Upload
walaywan
View
224
Download
0
Embed Size (px)
Citation preview
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
1/49
Fort Buhlow Bridge
US 71/165 Over the Red River
Alexandria, Louisiana
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
2/49
Location
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
3/49
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
4/49
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
5/49
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
6/49
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
7/49
Goals & Objectives
1. Replace the existing Red River Bridge and KCS Railroad Overpass as
they are both structurally deficient and functionally obsolete.
2. Improve the horizontal and vertical roadway geometrics as they no
longer meet present day design standards.
3. Reduce traffic accidents.
4. Improve traffic levels of service while protecting environmental,
cultural and historic assets.
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
8/49
Replacing the O.K. Allen Bridge
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
9/49
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
10/49
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
11/49
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
12/49
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
13/49
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
14/49
Project Features
Construction Phases I & II
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
15/49
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
16/49
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
17/49
Project Features
Construction Phase III
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
18/49
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
19/49
Project Features
Red River Crossing
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
20/49
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
21/49
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
22/49
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
23/49
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
24/49
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
25/49
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
26/49
Renderings
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
27/49
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
28/49
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
29/49
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
30/49
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
31/49
Milestones
Begin Line & Grade Study and EA
November 1993
Line & Grade Study (Final Configuration) June 1997
FONSI Finding of No Significant Impact October 1998
Begin Preliminary Plan Design November 1999
Preliminary Plans Completed November 2001
Cost Reduction Study Completed October 2003
Cost Reduction Study Alternate V Approved by DOTD January 2004
Revise Environmental Assessment
July 2004
Revised Preliminary Plans Completed February 2006
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
32/49
More Milestones
Begin Final Plan Design Phase I June 2006
Begin Final Plan Design Phase II August 2008
ACP Submittal September 2009
100 % Final Plan Submittal May 2010
Project Advertisement & Award - July-August 2010
Begin Construction September 2010
Construction Approximately 3 Years
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
33/49
Funding
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
34/49
Construction Estimate
July 2010
$114,271,679.26
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
35/49
Winning BidAugust 2010
$82,861,116.04
With Life Cycle Cost
$89,443,916.04
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
36/49
Construction
Photos
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
37/49
Looking West
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
38/49
Loading 24
Steel Test Pile
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
39/49
Column Bent
Looking West
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
40/49
Looking East from Levee
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
41/49
Looking West from East Bank
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
42/49
Cofferdam for Pier 14
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
43/49
Cofferdam for
Pier 14
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
44/49
Excavation for Pier 14
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
45/49
Pier 14
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
46/49
Animation
ByLTM
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
47/49
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
48/49
Project Owner: Louisiana DOTD
Project Designer: GEC, Inc.
Project Constructor: Jensen Construction
February 19, 2013
7/29/2019 S22_Fort Buhlow Bridge Project (Design)_LTC2013
49/49
Questions