    Business Case

    RESIDENTIAL SAFETY OFFICE (GOGREEN INITIATIVE)AT

    NORTHEASTERN UNIVERSITY

    VERSION 1.0

    DATE 04/21/2013

  • 7/30/2019 Residential Safety Office Business Case

    2/74

  • 7/30/2019 Residential Safety Office Business Case

    3/74

  • 7/30/2019 Residential Safety Office Business Case

    4/74

  • 7/30/2019 Residential Safety Office Business Case

    5/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 5

    1.3.Recommendation

    The approach for this recommendation should be, all the supervisors and the proctors

    should be trained for the new system. For 6 months, both the systems will be active so as to

    make the users and the supervisors familiar with the new proposed system. This will be

    implemented in three phases; the duration of the first phase will be two months. The users

    will get introduced in first phase. In the second phase, it will be compulsory for the user, to

    use the new system. In the third phase the bugs and the fixes will be made based on the

    feedback from the users.

    1.4.Justification

    Since starting this system, the approach has been without using any online-based system;

    even the swap board used in this system is from a third party. This is only used for swapping

    the users. The new approach will make everything online this will help in better traceability

    of a user, his information like who is doing what when where. This approach is also aligned

    with best strategy and objectives since it uses newer technology to improve the way we do

    business by replacing the older system. While other alternatives and the status quo were

    analyzed, this Project was selected for proposal in this business case because it provides the

    best opportunity to realize benefits for the greatest improvement in efficiency and costreduction.

    70% cost saving in project estimated budget. 60% immediate increase in proctor work efficiency in daily manner. 80% immediate decrease in the amount of time taken to sign in a guest. 98% reduction in maintenance due to paper elimination (GoGreen initiative).

    Effective increase in NUPD communication.

  • 7/30/2019 Residential Safety Office Business Case

    6/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 6

    2. BUSINESSCASE ANALYSISTEAM

    The following individuals comprise the business case analysis team. They are responsible for the

    analysis and creation of the Project business case.

    Role Description Name/Title

    Project

    Manager

    Project managers can have the responsibility of

    the planning, execution and closing of any project.Kaustubh Pathak

    Business

    Analyst

    Identify and articulate the need for change in how

    organizations work, and facilitate that change.

    Nisha Pepsi

    Selvarajan

    System

    Analyst

    Identify, understand and plan for organizational

    and human impacts of planned systems.

    Pratik Zingade

    Data

    Analyst

    Specializes in collecting, organizing, and analyzing

    data from various resources.Nilesh padwal

    Quality

    Engineer

    Monitors the software engineering processes and

    methods used to ensure quality.

    Pragati

    Dhavaleshwar

    Graphic

    designer

    Creates the graphics primarily

    for published, printed or electronic media, such

    as brochures and advertising.

    Fenil Gandhi

  • 7/30/2019 Residential Safety Office Business Case

    7/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 7

    3. PROBLEM DEFINITION

    3.1.Problem Statement

    Northeastern university has on campus Residential Security Office (RSO) whose primary

    responsibility is access control of the more than 40 residence halls . RSO manages its employeesby a third party web based software to assign the employees shifts which has its own

    disadvantages including security, shift blocking, and improper scheduling process. The manual

    process of data fill ing and submiss ion tasks is involved in proctor hiring process. The major

    challenges faced by the RSO are proctor management, workstation management, shift

    management, Cost and Staffing Management, Human Resource management and Incident

    Management. Poor organization of shifts among available proctors, Shift blocking in Swap board,

    No proper break management are not well managed by the existing third party software.

    Proctors get manual write-ups based on different rule violations which may include superfluous

    conditions. This increases restriction on proctors and encourages high attrition rate at RSO.As a

    result, to keep up with the workload RSO staff management keeps the resource pool large. This

    results in poor management, dissatisfaction of proctors and supervisors, insecurity of jobs and

    weak work ethics.

    Goals and Objectives:

    To develop software which clock-in at the arrival and 'clock-out when proctors leave or

    when they take the lunch break. This will lead to effective distribution of breaks and effective

    resource management.

    Retrieve guest details and Black list entries that are not welcome back while trying to make

    an attempt to residence halls from the database.

    To propose a solution for better handling of emergency situations and disciplinary actions.

    To develop software which can eliminate draw backs of existing third party software like

    shift conflicts and swap board blocking.

    To redefine existing manual process of proctor hiring process and writing works by proctors

    during residence hall monitoring.

    Digital Memos are available in dashboard for every proctor as per their respective station.

  • 7/30/2019 Residential Safety Office Business Case

    8/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 8

    3.2.Organizational Impact

    1. Impact on Manager

    a. Hiring Process:

    Instead of paper-based application process, manager can go through all the application easily

    through an application portal. The application portal can help manager sort appropriate

    candidate as per the requirement. Also, it would help RSO to follow its rules regarding

    applicants. For example, we can avoid first semester student applying by putting constraint in

    the web-application itself.

    IMPACT: Transparency in Hiring Process

    b. Staff Management:

    After every semester, a number ofstudents graduation leads to a necessity of new proctors.

    But, most of the times students fail to disclose their graduation which leads to an incorrect

    number of active proctor accounts (Which are used as buffer). The portal will link Northeastern

    University Students portal with RSO portal in order to identify and close the accounts of

    graduating student.

    By getting who will be able to work next semester, RSO can get to know about how many

    proctors it should hire for the upcoming semester. This will allow RSO to distribute the shifts

    properly and assign each proctor proper amount of shifts. Managers can also get to know about a proctors performance easily. Through the web

    portal, manager can get to know about a proctors write-up history and his performance.

    IMPACT: Proper Staff Management

    2. Impact on Supervisor:

    a. Incident Management:

    Currently, supervisor manage all the incidents in an excel sheet which is very inconvenient.The new portal will allow all the proctors s itting at the station to report incident directly. It will

    not only reduce work of supervisor but also increase reliability and efficiency

    By converting paper-based write up system to an online portal, assigning write-ups will be

    easy and supervisor will be able to record it accurately.

  • 7/30/2019 Residential Safety Office Business Case

    9/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 9

    The new system will allow each proctor to directly start/stop the break. The relief proctor

    will no longer need to call RSO in order to register the break timings. Also, it would make it more

    efficient and reliable compared to current excel sheet system.

    2. Proctor:

    a. Workstation assignment:

    Currently, each proctor has to go one hour early in order to get assigned to a workstation.

    Using the new system, proctors will be assigned their respective stations automatically, online

    only which will save an hour.

    The proctor will be able to go to their workstation directly w/o going to RSO station. They

    can get signed in directly by swiping the card at the particular station

    IMPACT: time and effort saving.

    Hardware/Software: In addition to the workforce impact, the online software need to be

    installed on the local server and domain name also be needed to publish the website. Server

    related hardware cost is included in the software deployment to keep the website up and

    running all times for staff.

  • 7/30/2019 Residential Safety Office Business Case

    10/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 10

    3.3.Technology Migration

    Technology migration occurs when changes require the organization switch to a different

    technology. Beyond the risks in technology migration, four key must be considered when

    attempting any IT system migration.

    The following is a high level overview of each phase:

    Phase 1: Readiness of the existing IT infrastructure, which consists of the servers, storage

    networks, and security technologies. New IT infrastructure must be purchased and make sure

    that every computer works well.

    Phase 2: Look at primary databases and determine if they are sufficient or need to be upgraded

    or migrated too.

    Phase 3: Check any custom applications running. They may have to be revamped or replaced or

    otherwise modernized

    Phase 4: Check with RSO packaged software providers to make sure their applications will run

    with new system.

    IBM has its Migration Factory which has some combination of tools, testing and assessment

    methodologies, and professional services to help migrate to technologies.

    3.4.Project Overview: The RSO management project will provide detail for how this project will address the current

    Northeastern residential security business problem. The overview consists of project

    description, goals and objective, project performance criteria and major milestones.

    To ensure that only authorized residents and their guests enter University residences,Northeastern University provides uniformed security coverage twenty-four hours a day,

    seven days a week at the main entrances of the large residences. All students who enter the

    large residences must show their NEU ID Cards to the proctors each time they enter.

    When someone visits a resident of a large residence, they must be checked against thebanned list and entered into guest details. All guests must leave a photo identification card

    at the security desk. No more than three guests per student are permitted at any time.

  • 7/30/2019 Residential Safety Office Business Case

    11/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 11

    Proctors can fill time availability and can pick their shift. Up-to-date staff availabilityinformation, no conflicts due to overlapping shifts, no scheduling conflicts will help to

    increase proctors satisfaction. Unfortunately RSO has lot of scope for improvement such as

    automating the process and to increase proctors satisfaction.

    3.5.Project description:

    The mandate of the Residential Security Office, Northeastern University, is to improveworkstation management, shift management, proctor management and incident

    management.

    The manual process of data filling and submission tasks has to be automated. New solutionhas to be defined for effectively handling shift distribution to proctors and supervisors.Efficient Algorithm has been defined to prevent shift conflicts and swap board blocking.

    Better handling of emergency situations and disciplinary actions by connecting application

    with NUPD.

    Proctors will be able to add their breaks during each shift. Memos, Banned list and sign insheets can be viewed online which will eliminate poor management, dissatisfaction of

    proctors and supervisors.

    The products the project will produce are: a DVD, an information kit for new users andsoftware package. The tools that the organization will use to measure the results of the

    project are: surveys, pilot tests and focus groups involving proctors, supervisors, Residential

    Assistant and managers.

    3.6.Goals and Objectives

    To develop software which clock-in at the arrival and 'clock-out when proctors leave orwhen they take the lunch break. This will lead to effective distribution of breaks and effective

    resource management.

    Retrieve guest details and Black list entries that are not welcome back while trying to makean attempt to residence halls from the database.

    To propose a solution for better handling of emergency situations and disciplinary actions.

  • 7/30/2019 Residential Safety Office Business Case

    12/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 12

    To develop software which can eliminate draw backs of existing third party software likeshift conflicts and swap board blocking.

    To redefine existing manual process of proctor hiring process and writing works by proctorsduring residence hall monitoring.

    Digital Memos are available in dashboard for every proctor as per their respective station.

    3.7.Project Assumptions:

    The following assumptions apply to residential security management.

    Funding is available for training. Funding is available for purchasing hardware/software for residential security management. Project has executive level support and backing All department head will provide necessary support for successful project completion. All staffs and employees will be trained according to their respective data entry, Timesheet and reporting tasks.

    3.8.Project Constraint

    The development or operating environment is new, and no project staff members arefamiliar with it.

    Deliverables submitted for approval will require working days for review. Cannot produce high quality on a restricted budget and within a tightly restricted time

    schedule.

    The estimated staff resources needed to complete the project, according to number, type,work hours, and skills can be inaccurate.

    3.9.Major Project Milestones

    The following are the major project milestones identified at this time. As the project

    planning moves forward and the schedule is developed, the milestones and their target

    completion dates will be modified, adjusted, and finalized as necessary to establish the

    baseline schedule.

  • 7/30/2019 Residential Safety Office Business Case

    13/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 13

    Milestones/Deliverables Target Date

    Project Charter 01/21/2013

    Project Plan Review and Completion 02/11/2013

    Project Kickoff 02/18/2013

    Phase I Complete 03/07/2013

    Phase II Complete 03/24/2013

    Phase III Complete 04/14/2013

    Closeout/Project Completion 04/20/2013

  • 7/30/2019 Residential Safety Office Business Case

    14/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 14

    Release Planning

    Sprint 1Feb12-Feb 25

    Regis ter as proctor, supervis or. Login

    as Proctor/Supervisor.

    Sprint 2Feb 26-Mar 11

    Submit and view memos, banned li st,

    onli ne sheets.

    Sprint -3\ Release 1

    Mar 12-Mar 25Swap board, Picking the shift, Setting

    the avai lability, view schedules.

    Sprint 4Mar 26-Apr 8 Proctor online traini ng material , Download

    appli cation form .View results of exam.

  • 7/30/2019 Residential Safety Office Business Case

    15/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 15

    Release 1 Burn Down chart

  • 7/30/2019 Residential Safety Office Business Case

    16/74

  • 7/30/2019 Residential Safety Office Business Case

    17/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 17

    Cumulative Flow for Release 1 &Release 2

  • 7/30/2019 Residential Safety Office Business Case

    18/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 18

    Total effort for the project

  • 7/30/2019 Residential Safety Office Business Case

    19/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 19

    4. STRATEGIC ALIGNMENT

    The Res idential Safety Offices primary responsibility is access control of the residence halls. Access

    control is achieved with a comprehensive package of "people protecting people," while utilizing a

    computerized electronic access control system and various alarms.

    We aimed the following key factors which can be achieved using respective module of the system.

    1. Security: RSO being the primary center for security of all the residential halls, the systemaims to improve this by providing a better solution which guides proctors and by intuitively

    indicating accesibility and thus reducing scope of any human error.

    The system also provides an interface to quickly access all the information about anyone

    entering the residence hall at a particular time.

    2. Efficient Staff: In any organization, the efficiency is measured by its staff. Throughperformance management, we not just encourage them to perform well, but managers can

    get a clear idea about all the proctors performance.

    Also, predictive HR management helps manager to shut down unused proctor accounts and

    also estimating required proctors for the upcoming term.

    3. Accurate Sign-in: To ensure security, it is very important to preserve exact timing of guestsign-in. And also to retrive the guests being signed quikly is very important. The new system

    will provide access to all information very intuitevely.

    4. Go Green: The system will eliminate need of papers and will store everything online. Andthus saving about 100,000 papers per annum. It also helps organizaion to save cost by notusing papersheets.

    5. Time Efficiency: The system allows everything remote and thus reducing a lot of time andavoid confusion drawn through a lot of conversation.

  • 7/30/2019 Residential Safety Office Business Case

    20/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 20

    5. COST BENEFIT ANALYSIS

    Cost benefit analysis in this project takes a different turn where mutual coordination of

    resources and the online website for daily work is crucial. Major costs are involved in the day to

    day work where most of the paper is involved and extra resources are kept for the printing,

    sorting and analyzing the content of all the sign-in sheets filled by the proctors.

    Also in this analysis some benefits are not cost related but work related which makes work

    easier and reduces the efforts which are required by each proctor and supervisor.

    Some of those cases are as follows

    1) Making the proctor sign-in and sign-out online

    2) Searching for the banned list based on the database content

    3) Swiping the cards of the guest with any bar code.

    4) Writing the detailed incident report and storing it in web based software for future use.

  • 7/30/2019 Residential Safety Office Business Case

    21/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 21

    These changes will save little cost in RSO new implementation but it will have a long term impact

    which will in turn change the functionality of the RSO.

    Major cost savings are included though GoGreen initiative. This will allow eliminating all the

    paper work which currently involved being available online.

    Some of the major cost savings are shown below

    Action Action Type Description

    First year costs (-

    indicates

    anticipated savings)

    Purchase Web-

    based product

    and licenses

    Cost Initial investment for RSO Project $40,000.00

    Software

    installation and

    training

    Cost

    Cost for IT group to install new

    software and for the training

    group to train all employees

    $10,000.00

    Reduce

    Supervisors and

    Proctors staff by

    4-5%

    Savings

    Optimization of the supervisors

    and proctors resource strength

    after implementing paperless

    system

    -$200,495.00

  • 7/30/2019 Residential Safety Office Business Case

    22/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 22

    Action Action Type Description

    First year costs (-

    indicates

    anticipated savings)

    Managers/Super

    visors no longer

    required to go

    through each

    and every

    proctor sheet

    for finding

    mistakes

    Savings

    2-3 managers and 18-20

    supervisors are required to

    invest almost every week almost

    more than 5 hours ($30 x 5) &

    ($15 x 5) to find the mistakes,

    write-ups, no-shows and

    probation related info for each

    and every proctor

    -$40,744.00

    Space and paper

    based system

    requires new

    papers and

    memos every

    week, and their

    maintenance

    Savings Work load and papers cost saved -$402,000

    Reduce

    employee

    turnover by 10%

    Savings

    Savings in cost to out-process

    exiting employee and recruit,

    hire, and train new employees by

    providing efficient training and

    resource planning is

    approximately $50,000 in the

    first year.

    -$50,000

  • 7/30/2019 Residential Safety Office Business Case

    23/74

  • 7/30/2019 Residential Safety Office Business Case

    24/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 24

    6. ALTERNATIVES ANALYSIS

    The following alternative options have been considered to address the business problem. These

    alternatives were not selected for a number of reasons which are also explained below:

    Alternative Analysis Reason for not selecting alternative

    Consider a different alternative COTS

    solution for web based solution

    Significantly higher costs and may not

    meet all the needs.

    Alternative Analysis Reason for not selecting alternative

    System algorithms with auto shift

    assignment

    Might not be convenient for all the

    proctors to pick up a shift allotted to

    them.Alternative Analysis Reason for not selecting alternative

    Outsource the security services to outside

    agencies

    It is better to give opportunity to the

    university students instead of paying and

    outsourcing the services.

  • 7/30/2019 Residential Safety Office Business Case

    25/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 25

    7. REQUIREMENTS DOCUMENT

    7.1.EXECUTIVE SUMMARY

    This requirement document examines and shows the users and specifications in implementations of

    Residential Safety Office and how the GoGreen initiative is used to eliminate the entire paper based

    system and efficiently perform the daily critical and routine tasks. This migration of the system will

    be a big-bang approach where all the system are shifted to new implementation affecting following

    users and the depending services. The important function of the system is up all times and record

    accurate data to be stored securely. This online system is implemented targeting the following

    audience

    1) Proctors

    2) Supervisors

    3) Managers

    Above audience mainly interacts with the system to record the data and operates with secondary

    components of the system.

  • 7/30/2019 Residential Safety Office Business Case

    26/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 26

    7.2.ASSUMPTIONS,RESTRICTIONS &LIMITATIONSAssumptions:

    1) Servers are always up and running 24*72) All users know how to use the system functionality3) All software functions will continue to function as required.4) During daily work all proctors use the software to fill online sheets.

    Restrictions:

    1) All proctors must use the online sign sheet at all time. Usage of paper work is not allowed2) Once the sheets are entered after shift no changes are allowed.

    7.3.DATA FLOW

    Daily sign in data All day sign in info

    Daily shift allocation Stations with shifts

    Allocation

    Check sign in

    data

    Store sign in

    data

    Check proctor

    availability

    Assign shifts to

    proctors

  • 7/30/2019 Residential Safety Office Business Case

    27/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 27

    7.4.CUSTOMER WORKFLOWS

    7.4.1. AS-IS BUSINESS USE CASES AND ACTORS

    The Business use casedepicts the big picture of the business processes (business use cases) that

    will be modified or replaced with the RSO project.

    The actors involved with each process are also shown.

    Figure 7.4.1-1: Business Use Case Diagram

  • 7/30/2019 Residential Safety Office Business Case

    28/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 28

    7.4.2. TO-BE USE-CASES AND ACTORS

    The RSO functional use case belowshows all use cases and actors involved in the RSO project.

    The box represents the scope of this project. The ovals inside are the different use cases sequence of actions that a system performs by

    interacting with the actors.

    The actors involved with the use cases could be the human beings, other system or pieces ofhardware.

    Figure 7.4.2-1: Actors Generalization and Functional Requirements (Use Cases) Diagram

  • 7/30/2019 Residential Safety Office Business Case

    29/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 29

    Actors are user types that represent certain behavioral patterns and are responsible for different

    operations with different sets of authorities . They represent the customer goals, to be achieved by

    means of the product. The actor could be a person, another system, a piece of hardware that

    interacts directly with the system.

    Each actor participates in at least one use case or coherent set of use cases to accomplish an overall

    purpose.

    Actor Background and Skill Set Goals

    proctor Perform majority tasks in

    system and lower inhierarchy

    Monitor Daily activities in RSO and note them

    supervisor Perform admin tasks and

    middle in hierarchy

    Track proctors and stations activities

    Online

    workflow

    system

    Software that acts as

    middleware between

    proctor and supervisor

    Gather and maintain data, perform different

    functions on data and generate reports

    Use-cases are collections of scenarios about system use, where each scenario describes a sequence

    of events. Each sequence is initiated by an actor or by passage of time. The result has to be

    something of use either to the actor who initiated or to another actor.

    Use-Case ID Actor Brief Description

    RSOUC1 Proctor Daily Activities including filling sign in sheet, check in/out

    RSOIUC2 Supervisors Daily monitoring activities and station reports

    RSOUC3 System Different report and shift generation

  • 7/30/2019 Residential Safety Office Business Case

    30/74

  • 7/30/2019 Residential Safety Office Business Case

    31/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 31

    o Personal Dashboard for the proctors to see their current days schedule,assigned Work Orders, and to dos... The personal home page is designed to help

    them manage their schedule and it is unique to them.

    o Define a solution which will a llow proctors to manage their shift allocationonline.

    o Securely access the solution from anywhere, to quickly create and publishschedules.

    o Notify the proctors by email and text messages when schedule is published.o Control what proctors can see and do online using their own ID, view schedules,

    enter work time preferences, trade and pick up shifts, request time off and send

    messages, and much more.

    o Proctors will be able to pick their shifts online.

    7.5.4. HRMANAGEMENT

    o Supports the Tracking of Time and Attendance Reporting for Proctors.o Manage the employee shift allocation and no of hour worked by proctors and

    supervisors.

    o Better handling of emergency s ituations and disciplinary actions.

    7.6. GENERAL REQUIREMENTS

    o Predict the future budget of the management using statistics.o Analyze revenue by seeing trends in increase or decrease of the proctors

    And use the data for forecast the future budget.

    o Develop the software which follows web access ibility guidelines.o

    View interactive and static maps of the university's main campus, as well aso Travel directions to Northeastern residence halls.o Use skip navigation that allows users go directly to the main content of the

    page.

  • 7/30/2019 Residential Safety Office Business Case

    32/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 32

    7.6.1. DATA STORAGE

    If the data are stored electronically, the data should be regularly backed up on disc;a hard copy should be made of particularly important data; relevant software must

    be retained to ensure future access, and special attention should be given to

    guaranteeing the security of electronic data.

    Protect systems and individual files data with login and passwords. Manage access rights (in the case of computer system administrators not involved in

    the project their access rights could be limited).

    Regularly update virus protection to prevent vulnerability of data. Limit physical access to equipment and storage media (for example, in the case of

    data stored on a computer using a stand-alone computer may be secure than anetworked, computer).

    Accurate data removal from old hardware and certification that the data wasremoved.

    Ensure data recoverability in case of emergencies. Regularly update electronic storage media to avoid outdated storage/retrieval

    devices.

    Backup multiple copies in secured multiple locations. Encrypt fi les when wireless devices are used, and keep track of wireless connectivity

    to prevent accidental file sharing.

    Record date and time when a piece of electronic data was originally recorded toprevent alteration or manipulation at a future date.

    7.6.2. DATA DE-IDENTIFICATION

    Data not to be De-identified

    1. Details of proctor on shift2. Details of supervisor on shift3. Details about RA on shift4. Working hours of proctors, RAs and supervisor

  • 7/30/2019 Residential Safety Office Business Case

    33/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 33

    7.6.3. DATA VALIDATION

    Identify duplicate records and merge or group together related information to get aunified view for business.

    Allowed character checks that only expected characters are present in a field. Forexample a numeric field may only allow the digits 0-9, the decimal point and perhaps

    a minus s ign or commas. A text field such as a personal name might disallow

    characters such as < and >, as they could be evidence of a markup-based security

    attack. An e-mail address might require at least one @ sign and various other

    structural details.

    Consistency checks fields to ensure data in these fields corresponds, e.g., If Title ="Mr.", then Gender = "M".

    Data type checks the data type of the input and give an error message if the inputdata does not match with the chosen data type, e.g., In an input box accepting

    numeric data, if the letter 'O' was typed instead of the number zero, an error

    message would appear.

    Format or picture check Checks that the data is in a specified format (template), e.g.,dates have to be in the format DD/MM/YYYY.

    Regular expressions should be considered for this type of validation. Logic check Checks that an input does not yield a logical error, e.g., an input value

    should not be 0 when there will be a number that divides it somewhere in a

    program.

    Presence check Checks that important data is actually present and have not beenmissed out, e.g., customers may be required to have their telephone numbers listed.

    Range check checks that the data lie within a specified range of values, e.g., themonth of a person's date of birth should lie between 1 and 12.

  • 7/30/2019 Residential Safety Office Business Case

    34/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 34

    7.6.4. DATA AND USER ACCESS

    Object-Level Security has to be set to limit proctors from viewing timesheet approvalsheet of manager. Supervisor should see data related to proctor, RAs and residents.

    Field-Level Security should be set for proctors when they are viewing banned list. Record-Level Security has to be set for proctor details. Each Proctor s hould be able

    to view only their personal information.

    7.7. AUDITING

    Software Quality Assurance Audit should assess technical quality, form and functionwith the aim of improving aspects such as ease-of use, reliability, security and

    performance. Software Compliance Audit should audit, the type that can produce anxiety, measures

    softwares level of compliance with regulatory mandates. A body outside of the

    company such as an industry watchdog or government regulator should conduct

    compliance audits.

    Software Licensing Audit can be audited as part of Software Asset Management or RiskManagement practices to determine where the software is distributed and how it isused. A license audit may be required to impose greater controls or find cost savings.

    The audit may seek to enforce software copyright protections. It can be mandated by

    the courts as part of a legal dispute. It can be ordered by risk managers who seek to

    determine the organizations level of exposure from continued use of the software.

    7.8. USABILITY

    The system should be understandable, learnable, operable and attractive.

    Understandability

    Interface elements (e.g. menus) should be easy to understand For a walk up and purchase or use system, the purpose of the system should be

    easily understandable

  • 7/30/2019 Residential Safety Office Business Case

    35/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 35

    Learnability

    The user documentation and help should be complete The help should be context sensitive and explain how to achieve common tasks The system should be easy to learnOperability

    The interface actions and elements should be consistent Error messages should explain how to recover from the error Undo should be available for most actions Actions which cannot be undone should ask for confirmation The system be customizable to meet specific user needs A style guide should be usedAttractiveness

    The screen layout and color should be appealing

    7.9. RELIABILITY

    Software reliability extends across the entire development cycle. Be focused on how services are implemented and look for possible problems within the

    application.

    Developers and operations staff should be properly trained in architecture and lifecyclemanagement practices. Create a team culture where reliability is considered critical.

    Training and education should be provided where possible.

    Use a Robust Operating System. For example, Windows servers often contain thefollowing features Workload Balancing, Storage management, Memory Protection,

    Diagnostic and Recovery tools, Installation protection, etc.

    Remove Failure Points from the Application Design

    All mission-critical data should provide monitoring data. Invest in Quality Software Engineering Processes Coding standards and programming practices should be shared across the business.

  • 7/30/2019 Residential Safety Office Business Case

    36/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 36

    Completed source code should be reviewed by peers for correctness, performance,reliability issues

    The use of a consistent, repeatable, formal software development method always leadsto more reliable systems.

    7.9.1. PERFORMANCE

    95% of ALL visible pages for normal customers respond in 8 seconds or less , includinginfrastructure, excluding back ends.

    The software must support 8000 customers which will on a busy day generate 4500customer interactions.

    The System should have downtime of maximum 88 hours (i.e. 1 % downtime) in a year. Response for user login must be no greater than four seconds throughout the day, with

    fewer than 3.4 errors per million transactions.

    7.9.2. SUPPORTABILITY

    The Customer Advisor Help desk will support users of from 09:00 to 17:00 daily. The ability to change the system to deal with additional international conventions such

    as languages, or number formats, styles should be done.

    The average time needed to port the application from Internet Explorer to NetscapeNavigator shall not exceed 6 person weeks.

    The MTTR shall be 1 day averaged over a 1 year.

    7.9.3. SYSTEM AVAILABILITY

    Redundancy engineering is used to create systems with high levels of Availability. The system should be 99% available.(i.e.)7.2 hr. outage in a month

  • 7/30/2019 Residential Safety Office Business Case

    37/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 37

    7.10.INTERFACES

    The server module must integrate with a dbms through the java databaseconnectivity (JDBC) interface.

    The server must run within a web server available for windowsnt, using dynamiccontent technology (e.g. jsp, cgi/Perl and cold fusion).

    7.10.1.USER INTERFACES

    Ensure compatibility with the High-Contrast option. Use text fields (usually with a label) when the user may type in anything they want. use lists when there are many fixed choices (too many for radio buttons);

    all choices vis ible on screen at once use combo boxes when there are many fixed choices; don't take up screen real estate by showing them all at once use a slider or spinner for a numeric value

    7.10.2.HARDWARE INTERFACES

    System should be implemented in a hardware-independent fashion and should notrely on any particular hardware interfaces expect for the power.

    The computer system must be able to be plugged into a power source. While thismay seem obvious, power is not common at all before the residence hall.

    7.10.3.SOFTWARE INTERFACES

    The System should use oracle database to save the proctor information, write ups,

    memos and more. To implement the project we have chosen Java language for its more

    interactive support. Since this is a web based project, System should run in all type of

    browsers without major changes.

  • 7/30/2019 Residential Safety Office Business Case

    38/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 38

    7.10.4.COMMUNICATION INTERFACES

    The new system will transfer data, which requires an Internet connection. There arealternatives to Internet connectivity, but due to time constraints we will make the

    assumption that the resident hall has Internet.

    When the "proctor" user class is included, user should allow communicating viastandard email and via the World Wide Web. No other communications interfaces

    are mandated.

    7.10.5.DATA MIGRATION INTERFACES

    AS/LIDB-AS/LIDB Data Migration Interface is used in migration of data from existing

    database to new database. It Support for descriptions, format, and encoding rules for

    two new line elements (data items), and to add them to the aggregate of the logical data

    model and associated requirements.

    7.10.6.PURCHASEDCOMPONENTS

    The System is developed in Windows platform. The System needs oracle database

    server and web application server to run. All these components must have a warranty

    with legal terms and issues.

    7.10.7.LICENSINGREQUIREMENTS

    In order to use the system, it should be licensed. Password must be protected, only

    authenticated users can operate the system.

    The terms and conditions of software licenses can vary considerably. It is the

    responsibility of each University organization, staff member, to understand and adhere

    to software license requirements. If you are ever in doubt regarding the appropriate useof a software product, please ask us, or the software vendor/manufacturer. Individuals

    who purchase software should do so in accordance with their purchasing rules. When

    you purchase software from Software Licensing, please be prepared to provide the

    following information:

  • 7/30/2019 Residential Safety Office Business Case

    39/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 39

    Your University Network ID (UNID) and password. Your organization name or ID, or the organization name or ID of the organization

    that you are purchasing for.

    The name of the person within your organization who is responsible for thetechnical operation of the software that is being purchased (if not you).

    The name of the person within your organization who is responsible for maintainingsoftware records.

    If you do not have purchase authority, the name and email address of the personwho will authorize the transaction.

    Youre purchasing card or campus order information.Software may be delivered in different ways. Some software products will be availableto download from the Software Licensing web site provided the license allows

    downloads and we have the capacity to support the download. Software may be picked

    up at our office or delivered via campus mail. Prepare to be flexible, as available delivery

    methods will vary by product.

    7.10.8.LEGAL,COPYRIGHT AND OTHER NOTICES

    These are terms and conditions set forth the rights being licensed to the customer foruse of this application. These rights are the only rights the customer has for usage of this

    software. If in any event the customer does not agree to the terms and conditions or

    violate the rights, they cannot use the software. There is 1 year of limited warranty

    given under this terms and conditions. By installing the system, the customer agrees

    that this terms and conditions is a legally binding and valid contract, agrees to abide by

    all of the terms and conditions, and further agrees to take all necessary steps to ensure

    that the terms and conditions are not violated by any person or entity under customers

    employment. Licensor grants this license software to solely use by the customers

    company.

  • 7/30/2019 Residential Safety Office Business Case

    40/74

  • 7/30/2019 Residential Safety Office Business Case

    41/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 41

    7.10.10. USER ACCEPTANCETESTSTRATEGYThe following are tasks and roles that team members will play for UAT:

    Prepare Test Plan Stage Data Provide help to the UAT users Create UAT user accounts Make system available Log and resolve issues and provide status.

    Prepare Test PlanCreate test scripts for Program and Solicitation setup.Responsibility: Nisha Pepsi Selvarajan

    Create Load Runner scripts for Performance testing of Application

    Responsibility: Kaustubh Pathak

    Create UAT Test Scenario test cases

    Responsibility: Fenil Gandhi

    Stage DataConfigure Programs

    Responsibility: Pratik Zingade

    Configure Solicitations

    Responsibility: Pragati Dhavaleshwar

    Initial ReviewPeer Review: Kaustubh Pathak

    Application Review: Kaustubh Pathak

  • 7/30/2019 Residential Safety Office Business Case

    42/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 42

    7.11.USE CASESIntroduction

    Use Case Name Use Case ID Date Created Created By

    Application for proctor

    position

    UC-1000 04/18/2013 RSO Team

    Primary Actors Secondary Actors

    Student Manager

    Use Case Name Use Case ID Date Created Created By

    Responsibility of proctor UC-1001 04/18/2013 RSO Team

    Primary Actors Secondary Actors

    Proctor Manager

    Supervisor

    Use Case Name Use Case ID Date Created Created By

    Responsibility of

    supervisor

    UC-1002 04/18/2013 RSO Team

    Primary Actors Secondary Actors

    Supervisor Manager

    Proctor

  • 7/30/2019 Residential Safety Office Business Case

    43/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 43

    Use Case Name Use Case ID Date Created Created By

    Responsibility of

    manager

    UC-1004 04/18/2013 RSO Team

    Primary Actors Secondary Actors

    Manager Supervisor

    Proctor

    Use Case 1: Student

    Student: Students of northeastern university are the only once who are eligible to apply for

    proctor position. They are the most basic users of the system.

    They will be accessing system for

    Sign Up: The NEU students need to create an account using their husky Id to create a newRSO account. They need to have an account in order to apply for any position.

    Login: The students are required to login to system before they can apply for proctoring.

    Applying for proctor position: Submit resume, fill up the application form. Check application status: They can check whether their application is accepted for

    interview, Interview results, Test result and job start date

    Check application deadlines: They can get a brief idea regarding when RSO will be acceptingthe applications and what are the deadlines for that.

    Schedule Interview: Student will be allowed to pick up a slot for his interview from theavailable slots.

    Refer Learning Material: Students wont require taking physical lecture anymore. They willgo through all necessary information directly from the web-portal, which will be helpful for

    their test.

  • 7/30/2019 Residential Safety Office Business Case

    44/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 44

    Give Online Test: Students can give test online. It will be a time based MCQ test, which isnecessary to pass in order to become a proctor. The system will prevent student to navigate

    during exam.

    Test Result: The test will be evaluated instantaneously giving students their result at theend of the test.

    Use Case 2: Proctor

    Proctor: The main responsibility of a proctor is to monitor students and their guests entering

    the dorm. Proctors are required to report to RSO if anything goes wrong. They also help

    residents in case of any lockouts or emergency.

    They will be accessing system for

    SHIFT MANAGEMENT

    1. Provide Availability: Proctors can give their availability for next shift release2. Pick Up Shift: Proctors can pick up shift from the swap board3. Drop Shift: Proctors can drop their shift, which will be available for others to pick up.

    Unless someone else picks it up, the same proctor will be responsible for the shift.

    4.

    Exchange Shift: Proctors can exchange their shifts safely w/o interference from otherproctors. They just need to know their user ID.

    WORKSTATION MANAGEMENT

    1. Workstation assignment: They can get their workstation by singing into the system. Thesystem will randomly give the proctor his workstation for the current shift.

    2. Remote Swipe In/ Swipe Out: the proctors will be considered as swiped in when theylogin from the computer at workstation.

    3. Guest Sign-In: Proctors can write down all guests for a resident. This systemautomatically detects if a banned list person is trying to get signed-in and thus

    improving reliability.

    4. Banned List: The list of all the people banned from dorms.

  • 7/30/2019 Residential Safety Office Business Case

    45/74

  • 7/30/2019 Residential Safety Office Business Case

    46/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 46

    Use Case 3: Supervisor

    Supervisor: The main responsibility of a supervisor is to ensure proper working of each

    workstation by assigning proctors and monitor their activity. They also provide a guideline to all

    the proctors during current shift.

    They will be accessing system for

    SHIFT MANAGEMENT

    1. Provide Availability: Supervisors can give their availability for next shift release2. Pick Up Shift: Supervisors can pick up shift from the swap board3. Drop Shift: Supervisors can drop their shift, which will be available for others to pick up.

    Unless someone else picks it up, the same proctor will be responsible for the shift.

    4. Exchange Shift: Supervisors can exchange their shifts safely w/o interference from otherproctors. They just need to know their user ID.

    WORKSTATION MANAGEMENT

    1. Look-up for no shows: supervisors are required to ensure that each workstation isassigned at least one proctor. He needs to check this before half an hour earlier than the

    shift. It is supervisors responsibility to ensure stand-by proctors in case of a no-show.

    2. Assign Shift/Station: The supervisor has authority to directly assign shift and workstationto a particular stand by proctor.

    3. Breaks Log: the supervisor needs to ensure that all the breaks for all station are runningas per schedule and no one has taken more time than allotted maximum time.

    INCIDENT MANAGEMENT1. Report Incident: The supervisor can report any incident occurred directly from this

    system. The retrieval and search of past incidents also become quite easy through this

    online database.

  • 7/30/2019 Residential Safety Office Business Case

    47/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 47

    2. Give Commendable and Write-up: supervisors can directly give write ups andcommendable to proctors and provide specific reasons for that as well. Upon receiving

    any write-up or commendable, proctors get a notification.

    3. Add NUPD enter-exit info: Supervisor can easily keep track of NUPD entering and exitingfrom a specific station. The proctors still need to inform supervisors by calling so as to

    maintain integrity.

    4. Go through lockout logs: Supervisors dont need to call RA on duty in case of lockout;proctors directly do this by sending a lockout request through their portal.

    MISCELLANEOUS

    1. Notification Management: They can manage their notifications regarding any shiftavailable and etc.

    2. Refer Training Material: Proctors can still refer any material if they find somethingconfusing.

    Use Case 4: Manager

    Manager: Manager is responsible to ensure sufficient and proper workforce and maintain

    security of all the dorms of Northeastern University.

    They will be accessing system for

    HR MANAGEMENT

    1. Check for proctors needed: The system connects with Northeastern students portal inorder to get an exact number of students who will be working in the next semester by

    eliminating users who are graduating or will be going on a co-op program. Thus, it notjust disables all unused accounts, but also gives an exact idea regarding how many

    proctors RSO need to hire.

    2. Go through sorted applications: Rather than going through each application, the portalsorts all the applications according to their eligibility and interests. Thus, giving

    managers a better list of applicants to be interviewed.

  • 7/30/2019 Residential Safety Office Business Case

    48/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 48

    3. Schedule Interview: The manager is supposed to interview before hiring any candidateand the portal provides an easy way to schedule interviews with applicants. The

    manager just need to fill up his availability and a notification will be sent to all sorted

    applicant automatically.

    4. Grant Privileges: After interview, if the applicant is hired for job, manager can directlygrant his account from here so as to give him proper privilege of proctor or supervisor.

    WORKSTATION MANAGEMENT

    1. Update banned list and memos: The main responsibility of manager is to ensureupdated banned list and provide memos at respective stations. Manager can update

    both banned list and write up memos for each station through the system. It also

    helps to keep track of all the memos for future reference.

    QUALITY MANAGEMENT

    1. Review incident: The manager is responsible to go through each incident occurred so asto ensure the security of all dorms. He can go through all incidents directly with this

    portal.

    2. Review write-up: In case any proctor appeal against any write-up given by supervisor,manager can directly go through his appeal from the system and take decision based on

    the appeal.

    3. Review proctor/supervisor performance: upon many write ups against any proctor ormany complaints against supervisor, the manager can easily review his performance by

    going through his profile built based on all his write-ups, no-shows, commendable notes

    and even incidents reported by him. This gives an index for manager so as to decide

    whether a proctor should be continues or should be probated.4. Probate proctor/supervisor: The manager can directly probate a proctors account for a

    specific amount of time. The system automatically notifies the proctor/supervisor.

  • 7/30/2019 Residential Safety Office Business Case

    49/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 49

    MISCELLANEOUS

    1. Update training material: The manager can directly update the training materialreferred by everyone in case of any confusion.

    2. Send notification: The system allows manager to send important notification, postdeadlines directly from the system.

  • 7/30/2019 Residential Safety Office Business Case

    50/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 50

    8. HIGH LEVEL SYSTEM OVERVIEW:

    High level system overview diagram to present complete picture

  • 7/30/2019 Residential Safety Office Business Case

    51/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 51

    9. DIAGRAMS AND PROCESS FLOWS:

    Online application system

  • 7/30/2019 Residential Safety Office Business Case

    52/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 52

  • 7/30/2019 Residential Safety Office Business Case

    53/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 53

  • 7/30/2019 Residential Safety Office Business Case

    54/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 54

  • 7/30/2019 Residential Safety Office Business Case

    55/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 55

  • 7/30/2019 Residential Safety Office Business Case

    56/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 56

  • 7/30/2019 Residential Safety Office Business Case

    57/74

  • 7/30/2019 Residential Safety Office Business Case

    58/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 58

    10.USER INTERFACE SCREENSHOTS

  • 7/30/2019 Residential Safety Office Business Case

    59/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 59

  • 7/30/2019 Residential Safety Office Business Case

    60/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 60

  • 7/30/2019 Residential Safety Office Business Case

    61/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 61

  • 7/30/2019 Residential Safety Office Business Case

    62/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 62

  • 7/30/2019 Residential Safety Office Business Case

    63/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 63

  • 7/30/2019 Residential Safety Office Business Case

    64/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 64

  • 7/30/2019 Residential Safety Office Business Case

    65/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 65

  • 7/30/2019 Residential Safety Office Business Case

    66/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 66

  • 7/30/2019 Residential Safety Office Business Case

    67/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 67

  • 7/30/2019 Residential Safety Office Business Case

    68/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 68

  • 7/30/2019 Residential Safety Office Business Case

    69/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 69

  • 7/30/2019 Residential Safety Office Business Case

    70/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 70

    11.REPORTS

    General

    The header and the footer are same for all the reports generated. The font size used will be 12

    and the font used is Calibri (Body) for all the reports.

    R 1.1. Report Header

    R 1.1.1. RESIDENTIAL SAFETY OFFICE NORTHEASTERN UNIVERSITY.

    R 1.2. Report Footer

    R 1.2.1.

    R 1.3. Page Header

    R 1.3.1. RESIDENTIAL SAFETY OFFICE NORTHEASTERN UNIVERSITY.

    R 1.4.

    Page Footer

    R 1.4.1.

    Report 1

    R 2.1. Effort Summary Report - Effort reporting is a federal requirement for certifying that the

    effort charged or cost-shared to each award has actually been completed. Non-compliance

    with this requirement has resulted in audit disallowances and significant fines to several

    large research universities.R 2.1.1. Effort Summary Report

    R 2.1.2. Effort is defined as the amount of time spent on a particular activity. It includes

    the time spent working on a sponsored project in which salary is directly charged or

    contributed (cost-shared effort).Individual effort is expressed as a percentage of the

    total amount of time spent on work-related activities (instruction, research, patient

    care, administration, etc.) for which the University compensates an individual. Effort

    reporting is the mandated method of certifying to the granting agencies that the effortcharged or cost shared to each award has actually been completed.

    R 2.2. Sample

  • 7/30/2019 Residential Safety Office Business Case

    71/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 71

    Report 2

    R 2.3. Monthly Turnover Report- A measure of how quickly a fund turns over

    its holdings during the year. A highly active fund will have a high annual turnover. It is equal

    to the dollar transaction volume of the trades in one year divided by the total portfolio size,

    expressed as a percentage.

    R 2.3.1. Monthly Turnover Report

    R 2.4. The report includes the following fields:

    Code Pulled from the monthly history file for the position. Beginning Period Number of Positions The total number of position full-time

    equivalent (FTE) values for the beginning date and code, pulled from the monthly

    history file based on the begin date entered.

    Beginning Period Number of Vacant Positions Total vacant positions for thebeginning date and code, pulled from the monthly history file, based on the begin date

    entered.

    Beginning Period Percentage of Vacant Positions Number of vacant positionsdivided by the number of positions and multiplied by 100, pulled from the monthly

    history file, based on the begin date entered.

    Ending Period Number of Positions The total number of position FTEs for the endingdate and code, pulled from the monthly history file, based on the end date entered.

    http://www.investorguide.com/definition/measure.htmlhttp://www.investorguide.com/definition/fund.htmlhttp://www.investorguide.com/definition/turn.htmlhttp://www.investorwords.com/7152/holdings.htmlhttp://www.investorguide.com/definition/year.htmlhttp://www.investorwords.com/9933/highly.htmlhttp://www.investorguide.com/definition/active.htmlhttp://www.investorwords.com/2306/high.htmlhttp://www.investorguide.com/definition/annual.htmlhttp://www.investorguide.com/definition/turnover.htmlhttp://www.investorwords.com/7129/dollar.htmlhttp://www.investorguide.com/definition/transaction.htmlhttp://www.investorwords.com/5258/volume.htmlhttp://www.investorwords.com/5014/trade.htmlhttp://www.investorguide.com/definition/total.htmlhttp://www.investorwords.com/3741/portfolio.htmlhttp://www.investorwords.com/8392/size.htmlhttp://www.investorwords.com/8392/size.htmlhttp://www.investorwords.com/3741/portfolio.htmlhttp://www.investorguide.com/definition/total.htmlhttp://www.investorwords.com/5014/trade.htmlhttp://www.investorwords.com/5258/volume.htmlhttp://www.investorguide.com/definition/transaction.htmlhttp://www.investorwords.com/7129/dollar.htmlhttp://www.investorguide.com/definition/turnover.htmlhttp://www.investorguide.com/definition/annual.htmlhttp://www.investorwords.com/2306/high.htmlhttp://www.investorguide.com/definition/active.htmlhttp://www.investorwords.com/9933/highly.htmlhttp://www.investorguide.com/definition/year.htmlhttp://www.investorwords.com/7152/holdings.htmlhttp://www.investorguide.com/definition/turn.htmlhttp://www.investorguide.com/definition/fund.htmlhttp://www.investorguide.com/definition/measure.html
  • 7/30/2019 Residential Safety Office Business Case

    72/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 72

    Ending Period Number of Vacant Positions Total vacant positions for the ending dateand code, pulled from the monthly history file, based on the end date entered.

    Average Number of Positions Beginning number of positions plus the ending numberof positions divided by two.

    Turnover Percentage The number of separations divided by the average number ofpositions, multiplied by 100.

    Sample

  • 7/30/2019 Residential Safety Office Business Case

    73/74

    Residential Safety Office (GoGreen Initiative)

    Business Case v 1.0 Page 1

    12.APPENDICES

    A A.1. RSO: RSO in these documents refers Residential Safety Offices whose primary

    responsibility is access control of residential halls.

    A A.2. Data: Data in this report includes information about proctors, supervisors, workinghours of proctors and supervisors, information related to residents of the building, guest

    visiting the residents.

    A A.3. Swap board: Swap board in the application means the platform where proctors and

    view available shifts, pick up a shift and drop a shift.

    A A.4. NUPD: NUPD refers to Northeastern University Police Department.

    A A.5. Write-ups: Write-ups are kind of warning for proctors when proctors violate the rules.

    A A.6. Memo: Memos contain important information like access information, NUPD alerts,

    policies etc. and are updated every day.

    A A.7. Banned List: Contains list of names whose entry into the building is restricted.

    A A.8. Workstations: Stations or resident building where proctor has to do his/her duty.

    A A.9. UNID: UNID stands for University Network ID.

    A A.10. UAT: User Acceptance Test Strategy.

    A A.11. MCQ test: Multiple choice questions test taken while a proctor is hired.

    A A.12.No shows: When a proctor is allotted a shift and the proctor does not come to the shift

    then it is called no show.

  • 7/30/2019 Residential Safety Office Business Case

    74/74

    Residential Safety Office (GoGreen Initiative)

    A A.13. Sign-in sheet: In this report sign-in sheet refers to a sheet where the details of the

    guests entering the building are written by the proctor.

    13.REFERENCED DOCUMENTS

    Contractor Performance Measurement Data Analysis Techniques by The DefenseSystems Management College, Fort Belvoir, Virginia (published January 1983)

    Summerville, Ian & Pete Sawyer. (1997). Requirements Engineering: A good practiceguide.

    o West Sussex, England: John Wiley & Sons. U.S. Air Force Systems Command Guide to Analysis of Contractor Cost Data (published

    August 1979)

    Human Resource Management -http://people.brandeis.edu/~molinsky/documents/Human%20Resource%20Management%20Eth ics%20and

    %20Employment.pdf

    For creating website -www.wix.org For creating USE Caseswww.creately.com

    14.APPROVALS

    The signatures of the people below indicate an understanding in the purpose and content ofthis document by those signing it. By signing this document you indicate that you approve

    of the proposed project outlined in this business case and that the next steps may be taken

    to create a formal project in accordance with the details outlined herein.

    Approver Name Title Signature Date

    Robert O. Jose Associate Dean and Director

    http://people.brandeis.edu/~molinsky/documents/Human%20Resource%20Management%20Ethics%20and%20Employment.pdfhttp://people.brandeis.edu/~molinsky/documents/Human%20Resource%20Management%20Ethics%20and%20Employment.pdfhttp://people.brandeis.edu/~molinsky/documents/Human%20Resource%20Management%20Ethics%20and%20Employment.pdfhttp://www.wix.org/http://www.wix.org/http://www.wix.org/http://www.creately.com/http://www.creately.com/http://www.creately.com/http://www.creately.com/http://www.wix.org/http://people.brandeis.edu/~molinsky/documents/Human%20Resource%20Management%20Ethics%20and%20Employment.pdfhttp://people.brandeis.edu/~molinsky/documents/Human%20Resource%20Management%20Ethics%20and%20Employment.pdf