Reporting during the lifetime of the project
Moldova – Research Horizon30 January 2013
Kristin Kraav
Roles• Coordinator:– Monitors the work according to the work plan– Monitors the quality of project deliverables– Monitors use of budget– Reports to the European Commission
• Partner:– Is responsible for their foreseen task– Reports to the Coordinator and/or WP leader
Reporting• Grant Agreement Annex II• Guidance notes on project reporting
• ftp://ftp.cordis.europa.eu/pub/fp7/docs/project_reporting_en.pdf • incl Templates (doc)
• Guide to financial issues• ftp://ftp.cordis.europa.eu/pub/fp7/docs/financialguide_en.pdf
• Guidance notes […] on certificates• ftp://
ftp.cordis.europa.eu/pub/fp7/docs/guidelines-audit-certification_en.pdf • Presentation of FORCE
• ftp://ftp.cordis.europa.eu/pub/fp7/docs/presentation-force_en.pdf • Wiki on FP7 Periodic report
• http://212.68.215.215/display/iKnowextern/FP7+Periodic+Report
Reports and deadlines• According to GA Annex II:
1. Periodic report – 60 days after the end of the reporting period• Overview of activities and outcomes, deliverables, milestones• Use of resources = explanation on the use of budget• Financial statement = Form C
2. Final report – 60 days after the end of the projectNB! In addition to the last periodic report
1. Outcomes, conclusions, impact (publishable)2. Various questionnaires (gender issues, dissemination, …)
– Audit certificate – Certificate on the financial statement: only when cumulative EU contribution exceeds 350 000 €
– After the final payment: coordinator submits distribution of budget in consortium
Submitting of reportsVia the Participants Portal :
FORCE = Form C EditorSESAM = IT reporting tool system
NB! These systems are subject to change and the screenshots may be outdated
http://ec.europa.eu/research/participants/portal/
Periodic report• Submitted electronically 60 days after the end of the
reporting period• Parts of the Periodic report:• Summary (publishable)• Core report:
• Aims of the period (according to Annex I)• Activities and outcomes – per each WP• Project management activities during the period
• Project deliverables – table• Milestones – table• Explanation on the use of resources (now integrated with Form
C)• Form C + Summary financial report