22
April 10 th 2019 Remote Monitoring System Improvements Robert Spelman, PE Supervisor, UG Distribution Standards

Remote Monitoring System Improvements...–Mix of LVAC and Spot Networks −480Y/277 –53% −216Y/125 –47% •N-1 System Design •~1,400 MVA Peak Load •Approx. 70,000 Customers

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Remote Monitoring System Improvements...–Mix of LVAC and Spot Networks −480Y/277 –53% −216Y/125 –47% •N-1 System Design •~1,400 MVA Peak Load •Approx. 70,000 Customers

April 10th 2019

Remote Monitoring System Improvements

Robert Spelman, PE

Supervisor, UG Distribution Standards

Page 2: Remote Monitoring System Improvements...–Mix of LVAC and Spot Networks −480Y/277 –53% −216Y/125 –47% •N-1 System Design •~1,400 MVA Peak Load •Approx. 70,000 Customers

1

Pepco Holdings Quick Facts

Page 3: Remote Monitoring System Improvements...–Mix of LVAC and Spot Networks −480Y/277 –53% −216Y/125 –47% •N-1 System Design •~1,400 MVA Peak Load •Approx. 70,000 Customers

2

• Incorporated in 1896

• 640 Square Mile Service Territory

• 2.3 Million Population Served

• 134 Substations

• 9 Facilities

• Washington DC Headquarters (PHI / Exelon)

Utilities With Network Systems

Pepco

Atlantic City Electric

• Incorporated in 1924

• 2,700 Square Mile Service Territory

• 1.1 Million Population Served

• 90 Substations

• 8 Facilities

Page 4: Remote Monitoring System Improvements...–Mix of LVAC and Spot Networks −480Y/277 –53% −216Y/125 –47% •N-1 System Design •~1,400 MVA Peak Load •Approx. 70,000 Customers

Network System Overviews

• Pepco 13kV Network

• ACE 23kV Network

• Pepco 13kV Network Remote Monitoring System

Section 1

Page 5: Remote Monitoring System Improvements...–Mix of LVAC and Spot Networks −480Y/277 –53% −216Y/125 –47% •N-1 System Design •~1,400 MVA Peak Load •Approx. 70,000 Customers

4

Pepco 13kV Network System• 51 Network Groups

– ~300 13kV Feeders

– 21 Substations with Network Feeders

– ~4,600 Network Protectors

– Average 6 Feeders/Group

– Mix of LVAC and Spot Networks

− 480Y/277 – 53%

− 216Y/125 – 47%

• N-1 System Design

• ~1,400 MVA Peak Load

• Approx. 70,000 Customers

– Residential → Large Commercial/Government

• Sidewalk / Street / Some Rooftops

• Substation Ring Bus, Closed Ties

Page 6: Remote Monitoring System Improvements...–Mix of LVAC and Spot Networks −480Y/277 –53% −216Y/125 –47% •N-1 System Design •~1,400 MVA Peak Load •Approx. 70,000 Customers

5

ACE 23kV Network System

• 1 Network Group

– 5, 23kV Feeders

– 48 Network Protectors

– All units 216Y/125

• N-1 System Design

• ~10 MVA Network Load

• Approx. 1,300 Customers

• Sidewalk / Street / Boardwalk Locations

• System Not Expanding, Slowly Shrinking

– Small Customers Can Still Be Connected to

Grid

• Large Customers Served From HV Feeders

(12kV/23kV)

Page 7: Remote Monitoring System Improvements...–Mix of LVAC and Spot Networks −480Y/277 –53% −216Y/125 –47% •N-1 System Design •~1,400 MVA Peak Load •Approx. 70,000 Customers

6

• Checking Protector Status

• Locate “Hung In” Protectors Much Faster

• Ensuring Opposite Protectors are Closed at Critical Facilities

Before Granting Outages

• Remote Operation

• ROBO – Remotely Block Open a Protector

• Load Information – Monitor Overloads – Intelligently Plan

System Loading

• Check and Update Protector Settings Remotely

• Identify Failed Protector or Blown Fuses via Alarm

• Phasing Remotely Following Cable Work

• Respond Quickly and Intelligently to System Emergencies

• Currently Installed on ~11% of Network Transformers

Benefits

• ~500 locations with RMS in service and communicating

• Eaton Vaultgard

• Developing dashboard for real time display of key data points

• Determine “best value” monitoring. Cost/benefit analysis

Current Status

Pepco Network Remote Monitoring System (RMS)

Page 8: Remote Monitoring System Improvements...–Mix of LVAC and Spot Networks −480Y/277 –53% −216Y/125 –47% •N-1 System Design •~1,400 MVA Peak Load •Approx. 70,000 Customers

7

Remote Monitoring System (RMS)Simplified System Schematic

Monitoring Inputs

• Relay Data

• Ambient Temp

• Water Level 1

• Water Level 2

• Main Tank Oil Temp

• Main Tank Oil Level

• Primary Cabinet Oil Level

• Primary Cabinet Oil Level (if 2 compartment)

1-8

Network Transformer

Network Protector

Primary

Switch

4

3

2

1

7

5 6

8

RelayBulk

head

IP 68 Enclosure

Silver Spring

E-BridgeVaultGard

Digital and Analog

Inputs

Antenna

Inputs

1-8

Operations Control CenterFiber

Substation

Other

Protectors

Page 9: Remote Monitoring System Improvements...–Mix of LVAC and Spot Networks −480Y/277 –53% −216Y/125 –47% •N-1 System Design •~1,400 MVA Peak Load •Approx. 70,000 Customers

8

RMS PI DisplaysTrending Data Analytics

Page 10: Remote Monitoring System Improvements...–Mix of LVAC and Spot Networks −480Y/277 –53% −216Y/125 –47% •N-1 System Design •~1,400 MVA Peak Load •Approx. 70,000 Customers

9

RMS DisplaysReal Time Monitoring - OCC

Page 11: Remote Monitoring System Improvements...–Mix of LVAC and Spot Networks −480Y/277 –53% −216Y/125 –47% •N-1 System Design •~1,400 MVA Peak Load •Approx. 70,000 Customers

10

Alarms and MonitorsDevelopment

Page 12: Remote Monitoring System Improvements...–Mix of LVAC and Spot Networks −480Y/277 –53% −216Y/125 –47% •N-1 System Design •~1,400 MVA Peak Load •Approx. 70,000 Customers

Remote Monitoring System Improvement Project

Section 2

Page 13: Remote Monitoring System Improvements...–Mix of LVAC and Spot Networks −480Y/277 –53% −216Y/125 –47% •N-1 System Design •~1,400 MVA Peak Load •Approx. 70,000 Customers

12

Example - 3 Transformer Spot Network

Cable Bus

Page 14: Remote Monitoring System Improvements...–Mix of LVAC and Spot Networks −480Y/277 –53% −216Y/125 –47% •N-1 System Design •~1,400 MVA Peak Load •Approx. 70,000 Customers

13

Example - 3 Transformer Spot NetworkCurrent Set Up

Cable Bus

V

G

U

P

S

4321

7

5

6

8ANT.

4321

7

5

6

8

4321

7

5

6

8

Monitoring Inputs

• Relay Data

• Ambient Temp

• Water Level 1

• Water Level 2

• Main Tank Oil Temp

• Main Tank Oil Level

• Primary Cabinet Oil Level

• Primary Cabinet Oil Level (if 2 compartment)

1-8

VG

U

P

S

Collection of 8 “Monitor” Cables From Each Vault

VaultGard Enclosure

SSN Radio

Qualitrol DIM

UPS Enclosure

Battery Backup

ANT. Radio Antenna (SSN)

Page 15: Remote Monitoring System Improvements...–Mix of LVAC and Spot Networks −480Y/277 –53% −216Y/125 –47% •N-1 System Design •~1,400 MVA Peak Load •Approx. 70,000 Customers

14

BackgroundRoom For Improvement

Labor / Modularity

Cable

Connections

Material

Gauge

Calibration

Input

ConfigurationGauge Quality

Water Ingress

Subject Matter Experts

Development and Iteration

Page 16: Remote Monitoring System Improvements...–Mix of LVAC and Spot Networks −480Y/277 –53% −216Y/125 –47% •N-1 System Design •~1,400 MVA Peak Load •Approx. 70,000 Customers

15

Gauges and Sensors

• Corrosion

• Water Ingress

• Sub Par Quality

• Non-Corrosive Housing

• IP68 3rd Party Certified

• Plug and Play

• No Need to Label

• No Calibration Required

Page 17: Remote Monitoring System Improvements...–Mix of LVAC and Spot Networks −480Y/277 –53% −216Y/125 –47% •N-1 System Design •~1,400 MVA Peak Load •Approx. 70,000 Customers

16

Water Ingress

• Minimizing

Openings

• Minimal Wiring

• IP68 Connections

• One Enclosure

Page 18: Remote Monitoring System Improvements...–Mix of LVAC and Spot Networks −480Y/277 –53% −216Y/125 –47% •N-1 System Design •~1,400 MVA Peak Load •Approx. 70,000 Customers

17

Ease of Installation

• Dedicated Conduit(s)

Usually Required

• Remove and Re-Attach

Cable Connections

• Careful Gauge Labeling

Required

• Current Process Is Labor

Intensive $$$$

• Many Connections and

Individual Cables to Pull

• Every Cable Kept Track of from

XFMR to Enclosure

• Error Prone Steps

Page 19: Remote Monitoring System Improvements...–Mix of LVAC and Spot Networks −480Y/277 –53% −216Y/125 –47% •N-1 System Design •~1,400 MVA Peak Load •Approx. 70,000 Customers

18

• No Calibration Required

• Plug and Play with New Gauges

• Magnetic or Bolted Mounting Options

• Accepts 12 Inputs – Fully Configurable

• More Distance Between Transformers

• All Gauges and Relay Wiring to Connect Locally to TRTL

• 1 Armored Ethernet Output Per Transformer Vault

– Greatly Reduce Main Enclosure Penetration

– Greatly Reduce Wire Pulling Labor and Connections

• Potted, Non-Corrosive, IP68 Certified

TRTL ConceptFuture Improvement?

Page 20: Remote Monitoring System Improvements...–Mix of LVAC and Spot Networks −480Y/277 –53% −216Y/125 –47% •N-1 System Design •~1,400 MVA Peak Load •Approx. 70,000 Customers

19

Example - 3 Transformer Spot Network – (End Goal)With TRTL Implementation

Cable Bus

4321

7

5

6

8

4321

7

5

6

8

4321

7

5

6

8V

GANT.

VG

TRTL Box

Armored DNP Ethernet (1 Per XFMR)

VaultGard Enclosure

SSN Radio

NP Serve

Battery Backup

HMI

ANT. Radio Antenna (SSN)

Monitoring Inputs

• Relay Data

• Ambient Temp

• Water Level 1

• Water Level 2

• Main Tank Oil Temp

• Main Tank Oil Level

• Primary Cabinet Oil Level

• Primary Cabinet Oil Level (if 2 compartment)

1-8

Page 21: Remote Monitoring System Improvements...–Mix of LVAC and Spot Networks −480Y/277 –53% −216Y/125 –47% •N-1 System Design •~1,400 MVA Peak Load •Approx. 70,000 Customers

20

RMS Installation – (End Goal)Mock Vault

Page 22: Remote Monitoring System Improvements...–Mix of LVAC and Spot Networks −480Y/277 –53% −216Y/125 –47% •N-1 System Design •~1,400 MVA Peak Load •Approx. 70,000 Customers

21

Questions?

Thank You!

Contact:

Robert Spelman202-388-2507

[email protected]