Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
MV Seasong 201307/004 1
Marine Safety Investigation Unit
SAFETY INVESTIGATION REPORT
201307/004 REPORT NO.: 18/2014 July 2014
MT Seasong Serious injury to crew member
in position 36° 19.5’N 035° 11.8’E
06 July 2013
SUMMARY
On 06 July 2013, at about 1100,
the second engineer on board
the oil tanker Seasong
commenced the overhaul of one
of the boiler’s main steam
valves.
The second engineer loosened
each of the six bolts holding the
valve bridge to the valve body
and gradually lifted it to ensure
that any entrapped steam and
hot condensate is released
gradually and safely.
Seeing that the release of steam
had died down, the second
engineer moved closer to the
main steam valve to lift the
valve bridge clear from the
valve body.
Suddenly, hot water escaped
from the valve housing and
spilled over both legs of the
second engineer. As a result of
the spill, the second engineer
suffered burn injuries, which
required hospitalisation.
The safety investigation found
that the immediate cause of the
accident was the escape of
steam and hot condensate water
which had remained entrapped
in the system.
As a result of the conclusions
reached, two recommendations
have been made to the Company
to ensure increased awareness
on the dangers of hot
condensate and steam.
The Merchant Shipping (Accident and Incident Safety Investigation) Regulations, 2011 prescribe that the sole objective of marine safety investigations carried out in accordance with the regulations, including analysis, conclusions, and recommendations, which either result from them or are part of the process thereof, shall be the prevention of future marine accidents and incidents through the ascertainment of causes, contributing factors and circumstances.
Moreover, it is not the purpose of marine safety investigations carried out in accordance with these regulations to apportion blame or determine civil and criminal liabilities. NOTE
This report is not written with litigation in mind and pursuant to Regulation 13(7) of the Merchant Shipping (Accident and Incident Safety Investigation) Regulations, 2011, shall be inadmissible in any judicial proceedings whose purpose or one of whose purposes is to attribute or apportion liability or blame, unless, under prescribed conditions, a Court determines otherwise.
The report may therefore be misleading if used for purposes other than the promulgation of safety lessons.
© Copyright TM, 2014.
This document/publication (excluding the logos) may be re-used free of charge in any format or medium for education purposes. It may be only re-used accurately and not in a misleading context. The material must be acknowledged as TM copyright. The document/publication shall be cited and properly referenced. Where the MSIU would have identified any third party copyright, permission must be obtained from the copyright holders concerned.
MV Seasong
MV Seasong 201307/004 2
FACTUAL INFORMATION
Vessel
Seasong is a 57,162 gt oil tanker, owned by
Rose Navigation Limited and managed by
Thenamaris Ships Management Inc. of
Greece. The vessel was built by Hyundai
Heavy Industries Co. Ltd, Republic of Korea
in 2005 and is classed by American Bureau
of Shipping (ABS).
Seasong has a length overall of 244.0 m, a
moulded breadth of 42.0 m and a moulded
depth of 21.0 m. The vessel has a summer
draught of 14.9 m and summer deadweight
of 105,472 tonnes.
The vessel is a double hull tanker, fitted
with 14 cargo oil tanks. The cargo lines are
fitted with valves and are arranged in such a
way that the vessel can carry three grades of
cargoes segregated in different cargo oil
tanks.
Propulsive power is provided by a
6-cylinder, two-stroke Hyundai-B&W
6S60MC, slow speed direct drive diesel
engine, producing 11323 kW at 97 rpm.
This drives a single fixed pitch propeller,
reaching a speed of about 14.5 knots.
Crew
At the time of the accident, the vessel had a
crew of 24. All crew members were
Bulgarian and Filipino nationals. The
vessel’s manning was in excess of the
number specified in the Minimum Safe
Manning Certificate. All crew members
were appropriately certified for their
respective positions on board.
The Bulgarian second engineer had joined
the vessel at Savona, Italy, on 17 June 2013.
He had been at sea for about 13 years and
had served as second engineer for about five
years under the management of the same
Company.
Ship’s steam generating plant
The steam supply on board Seasong is used
for the heating of bunkers, cargo, and
domestic needs. The supply is provided by
a plant, which consists of two oil-fired,
Hyundai HMT-25 water tube boilers. The
vessel is also fitted with one economizer,
utilising the heat from the exhaust gases
generated by the main engine.
The steam demand in port is served by
operating either or both of the boilers. At
sea, the demand on the system can be met by
operating the economizer, either solely or in
combination with one of the boilers.
Each of the boilers is designed to produce
25,000 kghr-1
steam at 18 kgcm-2
working
pressure. The boiler is of a rectangular type
construction, mainly incorporating the
furnace, steam and water drums connected
by generating tubes, membrane water wall
tubes and heated internal downcomer tubes
(Figure 1).
An oil-fired burner, located at the roof of the
membrane water wall construction furnace,
burns fuel to generate hot gases, which heat
the water as it rises in the steam-generating
tubes, producing steam in the steam drum.
The steam delivery lines between the two
boilers are connected and branch out to a
common line, leading to different services.
The delivery of steam from each boiler is
through two manually operated valves,
located at the top of the steam drum
designated as VIA (main steam valve) and
VIB. Valve VIB is a smaller valve used
during initial start up of the system with low
steam demands (Figure 2). Both valves are
of the non-return type, i.e. they prevent
steam and / or condensate water from back-
flowing to the steam drum.
MV Seasong 201307/004 3
Figure 1: Hyundai marine water tube boiler Adopted from boiler’s construction manual
After the steam delivery valves on each
boiler, a manually operated screw down
globe valve is fitted, designated as 48V
(Figure 2 and 3) on boiler no. 1 and valve
47V on boiler no. 21. In cases where only
one boiler is in operation (either due to low
steam demands or one of the boilers is on
stand-by mode), these valves are closed to
isolate the main delivery valves from the
1 This valve is not shown in Figure 2.
main delivery valves from the operating
boiler.
The water drums have built-in coils, which
enable the water to be heated by the other
boiler (supplied through the coils), even
when particular maintenance on any one of
the boiler is required to be carried out.
MV Seasong 201307/004 4
Figure 2: Boiler no. 2 indicating arrangement of
steam delivery valves
Figure 3: Side elevation of valve 48V
Narrative2
Seasong discharged a cargo of crude oil at
Sidi Kerir, Egypt on 03 July 2013 and sailed
out in ballast, bound for Ceyhan, Turkey to
load her next cargo. Due to the relatively
short distance to Ceyhan (approximately 400
2 Unless otherwise stated, all times are local.
nautical miles) and the loading date (which
was scheduled on 06 July 2013), the vessel
remained adrift several miles outside the
port as from 04 July 2013 at approximately
2330.
During the time the vessel remained adrift,
the steam demands were met by boiler no. 1,
which was operating at a working pressure
of between 5.6 bars and 8.8 bars.
Boiler no. 2 was on ‘stand-by’ mode, heated
up by steam from the other boiler and
maintaining a pressure of
3.3 bars. Since boiler no. 2 was not
generating steam, both delivery valves and
isolating valve 48V were closed.
On 05 July, at approximately 1700, the
second engineer observed water mist
forming over the insulation of the main
delivery valve VIA on boiler no. 2. It
seemed that the steam leakage was from the
valve’s gland, past the packing around the
valve spindle.
The second engineer informed the chief
engineer of the leakage. Isolating valve 48V
was tightened further and the steam leak
from the main valve was eliminated.
Nonetheless, the chief engineer decided to
cool down boiler no. 2 in order to overhaul
the leaking valve prior to the vessel’s arrival
at Ceyhan, where both boilers would then be
required during the cargo loading operation.
By 1730, the steam supply from boiler no. 1
to boiler no. 2 water drum was closed and
the latter boiler was left to cool down so that
maintenance could be started on the
following day. The chief and second
engineers left the engine control room at
approximately 1800. The engine-room was
switched to UMS, with all relevant
extension alarms being transferred to the
accommodation.
On the following morning, at about 0800,
the engineers returned to the engine-room
and proceeded to boiler no. 2. The pressure
MV Seasong 201307/004 5
Steam
delivery
Non-return valve disc
Valve bridge
Bolt holes
Steam drum
Valve
gland
Valve
packing
gauge on the steam drum read
0 kgcm-2
. No steam was seen escaping from
the vent valve. Zero pressure was also
confirmed on the remote control panel in the
engine control room. Based on the above
observations, the chief engineer considered
that the boiler had cooled down sufficiently
and that he may safely proceed with the
overhauling of the valve.
A chain block arrangement above the valve
was rigged to facilitate the lifting of the
valve bridge (Figure 4). However, the valve
was not overhauled at this stage since the
crew’s coffee break was due and a safety
meeting had to be held.
Figure 4: Arrangement rigged for remote lifting of
valve bridge
After the coffee break, the meeting was held
between the master, the chief mate, the chief
engineer, and the second engineer. The
safety issues for the intended work were
discussed in accordance with the Company’s
SMS procedures. The Company’s work
permit form for cold / pressurised system
was subsequently filled-in and signed by all
the meeting participants.
The work on the valve commenced at about
1100 by the second engineer under the
supervision of the chief engineer. In the
meantime, the other engine-room personnel
were carrying their normal duties. The
fourth engineer and the wiper were working
on the incinerator, the oiler sounding the
bunker tanks, whilst the third engineer was
working on the auxiliary engines.
Each of the six bolts holding the valve
bridge to the valve body were gradually
loosened up by about 12 mm. The valve
bridge was then lifted up (with the aid of the
chain block arrangement) by approximately
5 mm to 6 mm from the valve body (Figure
5). This approach was in accordance with
the agreed safety procedure prior to the full
removal of the valve bridge. It was intended
to ensure that no steam escaped / was
present and that the isolation valve (48V)
was indeed properly tightened.
Figure 5: Side elevation of main steam valve
MV Seasong 201307/004 6
When the valve bridge was lifted slightly, a
small trace of water mist was observed
coming out from the small gap between the
valve bridge and the valve body. However,
it soon died out. The insulation around the
valve body was subsequently removed and it
was verified again that there were no traces
of escaping steam.
Based on this, the chief engineer considered
that the isolation valve 48V was properly
tightened and boiler no. 2 was completely
isolated from boiler no. 1 and that it was
safe to lift the valve bridge completely clear
from the valve body.
The second engineer went back to the valve
to complete the work when at about 1115, a
splash of hot condensate water escaped
under pressure from the gap between the
valve bridge and valve body. The hot water
spilled over both the second engineer’s legs.
Figure 6: A reconstruction of the approximate
position of the second engineer next to the valve
when the hot water spillage happened
As a result of the water spill, the second
engineer sustained burn injuries and was
taken to the ship’s hospital for first-aid
treatment. The vessel’s managers were
notified of the accident by the master.
Subsequently, the chief engineer safely
completed the overhaul of the main steam
valve with the assistance of the third
engineer and the fitter. An internal
inspection after the removal of valve’s
bridge indicated that the valve body and the
one metre length of pipe up to the isolation
valve 48V were full of hot condensate water.
The vessel arrived at Ceyhan and was safely
moored alongside on 06 July at 2000. The
second engineer was transferred to hospital
to receive specialised medical care.
Safety management system
Safety procedures and standards for work on
boilers were addressed in Chapter 11,
Section 13 of the Company’s SMS manuals.
The sections included safety precautions for
work on boilers and steam lines, entering the
boilers, and closing of boiler drums after
opening-up for inspection.
The safety precautions for work on boilers
and steam lines specified the closing of
valves to isolate the working area, having
two-valve separation between live system
and place of work where possible, ensuring
awareness by all personnel of possible
leakage and that all these precautions remain
in force when work resumes after a break.
The handling of hot piping and pressurised
systems were separately addressed in
Chapter 11, Section 19 of the SMS manuals.
The safety procedures for the handling of
hot piping systems cautioned that any escape
of steam, hot water, etc. or accidental
contact with the naked skin can cause severe
injuries (burns, etc.). Reference was also
made to precautionary measures such as
pipe isolation and cooling down, draining
the pipe and associated control means
(manometers, thermometers, etc.) from any
MV Seasong 201307/004 7
content (oil, steam and / or water), utilising
personal protective equipment and
consulting makers’ manuals and / or ship’s
drawings.
The handling of pressurised systems was
also identified as involving similar risks of
hot piping and was addressed separately in
relevant Cold Work Permit Form SQ/43.
This Form was filled before the specific
maintenance work was initiated. It was
countersigned by the master, the chief mate,
and the chief and second engineers. The
Form outlined various preparations and
checks that had to be carried out.
As there were no records of similar work
carried out previously on board with the
steam plant in operating condition, the chief
engineer attempted to adapt the Form to the
specific job on the boiler valve, inter-alia,
by addressing the following safety
procedures:
boiler steam pressure to drop down to
0 kgcm-2
;
the valve bridge had to be cracked and
only from a remote position, before
the complete removal of the bolts; and
the damaged valve had to be isolated
from the rest of the live steam line.
The chief engineer cautioned that the
equipment was expected to contain hot
condensate water when opened. The Form
also referred to personal protective
equipment that had to be worn, i.e. a safety
helmet, safety shoes, safety goggles, boiler
suit, leather gloves and ear protections.
However, neither heat resistant boiler suits
nor protective aprons were included in the
list.
ANALYSIS
Aim
The purpose of a marine safety investigation
is to determine the circumstances and safety
factors of the accident as a basis for making
recommendations, and to prevent further
marine casualties or incidents from
occurring in the future.
Cause of hot water escape
The steam leakage from the main valve of
boiler no. 2, as initially observed by the
second engineer, suggested that apart from
defective packing of this valve, pressurised
steam was also leaking through the isolation
valve 48V. The steam was originating from
boiler no. 1, which was in operation at the
time (Figure 7). In fact, the leakage was
stopped by tightening valve 48V and boiler
no. 2 was left to cool down.
The pressurised steam trapped within the
approximately one metre length of pipe
section between the main valve and the
isolation valve 48V would have gradually
condensed to water during the cooling down
of the boiler, although it would have
remained hot (at a relatively high
temperature) by residual heat and the steam
reaching the other side of valve 48V from
boiler no. 1.
Masses of hot condensate would contain
relatively high levels of enthalpy. With the
pressure further reduced, the latent energy
would have vaporised the hot condensate. The
(large volumes) of generated steam would also
tend to travel in the direction of the lower
pressure, (even if this would have been slight),
such as where the valve bridge was lifted from
the valve body.
Whilst the chief engineer confirmed zero
pressure in the steam drum, there were no
available means to verify whether there was
any residual pressure within the isolated
pipe section between the main valve and
MV Seasong 201307/004 8
Bo
iler
no
. 2
B
oil
er n
o.
1
Figure 7: Schematic drawing of the boilers and steam lines
MV Seasong 201307/004 9
valve 48V. Furthermore, the presence and
status of any hot condensate water could not
be verified as the pipe section was not
provided with a drain valve.
It should also be noted that if hot condensate
was trapped at relatively high temperature, the
thermal energy could change into pressure
energy during the cooling down period,
ejecting the steam / condensate through an exit
point, such as the one provided as a result of
the removal of the valve bridge (Figure 8). It
must be stressed that this could only happen if
the means of drainage in the specific section
of pipeline were either inadequate or (as in
this case) not available.
Figure 8: Main steam valve indicating position of
valve bridge and the gap formed from the valve
body
The chief engineer focused his attention on
the tightness of the isolating valve 48V and
concluded that it was keeping well since no
further steam was observed after a waiting
time of about three to five minutes.
According to the chief engineer, the splash
of hot condensate water from the gap
between the valve bridge and the valve body
was sudden without any reason and at a time
when the second engineer had just only
approached the main valve and was standing
adjacent to it.
The safety investigation did not identify a
technical reason for the possible leakage of
the hot condensate water without some
intervention from the crew. It was therefore
not excluded that the valve bridge was
somehow lifted, most likely by the
(inadvertent) operation of the rigging
arrangement (Figure 4).
Protective clothing There was no doubt that the second
engineer, under the supervision of the chief
engineer, was cautious in his actions; he
slowly and partially removed the nuts that
held down the valve bridge to the valve
body. The valve bridge was only removed
when the crew members satisfied
themselves that there was no indication of
residual pressurised steam or hot condensate
water. However, it has to be stated that the
injuries sustained by the second engineer
confirmed that he was not wearing adequate
protective clothing.
Maintenance requirements/records
The PMS implemented on board Seasong is
in the form of AMOS computer software.
The crew members also keep files with hard
copies on board. The boilers’ manuals and
the Company’s planned maintenance system
implemented on board did not incorporate
any specific requirements or instructions
related to the inspection or overhauling of
this specific valve.
The chief engineer was not aware whether
the specific valve on either boiler had ever
been opened up before for overhauling and /
or the replacement of the packing.
Moreover, there were no records which
could give clear indications on the matter.
Risk assessment
The risk assessment followed on board is
based on computer software forms which
can also be accessed and reviewed by the
Company.
MV Seasong 201307/004 10
Company procedures establish that risk
levels between ‘0’ and ‘4’ were to be
considered as acceptable risk levels and the
ship would be able to proceed with the
specified work without the intervention of
the Company. For risk level ‘5’, no work
was to be executed, unless specific
instructions were received directly from the
Company.
Two Risk Assessment Analysis forms with
Code nos. TE006 and TE007 were filled
prior to the specific maintenance work on
the main steam delivery valve of boiler no. 2
was initiated. The activities were defined as
‘Boiler Overhaul – Water Side’ and ‘Boiler
Overhaul – Gas Side’. Both were assigned
the (acceptable) risk level ‘3’.
The forms seemed to suggest that the
incorporated hazards were not correlated
with the specific task to be undertaken. The
only relevant hazards seemed to be crew
fitness, crew eligibility, high temperatures,
side effects from steam production stop and
lack of personal protective equipment. All
these hazards had been assigned risk level
‘0’ apart from the high temperatures risk,
which was assigned risk level ‘2’.
The aim of a risk assessment exercise is to
qualify whether the status of any system is
acceptable and help determine what changes
are necessary to make it acceptable. Such
exercise is so important that it will not only
provide an estimate of the size of risk, but
should also enable a comparison of the risk
level with some given criteria and serve as a
platform for a professional judgement to be
made in determining what system
improvements are needed to increase safety.
Whilst risk assessments are part of
organisational functioning, they are also
strongly influenced by each individual’s
unique experiences and interpretation of the
‘input signal’. Understanding risk is vital as
it correlates to the degree with which risk is
observable.
Risk perception is the understanding of
perceptual realities and hazard indicators.
The residual steam / hot condensate water in
the one-metre long pipe and the valve body
was a hazard – and a very serious one.
However, it was not detected. What
distorted the perception of the crew on the
severity of the hazard was the lack of
perceptible indicators.
Thus, the lack of depth of the risk analysis,
influenced by the distortion mentioned
above, and the lack of past experience of
similar accidents, precipitated into a
situation where the crew members could
only react in a reflex mode as a result of the
sudden occurrence of escaping hot
condensate water and steam.
The problem with lack of perceptible
indicators is a hazard per se and this
phenomenon is not endemic to a particular
safety critical domain. Studies in domains
other than maritime transportation also
revealed similar problems. It was revealed
that less than half of the hazard indicators
were perceptible to the human senses and
almost a quarter had to be perceived and
inferred from comparisons with standards.
As indicated above, lack of past experience
was also an identified common problem –
retrieval from memory would have only
occurred if the crew members had past
experience of similar accidents or incidents.
Evidence showed that none of the crew
members had experienced similar accidents
in the past.
Studies in hazard perception revealed the
intricacy of the process, with different
cognitive processes involved. It is also
acknowledged that inaccurate hazard
perception is a source of limited hazards
control.
MV Seasong 201307/004 11
Situation awareness
Maintenance activities cause deviations
during normal operations. Thus, whilst
maintenance increases component reliability
and hence safety, accidents often occur
during maintenance. The importance of risk
assessment has already been described
above. From the perspective of situation
awareness, risk assessment is equally
crucial.
Risk assessment is a process (which depends
on, inter alia, perception), that will generate
a person’s knowledge of the system or
situation awareness. Naturally, the
distinction between risk assessment and
situation awareness may not necessarily be
crystal clear and some scholars even claim
that psychology is unable to separate the
process from the product.
To a certain extent, the safety investigation
has considered the two separately.
However, what is of utmost importance is
the understanding that rather than two
mutually exclusive constructs, risk
assessment and situation awareness are
interdependent. It is submitted that situation
awareness also arises from the interaction
between crew members and the work
environment – and risk assessment is one
way of ensuring crew ‘a healthy’ members-
environment interaction.
Thus, situation awareness is a phenomenon,
which is not only identifiable with the
individual but, as expressed scientifically, is
a function which is achieved by coordination
between the human and the environment
within the socio-technical system on board.
The link between risk assessment and
situation awareness is that the former is vital
to pave the way for a compatible
representation of people and systems i.e.
when the awareness of system status in the
minds of the crew members becomes a true
reflection of the actual and real status of the
system. Incompatible representations (either
on the crew member’s side or the machine’s
status) would definitely mean potential
problems. This accident was a case in point.
What actually happened prior and during the
unfolding of the events was that the chief
and second engineers were neither able to
comprehend accurately the system status nor
to accurately project its future status.
CONCLUSIONS
1. Pressurised steam and hot condensate
water was trapped within the
approximately one-metre length of
pipe section between the main valve
and the isolation valve 48V and the
valve body;
2. The thermal energy of the condensate
trapped at relatively high temperature,
changed into pressure energy during
the cooling down period, eventually
ejecting the steam / hot condensate
through an exit point, provided as a
result of the removal of the valve
bridge.
3. There were no available means to
verify whether there was any residual
pressure within the isolated pipe
section between the main valve and
valve 48V.
4. The injuries sustained by the second
engineer confirmed that he was not
wearing adequate protective clothing.
5. The risk assessment analysis forms
seemed to suggest that the hazards
incorporated in the Forms were not
correlated with the specific task to be
undertaken.
6. The chief and second engineers were
neither able to comprehend accurately
the system status nor accurately
project its future status.
MV Seasong 201307/004 12
RECOMMENDATIONS3
Thenamaris Ships Management Inc. is
recommended to:
18/2014_R1 Bring this safety
investigation report to the attention of
crew members serving on board
Company ships and highlight the
potential dangers of hot condensate
being trapped within parts of the steam
system;
18/2014_R2 Ensure that its SMS highlights
the importance of continuous awareness
of the efficient drainage of hot
condensate, where possible and
sufficient cooling before any
maintenance work is carried out.
3 Recommendations should not create a
presumption of blame and / or liability.
MV Seasong 201307/004 13
SHIP PARTICULARS
Vessel Name: Seasong
Flag: Malta
Classification Society: American Bureau of Shipping
IMO Number: 9290438
Type: Oil Tanker
Registered Owner: Rose Navigation Limited
Managers: Thenamaris Ships Management Inc.
Construction: Steel
Length Overall: 244.0 m
Registered Length: 235.8 m
Gross Tonnage: 57162
Minimum Safe Manning: 18
Authorised Cargo: Liquid bulk
VOYAGE PARTICULARS
Port of Departure: Sidi Kerir, Egypt
Port of Arrival: Ceyhan, Turkey
Type of Voyage: Short International
Cargo Information: In ballast
Manning: 24
MARINE OCCURRENCE INFORMATION
Date and Time: 06 July 2013 at 1115
Classification of Occurrence: Serious Marine Casualty
Location of Occurrence: 36° 19.5’N 035° 11.8’E
Place on Board Engine-room
Injuries / Fatalities: One serious injury
Damage / Environmental Impact: None
Ship Operation: Special Service - Drifting
Voyage Segment: Transit
External & Internal Environment: Slight seas with a South-westerly 0.5 m swell,
Southerly wind Beaufort force 2 and air
temperature of 28°C.
Persons on board: 24