Upload
klibi
View
17
Download
4
Embed Size (px)
Citation preview
1
EP 21388_a_A_ppt_01 - Risk management
RISK MANAGEMENT
©2
01
0 -
IFP T
rain
ing
EP 21388_a_A_ppt_01 - Risk management 2
Definition
What is a risk?
� An uncertain event or condition that, should it occur, has a
positive or negative effect on the project’s objectives. (PMBOK 4th
Edition)
� To qualify an event as a risk it must:
• Be in the future,
• Be uncertain,
• Generate an impact, positive or negative.
� An event which has already occurred or which will certainly occur isnot a risk but a problem. However if it the occurrence is certain butthe impact uncertain it can be treated as a risk.
An event which has a positive effect on the project is anopportunity
2
©2
01
0 -
IFP T
rain
ing
EP 21388_a_A_ppt_01 - Risk management 3
Introduction
Why should we manage the risks?
� Because most of the projects end up with a delay
� Because most of the projects end up with cost overruns
� Because management is anticipation
� Because to manage a project is mainly to deal with uncertainties.
� Because risk Management means also help for making decision,
with scenario study.
©2
01
0 -
IFP T
rain
ing
EP 21388_a_A_ppt_01 - Risk management 4
Introduction
What are the objectives of risk analysis?
� To minimize the consequences of adverse events and maximize the
results of positive events
� To implement action plans reducing the risk’s probability and / or
impact
� To assist project management for decision taking
� To assess the risks impact on schedule and budget
� To evaluate provisions necessary to compensate the risks
occurrence
3
©2
01
0 -
IFP T
rain
ing
EP 21388_a_A_ppt_01 - Risk management 5
Unknows / Risks
Known :
-Contract
-Basic data
-Project conrol
reference tools
Lev
el o
f ri
sk
Progress
Basic design Conceptual Fabrication Installation
Start
FinishThe knowledge increases
The risks decrease
The level and the nature of the risks evoluate with the progress of the project.
Commissioning
Introduction
©2
01
0 -
IFP T
rain
ing
2 – Identify risks
6 – Monitor and Control Risks
5 – Plan Risk Responses
3 – Perform Qualitative analysis
Score risks
Rank risks
Define action plans
Validate data
Create model
4 –Perform Quantitative analysis
Results :Confidence level for time and costDuration sensitivityCriticality indexCruciality (Sensitivity x Criticality)
Manage
1- Plan Risk Management
Note: Quantitative analysis is reserved To complex and large projects
Introduction –Risk management processes
4
©2
01
0 -
IFP T
rain
ing
Div. - Référence document 7
Plan Risk
Management
©2
01
0 -
IFP T
rain
ing
• How to proceed ?
• Who should be involved in (Risk team, risk owners) ?
• When risk management activities should be performed ?
• How frequently they should be?
Why a risk management plan? To decide
Plan Risk Management– to fix the context
5
©2
01
0 -
IFP T
rain
ing
EP 21388_a_A_ppt_01 - Risk management 9
Schedule
Performance
Cost
May the project have
other objectives ?
Plan Risk Management– Project objectives
©2
01
0 -
IFP T
rain
ing
EP 21388_a_A_ppt_01 - Risk management 10
Project
The contractor’s
objectives
The owner’s
objectives
To keep the cost of the
investment
To transfer efficiently to the
operator
To meet the performance
Etc.
To maintain contractor’s profit
To maintain the relations with
the client
Sécurity
Etc.
Plan Risk Management– Project objectives
6
©2
01
0 -
IFP T
rain
ing
AREAS Phases Objectives Risk types
Project Management Basic Engineering Schedule Organisation
Project control Call for Tenders Cost Resources
Pipeline Detailed Engineering Performance Technology, technical
Platform Procurement Revenue, NPV Schedule
Logistics Construction Safety (HSE) Cost
Operation Commissioning Local Content Procurement
Transport Innovation Logistics, transport
Installation Testing
Hook-up & Commissioning Interfaces
Start-up Operations Quality
Operations, production
Environment; physical, political,
legal, economic, local content
A number of frameworks should be used to examine all areas of
the project from different perspectives:
Plan Risk Management - Risk categories
©2
01
0 -
IFP T
rain
ing
The probability of
occurrence
Define levels and criteriaExample : 4 levels (as recommended by Total standards)
Note: A risk with a probability higher than 80% is no more a risk, but a fact,
And should be handled in the project execution plan.
Level Criteria Factor
Very Unlikely <5 % 1 Has occurred rarely on similar projects
Unlikely 5 % to 30 % 2 Has occurred on similar projects
Possible 30 % to 60 % 4 Has occurred several times on similar projects
Probable > 60% 8 Has occurred very often on similar projects
Plan Risk Management – Fix the range of probability
7
©2
01
0 -
IFP T
rain
ing
The impacts
Define the criteria's (project objectives) Example :
Finish date Cost
Define the levels for each criteriaExample :
Other possible criterias :
Keep the client
Ensure safety
Garanty profit
etc.
Level Criteria: Time Factor
Low < 1 week 1
Medium 1w to 1 month 3
High 1 month to 3
months
5
Very high > 3 months 7
Level Criteria: cost Factor
Low < 500 kUS$ 1
Medium 0,5 to 1,5 MUS$ 3
High 1,5 to 7 MUS$ 5
Very high > 7 MUS$ 7
Plan Risk Management – Fix the range of impact
©2
01
0 -
IFP T
rain
ing
The risk score
Probablity factor x Highest impact factor
Alternatively, the mean impact factor could be used instead of the highest
Risk title Probability Impacts Risk score
Time Cost HSE
A 2 5 1 5 10
B 2 5 7 14
C 4 3 1 7 28
D 1 7 3 7
E 8 7 5 56
Plan Risk Management – The Risk score
8
©2
01
0 -
IFP T
rain
ing
Define the limits of three score familiesExample :
Apply the categories in the register
Score family 1: Score >24 highly critical risks
Score family 2: 24 >= Score > 6 moderate risks
Score familiy 3: Score <= 6 low criticality risks
Probability Weight factor 1 3 5 7
Probable >60% 8 8 24 40 56Possible 30 to 60 % 4 4 12 20 28Unlikely 5 to 30 % 2 2 6 10 14
Very Unlikely < 5% 1 1 3 5 7
Risk title Probability Impacts Risk score
Time Cost HSE
A 2 5 1 5 10
B 2 5 7 14
C 4 3 1 7 28
D 1 5 3 5
E 8 7 5 56
Plan Risk Management – Define score categories
©2
01
0 -
IFP T
rain
ing
High score : Action plan neededMedium score : Action plan suggestedLow score : Evolution to be monitored
Reaction
ManagementAnticipation
Pro
ba
bil
ity
of
ocu
ren
ce
Level of impact
Low High
Low
To prevent and correct
Advance action
And correction
To prevent
Advance action
required
To correct
Action according
level of impact
Monitoring
Plan Risk Management – Define strategies
• Strategies may be: Reduce (Mitigate), Transfer (Insurance,
subcontracting), Avoid, Accept
9
©2
01
0 -
IFP T
rain
ing
Div. - Référence document 17
Identify Risks
©2
01
0 -
IFP T
rain
ing
• Identify and record a long list of threats and opportunities for
the project and by work package.
• Make sure all risks are in the cause-risk-effect format
• Understand the risks
• Capture other information to be used later:
• Potential risk owner
• Triggers
• Potential risk response strategies
The objectives of the Identify Risks process are:
Identify risks – Objectives
10
©2
01
0 -
IFP T
rain
ing
Risk identification
Lessons learned
from similar projects
Scope baseline
Activity cost and
duration estimates
Project Schedule
Project objectives
Contractor risk register
Identify risks – Inputs
©2
01
0 -
IFP T
rain
ing
1
2
3
4
5
6
7
8
Risks registerPrompt list
Risk notes
Brainstorming
Expert interviews
Cause and effect
diagrams
Identify risks – Tools
11
©2
01
0 -
IFP T
rain
ing
WPActivityRisk type
Source (Name/Dept)
Cause Risk Title Effect
PhaseObjective
Trigger Potential Risk Owner
Identify at least 3 risks, each of you, using the risk notes.
WP: Work package or project area
Trigger: Early warning that the risk will occur
Identify risks – Tools Risk notes
©2
01
0 -
IFP T
rain
ing
EP 21388_a_A_ppt_01 - Risk management 22
Prompt lists
1. Technology & Engineering2. Project Execution3. Construction4. Project Schedule5. Costs6. Contractual
REF. YES NO TECHNOLOGY & ENGINEERING
1.01 Is the technology well proven
1.02 Has the COMPANY built a plant using this technology
1.03 Are there any novel features in the plant design
1.04 Are we sure all process systems/units are covered by the PFDs/PIDs
1.05Are we sure all utility/offsite units are covered by the PFDs/PIDs
1.06 Have we identified all effluent streams
1.07 Have we confirmed all effluents streams are treated/ disposed of satisfactorilly
Identify risks– Tools
12
©2
01
0 -
IFP T
rain
ing
EP 21388_a_A_ppt_01 - Risk management 23
1. Technology & Engineering2. Project Execution3. Construction4. Project Schedule5. Costs6. Contractual
REF. YES NO PROJECT EXECUTION
2.01 Is the workscope within the contract clear
2.02 Is there a clear order of precedence of project scope/specification documents
2.03 Are interfaces between OWNER and CONTRACTOR workscopes clear
2.04 Are interfaces with other intervening parties clear
2.05 Have OWNER and CONTRACTOR successfull past experience
2.06 Is the CONTRACTOR familiar with the OWNER procedures
2.07 Are the OWNER procedures onerous for a LSTK contract
Identify risks– Tools
Prompt lists
©2
01
0 -
IFP T
rain
ing
EP 21388_a_A_ppt_01 - Risk management 24
Identify risks– Tools
Some hints
� Identify the cause and consequence for each risk
This will help when finding action plans
� Identify an owner for each risk
He will be in charge of updating the status and coordinating the action plans
� Make sure the level of detail is coherent through out the risk register.
� Make sure every identified risk is an event
� Wording must be accurate and validated by the owner
� Record every risks in one register together with support information
13
©2
01
0 -
IFP T
rain
ing
EP 21388_a_A_ppt_01 - Risk management 25
Different Register’s tool may be used:
Custom made tools: Spread sheet, Data base
Dedicated applications: Oracle Risk Analysis, Active Risk Manager from Strategic
Thought, Predict from Risk Decisions
Identify risks– Tools
RiskID Status Type RBS Area Title Description Cause Consequence
073 Proposed ThreatTechnical.HS
E
WP2 Pipe
Installation
human incident during contruction (handling incident, diving incident, ...)
human incident during construction ( diving incident, ...)
High current in sea at siteLow visibility in sea at siteExposition to sea state
LTI, Fatalities
086 Proposed ThreatContractual
Contracting
commercial offers exceeding pre project estimation
commercial offers exceeding pre project estimation
Project difficultiesRe biddingProject cancellation
017 Proposed ThreatExternal.Wea
ther
WP2 Pipe
Installation
Standby due to weather condiitons worse than estimated
Standby due to weather condiitons worse than estimated
weather condiitons worse than estimatedDelayCost of standby
071 Proposed ThreatTechnical.Installation
WP2 Pipe
Installation
shore approach not technically feasible or not feasible as per CPY requirements
shore approach not technically feasible or not feasible as per CPY requirements
Combination of : Soil MeteoceanAvailable means
Relax CPY requirements or change pipeline routes
079 Proposed ThreatTechnical.Installation
WP2 Pipe
Installation
Failure of trenching contractor to bury pipeFailure of trenching contractor to bury pipe
Poor performance of trenching contractorPipeline potentially unstable and exposed to stone blasting (4" pipe particularly)
032 Proposed ThreatTechnical.HS
EHSE
Fire on board on installation barge or spread vessel
Fire on board on installation barge or spread vessel
Extinguishing system failurePersonnel not trainedFire detection failure
Injuries and vessel damageDealy (Mob of new vessels)Repairs to be done
038 Proposed Threat
External.Loca
l content
Government affairs
New Request of local content New Request of local content New government regulation Delay on project
©2
01
0 -
IFP T
rain
ing
Div. - Référence document 26
Perform qualitative
analysis
14
©2
01
0 -
IFP T
rain
ing
• Subjectively evaluate the probability and impact of each risk
• Create a shorter list of risks by determining the top or critical
risks
• Help making a go/no-go decision (Final Investment Decision)
The objectives of the Qualitative analysis process are:
Perform qualitative analysis– Objectives
©2
01
0 -
IFP T
rain
ing
• Assumptions testing
“We suppose the weather will be fine”
• Data quality assessment
Amount and reliability of data available about the risk
• Probability and impact scales
Provided by the risk management plan
• Determining Risk ranking within the project by calculating the
risk score
The activities of the Qualitative analysis process are:
Perform qualitative analysis– Activities
15
©2
01
0 -
IFP T
rain
ing
Date :
Rev. :
Risk Owner : Jack
AREA : INSTALLATION6
Risk ID : R001 Statut : Proposed28
Title :
Description :
Causes :
Consequences :
Impacts : PRODUCTION : 3 COST : Probability :
DELIVERY HSE : Planning :
Probability : 2 Criticality : 6 Cost :
Mitigation action Responsible Status Planned Date Actual Date
1 - Ted Proposed
2 - Patrick Proposed
3 - Proposed
4 - Proposed
Impacts : PRODUCTION : COST : Probability :
DELIVERY: REVENUE : Planning :
Probability : Criticality : 3 Cost :
Notes :
Action 2
Risk 1
Pre-Mitigationqualitative quantitative
Action
Action 1
Risk Sheet
RBS :
BORGAS INC
BORGAS 2011 PROJECT
Perform qualitative analysis– Risk sheet
©2
01
0 -
IFP T
rain
ing
The risk score is the product of the probability by its impact. If there are several impacts (cost, schedule, performance), we choose the maximum impact.
Risk title Probability Risk score
Time Cost HSE
A 2 5 1 5 10
B 2 5 7 14
C 4 3 1 7 28
D 1 5 3 5
E 8 7 5 56
Impacts
Perform qualitative analysis– Calculate risk score
16
©2
01
0 -
IFP T
rain
ing
RiskID Status Type RBS Area Title Proba
bilitySchedule
Cost Hygien/Safety
Environment
Image
score Risk Owner
073 Proposed ThreatTechnical.HS
E
WP2 Pipe
Installation
human incident during contruction (handling incident, diving incident, ...)
H L VL VH L H 28 HSE Manager
086 Proposed ThreatContractual
Contracting
commercial offers exceeding pre project estimation
H H VH N N VH 28Project Control
Manager
017 Proposed ThreatExternal.Wea
ther
WP2 Pipe
Installation
Standby due to weather condiitons worse than estimated
H L H H N N 20 Pipe WPM
071 Proposed ThreatTechnical.Installation
WP2 Pipe
Installation
shore approach not technically feasible or not feasible as per CPY requirements
H H H N N N 20 Pipe WPM
079 Proposed ThreatTechnical.Installation
WP2 Pipe
Installation
Failure of trenching contractor to bury pipe H L L H L N 20 Pipe WPM
032 Proposed ThreatTechnical.HS
EHSE
Fire on board on installation barge or spread vessel
L L VL VH L L 14 HSE Manager
038 Proposed Threat
External.Loca
l content
Government affairs
New Request of local content L VH L N N N 14Project
Manager
Pre-Mitigated index
• For each risk, a Risk owner is appointed
• The different risks are ranked according to their risk score
Perform qualitative analysis– Risk owner
©2
01
0 -
IFP T
rain
ing
Div. - Référence document 32
Plan Risk Responses
17
©2
01
0 -
IFP T
rain
ing
• Determine what can be done to reduce the overall risk of the
project by decreasing the probability and impact of threats
and increasing the probability and impact of opportunities.
• The activities with the highest risk score
• The most common causes if risk
The objectives of the Risk Response analysis process are:
It will concern:
It will be done according to the risk response strategy defined
in the Risk Management Plan
Plan risk responses – Objectives
©2
01
0 -
IFP T
rain
ing
Avoid TransferReduce
Reduce
probability
Reduce
impact
Facing a risk
Transferring a risk is often partial
Delete causeand consequence
Risk acceptedby the project
Action plan
1 person responsible1 target date1 follow up indicator1 evaluation of potential incidence on the risk
1 Action =
Accept
Included in project perimeterAllocate provisions
Plan Risk Responses – Strategies for risks
18
©2
01
0 -
IFP T
rain
ing
Exploit ShareEnhance
Increase
probability
Increase
impact
Facing an opportunity
Retain part of opportunities
Increase the opportunity by making the cause more probable
Increase the value of the opportunity
Action plan
1 person responsible1 target date1 follow up indicator1 evaluation of potential incidence on the opportunity
1 Action =
Accept
Include in project perimeterAllocate provisions
Plan Risk Responses – Strategies for opportunities
©2
01
0 -
IFP T
rain
ing
EP 21388_a_A_ppt_01 - Risk management 36
Process Summary (Mitigation strategy)
Identify Risks Risk Scoring Risk Sorting
Create
action plans New scoring
Plan Risk Responses – Target Risk Score
RiskID Status Type RBS Area Title Proba
bilitySchedule
Cost Hygien/Safety
Environment
Image
score Probability
Schedule
Cost Hygien/Safety
Environment
Image
score Risk Owner
073 Proposed ThreatTechnical.HS
E
WP2 Pipe
Installation
human incident during contruction (handling incident, diving incident, ...)
H L VL VH L H 28 L L L VH L L 14 HSE Manager
086 Proposed ThreatContractual
Contracting
commercial offers exceeding pre project estimation
H H VH N N VH 28 H H VH N N VH 28Project Control
Manager
017 Proposed ThreatExternal.Wea
ther
WP2 Pipe
Installation
Standby due to weather condiitons worse than estimated
H L H H N N 20 L L L VL N N 6 Pipe WPM
071 Proposed ThreatTechnical.Installation
WP2 Pipe
Installation
shore approach not technically feasible or not feasible as per CPY requirements
H H H N N N 20 L L L N N N 6 Pipe WPM
079 Proposed ThreatTechnical.Installation
WP2 Pipe
Installation
Failure of trenching contractor to bury pipe H L L H L N 20 H L H H L N 20 Pipe WPM
032 Proposed ThreatTechnical.HS
EHSE
Fire on board on installation barge or spread vessel
L L VL VH L L 14 VL L VL H L L 5 HSE Manager
038 Proposed Threat
External.Loca
l content
Government affairs
New Request of local content L VH L N N N 14 L H L N N N 10Project
Manager
Pre-Mitigated index Post-Mitigated index
19
©2
01
0 -
IFP T
rain
ing
EP 21388_a_A_ppt_01 - Risk management 37
Mitigation plans Status / Owner / Date
1 - 01/10/2008
2 -
3 -
4 -
5 -
6 -
7-
8 -
Probability target: VL Impact: Cost MMFirst oil Schedule M
Criticality Target: 4 Ramp up Schedule M
Notes:
Action
Perform audit on critcal elements requiring alternative source of supply
Plan Risk Responses – Risk Sheet
©2
01
0 -
IFP T
rain
ing
• Contingency plan: a plan developed in anticipation of the
occurrence of a risk, to be executed only if specific,
predetermined trigger conditions arise.
The early warning of the risk occurrence is called the trigger
• Fallback plan: a reaction to a risk that has occurred and the
primary response (contingency plan) proves to be inadequate.
Plan Risk Responses – Contingency and fallback Plans
20
©2
01
0 -
IFP T
rain
ing
Div. - Référence document 39
Monitor and Control
Risks
©2
01
0 -
IFP T
rain
ing
• Implement the risk response plans
• Manage the contingency and management reserves
• Control the project risk
• Perform additional risk identification
• Re-estimate the project
• Create “Lessons learned”
The objectives of the Monitor and Control Risks process are
Monitor and Control Risks – Objectives
21
©2
01
0 -
IFP T
rain
ing
EP 21388_a_A_ppt_01 - Risk management 41
0
4
8
12
16
20
24
28
Oct 06 Dec 06 Feb 06 Apr 07 June 07 Aug 07 Oct 07 Dec 07 Feb 08 Apr 08 Jun 08 Aug 08
Ave
rage
crit
icity
0
20
40
60
80
100
120
140
160
180
200
220
240
260
280
300
320
Ris
ks O
pene
d /
Miti
gatin
g ac
tions
Quantity of Risks Opened in the register Number of mitigating actions
Project average criticality Project residual criticality (target)
Indicators: Number of opened Risks, of mitigating actions, project
criticality
Monitor and Control Risks – Indicators
©2
01
0 -
IFP T
rain
ing
EP 21388_a_A_ppt_01 - Risk management 42
Risks distribution
0
5
10
15
20
25
30
Package1
Package2
Package3
Package4
Package5
Package6
Qua
ntity
of r
isks High crit icality - Immediate
act ions required
M edium crit icality - Act ionsrequired
Low crit icality - To be monitored
Indicators: Risk repartition by criticality
Qualitative analysis
22
© 2
01
0 -
IFP T
rain
ing
EP 21388_a_A_ppt_01 - Risk management 43
Perform Quantitative Analysis
© 2
01
0 -
IFP T
rain
ing
• Make more informed decisions about the amount of risk
• Watch the effect of the combination of all risks together
• Determine the probability of achieving cost and schedule
objectives on the project.
• Give an evaluation of the potential gap between objectives
and most probable figures (P80)
The objectives of the Quantitative Analysis process are:
Perform Quantitative analysis – Objectives
23
© 2
01
0 -
IFP T
rain
ing
• Expected Monetary Value is the probability weighted average of all
possible outcomes and is calculated as
EMV = P x I
Perform Quantitative analysis – Expected Monetary Va lue
Quantitative Risk Analysis Form
Risk Activity Probability Cost
Impact
EMV of the
Cost
Risk moved into Plan
Risk Response
14 B 30% $60.000 $18.000 Yes
13 C 50% $40.000 $20.000 Yes
21 B 25% $10.000 $2.500 No
6 E 15% ($30.000) ($4.500) Yes
15 A 15% ($90.000) ($13.500) Yes
Total Expected Monetary Value $22.500
© 2
01
0 -
IFP T
rain
ing
• A reserve is an amount of time and/or cost added to the
project to account for risks.
• Contingency reserve: to deal with known unknowns, i.e., the
identified residual risks that remain after risk response
planning. (Provision pour Risques)
• Management reserve: to deal with unknown unknowns, i.e.,
risks that have not been identified.
• A method to calculate the reserve is to use the calculated EMV
of the project, then to add a percentage of the project cost as
a management reserve. (Provision pour Aléas)
Perform Quantitative analysis – Reserves
There are different kinds of reserve: Contingency reserves and management reserve
24
© 2
01
0 -
IFP T
rain
ing
Perform quantitative analysis – Schedule analysis - P rinciple
• The project schedule is used as a model to forecast project
outcomes.
• Model outputs may be:
Output Milestones dates (Project or WP finish date)
Project duration
Project or work package cost
• Model inputs may be:
Task duration
Input milestones dates
Resources cost
©2
01
0 -
IFP T
rain
ing
EP 21388_a_A_ppt_01 - Risk management 48
Schedule quantitative analysis – Create a model
The accuracy of the model makes the pertinence of the result
� Good level of detail (Detail only for the risky parts)
� Links on every tasks (No open-ended tasks, no constraints)
� Pertinent links between tasks (No negative lags)
� Risks and uncertainties properly simulated
25
©2
01
0 -
IFP T
rain
ing
EP 21388_a_A_ppt_01 - Risk management 49
Each task duration may
have a 3-point estimate.
The delay risk impact will
be added to the task
duration, giving the risk
impacted task duration.
Schedule Quantitative analysis – Create a model
Project DetailProbability
%PxI
Nb of
risks
MinMost
likelyMax
Pipe Detailed Eng
R1
R2
Pipe Procurement
Pipe Transportation
R3
Nearshore pipe installation
R4
R5
R6
R7
Barge Mobilization
R8
R9
Staff & Tools mobilization
Offshore pipe installation
Steel procurement
Platform Detailed Eng
Platform construction
Platform installation
Platform commissionoing
Total - 0
Risk Cost Impact (kUS$)
©2
01
0 -
IFP T
rain
ing
EP 21388_a_A_ppt_01 - Risk management 50
Example using Oracle Risk Analysis software
Min duration
Mean duration
Max duration.
Distribution
% of occurence
Quantitative analysis – Create a model
26
©2
01
0 -
IFP T
rain
ing
EP 21388_a_A_ppt_01 - Risk management 51
Determine the shape of uncertainty spreading
Tâche - +
Triangular : Minimum and maximum
durations are not likely to be met. The
intermediate duration is the most
probable
Uniform : Every duration are equally
likely to happen
Beta : The minimum and maximum
durations have a certain probability to
happen
The shape is selected according to the characteristic of the uncertainty
Quantitative analysis – Create a model
©2
01
0 -
IFP T
rain
ing
EP 21388_a_A_ppt_01 - Risk management 52
33
45
27
42
38
20
1 3 7 13 21 28 34 39 43 46
2 4 8 14 22
12
5
6
9 15
10 16
29 35
30 36
40 44
41
3724 31
23
2511 17
47
48
32
2618
19
10 jours
9 jours
14 jours
17 jours
10 jours
Min Probable Max
Etc.
During each iteration, for each task, a duration is randomly
selected within the shape of the duration profile
Quantitative analysis – The Monte Carlo method
27
©2
01
0 -
IFP T
rain
ing
EP 21388_a_A_ppt_01 - Risk management 53
Quantitative analysis – The Monte Carlo method
� The number of iteration is in the range of a thousand
� For each iteration corresponds a specific set of durations
� Hence :
• A range of end dates
• A series of different critical paths
©2
01
0 -
IFP T
rain
ing
EP 21388_a_A_ppt_01 - Risk management 54
Level of confidence:
A range of end date with their relevant probability of occurrence
Quantitative analysis – The Monte Carlo method
26/12/2013 05/04/2014 14/07/2014
Distribution (start of interval)
0
100
200
300
400
Hits
0% 05/10/2013
5% 15/10/2013
10% 19/10/2013
15% 24/10/2013
20% 29/10/2013
25% 01/11/2013
30% 06/11/2013
35% 10/11/2013
40% 15/11/2013
45% 20/11/2013
50% 25/11/2013
55% 01/12/2013
60% 06/12/2013
65% 12/12/2013
70% 18/12/2013
75% 27/12/2013
80% 05/01/2014
85% 18/01/2014
90% 04/02/2014
95% 25/02/2014
100% 11/07/2014
Cum
ulat
ive
Fre
quen
cy
(Pre-mitigated) 000092 - Ready for drilling : Finish Date
The deterministic date
for ‘Ready for Drilling’
(without risks) is
5/10/2013.
The 80% probable Finish
date is 5/01/2014.
Why the deterministic
date is so little probable?
28
©2
01
0 -
IFP T
rain
ing
EP 21388_a_A_ppt_01 - Risk management 55
The level of sensibility:
Level of contribution of a task to the overall duration
Quantitative analysis – The Monte Carlo method
0%
6%
6%
15%
17%
19%
20%
21%
35%
53% 000098 - Offshore Pipeline installation (24" & 4"MEG) + c
000090 - Installation: jacket + deck
000096 - Barge mobilization
0340 - Construction: deck (hyp: x t) 2
000095 - Sealine Detailed engineering
0350 - Platform Detailed engineering 3
000091 - Hook-up and commissioning
0320 - Platform Detailed engineering 2
000086 - Platform Detailed engineering 1
0390 - Pipeline procurement
(Pre-mitigated)Schedule Sensitivity Index: " 000092 - Ready for drilling" - All tasks
©2
01
0 -
IFP T
rain
ing
EP 21388_a_A_ppt_01 - Risk management 56
The level of criticity:
The proportion of iterations when the task is on the critical path
Quantitative analysis – The Monte Carlo method
91%
91%
91%
91%
100%
100%
100%
100%
100%
100% 000092 - Ready for drilling
000101 - Drilling for 1st oil
000102 - Drilling for ramp-up
000103 - Drilling remaining
000105 - RFSU
0300 - Drilling done
000099 - Overall Pressure Testing
000106 - Onshore Basic Engineering
000116 - Onshore Detailed Engineering
000126 - Onshore Construction
(Pre-mitigated)Criticality Index
29
©2
01
0 -
IFP T
rain
ing
0%
2%
2%
12%
12%
12%
12%
15%
36%
37% 000098 - Offshore Pipeline installation (24" & 4"MEG) + c
000090 - Installation: jacket + deck
000091 - Hook-up and commissioning
000095 - Sealine Detailed engineering
0350 - Platform Detailed engineering 3
0340 - Construction: deck (hyp: x t) 2
000096 - Barge mobilization
000086 - Platform Detailed engineering 1
0320 - Platform Detailed engineering 2
0410 - Pipeline concrete coating
(Pre-mitigated)Duration Cruciality: " 000092 - Ready for drilling" - All tasks
EP 21388_a_A_ppt_01 - Risk management 57
The level of crutiality:
Combination of sensibility with criticity
It is on the high crutiality task
that it is more efficient to act
Quantitative analysis – The Monte Carlo method
©2
01
0 -
IFP T
rain
ing
EP 21388_a_A_ppt_01 - Risk management 58
Similar approach can be
applied to cost risks with
the cost items replacing
the tasks.
Quantitative analysis - Cost
Project DetailProbability
%PxI
Nb of
risks
MinMost
likelyMax
Pipe Detailed Eng
R1
R2
Pipe Procurement
Pipe Transportation
R3
Nearshore pipe installation
R4
R5
R6
R7
Barge Mobilization
R8
R9
Staff & Tools mobilization
Offshore pipe installation
Steel procurement
Platform Detailed Eng
Platform construction
Platform installation
Platform commissionoing
Total - 0
Risk Cost Impact (kUS$)
30
©2
01
0 -
IFP T
rain
ing
EP 21388_a_A_ppt_01 - Risk management 59
Quantitative analysis - Cost
� Similarly to the schedule analysis, each iteration will combine a
different set of cost for each budget line
� Hence :
• The overall cost can differ as a result: …
©2
01
0 -
IFP T
rain
ing
EP 21388_a_A_ppt_01 - Risk management 60
The level of confidence: An evaluation of the contingencies needed to cover the potential cost overrun
Quantitative analysis - Cost
31
©2
01
0 -
IFP T
rain
ing
EP 21388_a_A_ppt_01 - Risk management 61
The level of sensibility:
Level of contribution of each
cost item to the overall cost
Quantitative analysis - Cost
©2
01
0 -
IFP T
rain
ing
EP 21388_a_A_ppt_01 - Risk management 62
Organize and manage the Risk analysis
� Implement a methodology as stated in the Risk Management PlanName a responsible (Risk manager)
Open a budget for the analysis
Define the timing of the risk meetings
Define strategies to be applied
Select a tool for Qualitative and/or Quantitative Risk Analysis
� Insure follow up of action plans
� Update the register with relevant risks identified by thecontractor.
� Update regularly the Quantitative Risk Analysis and theassociated reserves.
32
©2
01
0 -
IFP T
rain
ing
EP 21388_a_A_ppt_01 - Risk management 63
Organize and manage the analysis
The main sources of project stakeholders resistance to the risk
management process are:
� Reluctances on justifying and detailing the responsibilities
� Spirit of fatality for future difficulties
� Feeling of loss of power
� Feeling of admitting the weakness
� Reluctances on deciding on corrective actions