Amount R Item No Quantity Rate FOR UNIVERSITY OF SOUTH AFRICA AT MUCKLENEUK CAMPUS TO CVV 3RD FLOOR BUILDING PROPOSED ALTERATIONS AND REFURBISHMENTS SECTION NO 1 BILL NO 1 PRELIMINARIES The JBCC Principal Building Agreement (March 2014 Edition 6.1) prepared by the Joint Building Contracts Committee shall be the applicable building agreement, amended as hereinafter described BUILDING AGREEMENT AND PRELIMINARIES The JBCC Principal Building Agreement contract data from an integral part of this agreement The ASAQS Preliminaries (March 2014 edition) published by the Association of South African Quantity Surveyors for use with the JBCC Principal Building Agreement shall be deemed to be incorporated in these bills of quantities The contractor is deemed to have referred to the above- mentioned documents for the full intent and meaning of each clause The clauses in the above-mentioned documents are herein after referred to by clause number and heading only. Where standard clauses or alternatives are not entirely applicable to this agreement such modifications, corrections or supplements as will apply are given under each relevant clause heading and such modifications, corrections or supplements shall take precedence not withstanding anything to the contrary contained in the above-mentioned documents Where any item is not relevant to this agreement such item is marked N/A (signifying “not applicable”) -1- Preliminaries Bill No. 1 PRELIMINARIES Delta Quantity Surveyors CC Carried to Abstract R

SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

AmountR

ItemNo

Quantity Rate

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

SECTION NO 1

BILL NO 1

PRELIMINARIES

The JBCC Principal Building Agreement (March 2014 Edition 6.1) prepared by the Joint Building Contracts Committee shall be the applicable building agreement, amended as hereinafter described

BUILDING AGREEMENT AND PRELIMINARIES

The JBCC Principal Building Agreement contract data from an integral part of this agreement

The ASAQS Preliminaries (March 2014 edition) published by the Association of South African Quantity Surveyors for use with the JBCC Principal Building Agreement shall be deemed to be incorporated in these bills of quantities

The contractor is deemed to have referred to the above-mentioned documents for the full intent and meaning of each clause

The clauses in the above-mentioned documents are herein after referred to by clause number and heading only. Where standard clauses or alternatives are not entirely applicable to this agreement such modifications, corrections or supplements as will apply are given under each relevant clause heading and such modifications, corrections or supplements shall take precedence not withstanding anything to the contrary contained in the above-mentioned documents

Where any item is not relevant to this agreement such item is marked N/A (signifying “not applicable”)

-1-

PreliminariesBill No. 1PRELIMINARIES

Delta Quantity Surveyors CC

Carried to Abstract R

Page 2: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

The Model Preambles for Trades (September 2008 edition) as published by the Association of South African Quantity Surveyors shall be deemed to be incorporated in these bills of quantities and no claims arising from brevity of description of items fully described in the said Model Preambles will be entertained

PREAMBLES FOR TRADES

Supplementary preambles are incorporated in these bills of quantities to satisfy the requirements of this project. Such supplementary preambles shall take precedence over the provisions of the said Model Preambles

The contractor's prices for all items throughout these bills of quantities must take account of and include for all of the obligations, requirements and specifications given in the said Model Preambles and in any supplementary preambles

Should he contractor select Option A in terms of clause 26.9.4 of the contract data for the purpose of adjustment of these preliminaries, the amount entered into the amount column in these preliminaries is to be divided into one or more of the three categories provided namely fixed (F), value related (V) and time related (T)

PRICING OF PRELIMINARIES

PRINCIPAL BUILDING AGREEMENT (JBCC-CODE EDITION 6.1, MARCH 2014)

Item

Clause 1.0 - Definitions and interpretation F:............................. V:............................ T:............................

1

INTERPRETATION

Item

Clause 2.0 - Law, Regulations and Notices F:............................. V:............................ T:............................

2

-2-

PreliminariesBill No. 1PRELIMINARIES

Delta Quantity Surveyors CC

Carried to Abstract R

Page 3: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

ItemClause 3.0 - Offer and Acceptance F:............................. V:............................ T:............................

3

Item

Clause 4.0 - Assignment and Cession F:............................. V:............................ T:............................

4

ItemClause 5.0 - Contract Documents F:............................. V:............................ T:............................

5

ItemClause 6.0 - Employer’s Agents F:............................. V:............................ T:............................

6

ItemClause 7.0 - Design Responsibility F:............................. V:............................ T:............................

7

ItemClause 8.0 - Works risk F:............................. V:............................ T:............................

8

INSURANCE AND SECURITY

ItemClause 9.0 - Indemnities F:............................. V:............................ T:............................

9

ItemClause 10.0 - Insurances F:............................. V:............................ T:............................

10

ItemClause 11.0 - Security F:............................. V:............................ T:...........................

11

ItemClause 12.0 - Duties of the Parties F:............................ V:............................T:............................

12

EXECUTION

ItemClause 13.0 - Setting Out F:............................. V:............................ T:............................

13

Item

Clause 14.0 - Nominated Subcontractors F:......................... V:............................ T:............................

14

-3-

PreliminariesBill No. 1PRELIMINARIES

Delta Quantity Surveyors CC

Carried to Abstract R

Page 4: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

Item

Clause 15.0 - Selected Subcontractors F:......................... V:............................ T:............................

15

ItemClause 16.0 - Direct Contractors F:............................. V:............................ T:............................

16

ItemClause 17.0 - Contract Instructions F:............................. V:............................ T:............................

17

Item

Clause 18.0 - Interim Completion = N/S Subcontract Agreement F: ............................ V:...........................T:...........................

18

COMPLETION

ItemClause 19.0 - Practical Completion F:.......................... V:............................ T:............................

19

ItemClause 20.0 - Sectional Completion F:.......................... V:............................ T:............................

20

Item

Clause 21.0 - Defects Liability Period and Final Completion F:............................. V:............................ T:............................

21

Item

Clause 22.0 - Latent Defects Liability Period F:.......................... V:............................ T:............................

22

Item

Clause 23.0 - Revision of the Date for Practical Completion F:............................. V:............................ T:............................

23

Item

Clause 24.0 - Penalty for Late or Non-Completion F:............................. V:............................ T:............................

24

ItemClause 25.0 - Payment F:............................. V:............................ T:............................

25

PAYMENT

-4-

PreliminariesBill No. 1PRELIMINARIES

Delta Quantity Surveyors CC

Carried to Abstract R

Page 5: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

Item

Clause 26.0 - Adjustment of the Contract Value and Final Account F:............................. V:............................ T:............................

26

Item

Clause 27.0 - Recovery of Expense and/or Loss F:............................. V:............................ T:............................

27

Item

Clause 28.0 - Suspension by the Contractor F:............................. V:............................ T:............................

28

SUSPENSION AND TERMINATION

ItemClause 29.0 - Termination F:............................. V:............................ T:............................

29

ItemClause 30.0 - Dispute Resolution F:............................. V:............................ T:............................

30

DISPUTE RESOLUTION

Agreement

AGREEMENT

Category : Fixed R.........................................................

Category : Value R.........................................................

Category : Time R.........................................................

SUMMARY OF CATEGORIES

-5-

PreliminariesBill No. 1PRELIMINARIES

Delta Quantity Surveyors CC

Carried to Abstract R

Page 6: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

Preliminaries

Section No. 1

Bill No. 1

AmountR

PageNo

COLLECTION PAGE

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

5Total Brought Forward from Page No.

4Total Brought Forward from Page No.

3Total Brought Forward from Page No.

2Total Brought Forward from Page No.

1Total Brought Forward from Page No.

-6-

PreliminariesBill No. 1PRELIMINARIES

Delta Quantity Surveyors CC

Carried to Final Summary R

Page 7: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

AmountR

ItemNo

Quantity Rate

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

SECTION NO. 3

BILL NO. 1

ALTERATIONS

The contractor is referred to the Model Preambles for Trades (2008 Edition) as issued by the Association of South African Quantity Surveyors before pricing this bill.

PREAMBLES

TEMPORARY BARRIERS, SCREENS, ETC

399m

Dust screen 3000mm high between concrete floor and ceiling formed of suitable timber framing with 375 micronpolyethylene sheeting stapled on including corners, ends, etc

1

Temporary barriers, screens, etc including removal

REMOVAL OF EXISTING WORK

143m²Half brick wall2

Breaking down and removing brickwork etc

949m²One brick wall3

30NoTimber single door and steel frame not exceeding 2,5m2

4

Taking out and removing doors, windows, etc including thresholds, sills, etc and prepare opening for new doors, windows, etc elsewhere measured

-7-

AlterationsBill No. 1BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 8: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

2,625m²Gypsum plasterboard suspended ceilings including cornices, timber brandering, etc

5

Taking down and removing roofs, floors, panelling, ceilings, partitions, etc

502mDrywall partitioning 3000m high including doors, ironmongery, glazed borrowed lights, etc

6

191mCurtain wall partitioning 3000m high including doors, ironmongery, glazed borrowed lights, etc

7

209mTimber joinery fittings size 1000 x 800mm high (Provisional)

8

Taking out and removing joinery fittings etc

2,625m²30mm Screed from floors9

Hacking up/off and removing granolithic, screeds, plaster, etc from concrete or brickwork and preparing surfaces for new screeds, plaster, etc

2,892m²Internal plaster from walls and columns10

1,770m²Porcelain/Ceramic tiles to floors11

Hacking up/off and removing ceramic tile floor and wall finishes including skirtings, removing mortar bed or backing and preparing concrete or brick surfaces for new screed, plaster or tile finishes

308m²Porcelain/Ceramic tiles to walls12

200mGalvanised steel piping including fittings and brackets13

Taking out and removing piping, sanitary fittings, etc including disconnecting piping from fittings and making good floor and wall finishes (making good tiling and paintwork elsewhere)

250mCopper piping including fittings and brackets14

150m50mm uPVC piping including fittings and brackets15

-8-

AlterationsBill No. 1BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 9: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

19NoVitreous china wash hand basin16

21NoVitreous china WC pan with cistern17

1NoStainless single steel sink including cupboard18

2NoStainless steel double sink including cupboard19

2NoVitreous china wall hung urinal with flush valve20

19NoMirror 800 x 800mm high from wall21

Taking out and removing glass and mirrors

2,625m²Making good defects in existing screeded floors with "Pavelite"

22

PREPARATORY WORK TO EXISTING SURFACES

MAKING GOOD OF FINISHES ETC

74mFloors where one brick walls removed23

Making good screed on

2,625m²Floors where tiles removed24

502mFloors where partitions removed25

200m²Timber floors26

Making good internal timber floors including sanding down, treating where needed by specialist (varnish elsewhere)

-9-

AlterationsBill No. 1BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 10: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

Alterations

Section No. 2

Bill No. 1

AmountR

PageNo

COLLECTION PAGE

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

9Total Brought Forward from Page No.

8Total Brought Forward from Page No.

7Total Brought Forward from Page No.

-10-

AlterationsBill No. 1BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried Forward to Summary of Section No. R

Page 11: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

AmountR

ItemNo

Quantity Rate

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

SECTION NO. 3

BILL NO. 2

MASONRY

The contractor is referred to the Model Preambles for Trades (2008 Edition) as issued by the Association of South African Quantity Surveyors before pricing this bill.

PREAMBLES

SUPPLEMENTARY PREAMBLES

BRICKWORK

Where sizes in descriptions are given in brick units, "one brick" shall represent the length and "half brick" the width of a brick

Sizes in descriptions

Lintels shall bear at least 160mm onto adjacent walling. Where such bearing cannot be obtained due to the proximity of adjacent openings the lintel shall be continuous

Reinforced brick lintels

SUPERSTRUCTURE

143m²Half brick walls27

Brickwork of NFP bricks in class II mortar

949m²One brick walls28

-11-

MasonryBill No. 2BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 12: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

BRICKWORK SUNDRIES

561m75mm Wide reinforcement built in horizontally29

Brickwork reinforcement

3,720m150mm Wide reinforcement built in horizontally30

22mLintels in lengths not exceeding 3m31

Concrete prestressed fabricated lintels

-12-

MasonryBill No. 2BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 13: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

Masonry

Section No. 2

Bill No. 2

AmountR

PageNo

COLLECTION PAGE

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

12Total Brought Forward from Page No.

11Total Brought Forward from Page No.

-13-

MasonryBill No. 2BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried Forward to Summary of Section No. R

Page 14: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

AmountR

ItemNo

Quantity Rate

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

SECTION NO. 3

BILL NO. 3

CARPENTRY AND JOINERY

The contractor is referred to the Model Preambles for Trades (2008 Edition) as issued by the Association of South African Quantity Surveyors before pricing this bill.

PREAMBLES

Joinery

Descriptions of frames shall be deemed to include frames, transomes, mullions, rails, etc

SUPPLEMENTARY PREAMBLES

Descriptions of hardwood joinery shall be deemed to include pelleting of bolt holes

Fixing

Items described as "nailed" shall be deemed to be fixed with hardened steel nails or shot pins to brickwork or concrete

Decorative laminate finish

Laminate finish shall be glued under pressure. Edge strips shall be butt jointed at junctions with adjacent similar finish

DOORS, ETC

26No40mm Door 813 x 2032mm high32

Hollow core flush doors with commercial veneer on both sides hung to timber frames

-14-

Carpentry and JoineryBill No. 3BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 15: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

3No40mm Door, size 813 x 2100mm high33

1No40mm Door, size 813 x 2032mm high34

11No40mm single Door 900 x 2420m high35

Solid timber door hung to steel frames

7No40mm Double Door 1600 x 2420mm high36

-15-

Carpentry and JoineryBill No. 3BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 16: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

Carpentry and Joinery

Section No. 2

Bill No. 3

AmountR

PageNo

COLLECTION PAGE

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

15Total Brought Forward from Page No.

14Total Brought Forward from Page No.

-16-

Carpentry and JoineryBill No. 3BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried Forward to Summary of Section No. R

Page 17: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

AmountR

ItemNo

Quantity Rate

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

SECTION NO. 3

BILL NO. 4

CEILINGS, PARTITIONS, ETC

The contractor is referred to the Model Preambles for Trades (2008 Edition) as issued by the Association of South African Quantity Surveyors before pricing this bill.

PREAMBLES

SUPPLEMENTARY PREAMBLES

Items described as "nailed" shall be deemed to be fixed with hardened steel nails or pins or shot pinned to brickwork or concrete

Descriptions

Items described as "plugged" shall be deemed to include screwing to fibre, plastic or metal plugs at not exceeding 600mm centres, and where described as "bolted", the bolts are measured elsewhere

Electric light fittings, diffusers, panels, etc generally are "lay in" units of the same dimensions as the suspension grid described and allowance shall be made accordingly for their support, inclusive of any flexibility in setting out that may be required (ceiling panels have not been deducted and pricing shall take cognisance thereof)

Proprietary suspended ceilings

-17-

Ceilings, Partitions and Acess FlooringBill No. 4BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 18: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

SUSPENDED CEILINGS

Proprietary suspended ceilings

74m²Suspended flush plaster moisture resistant ceiling37

New Gyproc acoustic ceiling tiles 595 x 595mm, celotex mineral fibre, perforated white from saint Gabain to be on Donn Tee system and M6 wall angle.

131m²suspended flush plaster ceiling 38

49m²Horizontal bulkhead ceilings nailed not exceeding 1m below timber trusses soffits

39

35m²Laminated timber boards40

604mShadowline cornices 41

Cornices to suspended ceilings

Drywall partitioning shall comprise steel studding formed of 64mm top and bottom tracks with vertical studs at maximum 600mm centres, friction fitted or pop-riveted to the top and bottom tracks with similar additional vertical studs as necessary at abutments, ends, etc and covered as described with wallboard screwed to studding with drywall screws at maximum 220mm centres. Boards are to be butt jointed and finished with tape and readymix jointing compound all inaccordance with the manufacturer's instructions. Intersections and abutments are measured separately and descriptions shall be deemed to include any additional studs, corner beads, jointing compound, tape, etc

PARTITIONS ETC

223mPartitioning 3000mm high with bottom and top tracks plugged

42

" 90mm Drywall System No 1" steel stud partitioning with "Wallboard" on both sides

-18-

Ceilings, Partitions and Acess FlooringBill No. 4BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 19: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

47NoExtra over partition 3000mm high for vertical abutment43

33NoExtra over partition 3000mm high for fair end44

67NoExtra over partition 3000mm high for T-intersection45

45NoExtra over partition 3000mm high for corner46

7No

Extra over partition for 44mm solid flush panel door 813 x 2032mm high with commercial veneer on both sides and hardwood edge strips to vertical edges hung to and including standard bronze coated aluminium door frame with two pairs of 100mm heavy duty 100mm brass butt hinges including three lever lockset and additional studding, trimming, etc

47

Doors

-19-

Ceilings, Partitions and Acess FlooringBill No. 4BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 20: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

Ceilings, Partitions and Acess Flooring

Section No. 2

Bill No. 4

AmountR

PageNo

COLLECTION PAGE

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

19Total Brought Forward from Page No.

18Total Brought Forward from Page No.

17Total Brought Forward from Page No.

-20-

Ceilings, Partitions and Acess FlooringBill No. 4BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried Forward to Summary of Section No. R

Page 21: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

AmountR

ItemNo

Quantity Rate

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

SECTION NO. 3

BILL NO. 5

FLOOR COVERINGS, PLASTIC LININGS, ETC

The contractor is referred to the Model Preambles for Trades (2008 Edition) as issued by the Association of South African Quantity Surveyors before pricing this bill.

PREAMBLES

NOTE : All materials shall be in colours to be selected by the Representative/Agent and, where applicable, laid to approved patterns

SUPPLEMENTARY PREAMBLES

FLOOR COVERINGS

224m²On floors48

Approved carpet tiles by specialist (allow a PC of R 250.00 per square metre installed)

98m²On floors49

Approved wood laminate by specialist (allow a PC ofR 250.00 per square metre installed)

92mSkirting 100mm high50

306m100mm High Aluminium skirtings51

SKIRTINGS, NOSINGS, ETC

-21-

Floor CoveringsBill No. 5BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried Forward to Summary of Section No. R

Page 22: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

AmountR

ItemNo

Quantity Rate

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

SECTION NO. 3

BILL NO. 6

IRONMONGERY

The contractor is referred to the Model Preambles for Trades (2008 Edition) as issued by the Association of South African Quantity Surveyors before pricing this bill.

PREAMBLES

SUPPLEMENTARY PREAMBLES

Where applicable finishes to ironmongery are indicated by suffixes in accordance with the following list: BS Satin bronze lacquered CH Chromium plated SC Satin chromium plated SE Silver enamelled GE Grey enamelled AS Anodised silver AB Anodised bronze AG Anodised gold ABL Anodised black PB Polished brass PL Polished and lacquered PT Epoxy coated SD Sanded

Finishes to ironmongery

HINGES, BOLTS, ETC

60No100 x 75 x 3mm Brass butt hinge52

Approved

5NoH102SC type: 200 x 32mm Chromium plated brass barrel bolt

53

"Union"

-22-

IronmongeryBill No. 6BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 23: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

LOCKS

30No2157- 78SS three lever dead lock54

"Union"

30NoPS 53035-24S keyhole escutcheon55

HANDLES

30NoA6-300mm satin chrome brass offset pull handles56

"Union"

PUSH PLATES AND KICKING PLATES

30No813 x 1200mm Thick anodised aluminium kick plate57

"Solid"

DOOR CLOSERS

30NoTS73 standard arm door closer58

"Dorma"

SUNDRIES

30NoCZ8731SC door stop floor mounted59

"Union"

-23-

IronmongeryBill No. 6BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 24: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

Ironmongery

Section No. 2

Bill No. 6

AmountR

PageNo

COLLECTION PAGE

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

23Total Brought Forward from Page No.

22Total Brought Forward from Page No.

-24-

IronmongeryBill No. 6BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried Forward to Summary of Section No. R

Page 25: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

AmountR

ItemNo

Quantity Rate

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

SECTION NO. 3

BILL NO. 7

METALWORK

The contractor is referred to the Model Preambles for Trades (2008 Edition) as issued by the Association of South African Quantity Surveyors before pricing this bill.

PREAMBLES

Descriptions

Descriptions of bolts shall be deemed to include nuts and washers

Descriptions of expansion anchors and bolts and chemical anchors and bolts shall be deemed to include nuts, washers and mortices in brickwork or concrete

Metalwork described as "holed for bolt(s)" shall be deemed to exclude the bolts unless otherwise described

SUPPLEMENTARY PREAMBLES

PRESSED STEEL DOOR FRAMES

25NoFrame for door 813 x 2032mm high60

1,6mm Rebated frames suitable for half brick walls

5NoFrame for door 813 x 2032mm high61

1,6mm Rebated frames suitable for one brick walls

ALUMINIUM SHOPFRONTS

-25-

MetalworkBill No. 7BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 26: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

14NoPurpose made shopfront SH01, size 2500 x 3000mm high with one double door 1800 x 2400mm high

62

Powder coated aluminium shopfront with 6.38mm laminated safety clear/obscured glass with Low E coating with structural silicone all round and secret fixed glazing beads on one side including ironmongery, subframes, etc and plugged to brickwork or concrete

72NoPurpose made shopfront SH02, size 2500 x 3000mm high

63

10NoPurpose made shopfront SH04, size 7560 x 3000mm high with one single door 895 x 2100mm high

64

6NoPurpose made shopfront SH03, size 3650 x 3000mm high

65

-26-

MetalworkBill No. 7BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 27: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

Metalwork

Section No. 2

Bill No. 7

AmountR

PageNo

COLLECTION PAGE

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

26Total Brought Forward from Page No.

25Total Brought Forward from Page No.

-27-

MetalworkBill No. 7BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried Forward to Summary of Section No. R

Page 28: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

AmountR

ItemNo

Quantity Rate

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

SECTION NO. 3

BILL NO. 8

PLASTERING

The contractor is referred to the Model Preambles for Trades (2008 Edition) as issued by the Association of South African Quantity Surveyors before pricing this bill.

PREAMBLES

SCREEDS

1,831m²30mm Thick on floors 66

1:3 Screeds wood trowelled on concrete

INTERNAL PLASTER

1,770m²On walls67

Two coat plaster with gypsum finish on brickwork

31m²On narrow widths68

24m3 x 25mm Flat section brass dividing strip between different floor finishes

69

CORNER PROTECTORS, DIVIDING STRIPS, ETC.

-28-

PlasteringBill No. 8BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried Forward to Summary of Section No. R

Page 29: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

AmountR

ItemNo

Quantity Rate

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

SECTION NO. 3

BILL NO. 9

TILING

The contractor is referred to the Model Preambles for Trades (2008 Edition) as issued by the Association of South African Quantity Surveyors before pricing this bill.

PREAMBLES

SUPPLEMENTARY PREAMBLES

Unless described as "fixed with adhesive to plaster (plaster elsewhere)" descriptions of tiling on brick or concrete walls, columns, etc shall be deemed to include 1:4 cement plaster backing and descriptions of tiling on concrete floors etc shall be deemed to include 1:3 plaster bedding

Descriptions

WALL TILING

307m²On walls70

Porcelain wall tiles (allow a PC of R 250.00/m2 excluding VAT) fixed with adhesive to plaster (plaster elsewhere) and flush pointed with tinted waterproof jointing compound

10m²On narrow widths71

-29-

TilingBill No. 9BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 30: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

FLOOR TILING

169m²On floors 72

Porcelain floor tiles (allow a PC of R 250.00/m2 excluding VAT) fixed with adhesive to screed (screed elsewhere) and flush pointed with tinted waterproof jointing compound

206mSkirtings 100mm high 73

206mStainless steel brushed edge strip along the top edge of wall tiles

74

FLOOR TRIM, EXPANSION JOINT ETC

-30-

TilingBill No. 9BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 31: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

Tiling

Section No. 2

Bill No. 9

AmountR

PageNo

COLLECTION PAGE

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

30Total Brought Forward from Page No.

29Total Brought Forward from Page No.

-31-

TilingBill No. 9BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried Forward to Summary of Section No. R

Page 32: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

AmountR

ItemNo

Quantity Rate

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

SECTION NO. 3

BILL NO. 10

PLUMBING AND DRAINAGE (PROVISIONAL)

The contractor is referred to the Model Preambles for Trades (2008 Edition) as issued by the Association of South African Quantity Surveyors before pricing this bill.

PREAMBLES

SUPPLEMENTARY PREAMBLES

Tenderers are advised to study the Model Preambles for Trades (1995 edition) as recommended and published by the Association of South African Quantity Surveyors

PREAMBLES

Items, materials or methods to be used specified by trade names or catalogue numbers are only an indication of the quality required. Items, materials or methods of similar quality may be used with prior written approval from the Representative / Agent

TRADE NAMES

Reference shall be made to other trades for preambles and full descriptions of items not fully described in this trade which shall apply equally to work in this trade, unless otherwise described

DESCRIPTIONS AND PREAMBLES

-32-

Plumbing and Drainage (Provisional)Bill No. 10BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 33: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

Rates for all piping, fittings, etc shall include for all fixing in position of fittings, cutting of chases in brickwork or concrete, excavation of trenches, backfilling, etc unless otherwise described

RATES

Diameters stated for pipes, traps, valves, etc are internaldiameters, except uPVC, polyethylene, stainless steel and copper pipes for which external diameters are stated

DIAMETER OF PIPES

Where fittings have reducing ends or branches they are described as "reducing"

In the case of pipes with diameters not exceeding 60mm, only the largest end or branch is given. Should the contractor wish to use other fittings and bushes or reducers, he may do so on the understanding that no claim in this regard will be entertained

In the case of pipes with diameters exceeding 60mm, all sizes are given and no claim for extra bushes, reducers, etc will be entertained

REDUCING FITTINGS

Sewer and drainage pipes and fittings shall be according to SABS 791, jointed and sealed with butyl rubber rings

Soil, waste and vent pipes and fittings shall be according to SABS 967 and solvent jointed

Cold water supply pressure pipes and fittings shall be according to SABS 966 and jointed by means of the "Lyng" type jointing system

Pipes shall be fixed and jointed according to SABS 0112

uPVC PIPES AND FITTINGS

-33-

Plumbing and Drainage (Provisional)Bill No. 10BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 34: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

Pipes shall be hard drawn and half-hard pipes of the class stated. Class 0 (thin wall hard drawn) pipes shall not be bent. Class 1 (thin walled half-hard), class 2 (half-hard) and class 3 (heavy walled half-hard) pipes shall only be bent with benders with inner and outer formers. Fittings to copper pipes, capillary soldier fittings and compression fittings shall be Cobra Watertech or other equal approved type. Capillary soldier fittings shall comply with ISO 2016

COPPER PIPES

HDPE pipes shall be according to SABS 533 and fittings shall be of plastic compression type jointing. Jointing and laying shall be in accordance with the manufacturer's instructions

HEAVY DUTY POLYETHYLENE PIPING (HDPE)

Descriptions of gutter outlets, etc shall be deemed to include wire balloon gratings

WIRE GRATINGS

SANITARY FITTINGS

19No

Vitreous china semi close couple washdown pan comprising 90 degrees outlet open rim, flushing valve including lid and accessories and heavy duty seat, and including 20mm BSP with union brass built-in front access box type toilet flushing valve complete with galvanised box, stainless steel concealing cover plate, flush pipe, elbow and pan connector and with ability to maintain water pressure at 100 - 600 kPa.

75

Water Closet

-34-

Plumbing and Drainage (Provisional)Bill No. 10BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 35: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

2No

Paraplegic vitreous china floor mounted washdown suite, colour White, comprising,semi close couple 900

outlet open rim washdown pan and matching 9 Litre cistern, including lid, fitments, purpose made chromium plated side flush lever and double flap heavy duty plasticseat all fixed in accordance with manufacturer's instructions.

76

Paraplegic Water Closet

17No

Vitreous china wall mounted basin, colour white, size 510 x 400mm with two tap holes including integrated overflow and chainstay hole bolted to wall with two 10mm bolts and sealed with silicone sealant where basin meets wall.

77

Wash hand basin

2No

Wall mounted paraplegic basin colour white, size 510 x 405mm with one tap hole including intergrated overflow and chainstay hole bolted wall with two 10mm bolts and including floor mounted pedestal and sealed with silicone sealant where basin meets wall with 2 x medical elbow action pillar tap with raised nose and blue and red indicater 1/4 turn ceramic disc 1/2 BSP male connection inlet Hot on left / Cold on right complete with pop-up waste mounting kit. Manufactured in accordance with SANS 226:2004 Type 2

78

6No

White vitreous wall mounted top inlet urinal, size 600 x 385 x 380mm fixed on and including two hanger brackets

79

Urinal

2NoDouble centre bowl sink code 313852 inset type size 1800 x 535mm complete

80

Sink

-35-

Plumbing and Drainage (Provisional)Bill No. 10BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 36: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

1No

Polished stainless steel sink size 1000 x 460mm, Grade 304 18/10 single end drop in bowel size 350 x 460 x 140mm deep, fitted onto cupboard (elsewhere measured) fixed in accordance with manufacturer's instructions.

81

WASTE UNIONS ETC

19No32mm Cobra no 301 waste union82

"Cobra Watertech" or equal approved

3No40mm Cobra no 317-40 sink waste83

TRAPS ETC

3No38 x 38mm Deep seal "P" or "S" trap84

Rubber

3No40 x 300mm Sink combination for double bowl with reseal "P" trap

85

25No50mm No.365/50 chromium plated bottle trap86

"Cobra Watertech" or equal approved

TAPS, VALVES ETC

3NoTivoli Monza Sink mixer pillar type87

"Cobra Watertech" or equal approved

19NoTivoli Riveira basin mixer88

HOLES ETC

16No200mm Reinforced concrete slab, beam, wall, etc89

Core drilling of hole for pipe not exceeding 100mm diameter

-36-

Plumbing and Drainage (Provisional)Bill No. 10BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 37: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

17No200mm Reinforced concrete slab, beam, wall, etc90

Core drilling of hole for pipe not exceeding 100mm and not exceeding 150mm diameter

21No200mm Reinforced concrete slab, beam, wall, etc91

Core drilling of hole for pipe not exceeding 150mm and not exceeding 300mm diameter

-37-

Plumbing and Drainage (Provisional)Bill No. 10BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 38: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

Plumbing and Drainage (Provisional)

Section No. 2

Bill No. 10

AmountR

PageNo

COLLECTION PAGE

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

37Total Brought Forward from Page No.

36Total Brought Forward from Page No.

35Total Brought Forward from Page No.

34Total Brought Forward from Page No.

33Total Brought Forward from Page No.

32Total Brought Forward from Page No.

-38-

Plumbing and Drainage (Provisional)Bill No. 10BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried Forward to Summary of Section No. R

Page 39: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

AmountR

ItemNo

Quantity Rate

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

SECTION NO. 3

BILL NO. 11

ELECTRICAL WORKS

The contractor is referred to the Model Preambles for Trades (2008 Edition) as issued by the Association of South African Quantity Surveyors before pricing this bill.

PREAMBLES

General trenching work for sleeves along the routes as pegged out on site after co-ordination with other services.

Excavation and Trenching

Allowance must be made for the sifting of soil when required, removal and carting away of all stones and rocks including dumping off site. Backfilling and compaction shall be carried out as specified for overall siteworks.

27m³Excavation and backfilling in soft soil92

7m³Excavation and backfilling in hard rock-supply cable93

Cable and Data Sleeves

20m50mm diameter for data94

Supply and installation of PVC Sleeves through floor construction to power distribution board and communication board complete with standard radius sleeve bends

10m75mm diameter for power cable95

-39-

Electrical WorksBill No. 11BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 40: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

3No50mm diameter 96

Radius bends:

2No75mm diameter97

800mSupply and install a 0.6mm diameter galvanised draw wire in sleeves and conduit for data installation

98

Draw Wires

Distribution Boards

1NoDistribution Board for outdoor packaged units, complete with equipment as per drawing.

99

Supply, delivery, storage and submission of workshop drawings for the Flush mounted architrave steel type power distribution boards complete with flush trays,doors,switch gear mounting trays, copper busbars, neutral and earth bars, correctly sized internal PVC wiring, labelling and legend cards

1No200A 3P 10kA, circuit breaker100

Low Voltage PVC Cables

180m120mm2 4 core PVC SWA Cable101

Supply and installation of PVC SWA PVC cable and Bare Copper Earth Wire on cable tray or in duct

180m70mm2 BCEW102

2No120mm2 4 core PVC SWA Cable103

Terminations:

2No70mm2 BCEW104

-40-

Electrical WorksBill No. 11BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 41: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

Conduit Work

Supply, delivery and installation of SABS approved Conduits completed with all required conduit accessories.

150m20mm PVC Conduit105

Built or Chase into brick or concrete work:

100m25mm PVC Conduit106

100m20mm Galvanised Conduit107

50m25mm Galvanised Conduit108

150m20mm PVC Conduit109

In Ceiling space and Timber work:

100m25mm PVC Conduit110

400m20mm Galvanised Conduit111

400m25mm Galvanised Conduit112

Conduit Boxes

10No20mm diameter PVC 4 way type (round box)113

Supply and installation of SABS approved conduit boxes, installed in the run of the conduit installation, cast into concrete and built into brickwork or flush inside false ceiling spaces, complete with all required conduit termination accessories.

150No20mm diameter Galvenised 4 way type (round box)114

-41-

Electrical WorksBill No. 11BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 42: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

Supply and installation of SABS approved galvanised pressed steel wall boxes for building flush into brickwork or cast into concrete work.

Wall Boxes

30No100 x 50 x 50mm115

Flush mounted type:

30No100 x 100 x 50mm116

PVC Wiring

7,000m2.5mm² for lights circuits117

PVC Wiring in conduits:

8,000m4mm² for plug sockets circuits118

100m6mm² 119

Stranded Copper Earth Wire

3,500m2.5mm² 120

Supply and installation of stranded copper earth wire along with PVC wiring in conduits. Tendered rates shall make provision for wastage.

4,000m4mm² 121

50m6mm² 122

Light Switches

-42-

Electrical WorksBill No. 11BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 43: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

5No1 Lever 1 way123

Supply and installation of SABS approved type 16A flush and surface type light switches. Final paint finishes shall be confirmed at a later stage, allowance shall however be made as specified in the general specification. All boxes for flush mounting measured elsewhere.

2No1 Lever 2 way124

30NoRadiant 06SE10-W occupancy sensor or similar approved.

125

Supply and installation of SABS approved switched and unswitched type flush and surface mounted type 16A switched socket outlets suitable for mounting in flush steel wall boxes or in steel pedestal units or on surface.

Socket Outlets

The final colour of the paint finish shall be confirmed at a later stage, allowance shall be made as specified in the specification.

All flush type boxes and special pedestals measured elsewhere.

70No16A 3 pin single socket outlets126

Flush switched sockets type:

SUM16A 3 pin double socket outlets127

Supply, delivery to site, storage and installation of the below specified light fittings complete with lamps and tubes. Allowance must be made in the rates for all the required fixing materials and accessories.

Light Fittings

-43-

Electrical WorksBill No. 11BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 44: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

Fittings to be equal and similar approved to the below quoted manufacture.

150NoRegent Linear Maxi LED 1200mm 56W (flush mounted) or similar approved

128

50NoRegent Perox Elux 10W down light or similar approved129

20NoLED Bulkhead130

20NoRazzle 5 chandelier or similar approved131

Making provision for the required inspection, tests and the commissioning of the complete installation and the issuing of the required certificate.

Electrical Tests

SUMBuilding Installation132

Make allowance for decommissioning existing installation.

Decommisioning

300mDecommission existing power skirting.133

150NoDecommission existing lighting.134

200mSupply and install 2 compartment power skirting complete with accessories

135

Others

52No16A power socket outlet on power skirting136

35No60A D/P Isolator (waterproof)137

145NoDesktop mount (consisting 2 socket outlets and 1 Cat6 data point)

138

6NoDesk mount for boardroom (consisting 1 socket outlets, 1 Cat6 data point, 1 VGA and 1 HDMI point)

139

-44-

Electrical WorksBill No. 11BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 45: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

1,500mP9000 trunking complete with accessories140

800mP2000 trunking complete with accessories141

200m25mm flexible conduit142

1,200mHeavy duty 305mm width perforated cable tray complete with accessories

143

700mHeavy duty 300mm width wire mesh cable tray completewith accessories

144

7NoCisco 3650 Switch 24 port PoE or similar approved.145

IT INFRASTRUCTURE

3No9U Wallmount Swingframe Network Cabinet 450mm for blocks

146

3No9U Collar 100mm147

7NoCat6 Patch Panel 24 Port 148

3NoBrush Panel 50mm Base149

3NoFan FS 2× Fan Tray150

3NoPower Rail 6 Way 16A 19" Rack151

200NoCat6 UTP Patch cord 1M152

5,000NoCat6 Ethernet Cable153

60NoCat 6 Network point154

SUMInstallation and comissioning155

300m4 Core HDD multi mode fibre including routing156

Optical Fibre Network

4NoSplice box - Ext Enclosure LC DPX157

-45-

Electrical WorksBill No. 11BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 46: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

4NoFibre Optic Management Kit158

4NoLC Duplex mid couplar159

8NoLC Pig tails160

4NoLead MM LC-LC 1m161

4NoMM Midcouplar LC162

4NoEntry Glands163

4NoSplicing164

20NoSmoke detectors complete with accessories165

Fire Detection Equipment

3NoHeat detector complete with accessories166

4NoLoop Sounders/Sirens167

5NoBreak glass unit168

600NoFR20 Fire Cable installed in trunking/conduits169

30NoReposition/refit existing smoke detectors170

ItemInstalling and Commissioning (link to existing fire control panel)

171

-46-

Electrical WorksBill No. 11BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 47: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

Electrical Works

Section No. 2

Bill No. 11

AmountR

PageNo

COLLECTION PAGE

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

46Total Brought Forward from Page No.

45Total Brought Forward from Page No.

44Total Brought Forward from Page No.

43Total Brought Forward from Page No.

42Total Brought Forward from Page No.

41Total Brought Forward from Page No.

40Total Brought Forward from Page No.

39Total Brought Forward from Page No.

-47-

Electrical WorksBill No. 11BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried Forward to Summary of Section No. R

Page 48: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

AmountR

ItemNo

Quantity Rate

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

SECTION NO. 3

BILL NO. 12

MECHANICAL WORKS

The contractor is refered to the Model Preambles for Trades (2008 edition) as issued by the Association of South African Quantity Surveyors before pricing this bill.

PREAMBLES

PRELIMINARIES AND GENERAL

All items shall be priced for whatever cost may be considered necessary for Preliminary and General items to carry out the Fire Protection installations in full. This bill must be read and completed in conjunction with specifications and drawings.

Important notice:

4No

Provision of fire plan in laminated A3 size for each building. The plans are to be fixed in the Foyer of each floor level.

172

FIRE HYDRANTS, HOSE REELS AND PORTABLE FIRE EXTINGUISHERS

25mØ25mm173

Supply and Install SANS 62-1/2 class medium steel piping. Pipes shall be free of rust, flakes or other defects and shall be cleaned internally before installation. The pipework shall be c/w Victaulic connections, hangers, supports, fittings and all necessary accessories. 25NB piping to be screwed.

-48-

Mechanical WorksBill No. 12BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 49: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

5mUnions - 25mm174

8mElbows - 25mm175

1mReducing Tees - 100/25/100176

14No4.5kg Dry Powder Fire Extinguisher177

25mPainting and labelling of all fire pipework(25NB) as per SANS 10252 and SANS 10140.

178

SUMFlushing of pipework and pressure testing as per SANS 10287 and 10252

179

7NoEscape and Exit signage with directional arrow180

Photoluminescent Signage in line with SANS 1186. Signage detail and fixing detail to be allowed for. Sign fixing detail to be presented to the architect for approval before procurement and installation

6NoHose reel and extinguisher signage with directional arrow

181

10NoHydrant, hose reel and extinguisher with directional arrow

182

18NoAccess and Direction of travel Signage183

2No

Supply and install Fire Hose Reels (30m long) swing type c/w chromium plated 25mm valve, connection, fittings, fixings and dial type (100mm) glycerine filled pressure gauge with union and isolating valve suitable for systems working pressure. Allowance for Weld-o-let to connect onto existing piping.

184

SUMTest and commission fire installation as required by SANS 10400 and SANS 10287

185

TESTING AND COMPLETION

5NoRefurbish and maintain Hydrant in line with SANS 1128186

-49-

Mechanical WorksBill No. 12BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 50: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

5NoRefurbish and maintain Hose Reel in line with SANS 543

187

Where trades names are used, it shall be read to include the phrase "or approved equal".

AIR CONDITIONING AND VENTILATION

ACCEPTABLE TRADE NAMES: Midea, Samsung, LG, Carrier, McQuay, Panasonic, Trane, Daikin, York

Installation and Commissioning of air conditioning units and ducting must include for all hangers, support, condensate drains and trunking

All items on the Bill are re-measurable

Controllers for cassette units to be wired, controllers for midwall units to be wireless.

Drip tray to be installed below slab penetration between condensor and indoor unit. Drain to be connected to condensate pipe. Tray to sit in ceiling void.

Reverse Cycle Split Units

AIR-CONDITIONING

7No

Mid wall indoor unit Midea MDV-D 28 G/N1-S or similar approved, cooling capacity of 9 000 BTU, to include all necessary supports, controllers, and ancillaries

188

Supply, delivery and install to site of the following items

7No

Mid wall indoor unit Midea MDV-D 36 G/N1-S or similar approved, cooling capacity of 12 000 BTU, to include all necessary supports, controllers, and ancillaries

189

1No

Mid wall indoor unit Midea MDV-D 45 G/N1-S or similar approved, cooling capacity of 15 000 BTU, to include all necessary supports, controllers, and ancillaries

190

-50-

Mechanical WorksBill No. 12BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 51: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

5No

Mid wall indoor unit Midea MDV-D 56 G/N1-S or similar approved, cooling capacity of 18 000 BTU, to include all necessary supports, controllers, and ancillaries

191

1No

Cassette indoor unit Midea MDV-D 36 Q4/N1-D or similar approved, cooling capacity of 12 000 BTU, to include all necessary supports, controllers, and ancillaries

192

2No

Cassette indoor unit Midea MDV-D 45 Q4/N1-D or similar approved, cooling capacity of 15 000 BTU, to include all necessary supports, controllers, and ancillaries

193

3No

Cassette indoor unit Midea MDV-D 56 Q4/N1-D or similar approved, cooling capacity of 18 000 BTU, to include all necessary supports, controllers, and ancillaries

194

7No

Cassette indoor unit Midea MDV-D 71 Q4/N1-D or similar approved, cooling capacity of 24 000 BTU, to include all necessary supports, controllers, and ancillaries

195

4No

Cassette indoor unit Midea MDV-D 80 Q4/N1-D or similar approved, cooling capacity of 27 000 BTU, to include all necessary supports, controllers, and ancillaries

196

11No

Cassette indoor unit Midea MDV-D 100 Q4/N1-D or similar approved, cooling capacity of 34 000 BTU, to include all necessary supports, controllers, and ancillaries

197

1No

Variable refrigerant outdoor heat pump unit Midea MDV-560W/DRN1-i(C) or similar approved, cooling capacity of 56kW, to include all necessary supports, controllers, and ancillaries

198

100mComplete piping installation including but not limited to piping, junction boxes, cable trays

199

-51-

Mechanical WorksBill No. 12BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 52: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

1No

Variable refrigerant outdoor heat pump unit Midea MDV-615W/DRN1-i(C) or similar approved, cooling capacity of 61.5kW, to include all necessary supports, controllers, and ancillaries

200

200mComplete piping installation including but not limited to piping, junction boxes, cable trays

201

2No

Variable refrigerant outdoor heat pump unit Midea MDV-900W/DRN1-i(C) or similar approved, cooling capacity of 90kW, to include all necessary supports, controllers, and ancillaries

202

300mComplete piping installation including but not limited to piping, junction boxes, cable trays

203

4NoInstallation and commissioning of each complete system204

FRESH AIR SYSTEMS

2NoAxial Fan - 1600 l/s @ 250 Pa in line duct fan mounted on anti-vibration mounts

205

Supply, delivery and install to site of the following items

2NoFilter box with washable pleated filters to suit 1600l/s fanspec, mounted on roof

206

2NoWeather louvre 1200x700 natural anodized with wire mesh screen.

207

22NoEpoxy Powder coated diffuser with damper to suit 20l/s -50l/s air flow.

208

26NoBalancing Damper - 250 diameter 209

645m²Galvanised ducting including all transformation pieces (including all brackets and supports)

210

2NoInstallation & Commissioning (incl all brackets, supports etc.) for each system

211

-52-

Mechanical WorksBill No. 12BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 53: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

TOILET EXTRACTION SYSTEMS

1NoAxial Fan - 1100 l/s @ 150 Pa in line duct fan mounted on anti-vibration mounts

212

Supply, delivery and install to site of the following items

1NoCowl to suit fan with wire mesh screen213

19No300X200 wall mounted RA extract louvre epoxy powder coated c/w balancing damper

214

6No500x400 Epoxy Powder coated Door grille215

25m²Galvanised ducting including all transformation pieces (including all brackets and supports)

216

1NoInstallation & Commissioning (incl all brackets, supports etc.) for each system

217

2NoCeiling mounted extract fan 50l/s @ 100Pa boxed and suitable for duct connection

218

1NoCeiling mounted extract fan 200l/s @ 100Pa boxed and suitable for duct connection

219

30m²Galvanised ducting including all transformation pieces (including all brackets and supports)

220

3NoInstallation & Commissioning (incl all brackets, supports etc.) of each system

221

Item4 copies of the O&M Manuals222

SUNDRIES

ItemAs-Built Drawings (4 copies)223

Item12 month guarantee period224

ItemFree maintenance during guarantee period225

-53-

Mechanical WorksBill No. 12BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 54: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

Item

Stripping of all existing ducting and air handling units in areas receiving new AC plant (chilled water piping to remain and blocked at ends)

226

PLUMBING INSTALLATION

All items shall be priced for whatever cost may be considered necessary for Preliminary and General items to carry out the Fire Protection installations in full. This bill must be read and completed in conjunction with specifications and drawings.

This BOQ is to be read in conjunction with the project specification document.

1No

Provision of fire plan in laminated A3 size for each building. The plans are to be fixed in the Foyer of each floor level.

227

COLD WATER AND HOT WATER

Supply and install SABS 460 Class 2, pipes, fittings,saddles, bracketing and accessories fixed to soffit and walls, or as described in accordance with the manufacturer's specification complete with labour. Size indicated is the Pipes Norminal Diamter in mm.

35mØ 15 mm Pipe228

Chased into Wall Pipes

59mØ 22 mm Pipe229

6mØ 28 mm Pipe230

52mØ 15 mm Pipe231

Surface Mounted Pipes

67mØ 22 mm Pipe232

-54-

Mechanical WorksBill No. 12BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 55: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

6mØ 28 mm Pipe233

30NoØ 15 mm234

Bends

29NoØ 22 mm235

4NoØ 28 mm236

1NoØ 35 mm237

24NoØ 15 mm238

Equal Tees

41NoØ 22 mm239

4NoØ 28 mm 240

2NoØ 35mm to Ø 28mm241

Reducers

8NoØ 28mm to Ø 22mm242

1NoØ 28mm to Ø 15mm243

7NoØ 22mm to Ø 15mm244

1NoØ 35mm to Ø 15mm245

10NoØ 15 mm246

Supply and install lever ball valve, including connection fittings to piping:

8NoØ 22 mm247

3NoØ 28 mm248

-55-

Mechanical WorksBill No. 12BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 56: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

18NoWash Basin- Ø 15 mm249

Sanitary connection equipment to include all necessary fittings to facilitate connection between supply pipe and sanitary fitting, to facilitate correct working of sanitary ware. Any exposed fittings to be approved by the architect . The sanitary schedule is in the main bill.

23NoToilet- Ø 22 mm250

4NoUrinal- Ø 15 mm251

3NoTaps- Ø 22 mm 252

24NoØ 15 mm253

Supply and Install Insulation

13NoØ 22 mm254

SUNDRIES

1No5% pressure test255

Testing and commissioning of hot water system in the presence of the manufacturer.

1No50 Litres,600kPa cylinder, Kwikot256

Supply and install Hot water cylinder complete with electric back up element, drip tray with P traps, multi control valve and all necessary accessories. All products and installation are to be in accordance to SANS 1098, SABS 115102002 and SANS 10254 respectively. The HWC shall be installed and positioned as indicated on the drawings.

1NoAllow for adapter for Galvanised steel to Copper adapter to suit 28 NB Copper pipe.

257

1NoAllow for adapter for Galvanised steel to Copper adapter to suit 35 NB Copper pipe.

258

-56-

Mechanical WorksBill No. 12BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 57: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

1NoTesting and commissioning of water systems259

1No

Supply, install and commission 10 litre hydro boil with associated piping and take-off from nearest water line. Position to be mounted above sink

260

DRAINAGE INSTALLATION

36m50mm diameter pipes261

Supply and install uPVC pipes and fittings, in accordance with the manufacturers approved installation procedure complete with labour, saddles, bracketing and accessories.

30m110mm diameter pipes262

3m110mm diameter 90 degree bend with inspection eye263

Extra over uPVC pipes for fittings:

6m110mm diameter 90 degree bend264

3m110mm diameter Tee265

19m110mm diameter Tee with inspection eye266

2m50mm diameter 90 degree bend with inspection eye267

8m50mm diameter 90 degree bend268

3m50mm diameter Tee269

9m50mm diameter Tee with inspection eye270

10No50mm diameter 45° junction 271

6No50mm diameter socket adaptor272

5No50mm diameter male adaptor 273

6No50mm diameter 45° Bend with inspection eye274

-57-

Mechanical WorksBill No. 12BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 58: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

5No50mm diameter 45° Bend 275

3No110mm double junction 276

2No110mm double 45 degree junction277

4No110 x 50mm Access Junction278

1No110 x 50mm double Junction279

6No110mm Access straight pan connector 280

2No50mm "Flexi Trap" P or S type trap jointed to waste pipe including connection or clamp etc

281

2No110mm uPVC to cast iron adapter282

4No110mm vent cowl283

70No22mm diameter PVC- for HVAC Drainage284

5NoAllow for adapter for cast iron to uPVC connection and tap off with existing system (110mm pipe)

285

-58-

Mechanical WorksBill No. 12BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 59: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

Mechanical Works

Section No. 2

Bill No. 12

AmountR

PageNo

COLLECTION PAGE

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

58Total Brought Forward from Page No.

57Total Brought Forward from Page No.

56Total Brought Forward from Page No.

55Total Brought Forward from Page No.

54Total Brought Forward from Page No.

53Total Brought Forward from Page No.

52Total Brought Forward from Page No.

51Total Brought Forward from Page No.

50Total Brought Forward from Page No.

49Total Brought Forward from Page No.

48Total Brought Forward from Page No.

-59-

Mechanical WorksBill No. 12BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried Forward to Summary of Section No. R

Page 60: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

AmountR

ItemNo

Quantity Rate

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

SECTION NO. 3

BILL NO. 13

GLAZING

The contractor is referred to the Model Preambles for Trades (2008 Edition) as issued by the Association of South African Quantity Surveyors before pricing this bill.

PREAMBLES

GLAZING TO STEEL WITH PUTTY

13m²Panes exceeding 0,1m2 and not exceeding 0,5m2286

4mm Clear glass

21m²Panes exceeding 0,1m2 and not exceeding 0,5m2287

4mm Obscure glass

TOPS, SHELVES, DOORS, MIRRORS, ETC

21NoMirror 420 x 860mm high288

Mirrors with polished edges holed for and fixed with chromium plated dome capped mirror screws with rubber buffers to plugs in brickwork or concrete

-60-

GlazingBill No. 13BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried Forward to Summary of Section No. R

Page 61: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

AmountR

ItemNo

Quantity Rate

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

SECTION NO. 3

BILL NO. 14

PAINTWORK

The contractor is referred to the Model Preambles for Trades (2008 Edition) as issued by the Association of South African Quantity Surveyors before pricing this bill.

PREAMBLES

SUPPLEMENTARY PREAMBLES

Descriptions of paintwork shall be deemed to include for all cutting in

DESCRIPTIONS

Previously painted plastered surfacesSurfaces shall be thoroughly washed down and allowed to dry completely before any paint is applied. Blistered or peeling paint shall be completely removed and cracks shall be opened, filled with a suitable filler and finished smooth

PREPARATORY WORK TO EXISTING WORK

Previously painted metal surfacesSurfaces shall be thoroughly rubbed and cleaned down. Blistered or peeling paint shall be completely removed down to bare metal

Previously painted wood surfacesSurfaces shall be thoroughly cleaned down. Blistered or peeling paint shall be completely removed and cracks and crevices shall be primed, filled with suitable filler and finished smooth

-61-

PaintworkBill No. 14BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 62: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

All painting shall be done in accordance with "Plascon-Evans" specifications

PAINT SPECIFICATIONS

PAINTWORK ETC TO NEW WORK

METAL SURFACES WITH

39m²Door frames289

Spot priming defects in pre-primed surfaces with zinc phosphate metal primer, one coat universal undercoat and two coats super universal enamel paint on steel

WOOD SURFACES WITH

99m²Doors290

Three coats Plascon matt vanish paint on

39m²Door frames, etc291

92mSkirtings292

One coat dulux trade alkali resistant plaster primer and two coats final coats dulux 100 low sheen to be applied after surfaces have been cleaned and dried. Moisture content should not exceed 12%. Coats two and three to be applied to achieve a close film and solid colour after coat one has been applied as a patch primer.

-62-

PaintworkBill No. 14BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 63: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

PAINTWORK, ETC TO PREVIOUSLY PAINTED WORK ON

FLOATED PLASTER SURFACES WITH

1,770m²Internal walls293

One coat dulux trade alkali resistant plaster primer and two final coats dulux 100 low sheen (code 20YY 57/060) to be applied after surfaces have been cleaned and dried. Moisture content should not exceed 12%. Coats two and three to be applied to achievea close film and solid colour after first coat has been applied as a patch primer.

1,592m²Ceilings and beams294

METAL SURFACES WITH

47m²Door frames, etc295

Spot priming defects in pre-primed surfaces with zinc phosphate metal primer, one coat universal undercoat and two coats super universal enamel paint on steel

WOOD SURFACES WITH

98m²Timber floors296

Two coats Plascon matt vanish paint on

104m²Doors297

Two coats Plascon matt vanish paint on

-63-

PaintworkBill No. 14BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 64: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

Paintwork

Section No. 2

Bill No. 14

AmountR

PageNo

COLLECTION PAGE

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

63Total Brought Forward from Page No.

62Total Brought Forward from Page No.

61Total Brought Forward from Page No.

-64-

PaintworkBill No. 14BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried Forward to Summary of Section No. R

Page 65: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

AmountR

ItemNo

Quantity Rate

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

SECTION NO. 3

BILL NO. 15

PROVISIONAL SUMS ETC

The contractor is referred to the Model Preambles for Trades (2008 Edition) as issued by the Association of South African Quantity Surveyors before pricing this bill.

PREAMBLES

SUPPLEMENTARY PREAMBLES

Unless otherwise described, all prime cost amounts and provisional sums exclude the cash discount of 5% and include for delivery to site of all articles concernedAll prime cost amounts and provisional sums are net and include for delivery to siteof all articles concerned

General

The contractor is referred to the Preliminaries for further amplification of "Prime Cost Amounts and Provisional Sums"

Preliminaries

BUDGETARY ALLOWANCES

The Following budgetary allowances are for work to be executed by the contractor and will be measured and valued at bill and sub-contractors rates in accordance with the Principal Building Agreement :

-65-

Provisional SumsBill No. 15BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 66: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

100,000.00Item

Provide the sum of R 100 000.00 (One Hundred Thousand Rand) for Electrical builders work to be used at the discretion of the Employer and deducted in whole or in part if not required.

298

Electrical Builders Work

100,000.00Item

Provide the sum of R 100 000.00 (One Hundred Thousand Rand) for Mechanical builders work to be used at the discretion of the Employer and deducted in whole or in part if not required.

299

Mechanical Builders Work

100,000.00Item

Provide the sum of R 100 000.00 (One Hundred Thousand Rand) for Plumbing and Drainage Repairs to be used at the discretion of the Employer and deducted in whole or in part if not required.

300

Plumbing and Drainage Works Repairs

50,000.00Item

Provide the sum of R 50 000.00 (Fifty Thousand Rand) for Ironmongery to existing doors to be used at the discretion of the Employer and deducted in whole or in part if not required.

301

Ironmongery to existing doors

1,000,000.00Item

Provide the sum of R 1000 000-00 (One Million Rand) for Asbestos Removal to be used at the discretion of the Employer and deducted in whole or in part if not required.

302

Asbestos Removal

-66-

Provisional SumsBill No. 15BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried to Abstract R

Page 67: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

Provisional Sums

Section No. 2

Bill No. 15

AmountR

PageNo

COLLECTION PAGE

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

66Total Brought Forward from Page No.

65Total Brought Forward from Page No.

-67-

Provisional SumsBill No. 15BILLS OF QUANTITIES - CVV BUILDING

Delta Quantity Surveyors CC

Carried Forward to Summary of Section No. R

Page 68: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

SECTION SUMMARY - BILLS OF QUANTITIES - CVV BUILDING

BillNo

PageNo

AmountR

10Alterations1

13Masonry2

16Carpentry and Joinery3

20Ceilings, Partitions and Acess Flooring4

21Floor Coverings5

24Ironmongery6

27Metalwork7

28Plastering8

31Tiling9

38Plumbing and Drainage (Provisional)10

47Electrical Works11

59Mechanical Works12

60Glazing13

64Paintwork14

67Provisional Sums15

-68-

BILLS OF QUANTITIES - CVV BUILDINGDelta Quantity Surveyors CC

Carried to Final Summary R

Page 69: SECTION NO 1 BILL NO 1 BUILDING AGREEMENT AND ... - Unisa departments...given in the said Model Preambles and in any supplementary preambles Should he contractor select Option A in

FOR UNIVERSITY OF SOUTH AFRICA

AT MUCKLENEUK CAMPUS

TO CVV 3RD FLOOR BUILDING

PROPOSED ALTERATIONS AND REFURBISHMENTS

PageNo

FINAL SUMMARY

SectionNo

AmountR

6PRELIMINARIES1

68BILLS OF QUANTITIES - CVV BUILDING2

RSUB TOTAL

600,000.00Item

Contingency

Allow an amount of R 600 000.00 (Six Hundred Thousand Rand) for Contingencies for unforeseen items to be authorized and deducted in part or whole if not required.

CONTINGENCIES

RSUB-TOTAL

RProvision for Value-Added Tax (VAT) at 15 percent

Note:

Tenderers must submit their tenders on the official form supplied for this purpose.

-69-

Delta Quantity Surveyors CC

TOTAL CARRIED TO FORM OF TENDER R