RF work plan • Test first large amplifier at Daresbury – Electric checks are being made now – Driver amplifiers being retested now – Expect results mid Dec 09 • Study of requirements/desires for MICE hall RF layout, coax systems, component sizes and method to construct under MICE hall floor – starting Jan 10 – report after 3 months • CAD visualisation of RF layout required

RF work plan

Embed Size (px)

DESCRIPTION

RF work plan. Test first large amplifier at Daresbury Electric checks are being made now Driver amplifiers being retested now Expect results mid Dec 09 - PowerPoint PPT Presentation

Citation preview

Page 1: RF work plan

RF work plan

• Test first large amplifier at Daresbury– Electric checks are being made now– Driver amplifiers being retested now– Expect results mid Dec 09

• Study of requirements/desires for MICE hall RF layout, coax systems, component sizes and method to construct under MICE hall floor – starting Jan 10 – report after 3 months

• CAD visualisation of RF layout required

Page 2: RF work plan

• If funding allows – rebuild and test of large amplifier 2 beginning April 2010 – 6 months

• Disassembly of first large amplifier system and power supplies, transport to RAL, install in MICE hall and prepare for test in area, autumn 2010

• Prepare report into RF layout installation for step 5 and specification of design for step 6 if changes are needed