.1.3 #05008 Airframe Weight Analysis - Cg ....................................................................... 51 6.1.2 Senior Telemaster Performance Analysis ..................................................................... 51
6.2 Motor Selection and Analysis .............................................................................................. 54 6.3 Structural Design and Analysis ............................................................................................ 55
6.3.1 Structural Design .......................................................................................................... 55 6.3.2 Structural Analysis ........................................................................................................ 57 6.2.4 Camera Mounting System Design ................................................................................ 65
6.4 Power Consumption ............................................................................................................. 65 6.5 Battery Selection .................................................................................................................. 65 6.6 Vision Guidance System Design and Analysis .................................................................... 66
6.6.1 Camera Design .............................................................................................................. 66 6.6.2 RF Link Budget Analysis .............................................................................................. 68 6.6.3 Communications System Design .................................................................................. 69
6.7 Telemetry and Stability Augmentation System Design and Analysis ................................. 70 6.7.1 Control .......................................................................................................................... 70
6.8 Launch .................................................................................................................................. 71 7.0 Future Plans ............................................................................................................................. 71 8.0 Budget ...................................................................................................................................... 72 9.0 Conclusion ............................................................................................................................... 72 Appendix A – Airframe Stability calculations ............................................................................... 74
6
Takeoff Performance Equations Used ....................................................................................... 74 Stability & Control Equations Used .......................................................................................... 76
Appendix B – Cg Calculations ...................................................................................................... 77 Appendix C – Detailed structural drawings ................................................................................... 79 Appendix D – Path loss Calculations ............................................................................................. 84 Appendix E – Power Budget Analysis ........................................................................................... 87 Appendix G – Bill of Materials ..................................................................................................... 90
7
TABLE OF FIGURESFigure 1: Work Breakdown Structure.............................................................................................9Figure 2: On-Board Communication System Architecture.......................................................... 15Figure 3: Vision Guidance System Diagram................................................................................ 16 Figure 4: Table of Communication Systems Trade Study Results.............................................. 28Figure 5: Table of Camera Selection Trade Study Results...........................................................30Figure 6: Table of GPS Trade Study Results................................................................................31 Figure 7: Table of Radio Controller Trade Study Results........................................................... 33Figure 8: Table of Stability Augmentation System Trade Study Results.....................................34Figure 9: Table of Autonomous Systems Trade Study Results.................................................... 35Figure 10: Table of System Level Feasibility Study.................................................................... 37Figure 11: Plot of CL3/2 / CD vs. Speed......................................................................................53Figure 12: CL / CD vs. Speed.......................................................................................................53Figure 13: Tabulated results of Telemaster performance analysis............................................... 54Figure 14: Rail Cage Assembly.................................................................................................... 56
Figure 15: Table of total weights.................................................................................................57Figure 16: Worst-case loading scenario........................................................................................58Figure 17: Decoupled stress scenario........................................................................................... 59Figure 18: Cross-section dimensions and section divisions......................................................... 59Figure 19: Centroid location and axis placement......................................................................... 60
Figure 20: Table of calculated values........................................................................................... 62Figure 21: Location of neutral axis...............................................................................................62Figure 22: Wiring Diagram of Camera System............................................................................ 68Figure 23: Vision Guidance System Diagram.............................................................................. 68Figure 24: Control System Diagram.............................................................................................70Figure 25: Projected Schedule...................................................................................................... 72
8
1.0 TEAM ORGANIZATION AND WORK BREAKDOWN STRUCTURE
In order to conduct the design and analysis efficiently of the project subsystems it was
necessary to divide the team into subgroups based on area of expertise and previous experience.
The team was comprised of both mechanical and electrical engineers with a skill set that bridged
the gap between both disciplines. Most members of the team have some familiarity with design
and analysis outside their core area of study, which helped considerably with concept
development and other tasks. The three subgroups and there associated members can be seen
below in Figure 1.
Figure 1: Work Breakdown Structure
Although the team worked together to complete assigned tasks, the subgroups were divided
to provide the most efficient means for completing the project on time and under budget.
Airframe design and analysis was mainly concerned with the structural integrity and handling
qualities of the aircraft to be used in the project. Mechanical design and analysis centered on the
hardware mounting scheme, vibration damping, dynamic loading of the aircraft, and control of
the aircraft. The electrical portion centered on the communication system, vision guidance, and
power needs of the project.
9
Airframe ElectricalMechanical
Eric Greenwood Joseph O’Day
Jonathan Fentzke
Jean Laurin
John Priestly
0500
9
2.0 RECOGNIZE AND QUANTIFY NEED
2.1 Mission Statement
The purpose of the student design team is to design and build a guidance and navigation
system for an Unmanned Aerial Vehicle (UAV) for the Center for Imaging Science. This project
will produce a passively stable airborne sensing platform test bed with a vision guidance flight
control system, as well as to integrate onboard sensors allowing long-range remote sensing tasks
to be completed.
2.2 Project Description
An interdisciplinary team of senior RIT engineering students will complete a fully
functional airborne sensing platform test bed with assistance from the Center for Imaging
Science and the Mechanical and Electrical departments at RIT. The airborne sensing platform
utilizes an onboard guidance and navigation system comprised of video and telemetry
subsystems. These systems allow a pilot to complete remote sensing tasks at a maximum
altitude of up to 1,000 feet at a maximum range of 2 miles away from the pilot’s location. The
platform can also execute mission objectives autonomously based on its telemetry hardware.
The platform is capable of carrying a modular 3 lb payload provided by the Center for Imaging
Science in addition to the onboard equipment and sensors needed by the pilot to complete a
successful mission.
The platform gives real time continuous feedback to the base station from the video
camera, telemetry, and other sensors to allow the pilot to navigate the airborne sensing platform
beyond the pilot’s line of sight. Using GPS waypoint information, the platform can also target
an objective area while outside the line of sight of the pilot. Sensors for temperature, pressure,
10
battery life, as well as the onboard processing allow the pilot to avoid catastrophic crashes and
remote sensing conditions that may be hazardous to onboard equipment or the platform itself.
The platform has been efficiently designed both electronically and aerodynamically to
provide a launch and loiter condition that allows it to carry out a maximum mission time of one
hour. Upon completion of the remote sensing task, the platform can be navigated back to the
base station and landed in a manor that preserves the integrity of the onboard equipment and the
platform structure.
2.3 Scope Limitations
The platform is limited in size and carrying capacity. It shall be designed to carry the
Center for Imaging Science payload and a navigation system. The platform must be portable and
provide a design that allows for future upgrades. Consideration will be given to providing power
and mounting space for as much additional equipment as possible. This initial airborne sensing
platform shall be a test bed for the Center for Imaging Science.
2.4 Key Business Goals
The project must be completed within the $10,000 budget and before the completion of the
academic year in May 2005. A working prototype shall be demonstrated to the Center for
Imaging Science. The prototype shall provide a means for the Center of Imaging Science to
conduct remote sensing experiments and continue further development with future senior design
projects.
11
2.5 Primary Market
This project provides a relatively small and compact means of carrying out remote
sensing tasks related to forest fires. Because it is being designed and built to meet fire detection
needs, the primary market is the U.S. Forest Service and Center of Imaging Science. These
groups can exploit the platforms capabilities to display there new remote sensing technologies
currently under development.
2.6 Secondary Market
Recently the advent of autonomous technology has sparked a sharp increase in market
demand for unmanned aerial vehicles. The intelligence community including, but not limited to,
the Central Intelligence Agency, Department of Defense, and branches of the armed services are
all interested in acquiring UAV technology for reconnaissance and communication. The
airborne sensing platform is a perfect candidate for mid-range reconnaissance and target tracking
due to its relatively small size, payload capacity, and range.
In addition to military applications, the airborne sensing platform can be modified for use
in the commercial sectors. Its applications range for urban fire-fighting capabilities to traffic
detection and weather service applications. The modular design and large payload space allow
for quick adaptation to meet consumer demands.
Thus this product can be marketed to both commercial and government consumers as a
means of additional funding to the Center for Imaging Science.
2.7 Innovation Opportunities
Due to the nature of the project, the opportunity for innovation is high. The platform is
designed to modified and upgraded with ease. The additional payload capacity allows for
12
additional sensors to be placed on board. This allows for innovation in the areas of sensor design
and packaging. Sophisticated weather sensors could be placed onboard allowing for scientific
research on weather conditions and patterns. Also, biological or chemical sensors could be
implemented to test for hazardous materials over a given area. This has applications in both
military and agricultural settings. Swappable camera packages could be implemented allowing
for spectral analysis via infra-red, ultraviolet, or other camera configurations. In addition, the
configuration of the control system allows for continual modification and improvement. Thus,
dynamic stability augmentation research and control theory applications can be implemented.
This would lead to a great deal of progress in completing autonomous remote sensing tasks for
students and faculty at RIT, as well as outside interests in the commercial and defense
communities.
2.8 Formal Statement of Work
The main objective of this project is to produce an airborne sensing test bed for the
Center of Imaging Science. The design will allow for platform portability while providing ample
space in the design envelope to allow for future upgrades and modifications. The platform will
house the Center for Imaging Science payload, as well as guidance and telemetry equipment. It
will have the capability to perform remote sensing tasks at distances at a maximum of two miles
away from the pilot location and loiter at altitudes of less than 1,000 feet. The system must
provide real time feedback to the pilot about the location and attitude of the platform to help
ensure mission success.
13
3.0 CONCEPT DEVELOPMENT
3.1 Communication
After establishing the sponsor requirements, we began to develop concepts to manage the
communication needs for the airborne sensing platform. A very crucial design aspect of the
overall system architecture is the ability of the embedded system, on the plane, to communicate
real-time information back to the base station. The communication system must have the ability
to transmit real-time video and telemetry.
3.1.1 Wireless Communication Scheme
In order to meet the range requirements, and due to the nature of the airborne sensing
platform, a radio frequency (RF) wireless communication system best fit this application. An
analysis was performed to determine the RF frequency range best suited for this application. The
parameters that guided this study were data throughput, typical power consumption, free space
path loss, interference rejection, cable/connector loss, and freznel zone requirements. The main
frequencies under consideration were 900 MHz, 2.4 GHz and 5.8 GHz. Once we identified
several frequency ranges, we then developed two basic system architectures that could be
implemented to meet the needs of the communications system. The two architectures developed
were (1) a dedicated transmitter for video feedback and a separate telemetry system, and (2)
combining the telemetry system and video feedback system by utilizing the audio channel on a
video transmitter. The first architecture incorporates one transmitter/receiver combination to
send video feedback to the base station. The aircraft supports the transmitter and the associated
antenna, and the base station supports the receiver and its associated antenna. The video
transmitter is specifically designed for video, typically interfacing with a camera via standard
14
coaxial connectors used in National Television System Committee (NTSC) systems. This
architecture also includes a separate transmitter/receiver combination, configured similar to
video communication above, as a telemetry system. The second architecture developed attempts
to minimize the number of transmitters supported by the aircraft. To do this the system utilizes
the audio channel provided by a standard wireless video transmitter to send telemetry data back
to the base station. Byonics offers the Tiny Track product, which encodes GPS data on the audio
output of a camera. The base station then utilizes a standard sound card and a software package,
such as AGW Packet Engine (AGWPE), to extract the data received over the audio channel.
Considering our application does not require sound feedback, this may be a viable option.
Audio In
Video In
TTSMT Encoder
Camera
Telemetry Data
Figure 2: On-Board Communication System Architecture
3.2 Guidance and Telemetry System
In order to complete remote sensing tasks successfully, it is vital to utilize a guidance and
navigation system onboard the airborne sensing platform. This system provides navigational
cues to the base station and pilot. The concepts described here can be used as stated alone or in
concert to provide varying levels of feedback and upgradeability. They range from stand-alone
vision guidance to fully autonomous flight options.
15
3.2.1 Vision Guidance System
The requirement of real-time piloted control at long distances necessitates a platform with
a vision guidance system. The vision guidance systems allows the pilot to maintain absolute
reference to the horizon and determine local topographic information to aid in control and
attitude determination when the airborne sensing platform is not in the pilot’s line of sight.
3.2.1.1 Camera Packaging Schemes
The team developed two primary concepts for the ways to implement a vision guidance
system. The first concept involved a commercially available system consisting of a video
camera and a transmitter packaged together. The alternative concept involved a stand-alone
camera and a separate transmitter. Based on physical dimension constraints and integration
difficulty the team elected to pursue a stand-alone camera and transmitter, allowing for
maximum design flexibility and upgradeability as well as ease of system integration. Figure 3
represents the system diagram for vision guidance.
ImageryCamera Transmitter Reciever Base Station Pilot
Figure 3: Vision Guidance System Diagram
3.2.1.2 Camera Options
Camera units are commercially available with a large array of attributes. The two main
types of imagers available for video cameras are Charge Coupled Device (CCD) and transistor
type Complementary Metal-Oxide Semiconductor (CMOS). CCD imagers provide a more
accurate picture than CMOS imagers due to their superior electronic shuttering and smaller
amount of noise within the imager.
16
Most cameras are available in black and white or color. Color cameras generally require
more power than their black and white counterparts. The team discussed a concept involving
night vision and infrared. However, at this time the sponsor deems them to be outside of the
scope of this project. They are possible upgrades for future designs.
A concept for a camera that comes capable with an audio channel developed from a
desire to encode and transmit telemetry or other sensor data on that channel. Another important
feature considered was the minimum amount of light that will produce adequate pictures, or
LUX. Cameras with a small LUX can operate with less light and thus are more desirable. In
addition, the format of the camera output signal is important. To alleviate integration concerns
the output should be the American standard, NTSC. This will facilitate integration with the
communication system and allow the base station to easily convert and display the video signal.
3.2.2 Positioning/Telemetry System
The two mile range requirement drives the need for some type of telemetry data from
onboard the plane to be transmitted back to the base station once the plane is beyond line of
sight. For a successful flight and adherence to the defined mission route, the pilot would need to
know where the plane is, where it is going, and how fast it is getting there. To this end, some
necessary attributes of a positioning telemetry system will be latitude, longitude, altitude,
headway, speed, and time.
Brainstorming resulted in five feasible options. Commercially available Original
Equipment Manufacturers (OEM) modules and engines exist for providing telemetry bases on
the standard Global Positioning System (GPS). Secondly, a wireless signal could be used to
relay the attributes of the plane’s motion back to the base station. Thirdly, an inertial guidance
system using a combination of accelerometers and rate gyros could be used to determine the
17
motion of the plane relative to the pilot/base station location. This type of system is commonly
used on fighter aircraft. Magnetometry was also considered to be an option. This type of system
relies on the magnetic field of the Earth to provide relative positioning. Lastly, a signal
triangulation scheme could be used to find the plane’s position
Based on ease of implementation, the wireless signal option was discarded. In addition,
based on system usability, the signal triangulation scheme was also discarded as a viable option.
The limited accuracy and high susceptibility towards interference of magnetometry far
outweighed any potential cost savings by using that system. The initial brainstorming down
select resulted in two options, Global Positioning Satellite (GPS) system and an inertial
navigation system.
3.2.2.1 GPS System
A GPS system would rely on the standard GPS satellites in orbit above the Earth. This
option would fulfill all of the aforementioned system attributes. Should this system prove to be
the most viable, there exists a wide variety of commercial OEM modules and engines that could
be easily implemented into the overall system design. The size and weight of these modules is
also very low, typically under an ounce and with a maximum linear dimension of two inches.
This system would also fulfill coexisting requirements between our design and the sponsor. GPS
systems adhere to an industry standard, and have standard data outputs that could be easily
manipulated using a microcontroller. The downsides to using a GPS system include the
requirement of external communication with at least one of the GPS satellites in orbit. This, in
turn, would require the use of an external antenna. Also, GPS is limited by obstruction
interference, i.e. foliage and urban environments.
18
3.2.2.2 Inertial Navigation System
An inertia system would provide relative positioning based on sensor data from 6-axis
accelerometers and gyros. This system would provide the most accurate measurements on the
position and motion of the plane. The inclusion of accelerometers and gyros allow the option for
a follow-on control system to augment the stability of the aircraft. In contrast with the GPS
system, no external signal is required for the use of this system. There is some error build-up
associated with sensor drift, which may become a problem during extended flight times.
Typically these sensors are also fairly costly. Also implementing a stand-alone inertial guidance
system would add to the overall complexity of the entire system.
3.3 Control
In order to meet the requirements of the project it is necessary to implement a means of
control for the airborne sensing platform. Typically, for hobby plane applications the RC radio
controller is used. Naturally, this became our first concept for implementing a means of control.
In addition to pilot in the loop control, it is possible to implement varying levels of autonomous
control for the airborne sensing platform. This includes customizable levels of pilot and
autonomous function, as well as, full platform autonomy. This autonomous control scheme was
considered as an alternative or complement to piloted control of the airborne sensing platform
3.3.1 Piloted Control
In order to pilot the Airborne Sensing Platform remotely, it is necessary to implement a
radio controller. This radio controller allows the pilot to control the servomotors that actuate the
control surfaces of the aircraft, as well as the throttle. It should also be noted that the radio
controller is a vital component for takeoff and landing scenarios.
19
3.3.1.1 Radio Controller
A radio controller is normally classified based upon the number of channels it has and the
frequency it operates on. Radio controllers normally vary between 2 and 9 channels. This
means that the controller has the ability to send signals on 2 to 9 separate pieces of equipment
onboard the aircraft via an onboard receiver. The initial concept was a 4-channel controller to
handle the four servomotors onboard the aircraft, specifically, the ability to actuate the rudder,
elevator, aileron and throttle. However, upon further investigation it was determined that these
four channels would not suffice. In addition to the servos themselves, a channel would be
needed for the speed controller to allow proper speed adjustment. This fact created a need to
consider a 6-channel and 9-channel alternative to the first concept developed. The 6-channel
radio controller increases the amount of controller surfaces that can be actuated. This makes it
possible to implement pilot control over an additional flap and spoiler, in addition to the
previously mentioned control surfaces. The knowledge that we were developing a test platform
for future improvement leads to a concept involving a 9-channel radio controller. This controller
model has the ability to actuate the aforementioned control surfaces, as well as control brakes
and mode-select settings. Also, the extra channels can provide a means of bypassing on board
controls and implementing emergency routines. Commercially available radios exist in all many
channel varieties, however, only controllers with 7 to 9 channels allow for extra pilot comfort
features such as customizable stick control and LCD display.
3.3.2 Partial Autonomous Control Systems
Three different flight control system concepts have been developed. They are listed in
order of complexity, from least complex to most complex. More complex systems must have the
full range of capabilities possessed by less complex systems in order to function.
20
3.3.2.1 Digital Servo Controller
The most rudimentary concept is that of the digital servo controller. This system consists
of a single microprocessor, analog-to-digital converter, and supporting components. A digital
servo controller is situated between the command signal receiver and the servos. The primary
function of the system is to apply post processing to the command signal to allow the pilot to
choose from various flight modes, such as air braking, landing and takeoff modes, or thermal
soaring modes. Flight modes will reduce pilot workload, increase control effectiveness, and
reduce operational power requirements. Additional functions may include data recording from
on-board sensors, and rudimentary signal reacquisition routines. Additionally, a servo controller
can be programmed to activate accessories, such as a recovery parachute, retractable landing
gear, or customer determined equipment. This concept will be relatively inexpensive to
implement, and is very simple, but will require some minor programming.
3.3.2.2 Stability Augmentation System
A more advanced implementation of the digital servo controller is a complete stability
augmentation system. The system would be similar to that described in 3.3.2.1, but would
require the addition of inertial sensors, such as rate gyros and accelerometers. An onboard
microcontroller would be used to provide closed-loop feedback based on data collected from the
sensors, effectively actively augmenting the stability of the aircraft. This would greatly reduce
pilot workload, particularly beyond line of sight where aircraft orientation can be difficult to
ascertain. Stability control greatly increases the effectiveness and availability of flight modes,
permitting more robust signal reacquisition and enabling limited autopilot capabilities such as
wing level hold, altitude hold, and heading hold. Flight characteristics of the plane can also be
adjusted in software to match pilot preferences and compensate for drastic changes in sensing
21
equipment configuration. The concept will be more difficult to implement than 3.3.2.1, requiring
calibration and installation of inertial sensors, and more careful microcontroller selection to meet
the increased computational load. Programming complexity will be similar to 3.3.2.1, as the
stability algorithm is easy to implement.
3.3.3 Fully Autonomous System
A fully autonomous flight control system would require all of the components of 3.3.2.2
in order to function effectively. Additionally, some method of absolute position referencing
would be required, either magnetometer or GPS based. A fully autonomous system would be
capable of flying to a predetermined set of waypoint coordinates without pilot intervention
except during the takeoff and landing stages of flight. This would free the operator to control
sensing telemetry, and would eliminate control problems beyond line of sight. The autonomous
system could be programmed to return to the operator position upon loss of communications, and
would be capable of a controlled emergency landing if manual landing were not possible. A
fully autonomous system is a significantly greater undertaking than 3.3.2.1 or 3.3.2.2, requiring
much more program code, greater processing capability, more advanced base station software,
and additional sensors. However, fully autonomous systems are readily available from a range
of vendors, often with integrated telemetry subsystems. As with the previous system types, the
on-board flight control systems can be programmed to suit changing customer requirements,
even completely different aerial platforms.
22
3.4 Sensor Equipment
Due to the nature of the remote sensing tasks being undertaken by the airborne sensing
platform it is important to implement additional sensor arrays to cover the needs of the sponsor,
as well as permit additional utility for the planned future development of the platform.
3.4.1 Temperature Sensor
A temperature sensor onboard the aircraft is important because the primary use of the
airborne sensing platform is in remote sensing of fires. Because the heat generated from fires
can cause severe damage to both internal and external components it is necessary for the pilot to
be aware of external conditions in real time for the duration of the flight. This assures the
integrity of the internal hardware and allows for emergency landing or evasion maneuvers in the
case of extreme heat caused while flying over the fire.
3.4.2 Pressure Sensor
A pitot-static pressure transducer is an extremely desirable piece of equipment to
implement onboard the airborne sensing platform. The sensor provides a mean to determine
static and dynamic pressures, thus allowing for calculation of platform velocity. This piece of
equipment is also important because it provides a means to trim the airborne sensing platform if
using autonomous navigation software. Also, it is possible to purchase a pitot-static pressure
transducer that measures temperature additionally. This would allow for combined measurement
of pressure and temperature in a compact design envelop.
3.5 Base Station
The base station serves as a platform to manage and monitor the remote sensing platform
test bed. The base station must meet several objectives in order to be successful. The primary
23
objective is to receive all communications sent by the remote sensing platform. The second
objective is to provide a Graphical User Interface (GUI) for the pilot, which shows real-time
video of the flight, telemetry data, and system characteristics. Finally, it is desired that the base
station is mobile, in that the components can be easily transported to the launch site.
3.5.1 Base Station Configuration
Coordinating with the sponsor proved to limit the scope of the base station complexity.
For this iteration of the remote sensing platform project, the base station serves only as a test bed
for proof of concept; however, the sponsor did express the desire to incorporate as much
functionality as possible. With this in mind, we decided to concentrate efforts on component
requirements and selection. It is also important to realize that the components of the base station
are driven primarily by the design choices of the remote sensing platform. The required
components of the base station are a laptop or mobile PC setup, RF receivers, RF antenna, and a
power supply. The computer is used to process information and display the information in an
organized manner. One receiver is used to collect telemetry and system data from the remote
platform in the 900 MHz frequency range. The second receiver is used to receive and process
the video feedback from the remote platform, which is also on the 900 MHz frequency range.
To receive the RF waves both receivers incorporate high gain omnidirectional antennas. The
power supply is not an important aspect of the concept development as the sponsor is developing
this along with their base station payload; therefore, we must only worry about stable power for
proof of concept testing.
24
3.5.2 Antenna
The antennas used in the overall communications scheme play a large role in successfully
maintaining an RF link. The combination of transmitter output power and the antenna gain must
provide ample margin to overcome the losses incurred during transmission of RF signals. A
successful link is one that is stable at a linear distance of 2 miles.
3.5.2.1 Antenna Scheme
Several key aspects are considered when determining the appropriate antenna
arrangement. These aspects include, but are not limited to frequency range, marginal beam-
width, radiation pattern, polarization, and gain. The frequency range is 900 MHz for both
communication systems onboard the airborne sensing platform. There are two major obstacles
inherent in this application of long-range aerial vehicle communication system, achieving
enough margin and signal separation. Frequently, long-range applications require directional
antennas to achieve the distance requirements while remaining within FCC regulations; however,
due to the nature of aerial vehicles directional antennas are not as desirable. For this reason the
first design iteration will incorporate high-gain omnidirectional antennas at the base station, with
smaller gain omnidirectional antennas onboard the plane. There are several ways to achieve
signal separation when using multiple transmitters within close proximity to one another. The
first is to use different polarization techniques in antenna selection/design. Omnidirectional
antennas are either vertically or horizontally polarized. The second option to mitigate signal
interference is by channel separation within a given frequency band. Due to the high costs of
horizontally polarized omnidirectional antennas, the chosen method to mitigate the effects of
multiple transmitters is channel separation. In summary, both antenna sets incorporate
omnidirectional vertically polarized 900 MHz antennas.
25
4.0 FEASIBILITY
A trade study evaluated the overall feasibility of the individual components and
subsystems considered during concept development. Then the overall system feasibility of
competing concepts was determined by using a weighted method.
Considering the wide variety of components for our application that are commercially
available, it becomes necessary to employ a method to determine which components would be
better for our use than others. By giving weights to various component parameters and
specifications, and then placing ratings or grades based on that particular component’s
performance in that category, a component’s overall rating can be assessed. In our concept
development, subsystem attributes were defined based on the requirements of that particular
subsystem. The team identified the attribute weighting factors, typically with the weight of the
component and power consumption as two of the major factors. Some of these attributes are
pertinent to all or the majority of the components identified for selections, some are specific to
that individual component. Component specifications and data were collected and given a grade.
A 1-3-9 grading scale was used, with 1 being the worst, 3 being baseline, and 9 being the best.
The use of this scale typically better defines the component best suited to the application, and
removes some of the associated ambiguity from the trade study. This rating scale and trade
study method is employed by systems engineers at Boeing Satellite Systems.
4.1 Communication
A communication system is necessary to meet the requirements of the project and to
allow the exchange of telemetry, instrument, and control data between the base station and
platform. A trade study conducted on various communication concepts revealed the most viable
options for the team given cost, schedule and project requirements.
26
4.1.1 Wireless Communication
Once the team determined what frequency range to use for RF communications, the team
performed a trade study on possible communication system architectures that would best meet
the design requirements. The two feasible architectures studied were (1) a dedicated transmitter
for video feedback and a separate telemetry system, and (2) combining the telemetry system and
video feedback system by utilizing the audio channel on a video transmitter. From the trade
study the team determined the best system incorporated a 900 MHz audio/video transmitter
(embedded in the platform), a 900 MHz audio/video receiver (at the base station), and a surface
mount global positioning system (GPS) encoder. See Figure 4 below. This option had lower
power consumption, size, weight and cost. Also, it would have less interference potential due to
fewer radios on-board the aircraft. The range of the transmitter/receiver combination is mainly
driven by the antennas used, output power, path loss, and any interference. By incorporating the
appropriate RF components, the system is expected to exceed the range requirement of two
miles, while remaining within the allowable power consumption, size, and weight limitations of
the aircraft. Numerous vendors offer audio/video transmitters and receiver systems that utilize
the NTSC standard output of a video camera. The system does not require that sound feedback
be provided to the base station; however, the audio channel of the transmitter can be used as a
medium for our telemetry system. The Tiny Track Surface Mount (TTSMT) GPS encoder
offered by Byonics, allows the telemetry information to be encoded on the audio channel of the
transmitter. The telemetry data is decoded at the base station utilizing a standard sound card and
a software package such as AGW Packet Engine (AGWPE).
27
Concept:
RF Aux Compon (ant,amp,etc) & S/W RF Aux Compon (ant,amp,etc) & S/W RF Aux Compon (ant,amp,etc) & S/W RF Aux Compon (ant,amp,etc) & S/WAttribute % Value Score Result Value Score Result Value Score Result Value Score Result
Size (on plane) 10% 1.6x2.825x.7 3 0.3 1.6x2.825x.3 3 0.3 2.6x1.8x.38 3 0.3 2.6x1.8x.2 3 0.3Power (on plane) 25% 3.75 W 1 0.25 3.1 W 3 0.75 3.75 1 0.25 3.1 3 0.75
Cost 10% 540.00$ 1 0.1 295.00$ 3 0.3 640.00$ 0 0 330.00$ 3 0.3Range 20% Medium-High 3 0.6 Medium-High 3 0.6 Medium 1 0.2 Medium 1 0.2
Interface 5% RCA,DB9 9 0.45 RCA, I/O Pins 9 0.45 RCA,DB9 9 0.45 RCA,Pin 9 0.45Weight (on plane) 10% 1.47oz 3 0.3 0.67 9 0.9 3.6 3 0.3 3 3 0.3
Resolution 10% 400+ lines 9 0.9 400+ lines 9 0.9 400+ 9 0.9 400+ Lines 9 0.9Data Throughput 5% 19kbps 3 0.15 ~ 300 baud 1 0.05 19kbps 3 0.15 ~ 300 baud 3 0.15Channel Capacity 5% 1, 7 1 0.05 1 3 0.15 4,7 3 0.15 4 3 0.15
Total 100% 3.1 4.4 2.7 3.5
DOES NOT INCLUDE:
900 MHz - (2) Comm Systems: Data & Video
Video Transmitter: TX-9500 Video Reciever: RX-900
Data Tranmistter: 9Xstream OEM Description:
900 MHz - (1) Comm System: Data & Video
Video Transmitter: TX-9500 Video Reciever: RX-900
Tiny Track SMT GPS Ecnocder
DOES NOT INCLUDE:
Data Reciever: 9Xstream OEM Data Reciever: 24Xstream OEM
DOES NOT INCLUDE:
2.4 GHz - (2) Comm Systems: Data & Video
Video Transmitter: THX-2450Video Reciever: RX-2400
RF Module
DOES NOT INCLUDE:
2.4 GHz - (1) Comm System: Data & Video
Video Transmitter: THX-2450Video Reciever: RX-2400
Tiny Track SMT GPS Ecnocder
Figure 4: Table of Communication Systems Trade Study Results
4.2 Guidance and Telemetry System
The concept development yielded several potential concepts for a means of implementing
platform guidance. As a result, a trade study was conducted to determine the best means of
platform guidance.
4.2.1 Vision Guidance System
4.2.1.1 Camera Packaging Scheme
Video cameras are available as a camera-transmitter package or as a camera only. A
camera that is separate from the transmitter is more practical for the airborne sensing platform
because a camera without a transmitter weighs less and provides more flexibility in the design
and implementation of a vision guidance system. Another transmitter is available on the
28
platform as part of the telemetry system, so the team will reduce the overall system weight and
power consumption by selecting a stand-alone camera unit and integrating it with the existing
transmitter.
4.2.1.2 Camera Selection
Video cameras are available with CCD or CMOS imagers. The fact that CCD cameras
provide superior image quality while having the same power consumption as CMOS cameras
made them the ideal choice for this platform. Other camera attributes are also important
considerations in addition to the type of imager.
Camera units are commercially available with a large array of attributes. The major
attributes included in the trade study were effective pixels, minimum illumination, cost, power,
video output, weight, horizontal resolution, dimensions, audio capability, color, and signal
system.
Power, resolution, and the presence of an audio channel were given the greatest weight in
the feasibility assessment because they drive the success of this project. Resolution determines
image quality and the associated power consumption. Also an audio channel may be necessary
to transmit telemetry data.
Figure 5 contains the results of the trade study. Our top choice camera is the Mini B/W
Camera w/Audio (VC-210B-AUDIO) from Circuit Specialists Inc. This model has low power
consumption, high resolution, audio capabilities, and can operate in minimal illumination. In
addition, the camera’s 1.0 Vp-p, 75 Ohm video output integrates well with our communication
system.
29
Concept:
Attribute % Value Score Result Value Score Result Value Score Result Value Score Result
Effective Pixels 5% 510x492 3 0.15 512x492 3 0.15 510x492 3 0.15 510x492 3 0.15Min. illum. (LUX) 10% .05 LUX 9 0.9 0.5 LUX 3 0.3 1.0 LUX 1 0.1 .05 LUX 9 0.9
Cost 10% $34.50 3 0.3 3 0.3 $54.50 3 0.3 $33.00 3 0.3Power 15% 1.08 W 9 1.35 1.8 W 1 0.15 1.44 W 3 0.45 1.2 W 9 1.35
Video Output 5% 1.0Vp-p 75 Ohm 9 0.45
1.0Vp-p 75 Ohm BNC / F
connector9 0.45 1.0Vp-p 75
Ohm 9 0.45 1.0Vp-p 75 Ohm 9 0.45
Weight (on plane) 3 0 9 0 3 0 3 0Horizontal Resolution 15% 420TV Lines 9 1.35 330 TV lines 9 1.35 380 TV lines 9 1.35 420 TV lines 9 1.35
Dimension 10%30.8mm x 30.8mm x
15mm3 0.3 3 0.3
36mm x 36mm x 20.5mm
3 0.3 38mm x 38mm 3 0.3
Audio 20% YES 9 1.8 YES 9 1.8 YES 9 1.8 NO 1 0.2BW/Color 10% BW 1 0.1 Color 1 0.1 Color 1 0.1 BW 1 0.1Package Case Case Board
Signal System EIA (NTSC) NTSC NTSC EIA (NTSC)
Total 100% 6.7 4.9 5 5.1
Mini B/W Camera w/Audio Color DSP Mini CCD w/audio SONY Super HAD CCD mini w/Audio SONY Super HAD CCD mini
Description DOES NOT INCLUDE: DOES NOT INCLUDE: DOES NOT INCLUDE: DOES NOT INCLUDE:
Figure 5: Table of Camera Selection Trade Study Results
4.2.2 GPS
GPS engines and modules are fairly standard across the industry. The majority of the
engines is based on the same two or three chipsets, and subsequently has very similar
characteristics.
For our evaluation, the team identified several parameters as being pertinent to our
system requirements. Accurate position and velocity measurements would assist the pilot in
adhering to the mission route. With the length of the flight time, the design is also restricted on
component weight and power consumption. Size also is a factor because there is a limited
amount of space for the payload bay. The sampling size affects the data throughput for the
30
communication system. The cost of the unit, acquisition time, and dynamics under which the
unit can properly operate also played a factor in the evaluation. The data transmission scheme or
interface will also have an effect on the overall system architecture. And finally, operating
temperature was also given consideration due to the fact that temperatures over a fire may be
extreme.
Several different units manufactured by several different companies were considered.
The results are tabulated below. One of the units manufactured by Royal Tech (REB3300)
available at Mobile GPS Online was selected as the best component for use.
GPSWeighting
Factor Value Utility Util*Wt Value Utility Util*Wt Value Utility Util*WtPos/Vel Accuracy 0.1 10 m, 0.1 m/s 9 0.9 15m, 0.05 m/s 3 0.3 25 m, 0.1m/s 1 0.1
Weight 0.1 0.12 oz 9 0.9 0.35 oz 3 0.3 0Sampling (pulse) 0.05 1 s 3 0.15 1 s 3 0.15 1 s 3 0.15Operating Temp. 0.1 -40 to 85 C 9 0.9 -30 to 85 C 9 0.9 -10 to 70 C 3 0.3
Size 0.1 1x1x0.12" 9 0.9 0.94x1.69x0.309" 3 0.3 1.18x1.57x0.28" 3 0.3Cost 0.1 $70 3 0.3 0 $75 3 0.3
Acquisition Time 0.05 38 s 3 0.15 15 s (warm) 9 0.45 38 s (warm) 3 0.15Dynamics 0.15 0 514 m/s, 6g's 9 1.35 515m/s, 4g's 3 0.45
Power 0.2 0.215 W 9 1.8 0.2805 W 9 1.8 0.165 W 9 1.8Interface 0.05 0 CMOS 1 0.05 serial (opt RS-232) 9 0.45
1 sum 6 sum 5.6 sum 4
MGO - REB3300 Garmin GPS 15 Laipac TF-30
Figure 6: Table of GPS Trade Study Results
4.3 Control
The feasibility of various control options was again considered via a trade study. The
main areas of feasibility were concentrated around ways to implement piloted control,
autonomous function, and fully autonomous flight.
31
4.3.1 Radio Control
In order to provide a means for take off, landing, and in flight control of the aircraft a
radio controller is needed. A feasibility trade study was conducted on various types of
controllers that were commercially available. The main attribute that drives controller selection
is the number of channels available to the pilot for actuating control surfaces. Also the degree of
customization that can be done to the controller to provide pilot comfort is important. For ease
of comparison, only Futaba brand controllers were evaluated. Futaba provides a detailed list of
features that are industry standard and are widely used for this application. At this time, there is
a need for at least four channels to control the actuation of the elevator, rudder, ailerons, and
throttle. However, additional control surfaces may be added. Because it is a development
platform, it is necessary to consider controllers with higher channel capabilities. The sponsor
expressed interest in the Futaba 9-channel receiver, and upon further research, it was found to
provide a wide variety of features for pilot comfort and customization. When coupled with a 9-
channel receiver on board it will provide the ability to control the platform control surfaces up to
the range requirement for the project. However, if interference becomes an issue the controller
signal can be amplified to meet the requirement.
Concept:
Attribute % Value Score Result Value Score Result Value Score Result Value Score Result
Size Receiver (on plane) 10% 2.52x1.39x0.82 in^3 3 0.3 2.52x1.39x0.82 in^3 3 0.3 1.3x 2.1x0.8 in^3 3 0.3 Not Specified 3 0.3Power (on plane) 20% 600 1000 mAh 3 0.6 600 1000 mAh 3 0.6 600 1000 1500 mAh 3 0.6 Not Specified 1 0.2
Cost (Radio) & Cost Receiver) 10% 250 + 60 3 0.3 300 + 60 3 0.3 350 + 130 3 0.3 2200 + 1 0.1Customizing 10% Medium 3 0.3 Medium 3 0.3 High 9 0.9 Very High 9 0.9
Range 20% High 3 0.6 High 3 0.6 High 3 0.6 High 3 0.6Weight Receiver (on plane) 10% 1.5 oz 3 0.3 1.5 oz 3 0.3 1.25 oz 3 0.3 3 oz 3 0.3
Channel Capacity 20% 6 1 0.2 7 3 0.6 9 9 1.8 14 9 1.8Frequency 72 MHz 0 72MHz 0 72MHz 0 72MHz 0
Total 100% 2.6 3 4.8 4.2
6 Ch. 7 Ch. 9 Ch. 14 Ch.
Description:
Futaba Futaba Futaba Futaba6 Channel suited for RC plane 7 Channel suited for RC plane 9 Channel suited for RC plane 7 Channel suited for RC plane
standard 7 channel w/o crystal standard 7 channel w/o crystal standard 9 channel no crystal req.standard 14 channel no crystal req.
DOES NOT INCLUDE: DOES NOT INCLUDE: DOES NOT INCLUDE: DOES NOT INCLUDE:
32
Figure 7: Table of Radio Controller Trade Study Results
4.3.2 Partially Autonomous Control System
Initially there were several competing concepts for partially autonomous control systems
for the airborne sensing platform. The concepts were a simple micro controller, stability
augmentation, and a fully autonomous sensor package. A trade study was conducted among
these concepts to determine the most feasible in each category.
4.3.2.1 Digital Servo Control
The digital servo controller provided a relatively inexpensive means of implanting
autonomous flight routines. However, it would require excessive time to program, debug and
integrate into the overall system. The main time consuming tasks would be interfacing between
the transmitters and telemetry equipment, and the creation and incorporation of the associated
control algorithms needed to maintain autonomous function.
4.3.2.2 Stability Augmentation System
In order to determine the best means for implementing a stability augmentation system, a
number of different commercially available sensor packages were evaluated. The desire to
produce an airborne sensing platform with as much customization as possible drove the selection
process. Important factors were telemetry features and range, as well as cost. The full stability
augmentation system would require the selected sensor package and additional control
algorithms executed by a microcontroller to create a means of servo control based on feedback
from the sensor package. This adds a great deal of complexity to the system, as it would involve
33
a great deal of time and programming to link all the onboard components. See Figure 8 below
for a summary of the sensor package trade study.
Concept:
Attribute % Value Score Result Value Score Result Value Score Result Value Score Result
Cost 20% 2590 3 0.6 250 9 1.8 225 9 1.8 80 9 1.8Axes 10% 6 9 0.9 5 3 0.3 4 3 0.3 3 1 0.1
Sensors 20% 3 Accel,3 Gyro,3 Magneto 9 1.8 2 Accel, 3 Gyro 3 0.6 2 Accel, 2 Gyro 3 0.6 3 Magneto 1 0.2CEP (Pos.) 10% 2m 9 0.9 NA 1 0.1 NA 1 0.1 NA 1 0.1CEP (Rel.) 10% 20cm 9 0.9 ? 1 0.1 NA 1 0.1 NA 1 0.1
Angular Rate 0% 90 deg/sec 3 0 90 deg/sec 3 0 90 deg/sec 3 0 ? 1 0Accel. Rate 0% 19.6 m/s^2 3 0 19.6 m/s^2 3 0 19.6 m/s^2 3 0 NA 1 0
Angular Prec. 0% 0.5-1 deg 3 0 0.5-1 deg 3 0 0.5-1 deg 3 0 ? 1 0Refresh 10% 200Hz 3 0.3 ? 3 0.3 ? 3 0.3 ? 3 0.3Power 15% 2.5W 3 0.45 ? 9 1.35 ? 3 0.45 ? 9 1.35
Interface 5% Ethernet 10/100T 3 0.15 RS232 9 0.45 RS232 9 0.45 8-bit SPI 3 0.15Notes: Inc. Servo Controller Inc. Servo Controller w/Servo Controller
Total 100% 6 5 4.1 4.1
5DOFIMU
Rotomotion
AHRS200ADescription: 4DOFIMU 2.4 3-Axis Magnetometer
Rotomotion RotomotionRotomotion
Figure 8: Table of Stability Augmentation System Trade Study Results
4.3.2.3 Fully Autonomous System
Another concept that was proposed was a fully functional autonomous navigation system.
Important factors were telemetry features and range, as well as cost and availability of base
station software packages. Also the ability to allow piloted control for take off and landing was
extremely important because it is nearly impossible to achieve smooth take off and landing using
only a commercially available autonomous sensor package. The best fully autonomous stability
augmentation system was the AP50 Autopilot. This system exceeded the range requirements and
provided a means to acquire both GPS and inertial information in a compact, lightweight design
envelope. The Autopilot also included extra A/D channels that can be used to transmit video or
other sensor information from onboard the Airborne Sensing Platform to the base station. The
Autopilot also comes with base station software that permits the pilot to track the flight path of
34
the platform and add additional waypoints during a mission. Although a fully autonomous
system is comprised of a more complex design, it provides a larger array of options for the
sponsor to modify or upgrade in the future. The commercial availability of the system limits
design and programming time on individual components allowing increased time to consider
system integration and configuration concerns. See Figure 9 for a summary of the fully
autonomous systems trade study.
Concept:
Attribute % Value Score Result Value Score Result Value Score Result Value Score Result
Cost 10% 5000 3 0.3 800 9 0.9 5000 3 0.3 ~4000 3 0.3
Telemetry 20%RS485 900MHz, 7 mile range (also avail. Seperately) 9
1.8RS485 900MHz, 7mi range
(not included (add $550)), 40 mile also avail.
3 0.6 Capable (std. 2.4 GHz wireless modem) 1 0.2 900 MHz Maxtream
Transeiver 15 miles range 9 1.8
Autonomy 10% Full (w/o ATOL) 9 0.9 Partial 3 0.3 Partial 3 0.3 Full (w/o ATOL) 9 0.9
Manual Mode 5% YES 3 0.15 YES 3 0.15 YES 3 0.15 YES 3 0.15Video 10% Not Included 1 0.1 Capable 3 0.3 NTSC w/GPS overlay 9 0.9 capable thru A/D? 3 0.3
Sensors 10% 6 axis inertial, GPS capable, pitot, baro.
3
0.3 GPS capable, SMT Baro., 2-axis inertial 1 0.1 DGPS, 6 axis inertial,
airspeed, alt. (ultrasound)9
0.93 rate gyros, 2 axis accel.
,Altimeter, Airspeed: designed to connect to pitot
3 0.3
Basestation 10% YES, TRACKER software 3 0.3 YES, TRACKER software 3 0.3 YES, HORIZON software 3 0.3 YES, GroudPilot Software 3 0.3Size 5% 4 x 2 x 1.6 in 3 0.15 1 x 2 x 0.5 in 9 0.45 10 x 4 x 2 cm 3 0.15 5.7x1.9x1.1 in 3 0.15
Weight 5% 3 oz 3 0.15 57 g or 2 oz 3 0.15 28 g or 1 oz 9 0.45 50g or 1.76 oz 3 0.15Power 10% 5-14 V @ 180mA 3 0.3 5-7 V @ 50mA 3 0.3 6.5 V @ 140 mA 3 0.3 5.4-8 V @ 120 mA 3 0.3
Waypoints: 5% 16 1 0.05 32 3 0.15 1000+ 9 0.45 24 add / change during flight 3 0.15Notes 2 extra A/D for other sensors
Total 100% 4.5 3.7 4.4 4.8
UNAV3300 PICO-PILOT MP2028 AutoPilot 50
UAV Systems
DescriptionAutonomous Packages Autonomous Packages Autonomous Packages Autonomous Packages
U-NAV U-NAV Micropilot
Figure 9: Table of Autonomous Systems Trade Study Results
4.3 System Level Feasibility
In preparation for the sponsor concept design review, the team completed a trade study
on the various component concepts. The results allowed the team to narrow down the best
35
options for individual components and subsystems and present them to the Center of Imaging
Science. This information was then used to create three competing concepts for an overall
system that would provide the sponsor with an airborne sensing platform that met or exceeded all
the objectives and specifications of the project. These system concepts were: piloted control,
piloted and autonomous control, and a complete commercially available UAV system that
included the platform and telemetry components. After the three system level concepts were
developed, a feasibility analysis was performed using a weighted feasibility method. Driving
factors were sponsor requirements, cost, weight, and time considerations based on complexity
and resource availability. Due to the limited nature of the commercially purchased system
configuration, it scored low in the feasibility analysis. See Figure 10 for a complete review of a
system level feasibility study.
36
Figure 10: Table of System Level Feasibility Study
4.3.1 Piloted Control
This system level design incorporates an RF communication system comprised of a
Futaba radio controller and receiver pair. This allows for piloted control of the airborne sensing
platform. The pilot handles take off and landing maneuvers and guides the plane to the target
location. The platform incorporates the video camera and GPS systems previously mentioned.
The GPS signal is encoded via the Tiny Track and sent down to the base station over the audio
channel provided by the video camera. This system provides the navigational cues necessary to
fly the plane at long distances because the pilot has location and velocity information from the
GPS and stability cues such as the horizon from the real time video feedback. This system
configuration is the least expensive option and the easiest to implement, however, it provides
limited capabilities and less customization. Also, pilot work load is high due to the potential for
long range missions.
4.3.2 Autonomous Control Capability
The proposed system utilizing autonomous control capability provides a means for both
pilot in the loop and autonomous control of the airborne sensing platform. The system would
still implement a Futaba radio controller and receiver pair, however this would utilized only for
take off and landing scenarios and the avoidance of situations detrimental to the integrity of the
platform. It is important to maintain piloted capabilities because commercially available
autonomous systems cannot provide an accurate means for take off and landing. It is also
necessary to maintain some level of piloted control during adverse conditions that may be
created by the fire such as thermal updrafts and shifting winds. A much more serious condition
37
known as flashover may also occur. Flashover is a condition in which the air above a fire
combusts. A fire may begin to die down with an expiring oxygen supply; however, a sudden
wind gust can provide a new supply which causes the fire to suddenly flare up. In these
situations, the pilot can take control of the aircraft and safely navigate the platform away from a
potentially harmful situation.
The autonomous capability is implemented with the AP50 AutoPilot hardware and
GroundPilot software at the base station. The AP50 AutoPilot has both GPS and inertial
guidance capabilities. It also incorporates a long-range transceiver to provide a means of
communication between the base station and the airborne sensing platform. Another appealing
feature of the AutoPilot system is extra open A/D channels allowing the team and or sponsor to
transmit data from additional sensors onboard the plane. This system configuration will also
incorporate a vision guidance system. This system will be comprised of a small CCD video
camera connected to a wireless modem. It will provide real time feedback to the pilot to aid in
piloted flight and alert the pilot to potential problems during a mission. The camera chosen has
an available audio channel. This provides the sponsor a means to send down GPS or other
encoded data in the future. Although this is a somewhat redundant system, it provides the
sponsor with maximum flexibility in customizing and upgrading the system in the future. It is
important to note that this system, while more expensive than the system previously mentioned,
can still be implemented under the given budgetary constraints. The lightweight and small size
of all the aforementioned components allow the team to meet the requirements for endurance and
loiter, while providing maximum capability and flexibility to the sponsor. Not surprisingly, this
option scored the highest in the feasibility analysis. See Figure 10.
38
4.3.3 Commercially Available Complete System Solutions
The Micropilot MPUAV was selected as the best complete UAV system from among
competing vendors that met basic sponsor specifications. Driving factors in the decision were the
low cost when compared with other systems, commercial availability of base station equipment,
and the ability to store a large numbers of programmable waypoints. However, this system
concept was extremely expensive and could not be customized to the degree necessary to provide
a quality durable airborne sensing platform test bed. This is apparent from its lower score in the
feasibility analysis.
4.4 Overall System Selection
The team in conjunction with the sponsor has elected to implement a design that allows
for both piloted and autonomous control of the airborne sensing platform. The platform will use
the AP50 AutoPilot to provide GPS and inertial data to the base station. The AP50 will also
provide the means of autonomous navigation when combined with a pitot-static tube and the
GroundPilot software package at the base station. The team will implement a vision guidance
system that consists of a camera and receiver/transmitter pair that is separate from the long-range
radios on the AP50 autopilot. Also a temperature sensor will be placed onboard the platform to
provide additional feedback to the pilot about the ambient conditions around the platform. This
data will be transmitted on the additional A/D channels of the AP50 AutoPilot.
5.0 OBJECTIVES AND SPECIFICATIONS
The team in conjunction with the Center for Imaging Science developed a set of
guidelines, performance specifications, and design objectives. These were used in order to
39
assess the successfulness of the project. This section will discuss these guidelines, performance
specifications and design objectives as agreed upon by the team and the sponsor.
5.1 Performance Specifications
1) The platform shall loiter long enough for remote sensing tasks to be executed by
the Center for Imaging Science. Based on sponsor input a flight duration time of
1 hour will allow the pilot to complete remote sensing tasks.
2) The platform must have the ability to fly autonomously or via piloted control to
altitudes at or below 1,000 ft.
3) The platform must have the ability to fly autonomously or via piloted control to
distances of 2 miles away from the base station.
4) The platform shall cruise at a range of speed between 15-25mph.
5) The platform must be able to carry a 3 lb modular payload designated by the
Center for Imaging Science.
5.2 Design and Implementation Specifications
5.2.1 Platform Durability
The platform airframe must be able to withstand takeoff and landing loading conditions.
The platform should be constructed to allow for multiple remote sensing missions. The vision
guidance system and telemetry should be protected from shock due to take off and landing.
40
5.2.2 Fuselage
5.2.2.1 Fuselage Interior Payload
The fuselage must be capable of holding the Center for Imaging Science payload and the
onboard vision guidance equipment and telemetry. Measures should be taken in mounting
onboard equipment to allow easy access to vision guidance and telemetry system, as well as CIS
payload. Consideration should be given to future development of platform and allow mounting
space for additional equipment and sensors. The fuselage must provide a means by which to
protect equipment for heat exposure during remote sensing tasks.
5.2.2.2 Fuselage Exterior Payload
The fuselage must be capable of mounting exterior sensor equipment safely and easily.
The fuselage must provide a means by which to protect equipment for heat exposure during
remote sensing tasks.
5.2.3 Dimension
The overall size of the platform will be minimized to allow cost and weight savings.
However, this act shall not compromise the performance goals previously set forth.
5.3 Stability and Control
The pilot must be able to adequately control the platform in a manner that allows for
successful completion of remote sensing tasks.
5.3.1 Control Surfaces
The control surfaces on the platform will provide the pilot with the ability to navigate.
41
There shall be enough dynamic control surface available for the pilot to perform aerial
maneuvers associated with remote sensing tasks. The static surfaces on the platform will also be
designed to improve overall stability. Overall, the platform shall be designed to be passively
stable.
5.4 Electrical Systems
5.4.1 Video
The platform will utilize a camera as part of a vision guidance system. The camera
system will transmit a real time video signal back to the base station. This will give the pilot the
ability to carry out remote sensing tasks when the platform is out of visual range. The conditions
under which the camera is operating should be considered to be ambient light on a sunny day.
5.4.2 Global Positioning System (GPS)
A GPS system onboard the platform will send back navigational information to the base
station. From this GPS data, the pilot will know altitude and distance from the base station. It
will also serve the purpose of locating remote sensing targets. In the event of a crash, the GPS
will aid in faster retrieval of the platform. Also the GPS should aid in panic mode if the plane
loses the control signal. The GPS system should be implemented in a way that allows the Center
for Imaging Science to utilize GPS information for their payload.
5.4.3 Transceiver
The platform will utilize an RF communication scheme to send and receive data. The
pilot will transmit a control signal from the base station. A receiver onboard the platform will
then use that control signal to actuate the dynamic control surfaces on the platform. A
42
transmitter will send data from the navigation and GPS systems to the base station. A receiver at
the base station will then utilize the streaming data to give the pilot real time feedback about the
platform.
5.4.4 Base Station
The base station will provide the pilot with the necessary navigational cues to assist in
flying the platform when it is no longer in sight. It shall provide a means of displaying the
streaming video and GPS signal. The base station should provide the pilot with information
about power consumption on board the platform. The base station should assist in signal
processing on the control signal. The base station should be durable enough to complete
multiple remote sensing tasks. The base station should be portable.
5.4.5 Batteries
The power plant onboard must supply sufficient power to run the vision guidance and
telemetry systems, as well as additional sensors to be determined. Also the batteries must
provide enough power to actuate the dynamic control surfaces and power the motor in
accordance with the previously outlined specifications. The battery must be rechargeable to
accommodate multiple remote sensing missions. The battery should be chosen to maximize
power while minimizing weight.
5.4.6 Possible Platform Features
Additional features may be added to the platform to increase its utility. These features
are dependent on cost, time, and skill set. Their feasibility will be considered throughout the
project based on analysis and synthesis work done for the project and may be implemented on
the final design of the Airborne Sensing Platform.
43
5.4.6.1 Inertial Navigation
A set of rate gyros would allow a greater degree of controllability for the pilot. Also, it would
allow for autonomous or semi-autonomous flight if implemented with a stability augmentation
system. At this time, the team plans to implement an inertial navigation system as part of the
AP50 AutoPilot hardware.
5.4.6.2 Stability Augmentation System
A stability augmentation either commercially available or custom made would provide a
feedback control loop for the Airborne Sensing Platform. This would allow of semi-autonomous
or autonomous flight. At this time, the team will implement a stability augmentation system via
the AP50 Autopilot hardware. This system uses imbedded control algorithms and sensor inputs
from GPS and inertial systems to provide pilot out of the loop control of the platform.
5.4.6.3 Flight Control and Recovery Systems
An algorithm for implementing emergency landing procedures may be implemented to
allow for ease of recovery of the platform in the event of communication loss with platform. In
the event of signal loss from the base station, the AP50 hardware previously mentioned provides
circling flight routines that allow for signal recovery or emergency landing.
5.4.6.4 Onboard Temperature Sensor
Due to the sensitive nature of the remote sensing equipment, hot updrafts from a fire
could cause damage to the platform. A temperature sensor onboard the platform would aid the
pilot in determining if conditions are unfavorable for flight over a fire. At this time, the team
plans to implement a temperature sensor onboard.
44
5.4.6.5 Onboard Pressure Sensor
A pressure transducer accompanied by a pitot-static tube attached to the exterior of the
Airborne Sensing Platform will allow for dynamic and static measurements of pressure while the
platform is in flight. This will enable measurement of ambient conditions through which the
platform is flying. It also allows for the determination of local velocity. The AP50 AutoPilot
has a temperature compensated integrated silicon pressure sensor. The team will construct a
pitot-static tube and combine it with the pressure sensor to provide pressure information and
velocity measurement.
5.4.7 Controller
The controller must be able to transmit a control signal to the platform either stand-alone
or with the aid of the base station based upon previously stated requirements. The controller
must be capable of actuating at least four control surfaces. The controller should be easy for the
pilot to learn and operate.
5.4.8 Controller Receiver
The receiver must be capable of receiving control signal from controller. The receiver
must be able to control at least four control surfaces. The receiver should minimize size and
weight in accordance with previous requirements.
5.4.9 Onboard Processing
Utilizing a programmable integrated circuit (PIC) or digital signal processing (DSP) chip
will allow the platform to store GPS and other data to aid in logical decision making for control
purposes. The PIC or DSP chip should allow the platform to actuate the control surfaces in the
event of control signal loss. The chip should allow for semi-autonomous control option. The
45
chip should also include a sufficient means of data storage and processing onboard to aid in
flight control and recovery.
5.5 Design Practices
In order to accomplish the design objectives and specifications the team utilized the
following list of design practices as a guide throughout the design process.
1) Design for Manufacturability – The platform and subsystems should be designed
with components that are readily available or relatively easy for someone
unfamiliar with the project to machine. This ensures the sponsor will be able to
maintain a viable platform after the senior design team turns the prototype of to
the Center for Imaging Science.
2) Design for Assembly – The platform is intended to be a development platform.
As such, it will be assembled, disassembled, and modified frequently. The design
must allow ease of access to cargo bays. Also issues surrounding fatigue failure
and wear on components due to assembly and disassembly should be addressed.
3) Design for Reliability – The platform and subsystems should be reliable enough
to allow for multiple flights. It is common to have minor failures on platforms of
this type; however, major subsystems should be designed to provide impact
resistance to ensure the longevity of the components.
4) Design for Accuracy – The mounting systems within the fuselage and the other
platform components should have a tolerance that provides minimal error to allow
ease of replacement.
46
5) Design for Safety – The platform design should consider safety to the pilot during
launch and landing, as well as FCC and FAA guidelines for operating platforms
of this type.
5.6 Safety Issues
The team should consider both FCC and FAA regulations and licensing requirements as
they pertain to Unmanned Aerial Vehicles when considering electrical and mechanical
components for the platform. However, due to the nature of the missions to be carried out by the
Airborne Sensing Platform, no emphasis shall be placed on these regulations at this time. Also,
the design of individual components should consider ergonomics. Removing sharp corners and
providing ease of assembly will reduce the potential for accidents and injuries related to
repetitious activities.
5.7 Launch
A means of launching the platform must be accomplished. The launch should not
damage any equipment onboard the Airborne Sensing platform. At this time, the team plans to
use either hand launching or a winch launch system.
5.8 Pilot
A pilot will be needed to provide take of and landing for the Airborne Sensing Platform
in order to complete remote sensing tasks. The pilot should have an AMA license and
knowledge of RC planes.
47
5.9 Deliverables
1) Preliminary Concept Review (January, 2005) – This was completed during the
month of January. It includes a presentation and brainstorming session with the
sponsor to determine concept and feasibility for features on the Airborne Sensing
Platform.
2) Preliminary Design Review (February, 2005) – This will be completed at the end
of Senior Design 1. It includes a written report and a formal presentation on the
progress completed by the Senior Design Team
3) Airframe Completed (February, 2005) – The current Senior Design 2 team 05008
will complete and demonstrate a working RC plane at the end of Winter Quarter
and turn it over to our team in order to complete the necessary upgrades to
complete the Airborne Sensing Platform. If the platform is not ready the team
will construct a plane.
4) Critical Design Review (May, 2005) – This will be completed at the end of Senior
Design 2. It will include a final report and presentation, as well as, a
demonstration of the prototype.
5.10 Overall Period of Performance and Schedule
Start Development – December 2004
PDR – February 2005
CDR – May 2005
48
6.0 DESIGN ANALYSIS AND SYNTHESIS
6.1 Airframe Analysis
In order to evaluate the design of the overall system to be implemented in the airborne
sensing platform it was necessary to analyze the airframe that would carry the telemetry
subsystem, vision guidance subsystem, and other sensor subsystems. This included a dynamic
analysis of the aircraft being produced by the #05008 senior design team, and a performance
analysis of aircraft alternatives.
6.1.1 #05008 Airframe Stability Analyses and Redesign
The #05008 aircraft stability and control characteristics were evaluated in order to ensure
adequate passive stability performance for integration of automatic flight systems and accurate
data acquisition in a high updraft flight envelope. The design presented by the #05008 PDR
document specifies empennage dimensions which result in vertical and horizontal tail volume
coefficients of 0.01 and 0.21, respectively. These values fall below generally accepted criteria
for highly stable flight, and are deficient when compared against the stability properties of
successful RIT Aero Design Heavy Lift planes designed for similar tasks. Software designed for
the RIT Aero Design team shows that the unmodified #05008 will possess a static margin below
7%, which is much too low for sustained flight in turbulent regions.
A least-squares optimization routine coupled with the previously existing RIT Aero
Design software was used to develop new tail volume coefficients for increased stability.
Vertical and horizontal tail volume coefficients of 0.06 and 0.3, respectively, were developed to
ensure stable flight with a static margin of 15 - 20%. The following tail dimensions were
49
recommended to the #05008 design team to reach the desired stability performance with a
minimum of modification to the original design.
bh (horizontal span) = 30”
ch (horizontal chord) = 8”
bv (vertical span) = 15”
cv (mean vertical chord) = 6”
Also computed were new control surface volume coefficients resulting in the dimensions
given below. The control characteristics selected are based on pervious experience design
control surfaces for aircraft of this type, and are confirmed by aeronautics reference texts.
Experience has shown that control surfaces for aircraft of this type must be slightly oversized
compared to full-scale aircraft. This is likely due to a loss in control surface effectiveness due to
low Reynolds number effects and high vortex flow lift loss over short spans.
bξ (aileron span) = 23”
cξ (aileron chord) = 2”
be (elevator span) = 30”
ce (elevator chord) = 2”
br (rudder span) = 15”
cr (rudder chord) = 2.5”
Other attributes that can improve stability with little to no cost of performance or
manufacturing complexity are the addition of main wing dihedral and aileron relocation. The
recommended changes are as follows:
1) Add 3°of dihedral to the main wing. This can also be expressed as a 2.75” rise over the
span from root to tip.
50
2) Relocate the ailerons so they are centered about the 2/3 half-span point. Vortex-induced
tip losses reduce aileron effectiveness when they are placed near the wingtips; however,
this loss of effectiveness is not considered in the standard aileron volume coefficient
formula. This is a misunderstanding which often results in the intuitive placement of the
ailerons at the extreme outboard edge of the wing, reducing their actual effectiveness.
All of the above recommendations were issued to the #05008 design team, and have been
implemented in the aircraft design, as of the publication of this document.
6.1.3 #05008 Airframe Weight Analysis - Cg
Center of gravity calculations were done to determine the ideal location for the wing. The
calculation provides a location for the wing that places the quarter chord of the wing at the center
of gravity of the airframe. All telemetry equipment used by the team along with airframe
components as specified by team #05008 were used to tabulate the theoretical center of gravity
by summing the moments created by the components and the airframe pieces. The Cg of the
quarter chord of the wing was found to be 29.38in. The results are summarized in Appendix B.
This information was then provided to team #05008 to help complete the airframe under
development.
6.1.2 Senior Telemaster Performance Analysis
As an alternative to the #05008 airframe, the Senior Telemaster aircraft design is offered
as a performance enhancing replacement. The Senior Telemaster is a highly affordable
commercially available kit plane designed to lay telecommunications cable between
mountaintops. The design payload is in excess of 40 N, and when coupled with the electric
powerplant from the #05008 aircraft, can be substantially increased. It is well known for its
51
docile handling qualities, and is often used to train radio controlled aircraft pilots. Power and
speed requirements for an aircraft carrying a 45 N payload were tabulated, resulting in plots of
CL3/2 / CD vs. Speed (Fig. 11) and CL / CD vs. Speed (Fig. 12), the local maximums of each
corresponding to the speed for best endurance and best range, respectively. The results of this
analysis are tabulated in Figure 13.
CL3/2/CD at Sea Level and Cruise Condition
0
2
4
6
8
10
12
14
0 5 10 15 20 25 30 35 40
Velocity (m/s)
CL3/
2 /CD
(CL3/2/CD)Max is 12.5
52
Figure 11: Plot of CL3/2 / CD vs. Speed
Lift to Drag Ratio vs. Velocity at Sea Level and Cruise Conditions
0
2
4
6
8
10
12
0 5 10 15 20 25 30 35 40
Velocity (m/s)
CL/
CD
(CL/CD)Max is 10.6.
Figure 12: CL / CD vs. Speed
Range and Endurance Calculations Lowest Power Consumption (W) 71.00Cruise at LPC (m/s) 9.00Stored Energy (W - h) 148.00
53
Endurance (h) 2.08Range at Lowest Consumption (km) 67.54 Best Range Consumption (W) 84.00Cruise at BRC (m/s) 13.00Stored Energy (W - h) 148.00Endurance (h) 1.76Range at BRC (km) 82.46 Energy Expenditure for 300m climb (W - h) 23.00Remaining Energy (W - h) 125.00Minimum Time to Altitude (s) 93.00Endurance at Altitude (h) 1.76
Figure 13: Tabulated results of Telemaster performance analysis
The handling qualities of the Senior Telemaster are well established by its excellent service
record in gusty mountain environments. The tail volume coefficients exceed those of the
redesigned #05008 airframe and a static margin of 20% or more can be achieved, resulting in a
high degree of passive stability. Simulator flight models are also commercially available for the
Senior Telemaster, enabling novice pilots to adapt to the handling qualities of the aircraft without
risking damage to the airframe or other onboard equipment. A speed of 15 m/s is recommended
for takeoff and landing, with estimated minimum runway lengths of 5 and 16 meters,
respectively. Landing field length could be reduced to within 10 meters through the addition of
brakes, if requested by the sponsor.
6.2 Motor Selection and Analysis
The motor and battery were chosen by team #05008 based on there preliminary design
completed during Senior Design I, term 20041. Once the motor and battery arrived, our team
conducted testing on the motor and battery to determine the thrust characteristics and battery life
to confirm the manufactures specifications. In order to test the motor effectively, a sled and
54
force transducer combination was used to determine the static thrust value. A mounting plate
was designed and machined to adapt an existing sled provided by the vibrations lab. This plate
will also allow the team and the sponsor to conduct future tests on the motor and alternate
propellers. From the data gathered in this initial testing phase, the static thrust value was found
to be 4.2 lbs.
6.3 Structural Design and Analysis
6.3.1 Structural Design
The mounting system for the electronics was based on two 2024-T4 aluminum L-
channels with a thickness of 0.1 inches and legs of a length of 0.75 inch. This type of aluminum
was chosen because it is typically used in structural applications. The electronic components
will be mounted on standoffs to aluminum plates of the same material. These plates will be
bolted to each of the rails. This allows alternate placements for the components to modify the
center of gravity of the airframe. It also enables each electronic component package to be
modular. For cross bracing, the two rails will be connected by two plates at each end. Finally,
the whole assembly will be bolted to the bulkheads of the airframe through four L-brackets. An
isometric view of the completed assembly can be seen in Figure 14 below. Detailed drawings
for all of these components can be found in Appendix C.
55
Figure 14: Rail Cage Assembly
56
6.3.2 Structural Analysis
This type of aluminum has a weight density of 0.1 lbs/in3. Adding all of the aluminum
parts, the electronic components, and miscellaneous fasteners resulted in a total assembly weight
of approximately 16 oz, or 1 lb.
PartWeight
(oz) QuantityTotal (oz)
AP50 Autopilot 1.76 1 1.76TX-9500 2.1 1 2.1Rail 2.7 2 5.4Plate (3x6x0.1") 2.9 1 2.9Plate (3x3x0.1") 1.4 1 1.4Plate (3.5x0.75x0.1") 0.4 2 0.8Bracket 0.17 4 0.68Misc. fasteners 0.96 1 0.96
Total 16
Figure 15: Table of total weights
The loading scenario defined for the analysis was a 6G drop. The total force applied will be 6
lbs. This type of loading would be typical in a semi-moderate crash landing. The worst-case
loading scenario on the rail cage itself would be if the total load was borne by a single rail, and it
was applied at the opposite corner of the other rail through a rigid plate. This is a conservative
modeling scenario because in actuality, the load would be borne by both rails and the plates
would also deflect to absorb some of the load. A diagram of this loading is shown in Figure 16
below.
57
Figure 16: Worst-case loading scenario
Using the principle of superposition, this problem can be decoupled into an asymmetric beam
bending and a torsion problem. The results of each can then be added to provide a total solution.
58
Figure 17: Decoupled stress scenario
6.3.2.1 Asymmetric Beam Bending
Asymmetric beams add to the complexity of stress prediction because the cross moments
of inertia are no longer zero. This introduces coupling between the two directions of the cross-
section. The first step in completing this type of analysis is to locate the centroid of the cross-
section. Then the each of the second area moments of inertia can be calculated. For ease of
computation, the cross-section was split into two separate sections as shown in Figure 18 below.
Figure 18: Cross-section dimensions and section divisions
The centroid in the y and z directions can be calculated using the following formulas.
∑ ⋅=i
ii AyA
y 1 ∑ ⋅=i
ii AzA
z 1
Once the centroid has been calculated, the y-z axis can be placed as shown below.
59
Figure 19: Centroid location and axis placement
The second area moments of inertia for each section are then calculated and summed, making
use of the Parallel Axis Theorem when necessary. The Parallel Axis Theorem states that the
moment of inertia about a parallel axis not located through the centroid of the section can be
calculated by the adding the moment of inertia of the section about its own centroid and area of
the section multiplied by the distance to the axis of rotation.
2_ dAII centroidaxisparallel ⋅+=
Typically, bending stresses for symmetric cross sections are calculated using the linear relation
yI
Mx =σ , where
IM
is typically a constant as long as the cross-section remains constant along
the x direction. Since the rail under consideration has a constant cross-section we can assume a
stress field of the following form.
zcycx 21 +=σ (1)
Equilibrium of moments requires that
60
dAzM xy ⋅⋅= ∫ σ(2)
dAyM xz ⋅⋅=− ∫ σ(3)
Substituting Eqn.1 into Eqns. 2 and 3, and making use of the definitions,
∫ ⋅= dAzI y2 ∫ ⋅= dAyI z
2 ∫ ⋅⋅= dAzyI yz
results in the following equations.
yyyz MIcIc =+ 21
zyzz MIcIc −=+ 21
Solving for c1 and c2,
( ) zyyz
yzyzy
IIIIMIM
c−
−= 21
( ) zyyz
zyyzz
IIIIMIM
c−
−−= 22
In order to locate the maximum stress locations, it is necessary to determine the neutral axis of
the beam. The neutral axis is defined as the axis along which bending stresses are zero. In this
situation,
021 =+ zcyc
Rearranging,
61
yzzzy
yzyzy
IMIMIMIM
cc
yz
++
==−
= βtan2
1 .
Solving for β,
yzzzy
yzyzy
IMIMIMIM
++
= −1tanβ
The values for the constants defined by the above formulas appear in Figure 20 below.
224.0=y in224.0=z in00725.0=yI in4
00725.0=zI in4
00424.0=yzI in4
0=yM72=zM in-lbs150931 −=c
88272 =c lbs/in3
°= 6.59β
Figure 20: Table of calculated values
Showing the angle β on the cross-section of the beam reveals that points A and B are the furthest
from the neutral axis (Figure 21).
Figure 21: Location of neutral axis
62
Given the orientation of the moment, this implies that point A has the maximum compressive
stress and point B has the maximum tensile load. Point A has the coordinates (y,z) = (0.526,
-0.224) and point B has the coordinates (y,z) = (-0.224, 0.526). Substituting the above tabulated
values and the coordinates into Eqn. 1 results in a maximum compressive stress at point A of
9916 psi and a maximum tensile stress at point B of 8024 psi.
6.2.3.2 Transverse Shear
The maximum shear force is in the y direction and has a value of 6 lbs. The maximum
transverse shear will occur in the thinner portion of the cross-section. Using the formula
bIVQ
zxy =τ , where V is the shear force, Q is the first area moment of inertia, Iz is as previously
defined, and b is the thickness of the section under examination. Q is defined as ∫ ⋅= dAyQ and
is calculated to be 0.0138 in3. The transverse shear at point A is calculated to be 114 psi, and at
point B is 15 psi.
6.2.3.3 Torsion
Based on the placement of the load, the torque applied (T) is 19.7 in lbs. A closed form
solution for the shear stress due to torsion for the cross-section that we have defined does not
exist. A good approximation is given as 21
max 23
tbT=τ , where b1 is the leg length and t is the
thickness of the cross-section. The maximum shear stress due to torsion is 3940 psi. A torsional
stress concentration will exist in the fillets of the cross-section. The stress concentrations are
63
calculated using the Trefftz criteria where 3max74.1
rt
fillet ⋅⋅= ττ . Given our thickness to radius
ratio of 1:1, the stress concentrations will have a value of 6860 psi.
6.2.3.4 Principal Stresses and Failure Criteria
The stress state for point A is
[ ]
=
114.00000932.30932.3024.8
σ ksi.
The principal stresses for this state are {σ1, σ2, σ3} = {-1.61, 0.114, 9.63} ksi. The stress state for
point B is
[ ]
−=
015.00000932.30932.3916.9
σ ksi.
The principal stresses for this state are {σ1, σ2, σ3} = {-11.29, 0.015, 1.37} ksi. The Von Mises
failure criteria, which is typical to use for ductile materials such as aluminum, is as follows,
( ) ( ) ( )[ ]213
232
2215.0 σσσσσσσ −+−+−=vm .
Calculating the Von Mises stress for point A and point B results in 10.48 ksi and 12.04 ksi. The
yield strength of 2024-T4 Aluminum is 47 ksi. This gives us an overall static margin at point A
and point B of 450% and 390% respectively. This analysis clearly shows that we have
considerable margin over the worst-case expected loading of the electronics mounting structure.
64
6.2.4 Camera Mounting System Design
A mounting fixture is provided along with the camera package. The mounting fixture
will be bolted to the foremost bulkhead of the aircraft. A small hole for the camera lens will be
cut in the fuselage cowling. More advanced vibration testing with the motor running at various
speeds and accelerometers placed at the camera mounting location will be conducted next
quarter. From the results of that testing, vibration damping, if any will be applied to the
mounting structure.
6.4 Power Consumption
To meet the requirements of the sponsor, power calculations were performed to
determine the maximum requirement of each subsystem. This allowed the team to determine the
endurance time of the airborne sensing platform and determine necessary battery to provide
power for the telemetry vision guidance and other sensors. The total power consumption was
found to be 105.5 Whrs for a little over an hour of flight time. See Appendix D.
6.5 Battery Selection
At this time the 18.5 Volt 8000 mAhr (148 Whrs) Li-Polymer battery will be designed to
power only the motor for isolation and redundancy. A separate battery was chosen based on the
power consumption of the electronics. The battery to be used at this time is a 14.8 Volt 2100
mAhr (14.6 Whrs) Li-Polymer battery. This lower voltage will also aid in voltage regulations
for the various components.
65
6.6 Vision Guidance System Design and Analysis
6.6.1 Camera Design
The team has selected a mini black-and-white camera with audio capabilities. The 14.8-
volt Li-Polymer battery supplies power for the entire camera system as shown in Figure 22. A
12-volt, positive voltage regulator and decoupling capacitor combination provides a constant
voltage to the camera and the transmitter. The regulator vendor recommends a 0.33uF capacitor
at the input and 0.1uF capacitor at the output of the regulator for the lengths of wire that this
project requires. The team may add components to this system in the future, such as switches for
system testing and component isolation. The team will test the individual components before
subsystems and the entire system. This will minimize the consequences of utilizing a faulty part.
An RCA cable transmits the NTSC video signal from the camera to the transmitter’s video input
connector. The transmitter broadcasts a 900Mhz signal to the receiver at the base station as
shown in Figure 23.
66
GNDVout
Battery
U1
23 45 67 89
1114
15 1617 1819
1312
1
10
2022242628303234363840
25
31
37
23
39
21
27
35
29
33
J1
J1 Connector
GN
D
VoutVin
M C7812
U4
Regulator
Regulator
GN
D
VoutVin
M C7805
U5
AutoPilot 50
POWERGND
Port 1 AILPort 2 ElePort 3 ThrPort 4 RudPort 5 GearPort 6 FLPPort 7 Au1Port 8 Au2Port 9 Ch9
Antenna
Receiver
Video_OutPower 12vGND
Cam era
U2
Antenna
Video_In
Power 12vGND
T x_9500
U6
Transmitter
2 RCVR POWER3 Ch1 Ailerons4 Ch2 Elev ator5 Ch3 Throttle6 Ch4 Rudder7 Ch5 Flaps8 unused
1 GNDRCVR
12 V
12 V
5 V
To Servos
To Servos
C10.1uF
C20.33uF
C3 0.33uF C4 0.1uF
14.8V
GPSAntenna
67
Figure 22: Wiring Diagram of Camera System
Figure 23: Vision Guidance System Diagram
6.6.2 RF Link Budget Analysis
In order to predict the components necessary to achieve a successful communication link
at two miles it was essential to perform a link budget analysis. This analysis uses theoretical
calculations to determine the losses associated with free space transmission, cables, and
connectors. The typical losses associated with these parameters are determined by the operating
frequency, in this case 900 MHz. The calculations use the center frequency of the 900 MHz
68
spectrum, which is assumed to be 912 MHz. Three sets of calculations were performed. Each
set had identical parameters with the exception of the output power. These calculations are only
used to get an idea of what is needed to meet the sponsor requirement of two miles. At a
minimum, the goal was to achieve link margin of 30 dB, which would account for unexpected
losses such as foliage, weather, buildings, etc. Any component that is improving over the
theoretical calculations can be expected to improve the overall link. In other words, a
component that reduces loss, increases power, or provides increased gain is expected to improve
to the link. The calculations used and the results are shown in Appendix E. These results were
used to determine the transmitters/receivers, antennas, and operating frequency.
6.6.3 Communications System Design
The implementation of each component in the communication system plays a
determining factor in the system performance. Some important parameters are connector
adapters, cable lengths, and antenna positioning. The antennas chosen for the platform require
an MMCX connector. To incorporate the antenna with the video system, an N-type female to
MMCX adapter is used. To incorporate the antenna with the integrated Maxstream radio this is
not required, as both components utilize the MMCX connector. Testing will be performed to
determine the best position of the antennas on the plane. Several options include mounting them
to the vertical stabilizer, mounting them to the side of the plane just before the tail, or mounting
the antennas to the bottom of the plane. The goal is to utilize as much of the radiation pattern as
possible, while minimizing interference from the plane and other RF sources on the platform.
The position of the antennas is the determining factor in the length of the transmission cables;
however, the routing of the cables will minimize this required length.
69
6.7 Telemetry and Stability Augmentation System Design and Analysis
6.7.1 Control
Figure 24: Control System Diagram
[logic and wiring diagrams [base station, speed controller, AP50, RC receiver, servo
connections, voltage regulators etc] NOT SURE WHAT’S GOING ON HERE!!!
70
6.8 Launch
The method for launching the platform specified by team #05008 was hand launch.
However, hand launching this platform given the size and handling characteristics could prove to
be dangerous to the operator and potentially damaging to the onboard equipment. A winch
launching system for the airborne sensing platform was investigated as an alternative. The
winch launcher provides approximately 15 minutes more endurance time over a hand launched
system. Also the winch launcher minimizes the potential for injury and equipment failure by
accelerating the platform via a small motor and cable system. See Appendix F for a picture and
link to the manufacturer web site.
7.0 FUTURE PLANS
At this time, the team has completed the major design portion of the project. The task to
be undertaken during the spring session of Senior Design II is system integration and testing. As
Senior Design II begins, the team plans to test components as they arrive from vendors and
complete the necessary machining and circuitry associated with the systems designed. Slight
design modification will occur as needed and systems integration into the airframe will then
begin according to the schedule below. Then the prototype will undergo testing in preparation
for demonstration to the Center for Imaging Science at the end of Senior Design II in May. See
Schedule below.
71
Spring Production Schedule
Task Name Start Date Finish DatePlane Construction 2/26/2005 3/16/2005Purchasing 2/26/2005 3/25/2005Class1 3/11/2005 3/11/2005Meet with team to Review Design 3/11/2005 3/11/2005Detailed CAD Plane & SubSystems 3/14/2005 3/18/2005Website Development 3/14/2005 4/29/2005Analysis & Synthesis 3/14/2005 4/15/2005Individual Tasks 3/14/2005 4/15/2005Class 2 3/18/2005 3/18/2005Test Airframe 3/21/2005 4/15/2005Meet with Sponsor 3/21/2005 3/21/2005Class 3 3/25/2005 3/25/2005Machine Telemetry Structure 3/28/2005 4/8/2005Test Electrical Components 3/28/2005 4/8/2005Class 4 4/1/2005 4/1/2005Class 5 4/8/2005 4/8/2005Test Subsystem Assemblies 4/11/2005 4/15/2005Class 6 4/15/2005 4/15/2005Test Prototype 4/18/2005 4/29/2005Update Bill of Materials 4/18/2005 4/18/2005Write CDR Techical Paper 4/19/2005 5/6/2005Class 7 4/22/2005 4/22/2005Class 8 4/29/2005 4/29/2005Demonstrate Prototype 5/2/2005 5/6/2005Class 9 5/6/2005 5/6/2005Sanity Check 5/9/2005 5/9/2005Practice CDR Presentation 5/11/2005 5/11/2005Class 10 CDR 5/13/2005 5/13/2005
Week 9 Week 10Week 5 Week 6 Week 7 Week 8Week 1 Week 2 Week 3 Week 4
Figure 25: Projected Schedule
8.0 BUDGET
The combined budget for this project and the project being completed by team #05008
totals $10,000. Approximately 10% of the overall budget has been allotted to team #05008;
therefore, the goal is to complete our portion of the project with a budget of $9,000. Based on
the current Bill of Materials we are target to complete the project under budget. See Appendix G.
We expect some additional purchases to arise during Senior Design II as we continue with
assembly and test of the subsystems and airframe; however, we do not expect these additional
costs to exceed the given budget for the project.
9.0 CONCLUSION
The team has completed the first portion of Senior Design and created a preliminary
design for the Airborne Sensing Platform test bed. Although this was extremely challenging, the
true difficulty will arise when integration and testing begins next quarter. The team has
attempted to anticipate trouble areas and allow the schedule to accommodate such pitfalls. The
72
team will rely on individual team member skills, departmental, and sponsor assistance to
successfully complete a working prototype for the Center of Imaging Science at the end of
Senior Design II in May of 2005. The team has created a strong set of documentation throughout
the project, both in the PDR and the technical data package binder. This will assist the team in
completing the project on time, under budget, and to the specifications of the Center for Imaging
Science.
73
APPENDIX A – AIRFRAME STABILITY CALCULATIONS
Takeoff Performance Equations Used
2LDpD KCCC +=
eARK
πφ=
eARa
aa
π0
0
3.571+
=
( )0αα −= aCL
payloademptygross WWW +=
bcS =
LSCVL 2
21 ρ=
DSCVD 2
21 ρ=
cbAR =
74
Symbols:
α = AoA = angle of attack
0α zero-lift angle of attack
AR wing aspect ratio
0a 2-D lift coefficient slope
a 3-D lift coefficient slope
b wing span
c wing chord
LC lift coefficient
DC drag coefficient
PDC parasite drag coefficient
75
Stability & Control Equations Used
α
α
L
M
CC
inMStatic−
=arg_
cSlSV TT
H ⋅⋅=
4/cxac =
ee
tLHMcg
CVC δ
δ∂∂
−=∆ ,
76
( )( ) ( )( ) ( )( ) ( )( )
( )( ) ( )( ) ( )( ) ( )( )
)(
cossinsincos
cossinsincos
,0
21
2
21
2
21
2
21
2
222
1
11
1
11
1
11
1
111
ee LMWLM
TrimLMLMe
McgtailMcgwMcgwMcg
tailHTTMcgtail
w
cqwDw
w
cqwLw
w
acwcqDw
w
acwcqLwMacwMcgw
w
cqwDw
w
cqwLw
w
acwcqDw
w
acwcqLwMacwMcgw
CCCCCCCC
CCCC
VaC
cz
Cc
zC
cxx
Cc
xxCCC
cz
Cc
zC
cxx
Cc
xxCCC
δααδ
ααδ
αη
αααα
αααα
⋅−⋅⋅+⋅
−=
++=
⋅⋅⋅−=
−
+
−+
−+=
−
+
−+
−+=
Symbols:
HV horizontal tail volume
TS horizontal tail area
acx horizontal distance from reference plane to
aerodynamic center of subscripted component
cgx horizontal distance from reference plane to CG
cgz vertical distance to CG of subscripted
component
APPENDIX B – CG CALCULATIONS
Cg Calculation
W total = 11.352 lbs. L total = 48.5 in h empennage = 10 inW empennage = 0.600 lbs. L fuselage = 33.5 in h telemetry = 18 inW telemetry = 1.000 lbs. L empennage= 12 in h battery = 39.5 inW battery = 1.713 lbs. L cowling = 3 in h fuselage = 28.75 inW fuselage = 2.000 lbs. h cowling = 47 inW cowling = 0.400 lbs. h motor = 47 inW motor = 0.851 lbs. h payload = 39.5 inW payload = 3.000 lbs. h camera = 47 inW camera = 0.094 lbs. h tail = 4 inW total05009 = 1.094 lbs.W tail = 0.600 lbs.
#05009 Components
Cg*Wtotal05009=Wtelemetry*htelemetry+Wcamera*hcamera
Cg 5009 = 20.485714 in
Cg total = 29.3575 in
Assumptions: 1/4 Chord of Wing is Placed at CgWhen actual measurements were not available, PDR data was usedCg total does not include tailh distance referenced from empennage
ComponentsIndividuali
hWWCn
iiitotalg
≡
=∗ ∑=1
*
77
78
APPENDIX C – DETAILED STRUCTURAL DRAWINGS
79
80
81
82
83
APPENDIX D – PATH LOSS CALCULATIONS
( )
)()()(Margin
)()()(
)()()/(
)(20)(2056.35
1.0)(
)()(/
1010
LosSpaceFreeBudgetPowerRxBudgetPowerTx
LossConnectorLossCableGainAntennaySensitivitBudgetPowerRx
LossConnectorLossCablePowerAntennaTxBudgetPowerTx
MilesinLengthLinkLogMHzinFrequencyLogLossSpaceFree
GHzinFrequencyConnectorsOfNumberLossConnector
Lengthft
LossLossCable
GainAntennaTxPCowerTxPowerAntennaTx
−+=
−−+=
−−=
++=
×=
×=
+=
84
85
86
APPENDIX E – POWER BUDGET ANALYSIS
87
Component mA V mW (max) Runtime (min) Total Energy Used Used (Whr)Motor Climb 4870.00 18.50 90095.00 13.50 2.03E+01Motor Cruise/Loiter 4060.00 18.50 75110.00 60.00 7.51E+01Auto Pilot 50 150.00 8.00 1200.00 80.00 1.60E+00Camera (VC-210B-Audio) 90.00 12.00 1080.00 80.00 1.44E+00Servos 500.00 5.00 2500.00 73.50 3.06E+00Pitot Tube 80.00 0.00E+00Pressure Transducer 80.00 0.00E+00Temp Sensor (SMT 160-30) 0.20 5.00 1.00 80.00 1.33E-03900 MHz Transmitter (TX-9500) 250.00 12.00 3000.00 80.00 4.00E+00
148.00 Energy Available (Whr)105.49 Energy Consumed (Whr)42.51 Energy Remaining (Whr)
negligiblenegligible
Assume 2.5 ft/sec climb to 1000 feet
APPENDIX F – WINCH LAUNCH
88
APPENDIX G – BILL OF MATERIALS
2/18/2005
Product NumberTeam
ChargedDescription Status Quantity
Retail Price Per Unit
Total Price
LXPT40 #05008 Tower Hobbies Build-It CA- Thick Glue 2 oz. Arrived 1 $5.99 $5.99#05008 Derek Aero-Team Tail Build Complete 1 N/A $200.00
LXPT38 #05008 Tower Hobbies Build-It CA Thin Glue 2 oz. Arrived 1 $5.99 $5.99LXK110 #05008 Great Planes CA Hinges 3/4"x1" (24) Arrived 1 $2.99 $2.99LXL431 #05008 Hobbico Latex Foam Rubber 1/2" Arrived 3 $4.49 $13.47LXK108 #05008 Great Planes Nylon Control Horns Large (2) Arrived 3 $0.95 $2.85LX3609 #05008 Astro Flight Power Supply 13.5V Arrived 1 $74.95 $74.95
LXFWW2 #05008 Astro Flight 109 Lithium Charger 1-9 Cell 7.5 Amps BackOrder 1 $114.99 $114.99LXHRC2 #05008 APC 13x10 Folding Prop Arrived 2 $7.19 $14.38LXZL06 #05008 APC folding Propeller hub 45mm Arrived 2 $4.79 $9.58LXJD33 #05008 Tower Hobbies Plywood 1/8x6x12" Arrived 2 $1.79 $3.58LXJD32 #05008 Tower Hobbies Plywood 1/16x6x12" Arrived 2 $1.49 $2.98LXD867 #05008 Dubro Threaded Rod 2-56 12" (6) Arrived 1 $2.89 $2.89LXN666 #05008 Hitec HS-225MG Mighty Mini BB MG Servo J Arrived 4 $27.99 $111.96LXHV43 #05008 Top Flite Monokote Blue 6' Arrived 1 $10.99 $10.99
PM412018 #05008 AXI4120-18 Model Motors - DC Motor Arrived 1 $139.00 $139.00JESAP70P #05008 Jeti 70A Speed Controller Arrived 1 $147.20 $147.20
#05008 18.2v Lithium Battery Arrived 1 $399.00 $399.00PM41002 #05008 AXI4120 Model Motors - Motor Mount Arrived 1 $18.50 $18.50LXK196 #05008 Great Planes Nylon Wing Bolt ¼-20x2 (4) Arrived 3 $1.25 $3.75
#05009 9 Channel Futaba Radio Controller Pending 1 $799.99 $799.99#05009 AP50 AutoPilot Autonomous Flight Hardware: GPS, Inertial, Rx/Tx Pending 1 $5,000.00 $5,000.00
VC-210B-AUDIO #05009SONY CCD Camera w/Audio CH- Circuit Specialists Inc (yahoo store) http://shop.store.yahoo.com/webtronics/mibwcav.html4 Pending 1 $34.50 $34.50
#05009 Aluminum stock McMaster Pending 1 $22.48 $22.48399-2054-ND #05009 Digikey.com - Capacitor, ceramic, 0.1uF,50V Pending 5 $0.21 $1.05399-2099-ND #05009 Digikey.com - Capacitor, ceramic, 0.33uF,50V Pending 5 $0.83 $4.15
MC7812CTOS-ND #05009 Digikey.com - Regulator, pos, 1A, 12V Pending 2 $0.58 $1.16MC7805CTOS-ND #05009 Regulator, pos, 1A, 5V Pending 2 $0.58 $1.16
LXHUP0 #05009 Futaba R319DPS 9-Channel PCM Receiver Synthesized Pending 1 $179.99 $179.99LXH258 #05009 Futaba TK50 & 72 FM/PCM Transmitter Module Pending 1 $54.99 $54.99
#05009 TX-9500 A/V Mini-Transmitter Pending 1 $129.99 $129.99#05009 RX-900 A/V Receiver www.eyespyvideo.com Pending 1 $109.99 $109.99#05009 Winch System - Tom McCann Pending 1 $600.00 $600.00#05009 Telemaster Building Materials Pending 1 $200.00 $200.00
A09-HBMM-P5I #05009 Omni Directional Airborne Antenna - MaxStream Pending 2 $25.00 $50.00OD9-6 #05009 Omni Dir. Basestation Antenna - Streak Wave (Order Online) Pending 2 $68.95 $137.90
TP2100-4S #05009 14.8 V 2100 mAh 4 Cell Li Polymer Battery Pending 1 $99.95 $99.95
Total Budget: $10,000 Subtotal: $8,291.11
Percent Spent: 82.91%
Rochester Institute of Technology, www.designserver.rit.edu
Bill of Materials*Covers Costs incured by team #
05008 & #05009
90