Federal AviationAdministrationRunway 16/34 Safety

Improvement ProjectInformation in this briefing is subject to change.

Safety Management

FTW ATCT

3/11/2009

Change 4, refers to current construction

February 18, 2009 2 2Federal AviationAdministration

Runway 16/34 Construction ProjectMarch 11, 2009

THIS PRESENTATION IS SUBJECT TO CHANGE

February 18, 2009 3 3Federal AviationAdministration

Runway 16/34 Construction ProjectMarch 11, 2009

The project is scheduled to begin on February 23, 2009.

The improvements include:• Adding new apron in the area of Texas

Aviation ramp• Adding new apron (Paving fillets west of

terminal)• Approximately 3 weeks to complete

February 18, 2009 4 4Federal AviationAdministration

Runway 16/34 Construction ProjectMarch 11, 2009

New Ramp space

NOT TO SCALE

February 18, 2009 5 5Federal AviationAdministration

Runway 16/34 Construction ProjectMarch 11, 2009

Procedures• Runway 9/27 closed for arriving and

departing aircraft. Taxi is authorized.• Flagmen on non-movement area.• Construction Vehicle call sign: “ABR1”• Taxi Lane Golf closed either side of

Taxiway Kilo adjacent to grass construction site on ramp.

• Taxiway Kilo available for taxi to and from ramp.

February 18, 2009 6 6Federal AviationAdministration

Runway 16/34 Construction ProjectMarch 11, 2009

NOT TO SCALE

Closed

Construction Site

Staging Area

Taxi Routes

February 18, 2009 7 7Federal AviationAdministration

Runway 16/34 Construction ProjectMarch 11, 2009

March 23, 2009

ILS Runway 16 and Runway 34 turned off in case of second phase starting

earlyGPS 16 and GPS 34 available

February 18, 2009 8 8Federal AviationAdministration

Runway 16/34 Construction ProjectMarch 11, 2009

Overview of Construction Projects

• Adding 25 feet asphalt shoulders to Runway 16/34

• Replacing all runway lights and conduit for Runway 16/34

• Improving the safety areas on both ends of Runway 16/34

February 18, 2009 9 9Federal AviationAdministration

Runway 16/34 Construction ProjectMarch 11, 2009

• Medium Intensity Approach Lighting System adjusted due to elevation changes in over-run

• Additional ramp space near Texas Aviation

• Runway improvement on bump south end of RWY34.

February 18, 2009 10 10Federal AviationAdministration

Runway 16/34 Construction ProjectMarch 11, 2009

25’ Shoulders

Safety Area Improvement

Additional Ramp

Proposed Construction Route

RWY 34 improvementNOT TO SCALE

February 18, 2009 11 11Federal AviationAdministration

Runway 16/34 Construction ProjectMarch 11, 2009

Overview of Changes to Airport Layout During Construction

• Runway 16/34 will be changed to “TAXIWAY ZULU”. – All painted runway markings on Runway 16/34

will be removed.– Runway End Identifier Lights (REILS) will be

removed.– Medium Intensity Approach Lighting System

will be removed on both ends of the runway and reset by the end of the project.

February 18, 2009 12 12Federal AviationAdministration

Runway 16/34 Construction ProjectMarch 11, 2009

• Runway Edge Lights replaced with taxiway edge lights.

• Precision Approach Path Indicators (PAPI) will be turned off for both Runway 16 and 34.

February 18, 2009 13 13Federal AviationAdministration

Runway 16/34 Construction ProjectMarch 11, 2009

Changes to Taxiway Alpha• Taxiway Alpha will become “RUNWAY

15/33”– All taxiway markings will be replaced with

appropriate runway markings.– A runway safety area (RSA) will be in effect for

Runway 15/33.– Displaced landing thresholds for Runway 15/33

(total length 6000 feet).

February 18, 2009 14 14Federal AviationAdministration

Runway 16/34 Construction ProjectMarch 11, 2009

• Taxiway lights will be replaced with runway edge lights.

• New runway hold lines will be painted for Runway 15/33 at all appropriate intersections.

February 18, 2009 15 15Federal AviationAdministration

Runway 16/34 Construction ProjectMarch 11, 2009

TWY ZULU

15

TWY ZULU

33

New Taxiway Zulu

Runway 15/33

Runway Safety Area

Displace ThresholdNot to Scale

February 18, 2009 16 16Federal AviationAdministration

Runway 16/34 Construction ProjectMarch 11, 2009

Runway 09/27• Runway 09/27 will be closed for arriving and

departing traffic. Taxi will be permitted.• Runway 09/27 west of Taxiway Zulu is being

considered as a run-up area for Runway 17/35 departures.

February 18, 2009 17 17Federal AviationAdministration

Runway 16/34 Construction ProjectMarch 11, 2009

Other Taxiways• Taxiways Alpha 4 (both sides of Alpha)

and Taxiway Alpha 5 closed. (possibly permanent)

• Taxiway Mike closed• Taxiway Alpha 3 closed• Taxiways Golf and Golf 1 closed • Taxiway Hotel closed

February 18, 2009 18 18Federal AviationAdministration

Runway 16/34 Construction ProjectMarch 11, 2009

TWY ZULU

15

TWY ZULU

33

New Taxiway Zulu

Runway 15/33

Runway Safety Area

Displace Threshold

Closures

Proposed Run-up AreaNot to Scale

February 18, 2009 19 19Federal AviationAdministration

Runway 16/34 Construction ProjectMarch 11, 2009

TRANSITION PHASES

February 18, 2009 20 20Federal AviationAdministration

Runway 16/34 Construction ProjectMarch 11, 2009

March 28, 2009 (Saturday)Phase 1– Airport CLOSED: Beginning Saturday evening

(10pm) until Sunday morning (8am)

Phase 2– At 8am Sunday morning, Runway 17/35 and only

limited taxiways (see next slide) will open until 10pm March 29, 2009,Sunday evening

February 18, 2009 21 21Federal AviationAdministration

Runway 16/34 Construction ProjectMarch 11, 2009

TWY ZULUTWY ZULU

Closed Movement Areas

Open Movement Areas

Coordination Required?

Proposed Run-up Area

Not to Scale

February 18, 2009 22 22Federal AviationAdministration

Runway 16/34 Construction ProjectMarch 11, 2009

Phase 3• Airport Closed: At 10pm Sunday evening until 8am

Monday morning.

March 30, 2009Phase 4 (63 days)

• Airport Open• Runway 15/33 and 17/35 in use.• Taxiway Zulu in use. EXCEPT: expect Taxiway Zulu

to be closed from 10pm until 8am nightly throughout construction project.

February 18, 2009 23 23Federal AviationAdministration

Runway 16/34 Construction ProjectMarch 11, 2009

Projects During Transition Phases

• Remove runway markings on Runway 16/34 and repaint with taxiway markings.

• Paint new hold short lines at all new intersections to Runway 15/33.

• Establish barricades at all intersections leading into closed movement areas.

• Place new airport signage for affected movement areas.

February 18, 2009 24 24Federal AviationAdministration

Runway 16/34 Construction ProjectMarch 11, 2009

Operations During Construction

• No Instrument Landing System (ILS) approach available. Other approaches available:

– RNAV (GPS) RWY 16 circle to RWY 17 and RWY 15 only between sunrise and sunset. (Night time still in question)

– GPS RWY 34 circle to RWY 35 only– IFR departure minimums may change. (200-1) for RWY

15/33• No practice approaches• Touch and go traffic not allowed for Runway

15/33, restricted to Runway 17/35

February 18, 2009 25 25Federal AviationAdministration

Runway 16/34 Construction ProjectMarch 11, 2009

• Traffic permitting/warrants: All single engine type aircraft will depart and land on Runway 17/35

• High performance aircraft will use Runway 15/33 (Displaced thresholds)

• Maintenance engine run-up areas will be determined as requested

February 18, 2009 26 26Federal AviationAdministration

Runway 16/34 Construction ProjectMarch 11, 2009

Taxi Thoughts for Pilots

• Expect non-standard taxi routes. Some taxiways will be one direction only. Some taxiways will be outbound only and others inbound/exit only.

• Listen for runway assignment from the Ground Controller. A majority of traffic will be using Runway 17/35 for departures and arrivals

• Read-back hold instructions

• WCC “When Confused Clarify”

• Be aware of construction vehicles also in the non-movement areas and their unfamiliar knowledge of airport surroundings

• Does taxi clearance to a runway authorize clearance to cross that same runway?

February 18, 2009 27 27Federal AviationAdministration

Runway 16/34 Construction ProjectMarch 11, 2009

TWY ZULU

15

TWY ZULU

33

Proposed Run-up Area

Displaced Threshold

Runway Safety Area (not to scale)

Closed

Traffic Flow

RWY 15/17 TRAFFIC FLOW

Construction Routes

New Taxiway Zulu

Open Taxiways

Open Runways

February 18, 2009 28 28Federal AviationAdministration

Runway 16/34 Construction ProjectMarch 11, 2009

TWY ZULU

15

TWY ZULU33

New Taxiway Zulu

Open Taxiways

Open Runways

Displaced Threshold

Runway Safety Area

(not to scale)

Closed

Traffic Flow

Weight Restriction

RWY 33/35 TRAFFIC FLOW

Proposed Run-up Area

Construction Routes

February 18, 2009 29 29Federal AviationAdministration

Runway 16/34 Construction ProjectMarch 11, 2009

Change Over -Runway 16/34 & Taxiway Alpha

• Date unknown at this time• Airport CLOSED• Will begin on Saturday (10pm) evening

until Sunday morning (8am).

February 18, 2009 30 30Federal AviationAdministration

Runway 16/34 Construction ProjectMarch 11, 2009

– Remove runway markings on Runway 15/33 and repaint with taxiway markings

– Paint new hold short lines at all intersections to Runway 16/34

– Remove barricades at all intersections leading into closed movement areas

– Replace new airport signage for affected movement areas

February 18, 2009 31 31Federal AviationAdministration

Runway 16/34 Construction ProjectMarch 11, 2009

• Phase 5- Airport Reopen normal operation

• REILS and PAPI’s repositioned onto Runway 16/34• MALSR return to service• ILS approach available (once flight checked)

February 18, 2009 32 32Federal AviationAdministration

Runway 16/34 Construction ProjectMarch 11, 2009

QUESTIONS ?