Salares Norte ProjectMAX COMBES: PROJECT DIRECTOR

10 April 2019

Page 2: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

2

Salares Norte

● The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga)● Maiden Reserve declared: 21.1Mt at 5.1g/t gold and 57.9g/t silver for 3.5Moz of gold and 4.0Moz of gold equivalent● Key metrics from the feasibility study:

Initial 11.5-year life of mine Annual process plant throughput: 2Mt Life of mine production: c.3.7Moz gold equivalent – front ended Average annual production of 450koz gold equivalent over first seven years at AISC of US$465/oz (355koz gold equivalent over first

10 years) Feasibility study capital cost estimate: US$834m (real Q4 2018 money) AISC: US$545 per gold equivalent ounce; AIC: US$785 per gold equivalent ounce (over LoM) IRR of 25% at US$1,300/oz gold price with a 2.2 year payback period; NPV of US$654m (discount rate of 7.5%) from investment

decision● Open pit operation envisaged with contractor mining and Merrill Crowe/CIP process design● More than adequate water secured in close proximity● Dry stacked tailings● Water and land rights have been secured and permitted for the future operational phase● On site diesel power station (gensets) – 14MW (Renewable Energy strategy in place)● The environmental impact assessment (EIA) was accepted for review on 11 July 2018

18 – 24 month review period anticipated● Detailed engineering underway

Overall Engineering progress: 35%

● Construction could commence in late 2020

Maiden Reserve declared in an attractive mining jurisdiction

Salares Norte Definitive Feasibility Study | April 2019

Page 3: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

Context: The Journey and Location

Page 4: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

4

The Salares Norte JourneyProject Lifecycle, DFS status

Salares Norte Definitive Feasibility Study | April 2019

High Level Project Timeline

ExplorationDiscovery

March 2011

Updated Resource 3.9 Moz AuEq31% Indicated

Dec 2015

Maiden Resource 3.55 Moz AuEq100% Inferred

Dec 2013

CommencedEIA Base Line

Oct 2015

Int. FeasibilityStudy

Mar 2018

ConstructionQ4 2020

EIA Preparation

Mar 2017EIA/RCA

FNTPQ1/Q2 2020

PER

MIS

OS

PRO

YEC

TO

DIA / RCA2014

2011 2015 2017 2018 2019

Detail Engineering

Apr 2018

2020 2021 2022

PER

MIT

SPR

OJE

CT

PermitsDevelopment

Nov 2018

24 Months 31 Months (*)

EIA Submission

Jul 2018

2023

FIRSTGOLD

Feb 2023

Acquired100% of SN

Feb 2012

Water RightsApplicationMarch 2014

ScopingStudy

Jul 2015

2012 2013 2014 2016

Water Rightsgranted 114 l/s

Nov 2016

Pre FeasibilityStudy

Mar 2017

Def. FeasibilityStudy

Feb 2019

DIA/RCA2016

Maiden Reserve Declared

Page 5: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

5

~5 hrs (330 km) from Copiapo, ~4,500 m RL

Maricunga Belt, Atacama Region, Chile

El SalvadorCodelco

La CoipaKinross

Lobo-MarteKinross

RefugioKinross

VolcanHochschild

CaspicheExeter

Salares Norte

Cerro MaricungaAtacama Pacific

Cerro CasaleBarrick-Kinross

CandelariaLundin

Manto VerdeAudley Capital

Diego deAlmagroChañaral

Caldera

50 km

Salares Norte Social Area

Salares Norte

Salares Norte Definitive Feasibility Study | April 2019

Page 6: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

Regional Geology / District Exploration

Salares Norte Definitive Feasibility Study | April 2019

Page 7: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

7

High Sulfidation Epithermal DepositsGlobal Distribution

Salares Norte Definitive Feasibility Study | April 2019

Several oxide examples in the Miocene (23 – 5 Ma) of Peru, Chile and Argentina Andes

Page 8: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

8

Notable Andean HS Epithermal DistrictsAndean HS Epithermal Analogues

Salares Norte Definitive Feasibility Study | April 2019

History shows deposits grow into significant production centres – long-lived assets (15 to >20 years)

Mine Elevation (m)

ProductionStart Year

ProductionEnd Year

Initial Reserves

(Moz AuEq)

Produced(Moz AuEq)

R & RDec 2015

(Moz AuEq)

Reserve Growth

El Indio 4,000 1979 2002 2.5 7.2 Closed 2002 2.9x

La Coipa 4,100 1989 2013 3.7 7.6 C&M 2.1x

Yanacocha 3,950 1993 -- 4.0 36.2 11.3 11.9x

Pierina 4,000 1999 2014 6.1 8.2 Closed 2014 1.3x

Lagunas Norte 4,100 2005 -- 6.9 9.1 5.7 2.1x

Veladero 4,200 2005 -- 8.4 7.1 10.9 2.1x

Salares Norte 4,250 2023 (?) -- 3.47** -- 3.47** ?

** Mineral Reserve Dec 2018 – Au only + 39.2 Moz Ag

Page 9: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

9

● Total endowment + 90 Moz Au Eq;

● All, except La Coipa, Esperanza and Salares Norte are porphyry-style Cu-Au deposits, large but low grade;

● La Coipa in care and maintenance since2013, ~7.5 Moz AuEq production over 25 years;

● Maricunga (Refugio) suspended in 2016, ~3 Mozs Au production over 20 years;

● Salares Norte is the first discovery in thenorthern part of the belt.

Maricunga BeltNorthern Chile

Salares Norte Definitive Feasibility Study | April 2019

220 km

Page 10: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

10

History of Discovery

● 2008-2009: Initial RC drilling at Horizonte, with positive results: 24 m @ 4.1 g/t Au, in structurally controlled breccia with oxidised vuggy quartz

● 2009-2010: Follow-up drilling at Horizonte, intersections on the order of 100 m @ 0.5 g/t Au, in vuggy quartz breccia with advanced argillic alteration

● 2010-2011: First drill program at Salares Norte, March 2011: 980 m RC / 4 holes, discovery hole: SNRC002, with 96 m @ 1.54 g/t Au and 61 g/t Ag. Oxidized, good metallurgical response in preliminary leach tests

● 2011-2013: Delineation drilling; spectacular oxide intercept: 132 m @ 53.2 g/t Au and 59.3 g/t Ag (SNDD017). Maiden Resource Declaration (2013)

● 2013-2018: Infill and extension drilling (over 142 km drilled up to date) and resource update (31/12/2018):

• 25.6 Mt @ 4.76 g/t Au & 53.14 g/t Ag for 3.9 Moz Au & 43.7 Moz Ag• at prices of US$ 1,400/oz Au and US$ 20.00/oz Ag• approximately 97% of the resource is classified as Indicated and 98% oxide

Salares Norte Deposits

Salares Norte Definitive Feasibility Study | April 2019

Page 11: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

11

Salares Norte DistrictLand Consolidation

● Increase landholding + 25,880 ha – new claims;

● Exercised Aster 3, Aster 2, Helada and Pedernales Options in 2018;

● Other JVs under negotiation;

Salares Norte Definitive Feasibility Study | April 2019

Property Original Owner Hectares Year AcquiredGold Fields concessions Gold Fields 45,550 2008-2017Gold Fields applications Gold Fields 25,880 In progressSalares Norte Option SBX 900 2012Rio Baker Option SLM Rio Baker 900 2016Pircas Option SCM Aguas Heladas 1,800 2016Aster 2 Option Azufres de Atacama SCM 1,800 2018Aster 3 Option Azufres de Atacama SCM 1,200 2018Helada Option Azufres de Atacama SCM 2,000 2018Pedernales Option Azufres de Atacama SCM 1,600 2018Potential JVs under negotiation

Other 2,200 In progress

Total 83,830

Page 12: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

12

Salares Norte DistrictDistrict Targets and Priority Exploration Areas

Salares Norte Definitive Feasibility Study | April 2019

Salares Norte

Horizonte

Aster 3

Aster 2

Pedernales

Helada-Mayweather

Page 13: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

Salares Norte Geology

Salares Norte Definitive Feasibility Study | April 2019

Page 14: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

14

Drilling History: 2011 to 2018

Salares Norte Definitive Feasibility Study | April 2019

Presenter
Presentation Notes
Notes:
Page 15: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

15

Agua Amarga and Brecha Principal DepositsLongitudinal Section: Geology and Alteration

Salares Norte Definitive Feasibility Study | April 2019

4,370 m

4,320 m

Page 16: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

16

Agua Amarga and Brecha Principal DepositsSurface Geology and Cross Sections

Salares Norte Definitive Feasibility Study | April 2019

Page 17: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

17

Agua Amarga and Brecha Principal DepositsGeological Model Video

Salares Norte Definitive Feasibility Study | April 2019

Page 18: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

Resources & Reserves

Page 19: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

19

Salares Norte Project Mineral Resources

● Resource now mostly Indicated at 97% by gold metal 13,463 m additional AA infill drilling GC-spaced drilling at BP and AA

● Additional ~250 koz Au in latest update Process cost improvement Definition of additional high-grade at AA

● Internal and external audit complete and passed

● Maiden Reserve declaration based on DFS

2018 Mineral Resource Update

Salares Norte Definitive Feasibility Study | April 2019

Page 20: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

20

Salares Norte Project Mineral Resources

Class Tonnes(Mt)

Au(g/t)

Ag(g/t)

Au(Moz)

Ag(Moz)

Au metal(%)

Measured 0 0 0 0 0 0

Indicated 23.7 4.99 56.29 3.80 42.91 97

Inferred 1.8 1.84 12.62 0.11 0.75 3

Total 25.6 4.76 53.13 3.91 43.66 100

2018 Mineral Resources Update

US$ 1,400/oz Au and US$ 20/oz Ag

Salares Norte Definitive Feasibility Study | April 2019

Presenter
Presentation Notes
Notes: Preliminary figures subject to internal review. Don’t expect material changes. Other modifying factors to be reported.
Page 21: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

21

Mineral Reserve DeclarationDecember 2018 Reserve Statement by Source

Salares Norte Definitive Feasibility Study | April 2019

Probable Mineral Reserve

Mining Area Tonnes Au Grade Ag Grade Gold Silver

(kt) (g/t) (g/t) (koz) (koz)

Brecha Principal 15,373 5.23 69.20 2,587 34,205

Agua Amarga 5,706 4.84 27.57 889 5,058

Total 21,079 5.13 57.94 3,476 39,263

Note: No Proved Mineral Reserves have been defined since there are no Measured Mineral Resources

● US$ 1,200/oz Au and US$ 17.5/oz Ag

Presenter
Presentation Notes
Supported by the 2019 DFS
Page 22: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

22

Salares Norte Project Mineral ResourcesPlan View – Grade Control Grid AA/BP

Salares Norte Definitive Feasibility Study | April 2019

Agua Amarga

Brecha Principal

EIA Pit (2017)

Presenter
Presentation Notes
Notes:
Page 23: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

23Salares Norte Definitive Feasibility Study | April 2019

Salares Norte Project Mineral ResourcesGrade Control Sections (BP) – 4,382 NE

SNDD330: 114.00 m @ 5.20 g/t Au & 27.00 g/t Ag (from 171.00 m)

SNDD517: 118.50 m @ 7.44 g/t Au & 43.05 g/t Ag (from 167.50 m)

SNDD511: 98.55 m @ 10.51 g/t Au & 130.25 g/t Ag (from 170.00 m)

SNDD526: 100.00 @ 10.66 g/t Au & 23.67 g/t Ag (from 179.00 m)

SNDD297: 153.00 m @ 7.78 g/t Au & 59.45 g/t Ag (from 136.00 m)

Page 24: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

24

Salares Norte Project Mineral ResourcesGrade Control Sections (AA) – 4,100 NW

Salares Norte Definitive Feasibility Study | April 2019

SNDD458SNDD532: 31.00 m @ 9.06 g/t Au & 8.20 g/t Ag (from 223.00 m)22.30 m @ 1.39 g/t Au & 15.99 g/t Ag (from 254.00 m)9.20 m @ 13.76 g/t Au & 43.13 g/t Ag (from 276.30 m)

SNDD458: 31.50 m @ 5.62 g/t Au & 35.07 g/t Ag (from 256.00 m)

SNDD535: 14.90 m @ 26.28 g/t Au & 35.84 g/t Ag (from 258.10 m)

Page 25: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

25

Salares Norte Project Mineral Resources

● Geospark audits of QA/QC and database

● Santiago Gigola audits of Geology

● Optiro audit of Resource estimation (January 2019):

“Optiro endorses the estimation and reporting of the Salares Norte resource estimate and approves the classification accorded to the project under the guidelines of the SAMREC Code (2016).”

● Optiro Reserve audit completed.

External Audits

Salares Norte Definitive Feasibility Study | April 2019

Page 26: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

26

Salares Norte Project Mineral ResourcesResource Model Video

Salares Norte Definitive Feasibility Study | April 2019

Page 27: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

Mine Design

Page 28: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

28

Salares Norte Mine Design

● Mining Method: Open pit with conventional equipment

● Operating model: Mining and Blasting Services performed by Contractors

● System Constraint: Plant constrained, significant stockpiling strategy and rehandle of ore

● Key focus during DFS:

Optimized SMU and bench height

Phase design and sequencing

Define achievable ramp-up schedule (ensure mine can deliver)

Verify accelerated ore mining strategy (grade streaming strategy)

Salares Norte Definitive Feasibility Study | April 2019

Mining

Page 29: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

29

Mine Configuration

WSF - North

Filtered tailings deposit

WSF - South

Brecha Principal Sector

Agua Amarga Sector

Ore Stockpiles

Salares Norte Definitive Feasibility Study | April 2019

Page 30: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

30

Salares Norte Mine Design

Parameter Unit Value

Waste mined Mt 308.8

Pre-strip Mt 50.6

Ore mined Mt 22.2

Indicated Mt 18.8

Marginal* Mt 2.3

Inferred Mt 1.1

Strip ratio W:O 13.9:1

Gold grade g/t 4.96

Silver grade g/t 55.6

*Marginal material economic through cost restructuring at and of LOM.

Salares Norte Definitive Feasibility Study | April 2019

Physicals

Page 31: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

31

Salares Norte: Mining Schedule

Mining schedule criteria

● Pre-strip of 50 Mt during < 2 years compulsory

● Five years or more at peak mining rate to achieve reasonable mining rates from contractor

● Mining rate < 50 Mtpa (don’t stress contractor capability)

● Operable in terms of climatic conditions, with achievable ramp-up phase

0

5

10

15

20

25

30

35

40

45

50

-2 -1 1 2 3 4 5 6 7 8 9 10 11 12

Min

ing

Tonn

age

(Mt)

Year

BP Waste mined AA Waste mined BP Ore mined AA Ore mined Mining limit

Salares Norte Definitive Feasibility Study | April 2019

Page 32: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

Metallurgy

Page 33: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

33

DFS Recovery Models for Gold and Silver

● Extensive metallurgical test work performed – 211 variability samples

● Metallurgical recovery is head grade dependent

● Free milling ore amenable to cyanidation

● Plant feed predominantly oxides (>98%) with good extraction

● LOM average recovery;

Gold: 92.7%

Silver: 67.5%

Salares Norte Definitive Feasibility Study | April 2019

LOM average

Page 34: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

34

Metal Production Profile

0

1000

2000

3000

4000

5000

6000

1 2 3 4 5 6 7 8 9 10 11 12

Met

al p

rodu

ctio

n (k

oz)

Year

Au Produced Ag Produced

Salares Norte Definitive Feasibility Study | April 2019

Page 35: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

Process Flowsheet

Page 36: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

36

Salares Norte: Process Flowsheet

Salares Norte Definitive Feasibility Study | April 2019

Page 37: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

Processing Infrastructure

Page 38: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

39

Site Layout

Salares Norte Definitive Feasibility Study | April 2019

Page 39: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

40

Orientation and Terrain

Salares Norte Definitive Feasibility Study | April 2019

Page 40: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

41

Processing Plant

Main Generation Plant

Tailings Filter PlantCivic District

Workshop & Warehouse

Primary Crusher

Stockpile

Grinding Building

Raw & Potable Water

Leaching

CIP

Grinding Thickener

CCD Thickeners

MC ClarifierTailings

Thickener Reagents Warehouse

Reagents Area

Merrill Crowe

Elution Fuel

Oxygen Plant Cyanide Area

Lime Plant

Salares Norte Definitive Feasibility Study | April 2019

Page 41: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

Tailings Filtration Plant and Tailings Deposit

Page 42: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

43

Site Layout

Salares Norte Definitive Feasibility Study | April 2019

Page 43: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

44

Tailings Deposition – Selection criteria

Main criteria (from 2014)

• Avoid site being tailings constraint – limit footprint

• Limit infrastructure downstream of Facility

• Avoid upstream facilities > 75% of TSF failures associated with this methodology

• Adopt Best Available Technology

• Improve geotechnical and geochemical stability

• Reduce fresh water consumption

Salares Norte Definitive Feasibility Study | April 2019

Page 44: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

45

Tailings Deposition Methodology

Dry stack Operation in ChileConventional hydraulically placed tailings

Salares Norte tailings at 15.7% moistureFilter cake

Salares Norte Definitive Feasibility Study | April 2019

Page 45: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

46

Tailings Filter Plant

Salares Norte Definitive Feasibility Study | April 2019

Page 46: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

47

● Tailings placed on waste platform

● TSF design capacity: 24.1 Mt

● Geometry

Bench slope angle: 21 degrees

Bench height: 20 m

Berm width: 8m

● Lined facility with drainage system

● Removed tailings capacity constraint

Filtered Tailings Deposit - Dry Stack

Salares Norte Definitive Feasibility Study | April 2019

Page 47: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

Access and Roads

Page 48: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

49

Salares Norte Site Access

Distances:

● Copiapó: 330 km

● El Salvador Airport: 180 km

● Port of Angamos: 853 km

● Las Losas Port, Huasco: 670 km

4.500 m3.920 m

Salares Norte Definitive Feasibility Study | April 2019

Page 49: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

50

Salares Norte Project Access Road

Main Access Road - Existing(No improvement)

Salares Norte Definitive Feasibility Study | April 2019

Page 50: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

Power and Fuel

Page 51: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

52

Power and Fuel - Layout

Salares Norte Definitive Feasibility Study | April 2019

Page 52: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

53

Power Supply

● > 100 km from grid - Low demand, relatively short LOM, interconnection not feasible

● NCRE options possible, but 100% thermal generating capacity required

● Base case considers Diesel Power station (17.5 MW installed) operated under BOOT contract

● Staged introduction of NCRE, starting with non-process loads

Average Demand at Delivery Points (Steady State)

Delivery Point DescriptionMean Power Demand

kW kVAr kVA

DP1 Process Plant Electrical System 11,233 5,454 12,487

DP2 Water Wells and Pipeline System 133 99 166

DP3 Camp Electrical System 192 119 225

Total Mean Power Demand 11,557 5,672 12,874

Salares Norte Definitive Feasibility Study | April 2019

Page 53: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

54

0

2000

4000

6000

8000

10000

12000

14000

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 120

Aver

age

Dem

and

(kW

)

Month

Phase 1 - Non process loads Phase 2A - Process loads

Phase 2B - Process loads, improved storage Peak NCRE (% Avg demand to maintain stability)

Average demand (kW)

Salares NorteNCRE Strategy NCRE – 80% demand

20% Electrical Energy

500 kW NCRE(Non-process)

Process Plant Ramp-up

NCRE 40% of Avg. Demand

Salares Norte Project Definitive Feasibility Study| Max Combes| Feb 11, 2019

Page 54: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

55

Benefits of Staged Approach

Staged approach

● Secure and stabilize diesel power station for process plant commission and ramp-up - proven solution

● Demonstrate commitment by reaching ~500 kW of NCRE for non-process loads at commissioning

● Allow for construction of NCRE for process loads outside peak construction period

● No additional camp requirements, no additional stress on laydown areas, etc.

● Ramp-up power draw will make power cost inefficient under a take or pay arrangement (implement when plant has stabilized)

● Viability of high penetration to be proven from year 2 onwards

What is considered in the feasibility study

● Provision for phase 1 included in Owner´s cost (camp and civic district loads)

● Provision for management of phase 2A - Sustaining CAPEX (Improvement / debottlenecking projects during Y1)

● Project financials does not reflect upside from NCRE (approx. US$0.75/t during Phase 2B)

Salares Norte Definitive Feasibility Study | April 2019

Page 55: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

Water Supply

Page 56: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

57

Raw Water Supply

Pipeline (Steel 8”)

4100-TK-0042Raw Water Storage Tank

Pipeline (HDPE 10”)

● Salares Norte granted water rights are 114 l/s

● Water supply from 2 wells with current water rights

WEDR001 = 58 l/s (12 km)

WEDR003 = 27.2 l/s (13 km)

● Water extraction permit requested in the EIA is 30 l/s

● Water quality generally good

● RO plant provided for potable water

Salares Norte Definitive Feasibility Study | April 2019

Page 57: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

Sustainable Development

Page 58: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

59

OCCUPATIONAL HEALTH AND SAFETY

MANAGEMENT SYSTEM

Prepare and implement preventive actions to control the critical risks of the operation..

• Visible Leaderships• Inspections• Field Reports.• Audits.• Critical Risk Control.

RISK MANAGEMENTPromote and maintain the highest degree of physical and mental well-being.

Implementation of legal health protocols.Healthy life programs.Preventive control of common health.

OCCUPATIONAL HEALTH

Actively involve workers in health and safety management.

Gold Fields and Contractors Joint Committee.AcknowledgmentsHealth and Safety campaigns.

WORKERS - PEOPLEEstablish sequences of actions for the control of emergencies.Rescue brigade team.DrillsCertified brigadistas.

EMERGENCIES

HS Boundaries:● 1686 Activity records made by workers and supervision in Visible Leaderships, Inspections and Field reports

● Only 1 incident of high potential in 2018

● Recognition among 14,000 companies in Chile for participation in the National Hand Protection Campaign

Salares Norte Definitive Feasibility Study | April 2019

Safety & Health Management

Page 59: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

60

Environmental Management

Environmental Management

Management of the biotic environment and collection of information as the base line of the Salares Norte project.

• Fauna, with focus on the Chinchilla. • Flora and Vegetation.

BASE LINE AND BIODIVERSITYProtect Water resource.

• Monitoring wells• Hydrogeological model.• Environmental Monitoring Plan.21 monitoring wells and 5 monitoring points of surface water.

WATER MANAGEMENT

OPERATIONAL ENVIRONMENTAL MANAGEMENT

• Waste management.• Regulatory Compliance (RCA's).• Environmental Monitoring.• Recycling.

Quantify Greenhouse Gas emissions according to scope.

CLIMATE CHANGE

Salares Norte Definitive Feasibility Study | April 2019

Page 60: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

61

● Environmental Impact Assessment (EIA) was submitted on July 4th of 2018 to the EnvironmentalEvaluation Service of Atacama (SEA)

● It was accepted by SEA for processing on July 11th, 2018

● EIA submitted due to the significant effect on the renewable resources, specifically on:

- Alteration and loss of chinchilla habitat

● The first Authorities Clarification Requests as part of the EIA Processing (ICSARA) was issued toMGFSN on October 10th, 2018.

● The Inquiry to the Indigenous Community process started on January 10th, 2019. In this case it isaddressed to the Diego de Almagro Indigenous Community

● Indigenous Consultation was closed on March 7 th and the resolution issued on April 5th

● Addendum 1 is scheduled for submission on April 12th, 2019

EIA Process Status

March '19 Quarterly Review | Apr 10th, 2019

Page 61: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

Project Execution Strategy

Page 62: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

63

Salares Norte: Summary Schedule

Salares Norte Definitive Feasibility Study | April 2019

Page 63: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

Investment Case Results

Page 64: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

65

Salares NorteInitial CAPEX and AISC

Mine19%

Process Plant38%

Site Utilities15%

TSF and WSF1%

Owner´s Cost14%

Contingency13%

Initial CAPEX (US$833.3M)

Mine32%

Process39%

G&A15%

Closure4%

Other6%

Sust.CAPEX4%

AISC (US$545/Au-eq.oz)

Page 65: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

66

Metal Production and AISC

353

599 600

426406

352

457

154

103 10168

48

545

356 357

493

544

602

364

0

100

200

300

400

500

600

700

0

100

200

300

400

500

600

700

1 2 3 4 5 6 7 8 9 10 11 12

Year

All-i

n-Su

stai

ning

Cos

t (U

S$/e

q.oz

)

Gold

Pro

duct

ion

(Au-

eq. O

z)

Au-eq. Production AISC

Rehandle only

Salares Norte Definitive Feasibility Study | April 2019

Page 66: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

68

Investment Evaluation Model: Main Outcomes

Includes Inferred Material

Metal price deck: Au - US$1200/0z Ag-US$17.50/oz

District potential not included

Cost reported in 2018 Q4 real terms

* NPV at Au - US$1300/=Z Ag-US$17.50/oz = US$ M 654

Metric Units IFS

Pre-Development Cost from Date of Study (DFS) US$M 80.5

Initial Capex US$M 833.8

All-in-Sustaining Cost (excluding Initial Capex) US$/eq.oz 545

All-in-Cost (including Initial Capex) US$/eq.oz 785

FCF Margin % 46

Discounted to Construction Decision – Excluding any Pre-Development (*) Cost

NPV7.5% US$M 510*

IRR % 21.8%

Payback Period from Start of Operations Years 2.4

Discounted to Date of Study – Including all Pre-Development Cost from March 2019

NPV7.5% US$M 402

IRR % 18.4%

Salares Norte Definitive Feasibility Study | April 2019

Page 67: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

Next steps

Page 68: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

70

The Next Steps

● Obtain EIA approval

● Advance Detail Engineering and Permitting

● Funding strategy

● Final Board approval

● Continue District exploration

Salares Norte Definitive Feasibility Study | April 2019

Page 69: Salares Norte Project - Mining News · Salares Norte The feasibility study for Salares Norte completed and peer reviewed (Brecha Principal and Agua Amarga) Maiden Reserve declared:

Thanks