Upload
francine-dorsey
View
213
Download
0
Embed Size (px)
Citation preview
Response Analysis Institutional Linkages and Process – some examples from Afghanistan
FSNWG WorkshopNairobi April 2013
Conceptual space For food security Response Analysis
Process of selection of appropriate and feasible response options;
Response Analysis
Response Options Analysis
Response Planning
Problem-Cause Analysis
Situation Analysis
Current + Projected
Understanding the food security and nutrition problems; what are the proximate, underlying and structural causes
Key linkages: IPC / FS analysis – RA – FS Cluster
March – June 2012 : Drought response; CAP MYR; other appeals....
July – October 2012: CAP 2013
IPC RA Cluster(s) IPC RA Clusters
More effective and appropriate response
FSA FSA
Example
2012 Food Security Cluster Flood Contingency Planning
Background• From March to May 2012, the Food Security and
Agriculture Cluster (FSAC) conducted three (3) regional workshops to develop livelihood based flood preparedness plans for humanitarian actors in Afghanistan;
Background
• Objectives:• Identification of potentially flooded areas within each
region; • Better understanding of both the local livelihoods and
coping capacities to flood events. • Produce livelihood and flood hazard based contingency
plans.
In order to: • Reinforce the capacity of the FSAC community to
provide improved responses to flood events within Northern, Western and Eastern regions;
Participating agencies
Government: ANDMA, DAIL,
UN Agencies: WFP, FAO, UNHCR, IOM, OCHA
Red Cross: ARCS
International NGO: Action Aid, Tear fund, ACTED, DACAAR, Save the Children, Solidarities‘, Afghan Aid, ZOA, Johanniter;
National NGO: COAR, SWNHO, ADEO
Process• Step 1 - Presentation of the flood specific 3Ws tool:
Objective: to show the capacity and the geographical gaps to respond to a flood event at provincial level.
• Step 2 – Identification of most flood prone areas : Provincial working groups divided each province in three (3) different zones, namely most flood prone, medium and less prone areas to flood. IMMAP maps were used as a tool to guide the process.
Process• Step 3 – Identification of main livelihood patterns
with seasonality: cross checked, and validated with FEWSNet 2011 Livelihood zoning publication.
• Step 4 – Identification of potential impacts on livelihoods: Using IMMAP mapping information and simulation material and combining an understanding of seasonal impact of floods with seasonality of livelihoods to derive impact statements
Process• Step 5 – Identification of potential responses
(emergency, rehabilitation, mitigation): during these two sessions, working groups were requested to list the response options according to the livelihoods and the risks and key issues.
• Step 6 – Response Options Analysis – screening of most feasible response options against certain criteria.
Process• Step 7 – Sharing of existing disaster plans:
OCHA and ANDMA shared their information and plans on disaster management;
• Step 8 – Developing priority response plans:
Group works were requested to develop the response plan based on the priority. It provides details about the expected number of affected households need to be supported, modalities of implementation, timeliness, list the experienced agencies, and a rough estimation of budget.
Summary
Step 1 :3W matrixStep 1 :3W matrix
Step 2 :Flood-prone areas Step 2 :Flood-prone areas
Step 3 :Livelihood and seasonalityStep 3 :Livelihood and seasonality
Step 7 :Sharing of existing plans
Step 7 :Sharing of existing plans
Step 8 :Response Plan Development
Step 8 :Response Plan Development
Response Identification Matrix
Response Identification Matrix
Response Analysis Matrix
Response Analysis Matrix
Step 5 :Response Options Identification
Step 5 :Response Options Identification
Step 6 :Response Options Analysis / screening
Step 6 :Response Options Analysis / screening
Step 4 :Hazard – livelihood impact/ extent of vulnerability
Step 4 :Hazard – livelihood impact/ extent of vulnerability
Response Analysis Matrix – emergency phase
During Disaster (1st phase emergency)
. Agriculture . Livestock . Handcraft . Crop . Business . Gardening
. loss of actual and potential food from own production (crops + livestock) . No income from own production (crops + livestock) . No work opportunity
. Support immediate access to food and income
. Potable water
. First Aid Kits . Transfer of affected people to safe place . Transfer of livestock to safe place . Food distribution . Cash transfer
. Area is secure . accessible . Phone accessible . No internet
. ANDMA
. WFP
. FAO . Local people support
. Physically Accessible . tFood not available
. Prices high
. Potable water . First Aid Kits Food distribution . Transfer of people to safe place . Transfer of livestock to safe place
Phases
Livelihood Sources
Impact on livelihood
Key issues to be addressed
Possible response options
Is the Area secure?
Agencies with capacity to respond at scale?
Market dynamics favour cash/vouchers or in kind
Response Recommendation
. Market disrupted
Response Analysis Matrix – recovery phase
After Disaster (Recovery)
. Agriculture
. Livestock
. Handcraft . Crop . Business . Gardening
. loss of actual and potential food from own production . No income from own production . No work opportunity
. Continued food access support . Enable access to seeds and fertilizer . Increase access to business
. Seeds . Fodder . CFF . FFW . Cash grant
. Food distribution
. Area is secure . accessible . Phone accessible . No internet
. WFP
. FAO
. ANDMA
. Donor agencies . NGOs . Government
. Physically Accessible . Less food available . Prices lower .
. Cash . Voucher Seeds . Fodder . FFW
Phases
Livelihood Sources
Impact on livelihood
Key issues to be addressed
Possible response options
Is the Area secure?
A gencies with capacity to respond at scale?
Market dynamics favour cash/vouchers or in kind
Response Recommendation
Food distribution
Opportunities
• Proved very useful way of developing consensus around response options
• Based on livelihoods and likely impacts of a shock
• Was integrated into food security cluster led process
Challenges• Gap analysis (step 7) was problematic• Large numbers of participants made facilitation
difficult YET at the same time, some stakeholder groups not represented (academia, Community representatives).
• Insufficient time for training thus language barriers posed some problems for facilitation
• Insufficient time to build adequate understanding of response analysis technicalities