78
Unbonded CRCP Overlays Jeffery Roesler, Ph.D., P.E. Professor Department of Civil and Environmental Engineering University of Illinois Urbana-Champaign FHWA-CRSI Creating Long Life Pavement Solutions - Continuously Reinforced Concrete Pavements Workshop Fresno, California February 22, 2012

RoeslerFresno CRCP overlay 2 22 2012 - CRCPavement.orgcrcpavement.org/wp-content/uploads/2015/04/RoeslerFresno... · 2015. 4. 3. · FHWA-CRSI Creating Long Life Pavement Solutions

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

  • Unbonded CRCP Overlays

    Jeffery Roesler, Ph.D., P.E.Professor

    Department of Civil and Environmental EngineeringUniversity of Illinois Urbana-Champaign

    FHWA-CRSI Creating Long Life Pavement Solutions -Continuously Reinforced Concrete Pavements Workshop

    Fresno, CaliforniaFebruary 22, 2012

  • Acknowledgements

    • Illinois Department of Transportation– Dave Lippert, Amy Schutzbach, Chuck

    Wienrank

    • Mike Plei

  • CRCP CRACKING PATTERN

  • Presentation Overview

    • CRCP in heavy traffic areas in Illinois

    • CRCP Unbonded Overlay Basics• Review of CRCP Overlay Projects• Key design issues for CRCP overlays• Illinois Experience with Unbonded CRCP• Summary

  • Example Urban CRCP

    • Illinois experience: – I-90/94 Dan Ryan Expressway – Chicago– Other projects

    • I-95 Georgia experience

  • Illinois Conditions

    • Wet and Freeze-Thaw Climate• Limestone-Dolomite aggregates

    – CTE=5.5x10-6/F• Design Flexural strength = 750 psi• Temperature Ranges:

    – 0F to 100F• Long. Bars = 26 - #7 @5.5inch• Tranverse bars = #4 bars at 48 inches

  • ATLAS CRCP Testing

  • Summary of CRCP Section Failure

    Section one

    Section two

    Section three

    Section four

    Section five

    Duration of testing(1)12 months(6/16/02-6/23/03)

    11 weeks (6/30/03-9/13/03)

    10 weeks (5/26/04-8/4/04)

    9 weeks (1/3/04-3/6/04)

    2 weeks (4/6/04-4/15/04)

    Total load repetitions 246,800 118,600 163,400 64,300 1,800

    Total ESALs 911 M 778 M 627 M 764 M 12.5 M

    Approx ESALs at first failure 511 M 230 M 548 M >764 M N/A

    Maximum load applied 222 kN 222 kN 245 kN 245 kN 156 kN(3)

    Pavement temperature range 1-27°C

    (2) 24-35°C 18-27°C -4-10°C 4-18°C

    Failure description Extended punchoutsExtended punchouts

    Extended punchouts

    Section did not fail

    Response loading only

    34k

    1i

    ii 40

    Pn18ESALs

    ÷

  • Bituminous BaseAggregate Working Platform

    Extended-Life CRCP DesignIllinois DOT (2005)

    4 & 6 in.

    40 Year

    CRCP

    Bituminous BaseAggregate Working Platform

    12 to 24 inches

    0.8% Steel Epoxy Coated

    14 in.

  • Dan Ryan Expressway, I-90/94 (2007)

  • • Original CRCP design (1961)• 2006-2008 reconstruction for 500 million

    ESALs and 40-year life.– Slab thickness = 14-in– Steel content = 0.80%– Steel depth = 4.5-in– Tied JPCP shoulder– 4-in dense graded HMA – Min. 12-in granular subbase– Fine grained subgrade (A-6 soil)

    I-90/94 Dan Ryan Expressway Chicago

  • CRCP – Dan Ryan Expressway 40 Year

  • CRCP – Dan Ryan Expressway

  • • 5 mile project (I-80 to Indiana)• CRCP design ESALs= 175 million (40 yrs)

    – 12-in CRCP– 0.75% steel– Depth of steel = 3.5-in– Tied JPCP shoulder– 4-in dense HMA base– 12-in granular subbase (PGE)– Fine grained subgrade (A-6 soil)

    Illinois State Toll Highway Authority I-294 Chicago (2005)

    15

  • • 12.5 mile project (I-80 to 95th)• CRCP design ESALs= >60 million (40 yrs)

    – 13-in CRCP– 0.75% steel– Depth of steel = 3.5-in– Tied JPCP shoulder– 3-in dense HMA base– 24-in recycled concrete aggregate subbase– Fine grained subgrade (A-6 soil)

    Illinois State Toll Highway Authority I-294 (2008-2009)

    16

  • Other Illinois DOT CRCP Projects“Extended Life”

    I-80* Morris2003

    14in CRCP6in HMA

    12in CRCP

    I-70* Marshall2002

    12in CRCP5in HMA8in CRCP

    I-290 Schaumburg

    200314in CRCP

    6in HMA

    24in Aggregate

    I-74 Peoria2006

    11.5in CRCP

    6in HMA

    12in Aggregate

    12 14

    14

    11.5

    *overlays

  • Continuously Reinforced Pavements• No man-made “joints”• Steel reinforcement bars• Numerous transverse cracks

  • Concrete Overlays CategoriesConcrete Overlays

    Bonded Concrete Resurfacing of Concrete Pavements

    Bonded Concrete Resurfacing of Asphalt Pavements

    Bonded Concrete Resurfacing of Composite Pavements

    Bonded Resurfacing Group

    Unbonded Concrete

    Resurfacing of Concrete Pavements

    Unbonded Concrete

    Resurfacing of Asphalt Pavements

    Unbonded Concrete

    Resurfacing of Composite Pavements

    Unbonded Resurfacing Group

    Thin Thick

    Bond is integral to design Old pavement is Support

  • Pavement Overlay Comparisons Bonded

    Concrete Overlays (BCOs)

    Unbonded Concrete Overlays (UBOLs)

    HMA Overlay on Intact CRCP

    HMA Overlay on Rubblized CRCP

    Con

    stru

    ctab

    ility

    Vertical Clearance

    Not a problem (typically 50 to 100 mm (2-4 inches) thick)

    May be a problem (typically 180 to 250 mm (7 to 10 inches) thick)

    May or may not be a problem, depends on the overlay thickness

    May be a problem, overlay may be relatively thick

    Traffic Control May be difficult to construct under traffic

    May be difficult to construct under traffic

    Not difficult to construct under traffic

    Not difficult to construct under traffic but rubblization adds time

    Construction Special equipment and experienced operators needed

    No special equipment required

    No special equipment required

    Special equipment required for rubblization

    Perf

    orm

    ance

    Existing CRCP Condition

    Good condition with no MRD

    All conditions (good to bad)

    Good condition, may accelerate MRDs

    Poor condition

    Extent of Repair

    Repair all deteriorated joints and cracks

    Repair limited to severe damage

    Repair all deteriorated joints and cracks

    Limited repair required

    Future Traffic Any traffic level Any traffic level Any traffic level Any traffic level Historical Reliability

    Fair to Poor* Good Good Good to poor, depending on the support

    Cos

    t E

    ffec

    tiven

    ess

    Initial Cost Depends on pre-overlay repair, but usually high

    Higher than conventional HMA overlay

    Depends on the pre-overlay repairs

    Requires a thick HMA overlay

    Life Cycle Cost Analysis (LCCA)

    Competitive if future life is substantial

    Competitive Cost-effective unless the pavement is in poor condition

    Competitive if pre-overlay repairs are required

    (Smith et al. 2002)

  • Unbonded Concrete Overlay

    Concrete Overlay hol

    Existing Concrete Pavement

    heSeparator layer

    - Asphalt Concrete Interlayer

  • Unbonded CRCP OverlayObjective

    • Isolate excessive movement of existing pavement from concrete overlay

    • Limit concrete distress reflection into concrete overlay

    • Provide uniform & non-erodible support to overlay

  • Concrete Overlay Stress Distribution

    -100

    0

    100

    200

    300

    400

    500

    600

    700

    800

    -60 -50 -40 -30 -20 -10 0 10 20 30 40 50 60

    Distance from crack, in

    Bot

    tom

    stre

    sses

    , psiO

    OO

    O

    Noncrackked underlying slab Cracked underlying slab

    Khazanovich et al. 2002

  • CRCP Unbonded Overlays General Overview

    • Existing pavement condition is fair to poor• Asphalt separator layer or “bond-breaker”

    – Friction layer that provides uniformity– Durable, moisture insensitive layer– Allows deflection profiles of two concrete

    layers to be independent• Roadway & roadside geometrics

    – shoulders, ramps, guardrail modifications

  • (Smith et al. 2002)

  • Unbonded CRCP Overlays Abridged History

    • 600 miles of CRC Overlays (6 to 9-inches) since 1959 (CRSI 1988) – Waco, TX first CRCP overlay (CRSI 1973)– IN, MD, MS, TX, OR, IL, PA, ND, IA, CT

    (PCA 1976)• Oregon DOT (e.g., 1970 to 1975)

    – 4 projects (29.6 miles)• TxDOT (e.g., 1972- present) > 10 projects• Illinois DOT (1967- present) - 8 projects

  • Oregon I-5 CRCP Overlay(1970-1975)

    CRSI 1988

    7 to 9 inch CRCP over flexible pav’t

  • TxDOT Experience• I-35W Johnson County (1965)

    – 6-inch CRCP over 9-inch JPCP– ADT=22,000 w/ 14% trucks– 8.78 mile section

    • I-45W Galveston area (1972-1976)– 6-inch CRCP over JPCP– ADT=50,000 – 15.5 mile total section (4 projects) CRSI 1988

  • Recent TxDOT ProjectsCRCP Overlays

    1. IH-30 in Paris District: existing pavement is JPCP2. IH-45 in Dallas District: existing pavement is JPCP.3. IH-35 in Wichita Falls District: existing pavement is CRCP.4. IH-45 in Houston District: existing pavement is JPCP.5. IH-20 in Fort Worth District: existing pavement is CRCP.6. IH-20 in Tyler District:7. IH-20 in Beaumont District: existing pavement is JRCP.8. IH-35W in Fort Worth District: existing pavement is JPCP.

    from Moon Won

  • Arkansas DOT Experience• I-40/55 West Memphis (1972)

    – 6-inch CRCP over 9-inch JPCP– ADT=27,000 w/ 25% trucks (1986)– 1.7 mile section

    • I-55 West Memphis (1980)– 6-inch CRCP over 9-inch JPCP– ADT=26,600 w/ 28% trucks (1986)– 2.2 mile section

    CRSI 1988

  • Unbonded CRCP Overlays Issues

    1. Assessing existing pavement conditions2. Interlayer type and thickness3. Overlay structural design4. Pre-overlay repairs (?)5. Construction specifications and details

  • Condition Survey Information• Failures / mile• Materials-related distress (freeze-thaw,

    ASR, etc.)• Deflection or PSIt• Drainage condition

    – Interlayer or subbase erosion

  • CRCP Structural Evaluation Current Distress

    Level Inadequate Marginal Adequate

    Punchouts (M,H), # / lane km (#/ lane mi)

    Interstate freeway > 6 (10) 3-6 (5-10) < 3 (5) Primary > 9 (15) 5-9 (8-15) < 5 (8) Secondary > 12 (20) 6-12 (10-20) < 6 (10)

    Patch deterioration (M,H), % surface area

    Interstate freeway > 5 2-5 < 2 Primary > 10 5-10 < 5 Secondary > 15 8-15 < 8

    Longitudinal joint spalling (M,H), % length

    Interstate freeway > 50 20-50 < 20 Primary > 60 25-60 < 25 Secondary > 75 30-75 < 30

    Materials related distresses: D-cracking and ASR

    All M to H severity with significant spalling & jt. disintegration

    L to M severity with spalling & jt disintegration

    None to L severity

    Deterioration of past maintenance activities (patches and other repairs), % surface area

    Interstate/Freeway > 8 3-8 12 5-12 15 10-15

  • Resurfacing Threshold Values TxDOT

    • < 1.2 failures/km/yr (2 failures/mi/yr) allowed for thin HMA overlay used

    • 1.2-1.9 failures/km/yr (2-3 failures/mi/yr) allowed for BCOs

    • > 1.9 failures/km/yr (3 failures/mi/yr) allowed for UBCOLs

    Failu

    res /

    km

    Time

    Thin HMA Overlay

    UBOL

    BCO

    1.2 F/km/yr

    1.9 F/km/yr

    Failu

    res /

    km

    Time

    Thin HMA Overlay

    UBOL

    BCO

    1.2 F/km/yr

    1.9 F/km/yr

    •CTR 920-F

    CTR 1990

  • CRCP Pre-overlay repairs

    Distress Types Repair Methods Wide transverse cracks with significant differential deflection

    FDR

    Punchouts FDR Unstable slabs with large deflections FDR

    Slab stabilization Retrofit edge drains

    Severely spalled joints or cracks FDR HMA filling

    Pumping / Faulting (> 6 mm (0.25 in)) Retrofit edge drains Slab stabilization

    Settlement Level-up with HMA Poor joint / crack load transfer Repair not necessary, but a thicker separation

    layer should be considered Materials related durability problems: D-cracking or reactive aggregate

    UBOLs can be constructed

    after Smith et al. 2002, AASHTO 1993, ACPA 1990

  • Interlayer or Separation Layer Properties

    • Dense-graded HMA– Provide interface friction for crack development– >1-inch thickness to level up– Greater distress requires > interlayer thickness

    • Interlayers with past performance issues– PE sheeting, chip seals, slurry seal, or curing

    compound, open-graded AC– Erodible/stripping, not resistant to reflective

    cracks, insufficient friction

  • Separation Layer, con’t• Geotextile layer

    – Nonwoven used for JPCP unbonded overlays

    • Germany & Missouri

    – Not used for CRCP, yet– If distress is high then GT

    probably is not useful to stop low shear reflective crack

    – Doesn’t level up surface– Durability?

  • Structural Design MethodsCRCP Overlays

    • Darwin M-E (MEPDG)– Results in better thickness values

    • IDOT– Modified-AASHTO JRCP/CRCP Method– Subtract 1-inch for overlay

    • TxDOT– Traditionally, AASHTO 1993 for thickness design

  • 5 Million ESAL’sSoil CBR or “k”

    Soil CBR = 3.0

    “k” = 100

    100 ft Jointed = 10in.

    CRCP = 8in.

    CRCP 80% of Jointed

  • Typical Illinois DOT (2007)New CRCP Thickness Design

    Thickness ESAL, Millions

    8 in. 5

    10 in. 20

    12 in. 100

    14 in. (max) 300+

    •CRCP overlay design minus 1-inch

  • Construction Issues• Pre-overlay repairs

    – Punchouts!– High severity spalling– Subgrade/Drainage problems

    • Concrete Material Selection• Steel Content

    – Minimum 0.60%• Interlayer provides friction

    – Erodibility test of interlayer • Hamburg Test (after Zollinger et al.)

    – Whitewash surface or debond base layer (?)

  • IDOT CRCP Unbonded OverlaysHistory

    • Constructed Unbonded overlays since 1967• I-55 and I-70 (3 sections) – 1967,1970, 1974

    – Unbonded CRCP overlay of JRCP• I-74 Knox County - 1995• I-88 Whiteside Country – 2000-01• I-70 Clark County – 2002• I-57/I-64 Mt. Vernon – 2011-12

  • I-70 CRCP Overlay Sections• CRCP Overlay (1967) – MP 31-35

    – 8,7, and 6-inch CRC w/ 0.6, 0.7, & 1.0% steel• 6-inch HMA interlayer• 10-inch JRCP

    – ADT = 14,000 w/ 34% trucks• 17 million (1986)

    – CRS = 5.7 (1986) & R.I. = 86• 7.3% patching for 6-inch CRCP & 0% for 8-inch

    – Overlaid in 1989

    – Minimum req’d = 7 inches Lippert & DuBose 1988

  • I-55 CRCP Overlay Sections

    • 8-inch CRCP Overlay (1970)– Springfield, IL (MP 89-92)– 9-inch JRCP– Steel content= 0.6%– 4 inch HMA interlayer + 8 inch HMA overlay– ADT = 24,600 w/ 15% trucks– CRS=6.5 & R.I. = 85 (1986)– Crack Spacing = 2.9 ft (1986)– Percent patching= 0.1% (1986)– Total ESALs=9.2x106

    Lippert & DuBose 1988

  • I-55 CRCP Overlay Sectionscon’t

    • 9-inch CRCP Overlay (1974)– Springfield, IL (MP 105-108)– 10-inch JRCP– Steel content= 0.6%– 4 inch HMA interlayer– ADT = 17,000 w/ 22% trucks– CRS = 7.2 & R.I. = 97 (1986)– Crack Spacing = 3.2 ft– Percent patching= 0% (1986)– Total ESALs=9.1x106

    Lippert & DuBose 1988

  • I-74 Knox County (1995)Existing

    • MP 54-62 Westbound only– East of Galesburg

    • Existing pavement cross-section (1969)– 3 to 4.5 inches HMA overlay– 7-inch CRCP– 4-inch HMA base

    • Severe D-cracking and punchouts– Transverse and longitudinal cracks in HMA overlay– Full-depth concrete patches

    McNeal 1996; Heckel 2001

  • I-74 Knox County (1995)• 9-inch CRCP overlay w/ tied PCC shoulders

    – Design ESALs = 24 million– Crack spacing = 3.1 ft (1997); 2.3 ft (2001)

    • 2009 AADT = 14,800 (SU = 550, MU = 3300) – Annual ESALs = 1.070x106

    • Condition Rating Survey (CRS) value– 8.3 out of 9.0 (2001)– 8.2 out of 9.0 (2009)

    • IRI – 70 (2001); 69 (2009)• Transverse crack LTE = 92% (2001)

  • I-88 Whiteside County (2000-01)

    • IL 78 to west of Rock Falls

    • Existing 8-inch CRCP (1975)– Crushed river gravel– blowups and D-cracking problems– HMA overlays in 1988, 1991– Recurring blowups and D-cracking

  • I-88 Whiteside County (2000-01)

    • 9.25-in CRCP unbonded overlay– 1-inch leveling binder placed on top of the

    existing 3.25-inch HMA overlay

    • 2010 CRS = 8.0 out of 9.0• IRI (in/mi) = 52 EB, 57 WB• 2009 AADT = 8800 (SU = 300, MU = 2300)

    – Annual ESALs = 0.741x106

  • I-70 Clark County (2002)General Project Information

    • Originally constructed in 1969• 8-inch CRCP on 4-inch HMA base• Subsequent bituminous overlays totaling 7-

    3/4 inches• Traffic (2-way)

    – Current ADT of 24,000 with 42% trucks• Location = IL 1 to Indiana Line

  • Proposed Pavement Cross Section

    4” Asphalt Base

    8” CRCPBITUMINOUS

    SHOULDER

    BITUMINOUS OVERLAYBITUMINOUS OVERLAY

    MILL OR OVERLAY TO GRADE LINE

    12” UNBONDED

    CRCP OVERLAY

    12” PCC

    SHOULDERS12” PCC

    SHOULD.

    12 ft. 6 ft.24 ft.

  • IDOT CRCP Design (I-70)• Pavement design = Chapter 54 of BDE manual

    – 30-year design traffic of 116x106 ESAL’s (rigid)– New design = 13-inch slab thickness

    • Thickness credit of 1-inch given in areas of unbonded overlay (NCHRP/Corps of Engrs.)– 12-inch design thickness w/ 0.80% steel (#7 bars)– Nominal 5-inches of HMA interlayer– 25 bars at 6-1/4 in. centers-longitudinally– #4 bars at 2-ft. intervals-transversely

  • I-70 CRCP Overlay Warranty

    • 5-year duration• Warranty bond required• Warrants materials and workmanship• 95% of pavements expected to not need

    warranty work• Evaluated in 0.10-mile sections• Distress parameters defined in SHRP’s

    “Distress ID Manual for LTPP” P-338

  • Warranted CRCP Distresses• Transverse and longitudinal cracking

    (moderate and high severity)• IRI limited to 150 in./mi.• Spalling of longitudinal joints• Scaling• Patch deterioration• Punchouts• Corrective actions defined for each distress

  • I-70 Clark County (2002)Performance

    • 12-inch CRCP overlay w/ HMA interlayer• 5 yr. warranty contract

    – two dozen “punchouts” in 9 miles of pavement– problem (?) = 12-ft. full-depth PCC shoulders tied with

    #8 bars had punchouts located at jointed shoulder.

    • Overall performance very good– CRS = 8.1 (2010)

    • IRI = 65 (EB); 69 (WB)• 2010 AADT = 20,500 (SU = 650, MU = 8000)

    – annual ESALs = 2.55x106

  • I-70 CRCP Overlay

  • Example: Early-Age Punchout

  • I-57/I-64 Alternatives (2010)

    • HMA overlay of existing CRCP– Rubblization with HMA– JPCP and CRCP options

    • MEPDG & IDOT designs• Milling options vs. rubblization• Interlayer type• Thickness options

  • Poor Section I-57/I-64 NB

  • Good Section I-57 NB

  • MEPDG CRCP OverlayInputs

    • 20-year design life– Mattoon-Charleston, IL Climate

    • ESALs – 80x106

    • A-7-6 soil type– k=200 psi/in

    • Tied concrete shoulder– 40 to 80% LTE

    • CRCP Steel properties – 3.5 inch depth, #6, 0.7%

  • MEPDG CRCP DesignResults

    • New CRCP = 11 inches– HMA base unbonded = 4inches

    • Unbonded CRCP = 9 inches– AC base interlayer = 2 inches– CRCP (existing) = 8 inches

    • Unbonded CRCP = 10.5 inches– HMA interlayer = 1 to 2 inches– CRCP (rubblized) = 8 inches

  • I-57 / I-64 Mt. Vernon (2011)• Mill existing HMA overlay• Rubblize existing 8-inch CRCP• Place 3-inch HMA interlayer• 10.5-in. CRCP overlay w/ 0.7% steel

  • National Performance

    (Smith et al. 2002)15 sections in GA, IL, ND, WI, AR, MD, PA

  • Performance Recommendations

    • Concrete Overlay > 7 inches– Consistent with IDOT policy

    • HMA Interlayer > 1-inch– Dense-graded

    (Smith et al. 2002)

  • LTPP Database

    • 4 unbonded CRCP sections

    • Georgia– 20-yr– HMA Interlayer = 0.75 inch– CRCP overlay 8.25-inch– Existing section 8-inch

  • CRCP Overlay of JPCP in UK

    • Refurbish 6.2km section of M25 London Orbital Motorway during 2000/2001

    • Strengthened using hybrid solution of 200mm CRCPoverlay for most heavily loaded traffic lanes 1-2, with AC overlays for lane 3 & shoulder

    • Existing 3-lane dual carriageway of un-reinforced concrete slabs with contraction joints at 5m centres– Road opened to traffic in 1979– 10mm AC OL in 1990– Large amount of pavement faulting due to underlying clay– AADT currently exceeds 120,000 vehicles approximately

    15% classified as Heavy Goods Vehicles (HGV’s)

  • M25 London Orbital Motorway, UK

  • CRCP Unbonded Overlay Summary

    • CRCP unbonded overlays– 7 to 12 inches– Steel content = 0.6 to 0.8%– #5 to #7 bars– design ESALs from 5 to 100x106 ESALs

    • HMA interlayer– Dense-graded asphalt mixtures– >1-inch

  • Current I-39 Section Issue• Existing CRCP (~10in) and JPCP (11,14 in)

    with materials-related distress (?)• Constructed 1989

  • Concrete Material Distress

  • CRCP Polished Section

    Lankard 2012

  • Bibliography• Rasmussen, R., Rogers, R., Ferragut, T. (2009), Continuously Reinforced

    Concrete Pavements Design and Construction Guidelines, FHWA-CRSI.• Harrington, D. et al. (2008), Guide to Concrete Overlays Sustainable Solutions for

    Resurfacing and Rehabilitating Existing Pavements, National Concrete Pavement Technology Center, Iowa State University, Ames, IA.

    • Smith, K.D., H. Yu, D. Peshkin, (2002), Portland Cement Concrete Overlays: State of the Technology Synthesis, Federal Highway Administration, Washington, DC.

    • Lippert, D., DuBose, J. (1988), Performance Evaluation of Concrete Overlays, Physical Research Report No. 101, Bureau of Materials and Physical Research, Illinois Department of Transportation.

    • McNeal, A. (1996), Planning , Design and Construction of an UnbondedConcrete Overlay, Physical Research Report No. 122, Bureau of Materials and Physical Research, Illinois Department of Transportation.

    • Heckel, L.B. (2002), Performance of Unbonded Concrete Overlay on I-74, Physical Research Report No. 140, Bureau of Materials and Physical Research, Illinois Department of Transportation.

    • Gagnon, J.S., Zollinger, D.G., and Tayabji, S.D. (1998), Performance of Continuously Reinforced Concrete Pavements: Volume V: Maintenance and Repair of CRC Pavements, FHWA-RD-98-101

  • Bibliography, con’t

    • CRSI (1988), Performance of CRC Overlays: A Study of Continuously Reinforced Concrete Resurfacing Projects in Four States, 26 pp.

    • CRSI (1973), Design and Construction of Continuously Reinforced Concrete Overlays, 17 pp.

    • PCA (1976), Continuously Reinforced Concrete Overlay: 1975 Condition Survey, 26 pp.