Upload
others
View
5
Download
0
Embed Size (px)
Citation preview
RP-0006VOL. 1
The Capacity Expansion Project of
Wuchang-Guangzhou Railway Line of
The Seventh World Bank Financed Projects
Resettlement Action Plan
July 1998
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Contents
1 Project Introduction1. 1 Background and Significance of the Project1.2 The Ownership of the Project and the Organizational Institutions1.3 Measures for Minimizing Land Acquisition and Housing Demolition1.4 Preparatory Work for Land Acquisition, Housing Demolition and
Relocation, Resettlement
2 Project Impacts2.1 Land Acquisition2.2 Housing Demolition & Relocation2.3 Aboveground Attachments2.4 Affected Infrastructures2.5 Impact Analysis
3 Law Framework3.1 Policies, Laws and Regulations as the Basis3.2 Provisions of Policies and Laws3.3 Preferential Policies Specifically Stipulated for
the Project of Wu-Guang Railway Line3.4 The Concord of the Resettlement Policies between
the World Bank and China
4 Compensation Fees
4.1 Principles for Compensation
4.2 Contents and Standards of Compensation
4.3 Calculation of Compensation Rate of Land Acquisition
4.4 Calculation of Compensation Rate of Housing Demolition
4.5 Calculation of Compensation Rate of Fruit Trees
4.6 Funds Budgeting and Investment Planning
4.7 Fund Movement and Management
5 Resefflement and Rehabilitation Plans
5.1 Resettlement Goads
5.2 Resettlement and Rehabilitation Plans for Rural PAPs
2
5.3 Resettlement and Rehabilitation Plans for Urban PAPs
5.4 Resettlement and Rehabilitation Plans for Railway Internal Demolistion
6 Organizational Institutions
6.1 Institutional Establishments
6.2 Responsibility of the Institutions
6.3 Coordination and Liaison between the Institutions
6.4 Measures Takes to Enhance the Capabilities of the Institutions
7 Consultation, Mass Participation and
Grievance Appeal Channel
7.1 Consultation
7.2 Meeting on Displaced Population
7.3 Mass Participation
7.4 Grievance Appealing Channel
8 Monitoring and Evaluation
8.1 Goals of Monitoring
8.2 Internal Monitoring
8.3 Extemal Monitoring
8.4 8.4 Report Submission
9 Lists of Rights and Interests
Appendix 1 Socioeconomic Condition of Affected Area
Appendix 2 Tables of the Survey and Statistics of
Housing Demolition along Wu-Guang Line
Appendix 3 Agreements and Additional Agreements between
the Railway and Provinces
3
I Project Introduction
1.1 Background and Significance of the Project
(1) The Capacity-Expansion Project of Wuchang-Guangzhou Railway Line, covering a
length of 1082 km starting from Wuchang in the north and ending at Guangzhou in the
south, including the sublines related either to Wuhan pivot or Guangzhou pivot,
traverses over 20 cities and counties in Hubei, Hunan and Guangdong provinces.
In 1992, a feasibility report was finished for the Capacity Expansion of Wu-Guang Rail
Line, a national key construction project, and was submitted to the State Planning
Commission for approval. In 1996,a technical design was made and was examined and
approved by the Appraisal Center of the Ministry of Railways in March 1997.
Subsequently in March 1997, the 4h Surveying & DesigningInstitute of the Ministry of
Railways, as the designing agent, began spot-surveying along the rail line and by
Feb. 1998 had virtually finished the detailed design for construction.
The construction of the Capacity Expansion Project, to be started full-scaled in 1998,
will approach from the south to the north, with the section from Hengyang to
Guangzhou to be attempted in 1999 and the whole line to be completed in 2000.
(2) Beijing-Guangzhou Railway, a trunk line traversing China from north to south, has
been playing a very important role in boosting national economic growth and propelling
the society forward by functioning as the mainstay in the overall railway networks in
China. Wuhan and Guangzhou, two metropolises and passenger transportation centers,
are crucial termini in the passenger transportation framework along Jing-Guang Line.
After the engineering of the electrification capacity expansion for the section from
Beijing to Wuchang was completed, it is even more strategically urgent to start the samne
engineering for the section from Wuhan to Guangzhou so that the capacity expansion
4
will be able to augment transport volume, increase trains in operation, expedite the
transferring speed, add more comfort to passengers, improve the prestige of the railway
and enhance the competitive ability of the railway. More important is that Wu-Guang
line is the land line linking inland and coastal cities. It has been playing a very
important role in politics, economy and other fields in the past, at present and will still
be so in the future, and it is also the important transport artery from north to south in the
existing and planned railway net.
1.2 The Ownership of the Project and
the Organizational Institutions
The Ministry of Railways (MOR) is the project owner of the Capacity Expansion of
Wuhan-Guangzhou Railway Line. Guangzhou Railway Conglomerate Company
(GRCC) and Zhengzhou Railway Bureau (ZRB) are the authorized agents functioning
as the project owner in the capacity of MOR. GRCC has set up an engineering
headquarters at Zhuzhou responsible of the engineering in Guangdong Province and
Hunan Province. Likewise, Zhengzhou Railway Bureau has also set up an engineering
headquarters at Wuhan responsible of the engineering in Hubei. The land acquisition
and resettlement for the Project have been contracted by the MOR respectively to the
Guangdong Provincial Land Administration Bureau (LAB), Hunan Provincial LAB and
Hubei LAB. The MOR and the local governments have reached agreements about
such issues as organizational institutions, compensation policies, population
resettlement, and compensation payment.
1.3 Measures for Minimizing Land Acquisition
and Housing Demolition
A remarkable revision has been made to the original design plan for the Capacity-
5
Expansion Project by the MOR based on the following considerations:
(1) Beijing-Guangzhou railway shall center on passenger transport while Beijing-
Kowloon on cargo transport. Thus Jing-Guang railway line shall be the mainstay in
China's north-south passenger transport at the end of this century and early next
century.
(2) "Electrification based on the current status " principle shall be applied in Wuhan-
Guangzhou rail line capacity expansion, which means except for a few railway stations,
railway yards and passenger service installations, the current railwvay installations shall
largely remain unaltered, without adding new tracks and extending the existing tracks to
the stations and the sections along the line.
(3) In principle, no new living facilities shall be constructed and the building of new
residential housing shall be strictly limited. The welfare residential housing shall be
built only sufficiently for the new recruits resulting from the expansion project.
(4) Technical renovation shall be minimized. Wherever it is necessary, it shall be
proved with sufficient sound grounds.
(5) No new water sources shall be built.
(6) The design for construction shall be optimized. The relation between land
acquisition and resettlement on the one hand and the engineering construction on the
other shall be tackled in an appropriate way, taking full advantage of slack farning
seasons and the breaks between rounds of crop growing, diminishing the impacts.
(7) Some sub-projects which are not necessary ones and have more difficulty and more
housing demolition were canceled in the second examination of the Project. For
example: the sub-project of Huadu engine back-tuming section, the sub-project of
6
Huadu train repairing section, the sub-project of Changsha passenger engine
maintenance yard, the sub-project of Liouyanghe linking line, the sub-project of Miluo
rail track increase and station reconstruction.
Compared wvith the original design plan, the revised one shows a considerable drop of
the land amount to be acquired, the housing to be demolished and the number of
persons to be affected. According to the original plan, a sum of 6582 mu of land
would be acquired along the line for the project as against only 3708.26 mu in the
revised plan, a decrease by 44%; 279467 m2 of housing would be demolished and
relocated as against 11365.64m2 in the revised plan, a decrease by 60%;.
According to the revised plan, the land acquisition will be concentrated on Wuhan
railway pivot, Changsha district, Zhuzhou pivot, Hengyang pivot and Guangzhou pivot
where the capacity expansion will focus on electrification engineering and its necessary
auxiliary engineering of facilities conceming communication, signal system and engine
maintenance sector, and the technical renovation engineering necessary for enhancing
the travelling speed of passenger train and the capability of ensuring its traverse, arrival
and departure.
1.4 Preparatory Work for Land Acquisition, Housing
Demolition and Relocation, Resettlement
(1) Circumscription of Land Acquisition
The project designing unit conducted explorations along the line for the project during
its technical design stage, surveying and circumscribing the land to be acquired and
housing to be demolished, working out the cross-sectional drawings of the rail line and
the drawings of housing. The land acquisition and housing scope maximally
circumnscribed at the technical design stage, can be more specified and diminished in
the actual implementation of land acquisition and housing demolition & relocation
7
according to the design of construction.
(2) Socioeconomic Survey
In order to make analyses of the impacts on the localities caused by the Project and
work out a practicable and feasible action plan, the 4th Surveying & Designing Institute,
entrusted by the MOR, collabourated with the Wuhan Engineering Headquarters of
Zhengzhou Railway Bureau and Zhuzhou Engineering Headquarters of Guangzhou
Railway Conglomerate Company in conducting a socioeconomic survey along Wuhan-
Guangzhou rail line. The joint survey squad, in close cooperation with the land
administration departments of Hubei, Hunan and Guangdong provinces, organized a
socioeconomic survey to Guangzhou, Hengyang, Zhuzhou, Changsha, Wuhan and their
subordinate districts and counties from May to Sept of 1998. A great amount of
valuable information was obtained by collecting various existing statistics, making on-
the-spot interviews and conducting sample investigation.The socioeconomic survey has
provided a sound base for mapping out the resettlement action plan.
(3) Investigation on the Project Impacts
In June 1998, ZRB and GRCC respectively entrusted the local government of various
levels in Hubei, Hunan and Guangdong to conduct on-the-spot investigations on the
various subprojects of the Project, conceming the land acquisition, the housing
demolition & relocation, the number of affected population, the labour resettlement,
infrastructure, above-ground attachment, etc. By investigating from village to village,
block to block and door to door, the investigation squads got to know in great detail the
damages caused by the project engineering.
(4) Consultation of the MOR and the Relevant Provinces
In May 1998, vice-minister Cai Qinghua of the MOR, director of Foreign Capital
Introduction & Utilization of the MOR and their party went to Hubei, Hunan and
Guangdong to interview the vice-govemors of these provinces who are responsible of
national key projects. They reached a consensus on the issues relating to land
S
acquisition, housing demolition and population resettlement, as well as the forming of
organizational institutions and the coordination between the MOR and the local
govermnents.
(5) Preparation of Population Resettlement Action Plan
The preparation of resettlement action plan (RAP) was entrusted by the project owner
to GRCC, ZRB and the 4h Surveying & Designing Institute of the MOR and joined by
the land administration departments of Hunan, Hubei and Guangdong provinces. The
project owner also invited specialists in resettlement from the Research Institute of
Foreign Capital Introduction & Utilization of SWJU as advisers for the project. All
the particinants in the drawing-up of RAP have successively finished the founding of
the resettlement institutions, the scope detennination of the project impacts, the
socioeconomic surveys, the investigation on the property damage, the study and analysis
of relevant policies and regulations, the consultation and decision of the resettlement
plan of affected population, and the compensation estimation calculation. Based on
the above work, the Resettlement Action Plan for the Electrification Capacity
Expansion Project of Wuhan-Guangzhou Railway was completed.
The following table shows the statistics of the land acquisition and housing demolition
along the Wu-Guang railway line.
9
Table the Statistics of the Land Acquisition and Housing
Demolition along the Wuguang Railway LineItem Unit Amount
Total area of the land acquired mu 3708.26Total area of cultivated land acquired mu 2397.72
Households affected directly by land acquisition household 3871Population affected directly by land acquisition person 16210Total area of houses demolished m2 113656.64
Private houses in rural m2 28321.45Private houses in urban m2 1033Housing of railway staff m2 13914.8Enterprise houses outside railway sector m2 7951.2Enterprise houses within railway sector m2 41951.52Shop houses outside railway sector m2 15899.6Shop houses within railway sector M.2 865.18Building illegal m2 3719.89Households affected by housing demolition household 435Population affected by housing demolition person 3309Enterprises affected by houses demolition one 40Shops affected by houses demolition room 29Reconstruction of roads Km 9.8Reconstruction of water conservancy pipes Km 204.48Reconstruction of communication cables Km 1082.41Reconstruction of power supply wire Km 67.44Young crops to be compensated mu 1449.08Trees to be compensated tree 104363Fruit trees to be compensated tree 4732Wells to be compensated one 15Tombs to be compensated one 81Concrete sunning ground to be compensated m2 2173Enclosures to be compensated m 2855
Total fees I0 thousandyuans 31842.61Fees for land acquisition 10 thousand yuans 11808.82Fees for houses demolition 10 thousand yuans 6813.88Fees for infrastructures 10 thousand yuans 9782.73Fees for aboveground attachments 10 thousand yuans 538.06Unforeseen fees 10 thousand yuans 1916.08Administration fees 10 thousand yuans 574.82Fees for writing RAP 10 thousand yuans 25Fees for external monitoring and evaluation 10 thousand yuans 383.22
10
2 Project Impacts
In the design of the capacity expansion engineering of Wuhan-Guangzhou rail line,
means have been tried as many as possible to minimize land acquisition by making full
use of the existing rail lines and facilities. Nevertheless, land, however limited, has to
be acquired and housing to be demolished, and some people to move away to a new
place. This is especially true with such pivot sub-projects as in Guangzhou, Hengyang,
Zhuzhou, Changsha and Wuhan.
2.1 Land Acquisition
(1) The Project will use 3708.26 mu of land, including 2397.72 mu cultivated land
and, with 16210 persons from 3871 households to be affected.
(2) The Project will use 1562.46 mu of land in the three big cities ( Guangzhou city,
Changsha city and Wuhan city ), and 2145.8 mu of land along the line in the three
province (Guangdong, Hubei, Hunan). Except for 1000 mu of waste land in Qingyan
city, only 1145.8 mu of land will be acquired along over 1000 Km of line in the three
provinces, only one mu of the land being acquired per Km.
(3) Land acquired are owned collectively, the land left after acquisition, therefore
allow of reallocation within the village, Except for the three big cities, namely
Guangzhou, Wuhan and ChangSha which may have troubles in land reallocation, the
other places along the line can handle the land for people affected by way of land
reallocation.
X All cities and counties along Wu-Guang line are comparatively developed rural
areas. The income from farming makes up low proportion in their total income. For
example, the income from farning of peasants on the suburb of Guangzhou taken up
less than 10% of their total income, that of Changsha taken up 20% of their total
income. So, it is possible to handle the production problem of people affected by way of
various means.
11
(5) The Project involves 100 mu of the land owned by the Railway and cultivated by
farmers. Though the consultation between the railway construction units and local
goverrnents , the same land compensation standards will be adopted with these land,
which means these land will be treated in compensation as land owned by collectives.
The following table is about the amount, types and places land acquired along Wu-
Guang line.
12
Aniount, Types and Places of Land to be acquired in Wuguang Line
Amount of Typs of landCity or land Vegetable Housing Nonculti Land Districts,
Provinces ountySubprojcts acquired Dry land ground vat-ed acquired villages(mu) paddy ponds s site land villages and towns
fieldHankou passenger Changmatao Qiaokou
trains 94 64 10 20 vlae dsrcmaintenance yard . v
Handan up- 318 132.88 138 37.5 9.7 1-lejiadon Jlianglhangoing line _ 318 132.88 village district
West jiangan 110 110 Lianchen Jianganstation l _ village district
Hubei Tuoluokou 46 46 Shazhui Dongxiliuprovince marshalling yard village district
Wuhan East Wuchang 27Biniu Hongshanpivot station 27 village district
Tracks 3 and 4 of Fenqi HongshanWuchiang station 45 40 village district
Wuhan W tcity Wuchang Jingang Hongshan
passenger trains 28 28maintenance yard village districtSouth Wuchang 58 50 8 Shenli Jiangxi
station village district
Zifang contact network 13.4 13.4 Qinlong Jiangxiasection, track garage . . village district
Wulongquan division 7.6 7.6 Xinnu Jiangxiasection . . village district
Heshengqiao network 10.55 10.55 Hezhansection track garage village Jiangxia
district
13
Heshengqiao haulage 13 13 Jianguotransformer substation _ _ village
Xiannin Xianniin network section, 16.56 15.55 1.01 Dongmen YonganHubei city division section, track garage _ village agency
1Iubei -Guantangyi haulage Guantang Guantangyi
Province transformer substation 12.32 12.32 village town
Puqi division section 3.3 3.3 GonganquanPuqi _____village
city Chibi station: technical 29.23 29.23 Wangjiabaorenovation, network section, village
Renovation 30.43 10 20.43
Hubei province total 862.39 446.7 138 184 62.5 31.14
Linxiang Linxiang network 11.1 11.1 Wuli village Changan
city section, division section 1 town
Yunxi network section 5.6 5.6
Hunan Yueyang north switching 8.3 8.3 Yunxi
province section 8.3 8.3 town
Yueyang network 10.2 10.2section, division section 10.2 10.2
Yucyang Fubin network section 5.5 5.5city.._
Fubin station 1.25 1.25 B3infu Meixi
Fubin track garage line 6 6 village town
Yueyang residential 15 15quarters
14
Rongjiawan network 12.2 12.2section 12.2_ 12 2 Rongfang Chenguan
Rongjiawan transformer 13.5 13.5 village townYueyang substation .county Rongjiawan track garage 6 6 Fufang Fangshajie
Rongjiawan residcntial 22.37 8.42 2.18 11.77 village townquarters
Milou network section 5.6 5.6 Caiyi ChenguanHunan ______village town Province Miliu transforner 15 15 Baizang Chenjiao
substation ________ ____ _village town
Taolin network section, The first Taolindivison setion13.2 13.2 resident tw
.division section committcc townMilou -cityu Taolin residential 3 Milou Chenjiaocity qures20.58 9.23 11.35 vlaetw
quarters .village town
Chuanshanpin division Dongi'ie Shanquan3.4 3.4 resident
section committee pin town
Gaojiafang network 5.8 5.8 resident Gaojiafangsection committee town
Wangce Qiaotaoyi transformer 16 16 Qiaotaoyi Qiaotaoyin county substation , village town
Yaoyi GaoqiaoChangsha station 4.36 4.36 village town
Changsha residential 104 104 Yaoyi dXilaopingquarters . village dea
area
15
Laodaohe network 102 102 Laodaohe Xiayinsection earth borrow area . village town
Liuyanghe emergency 61.91 11.98 33.93 16 Liuyanghe Xiayinproject .1 . village town
Changsha down-going 59.12 27.34 25.48 6.3 Huangju Mawangduipassenger train dispersin2 lines village townChangsha east network 9.1 9 Youyi Gaoqiaosection ,division section _ . . village district
Datuopu transformer 13.5 13.5 Datuo Datuosubstation . village town
Chang Muyun city network 12.2 12.2 Muyun MuyunHunan sha section 12. . village townProvince Baimalong division 3Baima Baimalong
section 3.05 3.05 village town
Zhuzhou pivot 54.2 21.48 26.62 4.76 1.34 Dachong________ ________ ________village Hehua
._ _ehua townZhuzhou Xiangqian ushering line 68.2 40.2 7.6 6.7 10.5 3.2 village
city Zhuzhou residential 37 37 Tianxin Tianxinquarters village office
Laoguanzhong earth 46 46 Jiaojdilin Longtaopuborrow area committee town
Lukao network section, 10.7 10.7 Lukou Lukoudivision section 10.7_10_ village town
Jintian network section 10.2 10.2Zhuzhou _____ ____Linfu Jintian
county Jintian transformer 17.5 17.5 village townsubstation . . . .
Zlutin network section, 10 3 6.8 Chunshi Huangiondivision section 103268village g towvn
16
Henshan network section 6.6 6.6 Aoyanghai Xintang
Henshan transformer 16 16 village townIlendong substationcounty Xinxialiu division 4.4 4.4 Dashansi Xiayuan
section village town
Dapuwci network section 12.9 12.9 Dasiansi Xiayuan.__.__._ village town
Henyang pivot 69 69 1-leping Hepingvillage country
Henyang power supply 7.57 4.28 3.29 HepingHenyang section village Heping
Hunan city Henbai transformer 9.51 6.22 0.24 3.05 Xinlaua countryProvince substation village
Dongyangdu transformer 18.59 5.23 7.06 6.3 Qinhe Dongyangsubstation 1 . 6 village country
. . ~~~~~~~~~~~~~Wayuan LiutianHelnan Henyuan division section 2.34 21 0.24 villaye townn
Laiyang transforner 12.54 7.24 5.3 Nanlin ZhoushiL.iyang substation ._._._village officc
Laiyang Gongpinxu division 2.68 2.68 Gongping Gongpingxu
section village village
Yongxin Matianxu transformer 16.11 16.11 Matianxu Qiaozhuansubstation . 16.11 village town
Xujiadong track garage 9.03 2.68 6.35 Xujiadong Kuisliuline village town
Ceng Kuaishuxia KuishuZhou Cengzhou station 29 29 village towncounty Aoshang Kuishu
Jiedong division section 8.68 3.32 1.5 0.5 3.36 village town
17
Hunan province total 1051.09 174.83 559.71 88.79 13.55 214.21
Guang Lechang Pingshibai division 1.46 1.46 Pnsiai Ping |dong section 1.6____ ____ village town
province Shao Shaoguan station 28 28 town Sdiastriuctn
city Shaoguan passing yard 173.7 83.5 55.2 35 Leyun Sditictn
Shanzibei division Shanzibai Donghuasection 3.3 village town
Qujiang Donghuayua DonghuaCojuntnyg Maba network section 14.15 14.15 nge town
Wushi transforner Wushi Donghua
substation village townHetao Shakao
Heto network section 13.26 0.72 12.54 village town
Yingde Yinde station 13.22 13.22 Shanglhe Shakao
City village town
Shahekao division section, 17.55 17.55 Dongguapu Shakao
transformer substation . village town
Lianjiangkao transformcr 49.86 6.4 38.06 5.4 Zidong Lianjiantgk
substation, network section . village ou town
Jiaohenshi division Ximen Lianjianko
Qinyuan section 1.38 1.38 village town
City Shubuotang LianjiankoPajiangkou quarry 1005.7 0.9 4.8 10 00 vlgetw
Yuantan LianjiankoTanyuan network section 21.97 21.97 vuaga district
I I ~~~~~~~~ ~~~~~~~~~~~~~~~~village district
Shanhua ShanhuaHuadu station 7.4 7.4 village town
Huadu18
Juntian division section 1.9 1.9 Juntian Shanhua. j_village town
Guangzhou 81.4 80.48 0.92 Jianggao Baiyunnorth station 8.804092town district
Baiyun3uangdong Dalang station 76.6 55.6 21 Shijin town districtrovince .Baiyun
Tangxi station 74.14 54.02 20.12 Shijin town district
Guang Guang Thengbi-xin 138.18 75.57 23.7 16.4 2.48 20.03 Jianggao town Baiyufn
zhou zhou Guan.bai-tangxi shijin town districtCity pivot Guangzhou north
haulage transformer 14. 7 14. 7substation,
division section ._._l
Tangxi switching 13. 7 13. 7section .
Baiyunshan 33 33______ __ network section
Guangdong total 1794.78 506.14 155.13 7.4 57.52 3. 4 1065.19
Total 3708.26 1127.62 852.94 280.19 71.07 65.9 1310.54
19
2.2 Housing Demolition & Relocation
(1) After the original design for the Capacity Expansion Project was revised on the
principle of "electrification based on the current conditions", the housing demolition
demand of the project has decreased drastically and has been highly concentrated on
such major subprojects as Guanzhou pivot, Wuhan pivot, Changsha pivot, Zhuzhou
pivot and Hengyang pivot--especially Changsha Pivot. In order to alleviate pressure of
passenger transportation, the MOR has decided to have Changsha passenger station
expanded. As a result, Shangsha Station is protrude as a convergence of housing
demolition.
(2) The affected population who will lost the whole or part of their housing is 618
persons from 167 households. Except for 5 urban households, the others are farners.
The existing housing is improperly set with sanitary conditions poor and building
construction rough.
(3) Besides private housing, 35 enterprises and shops need to be demolished and
illegal buildings owned by 9 households does so. The illegal buildings were temporarily
built by the jobbing peasants from other places when they were employed in Wuhan.
(4) Among the features of the demolition along Wu-Guang line is that demolition
within the railway sector takes up the half of the whole demolition. In other words,
there are 256 households with 783 population and 34 enterprises within the railway
sector to be demolished, in addition to 3 illegal buildings owned by railway staff and
workers to be demolished.
The following table is about the housing demolition outside and within the railway
sector along Wu-Guang line.
20
Demolition outside and within the Railway Sector along Wu-Guang Line
Amount and structure of Amount and structure of Amount and structure of Amount and structure of Amount and structure ofenterprises to be demolished shops to be demolished illepl buildings to be private housing to be private housing to be
tem (Square meter) (Square meter) demolished (Square demolished in city area demolished in rural ares Total\_________ meter) (S_ uare meteL (Si usre meter) (Square
Plsce Brick Brick Simple Brick Brick Simple Brick Brick Simple Brick Brick Simple Brick Brick Simple meter)and and and and and and and and and and
concrete wood concrete wood concrete wood concrete wood concrete wood
Chang 1654.9 975.4 2577.2 1254 868 711.62 363.38 673 9077. zhou
Yinde 55.9 626.1 226.4 443.6 1352
Demolition Heng 225.3 579.4 3595.6 4400.3outside thc yang
railway Chang 1610 12856 478 4926.0o 19870.08sector shan
sha
Zhu 4042.72 2570. 592.26 7205. 37zhou 39
Wu 3500 1033 2610 7657 14800han
Tota 3320.8 1826. 2803.6 14553.6 1346 3500 1033 12869.82 14186. 1265. 56705.251 37 26
Demolition Guang 2614.64 s33 334.52 145.6s 74.21 100.57 295.92 15.17 4413. 71within the zhourailwaysector Shso 160 160
gua
Chang 10696. 8 4674 865.18 9543.24 735 26514.22sha
21
Xian 2433.56 3224. 9 5658. 46
fin
Pu 1175 1175
IDI4 19030 19030hbn
36110 5507 334.52 865. 18 145.68 74.21 12868.71 1030. 15.17 56951.39Total 92
Grandtotal 39430.2 7333. 3138. 15418.78 1346 145.68 3574. 13901.71 1030. 15. 17 12869.82 14186. 1265. 113656.2 12 21 92 37 26 64
22
2.3 Aboveground attachment
The aboveground attachment involved include young crops, trees, fruit trees, wells,
tombs, concrete sunning ground and enclosure. All kinds of the aboveground
attachments were counted on the spot and evaluated. Compensation for land acquired
does not contain the compensation for the aboveground attachments except for young
crops. The compensation for the aboveground attachment will be calculated in other
way.
The following table shows the aboveground attachments to be affected.
23
Aboveground Attachment of Wuguang Line
City Land acquired Young Sunning Enclosure
Provinces county Sub-projects villages crops Trees tree Well Grave groundcounty ~~~~~~~~~~~~(mu) tre(m2) (n
HankouHubei Wuha passenger trains Changmate 10 89900 650
province n city maintenance Villageyard
Handan up- Liangcheng 271 2632 71 681
going line Vollage
West jiangan HejiatunstationVilg
Tuoluokou
Wuhan marshalling Shazlhui Village 46 100 s
pivot yardEast wuchang Hubing Village 27
station
Tracks 3 and 4~ Hongqi Village 4 0of wuchangd Zhiyang Village 40 100 5
station___ ___
Wuchangpassenger trains Jinggan Village 28
maintenanceyard
South wuchang Shengli Village 50station
24
Zifang contact network Qinlong village 13.4 20station,track garage
Wulongquan division Xinnu village 7.6 10section
Hubei Heshengqiao network Hezhan village 10.55 15Province setion,track garage
Heshengqiao haulage Jianguo village 13transformer substation __ _ __
Xianni Xiannin network DongmenXncity setion,division setion,track village 15.55
garage .Guantangyi haulage Guantang 12.32
transformer substation village
Puqi division section Gonganquan 3.3PPuqi uvillagecity Chibi station: technical Wangjiabao
renovation,network villagesection,track garage
renovation Quhong village 10 460 ____ _ _
Hubei province total 557.72 90605 2632 5 71 1331
Linxiang Linxiang network Wuli village 11.1city section,division section
Yueyang Yunxi network section 5.6
city Yueyang north switchingllunan section
province Yueyang networksection,division section .Fubin network section Binfu village 4
25
Fubin station .
Fubin track garage line 6
Yueyang residentialquarters
Rongiawan network Rongfang 12.2section village
Yueyang Rongjiawan transformercuentg substationcounty Rongjiawan track garage Fufang village
Hunan Rongjiawan residential 8.42 260 1 300Province quarters
Milou network section Caiyi village 5.6 .
Miliu transformer Baizang villagesubstation
The firstTaolin network section, resident 13.2
division section ccommittee :.. .
Milou Taolin residential Milou village 9.23 180 1 180City quarters 9.3______
DonglieChuanshanpin division resident
section comitcommittee
Gaojiafang network The secondsao)lafang netior resident 5.8section committee
Waenngch Qiaotaoyi transformer Qiaotaoyi
substation villagecounty
26
Changsha station Yaoyi village 4.36
Changsha residential Yaoyi village 40quarters
Laodaohe network Laodaohe 6.2 110 19section earth borrow area village
Changsh Liuyanghe emergency Liuyanghe 11.98 20 105
a city project villageChangsha down-going Huangju village
Hunan passenger train 15 201 1dispersing lines
province Changsha east network Youyi village .
section ,division sectionDatuopu transfonner Datuo village 13.5
substation .changsh Muyun city network Muyun
a section village
Baimalong division Baima village 305section 3_05
Zhuzhou pivot Dachong 48 18 50_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _v illage _ _ _ _ __ _ _ _ _ _ _
Xianggianushering line Hehua village 22 2160 1440 150 300
Zhuzhoucity Zhuzhou residential Tianxin village 17
quartersJiaojilin
Laoguanzhong earth residents'borrow area committee
27
Jintian transformer 17. 5substation __.
Zhutin network Chunshi villagesection,division section ._._.
Hlenshan network section Aoyangiai 6. 6_____ _____ _____ ___ - v illag e_ _ _ _ __ _ _ _ _ __ _ _ _ _
Henshan transformerHendong substationcounty Xinxialiu division Dashansi
section village
Dapuwei network section Dashansi 5. 5Hunan . village .
province Henyang pivot Heping village 22 . .
Henyang power supply Heping village 7.57
Heyagsection. .Henyang Henbei transformer Xinhua village 6. 22'
substation . .
Dongyangdu transformer Qinhe village 10 2
substation 1Hlennan Wuyuan division section Wayuan village .
Laiyang transformer Nanlin villagesubstaion __ _
Laiyang Gongpinxu division Gongping 2.68section village 2
Yongxin Matianxu transformer Matianxu 16. Itsubstation village 16.___
Xujiadong track garage Xujiadong 145
Chcnzhou line villagecounty
28
Chenzho staKuaishuxiaChenzhou station village
Chenzhiou Jiedong division section Aoshang 4. 82 22 138county village
Hnan province total 407. 24 3116 1459 4 2 518 705
Guangdo Lechang Pingshibai division Pingshibaing section village
province Shaoguan Shaoguan station Leyuan town 28city Shaoguan passing yard Leyuan town 112 420 26 1 4
Shanzibei division Shanzibaisection village 36
Qujiang Maba network section Donihuayuan 14. 15County village
Wushi transformer Wushi village 10.21 1substation
lHetao network section Hetao village 12 44
Yinde station Shanghe village 13. 22 500 2 1050Yingde Shahekao division Dongguapu
CitY section, transformer village 145 80
substation .Lianjiangkao transformer Lidongvillage 20 60 1
substation, network section ._._._.Qinyuan Jiaohenshi division Ximen village
Qciyuan section
Cit | L Pajiangkou quarry Shubuotang 5.7 8600Pajiangkou quarryvillage 80
Tanyuan network section Yuantan village 21. 97
29
Huadu station Shanhua villageJuntian division section Juntian village 1. 9 2
Guangzhou Jianggao 15 1 205 300
north station township
Dalang station Shijin 20uD township
Tangxi station Shijin 400
_____ _ 5township 6
0 s Guang The third line of
Guangzhou Guang Guangbai- Jianggao tangxi 99. 27 1381 115 395City zhou Tangxi township
pivot .Guangzhou north Jianggao
transforner township 14.7
substation . .
Tangxi swithing Shijin 2
section township .
Beiyunshan Wangshentang 33network section
Guangdong province total 484.12 10642 641 6 8 1655 819
Total of the whole line 1449.08 104363 4732 15 81 2173 2855
30
2.4 Infrastructure Affected
Infiastructure affected include road reconstruction, water conservancy pipes,
communication cables and power supply cables. Main roads, simple roads in
countzyside, irrigation canal, drink eater pipes, cables and electric wires will be
rehabilitated by railway construction units according to their respective class and
quantity.
The following table shows the infrastructure rehabilitation along Wu-Guang line.
31
Infrastructure Reconstruction in Wu-guang line
\ Project Road reconstuction Water conservancy pipe Conmmurication Power reconstructionProject ~~~~~~~~~~~~~~~reconstruction Money in total
(Ten (Ten thousandPlace (km) (Ten thousand (kIn) (Ten thousand (hIn) (Ten thousand (km) thousand Yuan)
yuan) yuan) yuan) Y )
Guangzhou pivot 2. 78 219 2. 35 200. 0 245. 86 1784. 47 33. 24 24. 65 2048. 12
Hiengyang City 1. 72 123 1. 53 10. 5 124. 2 901. 15 11. 16 8. 4 1043. 05
Zhuzhou City 0. 36 9 3. 76 24. 8 23. 6 212. 4 246. 2
Changsha City 11. 29 92.4 13. 6 122. 4 214. 8
Wuhan pivot 1. 42 109 4. 76 39. 48 37. 3 335. 7 484. 18
The section between Hen-guang
except Hengyang city and 2. 7 188 2. 62 17. 3 157. 75 1143. 08 23. 04 22. 1 1370. 48
Guangzhou city
The section between Wu-Hen 0. 82 55 480. 1 4320. 9 4375. 9
except Wuhan city and Hengyang
city
Total 9. 8 703 26. 31 204. 48 1082. 41 8820. 1 67. 44 55. 15 9782. 73
32
2.5 Analysis of Project Impacts
The impacts resulting from the land acquisition and housing demolition for the
Capacity Expansion in Wuhan-Guangzhou Railway Line fall into three types:
(1) Impacts along the Line
Because of the application of "electrification based on existing facilities", there are
almost no projects along the line, no extension of rails nor widening of tracks, except
for some minor auxiliary projects involving very little land acquisition, averaging Is
than one mu every square km with a population affected, averaging less than one person
every square km. So the project can produce little impact along the line. The affected
villages can re-arrange the production and livelihood of the affected individuals by
reallocating land, which means there is no surplus laborer to be resettled.
(2) Impacts at the Pivots
As the land acquisition for the Expansion Project is converged at such major pivot areas
as Guangzhou, Hengyang, Zhuzhou, Changsha and Wuhan, a considerable amount of
land acquisition will result in a considerable amount of housing demolition in those
areas. The affected areas are either prosperous cities or comparatively prosperous
urban-rural junctions. The magnitude of land acquisition in the city suburbs is bound
to aggravate the problem of more population with less land, this is especially true of the
extra-large cities like Guangzhou, Changshs and Wuhan., along with urbanization and
modemization, which have caused a rapid diminution of cultivated land,. However, the
economic mainstay of those areas is no longer agricultual production. The income
from farming counts only 10% of the entire income in those areas. Therefore,
although land acquisition can generate grave impact on the local income from
agriculture, its impact on the total income of those areas is comparatively slight
Moreover, the local township enterprises and secondary and tertiary industries may
provide means of life and employment chances for the affected people.
(3) Impacts on the railway sector
33
The Capacity-Expansion Project of Wu-Guan Railing involves more than 50000 square
meter of housing, tens of shops, hundreds of the railway worker's housing to be
demolished. Particularly in Changsha and Xiannin , the People involved are
comparatively more, and demolition extends wide. The Ministry of Railway makes use
of the land of its own to handle employment and residence of affected people with the
Railway sector, moreover, these affected people from the places involved mass
demolition are resettled through purchasing a mass of Commercial apartments for them.
So no laborer will lose his job.
For detailed date of the impacts from the land acquired and housing demolition along
Wu-Guang line, see the following table:
34
Impacts of the Land Acquired and Housing Demolition in Wu-Guang Line
Item Unit Total Guangdong Hunan HubeiGuang Other Chang Other Wu Other__________ zhou sections sha sections han sections
I. Impacts of land acquiredI, Total area of landacquired Mu 3708. 26 431. 72 1363. 06 360. 19 690. 9 770. 55 91. 84
2. Areaofcultivatedlandacquired Mu 2397. 72 411. 69 317. 9 235. 89 600. 99 760. 85 70. 4
3. Households affected directly 3871 1109 602 465 469 1169 574. population affected directly Person 16210 4940 2606 1533 1866 5026 239
5. Proportionofcultivatedlandacquiredtothe % 2. 5 0. 4 1. 32 0. 56 2. 45 0. 2total cultivated land in affected area6. Average cultivated land acquired in affected mu 0.04 0.28 0.33 0.39 0.27 0.46
area per capita ._._.
7. Average cultivated land in affected area per mu 0. 12 0. 92 o. 89 1. 14 0. 76 1. 3capita _,....
8.. Average income of affected area Yuan/ 750 458 338 175 335 194month704533173319
9. Proportion of the income from farming to the % 10 45 20 70 15 68total income
II. Impacts of demolition
(i) Total area of demolition Square 113656.64 9077. 5 1352 19870.08 11605.67 14800______________________________ ______________ meter
I, Rural private housing Square 28321. 45 1748 4926. 08 11380. 37 10267_ _ _ __meter . _
2.. Urban private housing Square 1033 1033meter .
3. Housing of the railway staff and workers Square 13914. 8 411. 66 10278.24 3224. 9
35
4. Enterprises outside the railway sector Square 7951. 2 5207. 5 908. 4 1610___________________________________ meter _____
5. Enterprises within the railway sector Square 41951. 52 3782. 16 160 15370. 8 19030 3608. 56meter .
6, Shops outside the railway sector Square 15899. 6 2122 443. 6 13334meter _____
7, Shops within the railway sector Square 865. 18 865. 18___________________________________________ meter
8, Illegal buildings Square 3719. 89 219. 89 3500_____________________________________________ meter _________.
(OiiD) The total number of households with the 435housing demolition
I,. Household with rural private housing 162 9 24 68 61
2. Household with urban private housing 5 5
3.. Household with rural private housing 256 5 198 53
4.Household with housing in the railway sector 12 3 9
(iii).. Enterprises affected 40
I Enterprises outside the railway sector 12 8 2 1 12, Enterprises within the railway sector 28 7 1 10 5 5(iv) Shop affected 29I,. Shops outside the railway sector 23 16 2 5
2. Shops within the railway sector 6 6
(v) Population affected person 3309
1.. Population with rural private housing person 598 35 96 243 224
2. Population with urban private housing person 20 203.. Population with housing of railway staff and person 783 23 595 165
workers - -
4. Population with illegal buildings person 42 11 315' Employees of enterprises outside the railway person 420 289 60 36 35
36
sector -6, Employees of enterprises within the railway person 1012 231 25 410 185 161
sector .__7, Employees of shops outside the railway person 399 94 10 295
sector8, Employees of shops within the railway person 35 35
sector A_._.__.__._
(vi) average residential housing floorage Square 34. 35per capita meter1, rural average residential housing floorage Square 47. 36 49. 94 51. 31 46. 83 45. 83per capita meter2, urban average residential housing floorage Square 51. 65 51. 65per capita meter3, average residential housing floorage per Square 17. 77 17. 9 17. 27 19. 54
railway staff and worker meter(vii) size of enterprise and shops1I medium-sized enterprise within the railway
sector2, medium-sized enterprise within the railway 3 1 1
sector3, small enterprise within the railway sector 12 8 2 1 l
4, small enterprise outside the railway sector 25 6 1 9 4 55 medium-size shops outside the railway 5 5
sector .6, medium-size shops outside the railway
sector .7, small shops outside the railway sector. 18 16 28. small shops within the railway sector_ _ 6 6
37
3 Law Framework
In China, policies, laws and regulations conceming land acquisition and population
resettlement fall into a four-level hierarchy: at the top level are the fundamental polices,
laws and regulations stipulated and issued by the central government; at the second
level are the detailed implementation methods issued by provincial governments for the
motional regulations; at the third level are the specific policies and regulations by
municipal and county governments feasible in the localities and at the lowest level are
the preferential policies specifically stipulated by local governnents for a certain
project.
3.1 Policies, Laws and Regulations as the Basis
The following are the major policies, laws and regulations for the land acquisition and
resettlement of the Project to go by:
(1) "Land Administration Law of the People's Republic of China" (issued in June 1986
and revised in 1988).
(2) "Implementation Methods for the 'Land Administration Law 'of the People's
Republic of China".
(3) "China Regulations for Urban Housing Demolition & Relocation" (1991).
(4) "Guangdong Provincial Implementation Methods for the 'Land Administration Law
of China"'(July 1991).
(5) "Guangdong Provincial Regulations for Urban Housing Demolition & Relocation"
(1993)
(6) "Land Administration Regulations of Guangzhou City" (Dec. 1991).
(7) "Guangzhou Municipal Implementation Regulations for the Administration of
Urban Housing Demolition and Relocation" (Jan. 1992)
(8) "Hunan Provincial Implementation Methods for the 'Land Administration Law of
China"'(April 1992)
(9) "Hunan Provincial Detailed Implementation Regulations for the Administration of
38
Urban Housing Demolition & Relocation" (Oct. 1993).
(10) "Changsha Municipal Compensation and Resettlement Methods for the Land
Acquisition for State Construction" (Dec. 1991)
(I1) "Changsha Municipal Implementation Regulations for the Administration of Urban
Housing Demolition & Relocation" (Dec.1991)
(12)"Hubei Provincial Detailed Implementation Methods for the 'Land Administration
Law of China"' (March 1994)
(13) "Wuhan Municipal Compensation and Resettlement Methods for the Land
Acquisition for State Construction" (March 1994)
(14) "Wuhan Municipal Implementation Regulations for the Administration of Urban
Housing Demolition & Relocation" (March 1991)
3.2 Provisions of Policies and Laws
3.2.1 Relevant Regulations for Land Acquisition
(1) The urban land is owned by the state. The rural land is owned by the collective
except for that portion owned by the state according to relevant legal provisions. The
housing ground site, household reserved plots and hills are owned by the collective.
(2) In order to acquire land for state construction, the construction unit shall, after
obtaining relevant legal documents ratified by the responsible department of the State
Council or local governments at or above county level according to the relevant
regulations of the state, put in an application to the land administration departments at
or above county level for procedure handling for land acquisition.
(3) In the case of the land acquisition for state construction, the land utilizing unit shall
pay land compensation fee, resettlement subsidy and compensation for above-ground
attachment and young crops at the standards decided on in each province by referring to
national land administration laws and taking the local reality into consideration.
(4) The following are the general regulations of Guangdong, Hunan and Hubei
39
Provinces for land compensation:
A. In the acquisition of cultivated land, the compensation rate is 6 times the value of
the annual average output in the past three years prior to the land acquisition.
B. In the acquisition of such land as fish ponds and orchards, the compensation rate is
5 times the value of the annual average output in the past three years prior to the
land acquisition.
C. In the acquisition of such land as barren hilly land and shoals, the land shall be seen
as value-yielding and the compensation rate is 3 times the value of the annual
average output in the past three years prior to the land acquisition.
D. In the acquisition of housing ground site, the compensation rate is the same as that
for the neighboring cultivated land.
E. The compensation rate for young crops and above-ground attachment is the value
of one crop yield.
(5) The following are the general regulations of Guangdong, Hunan and Hubei
Provinces for resettlement compensation:
A. For the land expropriated unit whose cultivated land possession averages more than
one mu per capita before the land acquisition, the resettlement subsidy is 3 times
the value of the annual average output per mu in the past three years before the land
acquisition.
B. For the land expropriated unit whose cultivated land possession averages less than
one mu per capita before the land acquisition, the resettlement subsidy is 4 times
the value of the annual average output per mu in the past three years before the land
acquisition.
C. With every drop in average cultivated land possession by 0.1 mu per capita, the
resettlement subsidy shall accordingly rise one time the value of the annual average
output. But the maximum of resettlement subsidy shall be 10 times the value of
the annual average output.
D. If the above-stated compensation rates are still insufficient for the affected villagers
to maintain their former living standards, more subsidy can be added with the
approval of provincial govemments. But the sum of land compensation fee and40
resettlement subsidy shall not exceed the maximum of 20 times the value of the
annual average output of the land in the past three years before the land acquisition.
(6) The following are the general regulations of Guangdong, Hunan and Hubei
Provinces for labourer resettlement:
A. If the land expropriated unit has been acquired of all its land, or the village
production group has been left a land possession less than 0.1 mu per capita after
land acquisition, their agricultural residential registration can be converted into
non-agricultural one.
B. The surplus labour force resulting from the land acquisition for state construction
shall be resettled by the land administration departments of governments at or
above county level and township governments through either developing fanning of
sideline production or starting township industry or seeking some other ways.
(7) The following are the general regulations of Guangdong, Hunan and Hubei
Provinces for the use of compensation fees.
All sorts of compensation fees and resettlement subsidy disbursed for the land
acquisition for state construction shall be handled, except for the attachment
compensation and young crops compensation which are bound to go to the affected
individuals, by the govemments at or above county level through consultation with the
townships concerned, to be used for the land expropriated unit to develop production,
arrange jobs for the surplus labour force and allot allowance to those ineligible for
employment as their living expenses. These compensation fees shall not be detained
or diverted to any other purposes by any units or individuals.
3.2.2 Relevant Regulations for Housing Demolition and Relocation
(1) General Regulations for Management of Housing Demolition and Relocation.
A. After the administration department responsible of housing demolition & relocation
has checked and issued the license for demolition, it should publicize the relevant41
policies, formality procedure, resettlement plan and compensation rates for the
public to supervise the whole matter.
B. During the time limit set by the department concemed, the demolisher and the
demolished shall sign written agreement indicating unmistakably the scope of
demolition, the time of demolition, the payment of compensation and the
compensation sum, the resettlement housing area and location, the transitional
mode and the compensation for the transitional period.
C. In case the demolisher and the demolished have different opinions and can not
reach an agreement even through negotiation, the dispute shall be submitted to the
departnent issuing the license for arbitration.
D. If any one side in the dispute refuses to accept the arbitrate award, he can appeal
the case to the court within 15 days after he receives the award.
(2) General Regulations for Compensation of Housing Demolition & Relocation:
A. With the housing set up and tom down by the owner himself, it shall be
compensated at its reconstruction price.
B. If the area of the compensated new housing is within 2.5 times that of the
demolished one and falIs short of the urban per capita floorage standard, the excess
area of the new housing as compared with the old housing shall be paid for by the
house owner at construction cost price of its built-up area.
C. If the area of the compensated new housing is more than 2.5 times that of the
demolished one and exceeds the urban per-capita floorage standard, the area
exceeding the per-capita standard shall be paid for by the house owner at the
commodity price of its built-up area.
D. In the demolition of public housing, the residential part shall be compensated with
resettlement housing; the non-residential part shall be compensated according to
the original housing area.
E. In the demolition of housing and structure of public welfare nature and its
attachment, the demolisher shall reconstruct it, at the exact size and after the exact
nature, in conformity with the city's layout planning. Or the demolisher may
compensate it at its reconstuction price. The compensation shall also be used for
public welfare purposes.42
(3) General Regulations for Resettlement in Housing Demolition & Relocation.
A. The house user of the housing to be demolished refers to the resident who has the
legal residential registration and has actually been living in that house, or the office,
organization, enterprise or institution that either has the business license and has
started its business in that housing or takes it as its regular working place.
B. In the demolition of private residential housing, the demolisher shall resettle the
demolished by referring to the latter's former floor space. If the per-capita
floorage of the demolished is not up to the lowest urban standard, he shall be
resettled at the lowest urban standard.
C. If the demolished is removed from the city center in resettlement, his resettlement
floorage may be added, according to the different location of the resettlement site,
maximally by 50% of his former floorage.
D. For a temporaly removal of the demolished, the demolisher shall pay him the
transitional fee and fee for a second removal based on the standards stipulated by
the municipal land administration departnent.
E In the demolition of industrial and commercial housing, the demolisher shall, in the
event of no temporary resettlement housing for the demolisher or a break-off in
business or regular work because of removal, compensate the demolished by the
month according to the monthly average profit or salary on the part of the
demolished of one year prior to the announcement of housing demolition &
relocation, from the day of business cessation to the month when the demolished is
removed back to the resettlement housing.
F. If the industrial and commercial housing is relocated and the relocation is sure to
cause business loss, the demolisher shall make a lump-sum compensation to the
demolisher according to the actual conditions.
G. In the demolition of cereal shops, coal shops, post offices and public conveniences,
resettlement shall go before demolition.
43
3.3 Preferential Policies Specfically Stipulated for
the Project of Wu-Guang Line
The Capacity-Expansion engineering in Wu-Guang railway section is profoundly
significant in that it can raise the railway transport capacity of Guangdong, Hunan and
Hubei provinces, improve the investment environment of the three provinces, accelerate
the refonn and opening to the outside world and boost the economic development of the
three provinces. Some specific preferential policies have been made in each of the
three provinces, different in minor points but the same in essentials, for the purpose of
rendering support to the project engineering. Take Document No. 13(1993) of Hunan.
Provincial Government for example. There are some actual measures taken by the
local government to show its support to railway construction:
(1) According to the document, the Provincial Land Administration Bureau will be the
general contractor, the prefecture, municipal and county govenmments will be the
subcontractors;
(2) The land compensation and resettlement subsidy will conform the lowest times of
the Hunan Implementation Methods for Land Administration.
(3) Development fund for fish pond and vegetable plot, fee for auxiliazy projects to
urban construction, labour fee, fee for city layout planning and designing, post
installation fee and construction fund for traffic facilities will be exempted
unexceptionally at provincial, prefecture, municipal and count levels;
(4) Any additional fees claimed by townships and villages shall be exempted;
3.4 The Concord of the Reseftlement Policies
between the World Bank and China
44
(1) The General Policies and Goals Set Out by the World Bank
The major principles advocated by the Bank on population resettlement can be boiled
down into the following two: First, try the best to minimize the amount of land to be
acquired, housing to be demolished and the number of population to be affected by
comparing and appraising alternative resettlement action plans and adjusting the design
plans; second, try the best to handle the resettlement of the affected population if land
acquisition and housing demolition is inevitable, and at least to ensure the affected
population a living standard not lower than that before the land acquisition and further
to enable them to enjoy a better living standard by benefiting from the project.
Such principles of the Bank's can be expounded in the following ways:
A. All the alternative plans should be taken into consideration for the purpose of
avoiding or minimizing land acquisition, housing demolition and the number of
affected population.
B. If population displacement is inevitable; resettlement action plans should be
prepared at the initial stage of engineering preparation.
C. The affected population should receive the compensation sufficient enough to make
up for their loss before their actual removal.
D. The affected population should get help during their removal and transitional
period.
E. The affected population should have means of life and chances of getting better-off.
There should be resettlement policies and plans whereby the production and
livelihood of the resettlers can be rehabilitated.
F. The affected population should be encouraged to take an active part in the whole
process of the planning and conducting of resettlement Appropriate forms of
mass participation should be sought for and the conduit for grievance appealing
established.
G. The immigrants should become identical economically and socially with the native
residents of the resettlement area.
H. Special concern should be shown to the vulnerable group by giving them more
help. 45
(2) High Concord of China's Policies with the Requirements of the Bank
The current polices and regulations regarding population displacement caused by
project engineering are unanimous with the Bank's goal for migrant resettlement, which
can be illustrated by the resettlement of four types of affected population in the project:
Type 1: urban or rural population affected in residential housing demolition
All the regulations concerning housing demolition issued by the provinces concerned
are meant to ensure the affected population at least a recovery of their former living
standard. According to such regulations, the floorage of the resettlement housing shall
not be less than that of the fonner one; the compensation to all sorts of housing shall be
calculated according to the reconstruction cost; compensation shall be disbursed before
demolition; favorable policies shall be offered to the vulnerable group who are very
poor and suffering from difficult housing condition (if their floorage is below the lowest
average urban floorage standard, the gap shall be mad up; the solitary old folks will be
resettled at the same standard as the one for a couple)
Type 2: enterprises and their employees affected in industrial and commercial housing
demolition
All the regulations concerned are intended to protect the interests of industrial and
commercial enterprises from being impaired. According to such regulations,
enterprises and shops shall be compensated at reconstruction cost price.
Compensation shall also be paid for the loss caused by a cessation of production or
business, the cost of moving out and business doing in other place.
Type 3: villages and villagers affected in rural land acquisition
The detailed implementation metiods of land administration by the provinces
concemed prescribe the minimal and maximal sums of compensation for land
compensation. Whenever possible, compensation should be made by land exchange in46
order to diminish resettlement risk.
Type 4: proprietary right owners and the residents affected in the demolition of
infrastructure
Each province concemed has specific regulations for the infrastructure land acquisition.
According the regulations, infrastructure can be demolished only after it is
reconstructed at the same size elsewhere.
47
4 Compensation Fees
The fee for the land acquisition, housing demolition and resettlement in the Capacity
Expansion Project of Wuhan-Guangzhou railway line, as art of the total budget of the
project, shall be disbursed by the MOR (the project owner). The support from local
governments is manifested in the favorable policies to reduce or exempt various taxes.
4.1 Principles for Compensation
(1) Compensation for land acquisition and housing demolition will be paid in
accordance with "Land Administration Law", and "Housing Demolition Regulation"
issued by the state and the detailed implementation regulations issued by the localities
that are consistent with terms of this RAP, and the relevant regulations of the RAP.
(2) Replacement cost is the criterion whereby to determine whether the compensation
standard is reasonable
(3)Whether the affected population is ensured a recovery of its former
living standard in the shortest possible time is the criterion to judge the compensation
standards in terms of sufficiency.
42 Contents and Standards of Compensation
4.2.1 Compensation Contents
(I) compensation for land acquisition
A Land compensation fee
B Resettlement subsidy
C Young crops compensation
D. Fees to be paid to the provincial and municipal governments such as
agricultural development fund for key items, development find for new regrettable plots
48
and cultivated land utilization tax is all exempted.
(2) compensation for housing demolition
A housing compensation
B compensation for transitional period
C compensation for removing
D Compensation for work and production held up
E Compensation for illegal buildings
(3) Compensation for aboveground attachment
A. Compensation for trees
B. Compensation for fruit trees
C. Compensation for wells
D. Compensation for tombs
E. Compensation for Sunning concrete ground
F. Compensation for enclosure
(4) Compensation for infrastructure
A. Compensation for road removed
B. Compensation for water conservancy pipes
C. Compensation for Communication cables
D Compensation for power supply wires
The following table shows the compensation standards outside and with in the railway
sector in great detail.
49
Compensation Standard outside and within the Railway Sector in Wu-Guang line
item Guar dong Hunnan Hubeiunit Guanzhou Others Changsha Others Wuhan otherssections sections
1 Outside the railway sector(i), compensation for land acquired
and resettlement standard1. cultivated land __._._._-
paddy field 10,000yuan/mu 15.2 1.6-3.4 4.2 1.6-3.6 4.2 1.6vegetableplot 10,000yuan/mu 15.4 1.8-3.6 4.4 1.8-3.8 4.4 1.8dry land 10,000yuan/mu 14.4 1.2-3 3.4 1.2-3.2 3.4 1.2fishing pond 10,000yuan/mu 15 1.5-3.3 4 1.5-3.5 4 1.5orchard 10,O00yuan/mu 15.2 1.6-3.4 4.2 1.6-3.6 4.2 1.6land used to build house 10,000yuan/mu 14.8 1.3-3.1 3.8 1.3-3.3 3.8 1.3
2 . non-cultivated land ___Bush 10,000yuan/mu 0.06 0.04 0.06 0.04 0.06 0.04sloping field 10,000yuan/mu 0.08 0.06 0.08 0.06 0.08 0.06
( ii ) compensation for young crops1.. paddy field 10,000yuan/mu 0.16 0.12 0.12 0.1 0.12 0.12. vegetable plot I10,000yuanlmu 0.18 0.14 0.14 0.12 0.14 0.123. dar land 10,000yuan/nmu 0.1 0.07 0.07 0.06 0.07 0.06
(iii).. aboveground attachmentI . trees Yuan/one 60 40 45 35 45 352.. fruit tree Yuan/one 50-1500 20-1000 25-1000 15-800 25-1000 15-8003. well Yuan/one 500 300 500 300 500 3004, tombs Yuan/one 500-1000 300-600 300 250 300 2505. sunning concrete ground Yuan/square 80 30 40 25 40 25
meter .
50
6, enclosure Yuan/square 80 30 40 25 40 25meter
( iv ) . compensation for housingdemolition
I brick and concrete Yuan/square 1200 800 650 500 650 500meter .
2, brick and wood Yuan/square 800 500 400 250 400 250meter .
3, simple Yuan/square 250 150 150 100 150 100meter
4. brick and concrete (illegal) Yuan/square 1200 800 650 500 650 500m eter__ _ _ _ ___ _ _ _ _ ___ _ _ _ _ _
5, brick and wood (illegal) Yuan/square 800 500 400 250 400 250meter _
6, simple (illegal) Yuan/square 250 150 150 100 150 100p i)__ _ _ __ _ _ __ _ __ _ _ __ _ _m eter 250 _____________
(v), compensation for transition andremoving
1. compensation for transition Yuan/month/ 4.5 3 4.5 3 4.5 3period square meter
2. removing fee 460 350 460 350 460 3503, compensation for work and Yuan 1000 600 600 600 600 400
production held up /month, person11. within the railway sector
(i), compensation housing demolition _
I,. brick and concrete Yuan/square 700 700 700 700 700 700____ ___ ____ ___ ____ ___ ____ ___ ___m eter
2, brick and wood Yuan/square 400 400 400 400 400 400meter
3. simple Yuan/square 150 150 150 150 150 150
51
meter .
4, brick and concrete (illegal) Yuan/square 700 700 700 700 700 700m eter . _..._.___. __ . _..
5S brick and wood(illegal) Yuan/square 400 400 400 400 400 400meter
6. simple(illegal) Yuan/square 150 150 150 150 150 150meter _______
(ii.) compensation for transition andremoving
I. compensation for transitional Yuan/month/ 4.5 4.5 4.5 4.5 4.5 4.5period square meter
2, removing fee 460 350 460 350 460 350
3 compensation for work and Yuan 600 600 600 600 600 600production held up /month. Person111. infrastructure ___ _ __.
( i ) , compensation for roadreconstruction _ ______
1, main road 10,000/moth/ 311 300 300 300 300kilometer
2, road ofcountryside 10,000/moth/ 4. 32 3. 8 3. 61 3. 73 6. 1kilometer .
( ii) compensation for communication 10,000/moth!kilometer
1I cable 10,000/moth/ !S 15 IS 15 IS 15kilometer 5 5 _ _A 1 15
2, mainline 10,000/moth/ 4. 59 3. 95 4. 8 4. 67 4. 92 4. 79kilometer
(iii), power supply_1, main line removed 10,000/moth/ 1. 4 1. 4 1. 4
kilometer
52
2. wires 10,000/moth/ 0. 42 0. 36 0. 32kilometer
(iv)> water conservancyI,c irrigation cannel 10,000/moth/ 5. 33 4. 2 6. 53 4. 95 5. 14
kilometer2, drinking water pipes 10,000/moth/ 10 7. 6 9. 45 7. 84 11. 23
kilometer
53
4.3 Calculation of Compensation Rate for Land Acquisition
1) On account of the ever-increasing difficulties with labour force resettlement, the
proportion of resettlement subsidy in this project has been raised to 60% in contrast
with that of land compensation, which is 40%.
2) That the compensation disbursed in this project is sufficient enough to ensure the
rehabilitation for the affected villages and groups can be illustrated with Guangzhou
and Puqi, where the compensation is either the highest or the lowest in this project.
3) The compensation for land acquisition in Guangzhou is 150000 yuan per mu, of
which the land compensation fee is 60000 yuan, equal to the annual output value of
vegetable plot 1800 yuan/mu x 33.3 times; the resettlement subsidy is 90000 yuan,
equal to the annual output value of vegetable plot 1800 yuan/mu x 50 times.
According to the land law of the state, the sum of the land compensation fee and
resettlement subsidy should not exceed 20 times of the annual average output value
of the past three years prior to land acquisition. However, in view of the great
difficulty in the land acquisition, the total sum of land compensation fee and
resettlement subsidy in Guangzhou has reached 83.3 times of the annual average
output value of the past three years prior to land acquisition, far in excess of the
maximum fixed in the state land law.
4) The compensation for land acquisition in Puqi is 15000 yuan per mu, of which the
land compensation fee is 6000 yuan, equal to the annual output value of vegetable
plot 1200 yuan/mu x 5 times; the resettlement subsidy is 9000 yuan, equal to the
annual output value of vegetable plot 1200 yuan/mu x 7.5 times, the total
compensation thus being 12 times of the annual output value of vegetable plot per
mu. The compensation has reached the standard stipulated in the land law of the
state, sufficient enough to secure the welfare of the affected villages and individuals
from being impaired.
54
4.4 Calculation of Compensation Rate for Demolition and
Relocation
1) The housing compensation standard shall be determined by referring to the housing
reconstruction price. The used material from the demolished housing shall not be
deducted from the compensation fee.
2) Illegally set-up housing shall be treated in the same way as other housing in respect
of compensation standard.
3) Compensation for housing demolition and relocation is sufficient enough for the
affected units and individuals to reconstruct their housing at the reconstruction price,
which can be illustrated with the cases of Guangzhou and Hengyang, where the cost
of housing construction is either the highest or the lowest in this project.
4) In Guangzhou, the compensation rate outside the railway sector is 1200 yuan per
square meters for concrete-brick structured housing and 800 yuan for brick-wood
structured housing; that within the railway sector is 700 yuan per square meters for
concrete-brick structured housing and 400 yuan for brick-wood structured one. By
calculation, the reconstruction prices per square meters of concrete-brick and brick-
wood housing in Guangzhou are respectively:
Concrete-brick structured: material cost (steel bars, cement, sand, aggregate, bricks,
etc.) + labuor cost + machinery cost + earth & stone work cost = 700 yuan;
Brick-wood structured: material cost (timber, cement, sand, aggregate, bricks, etc.)
+ labuor cost + machinery cost + earth & stone work cost = 400 yuan;
Obviously, the compensation standard outside the railway sector is higher than the
reconstruction price, which accounts for the difficulty of the demolition and
relocation in Guangzhou.
5) In Hengyang, the compensation is 500 yuan per square meters for concrete-brick
structured housing, and 250 yuan for brick-wood structured housing. By calculation,
the reconstruction prices per square meters of concrete-brick and brick-wood
55
housing in Hengyang are respectively:
Concrete-brick structured: material cost (steel bars, cement, sand, aggregate bricks,
etc.) + labuor cost + machinery cost + earth & stone work cost = 500 yuan;
Brick-wood structured: material cost (timber, cement, sand, aggregate, bricks, etc.)
+ labuor cost + machinery cost + earth & stone work cost = 250 yuan;
By calculation, the compensation rate is sufficient enough for the affected units and
individuals to reconstruct housing at the reconstruction price.
4.5 Calculation of Compensation for Fruit Trees
Compensation with fruit trees is little bit more complicated compared with other
aboveground attachment. Along with the development of economy, the market
compensation for fruit trees has now doubled the standard prescribed by the
government. See the table of the categories, amount and unit prices of compensation for
the detail.
56
Compensation Standards for Fruit Trees in Wu uan Line\ Standards _ Young ruit tree Growin fruit trees Grown-up fruit trees
______I m :'2 m First year Second year Second category First categoryTypes Price Amount Price Amount Price Amount Price Amount Price Amount Price Amount1. Longan 45 220 60 45 1000 33 1500 402. Litchi 130 55 160 45 150 60 500 48 800 203. Mango 40 120 80 200 250 15 300 III4. Orange 25 158 35 86 120 456 160 2685. Chinese chestnut 80 112 145 12 200 66. Plus 35 160 45 64 140 186 180 227. Banana 20 116 40 5658. Pear . . 25 202 35 318 110 60 150 1259. Apple 25 360 35 70 110 44 150 50
10. Pomegranate 120 18 160 70
11. Pineapple . 19 48 .
57
4.6 Funds Budgeting and Investment Planning
(1) Expenses on resettlement is included in the total budget of the project. On effecting
of the project funds needed for resettlement is included in the annual investment plan of
the project.
(2) Investment on resettlement of the project totals 318,426,100 Yuans, including
118,088,200 Yuan expended on land acquisition, 68,138,800 Yuan housing demolition,
132,199,100 yuans other fees.
(3) To keep pace with the engineering plan ,investment in 1998 takes up 29% of the
total investment, investment in 1999 takes up 53% of the total investment, investment
in 2000 takes up 18% of the total investment.
(4) Management fee is 3% of the combination of compensation for land acquired,
compensation for housing demolished and compensation for aboveground
attachment.(excluding infrastructure fee)
(5) Unforeseen fee is 10% of the combination of compensation for land acquired,
compensation for housing demolished and compensation for aboveground
attachment.(excluding infrastructure fee)
For detailed budget of all expenses above, see sheet of funds for land acquisition and
demolition along Wa-Guan line. For the engineering schedule, see the table of the
engineering schedule of the Project.
4.7 Fund Movement and Management
(l)The MOR, as the project owner, shall disburse the fund to the land bureaus of the
three provinces at the given times and the given sums prescribed in the RAP.
58
(2)The land bureaus of the three provinces, in turn, shall forward the fund to the local
governments and affected institutions and enterprises punctually according to the
agreement signed with the cities and counties concerned.
(3)The township government, upon receiving the fund, shall duly allot the
compensation to the affected villagers, township enterprises and their staff members
and, at the same time, use the land compensation fee which belongs to the collective to
develop production, resettle surplus labor force.
(4)In urban housing demolition, the municipal land bureau allots compensation directly
to the affected individuals.
(5)The compensation to enterprises shall be allotted to the affected enterprises by the
land administration departnent. The former may use it to develop production and
compensate the affected workers resulting from the cessation of production.
(6)The management fee and unforeseeable fee shall be at the disposal of the provincial
land bureau who shall allot the fees to governments of different levels in proper
proportion according to their working.
(7)The project owner and governmental departrnents responsible at all levels should
take good care of the compensation fees and strictly forbid the funds to be used for
other purposes.
(8)Government at all levels should act strictly on relevant policies and regulations and
make sure no embezzlement of the funds in any form would happen.
(9)Establish a strict fund allotrnent system. Fund can be disbursed only to the approved
projects and in conformity with annual fund disbursement budget. No abuse of fund is
allowed.
(lO)Establish a strict accounting system. The accounting shall be open to the
59
supervision and examination by the project owner, persons responsible and thedisplaced population.
(11) Before the disbursement of collective compensation, either the provincial andmunicipal governments or district and township governments shall send personnel tocheck the feasibility of the utilization plan.
(12) Towards the end of each year, the government department responsible shall havethe financial and audit departments jointly examine the utilization of compensation.
(13) Every year, the relevant information about the financial income and expenditureshall be copied by the resettlement managerial departnent to the external monitoringinstitution.
60
Master Table of Primary Estimates of Compensation for Land Acquisition,
Housing Demolition in Wu-Guang Lineunit: ten thousand yuan
Guangdong province Hunan province Hubei rovinceItem Total Guang Other Changsha Other Wuhan Other
zhou city Sections city sections city sections1I compensation for land acquired 11808.82 _
I, land fee 4723.53 2508.02 183.27 342.16 456.41 1164.7 68.972.. resettlement fee 7085.29 3762.04 274.89 513.24 684.62 1747.04 103.46
II. compensation for demolition 6813.88I,. compensation for housing rebuilt 6778.09 939.67 85.87 2973.34 396.81 1904.06 478.342. compensation for transitional period3, compensation for removing housing 35.79 2.21 0.81 22.45 4.83 3.91 2.214 . compensation for work and
production held upIII compensation for aboveground 538.06attachment . ._.
1, trees fee 463.79 8.29 37.04 1.49 9.75 405.45 1.772. fruit tree fee 48.65 5.18 23.67 0.38 11.52 7.93. well fee 0.59 0.05 0.15 0.05 0.09 0.254. tomb fee 2.57 0.15 0.24 0.05 2.13
5S sunning concrete ground fee 9.29 4.84 3.15 1.36 .enclosure fee 13.17 5.56 0.37 0.42 1.5 5.32
IV, infrastructure fee 9782.73
(i) road reconstruction fee 7031.. main road fee 672 210 180 126 105 51
61
2, road of countryside fee 31 9 8 6 4 4(ii ) communication reconstruction 8820.1
I, cable fee 5545.5 945 705 84 615 226.5 29702, main line fee 3274.6 839.47 438.08 38.4 498.55 109.2 1350.9
(iii), power supply reconstruction fee 55.151, main line fee 14.63 18.62 6.32. wires fee 10.02 3.48 2.1
(iv). water conservancy 204.48I I irrigation cannel 61.89 4 3.46 32 10.59 11.842, drinking water pipes 142.59 16 13.84 60.44 24.7 27.61
V, others fee-I management fee 574.82 217.08 18.26 115.61 47.01 157.22 19.64-2. unforesecable fees 1916.08 723.6 60.88 385.35 156.69 524.08 65.483 RAP-writing fees 25 4. external monitoring fees 383.22 _ . ._._
VI, fund total 31842.61 10224.81 2058.45 4569.33 3059.82 6406.21 5115.77VIl, investment plan
1I, investment plan in 1998 9524.19 2965.19 596.95 1325.11 887.35 1857.8 1483.572, investment plan in 1999 16660.23 5419.15 1090.98 2421.74 1621.7 3395.3 2711.363. investment plan in 2000 5658.19 1840.47 370.52 822.48 550.77 1153.11 920.84
Note: The investment plan of 1998 includes the fees for both the RAP writing and the external monitoring of resettlement.
62
Schedule of the Land Acquisition and the Project Engineeringunits year, quarter
Schedule of land acquisition and Time of start and finish of engineeringSub-projects housing demolition
1998 1999 1998 1999 2000
4 1 2 3 4 4 1 2 3 4 1 2 3 4
llankou passenger trains - -
o mnintenanec yard
liandan up-going--o line _ _ _ _ ____ _ _
West jiangan - -
station _ _ ___
.t > Tuoluokou -
marshalling yard _ _ _East Wuchang - -
station _ _Tracks 3 and 4 of _Wuchang station _
.Wuchang passenger - -
trmins maintenance yard
South Wuchang - -_ station _ _
I -ifang contact network -
section, track garage . __ _
X Wulongquan division - -
section _ __.__
> HBeshengqiao network - - -
section track garage
63
Heshengqiao haulage - - -
- transformer substation
0 . Xiannin networksection, division - -.
i _ section, track garage
Guantangyi haulagetransformer suibstation ___.
Puqi division section - -
Chibi station: technicalrenovation, networksection , track garage
Renovation __
. Linxiang network section,division section -
Yunxi network section
Yueyang north - -
S El switching section . . _ _
>e Yueyang network section,division section . . .
I lubin network section
Hubin station
64
Hubin track garage line - -
Yueyang residential - -
quarters . _
Rongjiawan network -
sectionRongiiawan
0 transformer substationto Rongjiawan trackc garage _ _
>. >Rongijawan residential _
- quartersMilou network section _ -
Miliu transformnersubstation
Taolin network section, _ = = =division section _ _
c) Taolin residential _ -
0 quarters
.-, Chuanshanpin divisionsection
Gaojiafang networksection _
Qiaotaoyi transformersubstation .
65
Changsha station -
Changslia residentialquiarters ___
Laodaohe networksection earth borrow _
> ~~~areaQ ~ ~ ae __ __ .___ ____ _ _ _ _ _ _
c Liuyanghe emergency _project - -
co Changsha down-goingC... passenger train dispersing
lines line _ __ _ _ __ __ _ _ ._ _ __ __ _ _ _ _
Changsha east network - _
section division_section
Datuopu transformer - _ _
.5 substation _
0.. = ^Muyun city network3 3 > section
Baimalong divisionsection
Zhuzhou pivot . - -
Xiangqian ushering -
line . _c) Zhuzhou residential
0 quiarters
66
Laoguanzhong earthborrow area
Lukao netwvork section, _division section _ _
a Jintian network sectiona
o Jintian transformer - -_
substation _ _ ._.
N Zhutin network section,division section .. . __._ _
Weishan networksection _
o c Weishan transformer0
3 : . substation _ _ _ _
Xinxialiu division -
sectionDapuwei network .
sectionWeiyang pivot - -_
*w Weiyang power supply _ -
section _co Weibai transformer
substationDongyangdu
transformer substationWuytuan division
u.gn ssection67
to Laiyang transformersubstation _ _
Gongpinxu divisionsection
Pingshibai divisionsection
Shaogian station -
5 o 0 CZhitong Town,Shaogian City
a Shanzibei divisionsection _ _ _
Maba network section
c _ Wushi transformer
substation
Hetao network section : : r_= _
Yinde station _ _ _
Shahekao division section,
to transformer substation
Lianjiangkao transformer -
substation, network section . _
Jiaohenshi divisionsection . _ .__.
Pajiangkou quarry -
w Tanyuan networksection
68
Huadu station _
o X Juntian division section
Guangzhou north -
station
Dnlang station - _ - _
Tnngxi station - - = -. -
The thiird line of - -
Guangbai-tangxi
GCuanghou nortih haulage
CD) tnkmfaanner stlalIk, .,
dIvI-donnieccion _ _ _ _ __ _ _ _ _ _ _ _ _ _ _ _ _
Tungxi switching - - - -
section
Daiyunshnn network - - -
section
69
5 Reseftlement and
Rehabilitation Plans
5.1 Goals of Resettlement
(1) The displaced population should be given the chance of benefiting from project
development;
(2) The displaced population will be able to raise, with the help from the govermment,
their income standards, or at least restore their former income standards;
(3) The resettlement of agricultural population should depend on land as much as
possible in order to minimize resettlement risk;
(4) In the transference of jobs whenever necessary, the educational background of the
affected persons should be fully taken into account and consideration should be
given to the willingness of the affected persons;
(5) The resettlement plan should be made jointly with the villager representatives
through consultation and mass participation should be encouraged throughout the
whole process of resettlement;
(6) Before the actual implementation of land acquisition and displacement, the
affected population should get their due compensation for all their loss at the
standards stipulated in the RAP;
5.2 Resettlement and Rehabilitation Plans for Rural PAPs
S2.1 Resettlement Plan for Rural PAPs in Land Acquisition
(l)The fact that the land to be acquired along the railway line is small in amount and
segregated in distribution will produce comparatively slight impact on the per capita
land possession in the affected villages. On the other hand, the towns along the
railway line have over I mu of land possession per labour. Internal land reallocation
70
method, therefore, can be adopted in the affected villages along the line. Land
compensation fee will be utilized convergently in the transformation of the low- and
mediocre- yielding field, in the introduction of proved scientific and technological
achievements in order to raise the output value, which will be realized mainly in:
-improvement of irrigation facilities;
- amelioration of the soil, leveling of the fields and more application of fertilizer;
- more fumding in economic plants which are expected to bring more profit, for
example, development of hothouses to plant vegetables;
- development of such sideline production as the breeding of pigs, cattle, chicken
and ducks;
- sensible choice of 2 or 3 industries with potential to alter the rural production
setup.
(2) Very little land will be acquired from the counties of Guangdong Province along the
line, which will result in little impact, except for Qingyuan City where the amount of
land to be acquired is comparatively large, but the cultivated land to be acquired
takes only a small portion, of which 1000 mu is bushy and hilly land, all non-
cultivated with no economic plants. The Lianlian town in Qingyuan city has 0.92 mu
of land possession per labour before the land acquisition and 0.9 mu after the land
acquisition, so there will be little impact with the land acquisition.
(3)The land to be acquired for the construction of a new railway station in Puqi, Hubei
Province, several score mu in area, was specifically approved by the MOR at the
request of Puqi Municipal Govemnment. The present Puqi Station, closely adjoined
by a cement factory and thus severely suffering from pollution, is left with little
space to expand. For this reason, express trains seldom stop here. Puqi Govemment,
feeling an urgent need to boost the local economy, offers to acquire land with its
own fund to build a new Chibi Station (taking advantage of the renowned historical
site of Chibi (inflamed cliff) originating in the Three Kingdoms time) where all the
passing express btans are expected to halt The present station will then fimction as
a freight station.71
The affected population is pleased with the new station project for the reason that
the development of a new urban district and a Three Kingdoms tourist resort
centering on the new station will surely provide the affected population with more
openings of jobs and enable them to increase their income. In addition, business
floorage will be reserved in the new station square for the affected villages and
production groups. Puqi Government will also invest 50 million November 15,
1998yuan RMB to build such infrastructures as water and power supply, roads,
hospital and green belt auxiliary to the station. The affected population will be the
first to benefit from such construction which is bound to greatly augment the value
of the land around the station. Moreover, the present per capita land possession in
Puqi is 1.3 mu (that of Hubei Province being 0.86 mu). Even after the land
acquisition, the land possession per capita will still be over one mu in the affected
villages, which means the production resettlement can be done by internal land
reallocation.
The compensation rate for the land acquisition by Puqi Government is 1S thousand
yuan per mu for the land along the line, the stipulated standard for the project. Puqi
Government has by now disburse 50% of the total fund to the municipal land
administration bureau, with the rest part to be punctually paid once the contract
between the land bureau and the affected population is signed. The construction of
the new station will not be started until then.
(4) In subuiban rural areas, the villagers have already been left with comparatively small
land quantity. The project, again, will acquire a considerable amount of land from
Guangzhou, Changsha and Wuhan, which will certay make the problen more
acute. Internal land reallocation, therefore, is not applicable in this case. The local
governments, however, have found out solutions to this problem, each in a different
way:
-In Wuhan, the measure 'acquire ten to return one" is adopted in consideration
that the cultivated land in the suburbs is decreasing and it is impossible to prevent
the living standards of the affected population from descending by depending on
72
agriculture only. As a matter of fact, over 80% of the income of the suburban
villagers is no longer from agriculture. For the sake of affected population, the
government has decided to acquire ten percent more land in the land acquisition to
return it to the villagers. As the ownership of the returned land has changed (from
collective-owned to state-owned), it now can be used by the affected villages to
develop business (as collective-owned before, it could only be used for agricultural
purpose). The measure "acquire ten to return one" will be adopted in Chasha and
Guangzhou.
-In Changsha, the govenmuent has made a policy of providing the displaced
population with large-sized flats. After the land acquisition, a few production groups
will be virtually left with no cultivated land. In view of this situation, a unique
resettlement plan has been contrived in Changsha, according to which, housing
ground site will be chosen in prosperous urban zones to build four-storied housing
with government provided infrastructure (including facilities for water and electric
power and road and so on) and with each unit for only two households. The average
housing area for each family is about 280 m2; the household live on one floor with
the other three floors about 210 m2 in total area to be rent out If affected people is
in lack of funds, they can get loan from banks at low interests. It has turned out that
the income from the rent is over twice that from farming Again, the housing is
looked after largely by old or female folks of the household with the able-bodied
family members seeking jobs elsewhere to obtain more income.
Such large-sized flat providing method has also been adopted somewhere in
Guangzhou and Wuhan.
(5) According to the relevant regulations of the state, if the land possession per capita is
below 0.1 mu after land acquisition, the rural residential registration of the affected
villagers may be converted to non-rural one. The affected villagers in the suburbs of
Guangzhou, Changsha and Wuhan are by and large eligible for such conversion. But
according to investigation and questionnaires, the affected population basically tend
to abandon such 'chancee and keep their rural registration, probably for the
following reasons:73
A. Suburban rural collective economy is usually well developed and the village and
production group have fairly good economic means. If the affected villagers
remain their rusal registration, they can get a yearly bonus about 5000 to 10000
yuan from the collective. Otherwise, they can not have such bonus. Take
Hejiatun Village for example. It has village enterprises as many as 36 with an
annual output value last year 7 hundred million yuan. In other words, each
labourer had a bonus of ten thousand yuan. Any one above 50 of age there is
counted as senile and as such is eligible for a monthly pension of 120 yuan. Same
is the case with Huoju Village, Furong District of Changsha and Jianggao Town
of Guangzhou.
B. Urban enterprises, with limited oapacity of absorbing rural labourers, will pay
relatively low salary and are unable to guarantee sure jobs. Besides, the
requirements are strict, which appears disagreeable to the undisciplined villagers.
C. On the. other hand, suburban villagers enjoy numerous chances of earning money,
such as seeking jobs elsewhere, undertaking transportation or small business,
renting out their housing and working in township enterprises.
(6) Against the general economic background that China is transferring from planned
economy to market-oriented one, self-employment is the commonest and the most
realistic choice. Those who seek jobs by themselves may get a lump-sum
compensation, respectively, 60000 yuan per capita in Guangzhou, 25000 yuan in
Changsha and Wuhan, and 13000 yuan in Hengyang and Zhuzhou. Together with
income from other means, the living standards of the affected population can be
secured against a drop. One thing to note is that all the other job seekers do not like
to get the compensation for the reason that if they keep the compensation for
themselves, they will be seen as separated from the village collective and
accordingly they will no longer have their share in the village bonus and other
village welfare. The village collective will use land compensation fee and the
resettlement compensation to start village industries whereby the villagers can have
their bonus share. In this way, moreover, the surplus rural labourers will have more74
job openings and the villagers will have another steady source of income.
7) An investigation on the suburban villagers of Guangzhou, Changsha and Wuhan
shows that long before the project, the affected villagers of the three cities no longer
relied on agriculture to earn their living. Such methods as " acquire ten to return one"
and " large-size flat" and the comparatively high compensation standard will accelerate
their urbanization.
A. The population of 4940 from 1109 households in Guangzhou affected in land
acquisition will be resettled in 4 different ways: first, they can renounce their cash
compensation of self-employment and thus remain their membership of the village
collective. In fact, they have already found jobs for themselves, such as undertaking
small business or transportation. About 45% of the affected people will be resettled
in this way. Second, they can seek jobs in township or village enterprises. Some
people had already been working in such enterprises before the implementation of
the project. The land compensation fee and resettlement subsidy will be used
collectively to ameliorate and expand the original township enterprises. About 25%
of the affected people will be resettled in this way. Thirdly, they can make use of the
land returned by means of "acquire ten to return one" to develop commercial
business, set up farm product markets or office buildings. About 18% of the
population will be resettled in this way. Finally, they can rent out part of their large-
sized flats to immigrant workers. About 12% of the affected will be resettled in this
way.
B. The population of 1533 from 465 households in Changsha affected in land
acquisition will be resettled in 3 different ways: First, they can make use of the land
returned by means of "acquire ten to return one" to develop commercial business.
Take Gaoqiao Township. They have successfully resettled over 300 labourers by
75
using the 56 mu of returned land to set up large warehouse and develop
transportation business. About 48% of the affected population will be resettled in
this way. Second, they can rent out part of their large-sized flats. In addition, the
young and able-bodied labourers of the households can go out and find jobs
elsewhere. About 35% of the affected population will be resettled in this way.
Thirdly, they can start new township and village enterprises or resettle labourers in
the existing township enterprises. About 17% of the affected population will be
resettled in this way.
C. The affected population of 5026 from 1169 households in Wuhan will be resettled in
four different ways: First, they can be resettled in the existing township enterprises.
Take Hejiatun Village of Jianghan District. They have resettled nearly 200 labourers
in the present 36 village enterprises. The land compensation fee and resettlement
subsidy can be used collectively to renovate and develop the current enterprises.
About 30 % of the affected population will be resettled in this way. Second, they can
make use of the returned land from "acquire ten to return one" to develop
commercial business and other secondary and tertialy industries. Take Binghu
Village of Hongshan District. They make full use of the advantageous location of
the returned land to start hotels and catering trade and have resettled a large number
of labourers. About 38 % of the affected population will be resettled in this way.
Thirdly, they rent out their large-size flat and have their able-bodied household folks
seek jobs elsewhere. About 17% of the affected population will be resettled in this
way. Finally, they renounce their cash compensation for self-employment and
reserve their collective membership. In fact, they have found jobs for themselves
such as undertaking small business or transportation. About 9% of the affected
population will be resettled in this way.
76
(8) In consideration of the arduousness of the land acquisition in Guangzhou, Changsha
and Wuhan, the governments of the three provinces involved offer to add 10000
yuan per mu to the compensation for the land acquisition in the three cities with the
aim to give support to railway construction and boost the local economy. This
additional sum will be on local finances.
(9) Since the implementation of the project, the affected rural population has got access
to many means to retrieve their income by developing agriculture and non-
agricultural production. By a joint calculation with the relevant departments of local
governments, it is estimated that the average annual income per capita of the
affected population, either along the line or of the suburbs of the three cities, can
increase by 10% to 14%, which shows the living standards and income index of the
affected population are far from being deteriorated by the project.
For the impact with the land acquisition, please see the cultivated land of the towns
affected by the Wu-Guang capacity expansion project.
5.2.2 Resettlement Plan for Displaced Population in Housing Demolition
(1)In the villages and production groups along the line where land acquisition and
housing demolition have resulted in slight impact on the local production and
livelihood, the affected villagers will still stay in their villages and groups. The
village commission will allot housing ground site for the affected villagers to set up
new housing and demolish the old one on their own.
(2) Compensation standards and principle for the displaced households along the line:
-The housing compensation standard shall be determined by referring to its
reconstruction price. The used materials tom from the old housing belong to the
household and such materials shall not be deducted from the compensation.
77
Cultivated Land of Affected Towns in Wuguang Line
Place Culvated land (mu)
Province County or city Town Land per Land per Land per Land percapita before capita after labour before labour after
land land land landacquisition acquisition acquisition acquisition
Guangdong Guangzhou Jiangao town 0. 04 0. 02 0. 12 0. 09
Guangdong Guangzhou Shijin town 0. 04 0. 02 0. 12 0. 09
Guangdong Guangzhou Sheuxian town 0. 05 0. 03 0. 14 0. 12
Guangdong Guangzhou Shanhua town 0. 28 0. 27 0. 9 0. 89
Guangdong Guangzhou Lianjiankou 0. 31 0. 3 0. 92 0. 9
Guangdong Guangzhou Shakou town 0. 28 0. 27 0. 89 0. 88
Guangdong Guangzhou Donghua town 0. 33 0. 32 0. 96 0. 95
Guangdong Huadu city Shaliyuan town 0. 27 0. 25 0. 89 0. 87
Guangdong Qinyuan city Pinshi town 0. 32 0. 32 0. 91 0. 91
Guangdong Yingde city Gaoqiao town 0. 33 0. 3 0. 88 0. 8
Guangdong Qujian county Yixia town 0. 32 0. 3 0. 86 0. 79
Guangdong ShYoguan city MGwandui town 0. 34 0. 33 0. 9 0. 89
Guangdong Lechan county Datuo town 0. 35 0. 34 0. 9 0. 88
78
Cultivated Land of Affected Towns in Wuguang Line
Place Culvated land (mu)
Province County or city Town Land per Land per Land per Land percapita before capita after labour before labour after
land land land landacquisition acquisition acquisition acquisition
Hunan Linxian city Changan town 0. 44 0. 43 1. 26 1. 25
Hunan Yuanyan county Yunxi town 0. 39 0. 38 1. 14 1. 13
Hunan Yuanyan county Meixi town 0. 38 0. 37 1. 14 1. 13
Hunan Yuanyan county Chenguang town 0. 4 0. 39 1. 16 1. 15
Hunan Yuanyan county Huashaje 0. 41 0. 4 1. 15 1. 14
Hunan Miluo city Chenguang town 0. 38 0. 37 1. 15 1. 14
Hunan Miluo city Ch.ngjiao town 0. 39 0. 37 1. 14 1. 13
Hunan Miluo city Taoling town 0. 39 0. 38 1. 15 1. 14
Hunan Miluo city Chuansanping 0. 4 0. 39 1. 16 1. 15
Hunan Miluo city Gaojiafan 0. 4 0. 39 1. 14 1. 13
Hunan Wanchen county Qiaoteyi 0. 45 0. 44 1. 28 1. 27
Hunan Changsha county Muoyun town 0. 4 0. 39 1. 15 1. 14
Hunan Zhuzhou city Baimalong village 0. 31 0. 3 1. 08 1
79
Cultivated Land of Affected Towns in Wuguang Line
Place Culvated land (mu)
Province County or city Town Land per Land per Land per Land percapita before capita after labour before labour after
land land land land_ _ _ _acquisition acquisition acquisition acquisition
Hunan Zhuzhou city Hehua town 0. 32 0. 3 1. 1 0. 9
Hunan Zhuzhou city Longtepu 0. 3 0. 29 1. 07 1. 05
Hunan Zhuzhou county Lukou town 0. 31 0. 3 1. 09 1-.08
Hunan Zhuzhou county jingtLan town 0. 4 0. 39 1. 14 1. 13
Hunan Zhuzhou county Hualong town 0. 42 0. 41 1. 15 1. 14
Hunan Hengdong county Xintang town 0. 4 0. 39 1. 15 1. 14
Hunan Hengdong county Xiayuan town 0. 41 0. 4 1. 15 1. 14
Hunan Hengyang city Heping town 0. 38 0. 36 1. 12 1. 1
Hunan Hengyang city Dongyang town 0. 37 0. 36 1. 09 1. 06
Hunan Hengnan county Liaotiang town 0. 42 0. 41 1. 17 1. 16
Hunan Lelyang couty Gongpingxu 0. 43 0. 42 1. 17 1. 16
Hunan Yonxin city Qiaozhuang 0. 39 0. 38 1. 14 1. 13
Hunan Cenzhou county Kuishu town 0. 41 0. 4 1. 13 1. 12
80
Cultivated Land of Affected Towns in Wuguang Line
Place Culvated land (mu)
Province County or city Town Land per Land per Land per Land percapita before capita after labour before labour after
land land land landacquisition acquisition acquisition acquisition
Hubei Wuhan city Hongshang town 0. 26 0. 23 0. 76 0. 7
Hubei Wuhan city Jiefong town 0. 27 0. 25 0. 78 0. 74
Hubei Wuhan city Qingli town 0. 29 0. 28 0. 81 0. 8
Hubei Wuhan city Hewu town 0. 25 0. 22 0. 74 0. 7
Hubei Wuhan city Wulongquang 0. 26 0. 26 0. 77 0. 76
Hubei Wuhan city Zhifang town 0. 3 0. 28 0. 91 0. 89
Hubei Wuhan city Hezhang town 0. 28 0. 27 0. 8 0. 78
Hubei Xiangnin city Yongan town 0. 48 0. 47 1. 31 1. 3
Hubei Puxi city Guantangyi 0. 46 0. 45 1. 3 1. 28
Hubei Puxi city Fonghuan town 0. 5 0. 48 1. 34 1. 31
Hubei Puxi city Chimagan town 0. 51 0. 5 1. 32 1. 31
Hubei Puxi city Zhonghuopu 0. 45 0. 44 1. 28 1. 27
81
-The housing compensation shall be paid by installment with 70% delivered
before the construction of the new housing and the remaining 30% delivered after.
In rural areas, new housing shall be set up before the old one is torn down. If for
some special reason the old housing has to be demolished before the new one is set
up, the railway side shall pay transition fee according to the standard, namely, 3
yuan per square meter each month.
- The railway shall pay the cost for removal according to the standard, namely,
350 yuan per lorry shift
- Such public infrastructures as roads, water and power supply shall be designed
and financed by the local government and the construction shall be completed before
the displaced population move into the new housing.
- In locating housing ground site, priority should be given to such place with stable
geological structure, convenient for road construction and water and power supply.
At the same time, it should be as close to the original housing site of the displaced
population as possible in order to facilitate their production and life.
- The displaced population should be notified of the date of removal at least two
months in advance in order that they can have sufficient time to set up new housing.
(3)The village commission will take effective measures ( for example seeldng labours,
choosing housing ground for housing reconstruction, buying materials and so on) to
help the difficult families of the old, weak, ailing and disabled and families without
male labourers, by consulting their opinions, to build new housing and move in. The
poor households will get help in funds to ensure basic resetflement housing
(4) In the suburbs of large cities as Changsha, Guangzhou and Wuhan, as little land is
left (in some places, even the new housing ground site is hard to find), the new
housing has to be built congregately in urban district in order to provide the
displaced population with large-sized flats, as is the case in Changsha. For
fiagmentary displacement, the railway construction unit shall buy commodity
housing in urban district for the households, as is the case in Guangzhou. Another
alterative is to locate the new housing ground just in the current living place of the
displaced population for them to set up new housing on their own, as is the case in
Wuhan. Some displaced residents own two or more flats; the remaining housing can
82
still suffice them even one of their flats is torn down. In such case, compensation
can be disbursed in one lump sum to them at their request.
(5) Compensation standards and principle for the displaced households in the suburbs of
the big cities:
-The housing compensation standard shall be determined by referring to its
reconstruction price. The used materials torn from the old housing belong to the
household and such materials shall not be deducted from the compensation.
-- The housing compensation shall be paid by installment with 70% delivered
before the construction of the new housing and the remaining 30% delivered after.
But it shall be paid in one lump sum to those households buying commodity
housing.
- For those households who demolish their old housing and build the new one on
their own, new housing shall be set up before the old one is torn down. If for some
special reason the old housing has to be demolished before the new one is set up, the
railway side shall pay transition fee according to the standard, namely, 4.5 yuan per
square meter each month.
- The railway shall pay the cost for removal according to the standard, namely,
460 yuan per lorry shift
- Such public infastuctures as roads, water and power supply shall be designed
and financed by the local government and the construction shall be completed before
the displaced population move into the new housing. The affected people can not
pay for these infiasucture fees.
- In locating housing ground site, priority should be given to such place with
stable geological structure, convenient for road construction and water and power
supply. At the same time, it should be as close to the original housing site of the
displaced population as possible in order to facilitate their production and life.
- The displaced population should be notified of the date of removal at least two
months in advance in order that they can have sufficient time to set up new housings.
(6) The village commission will take effective measures to help the vulnerable families,
by fully consulting their opinions, to build new housing and move in. Special
RI
concern shall be given to those vulnerable families buying commodity housing or
resettled in congregately built housing flats. For instance, the old, ailing and
disabled households will be arranged under 4th floor. The poverty-stricken families,
if possible, will be arranged on the ground floor so that they may take the
advantage to open small shops to earn their living. The poor households will get
help in funds to ensure basic resettlement housings.
5.3 Resettlement and Rehabilitation Plans for Urban Displaced
Population
5.3.1 Resettlement and Rehabilitation Plans for Urban Displaced Population
(1) The impact of Wu-Guang Project on urban residents is found convergently in
Wuhan only. Exactly, the housing of 5 households and the temporary sheds
unlawfilly built by 8 immigrant households will be demolished. Still a temporarily
built warehouse of a residential commission will also be tom down.
(2) For the 5 urban households, the measure of purchasing commodity housing in the
nearest place possible will be adopted. Because though the size of the commodity
housing is smaller, the environment and residential quality will be by far improved.
Their original housing, close to the railway, has no lavatory, in an environment foul
and noisy. They are happy to buy commodity housing
(3) For the unlawfully built sheds, compensation will be paid at 150 yuan per square
meter according to the relevant standard of Wuhan City. In addition, the government
will find housing for them to rent, with the compensation they are given.
(4) The temporarily built warehouse is not to be rebuilt elsewhere once it is tom down.
Compensation will be paid at 150 yuan per square meter, according to the
regulations.
(5) Housing resettlement principle for urban residents:
84
- Consultation with the displaced population on equal standing;
- Depreciation of the demolished housing shall not be considered in the
reconstruction price;
-If the former average floorage per capita of the displaced residents is lower than
the stipulated lowest standard for urban residents, the deficiency shall be made up in
resettlement without charging fee for the made up area;
-The resettlement site shall be decided on by the government. Two resettlement
sites may be provided for the residents to choose, whenever conditions permit;
- The displaced residents shall move into the resettlement housing directly
without transitional period. Whenever transition is absolutely necessary,
compensation shall be paid at 4.5 yuan per square meter;
- Removal fee shall be paid by the railway construction unit at 450 yuan per lorTy
shift;
- Publicize the inforrmation and make announcement 60 days in advance so that
the affected population will have enough time to move out.
(6) Process for the housing demolition & relocation and resettlement:
-The govenmmental institutions responsible of resettlement shall send personnel
to conduct on-the-spot investigation and checking about the affected households on
the household number, the ownership, structure, area and other attachment of the
housing;
-Publicize the resettlement plan, the policy for housing demolition & relocation,
the resettlement procedure, the resettlement compensation, the scope of demolition
and the time limit for removal, so as to have the mass participate in and supervise;
-The govermmental institutions responsible of resettlement and the displaced
households shall sign agreement on compensation standard, compensation sum, the
size and the location of resettlement housing, etc.;
- After the displaced households have made an on-the-spot survey, an additional
agreement shall be signed between the department responsible and the households
on such more detailed issues as the story, the disposition and the room number of
the resettlement housing;
- The agreements on resettlement shall be signed and sealed by both parties and
notarized by the notary office;85
- The displaced population moves into the new housing.
5.3.2 Resettlement Plans for Enterprises and Shops
(1) Resettlement plan for enterprises
A Wu-Guang Project involves 12 enterprises, all small-sized (means there are less 50
workers), of which the metal products factory in Guangzhou has stopped its
production; Ruyi Plastic Factory has long been in deficit. The several chicken
ranches involved in Guangzhou have only the coops demolished. The police
substation in Jianggao Town has a car parking lot and several simple-structured
sheds demolished. The other 4 enterprises (small sized, less 50 workers)
respectively in Yingde City of Guangdong Province, Changsha and Hengyang cities
of Human Province are getting along with their regular production. The relocation
of enterprises will not result in unemployment for their stuff members.
B. The compensation standard for the enterpnses shall be made according to the
reconstruction price; no depreciation will be taken into account.
C. Compensation shall be paid by installment with 70% delivered before the
construction of the new housing and the remaining 30% delivered after.
D. The demolition and relocation of enterprises shall be done only after the new
housing has been set up. If for some special reason demolition has to go before the
constuction of new housing, the railway construction unit shall pay, according to
the compensation standard, a sum of compensation for the cessation of production
or business, which will ;cover the monthly salary of all the employees and an
additional 15% as managerial fee and another 15% as socially collected insurance
premium. This compensation, to be paid by month, is 1000 yuan per month for
each person in Guangzhou, and 600 yuan in Changsha and Yingde.
E. The railway construction unit shall pay for the enterprise removal, at 460 yuan per
lorry shift in Guangzhou and Changsha, 350 yuan in Yingde and Hengyang. A lorry
shift means a four-ton lorry running for the whole day. The railway construction
unit shall pay for whatever lorry shifts needed for the enterprise removal.
F. The new site for the enterprise should be as close to the old one as possible, in
order to keep the existing market environment of the enterprise intact If the
86
enterprise asks for a different relocation, it could be allowed if conditions permit.
G. If the housing of the enterprise has been fitted up, and the fit-up standard is
confirmedly higher than that of housing compensation, the gap can be compensated
by the railway construction unit.
HF The enterprise shall be informed of the removal 60 days in advance so that it will
have enough time to get prepared and avoid unnecessary loss.
(2) Resettlement plan for shops
A. Wu-Guang Project involves 23 shops in the relevant three provinces, 16 in
Guangzhou, 2 in Yingde and 5 in Changsha. The involved shops in Guangzhou and
Yingde are small (with less 10 korkers), and their business is not good; the profit is
mediocre. The 5 shops in Changsha, however, are comparatively large-sized (with
less 100 workers), with fairly good profit. Though there are far more salesclerks in
these 5 shops, the relocation will not result in unemployment for them.
B. The resettlement measures taken by Guangzhou and Changsha governments are: to
provide stalls in the nearby markets for the PAPs . The PAPs can rend these stalls
by there compensation fees. If the affected persons are not successful in their
business and want to try other trades, the government will, in addition to the
payment of compensation, introduce new means of life to them.
C. In Yingde, the govenmment will build new housing for the 2 small shops nearby to
ensure that they could continue their business in their former market environment
D. The compensation standard for the shops shall be made according to the
reconstruction price; no depreciation will be taken into account
E. Compensation shall be paid by installment with 70% delivered before the
construction of the new housing or removal and the remaining 30% delivered after.
F. The demolition and relocation of shops shall be done only after the new housing
has been set up. If for some special reason demolition has to go before the
construction of new housing, the railway construction unit shall pay, according to
the compensation standard, a sum of compensation for the cessation of production
or business, which will cover the monthly salary of all the employees and an
additional 15% as managerial fee and another 15% as socially collected insuance
premium. This compensation, to be paid by month, is 1000 yuan per month for
87
each person in Guangzhou, and 600 yuan in Changsha and Yingde.
G. The railway construction unit shall pay for the shop removal, at 460 yuan per lorry
shift in Guangzhou and Changsha, 350 yuan in Yingde. The railway construction
unit shall pay for whatever lorry shifts needed for the shop removal.
H. If the housing of the shop has been fitted up, and the fit-up standard is confirmedly
higher than that of housing compensation, the gap can be compensated by the
railway construction unit.
I. The shop shall be informed of the removal 60 days in advance in order to get
prepared.
5.4 Resettlement and Rehabilitation Plans for Railway Internal
Demolition
5.4.1 Resettlement and Rehabilitation Plans for Railway Clerks
(1) The impact of Wu-Guang Project on the residential housing of railway clerks
involves 783 persons of 256 households, including 595 persons from 198
households in Furong District of Changsha, 165 persons from 53 households in
Xianning City and only 23 persons from 5 households in Guangzhou.
(2) The affected railway clerks, like other affected residents outside the railway sector,
should also be compensated for their demolished housing, at the compensation
standards shown as follows: 700 yuan/m2 for brick-&-concrete housing; 400
yuan/m2 for brick-&-wood housing and 150 yuan/m2 for simple-structured housing.
As for the tansition fee and removal fee, they should be the same as those outside
the railway sector.
(3) The affected railway clerk shall be informed of the removal 60 days in advance in
order to have enough time to get prepared.
(4) As there are very few clerks affected in Guangzhou, GRCC will disburse the
compensation to the individuals for them to buy commodity housing downtown.
88
(5) As there are quite a number of affected households in Changsha, GRCC has decided
to buy commodity housing convergently near Changsha Railway Station for them,
the average size for each household being 65 m2. If the original housing is less than
the average 65 m2, the gap will be made up free of charge; if the household want to
buy the area exceeding 65 m2, they will have to pay for the exceeding part on their
own. The affected 198 households in Changsha have been living in the housing
transformed from workshop and office housing for a long time, without lavatory or
even kitchen, in poor living condition. They are happy to have such opportunity to
move into commodity housing.
(6) ZRB will set up new dormitory building on railway-owned land for the 53
households in Xianning, Hubei Province. The living environment and quality of the
53 households will then be greatly improved. The construction of new housing will
absolutely go before old housing demolition.
(7) In Guangzhou, the project impact also involves the unlawfully set structure on the
railway by three railway households, 400 m2 in size, dwelt by 11 persons. The
compensation paid by GRCC according to the standard is 200 yuan per square meter,
and the removal fee 460 yuan per lorry shift The three households have long been
living in shabby sheds and afflicted by roaring trains. And now they could use their
compensation of several ten thousand yuan, together with their own money, to buy
commodity housing in the urban district of Guangzhou.
5.4.2 Resettlement and Rehabilitation Plans for Railway Enterprises and Shops
(1) Wu-Guang Project involves 28 railway enterprises; 7 in Guangzhou, 10 in Changsha,
5 in Wuhan, 1 in Shaoguan, 3 in Puqi and 2 in Xianning. Railway enterprises enjoy
the same relocation policy as the non-railway enterprises. Each relevant railway
bureau shall conduct old housing demolition and new housing construction on
railway-owned land, strictly following the stipulation of construction prior to
demolition. The railway enterprise removal will not give rise to transition problem,
nor cessation of production and business, much less unemployment even to one
89
individual of the enterprises.
(2) The railway shops involved are mainly found around Changsha Railway Station.
The 6 involved shops are owned by the Passenger Service Company of Changsha
R- 'way Station, initiated to provide jobs for the children of the railway clerks. In
o; -.re jobs for those children, Changsha Railway Bureau has decided to
find nev uusiness zone near the station on railway-owned land for them. The old
shops will not be demolished until the new ones have been set up. Therefore, the
removal will not -sult in a cessation of business and unemployrn -It The
compensation tc -s will be done in the same way as the shop. outside
railway sector.
89.
6 Organizational Institutions
The organizational institutions for the expansion engineering of Wu-Guang rail section,
a complex system, involve not only 20 odd cities and counties in Guangdong, Hunan
and Hubei, but the coordination between the MOR and local governments, between the
two authorized agents of the MOR, GRCC and ZRB. Many executive institutions and
relevant departments from several administrative levels and subsystems will take part in
the designing, preparation and undertaking of the project.
631 Institutional Establishments
(1) A successful execution of the resettlement for the Capacity-Expansion Project by
and large depends on a forceful network of migration executive institutions. In view
of the difficulties in the coordination between provinces crosswise and those between
the MOR and the provinces vertically, a network of resettlement institutions is
extremely necessary for accomplishing planning, organizing, coordinating and
supervising resettlement action in order to reach the desired goal.
The migration institutional network for the Capacity-Expansion engineering is
composed of two systems, one being the land acquisition and resettlement organizations
of the railway construction units, as the project owner, the other being the land
acquisition and resettlement organizations of local govemments of all levels, as the
contractor.
(2) system 1: the land acquisition and resettlement organizations of all levels of the
railway construction units:
90
I
GRCC ZRB
IIEngineering Headquarters Engineering Headquarters
ofGRCC of ZRB
I ILand Acquisition & Resettlement Land Acquisition & Resettlement
Section of the Engineering Section of the Engineering
Headquarters Headquarters
I IStaff in Charge of Land Staff in Charge of Land
Acquisition & Resettlement Acquisition & Resettlement in
in the Construction Units the Construction Units
91
(3) system 2: the land acquisition and resettlement organizations of all levels of local
governments:
l l .Guangdong Provincial Hunan Provincial Hubei Provincial
Leading Group for Leading Group for Leading Group for
Supporting Raiway Construction Supporting Railway Construction Supporting Railway Construction
I I IGuangdong Provincial Hunan Provincial Hubei Provincial
Land Adminisitration Bureau Land Adminisitration Bureau Land Adminisitration
Prefecture or Municipal Prefecture or Municipal Prefecture or Municipal
Land Adminjstration Bureau Land Administration Bureau Land Administration Bureau
I ICounty Land County Land County Land
Administration Bureau Administration Bureau Administration Bureau
Acquisition Office Acquisition Office Acquisition Office
I . I ITownship Resettlement Township Resettlement Township Resettlement
Working Group Working Group Working Group
Village Commission and Village Commission and Village Commission and
Villager Representatives Group Villager Representatives Group Vilager Representatives Grop
(4) Other Institutions
the external independent monitoring & evaluation agency
Research Institute of Foreign Capital Introduction & Utilization, Southwest Jiaotong
University
the designing unit The 4h Surveying & Designing Institute of the MOR
92
6.2 Responsibility of the Institutions
6.2.1 Responsibility of All the Resettlement Institutions of the MOR
(1) Land Acquisition & Resettlement Working Group of the MOR.
The Land Acquisition & Resettlement Working Group of the MOR, made up of the
persons responsible from the Foreign Capital Introduction & Utilization Office of the
MOR, is the supreme power institution responsible of the land acquisition and the
resettlement of displaced population in the project functioning in the capacity of the
project owner. Its main responsibility is to strengthen the leadership for key
engineering projects and ensure a smooth progress of the land acquisition, housing
demolition & relocation and resettlement for the Capacity Expansion Project. It is
responsible of coordinating GRCC and ZRB. Its staff members, each specialized in
one sector of job, include the experienced specialists in migration work from Foreign
Capital Introduction and Utilization Office and professionally specialized technicians
and clerks with rich experience behind from GRCC and ZRB.
(2) Personnel of the MOR Specifically Engaged in Land Acquisition and Housing
Demolition
In order to strengthen migration resettlement, a staff member is appointed in the
Foreign Capital Introduction & Utilization of the MOR to be specifically engaged in
land acquisition and housing demolition, who has the following responsibilities:
A. Organizing, during the feasibility research stage of the project, the relevant units to
work out the framework for resettlement plan as the basis for project appraisal;
organizing, 6 months prior to the construction commencement of the project, the
relevant units to compile and complete the resettlement action plan (RAP);
B. Examining regularly, in accordance with the RAP, the execution of the resettlement
of the project on the part of the local govemments and railway departments;
C. Keeping close supervision of the progress of resettlement work, conducting
93
marnagerial work through computation and regularly renewing and enriching data,
and providing relevant data to external monitoring institute;
D. Investigating and gathering information irregularly on the spot of land acquisition
and housing demolition; punctually reporting the problems discovered to either the
local government and the relevant organs of the MOR in order to have the problems
solved promptly;
E. Accompanying the officials from the World Bank to the site of land acquisition and
housing demolition to get to know the progress; managing consultation and
subsequent procedures of negotiation;
Managing the compiling and examination of reports concerning resettlement to be
submitted to the World Bank.
(3) GRCC and ZRB
These are the leading bodies made up of the leaders of GRCC and ZRB, and the heads
of the capital construction departments of GRCC and ZRB, with the main responsibility
of strengthened leadership over the project implementation within their jurisdiction,
coordination the resettlement institutions under their leadership, supervising and
examining the work of the subordinate engineering headquarters, ensuring a smooth
progress of land acquisition and resettlement within their jurisdiction.
(4) Engineering Headquarters of GRCC, Engineering Headquarters of ZRB
Both headquarters, as the agencies of GRCC and ZRB respectively, are in full charge of
handling attains in land acquisition and resettlement within each administrative scope,
including the application to the departments concemed for the design license for land
utilization and the construction license for land utilization, the entrusting of the
investigation institution with measuring of the scope and degree of project impact, the
supervision and coordination in the drawing-up of RAPs, the signing of agreements and
contracts with local land bureaus, township governments and villagers, the compiling of
the work progress schedule, the provision of resettlement budget, the management of
compensation disbursement, the supervision of the execution of resettlement and the
94
handling of troubles rising from execution, the close connection with local governments,
the submission of intemal monitoring reports to the Bank, the examining of
independent mentoring & evaluation reports and the handling of grievance appeals.
(5) Land Acquisition & Resettlement Section of the Engineering Headquarters.
As the subordinate standing institution of the headquarters, it is engaged in the actual
work of acquisition and resettlement and carries out all the tasks the headquarters
assigns to it. The section is usually made up of 10-14 members who work almost the
whole day at the construction site and keep a close contact with the local governments
especially governments at the gross-roots level and the affected population and the
construction units. It is a very important operational body in that the ideas and
opinions of the local governments and the affected population will be notified to the
headquarters by it and the mandates from the headquarters will be carried out by it.
(6) Staff in Charge of Land Acquisition & Resettlement in the Construction Units
Railway construction projects have their particularity in that there are usually quite a
number of construction units simultaneously undertaking construction of the same or
different type on the same line or various lines. Therefore, the headquarters requires
that each construction unit have at least one staff member specialized in acquisition and
resettlement. As a matter of fact, the head of each construction unit often sees to
acquisition and resettlement all by himself in spite that there is already an official in
charge of this matter.
6.2.2 Responsibility of the Land Acquisition and Resettlement Institutions of
Local Governments
(1) Provincial Leading Groups for Supporting Railway Construction
As the work conceming land acquisition and resettlement is of heavily policy-relying
nature, the provincial governments have attached great importance to it. A leading
body for aiding railway construction has been formed in each of the three provinces
95
involved headed by a vice-governor responsible of state key construction, with the
persons in command from the provincial planning commission, land bureau, design
office and some other relevant departments as the group members. For a better
coordination, the leading group has also invited the leader from the railway bureau to be
the second head or the deputy secretary-general of the group.
The main responsibility of the leading group of each province is to carry out the polices
by the state and the province about railway construction, supervise and spur the units
concemed accomplish railway construction projects in time and in good quality
according to the approved scale, standard, investment, engineering schedule and annual
plan, supervise and urge the local government of all levels to administer unitarily the
allocation and acquisition of land to be utilized for railway construction in conformity
with the relevant policies of the state, settle problems in acquisition and resettlement
through mediation, contemplate preferential policies and implementation methods for a
speedier railway construction and have them carried out, urge the departments
concerned to collect and allot fund indispensable to railway construction punctually and
supply the needed material and facilities to the railway construction, supervise the use
of resettlement compensation, mobilize the enthusiasm of every party to transact
resettlement successfully, tackle the major issues rising from the construction promptly
and ensure a smooth implementation of state key construction projects.
(2) The Provincial and Municipal Land Administration Bureaus
As institutions contracting the land acquisition, housing demolition & relocation and
resettlement for railway construction projects in the capacity of their govenmments, the
provincial and municipal land bureaus have very important function in that they have
the power to examine and ratify any requests for land acquisition and resettlement,
negotiate on behalf of local govemments with project owners about compensation
standards, formulate various policies and regulations for local resettlement and
supervise their execution, participate in the drawing-up of resettlement action plans,
sign contracts on acquisition, demolition and resettlement with project owners on behalf
of local governments, supervise the implementation of resettlement and the allocation
and utilization of acquisition and resettlement fund, coordinate project owners and local
96
governments and handle contingent disputes, problems and appeals.
(3) Land Acquisition Offices
This is a unique creation by Hunan province in the formation of institution different
from Guangdong and Hubei provinces. In Hunan, every prefecture and city has its
own land acquisition office subordinate to the corresponding land bureau. The land
acquisition and housing demolition contracted by the Provincial and Municipal Land
Bureaus shall be transacted by the land office acquisition which consists of the land
acquisition section, the housing demolition & relocation section, the resettlement
section, the reconstruction section, the policies and regulations section and the financial
affairs section. The offices have been playing an important role acting on the principle
of "centralized designing, land acquisition & housing demolition, administration and
developing".
(4) County Land Administration Bureaus
County land bureaus are the executive institutions of acquisition and resettlement.
They are responsible of acquisition and resettlement in the counties in accordance with
the overall arrangement by the province and the city. They prepare the resettlement
plans for the county and see. to their being carried out according to the population
statistics provided by the investigation department and the resettlement polices
formulated by the province and the city, direct and supervise the work of township
resettlement working groups, mediate between the state, the collective and the
individual, see to the proper use of compensation fees collected, submit regular reports
on acquisition and resettlement of the county to the province and the city, cooperate
closely with construction units to ensure a smooth implementation of land acquisition,
housing demolition and resettlement within the county and receive grievance appeals.
(5) Township Resettlement Working Groups
They are institutions headed by town administration chiefs with the township land
administration offices as their functioning body. Their main duties are to provide
97
assistance in project survey, organize mass participation, publicize resettlement policies,
conduct and keep account of the resettlement in the township, sign agreements on land
acquisition and housing demolition & relocation with the affected villagers, take charge
of the disbursement and utilization of compensation fees, cope with disputes and
difficulties rising from acquisition and resettlement and provide information concerning
resettlement to the higher authorities, the project owners and the external monitoring
institutions.
(6) Village Commission and Villager Representative Groups
They are the gross-roots institutions for acquisition and resettlement, whose main
responsibility is to choose location for population displacement, allot housing ground
site to displaced households, make intemal land reallocation, allocate compensation for
housing demolition and young crops, offer help to the poor households, mobilize the
villagers to production developing and report the opinions and proposals from the
villagers to the high authorities, the project owners and the external independent
monitoring institutions.
6.2.3 Other Institutions Concerned
(1) External Independent Monitoring Institution
The extemal independent monitoring institution of this project is the Research Institute
of Foreign Capital Utilization of Southwest Jiaotong University, whose major
responsibility is to assist the departments concemed in preparing resettlement action
plans, make on-the-spot investigation and provide M&E reports to the Bank, the project
owner and the local governments, run training classes for the personnel involved in
acquisition and resettlement from the local governments and the project owner unit and
offer technical consultation in data gathering and processing. Refer to Chapter 8 for
the detailed description about the external dependent monitoring institutions.
(2) Designing Institutions
98
The designing agency for this project is the 4h Surveying and Designing Institute of the
MOR, which, as the engineering designer for a project covering a 1082km-long rail line,
is also playing a remarkable role in land acquisition and resettlement with regard to, on
the one hand, their effort to optimize the design and minimize the land acquisition and
housing demolition and on the other, their punctualness in working out engineering
drawings and their promptness in altering the design in order that resettlement can come
into action as early as possible.
6.3 Coordination and Liaison between
the Institutions
The Capacity Expansion Project has involved many institutional systems, which
necessitates a good coordination and liaison, not only between the MOR and the
involved provinces, but also between the provinces, and between GRCC and ZRB. In
addition, what is equally important is the coordination between the headquarters and the
construction undertaking units, the local governments and the project owner on the one
hand and the supervision units and the designing units on the other, the project owner
and construction units on the one hand and the local governments on the other. The
land acquisition and resettlement for the project will be undoubtedly hampered if
there's no good coordination between institutions.
The MOR and Guangdong, Hunan and Hlubei provinces all attach great importance to
coordination. They often hold joint meetings, exchanging information, conversing one
another and sending the minutes to all institutions concerned. Some other measures
such as information announcing and revealing are also taken to strengthen the
coordination.
MOR and the provinces of Hunan, Hubei and Guangdong have entered into contracts
specifying implementation procedures (see appendices). Issues or problems arising
during implementation are to be resolved locally when feasible. Issues that cannot be
resolved at the local level will be referred to a working group, including a provincial
vice-governor and a MOR vice-minister, for resolution. No change in compensation
99
rates, or eligibility criteria for entitlements is to be made without prior approval of the
Bank.
6.4 Measures Taken to Enhance the Capabilities
of the Institutions
(1) More Able Personnel
Both the MOR and the local govermments have carefully chosen persons experienced in
acquisition and resettlement with managerial skills and data processing skills to form
the resettlement institutions of all levels.
(2) More Training
Beginning from the second half of 1998, the MOR will start training classes of
"Displaced Population Resettlement for the World Bank Loaned Projects" for the major
staff members engaged in acquisition and resettlement from the institutions of both
railway and local systems to learn and have a good grasp of China's resettlement
policies, the Bank's requirements and the successful cases of other administrative
sectors in China and learn to master the skills of collecting and processing data.
(3) To reinforce internal monitoring and evaluation and resolve problems wherever
they are found.
(4) To reinforce external independent monitoring and evaluation and set up the
early warning system.
100
(5) Network of Institutions
Land Acquisition & Leading Groups for
Resettloment Worksing Supporting RailwayCVroup of the MOR Constmnction of the
c i sThree Pro-inces
GRCC Land Bureaus of
ZRB the Thrce Prov'ulcs. _ ..
Enginesring Prefectqui nd _ _ Headquarts Munficipal LandExal
of GRCC dsBurnau Inintdent
Engineering I A&I1E AgencyHcadquwtes
Land A&R Sections County Lan}d
of the Enginerig Bureaus
Headquarters
Tov6nship Resettlement Working Groups
Vilage Conunissions and Village r
Rspresentative Groups
Notes: 1. The Prefecture or Municipal Land Acqliisition Offices, as specific orly in Hunan, are
not listed in the network.
2. The design unit is not listed.
t ~~101
7 Consultation, Mass Participation and
Grievance Appeal Conduits
7.1 Consultation
Consultation is constantly adopted during the implementation of land acquisition and
resettlement of the Capacity Expansion Project chiefly on the compensation standards
for land acquisition and housing demolition, the methods of housing reconstruction and
population resettlement.
Consultation is mostly between (1) the MOR and the provinces and cities; (2) the
railway construction headquarters and the prefectures, cities and counties; (3) the local
land administration departments and the land expropriated townships villages, and
production groups; and (4) township, villages and production groups and farm
household.
(1) The consultation between the MOR and provinces (Guangdong, Hunan and Hubei)
is mainly about the amount of land needed for the railway project, the time for using the
land and the compensation standards for land acquisition and housing demolition, -etc.
Such consultation was held many times during the project preparatory stage (between
1997 and 1998) before the commencement of Wu-Guang project engineering. In May
1998, Cai Qinghua, vice-minister of the MOR and his party went to the three provinces
to hold talks with the vice-governors who are responsible of state key construction
projects in their own provinces; they reached a consensus on acquisition and
resettlement and formed the minutes.
(2) The consultation between Zhuzhou Project Engineering Headquarters and Wuhan
Engineering Headquarters on the one hand and the prefectures, cities and counties
concerned along the line of Wuhan -Guangzhou section on the other is about the
amount of land to be acquired, housing and attachment to be demolished, the number of
102
population to be affected and the compensation standards for housing and attachment.
Such consultation was held many times before the land acquisition and will continue to
be held during the land acquisition, substantially between the Land Acquisition &
Resettlement Sections of the Headquarters and the County Land Bureaus, detailed even
on every sub-project and every piece of land. The land acquisition and housing
demolition & relocation for each subproject is accomplished not without quite a
number of or even several scores of rounds of consultation.
(3) The consultation between the local land administrative departments and the land
expropriated townships, villages and production groups is usually held before land
utilization and housing demolition. According to the Land Administration Law, any
other institutions (including project owners) have no right to undertake land acquisition
except county land administration bureau, the only authorized department to acquire
land from the rural areas on behalf of the state. However, even entitled to conduct
centralized land acquisition for state construction, the county land administration
departments will have to consult with land expropriated townships, villages and groups,
mainly about the compensation standards (for land, housing, attachment and population
resettlement) and resettlement plans (for housing reconstruction, conversion of
residential registration, employment, self-employment, etc.). The leaders of townships,
villages and groups will be at the consultation.
(4) The consultation between townships, villages and groups on the one hand and
village households on the other (or between the demolisher and the demolished in cities)
is mainly about the distribution and utilization of compensation fees, the measures for
housing reconstruction, worker taking-in and land relocation. The affected households
will express their reasons for compensation and demands for compensation whatever at
the consultation. Every household will eventually sign agreements on land acquisition,
compensation and resettlement with the township, the village and the group. Such
consultation is chiefly attended by household heads and, in some consultation, by
villager representatives.
103
7.2 Meetings on Displaced Population
During the negotiation on land acquisition and housing demolition, two kinds of
meetings will be held in each village or group on population to be displaced:
(l)meetings of village representatives and (2) all the villagers.
(1) Meetings of village representatives are presided over by the county land bureau or
the township government. The purpose is to get across the significance of the project,
the scope and site of land acquisition, the time for acquisition, the relevant laws,
policies and regulations. The meetings are usually called at the same time as the
consultation and negotiation before the land acquisition for a certain subproject.
(2) Meetings for all villagers are called by the village commission, attended by all the
villagers or the household heads with the purpose of expounding the relevant lans,
policies and regulations, informing the villagers of the scope and amount of land to be
acquired, the compensation standards, the measures for housing reconstruction and
production resettlement. The meetings are usually held during the implementation or
land acquisition and the time limit for signing agreement.
In addition to the above two forms of meeting, the railway construction unit and the
resettlement institution will put up posters in residential quarters before they make a
decision with the aim to consult the opinions of the affected population and ask for their
supervision and examination. This is especially true with compensation standards which
must be made known in the affected area in notice.
7.3 Mass Participation
Mass participation will take place alongside (1) during the preparatory stage of the
project and (2) during the implementation of the land acquisition for the project,
involving (1) consultation; (2) meetings on population displacement; (3) investigation
on property loss and socioeconomic survey; (4) discussing about compensation standard;
(5) choice of housing reconstruction site; (6) setting up new housing by the villagers
104
themselves; and (7) seeking job by oneself
(1) During the preparatory state of the project, that is from 1997 to 1998, mass
participation was chiefly concerned with socioeconomic survey, investigation on
property loss, consultation meetings and the publicizing of land acquisition affairs.
Consultation meeting is about the discussion and conferring among institutions of all
sorts at all levels on the issues conceming land acquisition and compensation, with the
purpose of getting the villagers to know about the land acquisition for the project so that
they will be able to get prepared for that. Investigation on property loss and the
socioeconomic survey by the engineering design institution and the RAP compiling
institution entail the participation of the masses in the affected areas.
During the compiling of RAP, a typical investigation and a sample investigation were
made to the cities, prefectures, counties, townships, villages and households whose land
is going to be acquired, participated by households, village and group leaders, township
heads, the land administration departments, the planning departments and the statistical
departments at county level, and the relevant departnents of municipal and prefectural
level.
(2) During the implementation of the land acquisition for the project (1998-2000),
there will be an extensive mass participation on the part of the affected population in
the measuring and determining of property loss, the discussion about the compensation
standards, the signing of agreements on the compensation for households, the choice of
new housing ground site, the demolition of the old housing by the villagers themselves
in order to use the material, the construction of new housing by the villagers themselves
and self-employment. Mass participation, judging from above facts and measures, is
encouraged in China in order to arouse the masses' enthusiasm and achieve a more
desirable resettlement result.
105
7.4 Grievance Appealing Channel
During the actual implementation of the land acquisition and the resettlement of
displaced population, if the affected population have any problems, grievances and
discontent regarding land acquisition, housing demolition, compensation payment and
resettlement, they may appeal to either (1) the project owner, (2) the external
independent monitoring institution, (3) the township and the county land administration
department, (4) the county government or (5) legal action.
(1) Appealing to the Project Owner Unit
The project owner is the eventual user of the land acquired, and has the duty to resolve
problems rising from land acquisition, housing demolition and resettlement. The
project owner of this project is the MOR with Zhuzhou Headquarters and Wuhan
Headquarters functioning in its capacity during the project engineering, and ZRB and
GRCC executing the managerial duty after the project engineering is completed.
Therefore, appeals to the project owner may go to either of
A. the MOR;
B. GRCC and ZRB;
C. Zhuzhou Headquarter and Wuhan Headquarters of the Electrification Capacity
Expansion of Wuchang-Guangzhou Rail Line.
(2) Appealing to the External Monitoring Institution
The external monitoring institution conducts chasing-up investigation on the production
of affected villages several times in the year during the monitoring period, and evaluates
the resettlement consequences and submits its M&E reports to the project owner, the
local institutions conducting land acquisition and housing demolition and the World
Bank. The affected persons, therefore, may express their discontent and grievances to
the extemal monitoring institution, which is obligated to listen to and find out the
dissentient and grievances.
106
(3) Appealing to the Township and the County Land Administration Department
According to the administrative procedure of the local govemment, the discontent and
grievances rising from acquisition and resettlement should first be handled by the land
administration department. In case the land administration department is unable to
resolve the grievances, the apparel may turn to other conduits. These are the conduits
of the land administration departments the apparel may go:
A. the municipal land administration bureau;
B. the county land administration bureau; and
C. the township land administration bureau.
(4) Appealing to the County Govermment
If the discontent can not be resolved in the land administration department, it can be
appealed to the "correspondence and visitation department" of the local governments,
set up by various levels of government organs to handle letters and visits from the
masses.
The appealer may express his discontent orally or in written form to the correspondence
and visitation departments, which may coordinate departnents concemed to have the
matter resolved. If again the discontent can not be resolved in this way, the
correspondence and visitation departments will report the matter to the leaders of the
local govermment
(5) Legal Action
If discontent and grievances can not be resolved through the above 4 conduits, theappealer may resort to legal action by bringing the case to court
107
a Monitoring and Evaluation
8.1 Goals of Monitoring
Monitoring on resettlement refers to the collection and provision of data concerning the
resettlement activities and the resettlement consequences. Evaluation means the
analysis and appraisal of data gathered in monitoring by referring to the comparable
indexes (such as the plans, the former conditions before removal, and the conditions of
non-displaced population).
The World Bank has warned that every project is bound to be faced with a lot of
particular problems in its execution. Some of these problems are unforeseeable. The
purposes of monitoring and examining are, firstly, to ensure a punctual execution of the
plan as scheduled; secondly, to find out problems and have them resolved then and there;
and thirdly, to have the collected data fed back to the designing, executing and
managing work of the project.
The evaluation on displaced population resettlement is expected to examine and decide
whether the production and livelihood of displaced population are appropriately
resettled in sociological and anthropological perspectives. Monitoring and evaluation
are not the ends in themselves; the conclusions drawn from monitoring and evaluation
are expected to feed back to the execution and management of the project so that any
inappropriateness can be redressed promptly, or some alternation can be made to the
executive plan, or the existing problems can be solved.
After the loan to Wu-Guang Project enters into force, regular supervision will be
organized by the World Bank annually, with the relevant parties examining
implementation progress. If it appears that RAP terms themselves are inappropriate for
effective implementation, a resettlement mid-term review may be scheduled to allow
the relevant parties to devise new approaches or revise the RAP.
Resettlement monitoring falls into two kinds: internal and external monitoring.
108
Intemal monitoring is carried out by the population resettlement office with the purpose
of keeping the institutions of the resettlement network in good operation following the
schedule and the principles of RAP. A report of internal monitoring is submitted every
quarter of or half a year.
External independent monitoring is to be conducted by an independent social agency to
chasing-up investigation on the implementation of land acquisition, resettlement and
rehabilitation and evaluate the whole process from an impartial, comprehensive and
long-term point of view so as to secure the benefit of the displaced population. The
general task of extemal independent monitoring is to provide all sorts of information
and foresight, based on chasing-up investigation and data collection, to the project
resettlement office and the project administration institution in order that any problems
concerning population displacement and resettlement can be solved promptly. Two
reports on external monitoring will be submitted annually in the first two years; and
beginning from the third year, one report annually.
8.2 Internal Monitoring
The internal monitoring on this project is conducted by the Land Acquisition and
Housing Demolition Sections of Zhuzhou Engineering Headquarters and Wuhan
Engineering Headquarters.
The following are the steps of the procedure for internal monitoring:
(1) The Land Acquisition and Housing Demolition Offices design and establish
the information flow patterns and data bank systems;
(2) The Land Acquisition and Housing Demolition Offices store up investigation
data and the socioeconomic data of the affected area;
(3) During the project implementation, the Acquisition and Demolition Offices
copy down the relevant background information of individuals, households
and units from the city, county and township according to the prescribed
patterns;
(4) The Acquisition and Demolition Offices make periodic sampling on
109
townships and villages to check the copied data and progress.
Internal monitoring has its focus on:
(1) the progress of land acquisition;
(2) the progress of housing demolition;
(3) the progress of enterprises relocation;
(4) the measures conceming housing reconstruction;
(5) the resettlement measures for surplus labourers;
(6) the forms of mass participation;
(7) the disbursement of compensation fees;
(8) the choice and training of staff members for resettlement institutions
8.3 External Monitoring
The Research Institute of Foreign Capital Utilization of SWJU has been invited to
undertake the external independent monitoring of this project. Southwest Jiaotong
University, one of the key universities in China, enjoys a high reputation both at home
and abroad. Its Research Institute of Foreign Capital Utilization, a professional
research institute at the study of the resettlement of displaced population, has a staff
consisting of specialists and technical personnel in sociology, anthropology, managerial
science, economics, evaluation technology, information processing, system analysis, etc.
The institute has rich experience in monitoring population displacement and
resettlement and that under the Work Bank loaned projects. Listed in the following is
only part of the work it has done under either the Bank loaned projects or non-Bank
loaned projects:
(1) The monitoring and evaluation of the resettlement of displaced population in the 6t
World Bank financed Chinese railway projects;
(2) The monitoring and evaluation of the resettlement of displaced population in the
World Bank Financed Yunnan environmental protection projects;
(3) directing the drawing up of RAP for the World Bank financed Sichuan electricity
power transmission project;110
(4) The making of the aid plan for the later stage of resettlement implementation for
Sichuan Tongjiezi Power Station.
The extemal monitoring of this project has the following four stages as its procedure:
(1) the preparatory stage, to decide on the target persons and scope of investigation and
draw up the outline and forms for the investigation;
(2) The investigation stage, to investigate on the target persons at all levels and gather
information and material;
(3) The information feedback stage, to feed the information collected in the
investigation back to the construction headquarters and the MOR and consult with
them to have the problems found out in the investigation resolved;
(4) the report drawing-up stage, to draw evaluation conclusions and work out M&E
reports, based on the sorting out and diagnosis of the collected data and material.
These are the norms for external independent M&E to go by:
(1) Operation Guide 4.30 of the World Bank's Operation Directive concerning
involuntary resettlement;
(2) Relevant polices and legal corrosions regarding acquisition and resettlement of
both the state and localities;
(3)the action plan of acquisition and resettlement for this project.
(4) The security of a better or at least the maintenance of the former income and living
standards for the displaced population.
The investigation methods of the external M&E of this project involve sample
investigation, typical case investigation, focus investigation, group interviews,
interviews with important persons in the know, close-up interviews, observing and
learning, looking up literature documents, information checking in data bank, etc.
Extemal M&E has its main interest in the consequences of resettlement, the economic
income and the living standards of the displaced population. The following are the
main aspects for the external M&E of this project:
111
(1) analysis of the impacts resulting from the land acquisition and housing demolition;
(2) appraisal of the compensation standards;
(3) supervision over the allocation and utilization of compensation fees, including
collective land compensation;
(4) monitoring on the housing resettlement of the displaced population;
(5) monitoring on the production;
(6) monitoring on enterprises relocation;
(7) monitoring on the living standards of the displaced population;
(8) monitoring on the community rehabilitation;
(9) monitoring on the grievance appealing of the displaced population;
(10) monitoring on the operational efficiency of the resettlement network.
8.4 Report Submission
Monitoring reports for this project fall into reports of the implementation progress of
resettlement (intemal monitoring reports) and external monitoring reports on
resettlement
The implementation progress reports are written and submitted by Zhuzhou Engineering
Headquarters and Wuhan Engineering Headquarters while the extemal monitoring
reports are written by the Research Institute of Foreign Capital Utilization of SWJU.
An implementation progress report will have to be written and submitted once every
half a year and an external monitoring report, once a year (or twice a year in the busiest
period of land acquisition).
The external monitoring reports, according to the procedure, will by submitted by the
Research Institute of Foreign Capital Utilization of SWJU to the Land Acquisition
Section of Foreign Capital Utilization Office of the MOR who will forward them to the
World Bank.
112
9 The List of Right
Items Population Policies Standardsaffected affected
Collective- 1. villages l. given land compensation fee, 1. 150000 yuan per muowned land and groups resettlement subsidy and young crop in Guangzhou;(Guangdong 2. contractors compensation; 2. 33000 yuan per muProvince) of the land 2. land compensation fee to be used by in Huadu and
the village collective 'to develop Shaoguan;collective economy; 3. 20000 yuan per mu
3. resettlement subsidy to be used to in Yingde andresettle the labourers caused by land Qingyu;acquisition; 4. 15000 yuan per mu
4. the affected persons to get e full in the rural areasyoung crop compensation fee for the along the line;actual loss of the year; 5. young crops to be
5. the compensation rate being 10 to fully compensated80 times of the average annual output according to thevalue actual loss of the
year
Collective- l.villages and l.given land compensation fee, 1. 40000 yuan per muowned land groups resetflement subsidy and young crop in Changsha;(Hunan 2.contractors compensation; 2. 35000 yuan per muProvince) of the land 2.1and compensation fee to be used by in Hengyang and
the village collective to develop Zhuzhou;collective economy; 3. 30000 yuan per mu3.resettlement subsidy to be used to in Yueyang andresettle the labourers caused by land Chenzhou;acquisition; 4. 15000 yuan per mu4.the affected persons to get the full in the rural areasyoung crop compensation fee for the along the line;actual loss of the year; 5. young crops to be5.the compensation rate being 12 to 30 fully compensatedtimes of the average annual output value according to the
actual loss of the
Collective- L.villages and L.given land compensation fee, 1. 40000 yuan per muowned land groups resettlement subsidy and young crop in Wuhan;(Hubei 2.contractors compensation; 2. 15000 yuan per muProvince) ofthe land 2.1and compensation fee to be used by in Xianning;
the village collective to develop 3. 15000 yuan per mu
113
collective economy; in Puqi;3.resettlement subsidy to be used to 4. young crops to be
resettle the labourers caused by land fuilly compensated
acquisition; according to the
4.the affected persons to get the full actual loss of the
young crop compensation fee for the year
actual loss of the year;
5.the compensation rate being 12 to 30
times of the average annual output value
Above- The owners 1. the above-ground attachment of the 1. ordinary trees: 35-60
ground acquired land to be appropriately yuan PCs;
attachment compensated according to the 2. fruit trees: 15--1500
relevant policies of he local yuan PCs;
government and the current market 3. water well: 300-500
price; yuan PCs;
2. no compensation to be paid for the 4. tombs: 250--1000
hastily set up attachment after the yuan PCs;
beginning of consultation; 5. fence wall: 25-80
3. the compensation for above-ground yuan/m3;attachment to be directly disbursed to 6. cement sunny ground:
:__________ ____________ the affected persons 25--80 yuan/m3Private- The owner Altemative resettlement methods: 1. concrete-brick
owned and the user 1. The housing ground site is assigned structured: 500-
housing being the within the village scope. After the 1200 yuan/m3;
(rural areas) same one affected person gets his 2. brick-wood
compensation at the reconstruction structured: 250-800price, he shall build his new housing yuan/m3
all by himself. 3. simple-structured:
2. The housing compensation can be 100-250 yuan/m3;
calculated at the reconstruction price 4. removal fee: 350-
and be realized in the form of cash. 460 yuan per lorryThe affected person shall look for shift;
new housing all by himself. 5. transitional fee: 3-
3. If the affected person has actually no 4.5 yuan/month/m3
housing ground site, the government
shall find location in urban area to
build commodity housing.
4. The affected person gets removal
subsidy fee and transitional subsidyfee.
Private- The owner Alternative resettlement methods: 1. concrete-brick
owned and the user 1. The project owner or the local structured: 500- 1200
114
housing being the government provides the yuanlm3;
(urban areas) same one resettlement housing of similar 2. brick-woodvalue, same size, with similar structured: 250-800
conditions in the nearest possible yuanlm3;
location. 3. simple-structured:
2. The housing compensation can be 100-250 yuanlm3;calculated at the reconstruction 4. removal fee: 350--460
price and be realized in the form of yuan per lorry shift;cash. The affected person shall look 5. transitional fee: 3-4.5for new housing all by himself. yuan/month/m3
3. The affected person can be resettled
with commodity housing, with theexcess housing area to be paid for
by the affected person himself.4. Transitional fee can be disbursed
according to the actual transitional
time.5. The affected gets removal fee.
Persons The owner l. The resettlement housing shall be 1. concrete-brickdwelling in determined according to household structured: 700
publicly- types. yuan/m3;owned 2. The owner shall possess the 2. brick-woodhousing ownership of the equal area free of structured: 400
charge and pay for the excess area of yuan/m3;
the resettlement housing. 3. simple-structured: 1503. If the resettlement housing is smaller yuan/m3;
in size tan the original one, the 4. removal fee: 350--460shortage shall be compensated at the yuan per lorry shift;reconstruction price. 5. transitional fee: 4.5
yuan/month/m3
The user 1. The user shall possess the right tolive in the housing free of charge.
2. If the resettlement housing is
privately owned commodity one, the
excess area shall be paid for by theuser.
3. The affected can get removal fee.
- 115
Enterprises The owner Altemative resettlement methods: 1. concrete-brick
outside the and the staff I. The demolisher reconstructs the structured: 500--1200
railway members housing on the same size and with the yuan/m3;
sector samne accessory structures at the 2. brick-woodreconstruction price. structured: 250--800
2. The compensation fee can be yuanlm3;
calculated at the reconstruction price 3. simple-structured:and be realized in cash, and the 100-250 yuanlm3;
enterprise shall therefore manage the 4. compensation for the
reconstruction all by its self. cessation of
3. Any cessation of production and production or work:
work resulting from removal is 400-1000 yuan/per
compensated by the demolisher by capita/month;
the month. 5. removal fee: 350-460
4. The affected can get removal fee and yuan/per lorry shift;
transitional fee. 6. transitional fee: 3-45
5. Try to prevent the market yuan/month/m3environment of the enterprise from
negative impact as much as possible.
Enterprises The owner Altemative resettlement methods: 1. concrete-brick
within the and the staff 1. The demolisher reconstructs the structured: 700
railway members housing on the same size and with the yuan/m3;
sector same accessory structures at the 2. brick-wood
reconstruction price. structured: 400
2. The compensation fee can be yuan/m3;
calculated at the reconstruction price 3. simple-structured: 150
and be realized in cash, and the yuan/m3;enterprise shall therefore manage the 4. compensation for the
reconstruction all by its self. cessation of
3. Any cessation of production and production or work:
work resulting from removal shall be 600 yuan/per
compensated by the demolisher by capita/month;
the month. 5. removal fee: 350-460
4. The affected can get removal fee and yuan/per lorry shift;
transitional fee. 6.transitional fee: 4.5
5. Try to prevent the market yuan/month/m3
environment of the enterprise from
negative impact as much as possible.
116
Shops The owner Altemative resettlement methods: 1. concrete-brick
outside the and the staff 1. The local government provides from structured: 500--1200railway members the nearest place 2 or 3 business yuan/m3;
sector locations with similar conditions for 2. brick-woodthe affected to choose. structured: 250-800
2. Calculate the compensation at the yuan/m3;reconstruction price and the shop 3. simple-structured:owner looks for business quarters 100--250 yuan/m3;
himself 4. compensation for the3. Any cessation of production and cessation of
work resulting from removal shall production or work:
be compensated by the demolisher by 400-1 000 yuan/perthe month. capitalmonth;
4. The affected can get removal fee and 5. removal fee: 350-460
transitional fee. yuan/per lorry shift;
5. Try to prevent the market 6. transitional fee; 3-4.5environment of the enterprise from yuan/month/m3negative impact as much as possible.
Shops within The owner Alternative resettlement methods: 1. concrete-brickthe railway and the staff 1. The project owner provides business structured: 700
sector members housing of similar value, same size yuan/m3;and with similar conditions. 2. brick-wood
2. Calculate the compensation at the structured: 400reconstruction price and the shop yuan/m.3;
owner looks for business quarters 3. simple-structured: 150himself. yuan/m3;
3. Any cessation of production and 4. compensation for the
work resulting from removal shall cessation of
be compensated by the demolisher by production or work:
the month. 600 yuan/per
4. The affected can get removal fee and capitalmonth,
transitional fee. 5. removal fee: 350-460
5. Try to prevent the market yuan/per lorry shift;
enviromnent of the enterprise from 6.transitional fee: 4.5
negative impact as much as possible. yuan/monti/m3
117
Mllegal The owner Resettlement methods:
structure 1. It enjoys the same rights as other
(outside the demolished housing, namely, the
railway compensation standard.
sector) 2. The local government provides the
owner with rent housing, so that he is
able to rent housing with his
compensation fee.
3. The specially poor households can
have resettlement housing at the
lowest standard free of charge.
4. The owner can get transitional fee
and removal fee.
Illegal The owner Resettlement methods:
structure I. It enjoys the same rights as other
(within the demolished housing, namely, the
railway compensation standard.
sector) 2. The project owner shall buy
commodity housing for the owner in
urban distict, with the excess area to
be paid for by the owner.
3. The speciaUy poor households can
have resettlement housing at the
lowest standard free of charge.
4. The owner can get transitional fee
and removal fee.
Infra- The owner Reconruction See Chapter 4 for detail
structures
-118