Upload
ckopoleto
View
214
Download
0
Embed Size (px)
Citation preview
7/29/2019 Risk Ass. Difficult
1/4
1
Revised Risk Assessment Method for Use with OHSAS 18001:2007Hisao TOYODA
Owner, Toyoda Consultant, [email protected]
24-12, 3-chome, Kandaiji, Kanagawa-ku, Yokohama 221-0801, Japan
Abstract: In APSS 2009 the author submitted a paper entitled Proposed Risk Assessment Method for Use with OHSAS
18001:2007. A revised version of the methodology for risk assessment is presented after taking into account the last four years
experiences of the application of the original method. The new method also uses a repetitive procedure intensively for risk reduction.The framework of the method is consistent with the steps for the risk assessment specified in OHSAS18001 and they are
implemented in accordance with the scheme used in the original version but now considerably simplified and generalized for use inany industrial sector. The application of the risk control procedure is basically the same as the one specified in OHSAS 18002.The risk categorization and risk-based control plans recommended by BS 18004 are partly utilized. The proposed risk assessment
methodology is applicable not only for an independent execution of risk assessment itself but also for the one incorporated in theOH&S management system. For the users of the latter case, the interface between the risk assessment and management system is
carefully described elsewhere in the paper.
Keywords: ALARP, Hierarchy of controls, OH&S management system, prioritization, risk assessment, risk controls
INTRODUCTION
The risk assessment method introduced hereunder is
developed for OH&S management systems built and
operated under OHSAS 18001:2007. Although the
overall structure of the proposed method in this paper
follows the basic scheme of the original version1), the
procedure for each step has been simplified, as shown
in Fig. 1, and the entire framework was generalized so
that it can be used for risk assessments of any
industries.
The guidelines issued by the governmental agencies in
certain countries stipulate the risk controls are to be
capable of attaining ALARP level2), 3)
. Thus, to
achieve this, the risk assessment methodology has a
repetitive mechanism so that it can attain the risk level
defined as ALARP shown in Fig. 1 and Fig. 2.
Multiple repetition is seldom required. However, incase of overall risk assessments of major industrial
sectors such as manufacturing and construction where
risk level is high, repetition is necessary. Therefore,
the basic flow in Fig. 1 has been modified that
ordinary risk items are dealt with at Step 1 - Step 4.
RISK ASSESSMENT METHODOLOGY
1) Procedure for [A] in Fig. 1
For Step 1, Step 2 and Step 3, any risk assessment
procedure such as the risk matrix approach or
numerical approach is applicable and the details of
these processes are omitted here. Through the steps
referred to above, the risk assessment process is
applied for all the controls including any in place. The
results of these evaluations are stratified in 5 levels
(5-1) in the latter part of Step 3 as shown in Table
1 (extreme left).
Fig. 1 Flow chart for Risk assessment and Determining controls5)
7/29/2019 Risk Ass. Difficult
2/4
2
2) Step 4 (Initial assessment) - Question Is risk
negligible (risk level=1)?
In the first part of Step 4, Risk 1 is excluded and the
other risks (5-2) are sent through Planned
controls in Table 1 (second column from left) for risk
reduction in the latter part of Step 4.
3) Step 4 (Re-assessment) - Question Has
adequate risk level been achieved?
In accordance with the guidelines stipulated as Risk
control plan in Table 1 (center) for the relevant risk
level decided in Initial assessment, the planned
control corresponding to each level of risks in that
plan is determined by considering the hierarchy of
controls explained in Table 2. The risk reduction
scheme for the relevant level is summarized in Table 1
(center) by partly utilizing the risk-based control plans
recommended by BS 18004:2008. The resultant risks
are re-evaluated at the end of Re-assessment and they
are tabulated in 5 risk levels and categorized into U,A and B. For Risk A [4]-[2] no further reduction
is required unless specified otherwise and Risk B [1]
stays as it is as shown in Table 1 (center right) since
all of these risks are in ALARP zone or in the lower
category.
Table 1 Risk reduction process and Prioritization of risk assessment results
7/29/2019 Risk Ass. Difficult
3/4
3
Fig. 2 Acceptable risk and ALARP
4) Step 5 Repetitive risk reduction ([B] in Fig.1)
Risk category U-[5] Very high which has not
achieved ALARP is subject to further risk reduction in
Step 5 by a repetitive procedure for the revised
planned controls including a review on adequacy of
the preceding assessments (Table 1 right). The
procedure itself is the same as that used in Step 4
(Re-assessment). Even if a further risk reduction is
tried in Step 5 or in the ongoing steps, there would be
certain risks in the category U which cannot be
Table 2 Risk controls
brought down into ALARP zone. They are treated as
Special risks and their definition is in Notec)
to
Table 14)
.
INTERFACE-Prioritization of risks for usein OH&S management systems
The final process at the end of the risk assessment
including the prioritization (P3, P2, P1) of its results is
presented at the right side of Table 1 (extreme right).
At the interface between the risk assessment and
OH&S management system, the prioritization for the
relevant category of risks is made in preparation for
use in 4.3.3 Objectives and programme (s) of
OHSAS 18001: 2007 although the details are
specified in the specification. As the risks are the most
important factors to constitute OH&S Objectives, the
foregoing process is a basis for the establishment of
the risk-based operation of the system.
CONCLUSION and Acknowledgement
After four years experience using the original method,
several changes have been made. The method has
been simplified and its interface with management
systems has been improved. The prototype of this
revised version has been applied to the risk
assessment of construction projects under the
management system other than OHSAS 18001: 2007,
the details of which are reported in the recentpublication
5).
The author thanks Dr. Shigeo Umezaki, Mechanical
and System Safety Research Group, National Institute
of Occupational Safety and Hearth, Japan for his
valuable advice.
REFERENCES
1) Hisao TOYODA, Proposed Risk Assessment
Method for Use with OHSAS 18001:2007,
Proceedings of APSS 2009, Osaka, Japan2) Guidelines for LSB Notification No. 0310001,
March 10, 2006, Ministry of Health, Labour and
Welfare (http:// www. jniosh.go.jp/ icpro/ jicosh-old/
english/guideline/2007/ 070612b/ html)
3) Reducing risks, protecting people, HSEs decision
making process (http://www. hse. gov.uk/ risk/ theory/
r2p2.pdf)
4) Journal of Japan Association of Occupational
Safety & Health Consultants, July 2010
5) Separate volume to Journal of Construction Safety
& Labour Affairs, June 2011, Rodo-chosakai,
Tokyo, Japan
7/29/2019 Risk Ass. Difficult
4/4
4
SUPPLEMENT ON ALARP
The guidelines of Ministry of Health, Labour and
Welfare, Japan refer to ALARP- As low as reasonably
practicable in connection with the clause 10(2) Risk
controls in Notification2)
, however, no quantitative
criteria have been given to the upper and lowerboundaries of the zone.
In UK, HSE (Health & Safety Executive) stipulates
that the actual fatality rate for workers is 1 in one
million per annum as the lower boundary of ALARP
zone in Fig. 2. On the other hand, HSE is reluctant to
specify the upper boundary. Dr. Taketoshi Taniguchi,
who used to teach at the graduate school of Osaka
University, Japan indicated the rate of 1 in ten
thousand per annum in his book Decision-making on
Environmental and Technical Risks published from
Osaka University Press.
Based on the criteria referred to above, Fig. A is
drawn with the fatality data of the manufacturing and
construction industries in Japan between 2004 and
2010, which were calculated by using the statistics
released by MHLW. The following comments are
drawn from the figure:
1) The fatality rate of Construction which is
considered to be the most dangerous sector in
Japan is higher than that of Manufacturing. Both
of them have been decreasing for the last seven
years.2) In the case of Construction, the fatality rates
scatter along the boundary indicated by Dr. T.
Taniguchi. That is, the risks of Construction are
distributed at higher levels if compared with
Manufacturing and thus its risk evaluation
criterion has to be designed to yield higher risk
levels such as Risk [5] so that they are subject to
risk reduction by making use of controls.
3) Since the risk controls higher in the hierarchy,
such as Items a, b and c in Table 2 are difficult to
employ in construction projects, especially in the
case of civil engineering works such as tunnels,
bridges, hydroelectric power plants, and rivers
which show the accident frequency rate higher
than the average for Construction, their residual
risks found as the results of risk assessment are to
be carefully disposed of. In the case of
Construction, therefore, use of the controls lowerin the hierarchy, such as Items d and e in Table 2
are inevitable and their implementation at
construction sites must be monitored extensively
so that their effectiveness is continuously
confirmed.
Even in the case of countries with no regulatory
requirements for ALARP, its concept seems to be
helpful for deciding the Acceptable risk specified in
Clause 3.1 of OHSAS 18001:2007. Its
recommended upper limit is shown in Fig. 2 for
reference.
Fig. A Fatality rate in Japan