Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
REQUEST FOR PROPOSALS
FOR
The Design of a New Sawmill Building
AT
The CT DEEP Portland Complex
In Portland, CT
September 16th, 2019
Key Dates:
Pre-Bid Conference – September 26th, 2019
Bids Due - October 16th, 2019
The State is an Equal Opportunity and Affirmative Action employer and does not discriminate in its hiring, employment, or business practices. The State is committed to complying with the Americans with Disabilities Act of 1990 (ADA) and does not discriminate on the basis of disability, in admission to, access to or operation of its programs, services, or activities.
Page 2 of 6
I. Introduction
Title: The design of a new sawmill building at the Portland Complex.
Issuing Agency, Address and Contact: Department of Energy and Environmental Protection (DEEP) Bureau of Central Services Engineering & Field Support Services Division Engineering Unit 163 Great Hill Road Portland, Connecticut 06480 Attention: Alex Curry, Engineer Intern Phone: (860) 424-3407 Email: [email protected]
Location: DEEP Portland Complex, 163 Great Hill Rd, Portland, CT 06480
Purpose: CT DEEP Engineering and Support Services seeks architectural services for the design of a new sawmill building.
Background: CT DEEP Engineering and Support Services operates a sawmill at the Portland Complex in Portland, CT. The existing sawmill building is primarily a timber structure with a footprint of approximately 85’ x 45’. The sawmill uses logs cut from CT State Forests and mills lumber for many products such as picnic tables for parks or building material on DEEP structures.
The existing sawmill is outdated, inefficient, and hazardous compared to modern sawmills. DEEP Engineering and Support Services plans to purchase a new band-saw mill, comparable to a Wood-Mizer WM4500 industrial sawmill. The condition and footprint of the existing sawmill building will not accommodate the installation of the new mill. Renovating the existing structure to accommodate the new sawmill has been deemed impractical and not economical. DEEP Engineering and Support Services plans to operate the existing mill until the new mill has been installed.
The size of the existing mill building is a primary issue. The current building is not large enough to fit the proposed saw and accessory equipment such as a new log deck and edger. The floor of the existing building is also a key factor in the decision to construct a new mill. The floor of the existing building consists of multiple levels with a mix of wood, concrete, and dirt. The floor in the mill is inadequate for the installing of a new sawmill system. The new sawmill requires a uniform and level concrete floor throughout the entire milling area.
It is the goal of DEEP Engineering and Support Services to construct a new sawmill building adjacent to the existing sawmill building. This new building is anticipated to be a Morton style metal building, with a rectangular footprint, on a concrete slab foundation. The sawmill building must satisfy the following needs: provide space for the new sawmill and auxiliary equipment, protect the equipment from environmental elements (e.g. precipitation, humidity, and extreme cold), and functionality for the milling process. The new building will house the sawmill, edger, a 20 foot log deck, 3 way lumber transfer deck, a chipper, and a room to store and maintain
Page 3 of 6
band saw blades. The new building is estimated to have a footprint of approximately 110’ x 40’. Radiant floor heating is proposed as the heating method for the building. The building will not be cooled. It will not have restroom facilities and will operate off of existing site utilities. The new sawmill building shall be in compliance with OSHA 1910.265 Sawmill regulations.
II. Project Scope
Vendors are invited to submit proposals to complete the following tasks:
A. Attend a project initiation meeting with all parties at the project site. B. Complete a full onsite inspection of the proposed sawmill site and the existing sawmill. C. Develop 100% Schematic Design plans. D. Meet with DEEP to discuss the schematic design. E. Complete the design development phase with review submittals at 50% and 100%. Design
drawings of the new sawmill building shall include: 1. Sawmill equipment layout; Location of all equipment and electrical services.
Equipment proposed in the new sawmill; models comparable to:- WM4500 bandsaw- 20’ Log Deck- EG400 edger- Three-way Lumber deck- 9’ Roll Case Conveyor- 9’ Slave Conveyor Extension- Wood chipper
2. Blade maintenance and storage room3. Sawdust collection system4. Necessary mechanical, electrical, and plumbing systems
F. Site design including excavation, grading, and foundation. G. Develop a cost estimate for the proposed sawmill building. H. Develop contract documents for bidding and construction. I. Provide construction administration support to DEEP:
- Review and approval of shop drawings and other submittals - Attend weekly construction progress meetings
J. Deliverables and milestones: 1. 100% Schematic Design2. Cost estimates for construction of the new sawmill building3. 50% Design Development4. 100% Design Development5. 100% Contract Documents
III. Attachments and References
A. Plan drawings of existing and proposed sawmill layout B. Project location maps C. Property boundary survey
Page 4 of 6
D. Portland Complex Utilities Plan E. Example specifications for the sawmill and accessory equipment F. Sample sawmill and accessory equipment layout G. Photos of the existing building and site
IV. Bid Requirements
Project Approach:The Vendor shall clearly outline the firm’s understanding of the project.
Experience and References:The vendor shall demonstrate experience with projects similar in scope and adhering to allquality assurance and qualification requirements of this RFP. The vendor shall specificallyitemize experience with similar projects. Relevant experience shall involve the architecturaland site design of new industrial buildings. Include staff resumes, roles and specific referenceswith contact information.
Time and Cost:Provide detailed cost and time breakdown based on Section II Project Scope. Provide atimeline/schedule for the work items in the Section II Project Scope. The schedule shall bebased on the vendor’s ability to complete the work items in the Section II Project Scope assoon as possible.
Vendor shall assume a two week review period for all submissions to DEEP.
V. Bid and Selection Process
All submissions to the RFP for the sawmill building design at the Portland Complex must be in the possession of the DEEP Engineering Unit no later than October 16th, 2019. Bidder must submit one (1) copy, hard or electronic (PDF), of their bid submittal.
No submissions will be accepted after this date.
Method of Evaluation: An evaluation panel composed of DEEP representatives will review the bid submittals. The criteria requested under Section IV Bid Requirements will be used to evaluate the submittals.
Interviews, if required, will be held on a mutually agreed upon date. Candidates must be represented in interviews by managers and senior staff that will be responsible for the project, if applicable.
Upon selection of a vendor, a Purchase Order and Project Agreement outlining roles and responsibilities and financial terms and other conditions shall be negotiated between the selected vendor and the DEEP.
The following represents the timeline for the RFP and the final selection of the vendor for this work:
Page 5 of 6
RFP and Selection Timeline:
RFP Formally Announced Pre-Bid Conference (convened on-site) Bids Due at 163 Great Hill Road, Portland, Connecticut Award of Work
9/16/20199/26/201910/16/2019Approximately 1 week after bid opening
VI. General ConditionsAll bidders shall be willing to adhere to the following conditions and shall positively state thisin the bid:
1. All bids in response to this RFP are to be the property of the DEEP. All materialsassociated with this procurement process are subject to the terms of state laws definingfreedom of information and privacy and all rules, regulations and interpretationsresulting from those laws.
2. Any product, whether acceptable or unacceptable, developed under a contract awardedas a result of the RFP is to be the sole property of the DEEP.
3. Timing and sequence of events resulting from this RFP will ultimately be determinedby the DEEP.
4. The bidder agrees that the bid will remain valid for a period of 90 days after the closingdate for the submission and may be extended beyond that time by mutual agreement.
5. The DEEP may amend or cancel this RFP, prior to the due date and time, if the DEEPdeems it to be necessary, appropriate or otherwise in the best interests of the DEEP.Failure to acknowledge receipt of amendments, in accordance with the instructionscontained in the amendments, may result in a firm’s bid not being considered.
6. The bidder must certify that the personnel identified in its response to this RFP will bethe persons actually assigned to the project. Any additions, deletions or changes inpersonnel from the bid during the course of the project must be approved by the DEEP,with the exception of personnel who have terminated employment. Replacements forpersonnel who have terminated employment are subject to approval by the DEEP. Atits discretion, DEEP may require the removal and replacement of any of the bidder’spersonnel who do not perform adequately, regardless of whether they were previouslyapproved by the DEEP.
7. Any costs and expenses incurred by bidders in preparing or submitting bids are the soleresponsibility of the bidder.
8. A bidder, if requested, must be prepared to present evidence of experience, ability,service facilities, and financial standing necessary to satisfactorily meet therequirements set forth or implied in the bid.
9. No additions or changes to the original bid will be allowed after submittal. Whilechanges are not permitted, clarification of bids may be required by the DEEP at thebidder’s sole cost and expense.
10. In some cases, bidders may have to give presentations or further explanation to the RFPscreening committee.
11. The bidder represents and warrants that the bid is not made in connection with any otherbidder and is in all respects fair and without collusion or fraud. The bidder furtherrepresents and warrants that they did not participate in any part of the RFP development
Page 6 of 6
process, had no knowledge of the specific contents of the RFP prior to its issuance, and that no agent, representative or employee of the DEEP participated directly in the bidder’s submittal preparation.
12. All Responses to the RFP must conform to instruction. Failure to answer all questions or to follow the requested format may be considered appropriate cause for rejection of the response.
13. The DEEP shall assume no liability for payment of services under the terms of the contract until the successful bidder is notified that the contract has been accepted and approved by the DEEP. The contract may be amended only by means of a written instrument signed by the DEEP and the bidder.
Attachment A:
Existing and Proposed Drawings
Page 7 of 32
Electrical Panel
Cutoff saw
Log Deck
Chipper
Bathroom
Office
Sawdust Room
Saw
Furnace
Closet
Log Carriage
Edger
Streetlight
Stone Wall
B
i
t
u
m
i
n
o
u
s
C
o
n
c
r
e
t
e
D
r
i
v
e
Property Boundary
E
x
is
t
in
g
P
o
le
B
a
r
n
E
xis
tin
g S
hed
Loading Dock
Outfeed Conveyor
C
a
rt R
a
ils
Electrical
Substation
Power
Shed
Property Boundary
Meeting Room
Tool Room
Storm Drainage
Proposed Sawmill Building
INITIALS
ENGINEERING AND FIELD SUPPORT SERVICES
DEPARTMENT OF ENERGY
STATE OF CONNECTICUT
DESIGNED:
DRAWN:
SHEET #:
CAD FILE:
DATE:
SCALE:
DATE DESCRIPTION
REVISIONS
PORTLAND, CONNECTICUT
ENGINEERING UNIT
163 GREAT HILL ROAD
PHONE: 860-342-2215
FAX: 860-344-2560
PROJECT NAME & NUMBER:
SHEET TITLE:
AND ENVIRONMENTAL PROTECTION
Portland Complex Sawmill
S:PrtlndCmplx/Sawmill
APC
08/21/2019
Not to Scale
Existing Sawmill Building and Site
CHECKED:
1/2
Bathroom
Streetlight
Stone Wall
Gravel Parking Area
Property Boundary
Property Boundary
22'
13'
32'
6'6"
4'
110'
40'
Garage Door
Wood Chip
Trailer
Conveyor
9' Slave Unit
Chipper
Storm Drainage
12'
20'
22'
Edger
20' Log Deck
Sawdust
Trailer
Transfer
Table
Blade
Maintenance
& Storage
Room
Garage Doors
Headrig w/
Cab &
Powerpack
Three-way
Tranfer Deck
Incline Conveyor
Roll Case
9' Drive
Transfer
Table
Sawdust Blower
Garage Door
Sawdust Ductwork
12'
18'
INITIALS
ENGINEERING AND FIELD SUPPORT SERVICES
DEPARTMENT OF ENERGY
STATE OF CONNECTICUT
DESIGNED:
DRAWN:
SHEET #:
CAD FILE:
DATE:
SCALE:
DATE DESCRIPTION
REVISIONS
PORTLAND, CONNECTICUT
ENGINEERING UNIT
163 GREAT HILL ROAD
PHONE: 860-342-2215
FAX: 860-344-2560
PROJECT NAME & NUMBER:
SHEET TITLE:
AND ENVIRONMENTAL PROTECTION
Portland Complex Sawmill
S:PrtlndCmplx/Sawmill
APC
08/21/2019
2/2
Not to Scale
Proposed Sawmill Building
CHECKED:
Existing Sawmill Building
Attachment B:
Project Location Maps
Page 10 of 32
Map data ©2019 2000 ft
163 Great Hill Rd
Sawmill Location
163 Great Hill Rd - Google Maps
https://www.google.com/maps/place/163+Great+Hill+Rd,+Portland,+CT+06480/@41.5910... 8/1/2019
Page 11 of 32
Imagery ©2019 Google, Map data ©2019 100 ft
163 Great Hill Rd
163 Great Hill Rd - Google Maps
/
https://www.google.com/maps/place/163+Great+Hill+Rd,+Portland,+CT+06480/@41.5981... 1
/ 9Page
1
2 of 321
Imagery ©2019 Google, Map data ©2019 50 ft
163 Great Hill Rd
Portland Sawmill
163 Great Hill Rd - Google Maps
7/18/2019https://www.google.com/maps/place/163+Great+Hill+Rd,+Portland,+CT+06480/@41.599...
Page 4 of 6 Page 4 of 6
Page 4 of 6
Page 13 of 32
Attachment C:
Property Boundary Survey
Page 14 of 32
Page 15 of 32
Page 16 of 32
Attachment D:
Portland Complex Utilities Plan
Page 17 of 32
Page 18 of 32
Attachment E:
Sample Equipment
Specifications
Page 19 of 32
Industrial Sawmill
3-way Conveyor
Page 20 of 32
Edger
20 Foot Log Deck
Page 21 of 32
9' Roll Case Conveyor
Page 22 of 32
Attachment F:
Photos of Existing Building and Site
Page 23 of 32
Above Photo: Sawmill meeting room. This will continue to be used after construction of the new sawmill building.
Page 24 of 32
Above Photo: Tool room in the existing sawmill building. This will continue to be used after construction of the new sawmill building.
Page 25 of 32
Above Photo: Existing Sawmill building viewed from the east.
Page 26 of 32
Above Photo: Inside the existing sawmill building viewed from the east.
Page 27 of 32
Above Photo: Inside the existing sawmill building viewed from the west.
Page 28 of 32
Above photo: Existing sawmill building viewed from the north.
Page 29 of 32
Above photo: Existing sawmill building and yard viewed from the west.
Page 30 of 32
Above photo: Gravel yard outside the existing sawmill building; approximate location of the proposed sawmill building.
Page 31 of 32
Above photo: Gravel yard and parking area viewed from the north; approximate location of the proposed sawmill building.
Page 32 of 32