    Fort Buhlow Bridge

    US 71/165 Over the Red River

    Alexandria, Louisiana

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    2/49

    Location

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    3/49

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    4/49

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    5/49

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    6/49

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    7/49

    Goals & Objectives

    1. Replace the existing Red River Bridge and KCS Railroad Overpass as

    they are both structurally deficient and functionally obsolete.

    2. Improve the horizontal and vertical roadway geometrics as they no

    longer meet present day design standards.

    3. Reduce traffic accidents.

    4. Improve traffic levels of service while protecting environmental,

    cultural and historic assets.

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    8/49

    Replacing the O.K. Allen Bridge

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    9/49

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    10/49

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    11/49

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    12/49

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    13/49

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    14/49

    Project Features

    Construction Phases I & II

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    15/49

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    16/49

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    17/49

    Project Features

    Construction Phase III

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    18/49

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    19/49

    Project Features

    Red River Crossing

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    20/49

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    21/49

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    22/49

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    23/49

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    24/49

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    25/49

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    26/49

    Renderings

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    27/49

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    28/49

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    29/49

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    30/49

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    31/49

    Milestones

    Begin Line & Grade Study and EA

    November 1993

    Line & Grade Study (Final Configuration) June 1997

    FONSI Finding of No Significant Impact October 1998

    Begin Preliminary Plan Design November 1999

    Preliminary Plans Completed November 2001

    Cost Reduction Study Completed October 2003

    Cost Reduction Study Alternate V Approved by DOTD January 2004

    Revise Environmental Assessment

    July 2004

    Revised Preliminary Plans Completed February 2006

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    32/49

    More Milestones

    Begin Final Plan Design Phase I June 2006

    Begin Final Plan Design Phase II August 2008

    ACP Submittal September 2009

    100 % Final Plan Submittal May 2010

    Project Advertisement & Award - July-August 2010

    Begin Construction September 2010

    Construction Approximately 3 Years

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    33/49

    Funding

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    34/49

    Construction Estimate

    July 2010

    $114,271,679.26

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    35/49

    Winning BidAugust 2010

    $82,861,116.04

    With Life Cycle Cost

    $89,443,916.04

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    36/49

    Construction

    Photos

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    37/49

    Looking West

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    38/49

    Loading 24

    Steel Test Pile

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    39/49

    Column Bent

    Looking West

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    40/49

    Looking East from Levee

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    41/49

    Looking West from East Bank

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    42/49

    Cofferdam for Pier 14

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    43/49

    Cofferdam for

    Pier 14

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    44/49

    Excavation for Pier 14

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    45/49

    Pier 14

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    46/49

    Animation

    ByLTM

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    47/49

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    48/49

    Project Owner: Louisiana DOTD

    Project Designer: GEC, Inc.

    Project Constructor: Jensen Construction

    February 19, 2013

  • 7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013

    49/49

    Questions