Upload
nguyendat
View
219
Download
0
Embed Size (px)
Citation preview
Seamless Bulk Electric Grid Management: A Platform for Designing the Next Generation EMS
PSERC Project S-62G
Anjan Bose, Washington State University Tom Overbye, University of Illinois
Santiago Grijalva, Georgia Inst. Of Tech.
PSERC Public Webinar April 5 2016
1
Project Overview
• The overall research objective is to develop a flexible platform in order to test the next generation EMS and associated analytics • Platform should be able to simulate different layers
related to power grid operations including the system itself, its cyber infrastructure, various software applications
• Platform should be flexible to allow different components to be included
• Need to provide case study example systems
2
EMS Background
• The grid has long been a technology leader
3
Commonwealth Edison Control Room Circa 1920
Utility Control Room, 1960’s
Source: W. Stagg, M. Adibi, M. Laughton, J.E. Van Ness, A.J. Wood, “Thirty Years of Power Industry Computer Applications,” IEEE Computer Applications in Power, April 1994, pp. 43-49
EMS Background
• And we are continually getting smarter!
4
PSE&G Control Center in 1988
Source: J.N. Wrubel, R. Hoffman, “The New Energy Management System at PSE&G,” IEEE Computer Applications in Power, July 1988, pp. 12-15.
ISO New England Control Center
Previous Work
• Previous Work under this project established a framework and requirements for next-generation Seamless Energy Management Systems.
• Key Requirements included: • Support for explicit modeling of the effects of
imperfect communications in cyber-control. • Recognition of the need to manage faster and more
dynamic effects in the system. • Trends and opportunities of decentralized control.
• Study requires simulation of a cyber-physical system.
5
Project Coordination
• Project involves coordinated work taking place at UIUC, WSU and Georgia Tech
6
PMU Level Grid Simulation and
Case Development
(UIUC)
Communication Simulation
(WSU)
Decentralized Applications
including Real-time Control
(Georgia Tech)
Seamless Bulk Electric Grid Management (S-62G)
Part 1: PMU Level Grid Simulations and Cases
(UIUC)
Thomas Overbye Students and Staff: Frank Borth, Richard Macwan
7
PMU Level Simulations
• Traditionally the EMS has been driven by SCADA data
• Dispatcher Training Simulators have also used this time frame • Uniform frequency
• EMS of the future needs to work in the PMU (transient stability) timeframe, so this is required in the simulation • EMS is most important during
stressed operation! 8
Image Source: Jay Giri (Alstom Grid), "Control Center EMS Solutions for the Grid of the Future," EPCC, June 2013
Real-time, PMU Level Simulation Environment
• Project leveraged commercial, interactive, real-time transient stability simulation platform • Data is
exported in c37.118 format
• Closed-loop control is also implemented
• Standard transient stability models are used, including generator over excitation limiters and line relays 9
Case Development
• First case developed for this testing was a 42 bus, 345/138 kV, 11 GW of Generation/Load • Rather detailed dynamics models were included
allowing for interactive, transient stability simulation • RTUs were modeled
for each of the substations
• Scenario considered was a tornado moving by a substation, taking out three 345 kV lines and 500 MW of generation
• Case is public domain 10
Event scenario for 42 bus system
This is described as follows: 1.At 2.0 seconds, the system has a 3-phase ground fault at bus 15. 2.At 2.5 seconds, the line between buses 43 and 15 opens. 3.When control center receives fault data, it sends back control signal to trip the generator at bus 43. 4.The generator trip to keep system stable. Each PMU data packet will have PDC processing delay when it goes through each substation or PDC, which varies and needed to be considered.
Seamless Bulk Electric Grid Management (S-62G)
Part 2: Communications
(WSU)
PSERC Industry-University Meeting May, 2015
Anjan Bose Students and Staff:Yannan Wang, Fan Ye
Communication simulation using NS3
I. Preparation of the communication network • Communication network based on the power network • Control center based near existing substation
II. Protocol Stack • TCP or UDP? Why?
III. Communication network simulation and results • NS3 used to calculate time delays in communication • Output is PMU data plus time delays
Processing preparation, cont.
General rules in this case: 1.PMUs are installed at both ends of each transmission line, measuring voltage and current phasors both. 2.The sample rate for each PMU is 60 samples per second. 3.In each substation, phasor data concentrator (PDC) is collecting PMU measurements from PMUs connected to that substation. 4.PDCs are communicating each other over communication channels.
Our work is to compare different communication architectures to minimize communication delays.
Protocol stack
Communication network has 5-layer stacks according to TCP model.
• Application Layer: C37.118 is specifically designed for PMU messages exchanging.
• Transport Layer: Our choice is UDP but why? • UDP packet header is lighter thus transmit faster
than TCP. • TCP protocol is complicated because it has many
delivering-guaranteed mechanisms such as retransmission, congestion control, flow control.
• Network Layer: IPv4 (more common than IPv6). • Link Layer: Ethernet. • Physical Layer: Optical fiber.
Four different communication architectures with delay results
Two main kinds of communication network are presented: star and mesh networks.
• Star network: it defines a network in which all communication nodes communicate directly one node, in this case, control center.
• Mesh network: it defines a more flexile communication network in which communication links are along the same or similar right-of-way as the transmission lines.
Four different communication architectures with delay results, cont.
These four communication architectures have mesh and star networks both. They are: 1)Network along with the transmission lines. (Mesh) 2)Network divided by three areas. (Mesh) 3)Centralized structure. (Star) 4)Decentralized structure. (Star) The following slides describe them one by one, with delay results and demonstration on transient stability followed.
One control center with communication lines along the same right-of-way as the power transmission lines.
Network along with the transmission lines (network type 1)
Three sub-control can help PMU data routing. In each area the communication links along the same right-of-way as the power transmission lines.
Network divided by three areas (network type 2)
One control center through substation 9. Each substation is directly linked to Sub 9.
Centralized structure (network type 3)
Similar to type 2 yet each substation link one sub-control center in its own area.
Decentralized structure (network type 4)
0 5 10 15 20 25 30 35 40 45 50 550
500
1000
1500
2000
2500
3000
3500
4000
4500
5000
5500
Bandwidth(Mbps)
Del
ay(m
s)
Total delay of Type1 to trip the generator at substation43
PDC delay 10msPDC delay 50msPDC delay 100msPDC delay 500ms
Different communication bandwidth considered. When the bandwidth is below 5Mbps, the queuing delay is increasing much.
Type 1 delay results
The communication delays are almost “stable” even the communication transmission rate is below 5Mbps.
Type 2 delay results
0 5 10 15 20 25 30 35 40 45 50 550
500
1000
1500
2000
2500
3000
3500
4000
4500
5000
5500
Bandwidth(Mbps)
Del
ay(m
s)
Total delay of Type2 to trip the generator at substation43
PDC delay 10msPDC delay 50msPDC delay 100msPDC delay 500ms
0 5 10 15 20 25 30 35 40 45 50 550
500
1000
1500
2000
2500
3000
3500
4000
4500
5000
5500
Bandwidth(Mbps)
Del
ay(m
s)
Total delay of Type3 to trip the generator at substation43
PDC delay 10msPDC delay 50msPDC delay 100msPDC delay 500ms
0 5 10 15 20 25 30 35 40 45 50 550
500
1000
1500
2000
2500
3000
3500
4000
4500
5000
5500
Bandwidth(Mbps)
Del
ay(m
s)
Total delay of Type4 to trip the generator at substation43
PDC delay 10msPDC delay 50msPDC delay 100msPDC delay 500ms
Type 3&4 delay results
Similarly to type 1, rate as 5Mps can become a critical rate point, yet their delay values are different.
Communication results demonstration Three circumstances are considered in power system transient stability: stability, critical stability and instability. This system has the critical delay point as 800ms approximately.
We examine the situation (case 1) in the first place where the generator is tripped in a very short time (<300ms). The rotor angle performances of two generators in substation 43 are shown here.
Critically stable case in which the generator is tripped after around 800ms. The maximum degree for oscillation is roughly 122 degree, which is greater than case 1.
Instability case in which the generator is tripped after a long time (>800ms). The system goes unstable even the generator is tripped.
Conclusions
In our work four different communication architectures are compared and studied. It’s hard to say which one is the best and which one is the worst. For those applications which don’t have strict latency requirements, type 3, type 4 even type 1 might be a good choice. However, for those like real-time PMU-based applications, type 2 might meet the demands.
Seamless Bulk Electric Grid Management (S-62G)
Part 3:
Decentralized Applications (Georgia Tech)
PSERC Industry-University Meeting May, 2015
Santiago Grijalva Students and Staff: Leilei Xiong
29
Motivation
30
• We need to integrate into the grid: • Large amounts of highly variable and spatially
distributed renewable energy. • Need much faster, better, tighter coordination
across subsystems: ISO, utilities, microgrids, etc.
Motivation
• Various part of the grids are operated by EMS and DMS systems. • What happens in a region of the grid affects other
regions. • Decentralized coordination issues must be addressed.
• A dynamics co-simulator could be used to test decentralized control applications including the effect of imperfect communication and delays.
• Use Cases: • ISO to ISO coordination within an interconnection • Distribution Utilities to ISO coordination
31
Example: Decentralized Power Agreement
• Assume that a region needs to change their reference production (net interchange) due to: • Power plant emergency • Contingency • Variation in renewables
• Each region has:
• Can the regions agree on the needed levels of interchange to balance the system in a decentralized manner?
32
: Desired Power (ex-ante): Agreed-upon Power (algorithmic): Actual Power (ex-post)
i
i
i
ppp
Decentralized Power Agreement
• Given desired power levels we want to:
• An agreement dynamics, incorporating constraints, weights, and trust, is used by regions to agree on the power levels across the system in a decentralized fashion.
• How fast can an agreement be reached?
2
1
ˆminN
i i ii
w p p=
−∑
Ramachandran, Costello, Kingston, Grijalva, Egerstedt. Distributed Power Allocation in Prosumer Networks, NecSys, 2012.
33
Decentralized Agreement: Convergence
• Rate of converge depends on topology and connectivity • Second eigenvalue of the communication graph Laplacian.
34
Example: Decentralized Power Agreement for Frequency Control
• Current frequency response is proportional to frequency deviation with respect to nominal.
• Current frequency regulation is unilateral and may cause inter-area oscillations.
• Question: • Can approaches be developed that can start
correcting imbalances before frequency deviates? • Can agreement help drive the frequency closer to
nominal after an imbalance?
35
Small Case Simulation • 42 bus system with dynamics.
400 MW
505 MW
2238 MW
1650 MW
234 MW 55 Mvar
234 MW 45 Mvar
94 MW 30 Mvar
267 MW -50 Mvar
267 MW -50 Mvar
267 MW -50 Mvar
268 MW 128 Mvar
268 MW 128 Mvar
240 MW 110 Mvar
200 MW 82 Mvar
150 MW 30 Mvar
207 MW 54 Mvar
205 MW 65 Mvar
200 MW 45 Mvar 200 MW
45 Mvar
158 MW 43 Mvar
158 MW 43 Mvar
240 MW 0 Mvar
240 MW 0 Mvar
160 MW 32 Mvar
160 MW 27 Mvar
186 MW 56 Mvar
202 MW 32 Mvar
190 MW 42 Mvar
201 MW 52 Mvar
201 MW 62 Mvar
175 MW 32 Mvar 156 MW
23 Mvar 176 MW 15 Mvar
212 MW 30 Mvar 140 MW
33 Mvar 212 MW 30 Mvar
132 MW 15 Mvar
94 MW 35 Mvar
267 MW 0 Mvar
267 MW 0 Mvar
267 MW 0 Mvar
210 MW 45 Mvar
185 MW 33 Mvar
112 MW 40 Mvar
300 MW 60 Mvar
95 MW 23 Mvar 75 MW
15 Mvar 198 MW 35 Mvar
193 MW 30 Mvar
161 MW 21 Mvar
135 MW 20 Mvar
140 MW 20 Mvar
88 MW -49 Mvar
130 MW 45 Mvar
128 MW 28 Mvar
49%
63%
31%
57%
54%
83%
23%
58%
47%
31%
42%
28%
33%
48%
29%
45%
25%
60%
68% 75%
31%
42%
75%
31%
50%
62%
44%
78%
52%
54%
55%
77%
37%
54%
22%
67%
53%
47%
71%
50%
1100 MW
178 MW 162 MW 177 MW
77 MW
55%
1520 MW
250 MW 50 Mvar
Hickory138
Elm138 Lark138
Monarch138
Willow138
Savoy138Homer138
Owl138
Walnut138
Parkway138 Spruce138
Ash138Peach138
Rose138
Steel138 123 Mvar
73 Mvar
100 Mvar
124 Mvar 117 Mvar
116 Mvar
74%
32%
56%
52%
39%
76%
50%
63%
Badger
DolphinViking
Bear
SidneyValley
Hawk
49%
Illini
Prairie
Tiger
Lake
Ram
Apple
Grafton
Oak
Lion
65%
82%
1520 MW
41%
200 MW 40 Mvar
200 MW 45 Mvar
28%
81%
84%
53%
190 MW 63 Mvar
200 MW
505 MW
63%
57 Mvar
68%
34%
Eagle
57%
76%
500 MW
36
Small Case Simulation
• System is partitioned into regions (e.g. control areas) • No central agent, each region talks with neighbors.
~1400MW Generation Disconnected
Communication Links
37
Small Case Simulation
• At time t a generator is disconnected in region i causing an imbalance equal to ∆Pi.
• As soon as the generator trips, power agreement is invoked to match the imbalance.
• Regions reach agreement in a few iterations and take actions immediately.
• Performance depends on communication delays. 38
2 3 4 5 6 7 8 9 10 11 12-1400
-1200
-1000
-800
-600
-400
-200
0
200
400
Iterations
Regions determine (agree on) the power needed to compensate for
generator trip
1,
N
j ij j i
P P= ≠
∆ = ∆∑
Frequency Response Performance
39
Base Case (conventional response)
Line Trip Generator Trip at t=25 sec
Total time to agreement including
delays (sec)
sec
0.1
5
2 1
0.5
Note: Frequency approaches the
nominal because imbalance is known.
Summary
• Decentralized coordination methods can be of service in achieving scalable grid coordination.
• With appropriate communication system and small delays, fast applications such as frequency response can be improved.
• A co-simulation approach supports investigation of dynamic performance of decentralized control methods under imperfect communications.
40
Next Steps
• Development of larger cases for demonstrating additional and more realistic scenarios, and more closed-loop control
• Realistic modeling of communication delays using statistical simulator (WSU)
• More streamlined closed loop control • Prototyping and assessment of improved
visualizations utilizing the c37.118 data
41