68
PUBLIC EXPENDITURE REVIEW PROGRAM ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA Submitted to the World Bank, Colombo Amal S Kumarage University of Moratuwa Moratuwa, Sri Lanka [email protected] 15 th June 2006 FINAL REPORT

ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

PUBLIC EXPENDITURE REVIEW PROGRAM

ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

Submitted to the World Bank, Colombo

Amal S Kumarage

University of Moratuwa

Moratuwa, Sri Lanka

[email protected]

15th

June 2006

FINAL REPORT

Page 2: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

i

TABLE OF CONTENTS

1 PRELIMINARIES __________________________________________________________ 1

1.1 Scope and Objectives ____________________________________________________ 1

1.2 Methodology ___________________________________________________________ 2

2 INTRODUCTION ___________________________________________________________ 3

2.1 Road System in Sri Lanka _________________________________________________ 3

2.2 Government Policy of the Road Sector _______________________________________ 5

2.3 Government Developmental Objectives relating to inputs to Road Sector ____________ 5

2.4 Funding for Road Construction & Management ________________________________ 7

3 ANALYSIS OF PUBLIC EXPENDITURE ON ROADS ____________________________ 10

3.1 Public Expenditure on Roads _____________________________________________ 10

3.2 Sources of Funding for Roads and Budgetary Processes _________________________ 26

3.3 Efficiency of Utilizing Funds Allocated _____________________________________ 29

3.4 Sustainability of Road Expenditure _________________________________________ 32

3.5 Institutional Arrangements in Road Sector ___________________________________ 34

4 INTERVENTIONS FOR IMPROVING OUTCOMES OF SPENDING ON ROAD

SECTOR _____________________________________________________________________ 37

4.1 Identify the overall sector Investment Level __________________________________ 37

4.2 Identify Allocation Levels by Type of Investment _____________________________ 38

4.3 Improving Effectiveness of Expenditure Allocations ___________________________ 45

4.4 Improving Utilization of Allocations _______________________________________ 47

4.5 Enhancing Sector Capacity _______________________________________________ 48

5 PERFORMANCE INDICATORS ______________________________________________ 51

6 DATA COLLECTION FORMAT ______________________________________________ 54

7 SUMMARY TABLE OF CONCLUSIONS & RECOMMENDATIONS ________________ 57

Appendix I Data Collection ___________________________________________________ 62

Appendix II Treasury Allocations for Road Construction _____________________________ 63

Page 3: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

ii

LIST OF TABLES

Table 1: Road Network in kms _____________________________________________________ 3

Table 2: MTEF Budget Allocations for Pro-Poor and Pro-Growth Regional Development ________ 6

Table 3: Allocations to Local Authority Roads _________________________________________ 8

Table 4: Overview of Allocations for Road Development 2006 ____________________________ 10

Table 5: Spending on National Roads 2005-2006 (Rs Million) ____________________________ 15

Table 6: Spending on Provincial Roads 2005-2006 (Rs Million) ___________________________ 16

Table 7: Spending on Urban Roads 2005-2006 (Rs Million) ______________________________ 18

Table 8: Summary of Spending on Rural Roads _______________________________________ 19

Table 9: Spending on Rural Roads 2005-2006 (Rs Million)_______________________________ 20

Table 10: Total Public Expenditure on Roads and its Analysis (2006 Allocations)- Rs billion ____ 24

Table 11: Trends in Public Expenditure on Roads (2003-2008)- Rs million __________________ 26

Table 12: Road User Charges: 2003 (Million Rupees) ___________________________________ 26

Table 13: Total Public Expenditure on Roads and its Analysis (2006 Allocations)- Rs million ____ 27

Table 14: Treasury Allocations on Roads by Agency Level (2006 Allocations)- Rs million ______ 28

Table 15: Utilization of RDA Funds for 2005 _________________________________________ 29

Table 16: Allocations & Utilization of Funds for National Roads (Ministry of Highways) _______ 30

Table 17: Utilization Rates for funds made available for Provincial Roads ___________________ 32

Table 18: Utilization Rates for funds made available for Local Authority Roads _______________ 32

Table 19: Analysis of Public Expenditure on Roads by Sector (2006 Allocations)- Rs million ____ 39

Table 20: Lane kms of National Road Network ________________________________________ 39

Table 21: Rehabilitation Costs for Road Network ______________________________________ 40

Table 22: Maintenance Costs of Road Network after Rehabilitation ________________________ 42

Table 23: Sector Allocations at different Investment Levels ______________________________ 44

LIST OF FIGURES

Figure 1: Trends in Public Expenditure on Roads (2003-2008) ____________________________ 25

Figure 2: Utilization of Funds for National Roads (2001-2005) ____________________________ 31

Page 4: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

1

1 PRELIMINARIES

A core objective of the Public Expenditure Review for which this report is prepared is given as ‘to

assist the Government in increasing the output-orientation of the budget system as an integral part of

its medium term expenditure framework (MTEF), thereby strengthening the links between policy

priorities and the budget’.

The overall goal of this report is therefore, to identify the means by which the government can

improve the efficiency of its expenditures on roads, so that a desirable level of services can be made

available for road users for the level of expenditure provided for roads in the MTEF, which is taken as

the primary instrument of policy implementation of the government.

This review of the road sector budget allocation will investigate if it is in line with the intended

outcomes as defined by policy objectives and the medium term expenditure framework.

However, any success from an outcome-based budget will only be achieved if it translates into timely

delivery of the desired outcomes. Thus, the execution of the budget will also be examined in terms of

performance indicators and efficiency of expenditure.

Therefore, the specific objectives of the study as referred to in the Terms of Reference issued for this

purpose are understood to be as follows:

(i) To assess the expenditure levels in roads and evaluate if government objectives are being met in

allocations and spending.

(ii) To assess and formulate performance indicators to measure the efficiency of expenditures looking

at both costs and the outputs and outcomes of the road sectors in terms of service delivery.

1.1 Scope and Objectives

As outlined in the Inception Report dated 27th March 2006, this report is the Final Report combining

all material set out in the following parts:

• Part I -Assessment of Expenditure Levels

• Part II -Evaluation of Expenditures and Stated Objectives

• Part III -Assessing and formulation of performance indicators

• Part IV -Preparation of a Data Collection Format

The specific objectives for this report are:

• To identify the road network in terms of institutional responsibility for construction &

management

• To identify the different sources of funding

• To quantify the levels of funding provided and utilized for the period 2000 to 2006

• To establish trends in spending on roads during this period

• To identify reasons for any divergence between funds provided and actual utilization

Page 5: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

2

• To assess the capacities of these implementing agencies to undertake the scope of work

pertaining to the allocated expenditure and the desired level of output

• To assess the expenditure levels in roads and evaluate if government objectives are being met

in allocations and spending

• To assess if expenditure priorities have been identified in projects and if these priorities have

been observed in expenditure patterns;

• Formulating suitable performance indicators to be used for sector allocations and intra-

sectoral allocations and for budgetary monitoring and

• Formulation of a draft data collection form for prioritizing capital allocation for the road

sector.

1.2 Methodology

This report has been compiled after study of the funding methods pertaining to the road sector

especially with respect to actual expenditure for the year 2005 and allocations for the year 2006. It

has been derived from an examination of budget documents as well as implementation programs and

accounts of on-going projects at all tiers of road administration.

However, the scope of the study which has an overall time frame of six weeks, does not allow for

extensive data collection and verification of all details, particularly at the provincial and local

government levels, where such data is most difficult to arrive at.

Therefore the study, included visits to two provinces, namely Southern and Uva to obtain actual

expenditures received at both provincial and local authority levels and to identify the quantum and

procedures under which such funds are received. The rationale for selecting these two provinces and

the institutions from which data was collected by personal visits and interviews is given in Appendix

I. Spending in other provinces was estimated based on the experiences gathered from these two

provinces.

The estimates of expenditure made in this study are based on data that was collected within the scope

of the study. Road expenditure especially on rural roads has been obtained from numerous sources,

many of which have included such expenditure under broader accounting heads. As such the estimates

at the rural level are only the most educated and scientifically derived estimates and should not be

taken as the final accounting figures. Even at other levels, the lack of an acceptable convention for

accounting of different types of expenditure has led to some degree of discrepancy and variance in

reported figures.

Page 6: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

3

2 INTRODUCTION

2.1 Road System in Sri Lanka

The road network in Sri Lanka is made up of several types of roads classified according to their

functionality and management. There is no formally accepted classification system for Sri Lanka. The

following classification and notation will be followed in this report:

• National Roads

• Provincial Roads

• Urban Roads

• Rural Roads

The national road network had by 1959, expanded to 7,034 kms with a further 12,070 kms of other

roads of lesser importance. Since independence in 1948, a noteworthy shift in road building was seen

with emphasis on access roads, particularly to rural villages. This has today, increased to an estimated

75,424 kms. On the other hand, additions to the national road network have been comparatively less

significant, with the majority being upgrades from provincial roads. The most notable contribution of

new roads have come from agricultural and irrigation projects, especially the 467 kms under the

Mahaweli Diversion Program. The detailed inventory of road lengths was last carried out in 1990

when part of the road network was handed over to Provincial Councils by the Road Development

Authority. It was then 94,208 kms, returning a road density of 1.47 kms per square km of land area.

The estimated road length in 20021 was 108,103 kms with over 28,000 kms in paved condition.

Table 1: Road Network in kms2

Year

National

Roads

Provincial

Roads

Urban

Roads

Rural

Roads

Total

Road

1905 6,024 6,024

1959 7,034 12,070◊ 19,104

1990 10,447 14,916 2,791 66,054 94,208

2002 11,760 15,743 5,176 75,424 108,103

National Highways: These are roads that are presently managed by the Road Development Authority

(RDA) and constitute the roads classified as A & B Class. Such roads are generally those that are

considered as part of the national road network or provide access to places of national importance etc.

Roads that belong to the provincial authorities as well as agencies such as the Mahaweli Authority,

Municipal Councils are periodically gazetted and added to the national network. These roads are

maintained by the RDA, with the exception of around 80 kms within Colombo city which is

maintained by the Colombo Municipal Council. .

1 Source National Atlas 2001

Page 7: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

4

Provincial Roads: These are roads that were classified as C, D and E class when the Provincial

Councils were established in 1989 under the 13th amendment to the Constitution. Usually, these are

roads on which a bus service operates and where such road is situated entirely within the province.

There has been no physical verification carried out to determine the exact length of provincial roads.

Its extent was estimated at 15,743 kms in 2002. These roads are managed by the respective Provincial

Councils which have a statutory body commonly referred to as the Provincial Road Development

Authority (PRDA) or a Roads Department through which it manages the road network.

Urban Roads: Roads that are not classified as national roads or provincial rods but are within

Municipal or Urban Council areas (MCs and UCs respectively) are identified in this report as urban

roads. These roads are maintained by local governments- i.e. MCs or UCs. Some urban roads such as

in Colombo and Kandy are used by heavy traffic and in a functional sense is part of the national

highway network. The Dehiwela-Mt Lavinia MC has 594 kms of roads, while Colombo MC has 480

kms of road. Other municipal councils have between 30 to 200 kms each, while the urban councils

have between 10 to 50 kms each. There are 18 Municipal Councils and 48 Urban Councils managing

between them 5,176 kms of road. Around 1/4th of this road length may be considered as gravel or

earth roads. Only a length of around 80 kms in Colombo and 8 kms in Galle are two lane or wider,

other being single lane residential roads.

Rural Roads: These are roads in rural areas maintained by rural local authorities called Pradeshiya

Sabhas (Village Councils earlier). The length of these roads was estimated in 2002 as 75,424 kms.

Unlike the other roads described earlier, most of these roads are earth or gravel roads.

Roads maintained by other Institutions: There are yet other roads which do not belong to or are

maintained by any of the agencies specifically charged with road maintenance. These agencies

include the Mahaweli Development Authority, Irrigation Department, Forest Department, Wild Life

Conservation Department, Agrarian Services Department and Plantation Companies. The length of

these roads has also never been properly assessed, but is estimated at 4,500 kms by the Road Sector

Master Plan. Though these roads have not been gazetted as public roads, public funds are used for

their maintenance as these roads in most cases are used as public thoroughfares and accessed by the

rural population.

Roads not maintained by any Institution: There is also an unspecified length of road in each

province, which has not been included in the road inventory of any government institution. These are

usually roads serving a collection of houses or very small villages, which have been constructed

through self help schemes (Shramadana) or funded by the decentralized votes of parliamentarians or

provincial councilors, but have not been officially handed over to the Pradeshiya Sabha. The extent of

such road length is not known.

Page 8: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

5

Even though Sri Lanka has an impressive length of road network its performance in terms of speed

and safety are not satisfactory. The TransPlan3 road database on the national road network shows that

less than 2% of the network has an IRI (roughness index) of less than 2 m/km. In fact over 50% of the

length of the network has an IRI of more than 5 m/km- which is considered most unsatisfactory. With

the national network in such poor standard, the provincial and local authority roads for which there

are no measured indicators are bound to have worse conditions. The poor maintenance is contributing

to the congestion costs estimated at Rs 32 billion per annum, accident costs at Rs 12 billion per annum

and lost economic opportunities at Rs 270 billion per annum.4

2.2 Government Policy of the Road Sector

The National Road Policy (2002) give general objectives of the road sector to:

a) Promote the on-going economic development of the country, by taking into consideration the

present and future socio-economic development plans and policies, thereby improving the

quality of the people.

b) Facilitate greater mobility, shorter travel time and provide easy accessibility with improved

safety for the people.

c) Adequately meet the transport needs of the country, both passengers and freight transport

taking into consideration the current and projected future transport demand and such

projections shall accommodate restraint strategies.

d) Improve the quality of roads, by using cost effective and innovative techniques of design,

construction, maintenance and rehabilitation.

However, specific application of these policies in project formulation or in investment planning

cannot be observed at present. The budgetary process also does not include assessment of objectives

or outcomes of proposed projects in order to determine the degree of subscription of a project for

which funding is sought, to these policies.

2.3 Government Developmental Objectives relating to inputs to Road Sector

The Policy of the Government in terms of the ‘Mahinda Chinthanaya’ has been translated to an

implementation strategy through the Medium Term Expenditure Framework (MTEF) for the period

2006-2008. The MTEF perspectives are based on allocating resources to achieve the Millennium

Development Goals (MDGs) and targeting an economic growth rate of 6 to 8 percent. It emphasizes

on programs to eradicate poverty, remove regional disparities of socio economic development, to

empower the poorest and raise the living standards of all segments of the society.

3 University of Moratuwa, 2006

4 Source: Kumarage, Amal S. LBO, May 2006

Page 9: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

6

The 2006 budget—initially issued in November 2005 together with the MTEF was later revised in

December 2005 in order to reflect more closely the newly elected President’s vision, increased

emphasis on infrastructure and rural development.

There are a number of lead projects identified under the Pro-Poor Pro-Growth and Regional

Development strategy of the Mahinda Chinthanaya, which has a number of project through which

there are investments intended for roads and bridges. These are given in Table 2.

Table 2: MTEF Budget Allocations for Pro-Poor and Pro-Growth Regional Development5

Project

2006

Budget

Rs mn

2006-8

Projected

MTEF

Budget

Rs mn

Project location and benefits

Gamipubuduwa 672.85 672.85 Implementation of small scale 45,000

projects to develop basic infrastructure

which will include bridges

Maga Neguma 800.06 2900.0 Upgrading of 4,500 kms of rural gravel

roads to motorable level

North East Community Development

and Restoration Project (NECORD)

1450.0 1450.0 Rehabilitation of roads, irrigation systems

and buildings.

Pubudamu Wellasa 506.9 706.9 Rehabilitation and development of rural

roads, and other community

infrastructure.

Road Improvements in Sabaragamuwa,

and Central Provinces (JBIC)

2034.0 4310.0 Rehabilitation of 1280 kms of C,D and E

roads

Road development in Western, North

Western and Uva Provinces (ASB)

2500.0 6750.0

Rural Economic Advancement Project

(ADB)

350.0 2350.0 Rehabilitation and improvement of 25

suspension bridges and other

infrastructure

North East Community Restoration and

Development Project

607.3 607.3 Development of community through

provision of rural roads and other

infrastructure.

Conflict Affected Area Rehabilitation

Project (CAARP)

2538.0 5225.0 Rehabilitation of essential economic and

social infrastructure in conflict affected

areas.

Rehabilitation of bridges (UK) 421.3 421.3 Rehabilitation of 89 bridges

North east Roads rehabilitation project

(EU)

240.0 1021.0 Rehabilitation of provincial and rural

roads

North East Community Restoration and

Development Project (ADB)

1450.0 4450.0 Rehabilitation of roads, irrigation systems

and buildings in north and east.

Trincomalee Integrated Infrastructure

Development Project (ADB)

300.0 1050.0 Development of community through

provision of rural roads and other

infrastructure.

5 Source: Medium Term Expenditure Framework 2006-2008, Department of National Budget

6 Subsequently increased to Rs 1,800 million

Page 10: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

7

In addition to the regional development strategy, the following specific road infrastructure

development projects which were identified in the Budget Speech of December 2005 have also been

provided funds in 2006 for the construction of:

• Southern expressway- Rs 6,382 million and

• Highway from Kalutara to Jaffna along the tsunami affected coastal belt- Rs 1,585 million

Domestic funds have also been provided for feasibility studies and land acquisition in the following

projects;

• Katunayake expressway- Rs 935 million,

• Kandy-Colombo Highway- Rs 13 million and

• Outer Circular Road - Rs 625.6 million.

No specific development strategies have been identified for the above investments and are considered

to be part of the overall road sector policy of providing for shorter travel times and greater mobility.

The funding for these projects has not been finalized yet, except in the case of the Katunayake

Expressway Project, for which Chinese funding has been secured most recently.

2.4 Funding for Road Construction & Management

The Government strategy pertaining to the manner of funding the road sector has not been explicitly

stated. The implicit strategy it has followed can be gathered from the funding arrangements in past

years and particularly the manner in which funding has been allocated for the different road networks.

This section investigates the funding for the road sector as contained in the budgetary provisions of

the Government. The actual expenditures based on the data collected from the provinces will be

discussed in Chapter 3.

The past practices before the creation of provincial councils was that all funding for roads was

allocated to two ministries. The Ministry of Highways was given funds for all roads A, B, C, D and E

while each local authority was given an allocation through the Ministry in charge of Local Authorities

for its own road network within their areas. However, with the advent of the Provincial Councils, this

situation changed with the Finance Commission made responsible for determining distributional

criterion for the allocations made by the Government to the Ministry of Local Government and

Provincial Councils under the requirements as per 13th constitutional amendment, together with the

Provincial Council Act No. 42 of 1987 and the Provincial Council (Consequential Provisions) Act No.

12 of 1989 which established legislative and executive powers at the provincial level.

Provincial Roads

Even though it has been observed that decentralization of the public sector and service delivery that

followed the creation provincial administrations has given to confusion and duplicity in many sectors

such as health, education and transport, this has been less so in roads, because of the ability to carve

out roads on a functional basis. Even though the decentralization provided the provincial councils

Page 11: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

8

with facilities such as workshops and plants for the provincial use, its biggest set back has been

dealing with the vacuum that was left when the higher technical capabilities, training facilities, codes

and practices and databases were retained at the central government levels. Inmost cases these are yet

to be developed. The provision of foreign funding for provincial roads is a relatively new strategy.

Since, domestic funds provided did not allow for rehabilitation of their networks, provinces have not

developed any investment or developmental plans for roads, other than yearly maintenance schedules.

Local Authority Roads

With the creation of an intermediate 3rd layer of administration, a number of changes in funding,

planning and management of local authority roads also took place. These have continued up to now

thus becoming de-facto ‘policy’. These may be summarized as follows:

• Urban local authorities have been considered as been affluent enough to generate own funds

for maintaining and constructing roads. Hence only a percentage of salaries (around 60-70%)

were paid to them. No capital allocations have been granted until 2006.

Table 3: Allocations to Local Authority Roads7

Year

2002 2003 2004 2005 2006

PSDG Allocation 9,219.0 3,700.0 4,830.0 8,000.0 14,742.0

Allocation for Provincial Roads 1,865.0 690.0 905.0 1,650.0 1,895.0

Allocation for Local Authority Roads 470.0 207.0 245.0 355.0 1,430.0

Allocations for Urban Roads Nil Nil Nil Nil 700.08

• The Pradeshiya Sabhas did not fare any better, getting only a fraction of the total allocations

for roads within the province. As shown in Table 3, even by the year 2002, local authorities

were receiving on average only 1/5th of the Province Specific Development Grants (PSDG)

capital allocations made to the province for all roads. (This situation has since improved with

the 2006 budget providing more than ½ of capital allocation on roads in the PSDG to local

authority roads).

• With the changes to election systems including the introduction of the Proportional

Representative System, where elected representatives had to compete for support in a larger

area, there is a history of spending on rural roads as one of the key strategies to win support.

• With local authorities unable to maintain the existing roads and accessibility becoming a

major social issue particularly in rural areas, Members of Parliament as well as Members of

Provincial Councils began utilizing whatever funds they had access to, irrespective of their

7 Source: Finance Commission

8 From 2006 funding for urban local authorities has been provided. Of the Rs 436.5 million allocation made to

Western Province, Rs 288 million has been ear marked by the Finance Commission for urban roads. Such

allocations to other provinces are being worked out. The value of Rs 700 million has been estimated on this

basis. This amount is from the total allocation of Rs 1,430.0 million for 2006.

Page 12: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

9

source, for rehabilitation of roads or for new roads in rural areas, where credit for their actions

was most likely to translate to political support.

• During periods when the centre and the local government were controlled by different

political parties, this situation took an even more politically strategic turn, where different

ministries of the Central Government started spending on rural roads under different

development activities funded by the Treasury.

• As a result a number of institutions are now administering funds for rural roads. The

Commissioners of Local Government in the provinces are often under pressure to utilize

funds intended for local authorities on roads selected by Members of Parliament or of

Provincial Councils. As such District Secretariats and Divisional Secretariats are also found to

be implementing road programs.

• Even though this political situation is not predominant at present, the apparent success of

direct delivery has been further extended in the 2006 budget with the creation of several

regional and development oriented ministries, where most of the projects handled by them

have components for spending on rural roads.

• Since, funds were allocated to different agencies, and road services delivery effected through

each of them, there was no permanent instrument for coordination between them. As a result,

no reviews have been undertaken to consider the equitability of funding between the three

levels. This led to roads having vastly different standards between the different levels as well

as between provinces. Moreover, roads were hardly ever developed as networks for regional

development. In most instances, the benefits of rehabilitating a national highway were not

reaped by the province which did not invest in its provincial roads to improve access to the

highway. On the other hand there are number of instances where the access road has been

developed to a much higher standard than the national road.

In summary it could be concluded that there is presently no evidence of specific policy directions to

determine

a. The overall investment strategy for the road network in terms of determining

allocations between maintenance, rehabilitation and new assets

b. The level of funding required for the road sector

c. The distribution of such funds to the different road networks

d. The distribution of such funds by type of investment namely maintenance,

rehabilitation or new roads.

e. The instruments of coordination between different levels of government or even

between agencies under central government which are provided funds for roads.

Page 13: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

10

3 ANALYSIS OF PUBLIC EXPENDITURE ON ROADS

In this chapter the report will attempt to address the following key questions:

a) What is the present level of funding for the road sector?

b) Who provides these funds, what is the associated budgetary process and where and

how are such funds spent?

c) What is the efficiency of using existing funds?

d) Is the spending on target to achieve the development objectives of the Government?

e) What are the capacity constraints for executing the required work program for the

present level of funding?

3.1 Public Expenditure on Roads

According to the NBD, the 2006 budget allocates Rs 53,278 million to the roads sector, with Rs

30,748 million (57%) in foreign funds. An overview of this is given in Table 4. The detailed

allocations made by the NBD on a project basis, are given in Appendix II.

Table 4: Overview of Allocations for Road Development 20069

Ministry

Projects

Na

tio

nal

Ro

ad

Prov

incia

l R

oa

ds

Local

Au

thori

ty

Ro

ad

s

Ru

ral

Roa

d

Ma

haw

eli

Roa

ds

Est

ate

Roa

ds

Tsu

nam

i

Aff

ecte

d R

oa

ds

Co

nfl

ict

Aff

ecte

d

Ro

ad

s

To

tal

FA

Highways 28,039 - - - - - 7,947 35,986 21,714

Road Development 1,70010

100 1,800 500

Local

Government &

Provincial

Councils

PSDG 1,895 1,430 110 80 3,515

RSDB - ADB 2,400 2,400 1,700

PRIP - JBIC 2,034 2,034 1,601

CAARP - ADB 2,538 2,538 1,900

STAART - - JBIC 211. 211 174

Sub Total 6,329 1,430 110 80 211 2,538 10,698 5,375

National Building & Development 1,660 1,348 3,008 2,212

Estate Infrastructure & Livestock

Development

900 900

Regional Development 451 451 174.0

Agriculture, Irrigation & Mahaweli Development

426 426 396

Rural Economic Development 10 10

Grand Total 28,039 6,329 1,430 2,271 506 1,000 9,818 3,886 52,278 30,748

Accordingly, Rs 28,039 million is allocated to the Ministry of Highways for the RDA’s national

roads. The allocations made for provincial and local authority roads through the Province Specific

Development Grant (PSDG) is Rs 1,895 million and Rs 1,430 million respectively. There is also Rs

9 Source; Summarized from computations of National Budget Department

10 Includes Rs 1,000 million in supplementary estimates

Page 14: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

11

4,434 million for projects funded by foreign aid. This amount of Rs 7,769 million is allocated to the

Ministry of Local Government & Provincial Councils and disbursed directly to the Chief Secretaries

of the Provincial Councils on the recommendations made by the Finance Commission, based on

expenditure programs submitted by the relevant provincial councils.

There is a further Rs 3,777 million allocated for Rural, Mahaweli and Estate Roads- roads that would

fall within the rural definition adopted in this report. As seen above, in Table 4, this is provided

through 06 different line ministries of the Central Government. A further Rs 9,818 million is allocated

for Tsunami Affected Roads. The bulk of this (Rs 7,947 million) is allocated to the Ministry of

Highways for national roads; Rs 211 million is allocated to Ministry of Local Government &

Provincial Councils for provincial roads with another Rs 1,660 million allocated to the Ministry of

Nation Building & Development, mostly for national roads. In addition there is Rs 3,886 million

allocated for roads in Conflict Affected Areas, with 73% made up of foreign funds. In this instance,

the bulk of the allocation (Rs 2,538 million) is allocated to the Ministry of Local Government &

Provincial Councils for spending on provincial roads. The balance Rs 1,348 million is allocated to the

Ministry of Nation Building & Development for both national and provincial roads in the North East.

According to the above, the NBD has identified 08 line ministries to which funds have been allocated

for spending on roads with Rs 35,986 million voted to the Ministry of Highways and Rs 10,698

million voted to the Ministry of Local Government & Provincial Councils. The balance funds mostly

for rural roads amounting to Rs 5,594 million, is allocated through the following line ministries:

• Head 180 Ministry of Nation Building & Development –Rs 3,008 million

• Head 220 Ministry of Rural Economic Development – Rs 10 million

• Head 310 Ministry of Agriculture, Irrigation & Mahaweli Dev.- Rs 426 million

• Head 530 Ministry of Estate Infrastructure & Livestock Dev.- Rs 900 million

• Head 680 Ministry of Regional Development- Rs 450 million

• Head 630 Ministry of Road Development – Rs 1,800 mn (including to Rs 1,000 mn

from supplementary vote)

Even though these funds are destined for roads coming within the purview of provincial councils or

local government authorities, the funds are not channeled through the Ministry of Local

Government & Provincial Councils or the Finance Commission or even through the relevant

Provincial Council or Local Authority. These are often spent through the Divisional Secretaries

office or the District Secretary’s office.

Moreover, review of present practices reveals that many of the other central government ministries

and agencies were also spending directly on roads mostly at rural level. Information was collected

from the following institutions to quantify their spending on roads as well as the manner in which the

funds are being spent.

• Head 430 Ministry of Local Government & Provincial Councils

• Head 440 Ministry of Infrastructure Development and Fisheries Housing

• Head 500 Ministry of Samurdhi & Poverty Alleviation

Page 15: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

12

• Head 520 Ministry of Fisheries & Aquatic resources

• Head 660 Ministry Agrarian Services & Development

• Head 720 Ministry of Rural Livelihood Development

• Head 854 Department of Forests

• Head 863 Department of Wild Life Conservation

• Southern Development Authority

Other ministries which could be potential spenders on roads, but from which information could not be

gathered are:

• Head 360 Ministry of Urban Development & Water Supply

• Head 380 Ministry of Housing & Construction

• Head 450 Ministry of Enterprise Development & Investment Promotion

• Head 480 Ministry of Plantation Industries

• Head 610 Ministry of Agricultural Development

• Head 620 Ministry of Industrial Development

• Head 650 Ministry of Irrigation

• Head 660 Ministry of Agrarian Services & Development of Farmer Communities

• Head 750 Ministry of Environment

The allocations made for 2006 by each of the above agencies will be fully discussed in the next

chapter.

Treatment of Recurrent Costs

Most road sector analysis considers only the capital costs. However recurrent costs such as for salaries

are treated differently by different agencies. In the RDA, in the past an overhead was levied on all

capital work carried out. This was used for payment of salaries and other operational expenses.

However, now RDA receives a recurrent allocation in the budget. In the provinces, even though the

salaries are paid by the block grant from Government, most agencies levy a fee of between 3 to 4%

which is used to meet shortfall in recurrent expenses. This report will consider total costs including

both capital and recurrent costs.

In order to identify the budgetary processes involved in spending on each type of road, this report will

analyze the public expenditure on roads under the following sub headings:

• Public Expenditure on National Roads

• Public Expenditure on Provincial Roads

• Public Expenditure on Urban Roads

• Public Expenditure on Rural Roads

Public Expenditure on National Roads

As outlined earlier, the spending on national roads comes from more than a single sources. These are

identified as:

Page 16: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

13

a) Central Government Allocations for both capital and recurrent expenditures made to the

Ministry of Highways for work carried out through the RDA.

b) Projects funded through foreign loans channeled to the RDA through the Ministry of

Highways.

c) Projects funded through foreign loans channeled to the RDA through other central

government ministries and agencies without being allocated to and going through the

Ministry of Highways.

The review of the records of both the RDA and the NBD reveals that even though the spending on

national roads is mostly carried out through the RDA, there are other ministries such as the Ministry

of Nation Building & Development and the Ministry of Local Government & Provincial Councils that

handle budget allocations spent on national roads. The summary of spending for national roads in

2005 and the allocations for 2006 are given in Table 5. In this table the spending by the Ministry of

Mahaweli on a major road which will eventually become part of the national road network has also

been considered here. This is treated in this manner since; several hundred kms of roads constructed

by the Mahaweli Authority have been taken over by the RDA and included in the national network

over the last decade or two. The total allocations for this is Rs 4,829 million and is a significant

proportion when compared with the Ministry of Highways allocation for national roads at Rs 34,831

million.

Public Expenditure on Provincial Roads

The spending on provincial roads also comes from a number of sources. These are identified as:

a) Central Government Allocations for both capital and recurrent made to the Ministry of Local

Government & Provincial Councils and distributed to the individual provinces according to

the recommendation of the Finance Commission;

b) Projects funded through foreign loans channeled directly to the relevant province by the

Ministry of Local Government & Provincial Councils without going through the Finance

Commission;

c) Projects funded through foreign loans channeled directly to the relevant province by other

central government ministries and agencies without going through either the Ministry of

Local Government & Provincial Councils or the Finance Commission and

d) Provincial Revenue allocated for roads through the provincial budgets.

In order to obtain a more reliable estimate of the level of spending on provincial roads, two provinces

namely the Southern Province and the Uva Province were selected for an in-depth evaluation. The

two provinces were selected on the basis of their differences in socioeconomic profile as well as in

topography. The Southern Province has a coastline comprising mostly of agriculture and tourism

based economy. It has been developing slowly, but its main economic centers were severely affected

by the tsunami of December 2004. The Uva Province on the other hand is situated in the central hill

country and comprises of a predominantly plantation economy. It remains as a least developed

province having one of the lowest Regional GDPs.

Page 17: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

14

In each of the two provinces, discussions were held with the Chief Secretary as well as the agency

responsible for provincial roads. In the case of the Southern Province this was the Provincial Road

Development Authority and in the case of Uva, it was the Provincial Roads Department.

The report given as Appendix I, describes the data collection process and selection of agencies to

study the spending on roads. This information has been extrapolated to estimate the spending for all

the 08 provinces. Table 6 gives the estimated spending allocations for all provincial roads for the year

2006 as well as the corresponding expenditure incurred in 2005.

The total estimated allocation provided for provincial roads is Rs 9,140 million for 2006. Table 6

shows that the primary source of funding for provincial roads is through allocations made to the

Ministry of Local Government & Provincial Councils and on the recommendations of the Finance

Commission. Part of this is in the form of block grants for recurrent expenditure which is used for the

payment of a percentage (varying from 60 to 100%) of salaries of staff in the provincial councils and

local authorities and for other recurrent expenditure which includes an allocation for road

maintenance and office administrative costs at both levels. This is estimated at Rs 892 million for

2006.

There is also Province Specific Development Grants (PSDGs) amounting to Rs 1,895 million for

2006, which are capital grants to each province for designated purposes, which include spending on

roads. Since there is usually a shortfall from the block grants for administrative and operating

overheads, a percentage between 3 to 6 percent is deducted by the road agencies from the PSDG

capital allocations for provincial roads.

There is also criteria based and matching grants worked out on different basis where funds are

released for specific purposes, some of which includes roads. The portion spent on roads is estimated

at Rs 599.4 million.

However, at present the larger share of funds for provincial roads are for foreign funded road projects,

channeled through the Ministry of Local Government & Provincial Councils. Presently there are

projects funded by the ADB and JBIC amounting to allocations of Rs 4,645 million for 2006. The

provincial councils have varying degrees of involvement in these projects, but are clearly of the

opinion that such funding is not entirely at their discretion or management. Selections of roads, design

standards, contractual matters are some aspects that have been raised to explain the lack of

effectiveness in this spending.

There is a further Rs 896.8 million for tsunami rehabilitation allocated under the Ministry of Nation

Building & Development.. The estimated spending from provincial council funds is Rs 211.6 million

mostly used to pay the balance portion of salaries.

Page 18: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

15

Table 5: Spending on National Roads 2005-2006 (Rs Million)11

11

Source, Computations provided by University of Moratuwa, based on Budget Estimates for 2006 12 An estimated Rs 150 million has been reduced for maintenance spending on rural roads carried out by the RDA in 2005, with Rs 300 million allocated from the Road Fund. 13 As estimated Rs 500 million has been reduced for construction work carried out on rural roads by the RDA in 2005, with a provision of Rs 1,000 million for 2006. 14

From a total of Rs 425.7 million, it has been estimated that half would be spent on provincial roads. 15

Total spending for national roads is therefore the net spending on the national roads after reducing RDA spending for non-RDA roads and adding value of work accounted

through other agencies.

Ministry of Highways Other Ministries

Allocation

2005

Spending

2005

Allocation

2006

Project Allocation

2006 Institutional Expenses (Head

300 01 02 and 300 50 01)

Salaries, Administration, Land

Acquisition of Domestic Funded

Projects, Feasibility Studies, R&D

etc.

1,427.0 1,300.0 2,356.0 Nil

Maintenance (Head 300 50 02) 1,900.0 1,649.2 2,710.012 Nil

Rehabilitation & Improvement

of Existing Assets

Mostly FA projects which include

widening, surfacing and

reconstructions

8,810.0 7,096.4 26,123.513

CAARP thro M/LA&PC

STAART thro M/NB&D

Trinco IIDP thro M/NB&D

2,538.0

1,585.0

75.0

Replacement of Existing Assets Replacement of bridges 500.3 285.8 1,285.5 89 Bailey Bridges (EU)

Through M/NB&D

210.614

Acquisition of New Assets New road projects or new bridges 7,431.7 3,518.7 2,356.0 Dambulla-Bakamuna-

Kalagawela Rd project,

which is a Mahaweli Road

but should be part of the

National Network

425.7

Total spending for National Roads15

20,069.0 13,850.1 34,831.0 4,829.3

Page 19: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

16

Table 6: Spending on Provincial Roads 2005-2006 (Rs Million)

Source of Funding

Nature of Expenditure

2005 2006 Total

Allocation

of Vote

Actual

Expenditure

on Roads

% Spent

on Roads

Total

Allocation

of Vote

Estimated

Allocation

for Roads

Province Specific Development Grant (Channeled through the M/LG&PC and

provincial allocations made by the

Finance Commission)

All road related expenditure for Provincial

Roads

1650.0 1,286.2 100% 1895.0 1,895.0

Sub Total 1,895.0

Criteria Based Grants & Matching Grants for Capital Projects (Channeled

through the M/Local Government &

Provincial Councils and allocations

made by the Finance Commission)

Rehabilitation & Improvement of Capital Assets

(buildings, roads, bridges etc)

25% 1,998 499.5

Acquisition of Fixed Assets (buildings,

acquisition) etc

5% 1,998 99.9

Sub Total 599.4 Recurrent Grant (Channeled through

the M/Local Government & Provincial

Councils and provincial allocations made

by the Finance Commission)

Road Maintenance 0.75% 59,497 446.2

80% of Salaries Ministry & Road Agency Staff 0.75% 59,497 446.2

Sub Total 892.4

Foreign Funded Projects (Channeled

through the Ministry of Local

Government & Provincial Councils)

Road Sector Development Project (ADB-RSDP) 2,280 1,963.0 100% 2,400 2,400.0

Provincial Road Improvement Project (JBIC) 1,290 263.5 100% 2,034 2,034.0

STAART 211 211.0

Sub Total 4,645.0 Foreign Funded Projects (Channeled

through Ministry of Nation Building &

Development)

North East Community Restoration and

Development Project (ADB-NECORD)

1,986 1,249 100%

North East Emergency Restoration Project (WB) 620.0 100%

Part (estimated at 50%) of the funds for 89

Bailey Bridges Project for provincial roads (EU)

212.8 210.6

Projects -NECORD, NEIP and NECCDEP) 686.2 686.2

Sub Total 896.8

Provincial Revenue allocated to Roads (channeled through the Provincial

Budget)

Balance Salary (20%) 111.6

Other allocations (e.g. Chief Minister’s Fund) 100.0

Sub Total 211.6

TOTAL 9140.2

Page 20: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

17

Public Expenditure on Urban Roads

Urban roads have fewer sources of funding when compared to provincial roads. The primary

source of funding amounting to Rs 1,900 million out of a total allocation of Rs 2,776.2

million is through their own funds. As shown in Table 7, these funds are used primarily to pay

the shortfall in salaries after the payment of 60% of salaries provided by the Central

Government through the Ministry of Local Government & Provincial Councils and disbursed

direct to the respective Provincial Council based on the recommendation of the Finance

Commission. Except for a few councils which have reasonably good revenue bases, others

claim that they do not have adequate funds for maintenance and rehabilitation work on the

urban road system.

From 2006, the Finance Commission has agreed to release part of the funding under the

PSDG for local authority roads to urban and municipal councils as well. In addition, several

councils have to pay back loans taken for the UDLIHP program funded by the ADB during

2000 to 2004. This is for roads and bridges constructed under this project. The repayment is

based on a loan component of 20% of the total cost after a grace period of 3 years. While

some councils have kept up with repayments (e.g. Bandarawela UC), others (e.g. Badulla

M.C.) are struggling to do so. The overall spending on the urban road network is estimated at

Rs 2,776.2 million for 2006. Presently, urban roads do not receive any significant foreign

funds. Neither do they have any source of road user charges as opposed to Central

Government collections of import duties, fuel taxes etc and provincial revenues from fuel

taxes as well as vehicle licensing fees, which is reality is collected on their behalf too.

Public Expenditure on Rural Roads

The spending on rural roads cannot be estimated to any degree of reliability or accuracy. This

is because there are numerous sources, most of them executing the work through different

arrangements that vary from place to place. The primary source of funding is the annual

PSDG grant from the Central Government channeled through the Ministry of Local

Government & Provincial Councils and distributed through the Finance Commission with

instructions to the relevant Provincial Councils on the allocations to each Pradeshiya Sabha.

This has been estimated at Rs 1,000 million. There are also PSDG funds under a numerous

other headings such as Backward Areas Roads, Development of Scenic Resources, Mahaweli

Roads, Estate Infrastructure, Rural Infrastructure and 5 year Development Plan, which are

found to incur varying percentages of the allocated funds to each such vote on rural roads.

Such funding has been estimated at Rs 464.2 million in Table 8 which gives the summary of

the total calculations set out in Table 9. Apart from this there is Rs 199.8 million for varying

degrees of salary payments ranging from 70% to 100% and also for other recurrent

expenditure including an allocation for maintenance of roads.

Page 21: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

18

Table 7: Spending on Urban Roads 2005-2006 (Rs Million)16

Source of Funding

Nature of Expenditure

2005 2006

Total

Allocation

of Vote

Actual

Expenditure

on Roads

% Spent on

Roads

Total

Allocation

of Vote

Estimated

Allocation

for Roads

Province Specific Development Grant (Central

Govt funds voted to M/LG&PC on basis of

provincial allocations made by the Finance

Commission and distributed within province by the

relevant Provincial Council to Pradeshiya Sabha) )

Local Authority Roads (assuming 30% of this

for urban Local Authorities)

355.0 193.6 100% 430.0 430.0

Sub Total 430.0

Recurrent Block Grant (Central Govt funds voted

to the Ministry of Local Government & Provincial

Councils on and distributed within province by the

relevant Provincial Council to the Pradeshiya

Sabha)

60% of Salaries of Municipal or Urban Council

staff working on roads

0.75% 59,497 446.2

Sub Total 446.2

Municipal/Urban Council funds allocated for

roads (channeled through the own Budget)

Balance 40% of salaries above, Contract staff,

other recurrent expenditure including

maintenance for all councils and loan

repayments to roads and bridges projects carried

out under the ADB funded UDLIHP grant/loan

scheme 2000-2004. Computed from interviews

from 5 councils at the rate of Rs 1 million per

km for 200 kms of multi lane roads and balance

4,917 kms at Rs 350,000/- per km.

1900.0

Sub Total 1,900.0

TOTAL 2,776.2

16

Source: University of Moratuwa based on data collected for urban local authorities in Southern and Uva Provinces and the CMC

Page 22: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

19

Table 8: Summary of Spending on Rural Roads17

Source of Funding

Nature of Expenditure

2006

Total

Allocation

of Vote

Estimated

Allocation

for Roads

Province Specific Development Grant • Local Authority Roads 1000.0 1000.0

• Backward Area Roads 1153.0 462.6

Sub Total 1462.6

Criteria Based Grants & Matching Grants for Rehabilitation &

Improvement Capital Projects

3,998 199.8

Recurrent Block Grant mostly for 80%-100% of Salaries of Pradeshiya

Sabha staff

59,497 59.5

Foreign Funded Projects voted to a ministry other than the M/LG&PC but

implemented through the Provincial Council such as Rural Economic

Advancement Project

230.0 230.0

Foreign Funded Projects voted to a ministry

other than the M/LG&PC and implemented

directly

Maganeguma Program for

rural and estate roads

1800 1,800.0

Local Funded Projects identified as ‘Road Projects’ where funds are voted to

a ministry other than the M/ LG&PC is disbursed directly to the Pradeshiya

Sabha for rural roads

2,920.7 1,120.7

Local Funded Projects not identified hitherto as ‘Road Projects’ but where

funds voted to a ministry other than the M/ LG&PC is spent directly on rural

roads including Decentralized budget for all Members of Parliament at Rs 5

mn for 225 MPs (i.e. Rs 1,125 million @ 25% for roads Rs 281.3 mn).

814.7

Funds Allocated to RDA, spent on maintenance and reconstruction of rural

roads under vote heading such as ‘Emergency Road repairs’ etc

1,300.0

Provincial Revenue allocated to Roads

(channeled through the Provincial Budget)

PC Members and Chief

Ministers Vote

283.0

Pradeshiya Sabha funds allocated for roads

(channeled through the PS Budget)

Balance 20% of

salaries and other

expenditure

637.3

TOTAL 7,907.6

However, it can be seen from Table 8, that the majority of funds amounting to over 75% are

channeled outside of the purview of the Provincial Council or the relevant Pradeshiya Sabha.

This is because funds allocated to other ministries are usually spent through the District

Secretary’s office or the Divisional Secretary’s Office which come under the central

government.

17

Source: University of Moratuwa, computations based on Budget estimates and surveys made at rural

local authorities in Southern and Uva province.

Page 23: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

20

Table 9: Spending on Rural Roads 2005-2006 (Rs Million)18

Source of Funding

Nature of Expenditure Total

Allocation

of Vote

2005

Actual

Expenditu

re on

Roads

2005

% Spent

on Roads

Total

Allocation

of Vote

2006

Estimated

Allocation

for Roads

2006

Province Specific Development Grant (Central Govt funds

voted to Ministry of Local Government & Provincial

Councils on basis of provincial allocations made by the

Finance Commission and distributed within province by the

relevant Provincial Council to the Pradeshiya Sabha) )

Local Authority Roads (assuming only 70% for rural

Local Authorities from 2006)

355.0 193.6 100% 1000.0 1000.0

Backward Area Roads 70.0 67.2 100% 110.0 110.0

Maintenance of Mahaweli Assets 80.0 n/a 100% 80.0 80.0

Estate Infrastructure Other than Housing 32.0 n/a 20% 33.0 6.6

Development of Lesser Known Scenic Resources 23.0 n/a 20% 30.0 6.0

Rural Infrastructure 160.0 n/a 60% 100.0 60.0

Implementation of 5 year Development Plan - - 25% 800.0 200.0

Sub Total 1462.6

Criteria Based Grants & Matching Grants for Capital Projects (Central Govt funds voted to the M/LG&PC on

basis of allocations made by the Finance Commission and

distributed to Pradeshiya Sabhas within the province by the

relevant Provincial Council)

Rehabilitation & Improvement of Capital Assets

(buildings, roads, bridges etc)

5% 1998 99.9

Acquisition of Fixed Assets (buildings, acquisition

etc.)

5% 1998 99.9

Sub Total 199.8

Recurrent Block Grant (Central Govt funds voted to the

M/LG&PC and distributed within province according to

staff positions, by the relevant Provincial Council to each

Pradeshiya Sabha)

80%-100% of Salaries of Pradeshiya Sabha staff 0.1% 59,497 59.5

Sub Total 59.5

Foreign Funded Projects (voted to a ministry other than the

Ministry of Local Government & Provincial Councils but

disbursed through the relevant Provincial Council)

Rural Economic Advancement Project (ADB-REAP

(SP)) thro M/Regional Econ. Dev

220 220.0

Rural Economic Advancement Project (ADB-REAP

(Matale)) thro M/Regional Econ. Dev

10 10.0

Sub Total 230.0

Foreign Funded Projects (projects identified as ‘Road

Projects’ where funds are voted to a ministry other than the

Ministry of Local Government & Provincial Councils and

Maganeguma Program for rural and estate roads,

where funds are voted to M/Road Development and

spent on projects recommended by the Members of

575.0 500.8 1800 1800.0

18

Source: University of Moratuwa, computations based on Budget estimates and surveys made at rural local authorities in Southern and Uva provinces.

Page 24: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

21

Source of Funding

Nature of Expenditure Total

Allocation

of Vote

2005

Actual

Expenditu

re on

Roads

2005

% Spent

on Roads

Total

Allocation

of Vote

2006

Estimated

Allocation

for Roads

2006

disbursed directly to the Pradeshiya Sabha for rural roads) Parliament. (This was implemented thro M/Highways

up to Nov 2005)

Sub Total 1800.0

Local Funded Projects (projects identified as ‘Road

Projects’ where funds are voted to a ministry other than the

Ministry of Local Government & Provincial Councils and

disbursed directly to the Pradeshiya Sabha for rural roads)

Budget Proposal 10 ‘Estate Infrastructure

Development in Estate Sector administered by

M/Estate Infrastructure & Livestock Dev.

100 103 100% 750 750.0

Construction of Roads & Bridges administered by

M/Estate Infrastructure & Livestock Dev.

100% 150 150.0

Uva Wellassa Development (Rehabilitation of Rural

Roads) administered by the M/Regional Econ Dev.

100% 196.5 196.5

Integrated Rural Development Project for NW

Province administered by M/Regional Econ. Dev. In

2005 this was under M/Irrigation & Mahaweli Dev.

300 11 10 10.0

Infrastructure Development Galle District/Township

Development & Rural Roads administered by

M/Regional Econ. Dev.

14.2 14.2

Sub Total 1,120.7

Local Funded Projects (projects not identified hitherto as

‘Road Projects’ but where funds voted to a ministry other

than the Ministry of Local Government & Provincial

Councils and spent directly on rural roads)

Road Projects under Samurdhi Program (6114 in

2005) and around 6,500 in 2006) where each project

is provided with Rs 30,000 plus labour. Administered

through M/Samurdhi and Poverty Alleviation (only

voted funds considered here)

183.4 195

Under Head 310 04 04 Donor Assisted Projects of the

Mahaweli Authority implemented under the

M/Agriculture, Irrigation & Mahaweli Dev. In 2006

roads totaling 30 kms is being built in Udawalawe

Left Bank project estimated cost Rs 150 mn.

2,638 10 160

Rehabilitation of Road Network under Department of

Wild Life Conservation Head 863 58 01 Rs 7.5 mn in

2005 and allocated Rs 6 mn plus Rs 4.5 mn in 2006

7.5 6.7 11.5

Access roads to fisheries communities under Projects

of the M/Fisheries and Aquatic Resources Head 520

41 03 under Dheewara Gammana Program and

Project for Completion of Infrastructure Facilities for

265.9 25% 50 12

Page 25: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

22

Source of Funding

Nature of Expenditure Total

Allocation

of Vote

2005

Actual

Expenditu

re on

Roads

2005

% Spent

on Roads

Total

Allocation

of Vote

2006

Estimated

Allocation

for Roads

2006

Fishing Villages

Head 720 52 01 Decentralized budget for all MPs at

Rs 5 mn per year for 225 MPs.

1,125.0 25% 281.2 281.2

Batticaloa Development & Rehabilitation Project

administered by the M/Infrastructure Development &

Fisheries Housing

145.6 50% 118.9 55

Estimate of road expenditure under ‘Rehabilitation

and Improvement of Capital Assets’ of other relevant

ministries such as

• M/Urban Development & Water Supply

• M/Housing & Construction

• M/Enterprise Dev. & Investment Promotion

• M/Plantation Industries

• M/Agricultural Development

• M/Industrial Development

• M/Irrigation

• M/Agrarian Services & Farm Communities

• M/Environment

100

Sub Total 814.7

Funds Allocated to RDA, spent on maintenance and

reconstruction of rural roads under vote heading such as

‘Emergency Road repairs’ etc19

Maintenance20

(Head 300 50 02) 130.0 300.0

Rehabilitation and improvements of existing assets

(rural roads) 21

500.0 1000.0

Sub Total 1300.0

Provincial Revenue allocated to Roads (channeled through

the Provincial Budget)

Provincial Council Members Decentralized Budget

Allocations approx 488 M/PCs at average of Rs 1.5

mn each

488 25% 183.0

19Refer Table 4: Spending on National Roads 20

An estimated Rs 150 mn has been spent by the RDA for maintenance spending on rural roads in 2005, with Rs 300 mn allocated from the Road Fund for 2006. 21

An estimated Rs 500 mn assumed to be spent for construction work carried out on rural roads by the RDA in 2005, with an estimate of Rs 1,000 mn for 2006.

Page 26: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

23

Source of Funding

Nature of Expenditure Total

Allocation

of Vote

2005

Actual

Expenditu

re on

Roads

2005

% Spent

on Roads

Total

Allocation

of Vote

2006

Estimated

Allocation

for Roads

2006

Other allocations (e.g. Chief Minister’s Fund) 100.0

Sub Total 283.0

Pradeshiya Sabha funds allocated for roads (channeled

through the PS Budget)

Balance 20% of salaries 14.9

Contract staff, other recurrent expenditure and

maintenance costs average of Rs 8,000/- per km for

77,800 kms in the 270 Pradeshiya Sabhas.

622.4

Sub Total 637.3

TOTAL 7,907.6

Page 27: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

24

This includes, Rs 281.3 million estimated to be spent on roads by representatives at both the

national and provincial levels of government through the decentralized budgets to be spent in

their constituencies. A significant share (estimated at 25%) of the Rs 5 million given to each

MP and less amounts (varying by province) given to each MPC, is also known to be spent on

rural roads, bridges and road drainage. However, this situation prevails almost exclusively

only in rural areas. In contrast, urban areas do not receive such funds, other than what is

allocated through the respective council budgets.

While Provincial Councils and Pradeshiya Sabhas are aware of such spending, the degree of

involvement in such work or even agreement varies from place to place. In some cases, such

spending is on the invitation of the relevant Pradeshiya Sabha. On the other hand, those

having the discretionary power over the use of such funds appear to decide and some times

even complete the work without any concurrence of the legal owner/manager of the road

which is the Pradeshiya Sabha. As a consequence different roads are repaired to different

standards. Moreover, after repair the Pradeshiya Sabhas are expected to maintain them, even

though no specific allocations are provided for this purpose. Over riding the legal powers of

local authorities is rarely questioned as the funds are considered to be used for a public project

and it is perceived that questioning such an intervention would be unpopular and a potential

political risk.

Total Public Expenditure on all Roads

The total budgetary allocations made for roads for the year 2006 classified by the types of

roads, is given in Table 10. This shows that all public sources which includes both capital and

recurrent expenditure allocations for the year 2006 are Rs 59,484 million about 13.5% higher

than the amount reported by the NBD. As can be seen the largest degree of under-reporting is

from the urban sector, where only around 1/5th of the total public expenditure is recorded by

the Treasury as much of it goes directly from Municipal and Urban Council sources.

Similarly, rural roads are under reported by 2/3rd and provincial roads by 22.9%.

Table 10: Total Public Expenditure on Roads and its Analysis (2006 Allocations)- Rs

billion22

Total

Allocation as

per NBD

records

(1)

Percentage

of Allocation

as per NBD

records

(2)

Total

estimated

allocation

(all sources)

(3)

Percentage of

estimated

allocation

(all sources)

(4)

% of Under

reporting

{(3)- (1)}/(1)

National 39,660.3 75.9% 39,660.3 66.7% 0%

Provincial 7,436.8 14.2% 9,140.2 15.4% 22.9%

Urban 430 0.8% 2,776.2 4.6% 545.0%

Rural 4,750 9.1 7,907.6 13.3% 66.5%

TOTAL 52,278 100% 59,484 100% 13.7%

22 Source: Computed from Tables 5 to 9.

Page 28: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

25

Trends in Public Expenditure on Roads

The trend in expenditure (2003-5), allocations for 2006 and projections (2007-8) tabulated

from computations by NBD and adjusted for estimates given in Table 10 for expenditure not

accounted for by NBD (Appendix II) is given in Table 11. The table shows the rapid increase

in investment in the road sector where the investment ratio has doubled within 2 years, from

0.7 % of GDP in year 2003 to 1.4% by 2005, with further increases of up to 2.47 %

anticipated by 2007. However, the expenditures are projected to fall after this due to

completion of funding for tsunami projects. This is also illustrated by Figure 1.

Figure 1: Trends in Public Expenditure on Roads (2003-2008)

This clearly reveals the governments’ pursuit of the objective of making investing in roads a

high priority. It also underlines the need to increase the capacity in the road sector to handle

the increase work loads that will be forth coming and to improve the benefits from such

investments which are intended to bring about the desired economic, regional and social

benefits.

However, such intentions can only bear fruit if the sector can utilize the allocated funds

efficiently and effectively. Therefore these are two issues which will be examined in Sections

3.3 and 3.4. Statistically, Table 11 indicates a growth in expenditure of 65% from 2003 to

2004, which translates to an average annual growth of 30%. As such the potential for growth

from 2005 expenditure levels should be at least this range. This means that actual expenditure

in 2006 is likely to be around Rs 45 billion at a utilization rate of 75%, (consistent with past

performance). It will therefore be only in 2008 that spending could actually reach the desired

level of spending of around Rs 60 billion in 2006 prices. It is therefore necessary to have

capacity enhancement programs in place as quickly as possible.

-

5,000

10,000

15,000

20,000

25,000

30,000

35,000

40,000

45,000

2003 2004 2005 2006 2007 2008

Ru

pe

es.

(Mn

)

M/Highways Provincial Roads (PSDG & Foreign funded projects)

Urban & Rural Roads (under all heads in PSDG) Tsunami & Conflict Area (projects under different ministries)

Expenditure Allocation Projections

Page 29: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

26

Table 11: Trends in Public Expenditure on Roads (2003-2008)- Rs million23

3.2 Sources of Funding for Roads and Budgetary Processes

Road User Charges

It is of direct interest in budgetary preparation to determine the issue of road user charges or

the revenue that is collected from the road users. The collections for 2003 have been tabulated

in Table 12 taken from the Road Sector Master Plan.

Table 12: Road User Charges: 2003 (Million Rupees25

)

Central

Government

Provincial

Government

Local

Government

Total

Registration & Transfer of Vehicles 620 620

Annual Licensing of Vehicles 905 905

Duty & VAT on Petroleum Products 22,989 22,989

Vehicle Import Taxes 24,331 24,331

Duty & Taxes on Spare part imports 2,555 2,555

Provincial Tax on Petroleum

Products

778 778

TOTAL 50,495 1,683 Nil 52,178

Some of these revenues are used for the running of services such as the Department of Motor

Vehicles, Traffic Police, Traffic Courts, health care for accident victims etc. These costs have

not been computed accurately in recent years. Based on estimates made in 199926, this cost

would be around Rs 12 billion for the 2003. Moreover, the actual spending on road sector by

23

Source: Budget estimates and summary prepared by National Budget Department 24

Other sources refer to all other expenditures over and above what is recorded by the NBD as spent on

roads and given in Table 4 as well as Appendix II. Details of these sources can be obtained from Tables

5 to 9. 25

Source: Computed from Road Sector Master Plan, Final Report, December 2005 26 Assessment of Investment in Transport Sector Projects, 1999, Kumarage A.S. Ed Storm, et al.

Expenditure Allocation Projections

2001 2002 2003 2004 2005 2006 2007 2008

M/Highways 10,442.0 8,066.0 9,296.0 12,255.0 19,206.7 28,184.0 35,945.9 39,909.5

Provincial Roads (PSDG & Foreign

funded projects)

749.5 494.1 1,021.0 1,968.0 4,702.0 6,329.0 6,385.0 5,807.0

Urban & Rural Roads (under all

heads in PSDG)

80.2 59.9 285.0 503.0 1,180.0 4,207.0 4,834.0 4,854.0

Tsunami & Conflict Area (projects

under different ministries)

Nil Nil 102.0 2,204.0 3,662.0 13,704.0 17,644.0 8,853.0

Sub Total 11,271.7 8,619.6 10,704.0 16,930.0 28,750.7 52,424.0 64,808.9 59,423.5

% of GDP 1.33 0.98 0.60 0.81 1.19 1.92 2.10 1.72

Spending from other sources (add

approx 13.5%)24

1,521.6 1,163.6 1,445.0 2,285.6 3,881.3 7,077.2 8,749.2 8,022.2

TOTAL ESTIMATED 12,793.4 9,783.2 12,141.0 19,215.6 32,632.0 59,501.2 73,558.1 67,445.7

% of GDP 1.51 1.11 0.70 0.96 1.40 2.26 2.47 2.02

Page 30: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

27

the Treasury in 2003 was given as Rs 12,318 million in Table 8. Thus it appears from

estimates in the Road Sector Master Plan, that the Treasury made a net surplus on Road User

Charges of approximately Rs 26 billion in 2003. The Road Sector Master Plan does not

provide details computations of the manner in which these figures were arrived at. Hence, this

estimate may not be entirely reliable. However, it seems apparent that there was as substantial

surplus in previous years.

In the present context of higher fuel prices and governments having to subsidize some portion

of the fuel imports, it is possible that the Road User Charges have reduced. However on the

other hand, vehicle import duties increased in 2005 and the vehicle fleet and the registration

of new vehicles have also increased compared to 2003. Hence, this is possibly an urgent area

for a detailed study to determine if indeed the Road User Charges are been utilized for

improved road services.

Foreign Funding

The foreign funding for road projects varies between the different tiers. Prior to 2003, only

the national level roads and some urban roads received foreign funding. As shown in Table

13, it is clear that at present, both the provincial roads and rural roads receive 38.9% and

25.3% percent of their respective total funding in terms of foreign funds. However, it should

be noted that there is presently no aid/loan pipeline for urban roads, which have at present, the

lowest level of foreign fund allocations.

Table 13: Total Public Expenditure on Roads and its Analysis (2006 Allocations)- Rs

million27

Type of Road

Total

Allocation

Amount of

Foreign

Funding

Foreign

Funding as

% of Total

National Roads 39,660.0 25,669.5 62.2%

Provincial Roads 9,140.2 3,475.0 38.9%

Urban Roads 2,776.2 Nil Nil

Rural Roads 7.097.6 2,000.0* 25.3%

TOTAL 59,484.0 31,144.5 52.4%

Treasury Funding

The Treasury funding in terms of central government budgetary allocations for each level of

road agency is shown in Table 14. This shows that the Treasury provides 92.8% of the overall

allocations for all roads. At the level of the national roads, this is 100%. The lowest level of

Treasury funding is for urban roads at 31.6%. On the other hand, only 81.2% of these

allocations are made direct to the agency managing the roads. Even though urban roads get

the lowest percentage of their requirements from the Treasury, all of Treasury funds are

received directly to the particular council. On the other hand even though rural roads get

27 Source: Tables 5 to 9 and Appendix II

Page 31: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

28

nearly 82.5% of their requirements from the Treasury, the agencies managing the rural roads

get only 21.5% of this. This shows that both urban roads as well as rural roads have problems

albeit different to each other.

Table 14: Treasury Allocations on Roads by Agency Level (2006 Allocations)- Rs

million28

Type of Road

Total

Allocation

from all

sources

Treasury

Allocation

made to road

network

% of Total

Treasury

allocations to

agency managing

road network

% of

Treasury

allocation

to agency

National Roads 39,660.0 39,660.0 100.0% 34,831.0 87.8%

Provincial Roads 9,140.2 8,926.0 97.7% 8,031.8 90.0%

Urban Roads 2,776.2 876.2 31.6% 876.2 100.0%

Rural Roads 7,907.6 6,531.4 82.5% 1,722.2 21.8%

TOTAL 59,484.0 55,993.6 94.1% 45,461.2 76.4%

Provincial Council Funding

Provincial Councils are entitled to receive motor vehicle revenue license fees and a Provincial

petroleum taxes (termed Traffic Fees in the Budget estimates). The estimated allocations for

07 provinces, excluding the North East, amounts to Rs 2,130 million for the year 2006.

However as shown in Tables 6 and 9, the estimated allocations using Provincial Council

Revenues, is Rs 211.6 for provincial roads and Rs 283.0 million for rural roads, making up Rs

494.6 million which is only around 23% of the estimated ‘Traffic fees’ estimated for 2006.

Hence, it can be held that provincial councils are presently not investing an adequate share of

their own revenues on roads from the use of which they derive this revenue.

But in reality, these revenues are deducted by the Treasury from the block grant when it is

given to each provincial council Therefore in effect; this is added revenue to the central

government, even though it is collected for the province.

Local Authority Funding

Unlike Central Government or Provincial Government, local authorities are not entitled to

collect any revenue for the use of their roads. Therefore they are entirely dependent on either

general taxes or allocations from both central and provincial governments. Most local

authorities both rural and urban were found to be spending around 20% of their revenues on

roads. The total estimated expenditure on road by urban local authorities was found to be Rs

1,900 million, while the rural local authorities were spending Rs.637.3 million.

In summary it seems that the central government and provincial governments which is

entitled to collect road user charges (but the proceeds of which are deducted from the block

28

Source: Tables 5 to 9 and Appendix II

Page 32: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

29

grant) invest only part of such collections on the road network, whereas local authorities who

do not collect any funds are investing on roads.

3.3 Efficiency of Utilizing Funds Allocated

One of the measures of ascertaining the capacity of the road sector to utilize such a rapid

increase in funding levels is the historical utilization of such funds at the different levels of

the road network. The allocations and spending patterns of the two key funding sources for

the period 2001 to 2005 have been analyzed to determine the utilization of funding provided.

Funds Spent on National Roads

According to the NBD analysis, the RDAs overall utilization of funds is much higher at

83.1% of recurrent allocations and 69.8% for capital allocations provided for the year 2005.

The period between 2001 and 2005 saw this utilization range between a minimum of 76% and

a maximum of 92% for recurrent expenditure and a five year average of 82%. In the case of

capital expenditure has ranging between 70% and 91% during this same period, with a five

year average of 75%.

This analysis is presented in summary form in Table 15. The analysis by funding source

shows that foreign funded projects under loan or aid for the year 2005 have the lowest

utilization at 61.2%. However, the domestically funded components of the same projects have

a higher utilization at 84.2%. This is reasoned out as the costs for the physical operation of

Project Management Units (PMUs) in terms of staffing continuing even when other spending

has stopped due to problems of acquisition or mobilization delays. Since the required land

acquisitions for these projects are also included under this category, under assessment of

acquisition costs is also stated as a possible reason.

Table 15: Utilization of RDA Funds for 200529

Final Revised

Allocation

(Rs mn)

Actual

Expenditure

(Rs mn)

Utilization

%

By Expenditure Category Recurrent 708 588.1 83.1%

Capital 19,936.8 `13,912.0 69.8%

By Funding Source Domestic Funds 4,753.0 3,581.2 75.3%

Foreign Aid Loans & Grants 10,719.0 6,561.4 61.2%

Foreign Loan related Domestic

component

5,172.8 4,357.5 84.2%

TOTAL 20,644.8 14,500.1 70.2%

The RDA has computed the funds accounted by them and the Ministry of Highway for the

years 2001-2005 for the National Roads for some of the basic expenditure categories viz; (a)

maintenance, (b) improvements & rehabilitations (c) acquisition of new assets, (d) land and

29 Source: National Budget Department

Page 33: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

30

land improvements and (e) miscellaneous. . This excludes projects expenses incurred by the

office of the Ministry of Highways which is the reasons for the slight variance between the

total values reported between Table 15 which of excluding the ministry office and Table 16

which includes it.

Table 16: Allocations & Utilization of Funds for National Roads (Ministry of

Highways)30

2001 2002 2003 2004 2005

Maintenance Allocated (Rs mn) 337 908 1,625 1,212 1,900

Expenditure(Rs mn) 1,530 967 1,700 1,211 1,799

% Utilized 454 106 105 100 95

Improvements &

Rehabilitation

Allocated(Rs mn) 6,422 4,482 2,874 6,440 7,489

Expenditure (Rs mn) 8,445 5,095 4,867 4,942 6,606

% Utilized 132 114 169 77 88

New

Constructions

Allocated (Rs mn) 7,051 3,031 4,179 3,023 5,569

Expenditure (Rs mn) 119 2,018 3,092 1,833 2,048

% Utilized 2 67 74 61 37

Land &Land

Improvement

Allocated (Rs mn) 0 1,000 200 2,951 3,445

Expenditure (Rs mn)

% Utilized

Miscellaneous Allocated (Rs mn) 555 252 1,199 3,667 2,742

Expenditure (Rs mn)

% Utilized

Total Allocated (Rs mn) 14,365 9,613 10,077 17,293 21,145

Expenditure (Rs mn) 10,442 8,066 9,139 12,279 14,390

% Utilized 73 84 91 71 68

.This is also illustrated in Figure 2, where the following observations can be made:

• The maintenance funds have the highest utilization exceeding by far the allocations

provided. This indicates the back log rehabilitation and need for correspondingly

higher levels of maintenance funding.

• The utilization has been lowest for new constructions ranging from a low of 2% in

2001 (mostly due to the non mobilization of the Katunayake Expressway and the

Southern Expressway) up to a maximum of 74% in 2003.

• It is also noted that for the national network, the funds spent for new construction

since 2002 have exceeded those spent for maintenance by an average of

approximately 70%.

It must however be noted that the definition of maintenance and rehabilitations have not been

consistently followed in fund allocations. Thus a problem of project labeling and investment

identification exists particularly at the national level.

30 Source: Planning Division, RDA

Page 34: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

31

Figure 2: Utilization of Funds for National Roads (2001-2005)

Provincial Roads

20012002

20032004

20052006

Expendiure

Allocation-

2,000

4,000

6,000

8,000

10,000

12,000

14,000

16,000

Ru

pe

es M

illio

n

Amount Allocated & Spent for Rehabilitation of National Roads in Sri

Lanka (2001-2006)

Source : RDA

20012002

20032004

20052006

Expendiure

Allocation-

500

1,000

1,500

2,000

2,500

3,000

3,500

Ru

pee

s M

illio

n

Amount Allocated & Spent for Maintenance of National Roads in Sri Lanka

(2001-2006)

Source : RDA

20012002

20032004

20052006

Expendiure

Allocation-

1,000

2,000

3,000

4,000

5,000

6,000

7,000

8,000

Ru

pe

es M

illio

n

Amount Allocated & Spent on new constructions of National Roads in Sri

Lanka (2001-2006)

Source : RDA

Page 35: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

32

As discussed earlier, there are many sources of spending on provincial roads. Utilization rates

for all of these are difficult to obtain and even when available not entirely reliable. Table 17

gives the utilization of the Province Specific Development Grant (PSDG) for provincial

roads. This shows that utilization is around 78% in recent years.

Table 17: Utilization Rates for funds made available for Provincial Roads31

2000 2001 2002 2003 2004 2005

Allocations

under

PSDG

Allocated

(Rs mn) 1485 1405 1865 690 905 1650

Expenditure

(Rs mn) 768 749.5 494.1 539.3 N/A 1286.3

%

Utilized 51.7 53.3 26.5 78.2 78.0

Local Authority Roads

Both Provincial Councils that were studied have experienced that of the numerous sources of

funding made available at the local authority level, funding that is direct and personally

supervised such as the Decentralized Budgets have the highest utilization rates. However,

they may lack in effectiveness or perhaps even in transparency. The utilization of funds

allocated to local authorities through the PSDG is tabulated in Table 18. This clearly shows

that such funds are poorly utilized.

Table 18: Utilization Rates for funds made available for Local Authority Roads32

2002 2003 2004 2005 2006

Allocations

under PSDG

Allocated (Rs mn) 470 207 245 355 1430

Expenditure (Rs mn) 59.9 15.1 N/A 193.5

%

Utilized 12.7 7.3 54.5

3.4 Sustainability of Road Expenditure

Given that adequate funds are available and that projects are properly planned to achieve

optimum returns where projects are well implemented and funds fully utilized, there would

still be a question of sustainability of these infrastructure in the future. In other words, can

adequate funds be provided to ensure that these roads remain at an acceptable quality and able

to provide the outcomes that were intended of them? This is particularly pertinent in Sri

Lanka where the bulk of the road work is still awaiting rehabilitation and as such, increasing

level of maintenance funds will need to be provided in parallel with investments to bring the

road network to maintainable standard. Therefore, any rehabilitation has to be supported by a

source of sustained funding to keep it in optimum condition.

31

Source: Finance Commission 32 ibid

Page 36: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

33

Experience has shown that when the urgency for rehabilitation becomes apparent it is the

maintenance funds that are often reduced to accommodate such spending. Thus maintenance

has always been under provided. This of course leads to shorter life spans of even the new

roads as well as the rehabilitated roads and in most cases, the desired socioeconomic benefits

never fully materialize in the long-term. As such factories open and close, employment

increases and then falls away, even social services are abandoned due to deteriorating access.

However with the proliferation of the number of ministries and votes available for spending

on roads, most of this spending appears to be poorly planned, ad hoc and with little or no

targeted benefits. It is most likely that lead projects under the ‘Mahinda Chinthanaya’ would

also suffer a similar fate unless the question of continuity and sustainability can be addressed

satisfactorily. There are a number of issues that need to be highlighted under this aspect:

a) According to the present development strategy, road development occurs under

several ministries handling community development projects. These ministries

usually have no technical capacity to oversee such work. Moreover, once the project

is completed there are no funds made available to the local authority to maintain them

in that condition. Hence roads in the long-term will not be able to sustain the returns.

Therefore, it would be necessary to have an arrangement where the local authorities

are involved in every such project from the beginning. As such a condition may be

imposed that the local authority should be asked to design, construct and maintain

such roads. It may be better for such work to be awarded on contract basis, where the

contractor also maintains the roads for five years. This period should be adequate for

the local authority to obtain increased funding for maintenance under the road fund.

b) Foreign funded road projects carried out at the provincial and local authority level are

also presently suffering from this same problem. For example, the urban road &

bridge development projects implemented under the UDLIHP program are also not

been maintained as adequate resources are not available with the urban and municipal

councils. A similar situation exists on provincial roads where maintenance contracts

which were signed at time of contract have been terminated due to various problems,

especially after the intense flood damages that many of the rehabilitated roads

suffered in 2003.

c) GoSL has made progress recently by implementing an interim road maintenance trust

fund (known as the RMTF) so that continuous and adequate flow of funds is available

and to avoid funds required for maintenance competing with the more popular

spending on new roads. The Road Maintenance Trust Fund is now operative, but

presently is confined only for national roads. This year Rs 3,010 million has been

allocated. The Trust Fund intends to set up a process of disbursement and monitoring

of outcomes for disbursement made from the Fund. The efficiency of labour inputs

may also need to be studied with excess labor either offered a VRS or found alternate

work on projects rather than in maintenance work alone. This may need to be

extended to cover all roads. Provincial and local authority road could be drawn in on

the basis of setting up a fund for all future road rehabilitation and improvements.

Page 37: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

34

3.5 Institutional Arrangements in Road Sector

As discussed in Chapter 2, roads services across the country are delivered by all three tiers of

government. However the spending for roads is made through a number of different sources.

These were identified in Section 3.1.

National Roads

The RDA is the agency charged with managing the 11,760 kms of national highways. The

RDA which comes under the Ministry of Highways. The funds for the RDA are allocated

through the Treasury. The recurrent funds are based on staffing levels and other operational

costs, while the capital allocations are based on project proposals that are submitted to the

Treasury and included in the budget. These include projects that are funded entirely through

domestic funds as well as projects which are funded by foreign donors with counter part

funding. Most projects are identified by consultants provide by the donor agencies. In the case

of domestically funded projects there is no particular pipeline for projects. Projects are chosen

based on prevailing political expediencies. Large scale domestically funded projects however

are usually mentioned in the budget speech thus officially declaring such projects as policy

decisions.

Recent practice in the RDA has been to create a Project Monitoring Unit (PMU) for all

foreign funded projects. Such projects are usually staffed by RDA officers who are seconded

to such projects at a higher salary. There are presently no incentive schemes offered for

project completion. There is monitoring of the utilization of funds by the Ministry of Project

Implementation and the Ministry of Transport through quarterly reviews. However this

process only investigates bottlenecks in key projects and does not usually serve as a process

for monitoring all projects and their processes.

The RDA has in recent years obtained foreign assistance in strengthening its planning

functions. As such some software for Road Maintenance Expenditure Control (RMEC) and

HDM IV are now available for costing and prioritization of maintenance work. It is also

acquiring detailed road inventory and road condition data. The RDA has the technical

manpower to carry out the road works, but would need capacity enhancement in several key

areas including new techniques, project management, planning, road safety, traffic

management etc. Another short coming is that presently a significant portion of its manpower

is utilized in attending to emergency work on non-RDA roads. Other than for maintenance, all

project work is carried out through contractors and their labour.

From 2006, the maintenance funding has been channeled through a Road Maintenance Trust

Fund. This fund is considered an interim arrangement till a fully fledged fund is set up after

observing the effectiveness of having a trust fund. One of the issues facing the fund is the

high component of wages for maintenance. Unless more funds are made available it is

unlikely that there would be adequate funds to purchase material once wages are paid. Such a

fund therefore also runs the risk of becoming an employment generator. However, the

Page 38: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

35

Technical Advisory Committee is charged with setting up checks and balances for the funds

issued to the RDA. Moreover, it has been decided to set up a secretariat with technical and

financial assistance to facilitate this work under World Bank funding.

Provincial Roads

The primary source of funding for provincial roads is through allocations made to the

Ministry of Local Government & Provincial Councils and distributed to the provinces through

the Finance Commission. This is in the form of block grants for recurrent expenditure, part of

which is used for the payment of 80% percentage of salaries of all staff at provincial roads

agencies. The balance is usually funded through an administrative levy of between 3 to 6

percent made on all capital projects.

The provincial roads are owned and maintained by the relevant Road Development Authority

of Roads Department of the Provincial Council. Provincial Councils do not have any

Investment Plans. They rely on projects proposals which are usually a list of names with the

length and the total estimated cost as a means of getting funds through the Provincial Budget.

Projects are added on request made by elected representatives. The PCs do not use proper

road inventories or software for prioritization of rehabilitation or costing of road maintenance.

However, at present the larger share of funds for provincial roads are channeled through

several regional and subject specific ministries of the Central Government. These projects

have PMUs, similar to at the RDA. However unlike at the RDA, there is a severe dearth of

technical staff at the provincial councils. Hence, capacity is limited. Moreover even those

available are not adequately trained for functions such as design, planning, etc. The Provincial

Councils have deferred joining the Road Maintenance Trust Fund on the premises that the

present allocation for maintenance is in adequate and if the same quantum of funds were to be

given with more conditions, then joining such would not be advantageous. The provincial

councils do not have large labour forces and carry out most of their work through contractors.

Urban & Rural Roads

At the lowest level of rural local authority roads (i.e: Pradeshiya Sabhas), there are several

sources of funding for roads. The primary source once again is the allocations made to the

Ministry of Local Government & Provincial Councils and distributed to the Provinces, which

are required to pass these on to the Pradeshiya Sabhas through the Provincial Commissioner

of Local Government.

In addition to these funds, the Urban, Municipal Councils and Pradeshiya Sabhas use parts of

their own revenues collected through taxes for road construction & maintenance. Only

allocations made to the Provincial Councils and revenue collected from the local authorities is

considered for the road sector budget. These works are implemented by the relevant authority.

In the case of Pradeshiya Sabhas they usually have a Technical Officer and a few labour for

maintenance works. Larger works are contracted out. They do not have any other plant or

machinery. In the case of urban councils, they have a Works Superintendent and couple of

Technical Officers as well as maintenance staff. They also have fewer equipment. Most

Municipal Councils have one or more engineers and a technical staff. However except for the

Page 39: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

36

Colombo Municipal Council, none of them have staff qualified in modern road construction

techniques or have a design office or use any computational aids.

However, these funds are only fraction when compared to numerous other sources of funding

which is channeled directly to rural roads from central government allocations made to other

development oriented ministries. In most of these cases, the implementation of the work is

carried out by external agencies, with the Divisional Secretariat and the District Secretariat

also getting involved to varying degrees of project supervision and implementation. At

present District Secretariats also have technical staff that assist in carrying out these tasks. As

such there are often duplication of work between the Pradeshiya Sabha staff and the

Secretariat staff. While most central government agencies prefer to use the Secretariat and its

staff, the fact remains that such roads belong to the Pradeshiya Sabha and the legal

arrangements are by-passed.

Page 40: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

37

4 INTERVENTIONS FOR IMPROVING OUTCOMES OF

SPENDING ON ROAD SECTOR

This chapter will elaborate the strategic intervention that is required to improve the outcomes

of the current level of spending on roads. These include

• Identifying the overall sector investment levels that need to be set for the next decade

or so

• Identifying the allocations to be made for different types of investments required

• Identifying a strategy for improving efficiency of utilization of funds

• Identifying a strategy for capacity enhancement of road sector institutions

4.1 Identify the overall sector Investment Level

The total public expenditure allocated for roads for the year 2006 is estimated at Rs 59.5

billion. This is 2.26 % of GDP. This amount has increased favorably since 2003, when it was

only 0.7%. This is an unprecedented level of funding which if maintained for a decade, would

enable the backlog of un-rehabilitated roads at all levels to be brought up to maintainable

standard.

This is clearly a paradigm shift from previous years, where funds available for hardly

sufficient of the routine and periodic maintenance, which resulted in neglect of maintenance

and rehabilitated resulting in an almost totally deteriorated road network of which less than

5,000 kms (or 5%) has been rehabilitated within the last 10 years.

The objective of maintaining the present level of funding may be interpreted as a commitment

to allocate between 2% to 2.5% of the GDP for road sector, which is the funding level in the

MTEF for 2006 to 2009. This translates to allocating between Rs 55 billion to Rs 65 billion

per year (at 2006 prices).

The development strategy will need an element of urgency so that the road network is

developed as quickly as possible, so that the accumulating rehabilitation and maintenance

back log could be cleared while at the same time ensuring the sustainability in the long-term.

However, the efficiency of utilizing these funds has much room for improvement. Hence, the

ten year period could target increasing this from the 70% at present to at least 90%. This

would also provide for a 20% increase in spending levels or a 20% reduction in allocations,

whatever seems appropriate at that point in time.

An Integrated Investment Plan

Page 41: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

38

This increased funding also opens up hitherto closed doors for an integrated approach towards

managing the road network. Up to now since the level of funding was grossly inadequate for

even basic maintenance, the Central Government had no leverage to initiate developmental

activities that could be based on integration of the road networks. The low level of funding

only resulted in crisis-management of the road network at all levels, as described in Section 3.

This was most evident at the rural level with so many agencies spending funds from time to

time desperately trying to keep the rural road network from falling apart. .

But with increased funding one of the strategies would be to provide for additional funding in

a manner that promotes holistic development. This could start with a sector wide allocation

cutting across all three layers of government. The allocations made could be tied in to

motivational programs such as criteria based or matching grants which are even at present

well understood at the provincial and local authority level. However, such programs have to

be well designed and performance indicators to monitor output and outcomes accordingly.

The next section will determine the amounts of funding that each level will require.

Distributional formula based on road length, lane length, traffic volumes, terrain, type of road

surface and for rural roads, the number of households and service establishments served may

be considered in distributing these across the different agencies. Design standards may also be

tied in with this to prevent over designs, the most common of which would be to provide

metalled roads where compacted earth roads or gravel roads are appropriate.

4.2 Identify Allocation Levels by Type of Investment

In order to estimate the overall investment in the road sector, this report identifies the need for

the following capital expenditures:

• Rehabilitation & Improvements to Capital Assets

• New Capital Assets

• Maintenance of Capital Assets

• Institutional Development

Many previous studies have identified expenditure requirements based on developing a

section of the road network identified on priority basis. However, the fact that the

Government has committed Rs 59.5 billion for the road sector has to be considered when

considering the extent of the development. As will be shown in the following sections, this

report will propose an approach of developing the entire road network as a strategic approach

so that the heavy periodic maintenance that is being incurred now due to long over due

rehabilitations can be speedily reduced and correspondingly made available for a systematic

maintenance program.

The total spending (inclusive of capital and recurrent, maintenance, rehabilitation, new roads

etc) at present is distributed across the different types of roads as shown in Table 19. At first

glance this shows an approximately equitable variation in overall funding per km of road at

each level of the road network. However more analysis will be necessary to compute the

Page 42: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

39

overall cost per km and compared with international norms. The macro picture if Sri Lanka is

spending too much or too little on roads needs some international comparisons, not only of

costs but also of outputs and the conditions under which spending is incurred. This will be

further examined in Chapter 5 under the formulation of performance indicators.

Table 19: Analysis of Public Expenditure on Roads by Sector (2006 Allocations)- Rs

million33

Type of Road Total

Allocation

Rs Mn

Kms of road Allocation per

km (Rs/km)

National Roads 39,660.0 11,760 kms 3,372,449/=

Provincial Roads 9,140.2 15,743 kms 580,588/=

Urban Roads 2,776.2 5,176 kms 536,360/=

Rural Roads 7,907.6 75,424 kms 104,842/=

TOTAL 59,484.0 108,103 kms

Provision for Rehabilitation: To bring Road Network to Maintainable Standard

One of the long term objectives for a high level of capital investment on a road network is to

rehabilitate the badly deteriorated road network at present to maintainable levels, so that the

present requirements of maintenance would reduce to regular and scheduled maintenance.

This requires the extent of the network to be calculated.

The RDA which has 11,760 kms of road reports the lane length as 18,405 kms as shown in

Table 20. This means an average road width of 1.56 lanes. Since, similar data from provinces

and local authorities are not available; this report assumes an average road width of 1.3 lanes

for provincial roads, with 200 kms of 2 lane urban roads and the balance urban roads and all

rural roads as single lane.

Table 20: Lane kms of National Road Network34

Road

Classification

Width

(range)

Road Length

kms

Lane kms

Single Lane Less than 4metres 2,970 2,970

Intermediate Lane 4 to 5 ½ metres 4,690 7,035

Double Lane 5 ½ 9 metres 3,800 7,600

Multiple Lane Over 9 metres 200 800

TOTAL 18,405

In order to assess the total cost of rehabilitation of the entire network over the next 10 to 15

years, including the roads that have been rehabilitated in the last few years, Table 21 has been

prepared with current rehabilitation costs ascertain from the road agencies. The RDA costs

have been taken from average cost per lane for contracts signed recently, with additions for

33

Source: Tables 1 and 10 34 Source: Planning Division, RDA

Page 43: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

40

bridges and other administrative costs. A lane km of national roads with Asphalt Surfacing or

DBST has been estimated at Rs 15 million. Similar computations have been made for the

provincial and urban roads to be finished with DBST or metal and tarring and rural roads a

mixture of metal and tarring, gravel with sections in concrete where slopes are steep or

passing through poor ground conditions.

As shown below, the total cost of this exercise is Rs 466.2 billion. It should however be noted

that these costs are approximate, and indicative only. Moreover, each type of road will have a

different life cycle and the impact of that variation on costs has been ignored in this

calculation.

The Road Sector Master Plan projections for the 10 years i.e. 2006 to 2015 has a higher level

investment of Rs 47 billion per year and a constrained investment plan of Rs 37 billion per

year, both of which have been exceed by the provisions made available in the year 2006 itself.

Moreover this is only to develop selected sections of the road network as opposed to the entire

network.

Table 21: Rehabilitation Costs for Road Network35

Provision for New Roads: To provide for increased growth in traffic

Increase in vehicle registrations following increasing personal incomes leads to higher vehicle

use. The TransPlan traffic forecasting model shows that traffic growth in Sri Lanka for a 5%

growth rate in GDP, would translate to traffic flow growths of around 6 to 7 percent per

annum, in a scenario when quality of public transport deteriorates. But the increase in road

capacity is only 3% p.a. since the growth is mostly in the fleet of smaller vehicles, which

means that the average vehicle size (PCU) reduces together with the average vehicle

utilization (AVU) in annual kms per vehicle. With vehicle ownership increasing at faster rates

in rural areas than in urban areas, this means that the entire road network at all levels would

be constrained every year. Otherwise, traffic congestion which is estimated at Rs 3236

billion

will increase further.

35

Source: Table 1; Planning Division RDA, Commissioner General of Local Government and cost

estimates from interviews conducted by University of Moratuwa and evaluation of recent projects. 36 Estimated by TransPlan, University of Moratuwa, 2005

Type of Road Road

Length

kms

Lane

Length

Lane kms

Cost of Reconstruction

Rs per km

Total Value

Rs bn

National Roads 11,760 18,405 Rs 15 mn per lane km (DBST or AC) Rs 276.1 bn

Provincial Roads 15,743 20,466 Rs 4 mn per lane km (DBST or metalling) Rs 81.9 bn

Urban Roads 200 400 Rs 20 mn per lane km (DBST or AC) Rs 8.0 bn

4,976 4,917 Rs 3 mn per km (metalling or DBST) Rs 14.8 bn

Rural Roads 20,000 20,000 Rs 1.5 mn per km (metalling and concrete

sections)

Rs 30.0 bn

55,424 55,424 Rs 1 mn per km (gravel with concrete

sections)

Rs 55.4 bn

TOTAL 108,103 108,103 Rs 466.2 bn

Page 44: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

41

Therefore if one assumes that half of this requirement can be achieved through increased

capacity coming from the rehabilitation of roads-due to better surfaces, then the other half has

to come from entirely new roads or widening (e.g. Baseline Road). This means we need to

provide for a minimum 1 ½ % growth in lane capacity of the road network per annum. This

is consistent with the growth in lane kms over the last two decades.

If the asset value of the road network can be estimated at Rs 466.2 billion, then a 1 ½ %

growth p.a., roughly translates to a requirement of around Rs 7 billion per year for new roads.

This when compared to the spending of approximately Rs 2 to 3 billion for new roads over

the last 4 years, is reasonable, given the fact that utilization of funds was very low, with

many new road programs been substantially delayed for different reasons.

Provision for Maintenance: To provide for sustainability of the road network

Presently, the road network is badly deteriorated due to delayed rehabilitation for many

decades. Some roads have not been improved since their original construction 50 years or

more. This means that the network presently requires high maintenance inputs. It is

commonly observed that the life cycle of an application of sand sealing or DBST or even an

asphalt surfacing lasts much less on such roads where the bases have not been properly

reconstructed. In an unpublished study of the cost between routinely maintained roads and

roads under ‘stop-gap’ maintenance strategy in Uva Province, the overall life cycle cost was

found to be 19 times higher when compared with the cost of maintaining under routine

schedules37

.

The objective of higher level of investment on roads is to reduce this spending so that roads

remain within their maintainable life span, and maintenance costs both routine and periodic

would be minimal. An estimate of the total annualized maintenance cost has been given in

Table 22. It is assumed that the annualized cost is taken as 2% p.a. of replacement value for

higher end roads such as DBST and Asphalt Surfacing and 5% p.a. for others. This follows

norms in asset management techniques38

. This means that the annual maintenance cost would

be around Rs 12.3 billion for a fully rehabilitated road network.

This amount also tallies with the estimates in the Road Sector Master Plan of Rs 11.1 billion

for maintenance, which is made up of Rs 4.5 billion for national roads, Rs 2.9 billion for

provincial roads and Rs 3.7 billion for local authority roads.

37

Amerasekera, RM, unpublished paper, 2002. 38

Planning Division of RDA and other Engineering units such as in SPRDA, Uva Roads Department,

CMC. More work in this regards is intended in Parts III and IV under performance indicators.

Page 45: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

42

Table 22: Maintenance Costs of Road Network after Rehabilitation

The RDA presently uses the Road Maintenance Expenditure Program (RMEC) which is an

Exel based program spreadsheet with varying traffic levels and terrain and estimates cost for

different maintenance activities such as pothole patching, edge metalling etc. It does not cover

costs of maintenance of bridges, culverts, lighting, intersection controls, traffic signs,

markings & signal etc- other than cleaning and repainting. This year the RMEC program was

used to allocate the Rs 3 billion for the maintenance of RDA roads. The RTF at its very first

meeting wanted the RDA to update this program as the allocations appeared to be

inconsistent. For example, the program only categorizes traffic levels below 5,000 vehicles

ADT.

According to the program, the maintenance requirement for 2006 is

- Extensive Patching Rs 3,336 million

- Edge Metalling Rs 320 million

- Surface Profile Correction Rs 1,603 million

- Sand sealing Rs 819 million

No assessments have been made for other costs referred to earlier. These items alone total up

to Rs 6.1 billion, whereas only Rs 3 billion has been provided through the RTF for 2006.

This means the RDA is allocating around Rs 163,000 per lane km for a sub standard level of

maintenance. As per Table 21, 2% cost of an asset value of Rs 15 million works out to Rs

300,000 per lane km year. Therefore given that the present level of maintenance does not

include a total maintenance package, but only selected items for different roads, the present

level of maintenance requirement may be considered even as high as Rs 7 or 8 billion, which

is around 1/3rd more than what is provided in Table 21.

For provincial roads, even at present the suggested amount of Rs 1.6 billion is exceeded, since

the expenditure apart from the foreign funded projects is around Rs 3.6 billion (Table 6)

39

A 2% annual discounted rate has been used following World Bank sponsored research and published

in Road Maintenance Management, Robinson, Martinson and Snaith, p9.

Type of Road Road Length

kms

Total Value

Rs bn

Rate for

Regular & Periodic

Maintenance

(for 10 to 12 year

reconstruction cycle)

Total Annual

Requirement

Rs Bn

National Roads 11,760 Rs 276.1 bn @ 2.0 % p.a39

Rs 5.5 bn

Provincial Roads 15,743 Rs 81.9 bn @ 2.0 % p.a Rs 1.6 bn

Urban Roads 200 Rs 8.0 bn @ 2.0% p.a. Rs 0.2 bn

4,976 Rs 14.8 bn @ 5.0 % p.a. Rs 0.7 bn

Rural Roads 20,000 Rs 30.0 bn @ 5.0% p.a. Rs 1.5 bn

55,424 Rs 55.4 bn @ 5.0% p.a. Rs 2.8 bn

TOTAL 108,103 Rs 466.2 bn Rs 12.3 bn

Page 46: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

43

almost all of which is being spent on maintenance and back log maintenance work. As for

urban roads, the Colombo Municipality alone is spending Rs 150 million per year on

maintenance and hence the current spending on maintenance of urban roads may be estimated

from Table 7 to be around Rs 2,000 million far in excess of .Rs 900 million provided in Table

21 for a maintainable network.

In the case of rural roads also, apart from the foreign funded rehabilitation projects amounting

to around Rs 2.1 billion (Table 8), the balance Rs 6 billion seem to be spent largely on

maintenance. This is almost twice as much as what is provided in Table 21.

Hence it is evident that Sri Lanka is currently spending only a fraction of the cost required for

maintenance of its road network in its present condition. The present level of maintenance

required at least for the national roads seems around 1/3rd higher than what has been

calculated in Table 21 which is the amounts needed to maintain the network once it is brought

to maintainable standard.

Overall, there seems to be expenditure around Rs 14 to 15 billion spent on all roads for the

present level of sub standard maintenance, which is higher than the prescribed level of total

maintenance spending once roads are in maintainable standard.

In keeping with the Governments’ policy to move towards a Road Fund, it is recommended to

expand the existing fund to cover all tiers of roads and to increase contributions to the fund

gradually to the required level by increasing around Rs 1 billion per year from the present 3

billion for the next 10 years.

The present maintenance allocation may be considered at around Rs 14 to 15 billion per

annum when considering spending on the entire network. However, presently in addition to

delayed maintenance even what is done is incomplete. For example, pedestrian facilities,

traffic signs and markings, street lighting are all maintenance expenditures that are not

incurred as much as they should be. As a result, congestion costs and accident cost increase.

As such, a doubling or trebling of this expenditure cannot be considered as being excessive.

However, this cannot be done when the road network is in poor condition. Therefore the

network should be rehabilitated urgently in order to reduce the huge burden on maintenance.

It is the only way in which we can prevent roads that are rehabilitated from deteriorating

quickly.

Another aspect is the performance of the road sector, in terms of speed of travel time and

safety. The TransPlan road database on the national road network shows that less than 2% of

the network has an IRI of less than 2 m/km. Over 50% of the network has an IRI of more than

5 m/km- which is considered most unsatisfactory. With the national network in such poor

standard the provincial and local authority roads are bound to have worse indicators. As such,

this case again points that the present level of maintenance effort falls far too short of the

desired outcomes from the road network.

Page 47: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

44

It is assumed that the Fund would formulate the maintenance norms and norms for

input/output ratios, man to material ratios and other indices to ensure optimum utilization of

the contributions to the Fund. The fund is also required to setup performance indicators of

outcomes of maintenance spending. Moreover the must be clearly set out definitions on what

exactly maintenance activities are. Or else projects for rehabilitation and improvement may

also be funded through the road fund.

Incorporating into the Medium Term Budget Framework

Given that the present level of funding (i.e. between 2% and 2.5%) of GDP can be

maintained, then the allocations could be provided as follows

Table 23: Sector Allocations at different Investment Levels

Investment Level

At 2% of GDP At 2.5% of GDP At 3% of GDP

Maintenance Rs 12.3 billion Rs 12.3 billion Rs 12.3 billion

New Roads Rs 7.0 billion Rs 7.0 billion Rs 7.0 billion

Administration & other

support costs

Rs 0.7 billion Rs 0.7 billion Rs 0.7 billion

Rehabilitation Cost

(years to complete

rehabilitation)

Rs 35.0 billion

(14 years)

Rs 40.0 billion

(12 years)

Rs 45.0 billion

(10 years)

Rs 55.0 billion Rs 60.0 billion Rs 65.0 billion

Table 23 clearly shows that a realistic opportunity exists to bring all roads up to a

maintainable level within a foreseeable period, given that the present level of spending can be

maintained. This is achievable between 10 to 14 years for a spending level varying from 2 %

of GDP to 3% of GDP for the road sector. This maybe achieved in four consecutive 3-year

budgetary periods. Such programs have been successful in countries such as India and Japan

which have practiced 5-Year Development Plans The first program can be from 2006 to end

2009 (to coincide with the current MTBF and on going work) where it might be targeted to

develop approximately 1/5th of the most important roads at each level of the road network and

within the respective authorities. This would mean a total extent of over 20,000 kms

rehabilitated over 3 years. It should be noted that during this period a higher level of routine

maintenance may have to be incurred in keeping the road system motorable. A detailed cash-

flow program will have to be worked out in order to give effect to this approach.

This type of staged approach for the rehabilitation of roads would have a number of other

advantages as well:

• Provide time for the gradual capacity building, technical up grade, especially

of the provincial and local authorities to plan, design, supervise and monitor

road works.

• To attract by providing greater confidence in the continuity of opportunities

for construction for the local construction companies in order to invest in

Page 48: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

45

quality personnel, plant and equipment to develop their own capacity to

execute an increase amount of road works.

4.3 Improving Effectiveness of Expenditure Allocations

Effectiveness of spending begins with selecting the most beneficial item for spending. Some

key options in this are;

- To spend on maintenance or on new constructions

- To spend on Project A or on Project B

- To spend on rehabilitation or on routine maintenance

At the moment there is no systematic planning in place to make such decisions. The primary

reasons why such decisions cannot be made are:

- Lack of information such as traffic levels, road condition, costs, standards etc.

- Lack of personally that are trained and experienced in planning work.

- Lack of institutional arrangements such as planning divisions, traffic surveys units etc

that are required

While the RDA is in the process of acquiring such, the information at provincial and local

levels is almost non existent. This was also evident in the report of the recently concluded

Road Master Plan study where the road based statistics had been prepared on samples, rather

than on an inventory. As a result no benefit cost analysis, feasibility or rational selection

procedure is applied for selecting projects or type of investment to make. Traditional

processes are followed often at the directions of the political leadership of a given agency.

The exceptions are only the foreign funded projects. Here too the situation is far from

desirable are as demonstrated in the manner in which some roads have been selected in some

of the recently concluded rehabilitation projects. In this case, low trafficked roads have been

chosen at the expense of higher trafficked and more deserving roads. As such even these

project-driven selection criterions has not been successful.

What is required is a permanent and dynamic planning arm in each agency. While the national

level would require persons with wider capacity, at the lowest level, it could be a technical

officer. The solutions for these problems are described below.

Selection of Projects

A policy decision is required to be taken at the highest level to provide funds only on the

basis of a Medium Term Investment Plan (MTIP) for the road network of that agency. If this

needs to be consistent with the 3 Year MTEF, then it could either be reduced to 3 years or

increased to 6 years. This means, each agency should have a portfolio of such projects picked

from this Medium Term Investment Plan (MTIP). The External Resources Department should

encourage donors to ‘pick’ projects from these portfolios rather than ‘propose’ or ‘select’

their own projects. Countries such as India practice this with much benefit to the country.

Guidelines when making Budgetary allocations for National Roads

Page 49: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

46

No other ministry other than the Ministry of Highways should be provided with funds to work

on the national roads. The RDA should be the custodian of the National Roads MTIP and its

project portfolio duly ranked by order of priority. If the separate Ministry of Road

Development is to continue, its terms of reference may have to be reconsidered. There may

be scope for such a ministry to source additional funds for the road network development

belonging to the provincial and local authorities. However, the execution of such work should

be left to the relevant agencies and ministries and such a ministry may only be a facilitator.

Guidelines when making budgetary allocations for Provincial Roads

Similar to the national network, the Provincial Council and the respective PRDA or

equivalent agencies should take ownership for the MTIP for its own road network. As such,

all funds for this purpose should be channeled through the Ministry of Local Government &

Provincial Councils and the Finance Commission. Foreign funded projects should be

designed and implemented in close collaboration with the respective provincial roads agency.

However, it was noted that sourcing funds through several organizations causes delays and

poor utilization of funds. This could also be overcome to an extent by having a medium term

budget frame work for road sector allocations, so that each agency knows what funds it can

expect and prepare for implementation accordingly.

Guidelines when making budgetary allocations for Rural Roads

The spending on the rural road network needs most careful planning. Presently there are

numerous sources of funding from both central and provincial government. The following

guidelines may be necessary to improve the effectiveness of utilizing these funds.

1. Funds will be provided only to agencies that actually own roads. Ownership should

be on the basis of having gazetted these roads to that agency.

2. The Ministry of Road Development can perform as an ‘internal donor’ for facilitating

additional funds from centre to rural areas. In this case, the respective Pradeshiya

Sabhas can make a proposal for specific development projects from the funds

allocated to this ministry. This will also enable the Ministry of Highways to

concentrate on its national roads and forward the multitude of requests it now

receives for work on rural roads to the Ministry of Road Development for

consideration for funding.

3. It is important that such funds enter the budgets of the local authorities and that the

work is executed through them.

4. It is better if the Pradeshiya Sabhas can actually implement these projects as build-

maintain projects and thereafter include the maintenance of such projects to the road

fund.

5. The implementation of road projects from the Decentralized Budget (DCB) should

also be transferred from the Divisional Secretariat to the relevant Pradeshiya Sabha.

Guidelines when making allocations for Spending on Urban Roads

For urban roads, a similar program and MTIP should be designed. These councils should be

given the same consideration as Pradeshiya Sabhas as their incomes are not always adequate

to maintain roads in a satisfactory condition. It should also be noted that rural areas will also

develop only if the connected urban centers develop. The rural traffic ends up in urban centers

Page 50: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

47

and unless the urban roads are in good condition, economic benefits will not flow to the rural

communities.

Moreover roads in almost all urban areas are deficient in terms of traffic management, street

lights, parking facilities, road signs and markings etc, which are all functional parts of

ensuring the economic efficiency of the road system. It is recommended that the budget line

has a separate component for these items.

As with other road agencies, the urban local government authorities should be asked to

develop their own 5-year development plan. This should be funded through the Ministry of

Local Government & Provincial Councils and the Finance Commission. They could also

submit proposals for funding from the central government from the Ministry of Road

Development. They should also be considered for foreign funding with donors picking up

prioritized projects through ERD.

As a general rule if any roads to be developed or rehabilitated the proposal

should be channeled trough the owner/custodian of the road; funds could then

be allocated to the respective agency. As a rule standard road cross sections,

maintenance standard could be standardized to select from those by agency

concerned hence uniform standard could prevail right trough out the country.

4.4 Improving Utilization of Allocations

Overall, the national roads appear to be utilizing around 75% of the capital allocations

provide. The RDA claims that this is mostly due to the inability of the Treasury to make

available the cash imprest when invoices are presented by the contractors for payment. As a

result, contractors delay in procuring material, thus delaying the scheduled completion of

projects.

The utilization rate for provincial rate for PSDG funds is similar at 78%. The reasons ascribed

for this variation are:

• Problems of cash flow.

• Inadequate capacity to formulate requests, prepare BOQ, tender documents etc. at

short notice.

• Inadequate capacity of contractors to complete projects on time.

The utilization rate of the PSDG funds was 54% in 2005, much improved from 7 to 12

percent in 2002 and 2003. In addition to the reasons given earlier for provincial roads, the

local authorities have the added problems of having to source such funding through the

Provincial Councils and the Commissioner of Local Government, which also causes delay.

This also demonstrates the problems associated with funds being channeled through a number

of agencies. In this case, the payments are released by Treasury only after quarterly progress

reports are submitted by the Provincial Councils and are approved for payment by the Finance

Commission.

Page 51: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

48

Another stated reason for low utilization was that local authorities were not fully aware of the

amount or the time when such funds would be made available. Some Pradeshiya Sabhas

spoke of receiving such information almost at the end of the year. Another reason given is

that the contractors who often do not have the capacity to undertake such works, are unable to

keep to schedule and drag projects until the end of the year when they realize they have to

complete in order to get paid. This often causes a rush on payments towards the months of

November and December, resulting in some cases of carrying on payments to the next year as

continuing works.

It summary it could be stated that at the national level making cash imprest available is cited

as the biggest constraint, while at the lower levels, when funds are provided direct to the

implementing agency, the utilization is high. That is to also say, that when funds are

channeled through a series of agencies, such as in the case of local authorities, the utilization

decreases sharply. Utilization is also low, when it comes to new constructions. This is caused

mostly by acquisition delays and in the process of selection and mobilization of contractors.

4.5 Enhancing Sector Capacity

The institutional capacity of the roads sector requires urgent attention in order to effectively

rise to the challenge of increased spending provided and an ambitious development plan

setout earlier in the report. This cannot be over emphasized given that there is presently low

utilization of funds ascribed mostly to capacity problems particularly at the provincial and

local government levels.

The present budget allocations do not show any significant contributions for planning, human

resource development or research and development requirements in the road sector. With

much higher levels of funding in highways, it would be necessary to build up on an urgent

basis, the required sector capacities to ensure that higher levels of funding are effectively

utilized and the level of technological competence, planning and management capacities are

in place to facilitate this.

Sector capacity improvements are required in the following areas:

Human Resources Development

Presently, road sector agencies have very little provisions for training of personnel. Even most

road engineers have never taken highway construction or traffic courses as some of the

universities teach these only as optional subjects. Moreover, a significant proportion of those

who become engineers through continuing professional development also may not have

followed such courses of study.

In addition, middle grades such as clerical, technical officers lack basic computer and

communication skills. It would be most useful for a sector that has to undergo rapid

development to invest in its personnel especially in the next few years. Thus it is

Page 52: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

49

recommended that each agency is provided an allocation for HRD equal to 0.5% (1/200th) of

the Treasury allocations for provincial and local government institutions and 0.1% (1/1000th)

for the RDA. The overall cost of this would be around Rs 50 million per annum.

Research & Development

It is noted that a Road Development Master Plan was prepared in December 2005. While it

gives important baseline information, the need for a dynamic planning system to be set up at

each level of road management cannot be over emphasized. This requires the compilation of

data bases, road inventories, traffic surveys and general capacity development in project

appraisal and assessment techniques which needs to be regularly a systematically updated on

an on-going basis. Availability of such critical resources will greatly facilitate the preparation

of the Medium Term Investment Plan (MTIP) suggested earlier and the selection of the most

important roads in a portfolio of road projects for funding. Such investment plans need to be

continuously updated with the changing investment priorities and other priorities of the

country. For this, the road agencies at all levels should have the required trained personnel.

Thus it is recommended that each agency is provided an allocation for Capacity Development

equal to 0.5% (1/200th) of the Treasury allocations for provincial and local government

institutions and 0.1% (1/1000th) for the RDA. A Further allocation of 0.1% (1/1000th) of the

funds allocated through the Ministry of Local Government & Provincial Councils for roads

may be provided to the research funding organizations such as the National Science

Foundation or National Research Council as grants for disbursement to reputed research

organizations for research and development programs on provincial, urban and rural roads.

The cost of this would be around Rs 60 million per annum.

SME Road Contractors Capacity

Most road construction work is carried out through contractors. In the provinces the

maintenance is also on contract, as was in the RDA up to a few years ago. The low capacity

of contractors working on local authority roads and even on provincial roads is a stated reason

for the low utilization for allocated funds. In this respect, it will be necessary to conduct

regular programs to develop the management and technical capacities of such contractors.

This may be a program that could be funded by a donor agency to begin with and made in to a

self financing program afterwards.

System for Road Investment Assessment & Selection Criteria

It is noted that a Road Development Master Plan has been prepared in December 2005. While

it gives important baseline information, the need for a dynamic planning system to be set up

at each level of road management cannot be over emphasized. This requires the compilation

of data bases, road inventories, traffic surveys and general capacity development in project

appraisal and assessment techniques which needs to be regularly a systematically updated on

an on-going basis. Availability of such critical resources will greatly facilitate the preparation

of the 5-year development plan and the selection of the most important roads in a portfolio of

road projects for funding. Such investment plans need to be continuously updated with

changing investment priorities and other priorities of the country. For this, the road agencies

at all levels should have the required trained personnel.

Page 53: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

50

A good example of the inadequacy of having consultants make one-off development plans for

the sector is in the recently concluded Road Sector Master Plan, which envisages an

‘unconstrained’ development strategy with an investment of Rs 47 billion per year from 2006

to 2015. However, the projects formulated under the new policies under the ‘Mahinda

Chinthanaya’ have already led to increased investments surpassing these levels by as much as

27%.

Page 54: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

51

5 PERFORMANCE INDICATORS

Performance Indicators are important measures of effectiveness and utilization of expenditure

in the road sector. In this section it is intended to define a set of primary indicators that could

be used for the current budget cycle.

Performance Measures are necessary for different stages of the spending on roads. These are

best studied under the following categories:

• Resource Allocation Indicators

• Resource Utilization & Efficiency Indicators

• Output Indicators

• Input- Output Effectiveness Indicators

• Outcome Indicators

5.1 Resource Allocation Indicators

These are indicators that measure the extent of the allocation of resources for the sector.

These do not measure if such resources are fully utilized or the efficiency of such usage in

terms of achieving the intended outputs and outcomes. These may be considered as guiding

indicators on the equitable and efficient allocations for preparation of budgets.

These indicators are

• Rs allocated per lane km per year for maintenance

• Rs allocated for maintenance as % of asset replacement value

• Rs allocated per lane km per year for rehabilitation

• Rs allocated for rehabilitation as % of asset replacement value

• Rs allocated per lane km for network capacity improvements (including new

constructions)

• Rs allocated for improvements as % of asset replacement value

• Rs allocated for the year per estimated vehicle km on the road network

• Rs allocated for year per estimated Passenger Car Unit (PCU) km on the road

network

• Rs allocated for year per Equivalent Standard Axle (ESA) km on the road network

• % of total allocations provided for institutional capacity development

• % of total allocations provided for traffic management

• % of total allocations provided for road safety improvements

• % of total allocations provided for research & development

Page 55: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

52

5.2 Resource Utilization & Efficiency Indicators

These indicators measure the use of allocated resources, their utilization and efficiency of use.

They do not measure the outputs achieved from such inputs. These indicators are useful to

determine if the resources provided for the previous year are utilized and if there are

institutional capacity problems that prevent the utilization of the total allocation that is

provided. However, these indicators do not measure the effectiveness of the funds which are

utilized.

• Total expenditure incurred for the previous year as % of total funds allocated for that

year

• Average time for cash imprest to be received from treasury

• Average time for settling contractors

• % of funds from last year carried forward to current year

• % of projects completed on time

• Average project over run duration

• Amount spent on maintenance as % of funds allocated for maintenance

• Amount spent on rehabilitation as % of funds allocated for rehabilitation

• Amount spent for improvements as % of funds allocated for improvements

• Amount spent for traffic management as % of funds allocated for traffic management

• Amount spent for road safety as % of funds allocated for road safety

• Amount spent on research & development as % of funds allocated for research &

development

• Total amount spent for roads as % of total amount allocated for roads.

5.3 Output Indicators

These are indicators that measure the physical outputs that are realized as a result of the

application of resources. These should be measurable and may include the following.

• Lane kms maintained for the year

• Lane kms rehabilitated for the year

• New lane kms added to network during year

• Number of intersection improvements

• Number of intersection control systems rehabailitated

• Number of bridges improved

• Number of bridges rehabilitated

5.4 Input/Output Effectiveness Indicators

Page 56: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

53

These indicators measure the effectiveness of the inputs in producing the required outputs.

These indicators do not however measure the contributions of the resources to the desired

outcomes. These include:

• Maintenance expenditure per lane km

• Expenditure for rehabilitation per lane km

• Expenditure for all road works per vehicle km carried on network

• Expenditure for all road works per PCU km carried on network

• Expenditure for all road works per ESA km carried on network

• Percentage of lane kms in network in maintainable condition

• Percentage of vehicle kms carried on network in maintainable condition

• Percentage of bridges in maintainable condition

• Percentage of intersections with appropriate control systems

5.5 Outcome Indicators

• Average Free Flow Speed of the network

• Network Free Flow Speed weighted by traffic flow level

• Average Speed on network

• Average Speed on network weighted by traffic flows

• Average Roughness of the network

• Number of fatal accidents

• Number of road closures hours/year

Page 57: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

54

6 DATA COLLECTION FORMAT

In order to obtain data for implementing an outcome based budget allocation system, a draft

data collection form and set of accompanying instructions is shown in the following table for

budget proposals for the current budget cycle.

1. Project Proponent

2. Project Name

3. Classification

New

Ass

et

Im

pro

vem

ent

Rep

lace

men

t

Reh

abili

tatio

n

Mai

nten

ance

Tec

hnol

ogy

&

HR

Dev

elop

.

o Roads

o Bridges

o Intersection

o Traffic Management

o Road Safety

4. Objectives / Goals

5. Project Impact Area

6. Have Alternatives been

tested

7. Conformity to

Government Policy

Directions

8. Life of Project •

9. Project Commencement •

10.Conditions for

undertaking project

11. Environmental Issues

& Clearance Required

• Is it a prescribed project as per Gazette No: 722/22 of 1993?

• Other requirements

12. Costs @ Pre-Discounted Rate [Rs. (mn)]

Year 2007 2008 2009 2010

(a) Land Acquisition & Resettlement

(b) Civil Works

Page 58: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

55

(c) Consultancy & Supervision

(d) Maintenance & Operations

(e) Training

(f) Variations & Contingencies

Sub Total of Funding Required

(g) Cost of Externalities

• Congestion

• Environmental / Social

• Others

(i) Total

TOTAL COST

13. Benefits @ Pre-Discounted Rate [Rs. (mn)]

(a) Travel Time

(b) Goods Travel Time

(c) Vehicle Operating Cost

(d) Accident Reduction

(e) Vehicular Emissions

(f) Regional Development

(g) Other

(i) Total

14. Non - Quantifiable Benefits [Rs. (mn)]

15. BCA @ 0 % Discount Rate [Rs. (mn)]

a) Design Life (years)

b) Total Cost for Design Life

c) Total Benefits for Design Life

d) BC Ratio (Benefits/Costs)

e) NPV (Benefits - Costs)

f) EIRR

Page 59: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

56

1. Project Proponent: name of agency making the proposal.

2. Project Name: name by which the project is identified

3. Classification: the two-way dimensional classification of the type of project.

♦ New Assets: Investments that provide new and hither-to non-existant facilities.

♦ Improvements: Investments that develop or "make better" existing assets.

♦ Replacement/Rehabilitation: Investments that replace existing assets with identical assets in terms of

capacity and/or quality at the end of their economic design life.

♦ Maintenance: Normal recurrent expenditures—annual and periodic—required over the expected life

of an asset.

♦ Technology and Human Resources Development: Investments in research and development, in

training, and in studies/surveys to develop transport-related information and databases.

4. Objectives/Goals: The economic, social and environmental goals that are pursued in the project as

objectives should be listed here and ticked off against the appropriate column. These goals should

be set after considering the existence of any anticipated problems that need to be solved through

intervention by public investment.

5. Project Impact Area: A brief description of the geographical area that will be directly impacted by the

project during construction and the distribution of the direct recipients of the benefits. In large

projects, it is recommended that a map be attached.

6. Alternatives: All alternatives that are technically possible and are potentially capable of achieving

one or more of the objectives stated in item 4 above.

7. Government Policy Directions: How the proposed project relates to documented Government Policy,

strategic plans and investment plans.

8. Locality: the description of the Project Impact Area (PIA) in terms of administrative zoning.

9. Life of Project: the lifetime of the project over which benefits are anticipated.

10. Commencement of Project: the year (and possibly the month) when the project is to commence.

11. Environmental Issues & Clearance: If the project is a prescribed project under Gazette Extraordinary

722/22 of 1993. Also other clearance such as coastal, flora & fauna, archeological etc as may be

necessary.

12. Costs: the estimated total costs over the project life before discounting. The total annual and periodic

costs for the life time should be included. Consultancy and supervision costs include the cost of

administering the project, which should be apportioned on some basis. Training refers to specialised

training that needs to be a part of the project and required for its proper operation. A suitable

percentage may be added for variations and contingencies based on project experience. Cost of

externalities may also be estimated using unit values available for this purpose.

13. Benefits: Total benefits estimated over the project life before discounting. These maybe estimated

using approximate values and experience from previous detailed calculations.

14. Non-Quantifiable Benefits: A descriptive statement regarding nature and extent of such benefits not

included in item 13.

15. Benefit Cost Analysis at pre-discounted rates computed as; BC ratio (b) NPV and (c) EIRR, the

discount rate at which NPV is equal to zero.

Page 60: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

57

7 SUMMARY TABLE OF CONCLUSIONS & RECOMMENDATIONS

Status Quo Present Issues Proposed Interventions

- Condition of Roads - Even though Sri Lanka has an impressive length

of road network of 108,103 kms its performance

in terms of speed and safety are not satisfactory.

Only around 2% of the national network is in

good or maintained condition, while over 50%

can be considered to severely lag behind in

maintenance.

- This results in lost economic opportunities,

increased congestion costs, loss of life and

accidents costs. The loss due to the

congestion costs is estimated at Rs 32

billion per annum, accident costs at Rs 12

billion per annum and lost economic

opportunities at Rs 270 billion per annum.40

-

- An urgent plan is required to reverse this trend by reducing the loss in

outcomes within the present level of funding.

- Funding Level - Total funding for 2006 is Rs 59.5 billion. The

funding level is 2.26% of GDP and expected to

increase to 2.47% in 2007, before reducing to

around 2.0% in 2008.

- Road construction needs a longer term

investment plan for a systematic

intervention.

- To set total budget allocations for road sector at around 2.0% to 2.5% of

GDP for 10 years. This would approximately be in line with the present

level of funding of between Rs 55-65 billion per annum at 2006 prices.

- Policy Framework - The Government strategy pertaining to the

manner of funding the road sector has not been

explicitly stated. The implicit strategy it has

followed can be gathered from the funding

arrangements in past years and particularly the

manner in which funding has been allocated for

the different road networks.

- The level of funding required for the road sector

is not known as there is no overall strategy for

the development of the entire road network

- The distribution of such funds to the different

road networks has not been determined

- The distribution of such funds by type of

investment namely maintenance, rehabilitation or

new roads remains ad hoc

- There are no instruments of coordination

between different levels of government or even

- The basic policy framework required for

the application of a high level of spending is

not in place.

- These issues need to be urgently resolved

and put in place in order to ensure that the

objectives of the government in allocating a

high level of spending for roads through the

budget would be realized.

- An urgent need exists to determine (a) a rationally determined spending

levels based on a development strategy; (b) a distribution formula for the

different road networks, (c) an investment strategy in distributing funds

between maintenance, rehabilitation and new construction and (d) the

effective delivery mechanism to ensure effective delivery and efficiency

in use of allocated funds.

40

Source: Kumarage, Amal S. LBO, May 2006

Page 61: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

58

Status Quo Present Issues Proposed Interventions

between agencies under central government

which are provided funds for roads.

- -Spending Level - However, of the allocations for 2006, only

around Rs 14 to 15 billion (approximately 25%)

has been earmarked for maintenance.

- There is evidence that Sri Lanka is currently

spending less than what is required to achieve

the desired standards in maintenance of its road

network in present condition.

- However it is also noted that for the national

network, the funds spent for new construction

since 2002 have exceeded those spent for

maintenance by an average of approximately

70%.

- Given that there is a backlog of

maintenance, the present road maintenance

requirement appears around 1/3rd higher

than what is needed to maintain the network

once it is brought to maintainable standard.

- Since this level of maintenance funding is

not provided, the overall condition of the

network is still deteriorating.

- To first bring the network to maintainable condition, so that there would

be more funds available for new roads once the existing road network is

brought to optimum maintenance levels.

Greater performance monitoring is required at the provincial and local

authority roads level.

- Recovery of Funds - It is reported that in 2003, the Central

Government collected Rs 50 billion in Road

User Charges. It spending on roads was Rs 12

billion and even after adjusting for other

expenses, the Govt made a surplus of Rs 26

billion.

- The Provincial Councils is entitled to receive

Rs 1,683 million the central govt collects as

Provincial Traffic Fees, while the spending on

roads was Rs 494 million. However, these funds

are never received by the province since the

revenue amount is deducted from the block

grant.

- The local authorities do not collect direct Road

User Charges. Their source of revenues is from

property taxes, of which approximately 20% is

spent on roads.

- According to the estimates of the Road

Sector Master Plan, the road sector seems to

be a net revenue earner for both Central and

Provincial Governments. Hence, road

investments are in reality funded entirely by

road users. The inability to provide the

desired level of service even when payment

for it has been made is an issue with far

reaching social and economic implications.

- There is potential to gradually transfer the collection of RUCs to the

Road Fund.

- A brief study seems necessary to determine the exact amounts of RUCs

collected and to determine a formula for the short term distribution within

the present budgetary system and in the long term if transferred to a Road

Fund.

- Part of the RUCs should be made available to local authorities.

- The existing fund should be extended to provincial and local authority

roads after setting up norms and standards as well as addressing any

issues they might have.

- Source of Funds - Foreign Funds: 52% of funds for road sector are

foreign funds. However, this is not equitable

across the levels of the network. It is highest at

the national level at 62% and reduced to 23 %

for rural roads. Urban roads presently do not

receive any foreign funds.

- Rural and urban local authorities are not

able to fund major rehabilitations without

foreign funds, Hence networks remains in

deteriorated condition.

- Capacity enhancements is beginning at

provincial level with foreign funded

- To develop an integrated investment plan and source funding

accordingly, with responsibility with Treasury taking the responsibility

for raising the agreed funds for the entire sector.

- Each level of government also set targets to raise own funds through

property taxes or road user charges. This requires further study.

Page 62: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

59

Status Quo Present Issues Proposed Interventions

- Treasury Funds: Treasury funds also deteriorate

at lower levels. While the national network

received 100% funds through Treasury, at the

rural level it is 72%. Once again urban roads

receive the lowest at 32%

projects, but remains poor at local authority

level

-

- Developing an

Integrated

Investment Plan

- Since the level of funding up to now was

grossly inadequate for even basic maintenance,

the Central Government had no leverage to

initiate developmental activities that could be

based on integration of the road networks.

- The low level of funding only resulted in crisis-

management of the road network at all levels but

most evident at the rural level with so many

agencies spending funds from time to time

desperately trying to keep the rural road network

from falling apart. .

- The increased funding opens up hitherto

closed doors for an integrated approach

towards managing the road network

- But with increased funding one of the strategies would be to provide for

additional funding in a manner that promotes holistic development.

- This could start with a sector wide allocation cutting across all three

layers of government.

- The allocations made could be tied in to motivational programs such as

criteria based or matching grants which are even at present well

understood at the provincial and local authority level.

- However, such programs have to be well designed and performance

indicators to monitor output and outcomes accordingly.

- Distributional formula based on road length, lane length, traffic volumes,

terrain, type of road surface and for rural roads, the number of households

and service establishments served may be considered in distributing these

across the different agencies.

- Design standards may also be tied in with this to prevent over designs,

the most common of which would be to provide metalled roads where

compacted earth roads or gravel roads are appropriate.

- Allocation of Funds

by agency

- This shows that the Treasury provides 92.8% of

the overall allocations for all roads. At the level

of the national roads, this is 100%. The lowest

level of Treasury funding is for urban roads at

31.6%. On the other hand, only 81.2% of these

allocations are made direct to the agency

managing the roads. Even though urban roads

get the lowest percentage of their requirements

from the Treasury, all of Treasury funds are

received directly to the particular council. On the

other hand even though rural roads get nearly

75% of their requirements from the Treasury, the

agencies managing the rural roads get only

26.4% of this.

- At the lower levels there are 7 central

government ministries that are spending

more than 100 million rupees per annum.

None of these agencies manage the roads

they spend on.

- In addition there are possibly another 10

central government agencies spending at

least 10 million a year for roads in rural

areas that are used as thoroughfares. Some

of these are roads owned by those agencies.

- The majority of funds for rural roads

amounting to over 75% are channeled

outside of the purview of the Provincial

Council or the relevant Pradeshiya Sabha.

This is because funds allocated to other

ministries are usually spent through the

- Funds should be provided only to agencies that actually own roads.

Ownership should be on the basis of having gazetted these roads to that

agency.

- The Ministry of Road Development can perform as an ‘internal donor’

for facilitating additional funds from centre to rural areas.

- It is important that such funds enter the budgets of the local authorities

and that the work is executed through them.

- Pradeshiya Sabhas can actually implement these projects as build-

maintain projects and thereafter include the maintenance of such projects

to a road fund for such roads.

- The implementation of road projects from the Decentralized Budget

(DCB) should also be transferred from the Divisional Secretariat to the

relevant Pradeshiya Sabha.

Page 63: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

60

Status Quo Present Issues Proposed Interventions

District Secretary’s office or the Divisional

Secretary’s Office which come under the

central government.

- This causes problems of ownership and

gives rise to unnecessary dependencies on

external agencies not engaged in road

management.

- This also raises the problem of

sustainability as the legitimate owner does

not have funding to maintain the road and

the investment is short lived.

- Improving the

Efficiency of

Utilization of Funds

- RDA’s utilization of funds for capital works is

around 70%, while in the provincial councils the

PSDG is around 78%. PSDG funds given to

local authorities have the lowest utilization at

around 50-60%. Maintenance funds are almost

fully utilized, while funds for new constructions

have very low utilization.

- This means that actual expenditure in 2006 is

likely to be around Rs 45 billion at a utilization

rate of 75%, (consistent with past performance).

It will therefore be only in 2008 that spending

could actually reach the desired level of spending

of around Rs 60 billion in 2006 prices.

- When funds are provided direct to the

implementing agency, the utilization is high.

That is when funds are channeled through a

series of agencies, such as in the case of local

authorities, the utilization decreases sharply.

Utilization is also low, when it comes to new

constructions. This is caused mostly by

acquisition delays and in the process of selection

and mobilization of contractors.

-

- RDA Claims non availability of cash

imprest reduces the ability to fully utilize

funds allocated

- At the Provincial Level, utilization is

mostly due to capacity problems both

institutional and contractors

- At the Pradeshiya Sabha level the

problems are also similar to the provincial

level but more intense.

- New constructions may need to be carried

out in phases to avoid fund being tied up.

PMUs also set of for each phase.

For the national network, the cash imprest issue needs to be speedily

resolved so that all payments are promptly paid and that work that is

commenced does not stop half way.

At the provincial level, there is nned to introduce

- Improving the

Effectiveness of

Funding

- Specific application of government policies in

project formulation or in investment planning

cannot be observed at present.

- - Each agency need to be assisted and in turn required to develop and own

a Medium Term Investment Plan (MTIP)- (e.g. for 5 years) based on an

overall development strategy for its road network and an acceptable

Page 64: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

61

Status Quo Present Issues Proposed Interventions

- The budgetary process also does not include

assessment of objectives or outcomes of

proposed projects in order to determine the

degree of subscription of a project for which

funding is sought, to these policies

criterion of prioritization.

- There should be a process of publishing such plans.

- Selection of projects for funding using any source of funding should be

based on the MTIP for each road agency.

- Foreign funded projects should also subscribe to such plans when

properly prepared.

- As a general rule if any roads to be developed or rehabilitated the

proposal should be channeled trough the owner/custodian of the road;

funds could then be allocated to the respective agency. As a rule standard

road cross sections, maintenance standard could be standardized to select

from those by agency concerned hence uniform standard could prevail

right trough out the country.

- Enhancing Sector

Capacity

- Local contractors at the provincial and rural

level have little capacity.

- There is a lack of technical skills particularly in

road construction and traffic management skills

at the provincial and local authority level.

- There is no funding for on-going R&D activity

on construction material, techniques, processes,

traffic models or databases on the road sector.

- Lack of capacity of local contractors

results in poor utilization of funds and

inferior quality and high maintenance costs.

- Lack of Human Resource Development,

particularly at the provincial and rural levels

does not attract or allow retaining capable

technical staff.

- Provincial and local authority agencies are

severely handicapped without databases,

road inventories etc that assist them in

planning and managing roads more

effectively.

- To separately allocate 1/1000th of funds provided by Treasury to each

agency for Human Resources Development- to facilitate on-going

programs to provide technical and associated skills for road agency staff,

particularly at the provincial and local authority levels.

- To separately allocate 1/1000th of funds provided by Treasury to each

agency for Research & Development to develop road inventories,

undertake research in construction techniques (e.g. concrete roads) or

construction materials and other areas that would improve the

effectiveness of spending for road services.

- To provide one-off program of assistance for SME in the field of road

construction and road maintenance to improve in efficiency.

- Ensuring

Sustainability

- With the proliferation of the number of

ministries and votes for spending on roads, most

of this spending is poorly planned, ad hoc and

with little or no targeted benefits.

-

- It is most likely that lead projects under the

‘Mahinda Chinthanaya’ would also suffer a

similar fate unless the question of continuity

and sustainability can be addressed

satisfactorily.

- Strengthen the planning function of each agency and ensure that all new

roads have matching grants for maintenance preferably in a road fund.

- The Road Fund intends to set up a process of disbursement and

monitoring of outcomes for disbursement made from the Fund.

- The efficiency of labour inputs may also need to be studied with excess

labor either offered a VRS or found alternate work on projects rather than

in maintenance work alone.

- This may need to be extended to cover all roads. Provincial and local

authority road could be drawn in on the basis of setting up a fund for all

future road rehabilitation and improvements.

Page 65: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

62

Appendix I Data Collection41

Step 1: Meetings were held with the Finance Commission for (i) the identification of the

different heads under which funds channeled through the Finance Commission are provided

for provincial and local government roads; (ii) selection of two provinces as a sample for

collecting data at the spending/implementation end and (iii) identification of other sources of

funding of road construction and maintenance at the provincial and local government level.

The Southern and Uva Provinces were selected as two sample provinces as they represented

different socioeconomic conditions and road terrain. Moreover, these two provinces together

with the North Central Province were also included in the World Bank’s Road Sector

Assistance Project (RSAP) and its Rural Roads Pilot Component (RRP) which looks at

improving the planning, design and management of the tertiary roads, referred to as rural

roads. As this is an on-going project and given the complementary nature of the two projects

it was considered advantageous to select two of the same provinces.

Step 2: Meeting with the Project Implementing Agency, i.e. the National Budget Department

to collect the relevant national data and to appraise the senior officers of the intended program

of the project and to set time lines for submission of information and seek agreement for the

conduct of a workshop to discuss implementation strategies, prior to the commencement of

the next budget cycle planned for early June 2006.

Step 3: Meetings were held with the following Road Management Agencies.

National Roads-

• Road Development Authority

Provincial Roads-

Southern Province

� Chief Secretary and senior staff of the Southern Provincial

Council

� Southern Provincial Road Development Authority (SPRDA)

Uva Provincial Council

� Chief Secretary and senior staff of the Southern Provincial

Council

� Provincial Department of Road Development

� Uva Province Central Engineering & Construction Services

Urban Roads

• Colombo Municipal Council (Western Province)42

41

The data collection was carried out by the Transportation Engineering Division of the University of

Moratuwa, under contract to the World Bank. This work was undertaken by Messers Janaka

Weerawardena and Tissa Liyanage. 42

The Colombo Municipal Council was included due to its unique nature of being the central and most

developed municipality and the importance of its road network to the entire road network.

Page 66: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

63

• Bandarawela Urban Council (Uva Province)

• Badulla Municipal Council (Uva Province)

• Hikkaduwa Urban Council (Southern Province)

• Ambalangoda Urban Council (Southern Province)

Rural Roads

• Bandarawela PS (Uva Province)

• Karandeniya PS (Southern Province)

• Elpitiya PS (Southern Province)

Appendix II Treasury Allocations for Road

Construction

The Treasury allocates funds for national, provincial, urban and rural roads annually through

its budget. This includes funds for new constructions, improvements and maintenance. These

allocations include foreign funds. All such funds are channeled through a Central Government

Ministry and in most cases the funds are utilized by one of the statutory bodies charged with

the construction and maintenance of roads either at national, provincial or local government.

According to the estimates prepared by Ms Malarmathy Gangatharan, Deputy Director,

National Budget Department the allocated spending for the roads sector in 2006 budget is Rs.

52,278 million rupees, made up of a foreign aid component of Rs. 30,748 million. There also

comprises of Rs. 9,818 million allocated for tsunami affected roads and a further Rs 3,886

million for roads in conflict affected areas and there are eight (08) ministries through which

these funds are distributed. There are foreign funds provided for 26 projects by the ADB,

JBIC, EDCF, Saudi Fund, Kuwait Fund, JICA, WB, Austrian Aid, UK, France etc. However

it is observed that several items of spending on roads from Treasury Funds is not accounted

for in this table as the spending is either included as a recurrent expenditure or is included

under an infrastructure development vote which is not specifically for roads.

Page 67: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

64

Min

istr

y

Pro

vin

ce/

Pro

ject

s

Na

tio

nal

Ro

ad

Prov

incia

l R

oa

ds

Local

Au

thori

ty

Ro

ad

s

Ru

ral

Roa

d

Ma

haw

eli

Roa

ds

Est

ate

Roa

ds

Tsu

na

mi

Aff

ecte

d R

oa

ds

Co

nfl

ict

Aff

ecte

d

Ro

ad

s

To

tal

FA

Hig

hw

ays

Maintenance of Roads and Bridges 3,000 3,000.

Southern Transport Development Project 6,382 6,382 4,612

Outer Circular Highway 625.6 625.6

Colombo - Katunayake Expressway 935 935

Alternate Colombo - Kandy Highway 13 13

Road Network Improvement - ADB &

JBIC

3,370 3,370 2,008

Ratnapura - Balangoda - Bandarawela Road

Rehabilitation - EDCF

1,005 1,005 500

Batticaloa - Trincomalee Road Project (Kinniya

Bridge)- Saudi Fund

439.5 439.5 350

Reconstruction of Bridges Kuwait Fund 693 693 338

Construction of Manampitiya Bridge -JICA 132.5 132.5 100

Baseline Road Extension -Phase III 118 118 5

Road Sector Assistant Project - WB 3,635 3,635 2,900

National Highway Sector Project - ADB 10 10

Construction of steel Bridges - Austria 460 460 400

Widening and Improvements of Roads and

Bridges -SIRUP

4,370 4,370 3,800

Reconstruction of Damaged /Weak Bridges on

National Highway

270 270

Rehabikutation of Puttalam - Mannar Road (via

Marichchukkaddy)

125 125

project Preparatory Facilities, Surveys ,

Feasibility Studies and Land Acquisition

2,356 2,356 448

Improvement of Badulla - Kandy Road (Raja

Mawatha)

100 100

Rehabilitation of Tsunami Affected Road from

Kalutara to Jaffna

7,947 7947 6253

Sub Total 28,039 - - - - - 7,947 35,986 21,714

Ro

ad

Dev

elo

p Mage Neguma Rural Road Development

Programme

700 700 450

National Action Plan for Plantation Community 100 100 50

Sub Total 700 100 800 500

Loca

l G

ov

ern

men

t &

Pro

vin

cia

l

Provincial Specific Development Project

Western Province

300

436.5

736.5

Central Province 250 117.5 30 10 407.5

Southern Province 250 159 409

North East Province 220 197 417

North Western Province 215 205 20 10 450

North Central Province 210 107.5 30 40 387.5

Uva Province 230 45 30 10 315

Sabaragamuwa Province 220 162.5 10 392.5

Road Sector Development (Western,N.Western

,N.Central & Uva) - ADB

2,400 2,400 1,700

Provincial Road Improvement Project in Central

& Sabaragamuwa - JBIC

2,034 2,034 1,601

CAARP - Road Rehabilitation ADB 2,538 2,538 1,900

STAART - Western, Southern & North East -

JBIC

211. 211 174

Sub Total 6,329 1,430 110 80 211 2,538 10,698 5,375

N a Rehabilitation of Bridges in the North East UK 421.3 421.3 320

Page 68: ROADS PUBLIC EXPENDITURE REVIEW IN SRI LANKA

65

Min

istr

y

Pro

vin

ce/

Pro

ject

s

Na

tio

nal

Ro

ad

Prov

incia

l R

oa

ds

Local

Au

thori

ty

Ro

ad

s

Ru

ral

Roa

d

Ma

haw

eli

Roa

ds

Est

ate

Roa

ds

Tsu

na

mi

Aff

ecte

d R

oa

ds

Co

nfl

ict

Aff

ecte

d

Ro

ad

s

To

tal

FA

North East Road Rehabilitation Project - EU 240 240 232

Tsunami Affected Road Rehabilitation -WB 1,585 1,585 1,585

Trincomalee Integrated Infrastructure

Development Project - France

75 75 75

Projects such as NECORD, NEIP and NECCDEP 686.2 686.2 377

Est

ate

Infr

ast

r Construction of Roads & Bridges 150 150

Budget Proposal No.10 - "Infrastructure

Development in Estate Sector"

750 750

Reg

ion

al

Dev

elo

pm

en

t

Uva wellasa Development - Rehabilitation of

Rural Roads

196.5 196.5

Integrated Rural Development Project for North

Western Province

10 10

Infrastructure Development Galle

District/Township Development & Rural Road

Dev.

14.2 14.2

Southern Province - Rural Economic

Advancement Project - ADB

220 220 165.5

Matale REAP 10 10 8.5

Ag

ricu

ltu

re,

Irrig

ati

on

& Dambulla - Bakkamuna Galagawela Rd 425.7 425.7 395.5

Ru

ral

Eco

nom

ic Dept. of Up-Country Peasantry Rehabilitation 10 10

Sub Total - - - 460.7 425.7 900 1,660 1,348 4,794 3,159

Grand Total 28,039 6,329 1,430 1,271 506 1,000 9,818 3,886 52,278 30,748