Presented to:
By:
Date:
Federal AviationAdministrationRunway 16/34 Safety
Improvement ProjectInformation in this briefing is subject to change.
Safety Management
FTW ATCT
3/11/2009
Change 4, refers to current construction
February 18, 2009 2 2Federal AviationAdministration
Runway 16/34 Construction ProjectMarch 11, 2009
THIS PRESENTATION IS SUBJECT TO CHANGE
February 18, 2009 3 3Federal AviationAdministration
Runway 16/34 Construction ProjectMarch 11, 2009
The project is scheduled to begin on February 23, 2009.
The improvements include:• Adding new apron in the area of Texas
Aviation ramp• Adding new apron (Paving fillets west of
terminal)• Approximately 3 weeks to complete
February 18, 2009 4 4Federal AviationAdministration
Runway 16/34 Construction ProjectMarch 11, 2009
New Ramp space
NOT TO SCALE
February 18, 2009 5 5Federal AviationAdministration
Runway 16/34 Construction ProjectMarch 11, 2009
Procedures• Runway 9/27 closed for arriving and
departing aircraft. Taxi is authorized.• Flagmen on non-movement area.• Construction Vehicle call sign: “ABR1”• Taxi Lane Golf closed either side of
Taxiway Kilo adjacent to grass construction site on ramp.
• Taxiway Kilo available for taxi to and from ramp.
February 18, 2009 6 6Federal AviationAdministration
Runway 16/34 Construction ProjectMarch 11, 2009
NOT TO SCALE
Closed
Construction Site
Staging Area
Taxi Routes
February 18, 2009 7 7Federal AviationAdministration
Runway 16/34 Construction ProjectMarch 11, 2009
March 23, 2009
ILS Runway 16 and Runway 34 turned off in case of second phase starting
earlyGPS 16 and GPS 34 available
February 18, 2009 8 8Federal AviationAdministration
Runway 16/34 Construction ProjectMarch 11, 2009
Overview of Construction Projects
• Adding 25 feet asphalt shoulders to Runway 16/34
• Replacing all runway lights and conduit for Runway 16/34
• Improving the safety areas on both ends of Runway 16/34
February 18, 2009 9 9Federal AviationAdministration
Runway 16/34 Construction ProjectMarch 11, 2009
• Medium Intensity Approach Lighting System adjusted due to elevation changes in over-run
• Additional ramp space near Texas Aviation
• Runway improvement on bump south end of RWY34.
February 18, 2009 10 10Federal AviationAdministration
Runway 16/34 Construction ProjectMarch 11, 2009
25’ Shoulders
Safety Area Improvement
Additional Ramp
Proposed Construction Route
RWY 34 improvementNOT TO SCALE
February 18, 2009 11 11Federal AviationAdministration
Runway 16/34 Construction ProjectMarch 11, 2009
Overview of Changes to Airport Layout During Construction
• Runway 16/34 will be changed to “TAXIWAY ZULU”. – All painted runway markings on Runway 16/34
will be removed.– Runway End Identifier Lights (REILS) will be
removed.– Medium Intensity Approach Lighting System
will be removed on both ends of the runway and reset by the end of the project.
February 18, 2009 12 12Federal AviationAdministration
Runway 16/34 Construction ProjectMarch 11, 2009
• Runway Edge Lights replaced with taxiway edge lights.
• Precision Approach Path Indicators (PAPI) will be turned off for both Runway 16 and 34.
February 18, 2009 13 13Federal AviationAdministration
Runway 16/34 Construction ProjectMarch 11, 2009
Changes to Taxiway Alpha• Taxiway Alpha will become “RUNWAY
15/33”– All taxiway markings will be replaced with
appropriate runway markings.– A runway safety area (RSA) will be in effect for
Runway 15/33.– Displaced landing thresholds for Runway 15/33
(total length 6000 feet).
February 18, 2009 14 14Federal AviationAdministration
Runway 16/34 Construction ProjectMarch 11, 2009
• Taxiway lights will be replaced with runway edge lights.
• New runway hold lines will be painted for Runway 15/33 at all appropriate intersections.
February 18, 2009 15 15Federal AviationAdministration
Runway 16/34 Construction ProjectMarch 11, 2009
TWY ZULU
15
TWY ZULU
33
New Taxiway Zulu
Runway 15/33
Runway Safety Area
Displace ThresholdNot to Scale
February 18, 2009 16 16Federal AviationAdministration
Runway 16/34 Construction ProjectMarch 11, 2009
Runway 09/27• Runway 09/27 will be closed for arriving and
departing traffic. Taxi will be permitted.• Runway 09/27 west of Taxiway Zulu is being
considered as a run-up area for Runway 17/35 departures.
February 18, 2009 17 17Federal AviationAdministration
Runway 16/34 Construction ProjectMarch 11, 2009
Other Taxiways• Taxiways Alpha 4 (both sides of Alpha)
and Taxiway Alpha 5 closed. (possibly permanent)
• Taxiway Mike closed• Taxiway Alpha 3 closed• Taxiways Golf and Golf 1 closed • Taxiway Hotel closed
February 18, 2009 18 18Federal AviationAdministration
Runway 16/34 Construction ProjectMarch 11, 2009
TWY ZULU
15
TWY ZULU
33
New Taxiway Zulu
Runway 15/33
Runway Safety Area
Displace Threshold
Closures
Proposed Run-up AreaNot to Scale
February 18, 2009 19 19Federal AviationAdministration
Runway 16/34 Construction ProjectMarch 11, 2009
TRANSITION PHASES
February 18, 2009 20 20Federal AviationAdministration
Runway 16/34 Construction ProjectMarch 11, 2009
March 28, 2009 (Saturday)Phase 1– Airport CLOSED: Beginning Saturday evening
(10pm) until Sunday morning (8am)
Phase 2– At 8am Sunday morning, Runway 17/35 and only
limited taxiways (see next slide) will open until 10pm March 29, 2009,Sunday evening
February 18, 2009 21 21Federal AviationAdministration
Runway 16/34 Construction ProjectMarch 11, 2009
TWY ZULUTWY ZULU
Closed Movement Areas
Open Movement Areas
Coordination Required?
Proposed Run-up Area
Not to Scale
February 18, 2009 22 22Federal AviationAdministration
Runway 16/34 Construction ProjectMarch 11, 2009
Phase 3• Airport Closed: At 10pm Sunday evening until 8am
Monday morning.
March 30, 2009Phase 4 (63 days)
• Airport Open• Runway 15/33 and 17/35 in use.• Taxiway Zulu in use. EXCEPT: expect Taxiway Zulu
to be closed from 10pm until 8am nightly throughout construction project.
February 18, 2009 23 23Federal AviationAdministration
Runway 16/34 Construction ProjectMarch 11, 2009
Projects During Transition Phases
• Remove runway markings on Runway 16/34 and repaint with taxiway markings.
• Paint new hold short lines at all new intersections to Runway 15/33.
• Establish barricades at all intersections leading into closed movement areas.
• Place new airport signage for affected movement areas.
February 18, 2009 24 24Federal AviationAdministration
Runway 16/34 Construction ProjectMarch 11, 2009
Operations During Construction
• No Instrument Landing System (ILS) approach available. Other approaches available:
– RNAV (GPS) RWY 16 circle to RWY 17 and RWY 15 only between sunrise and sunset. (Night time still in question)
– GPS RWY 34 circle to RWY 35 only– IFR departure minimums may change. (200-1) for RWY
15/33• No practice approaches• Touch and go traffic not allowed for Runway
15/33, restricted to Runway 17/35
February 18, 2009 25 25Federal AviationAdministration
Runway 16/34 Construction ProjectMarch 11, 2009
• Traffic permitting/warrants: All single engine type aircraft will depart and land on Runway 17/35
• High performance aircraft will use Runway 15/33 (Displaced thresholds)
• Maintenance engine run-up areas will be determined as requested
February 18, 2009 26 26Federal AviationAdministration
Runway 16/34 Construction ProjectMarch 11, 2009
Taxi Thoughts for Pilots
• Expect non-standard taxi routes. Some taxiways will be one direction only. Some taxiways will be outbound only and others inbound/exit only.
• Listen for runway assignment from the Ground Controller. A majority of traffic will be using Runway 17/35 for departures and arrivals
• Read-back hold instructions
• WCC “When Confused Clarify”
• Be aware of construction vehicles also in the non-movement areas and their unfamiliar knowledge of airport surroundings
• Does taxi clearance to a runway authorize clearance to cross that same runway?
February 18, 2009 27 27Federal AviationAdministration
Runway 16/34 Construction ProjectMarch 11, 2009
TWY ZULU
15
TWY ZULU
33
Proposed Run-up Area
Displaced Threshold
Runway Safety Area (not to scale)
Closed
Traffic Flow
RWY 15/17 TRAFFIC FLOW
Construction Routes
New Taxiway Zulu
Open Taxiways
Open Runways
February 18, 2009 28 28Federal AviationAdministration
Runway 16/34 Construction ProjectMarch 11, 2009
TWY ZULU
15
TWY ZULU33
New Taxiway Zulu
Open Taxiways
Open Runways
Displaced Threshold
Runway Safety Area
(not to scale)
Closed
Traffic Flow
Weight Restriction
RWY 33/35 TRAFFIC FLOW
Proposed Run-up Area
Construction Routes
February 18, 2009 29 29Federal AviationAdministration
Runway 16/34 Construction ProjectMarch 11, 2009
Change Over -Runway 16/34 & Taxiway Alpha
• Date unknown at this time• Airport CLOSED• Will begin on Saturday (10pm) evening
until Sunday morning (8am).
February 18, 2009 30 30Federal AviationAdministration
Runway 16/34 Construction ProjectMarch 11, 2009
– Remove runway markings on Runway 15/33 and repaint with taxiway markings
– Paint new hold short lines at all intersections to Runway 16/34
– Remove barricades at all intersections leading into closed movement areas
– Replace new airport signage for affected movement areas
February 18, 2009 31 31Federal AviationAdministration
Runway 16/34 Construction ProjectMarch 11, 2009
• Phase 5- Airport Reopen normal operation
• REILS and PAPI’s repositioned onto Runway 16/34• MALSR return to service• ILS approach available (once flight checked)
February 18, 2009 32 32Federal AviationAdministration
Runway 16/34 Construction ProjectMarch 11, 2009
QUESTIONS ?