Upload
everett-rose
View
213
Download
0
Embed Size (px)
Citation preview
Section 2Capital Project Life Cycle
PROJECT PHASESProject
developmentالمشروع تطوير
Turn Over
والضمان التسليم
Detailed design
التفصيلي التصميم
Preliminary design
األولى التصميم
Construction
التشييد
87654321
Phase 1
ENTRY CRITERIATO PHASE 1
Signed & Approved Project Charterapproved budget
EXIT CRITERIATO PHASE 2
Baseline Schedule
Baseline CostsBaseline ResourcesRisk Management PlanProject Management Communication PlanEngineering Studies SOW/RFP for Preliminary DesignFeasibility Study & Enviromental Assessment completed & Accepted
Phase 2
ENTRY CRITERIATO PHASE 2
Baseline ScheduleBaseline CostsBaseline ResourcesRisk management PlanProject Management Communication PlanEngineering Studies SOW/RFP for Preliminary Design Feasibility Study and EA Completed & Accepted
EXIT CRITERIATO PHASE 3
Preliminary Design Report (PDR) and Design or Design Build SOWCurrent ScheduleCurrent Costs, Budget, & ResourcesRisk Management Plan (updated)Project management Communication Plan (updated)Review comments on PDR from Project Team IncorporatedReal Estate Confirmed
Phase 3
ENTRY CRITERIATO PHASE 3
Preliminary Design Report (PDR) and Design or Design Build SOWCurrent ScheduleCurrent Costs, Budget, & ResourcesRisk Management Plan (updated)Project management Communication Plan (updated)Review comments on PDR from Project Team IncorporatedReal Estate Confirmed
EXIT CRITERIATO PHASE 4
Final Design SubmittalBid Documents Ready To Issue for CM Consultant & Construction ContractorFinal Estimate of the Cost of Construction Management & ConstructionAll Land Acquisition completedAffirmation of Project Milestones
Phase 4
ENTRY CRITERIATO PHASE 4
EXIT CRITERIATO PHASE 5
Final Design SubmittalBid Documents Ready To IssueFinal Estimate of the Cost of ConstructionAll Land Acquisition completedAffirmation of Project Milestones
Punch List CompletedCommissioning Team in Place & FunctionalCommissioning Plan Ready to ImplementRisk Management Plan UpdatedProject Communication Plan Updated
Phase 5
ENTRY CRITERIATO PHASE 5
EXIT CRITERIAFROM PHASE 5
Punch List CompletedCommissioning Team in Place & FunctionalCommissioning Plan Ready to ImplementRisk Management Plan UpdatedProject Communication Plan Updated
Reliability Test Report AcceptedFinal O & M Manuals Delivered & AcceptedTraining CompletedWarranty Work CompletedRecord Drawings Completed & ReceivedAll Close-out items ReceivedAll Claims & Disputes ResolvedProject Completion Report Submitted & ApprovedFinal Invoice Submitted, Approved, & Paid