Upload
yakov
View
33
Download
1
Embed Size (px)
DESCRIPTION
Requirements for the development of EGS. Session: How to improve exploitation and cost-effectiveness of geothermal energy and manage environmental and social impacts?. Content:. Status: what we know/need Identification of Obstacles R+D Requirements. Dr. Th. Mégel GEOWATT AG, CH-Zürich - PowerPoint PPT Presentation
Citation preview
Requirements for the development of EGS
Content:
1. Status: what we know/need
2. Identification of Obstacles
3. R+D Requirements
Dr. Th. MégelGEOWATT AG, CH-Zürich
ENGINE Launching Conference, 13-15 th February 06, F-Orléans
Session: How to improve exploitation and cost-effectiveness of geothermal energy
and manage environmental and social impacts?
Status: what we know/need
EGS-PMDAHandbook developed underIEA-GIA, Annex III
Generic project
Index of Suppliers
Collected Experiences
Bibliography
• Principal milestones• Data Matrix: Data requirement• Task Matrix: First point of data need(EXCEL)
Register of suppliers (EXCEL)
Databases (ACCESS)Information to project documents and data• Fenton Hill • Rosemanowes• Soultz-sous-ForêtsEGS literature database (EndNote)
Project planning
Sources of Know-how
Chapters:
http://www.iea-gia.org/
Identification of Obstacles
Fact 1: R+D activities for EGS since over 35 years.
Obstacles:
1. Financially not attractive ?!
2. Too risky with regard to environmental andsocial impacts ?!
R+D Requirements
Fact 2: Still no commercial EGS power plant worldwide.
Will we have commercial EGS power plants in 35 years?
Identification of Obstacles
Costs Production Productioncosts
Investment costs + Operating costs
€ / year MWh / year € / MWh+
+
R+D Requirements
Minimising Maximising Minimiseduntil
Market(Politics)
€ / MWh<
Maximiseduntil
<
The economical rules are simple...:
Identification of Obstacles
Concept Exploration Development Production Abandonment
Phases of an EGS life cycle
?
Siteselected
Feasibility ofEGS at site
demonstrated
Installations andreservoir ready for
production
Productionlifetime reached
General regional planning:• technical• political• financial• environmental
• Pilot borehole• Stimulation tests• Production modelling
• Inj./Prod boreholes• Intensive stimulation• Production tests• Surface installations
• Power/Heat production:• Maintenance
If no re-investmentfor this site:Deconstruction
Milestones
Identification of Obstacles
Concept phase
Exploration phase
Development/Production/Aban. phase
Data matrix (EGS-PMDA):Information and data required foreach project phase
Identification of Obstacles
0
2
4
6
8
10
12
14
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35
Year
Inve
stem
ent
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35
Year
Pro
du
ctio
nP
rod
uctio
n
C Exp D Production A
Siteselected
Feasibilityevaluated
Maximising
Minimising
R+D requiredfor...
Inve
stm
ent
0
2
4
6
8
10
12
14
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35
Year
Inve
stem
ent
Inve
stm
ent
C Exp D Production AFeasibilityevaluated
GO - NO GO ?
Identification of Obstacles
High risk phase Low risk phase
Principal obstacle: High risk money is expensive
The GO - NO GO decision must be taken as early as possible !
1. shortening of the high risk phase
2. reduction of the high risk investment
3. limiting impacts (social/ environ.)
R+D required to minimise costs by ...
Identification of Obstacles
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35
Year
Pro
du
ctio
n
C Exp D Production A
Feasibilityevaluated
GO - NO GO ? Return of investment
Principal need: Production must be stable on a sufficient level to cover all investments and operating costs
1. maximise production
2. guarantee production
R+D required to...
R+D Requirements
Key task: • Technical productivity enhancement• Technical permeability enhancement
near-borehole domain + reservoir domain
Extended, systematic stimulation/enhancement R + D programme
Major problemso far:
At all EGS R+D projects the success was always coupled on an expected productivity for future production.Hence the systematic development of stimulation techniques was difficult. But this is what is needed!
• mechanical• chemical• others...new...
!!
for different techiques:
R+D Requirements
Extended, systematic stimulation/enhancement R + D programme
Tasks:
I Stimulation R+D tests in existing boreholes,not necessarily deep!
II Stimulation R+D tests in new boreholes,not necessarily deep!
III Laboratory test
• different rock types• different stress regimes• different methods (mechanical, chemical)• different fracture fillings• sites with no limits for massive tests !
IV Professionally managed, firmly concerted
V ...
Methods:
A Identification of physical/chemicalprocesses of permeability enhancement
B Identification of leading parametersfor each stimulation method
C Productivity as a function of leading parameters
D What combination of subsurface parametersdo we find in Europe?
E Which combination of parameters excludesuccessful enhancement?
F Are there limits of permeability enhancementfor given subsurface conditions?
G Can a limited seismic magnitude be guaranteedfor given conditions?
H ...
Conclusions
• Production must cover all capital costs
• Either the production is such that an extended exploration phase- including a lot of failures - can be financed, or the production can be predicted early in a projects life cycle
• Production must become predictable for conditions at a given site
• Production is based on stimulation/enhancement techniques
• Therefore: Enhanced permeability for given conditions and technique used must become predictable
If EGS power plants shall become commercial, then...:
Extended, systematic stimulation/enhancement R + D programme