Upload
others
View
18
Download
0
Embed Size (px)
Citation preview
SECUNDA SYNFUELS OPERATIONS - TAR, PHENOSOLVAN & SULPHUR
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT
16.4.28.34 EV1 - FEED PREPARATION PLANT
03 JUNE 2019
CONFIDENTIAL
WSP Environmental (Pty) Ltd.
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT
16.4.28.34 EV1 - FEED PREPARATION PLANT
SECUNDA SYNFUELS OPERATIONS - TAR,
PHENOSOLVAN & SULPHUR
TYPE OF DOCUMENT (VERSION)
CONFIDENTIAL
PROJECT NO.: 41101534
DATE: JUNE 2019
WSP
BUILDING C
KNIGHTSBRIDGE, 33 SLOANE STREET
BRYANSTON, 2191
SOUTH AFRICA
T: +27 11 361 1392
F: +27 11 361 1381
WSP.COM
Q U A L I T Y M A N A G E M E N T
ISSUE/REVISION FIRST ISSUE REVISION 1 REVISION 2 REVISION 3
Remarks Draft for Review –
Compliance Audit
EA Ref:
16.4.28.34 EV1
Draft for Review –
Compliance Audit
EA Ref:
16.4.28.34 EV1
Date April 2019 June 2019
Prepared by Ziyaad Kadwa Ziyaad Kadwa
Signature -
Checked by Jenny Cope Jenny Cope
Signature
Authorised by Jenny Cope Jenny Cope
Signature
Project number 41101534 41101534
Report number 1 1
File reference file:///W:\000 NEW Projects\41101534 - Sasol EA and EMP Audits\42 ES\2-REPORTS\
S I G N A T U R E S
PREPARED BY
-
Ziyaad Kadwa
Consultant
REVIEWED BY
Jenny Cope
Associate
This Compliance Audit report (Report) has been prepared by WSP Environmental (Pty) Ltd (WSP) on behalf
and at the request of Sasol Synfuels: Secunda Operations (Client), to provide the Client with an understanding
of their compliance with the conditions included in the Environmental Authorisation.
Unless otherwise agreed by us in writing, we do not accept responsibility or legal liability to any person other
than the Client for the contents of, or any omissions from, this Report.
To prepare this Report, we have reviewed only the documents and information provided to us by the Client or
any third parties directed to provide information and documents to us by the Client. We have not reviewed any
other documents in relation to this Report, except where otherwise indicated in the Report.
P R O D U C T I O N T E A M
CLIENT
SHE: Environmental Compliance
Specialist
Broni van der Meer
Tar, Phenosolvan & Sulphur Production
Senior Manager
July Mavuso
WSP
Associate Jenny Cope
Lead Auditor Anri Scheepers
Lead Auditor Ashlea Strong
Consultant Ziyaad Kadwa
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT Project No. 41101534 SECUNDA SYNFUELS OPERATIONS - TAR, PHENOSOLVAN & SULPHUR
WSP June 2019
TABLE OF CONTENTS
1 INTRODUCTION ........................................ 1
1.1 Terms of Reference ................................................. 1
1.2 Construction and Operation of the Feed
Preparation Plant (Authorisation Number:
16.4.28.34 EV1)......................................................... 1
2 AUDIT SCOPE ........................................... 3
3 AUDIT METHODOLOGY ........................... 4
3.1 Audit Checklist ........................................................ 4
3.2 Site Inspection ......................................................... 4
3.3 Documentation Considered ................................... 4
3.4 Audit Compliance Assessment .............................. 4
3.5 Audit Team ............................................................... 5
3.6 Assumptions and Limitations ................................ 6
4 AUDIT FINDINGS ...................................... 7
5 SUMMARY OF THE AUDIT FINDINGS ... 15
5.1 Environmental Authorisation ............................... 15
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT Project No. 41101534 SECUNDA SYNFUELS OPERATIONS - TAR, PHENOSOLVAN & SULPHUR
WSP June 2019
TABLES
TABLE 1: COMPLIANCE LEVEL DEFINITION AND TARGET COMPLETION DATES .................. 5
TABLE 2: AUDIT FINDINGS – ENVIRONMENTAL AUTHORISATION ......................... 7
TABLE 3: SUMMARY OF EA COMPLIANCE AUDIT FINDINGS ........................ 15
FIGURES
FIGURE 1: SSO – FEED PREPARATION PLANT (SOURCE: GOOGLE EARTH, 2018) ............................... 2
FIGURE 2: NUMBER/COUNT CONTRIBUTION OF FINDINGS MADE TO THE EA CONDITIONS PER SECTION ............................ 16
FIGURE 3: OVERALL COUNT FINDINGS ON COMPLIANCE TO THE EA CONDITIONS .............................. 16
FIGURE 4: PERCENTAGE CONTRIBUTION OF FINDINGS MADE TO THE EA CONDITIONS PER SECTION ..... 17
FIGURE 5: OVERALL PERCENTAGE FINDINGS ON COMPLIANCE TO THE EA CONDITIONS ................ 17
APPENDICES
A ENVIRONMENTAL AUTHORISATION (16.4.28.34 EV1)
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT Project No. 41101534 SECUNDA SYNFUELS OPERATIONS - TAR, PHENOSOLVAN & SULPHUR
WSP June 2019
Page 1
1 INTRODUCTION
1.1 TERMS OF REFERENCE
Sasol South Africa (Pty) Limited operating through its Secunda Synfuels Operations (Sasol) appointed WSP
Environmental (Pty) Ltd (WSP) as an independent environmental consultant, to undertake a compliance audit
and compile an audit report according to the requirements of the National Environmental Management Act (No.
107 of 1998) as amended (NEMA). This report presents the findings of the compliance audit completed for the
Environmental Authorisation (EA) (Reference number: 16.4.28.34 EV1 issued on 03 January 2002) for the
period December 2014 to February 2019.
1.2 CONSTRUCTION AND OPERATION OF THE FEED
PREPARATION PLANT (AUTHORISATION NUMBER:
16.4.28.34 EV1)
Sasol received an EA for the construction and operation of the Feed Preparation Plant (FPP) at the Carbo-Tar
Plant, to recover valuable products from the organic waste streams. The FPP treats and processes waste by
means of centrifugation and filtration, and cokes the remaining fraction. Products suitable for coking are
processed at U39 (which is outside the scope of this authorisation) and products suitable for fuel oil are stored
and sold.
The EA was issued by the Mpumalanga Department of Agriculture, Conservation and Environment, on 03
January 2002, and it has been confirmed that the construction phase was completed prior to December 2014 (i.e.
outside the audit period).
Figure 1 provides an overview of the location of the facility.
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT Project No. 41101534 SECUNDA SYNFUELS OPERATIONS - TAR, PHENOSOLVAN & SULPHUR
WSP June 2019
Page 2
Figure 1: SSO – Feed Preparation Plant (Source: Google Earth, 2018)
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT Project No. 41101534 SECUNDA SYNFUELS OPERATIONS - TAR, PHENOSOLVAN & SULPHUR
WSP June 2019
Page 3
2 AUDIT SCOPE The 7 April 2017 amendment to the Environmental Impact Assessment (EIA) regulations introduced the
requirement for the auditing for all EAs and EMPrs in effect on 8 December 2014 and submission of audit
reports to the Department of Environmental Affairs (DEA) by 7 December 2019 and every five years thereafter.
This audit is designed to meet the requirements of Regulation 34 of the EIA Regulations, 2014.
The audit period runs from December 2014 to February 2019, therefore any construction related conditions that
would have been relevant pre-December 2014 are considered not applicable (outside audit period).
The objective of the audit was to:
— Assess the level of compliance with the conditions of the EA;
— Identify and assess any new impacts and risks that result from undertaking the activity;
— Make recommendations in order to achieve compliance in terms of the EA; and
— Ensure the commitments contained in Condition 9.01 of the EA are completed, more specifically:
— “Records relating to the compliance/non-compliance with the conditions of the authorization must be
kept in good order. Such records must be made available on request by this Department within seven (7)
working days of the date of the written request by the Department for such records.”
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT Project No. 41101534 SECUNDA SYNFUELS OPERATIONS - TAR, PHENOSOLVAN & SULPHUR
WSP June 2019
Page 4
3 AUDIT METHODOLOGY The International Organisation of Standardisation (ISO) 14010, ISO 14011 and ISO 14012 guideline documents
were utilised as a template during the compliance audit process. This methodology ensures that the compliance
audit was conducted in a systematic and independent manner that was documented and objectively evaluated to
determine compliance to the EA conditions.
The audit process comprised the following:
— Confirmation of the audit checklist;
— Site inspection (12 March 2019);
— Review of documentation relevant to the conditions of the EA (e.g. records, permits/certificates/maintenance
logs/monitoring results/previous reports etc.); and
— Compilation of an audit report.
3.1 AUDIT CHECKLIST
WSP compiled an audit checklist to assist with the EA compliance audit (Section 4).
3.2 SITE INSPECTION
Ziyaad Kadwa conducted the site inspection on 12 March 2019. The findings and observations of the site visit
are recorded and summarised in Section 4 with evidence included in Table 2. Key personnel interviewed
included:
— Piet Kleynhans (Area Manager; TPS Production: Carbo Tar).
— Collin Jaynarain (Area Manager; Gas Liquor Separation: Unit 213).
3.3 DOCUMENTATION CONSIDERED
The following documentation was provided and considered:
— Environmental Authorisation: 16.4.28.34EV1_2002-01-03;
— SSO DQS ISO 14001 2015;
— Audit report_383569_ISO 14001_2015_stage2_2018-07-27;
— EA_EX Handover_SSO_TPS-CT-GLS-CTF;
— IWWMP SIC 2015 Final_2018-05-15;
— GWMonitor Report Aug 2018 Final_Prj6163_2018-10-31.pdf;
— CT_GLS and CTF_2016-11-07;
— Waste Management Procedure_SGR-SHE-000017_Rev10_2017-09;
— AEL Sasol Synfuels 0016-2018-F03 (2018);
— SOX Folder;
— Environmental Complaints Register_2019-02-18; and,
— Various email correspondence.
3.4 AUDIT COMPLIANCE ASSESSMENT
WSP utilised a pre-prepared audit checklist to assist with the audit execution (Table 2 ). The checklist included
the conditions and associated requirements as specified in the EA.
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT Project No. 41101534 SECUNDA SYNFUELS OPERATIONS - TAR, PHENOSOLVAN & SULPHUR
WSP June 2019
Page 5
Each condition was verified, either by reviewing documentation, interviewing employees and/or visually
inspecting the facility. Each condition was rated in accordance with Table 1 below, and recommendations with
associated target completion dates included.
It should be noted that some of the EA conditions were apportioned according to the elements requiring
compliance assessment therein. Although some elements of the condition may have been compliant, if one of
the elements was determined to be non-compliant, the entire condition has been reported as such (and counted
as such during percentage compliance calculation). This apportionment further allowed for the development of
focussed recommendations and timeframes.
Table 1: Compliance Level Definition and Target Completion Dates
COMPLIANCE LEVEL DEFINITION
Compliant (C) Sasol could provide evidence for compliance with the commitment and condition and/or
relevant actions were implemented.
Non-compliant (NC) Specified commitments, conditions and documents were not in place or implemented
according to the requirements of the EA. Non-complaint conditions are given target
completion dates, as follows:
— Short term: 0 – 6 months.
— Medium term: 6 – 12 months.
— Long term: 12 – 18 months.
Not applicable (N/A) These are commitments are either not required yet or not applicable to Sasol.
— Conditions marked as “Noted” are considered information points only.
— Where conditions are considered “not auditable” within the scope of this assessment this
is stated and explained within the condition commentary.
Refer to Section 4 for the detailed audit findings (including evidence, recommendations and target completion
dates).
3.5 AUDIT TEAM
The Consultant, Ziyaad Kadwa, was hosted by Broni van der Meer, Piet Kleynhans, and Collin Jaynarain, to
whom we express our gratitude for their time and attention during our visit. A brief summary of the external
auditors’ experience is provided below.
— Auditor: Ziyaad Kadwa
Ziyaad has 8 years’ experience. He completed his National Diploma in Agriculture (Plant and Animal
Production) at Cedara College of Agriculture in 2010. He then completed his Bachelor of Technology at the
Nelson Mandela Metropolitan University in 2012, specialising in Agricultural Management. He completed it
part time whilst working at the KZN Department of Agriculture, Environmental Affairs, and Rural
Development for 3 years. He is currently completing his BSc Honours in Environmental Management part
time at the University of South Africa. Ziyaad has experience working as an Environmental Auditor for a
number of high profile clients in various industries. He has three years of auditing experience, and has
successfully completed general and permit or licence specific audits for the ROSE Foundation, Sappi, RBM,
Impala Platinum and NPC (InterCement). He has also done environmental management programme audits
for BRPM and for various infrastructure projects as part of environmental control officer duties.
— Project Manager and Quality Assurance: Jenny Cope
Jenny is an environmental due diligence specialist, with over 11 years’ experience in the Environmental
Sector. Jenny’s experience includes managing and completing projects and portfolios internationally;
undertaking both detailed and broad Environmental, Health & Safety compliance and audits of across a
range of sectors. Jenny’s recent experience includes completion and management of several pan-European
and global projects requiring reviews of extensive virtual data rooms, on a very rapid turnaround, and
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT Project No. 41101534 SECUNDA SYNFUELS OPERATIONS - TAR, PHENOSOLVAN & SULPHUR
WSP June 2019
Page 6
providing clients with ‘red flag’ reports to give clear commercial advice. Jenny has worked both in
environmental consultancies and with a developer, giving context to understanding the practicalities of
implementing recommendations.
3.6 ASSUMPTIONS AND LIMITATIONS
This Report has been prepared by WSP on behalf and at the request of Sasol, to provide the Client an
understanding of the Relevant Documents.
Unless otherwise agreed by us in writing, we do not accept responsibility or legal liability to any person other
than the Client for the contents of, or any omissions from, this Report.
To prepare this Report, we have reviewed only the documents and information provided to us by the Client or
any third parties directed to provide information and documents to us by the Client. We have not reviewed any
other documents in relation to this Report and except where otherwise indicated in the Report.
The findings, recommendations and conclusions given in this report are based on the author’s best scientific and
professional knowledge, as well as available information. This report is based on survey and assessment
techniques which are limited by time and budgetary constraints relevant to the type and level of investigation
undertaken; WSP and its staff reserve the right to modify aspects of the report including the recommendations if
and when new information may become available from on-going research or further work in this field, or
pertaining to this investigation.
Although WSP exercises due care and diligence in rendering services and preparing documents, WSP accepts
no liability, and Sasol, by receiving this document, indemnifies WSP and its directors, managers, agents and
employees against all actions, claims, demands, losses, liabilities, costs, damages and expenses arising from or
in connection with the services rendered, directly or indirectly by the use of the information contained in this
document.
This report must not be altered or added to without the prior written consent of the author. This also refers to
electronic copies of this report which are supplied for the purposes of inclusion as part of other reports.
Similarly, any recommendations, statements or conclusions drawn from or based on this report must make
reference to this report. If this report is used as part of a main report, the report in its entirety must be included
as an appendix or separate section to the main report.
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT Project No. 41101534 SECUNDA SYNFUELS OPERATIONS - TAR, PHENOSOLVAN & SULPHUR
WSP June 2019
Page 7
4 AUDIT FINDINGS Table 2: Audit Findings – Environmental Authorisation
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
1. GENERAL CONDITIONS
1.01 This authorization refers only to the project specified above
and described in the Record of Decision. Separate
applications must be lodged for any other development
and/or activity at or near proposed development, which is
covered by Sections 21 and 22 of the Act and Government
Notice R1182 and R1183 of 5 September 1997.
N/A Noted. The activity remains as specified and no further alterations
or applications have been made.
None.
1.02 Authorization is only granted in terms of Section 22 (3) of
the Environmental Conservation Act, 1989 (Act 73 of 1989)
and does not exempt the holder from compliance with any
other relevant legislation.
N/A Noted. A full legal review does not form part of the scope of this
audit.
The Sasol Complex operates with a dedicated environmental and
legal teams, and therefore ensures that they comply with applicable
legislation.
In addition, site is operated under ISO14001:2015, which requires
the compilation of a legal register. Furthermore, WSP has been
provided with the 2018 ISO audit for review, which confirms
conformance with requirements to determine compliance
obligations, and how these apply to the organisation.
Evidence:
— SSO DQS ISO 14001 2015; and,
— Audit report_383569_ISO 14001_2015_stage2_2018-07-27.
None.
1.03 No development may take place on the site of concern
without the necessary permits/approvals and/or service
and/or lease agreements, where it is relevant, from or
between the following institutions:
C The Sasol Complex operates with a dedicated environmental and
legal teams, and therefore ensures that they comply with applicable
legislation.
None.
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT Project No. 41101534 SECUNDA SYNFUELS OPERATIONS - TAR, PHENOSOLVAN & SULPHUR
WSP June 2019
Page 8
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
1.3.1 CAPCO
1.3.2 DWAF
1.3.3 Highveld East Municipality (for record purpose)
Sasol is in possession of an AEL (issued per business unit) and has
an updated Integrated Water and Waste Management Plan
(IWWMP) (updated 2018) that applies to the whole complex.
Evidence:
— IWWMP SIC 2015 Final_2018-05-15; and,
— AEL Sasol Synfuels 0016-2018-F03 (2018).
1.04 This Department may change, add or amend any of the
conditions in this authorization if, in the opinion of the
Department, it is environmentally justified.
N/A Statement noted by Sasol. No changes or amendments have been
communicated to Sasol by the Department since issue of the EA.
None.
1.05 A copy of this authorization shall be available at the
premises of the Feed Preparation Plant at all times and all
staff, contractors, contractors and sub-contractors shall be
acquainted or made to be acquainted with the content of this
authorization.
C Sasol’s environmental team have soft copies of the EA and
where/when necessary, communicate any specific details or
requirements to the relevant business units.
Additionally, copies are maintained at the SHE: Environment
department and on SAP EC and SharePoint. Any specific
requirements are communicated during SHE induction training.
Sasol provided the auditor with the evidence that the responsible
person, Chwayita Faku (Senior Manager of CT, GLS & CTF
Production Area, was made aware of the EA on 25 September
2016.
Evidence:
— EA_EX Handover_SSO_TPS-CT-GLS-CTF.
None.
1.06 The contents of this authorization should be made known to
all interested and affected parties. N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None.
2 ESTABLISHMENT OF THE ENTERPRISE
2.01 This authorization is repealed if the construction has not
taken place within two (2) years from the date of this
authorization.
N/A This condition is considered outside of the audit period
(construction pre-2014). It is therefore considered not applicable.
None.
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT Project No. 41101534 SECUNDA SYNFUELS OPERATIONS - TAR, PHENOSOLVAN & SULPHUR
WSP June 2019
Page 9
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
2.02 In the event of decommissioning or closure of the FPP, sell
or transfer ownership of the infrastructure on the site in any
way, this Department must be informed of such a decision at
least 12 months prior to the date of closure or transfer of
ownership.
N/A Statement noted by Sasol. Closure is not yet planned for and
according to Sasol, is estimated to occur around 2050.
None.
2.03 In case of closure of the FPP, this Department shall evaluate,
monitor and approve the decommissioning and rehabilitation
of the site.
N/A Statement noted by Sasol. Closure is not yet planned for and
according to Sasol, is estimated to occur around 2050.
None.
3 CONSTRUCTION & OPERATION
3.01 If any changes need to be made to the FPP and/or associated
infrastructure, this Department must be informed thirty (30)
days in advance, to be able to decide whether the changes
need authorization.
N/A The activity remains as specified and no further alterations or
applications have been made.
None.
3.02 Sufficient provision must be made in the annual budget for
the mitigation of the environmental impacts during the
operation and rehabilitation of this site in the event of
closure of the FPP.
C Statement noted by Sasol. Closure is not yet planned for and
according to Sasol, is estimated to occur around 2050.
Due to being listed on the New York Stock Exchange, Sasol is
required to adhere to the Sarbanes Oxley (SOX) legislation in the
US which requires transparent financial disclosure, including its
environmental liabilities, to be included in the company financial
statements. Provision is made for the removal of surface
infrastructure, in line with the future land use, as well as for the
remediation of areas that would remain a liability post-closure in
terms of potential future contamination.
Evidence:
— SOX Folder.
None.
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT Project No. 41101534 SECUNDA SYNFUELS OPERATIONS - TAR, PHENOSOLVAN & SULPHUR
WSP June 2019
Page 10
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
4. AIR POLLUTION
4.01 Air pollution should be handled as indicated by the relevant
authorities. Any emissions must be permitted by CAPCO. C Sasol has a valid Atmospheric Emission Licence (AEL) that was
issued by the Gert Sibande District Municipality. The AEL
(reference: 0016/2014/F01) is valid to 31 March 2020.
According to the Environmental Team, Sasol works closely with
the local authority and operates units in line with the AEL and
minimum legal emission requirements.
The incidents registers for 2015- 2017 and 2017- 2019 do indicate
any emission exceedances from the plant.
Evidence:
— Compliance_Air_Secunda Complex
— Copy of Environment Impact register_ New FY17
— Environment Impact register_ New FY19_2019-02-18
— AEL Sasol Solvents 0017-2015-F02 (2015)
None.
5. WATER POLLUTION
5.01 It is the responsibility of the applicant and the relevant
contractor on the site to prevent any pollution of the surface
as well as groundwater.
C Surface water is managed at the site; the tanks and loading areas
are within hard surfaced and bunded areas that drain to an enclosed
system that pumps the water for reprocessing.
Surface water monitoring is done on a weekly basis as well as real
time for the various Receiving Environment Surface Monitoring
(RESMs).
Ground water monitoring is conducted biannually and quarterly.
The is no groundwater monitoring specific to the FPP, however
there are 6 active boreholes located within the Primary area which
are utilised for monitoring. The auditor note a number of
exceedances in the November 2017 sampling run, however these
exceedances cannot be directly attributed to FPP.
None.
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT Project No. 41101534 SECUNDA SYNFUELS OPERATIONS - TAR, PHENOSOLVAN & SULPHUR
WSP June 2019
Page 11
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
The latest IWWMP as well as surface and ground water
monitoring results were provided to the auditor as evidence. The
nearest surface water quality monitoring locations (RESM-6 and
RESM-7) showed results within limits.
Evidence:
— IWWMP SIC 2015 Final_2018-05-15; and,
— GWMonitor Report Aug 2018 Final_Prj6163_2018-10-
31.pdf.
5.02 In case of non-compliance with Section 19 of the National
Water Act, 1998 (Act 36 of 1998), the applicant will be held
responsible to remedy the effects of pollution.
N/A Statement noted by Sasol. None.
6. WASTE MANAGEMENT
6.1 All waste generated during the construction and/or operation
of the FPP shall be store, handled and disposed of in an
environmentally acceptable way.
C This construction related requirement of this condition is
considered outside of the audit period (construction pre-2014). It is
therefore considered not applicable.
During normal operation, a sludge is produced that is captured
within enclosed skips. This sludge is not discarded but is
recovered.
A small amount of contaminated materials and general waste is
generated at the FPP and handled according to Sasol’s Waste
Management Procedure.
Evidence:
— CT_GLS and CTF_2016-11-07; and,
— Waste Management Procedure_SGR-SHE-
000017_Rev10_2017-09.
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT Project No. 41101534 SECUNDA SYNFUELS OPERATIONS - TAR, PHENOSOLVAN & SULPHUR
WSP June 2019
Page 12
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
7. RISK ASSESSMENT
7.01 Risk assessment should be handled as indicated by the
relevant authorities. C Sasol has a Governance SHE Risk and Assurance department that
assesses environmental risks and drives implementation per
business unit.
The SHE Environment department facilitates Environmental Risk
Assessments per business entity to ensure that gaps are addressed
through implementation of mitigation measures via the Integrated
Management System. Sasol further addresses all Key Undesirable
Events (KUEs) from a group perspective.
All risk documentation is saved on the Sasol IMS; a folder
containing the risk assessments undertaken for TPS was shown to
the auditor in a screenshot of the IMS system folders.
None.
7.02 Fire extinguishing should be available at the site at all times. C Fire extinguishing equipment was inspected during the site
walkover and noted to be within service dates.
Fire Extinguisher at the Feed Preparation Plant – Within
Service Dates
None.
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT Project No. 41101534 SECUNDA SYNFUELS OPERATIONS - TAR, PHENOSOLVAN & SULPHUR
WSP June 2019
Page 13
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
8. MONITORING
8.01 Monitoring should be done as indicated by the relevant
authorities.
C According to Sasol’s Environmental Compliance Specialist, the
monitoring completed is as per the requirements in the AEL and
IWWMP.
Monitoring of surface and groundwater, and emissions monitoring
measures, are in place and was observed by the auditor during the
site inspection.
None.
9. REPORTING
9.01 Records relating to the compliance/non-compliance with the
conditions of the authorization must be kept in good order.
Such records must be made available on request by this
Department within seven (7) working days of the date of the
written request by the Department for such records.
N/A This audit represents the first required audit for this EA. Prior to
the introduction of the 7 April 2017 amendment to the
Environmental Impact Assessment (EIA) regulations, no audit
against this EA was required.
None.
9.02 Non-compliance with, or any deviations from the conditions
as set out in the Record of Decision is regarded as an
offence and, after reasonable provision has been made for
remedial action, will be dealt with in terms of Sections 29,
30 and 31A of the Act.
N/A Statement noted by Sasol. None.
9.03 Any complaint regarding the said development must be
brought to the attention of this office within 24 hours after
receiving the complaint.
C All environmental complaints received from interested and
affected parties, both internal and external to the organisation, are
recorded in a complaints register that is maintained by Sasol’s
Environmental Department. Complaints are investigated and
reported in line with the procedure (SGR-SHE-000022)) and as per
legal requirements.
Environmental complaints contact details are communicated to
internal and external stakeholders.
None.
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT Project No. 41101534 SECUNDA SYNFUELS OPERATIONS - TAR, PHENOSOLVAN & SULPHUR
WSP June 2019
Page 14
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
The complaints register (FY 2014-2019) was checked and no
complaints related to the Feed Preparation Plant were recorded for
this audit period.
Evidence:
— Environmental Complaints Register_2019-02-18.
9.04 A complaint register must be kept up to date for inspection
by members of this Department. C All environmental complaints received from interested and
affected parties, both internal and external to the organisation, are
recorded in a complaints register that is maintained by Sasol’s
Environmental Department. Complaints are investigated and
reported in line with the procedure (SGR-SHE-000022)) and as per
legal requirements.
Environmental complaints contact details are communicated to
internal and external stakeholders.
The complaints register (FY 2014-2019) was checked and no
complaints related to the Feed Preparation Plant were recorded for
this audit period.
Evidence:
— Environmental Complaints Register_2019-02-18.
None.
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT Project No. 41101534 SECUNDA SYNFUELS OPERATIONS - TAR, PHENOSOLVAN & SULPHUR
WSP June 2019
Page 15
5 SUMMARY OF THE AUDIT FINDINGS
5.1 ENVIRONMENTAL AUTHORISATION
The audit findings have been summarised into the following categories: compliance, non-compliance and not
applicable. The overall audit findings concerning compliance to the EA conditions are as listed in Table 3
below.
Table 3: Summary of EA Compliance Audit Findings
SECTION OF THE EA NO. COMMITMENTS C NC N/A
GENERAL CONDITIONS 6 2 0 4
ESTABLISHMENT OF THE ENTERPRISE 3 0 0 3
CONSTRUCTION & OPERATION 2 1 0 1
AIR POLLUTION 1 1 0 0
WATER POLLUTION 2 1 0 1
WASTE MANAGEMENT 1 1 0 0
RISK ASSESSMENT 2 2 0 0
MONITORING 1 1 0 0
REPORTING 4 2 0 2
Total Count 22 11 0 11
Total Percentage - 50% 0% 50%
Percentage Compliance with Applicable Conditions 100%
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT Project No. 41101534 SECUNDA SYNFUELS OPERATIONS - TAR, PHENOSOLVAN & SULPHUR
WSP June 2019
Page 16
Figure 2 illustrates the number/count contribution of the findings of the EA per section while Figure 3 presents
the total proportion of compliance for the facility.
Figure 2: Number/Count contribution of findings made to the EA conditions per Section
Figure 3: Overall count findings on compliance to the EA conditions
0
1
2
3
4
5
6
7
Sectional Count Contribution
C
NC
N/A
11
0
11
Total Compliance
C
NC
N/A
ENVIRONMENTAL AUTHORISATION COMPLIANCE AUDIT REPORT Project No. 41101534 SECUNDA SYNFUELS OPERATIONS - TAR, PHENOSOLVAN & SULPHUR
WSP June 2019
Page 17
Figure 4 illustrates the percentage contribution of the findings of the EA conditions. Figure 5 presents the total
percentage compliance for the facility.
Figure 4: Percentage contribution of findings made to the EA conditions per Section
Figure 5: Overall percentage findings on compliance to the EA conditions
0102030405060708090
100
Sectional Percentage Contribution
C
NC
N/A
50%
0%
50%
Total Percentage Compliance
C
NC
N/A
APPENDIX
A ENVIRONMENTAL AUTHORISATION
(16.4.28.34 EV1)